fp 420 connection cryostat design and integration

21
FP 420 Connection Cryostat Design and Integration Keith Potter, Jaak Lippmaa, Guido Ryckwaert, Benoit Florin, Thierry Renaglia, Thierry Colombet, Shrikant Pattalwar, Domenico Dattola. Torino 11-12 July 06

Upload: raphael-delacruz

Post on 03-Jan-2016

33 views

Category:

Documents


0 download

DESCRIPTION

FP 420 Connection Cryostat Design and Integration. Keith Potter, Jaak Lippmaa, Guido Ryckwaert, Benoit Florin, Thierry Renaglia, Thierry Colombet, Shrikant Pattalwar, Domenico Dattola. Torino 11-12 July 06. FP 420 Cryostat Design and Integration. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: FP 420 Connection Cryostat Design and Integration

FP 420 Connection Cryostat Design and Integration

Keith Potter, Jaak Lippmaa, Guido Ryckwaert, Benoit Florin, Thierry Renaglia, Thierry Colombet, Shrikant Pattalwar,

Domenico Dattola.

Torino 11-12 July 06

Page 2: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 2D. D. INFN To/CERN PH CMM

FP 420 Cryostat Design and Integration

Integration into the machine tunnel with existing equipment and reserved volumes – Cryo distribution line (QRL)– Tunnel Services, cable trays, cables and piping– Transport reservation– Alignment lines of sight

• Integration of services and detector on the new connection cryostat with warm beam pipes– Vacuum sector valves, pumps, vacuum gauges, diagnostic ports– Detector Interfaces– Detector cooling and services

• Assembly, transport and installation– First Installation must not take longer than the normal 3-4 month winter

shutdown Assembly the complete connection cryostat in surface hall. Structural Beam to assembly together Terminal Module (ATM) and

support cryogenics continuity lines, detectors positioning system, radiation shielding.

Page 3: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 3D. D. INFN To/CERN PH CMM

Typical tunnel section.

Page 4: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 4D. D. INFN To/CERN PH CMM

FP420 Connection Cryostat in tunnel.

Page 5: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 5D. D. INFN To/CERN PH CMM

Vacuum Instrumentation (VAA) on Reshuffling Module of Distribution Feed Boxes (DFB)

Vacuum Instrumentation (VAA)

Page 6: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 6D. D. INFN To/CERN PH CMM

DFB Vacuum Equipment (VAA)

Visit DFB Vacuum Assembly Facilities. (Keith Potter, Michele Arneodo, Detlef Swoboda, Benoit Florins, Guido Ryckewaert)

Page 7: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 7D. D. INFN To/CERN PH CMM

RF all metal gate valve

Page 8: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 8D. D. INFN To/CERN PH CMM

ATM Reshuffling Module. X Line

Superfluid He (X) Line. Existing raw interfaces

Page 9: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 9D. D. INFN To/CERN PH CMM

X line continuity

There is not continuity for the super-fluid He (X line) on the existing module. It can be added on existing raw interfaces in the reshuffling module.

A straight line between ATM flanges has been considered.

A: aligned to contiguous element B:Moved aside by 180 mm to allow easy accessibility to detectors

Page 10: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 10D. D. INFN To/CERN PH CMM

X Line Continuity new proposal. (I)•Previously layouts not compatible with Beam vacuum equipment.

Move X Line away by curved piping between ATM flanges

Page 11: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 11D. D. INFN To/CERN PH CMM

X Line Continuity new proposal. (II)

Detail on next slide

•Distance between flanges of reshuffling modules: 9810 mm

•Reserve to vacuum equipment 700mm per side. Available space for detectors ~ 8410 mm

Instrumentation must sectorise the warm and cold vacuum systems and provide roughing pumping/venting and UHV pumping of the warm vacuum system for both beams, independently. In addition it should provides tools to monitor the status and quality of each beam vacuum.

Combination of valve, pump and pressure gauges, as is on DFB modules (VAA), would occupy about 700 mm

Page 12: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 12D. D. INFN To/CERN PH CMM

X Line Continuity new proposal. (III)

Page 13: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 13D. D. INFN To/CERN PH CMM

X Line Continuity new proposal. (IV)

Page 14: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 14D. D. INFN To/CERN PH CMM

Assembly Structure (I)

Page 15: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 15D. D. INFN To/CERN PH CMM

Assembly Structure (II)

AA AA

Top side view

A-A view

Page 16: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 16D. D. INFN To/CERN PH CMM

Conclusion (next steps)

• Get detailed drawing of tunnel layout in all the 8 zone. Check QRL.

• Study on feasibility of 3rd proposal of X line routing. Design Interconnection inside shuffling module.

• Adapt Vacuum equipment- (R Veness ?) • Cryostat Assembly Beam – Transport Handling

Frame ?

Page 17: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 17D. D. INFN To/CERN PH CMM

ATM various pic. and fig.

Page 18: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 18D. D. INFN To/CERN PH CMM

DFP Arc Termination Module (ATM) in LHC

Page 19: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 19D. D. INFN To/CERN PH CMM

ATM DFB interface I

Page 20: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 20D. D. INFN To/CERN PH CMM

ATM DFB interface II

Page 21: FP 420 Connection Cryostat Design and Integration

FP 420 Cryostat Design and Integration. Torino 11-12/07/06 21D. D. INFN To/CERN PH CMM

ATM DFB interface III