fp420 meeting - 13 september 2007 beniamino di girolamo - cern ph telescope, installation and beam...
TRANSCRIPT
FP420 Meeting - 13 September 2007Beniamino Di Girolamo - CERN PH
Telescope, installation and beam area
B. Di GirolamoCERN
FP420 Meeting - 13 September 2007Beniamino Di Girolamo - CERN PH
Telescope
BAT telescope: 4 working moduleso Used until a week ago on H6 beam line by
RD42 test beamo Two modules need some additional tuning
to remove some chip-to-chip edge effects• That can affect slightly the resolution in some
zone over the surface• Tuning is simple, just need to find time to do it
o All hardware has to stay in the beam area• All power supplies and the control and daq pc
– Length of cables cannot exceed certain limits– SCSI-like type of bus: not meant for long distances
o Two options for module positioning on the table• See later
FP420 Meeting - 13 September 2007Beniamino Di Girolamo - CERN PH
Installation
One marble tableo For telescope mounting and DUTs
Second marble tableo In case the first one is not enough
• the beam pipe setup is quite long Issues when using two tables
o Alignment: we can have surveyors and align everything• Shimming to be foreseen
o Due to limitation in allowable cable length, telescope has to stay on one table• Divergence of the beam to be limited by
– Veto counter– Thin counter
• Both counters to be put downstream of the setup (veto could be put upstream)
FP420 Meeting - 13 September 2007Beniamino Di Girolamo - CERN PH
Main marble table
160 x 50 cmHoles pitch = 2.5”1 x-y assembly1 rotation assembly can be mounted
on x-y one2 kind of brackets to hold telescope
modules1 of the above brackets can be used to
hold sci-counters
FP420 Meeting - 13 September 2007Beniamino Di Girolamo - CERN PH
FP420 Meeting - 13 September 2007Beniamino Di Girolamo - CERN PH
FP420 Meeting - 13 September 2007Beniamino Di Girolamo - CERN PH
When to install and run
Installation start: Oct 10th at 8:00 Beam stop: Oct 16th at 8:00 Table with telescope and possible DUTs can stay until:
Friday 26th 14:00o Interest to use also by Muon people
Table and telescope will then be in H6 until Monday November 12th
FP420 Meeting - 13 September 2007Beniamino Di Girolamo - CERN PH
H8 Beam area
FP420 Meeting - 13 September 2007Beniamino Di Girolamo - CERN PH
Beam characteristics
180 GeV/c, positive polarity Secondary beam: under mm beam spot
o Tertiary beams with good rate down to 50 GeVo 20 and 10 GeV possible, rate is low
The H8 line can have beams in the ranges:o 1-9 GeVo 10-20 GeVo 20-180 GeVo Up to 300 GeV
Pions, muons and electronso At high energy relevant proton contaminationo Going lower in energy pions and electrons beams
contaminate each other, especially with positive polarity