forwards partial response to generic ltr 81-07 re control ... · generic letter 81-07 item 1 ......
TRANSCRIPT
DOCKET NO. 50-263 NSPC....MONTICELLO
CONTROL OF HEAVY LOADS NRC GENERIC LTR 81,07
Recdd w/1tr 9/30/81.. .8110060191
RECORDS FACILITY BRANCH
- NOTICE THE ATTACHED FILES ARE OFFICIAL RECORDS OF THE DIVISION OF DOCUMENT CONTROL. THEY HAVE BEEN CHARGED TO YOU FOR A LIMITED TIME PERIOD AND MUST BE RETURNED TO THE RECORDS FACILITY BRANCH 016. PLEASE DO NOT SEND DOCUMENTS CHARGED OUT THROUGH THE MAIL. REMOVAL OF ANY PAGE(S) FROM DOCUMENT FOR REPRODUCTION MUST BE REFERRED TO FILE PERSONNEL.
QEADLINE RETURN DATE
CONTROL OF HEAVY IDADS
NIC GENERIC LETTER 81-07
NORTHERN STATES POWER COMPANY
MONTICELLO NUCLEAR GENERATING PIANT
SEPTEMBER 30, 1981
RESPONSE 'IT REQUEST FOR INFORMATION IN SECTION. 2.1
GENERIC LETTER 81-07
Item 1 (NRC Question 2.1.1)
Report the results of your review of plant arrangements to identify all overhead handling system fran which a load drop may result in damage to any system required for plant shutdown or decay heat removal (taking no credit for any interlocks, technical specifications, operating procedures, or detailed structural analysis).
Response
A survey of the Mnticello Plant was performed to identify the overhead handling systems that fall in the category referred to in Question 2.1.1. These handling systems are listed below:
Capacity Location Handling System Main/Auxiliary ID No.
Turbine Building Turbine Building Crane 125/5 1 Reactor Buidling Reactor Building Crane 85/5 2
Item 2 (NRC Question 2.1.2)
Justify the exclusion of any overhead handling system from the above category by verifying that there is sufficient physical separation fran any load-impact point and any safety-related component to permit a determination by inspection that no heavy load drop can result in damage to any system or. component required for plant shutdown or decay heat removal.
Response
Table 1 lists the overhead handling systems which have been excluded from further oonsid ration because of capacity or physical separation from any system or com
ponent required for plant shutdown or decay heat removal. In addition the following handling systems have been eliminated fran consideration for the following reasons.
1. Reactor Recirc Pumps Monorail Motor Hoist (Capacity 32,000 lbs) ID E. 6
The function of this load handling device is to assist in the assembly & disassembly of the Reactor Recirculation Pumps during plant shutdown. This device is located in the drywell. The items handled by this handling device would typically consist of the Rx Recirc Pump Drive Motor and the individual parts of the R Recirc Pump as it is disasserbled. The potential impact item of concern is the applicable loop of of the R Recirc System. It is possible, but highly unlikely, that dropping the. Rx Recirc drive motor could rupture the recirc system piping of the loop being repaired. When this device is used to disassemble a Rx.
* Identification number (ID No) used to identify overhead handling systems in attached tables and figures.
1
Recirc Pump the applicable pump will be isolated. It is phycially impossible to drop this heavy load and disable both Ib Recirc loops. Therefore this load handling device is eliminated because of system redundancy.
2. MSRV Drywell Monorail (Capacity 10,000 lbs) ID Nb. 14
The function of this load handling device is to assist in moving equipment, tools and other omponents from the 935' elevation in the drywell to the 948' elevation when the Rx is in a shutdown condition. Equipment typically handled by this device consists of, Main Steam Safety Relief valves, 1000 lbs, Mtor Operated Valve Components 1000 lbs and tools. In the past it has been used to lift piping and other materials used for modification projects. If a heavy load were dropped it is possible for the heavy load to impact on the A Rx Recirc loop piping and/or the A RHR injection header, the RHR shutdown cooling suction header or the B Rx Recirc loop piping and/or the B RHR loop injection header. It is not physically possible to damage both the A RK Recirc loop & A RHR injection header and the B Rx Recirc loop & B RHR injection header. If the RHR suction header were damaged an alternate shutdown cooling suction would be available through the steam line, safety relief valve and the torus.. Therefore this load handling device is elminated because of system redundancy.
3. Torus Monorail (Capacity 10,000 lbs) ID No. 15
The function of this device is to assist in maintenance activities in the torus. Ioads typically handled by this device would consist of, torus to drywell vacuum breaker valves, tools and other miscellaneous equipnent. In the past this device has been used to handle piping and structural materials used to make modifications in the torus. This load handling device is only used when the reactor is in a cold shutdown condition and if loads
.were handled that were 1000 lbs the torus would typically be drained. No component or system required for plant shutdown or decay heat removal would be affected by a load drop at that time.
4. HPCI Turbine Monorail (Capacity 8,000 lbs) ID No. 17
The function of this load handling device is to assist in the assembly and disassembly of the HPCI turbine. This device would only be used when the HNI system is not required to be operable per plant technical specifications. Any load handled by this load handling device could not impact on the redundant system to the HPCI system. The RCIC system would be available to makeup water to the Px. Therefore this load handling device has been eliminated
,because of system redundancy.
5. Torus Access Hatch Hoist & Lifting Lug (Capacity 4,000 lbs) ID No. 28
The function of this load handling device is to assist in torus maintenance activities. This device is typically used to move tools, equipment and other components into and out of the torus in support of maintenance activities. In addition it may be used in maintenance activities on motor operated valves for other systems that are located in the area above the torus. A typical load would onsist of tools, motor operated valve parts, torus to drywell vacuum breaker valves and other miscellaneous loads within the capacity of the lifting device. It is very unlikely that a load drop from this
2
4
device would damage the torus to the point that the water in the torus would be lost. Typically heavy loads would only be handled by this device for torus modification when primary containment is not required and the torus is drained. N other component or system required for plant shutdown or decay heat removal is located in the area of this device.
6. Chlorine Container Monorail and Cylinder Grab (Capacity 4,000 lbs) ID No. 31
The function of this load handling device is to handle cylinders containing liquid chlorine. These containers of liquid chlorine are handled at various intervals depending on the volume used in the plant. It is very unlikely that dropping of one of. these chlorine containers would penetrate the floor of the chlorine storage room or that any spalling of the oncrete ould damage the B RHR-SW loop piping that is located in the area. In the unlikely event that the B RHR-SW loop were disabled the load drop would not damage the redundant A RHR-SW loop. Therefore load handling system has been elminated because of system redundancy.
7. Radwaste and Fuel Pool Shield Blocks Monorail (Capacity 10,000 lbs) ID No. 36
The function of this load handling device is the removal of shield blocks and the assembly and disassembly of the following components: Fuel Pool Filters (2), Radwaste Floor Drain Filter, Radwaste Equipment Drain Filter and the Radwaste Deep Bed Demineralizer. It is very unlikely that dropping one of the shield plugs would cause the load to penetrate the floors (3) separating the shield plugs fran the B Loop RHR & Core Spray systems and render these systems inoperable. In the unlikely event that this were to occur it would not disable the redundant A RHR & Core Spray loops that are located in a separate room. Therefore this load handling device has been eliminated because of system redundancy
8. "A" Turbine Floor Portable A-Frame & Monorail (Capacity 10,000 lbs) ID 1b. 44
The function of this load handling device is to assist in the assembly & disassembly of the turbine generator. This device is normally used to assemble and disassemble the turbine governor, bypass valves and the stop and control valves. No systems required for safe shutdown or decay heat removal are located below this load handling device during normal use.
9. Reactor Building Floor Drain/Equipment Drain Hatch Lifting Device (Capacity 8,000 lbs) ID N. 45
The function of this load handling device is to remove the shield block above the Rx Building Floor Drain & Equipment Drain Tanks. This device is also used for maintenance activities associated with sump pumps located in these drain tanks. This device is also used to move equipnent, tools and other components into and out of the torus area via this tank room. -loads handled by this device ould impact on system components associated with the HECI system, however, the RCIC system would be available to perform as a backup to the HICI system.. Therefore this load handling device has been eliminated from onsideration because of system redundancy.
3
10. RCIC Pump Rom Acoass Hatch Monorail (Capacity 7,800 1bs)
The function of this load handling device is to remove the shield block above the RCIC system steam driven pump and to assist in the assembly, disassembly and the removal of various system components located in the room. This devicewould not be used to remove the shield plug and disassemble the pump unless the system was not required to be operable per the plant technical specification. If the shield plug were to be dropped and disable the RCIC system it would not disable the alternate method of water makeup to the Rx at rated pressure. The HPCI system can perform this task. Therefore this load handling device has been eliminated because of system redundancy.
11. A RHR Pump Fbom Access Hatch Lifting Lugs (4) (Capacity 7,500 lbs ea.) Id No. 54
The function of these load handling devices is to provide an attachment for portable lifting devices for the removal of the A RHR Room Shield Plug. This load handling device could also be used to assist in the assembly and disassembly of either the A & C RHR Pumps or the A Core Spray Pump which is also located in this room. Maintenance would not be performed on these pumps unless plant technical specifications permitted. In the event of a heavy load drop in this area that would disable the RHR Pumps and/or the Core Spray Pump located in the room, two redundant RHR Pumps and a redundant Core Spray Pump located in a separate roam would not be affected and are capable of performing their functions in the shutdown of the plant and subsequent decay heat removal. Therefore this load handling device is eliminated because of system redundancy.
12. B RHR Pump Rom Access Hatch Lifting Lugs (4) (Capacity 7,500 lbs ea.) ID Ib. 55
The function of these load handling devices is to provide an attachment for portable lifting devices for the removal of the B RHR Room Shield Plugs. This load handling device could also be used to assist in the assembly and disassembly of either the B & D RHR Pumps or the B Core Spray pump which is also located in this room. Maintenance would not be perfornEd on these pumps unless plant technical specifications permitted. In the event of a heavy load drop in this area that would disable the RHR Pumps and/or the Core Spray Pump located in this room, two redundant RHR Pumps and a redundant Core Spray Pump located in a separate room would not be affected and are capable of performing their functions in the shutdown of the plant and subsequent decay heat removal. Therefore this load handling device is eliminated because of system redundancy.
13. B Turbine Building Portable A-Frame & Monorail (Capacity 10,000 lbs) ID No. 61
The function of this load handling device is to assist in the assembly & disassembly of the turbine generator. This devia is normally used to assemble and disassemble the turbine governor, bypass valves and the stop and control valves. No systems or components required for safe shutdown or decay heat removal are located below this devia during normal use.
4
ID No. 53
4
14. Drott Mobile Crane (Capacity 6,800 1bs) ID 1o. 62
The function of this load handling device is to assist in moving equipnent that is too heavy or awkward to handle by other methods. This device can only be used in a very limited area of the Reactor Building and in the railroad access area of the turbine building. It would be possible to transport a heavy load over the floor above the A & C RHR pumps and the A Core Spray pump or the B & D RHR and B Core Spray pumps. It is not normally used to assist in the assembly and disassembly of these system components. It would not normally be transporting a heavy load in these areas with the shield blocks removed. If it did transport a heavy load in this area it would be physically impossible to drop the load and disable both loops of these systems. The redundant loop to the disabled system would be available to perform its function in plant shutdown and decay heat removal. Therefore this load handling device has been eliminated because of system redundancy.
Item 3 (NRC Question 2.1.3)
With respect to the design and operation of heavy load handling systems in the reactor building and those load handling systems identified in the response to Question 1 above, provide your evaluation cncerning compliance with the guidelines of NURE 0612, Section 5.1.1. The following specific information should be included in the reply:
Sub Question 2.1.3a
Drawings or sketches sufficient to clearly identify the locations of safe load paths, spent fuel and safe shutdown equipment.
Response
Drawings are attached that show the location of the Reactor Core, the Spent Fuel Pool, Safe Shutdown equipment, and Safe load path.
Sub Question 2.1.3b
A discussion of measures taken to ensure that load handling operations remain within safe load paths, including procedures, if any, for deviations fran these load paths.
Response
Procedures are used to control the handling of loads by the Reactor Building Crane and the Turbine Building Crane. These procedures define the path of movement that are to be followed for each load handled by these cranes. As a part of the interim work for the control of, heavy loads, (enclosure 2 of Nuclear Regulatory Commission letter dated 22 December 1980), these procedures were reviewed and revised, .as necessary, to ensure that the load paths 'defined in the procedure were safe load paths. These procedures permit ontrolled deviations fran the specified safe load path.
5
Sub Question 2.1.3c
A tabulation of heavy loads to be handled by each crane which includes the load identification, load weight, its designated lifting device, and verification that the handling of such loads are governed by a written procedure ontaining, as a minimum, the information identified in NUREG 0612, Section 5.1.1(2).
Response
See Table II.
Procedures were prepared and or revised to meet the requirements of NUREG 0612 Section 5.1.1(2) as part of the interim actions for the control of heavy loads, (Nuclear Regulatory Commission letter dated 22 December 1980).
Sub Question 2.1.3d
Verification that the lifting devices identified in the response to Question 2.1.3c comply with the requirements of ANSI N14.6-1978 or ANSI B30.9-1971 as appropriate. For lifting devices where these standards, as supplemented by NUREG 0612, Section 5.1.1(4) or 5.1.1(5) are not met, describe any proposed alternatives and demonstrate their equivalency in terms of load handling reliability.
Response
a. Slings ANSI B30.9-1971
The slings used with the Reactor and Turbine Building Cranes for handling heavy loads omply with the design and inspection requirements of ANSI B30.9-1971. The slings have a minimum factor of safety of five (5) and the rated capacity of the slings used for handling heavy loads shall be taken as those listed in tables 3 through 14 of ANSI B30.9. Inspection of these lifting devices will be performed as required by ANSI B30.9-1971, per annual Hoisting Equipment and Rigging Inspection, Preventative Maintenance procedure.
b. Special Lifting Devices AMI N14.6-1978
The special lifting devices identified in Table II were manufactured as specific tools to be used to handle a specific load. These devices were manufactured prior to the existance of ANSI N14.6-1978. These special lifting devices are not used to handle loads other than the load they were designed to transport. These devices are inspected prior to each use. They have been used to transport the load they were designed to handle many times with no signs of design deficiencies. Inspection of these lifting devices will be performed per ANSI N14.6-1978 sections 5 & 6 Special Lifting Devices for Critical Loads. A procedure will be developed to cover the inspections of special lifting devices that satisfy the requirements of AISI N14.6-1978. Preparation of this procedure will begin without waiting on staff review so that implementation can occur within 2.years of information requested in section 2.4 of enclosure 3 of Nuclear Regulatory Commission letter dated 22 December 1980.
6
Sub Question 2.1.3e
Verification that ANSI B30.2-1976, Chapter 2-2 has been invoked with respect to crane inspection, testing and maintenance. Where any exception is taken to this standard, sufficient information should be provided to denonstrate the equivalency of proposed alternatives.
Response Procedures for inspection, testing and maintenance of the cranes were reviewed and revised as appropriate as part of the Interim Actions for Control of Heavy Loads, Enclosure 2 of Nuclear Regulatory letter dated 22 December 1980, to comply with the standards of ANBI B30.2-1976, Chapter 2-2. b excepticn to the standards is taken.
Sub Question 2.1.3f
Verification that crane design complies with the quidelines of CMAA Specification 70 and Chapter 2-1 of ANSI B30.2-1976, including the demonstration of equivalency of actual design requirements, for instances where specific compliances with these standards is not provided.
Response
These guideline requirements apply to overhead and gantry type, top running, multiple girder, electric, traveling cranes. The reactor building and turbine building cranes were both manufactured prior to the issuance of these guidelines. The respective code committees have been requested to review the adequacy of the earlier codes. A response is expected by November 1981. The NC Staff will be informed of the results of this review. The reactor building crane has been modified to provide redundant lifting features for Monticello based on Regulatory Guide 1.13. The modification takes into consideration the ANSI B30.2, CMAA Specification 70 requirements and Regulatory Guide 1.104 (subsequently withdrawn). The modifications made were. found acceptable with provisions by the NRC as described in the NRC letter of May 19, 1977.
Sub Question 2.1.3g
Exceptions, if any, taken to ANSI B30.2-1976 with respect to operator training, qualification, and conduct.
Response
Operator training, qualification and conduct was reviewed as part of the interim actions for the control of heavy loads, Enclosure 2 of Nuclear Regulatory letter dated 22 December 1980. No exception is taken to ANSI B30.2-1976in this respect.
Attachnents:
Table I & II Figures 1-34
7
. Table I
List of Overhead Load Handling Devias Not Considered Because of Physical Separation or Capacity
Handling Device Capacity-
Rx Building
RX Building
RX Building
RX Building
R.W. Building
R.W. Building
R.W Building
R.W. Building
O.G. Stack
R.W. Building
Turbine Building
Drywell
Refueling Facilities Channel Handling Jib Boom
Refueling Facilities Mtor Drive Jib Crane A
Refueling Facilities Motor Drive Jib Crane B
Channel Handling Overhead Rigging
Radwaste Conveyor Load-Out Monorail
Radwaste Centrifuge Hoist A
Radwaste Centrifuge Hoist B
Radwaste Building Monorail
Off Gas Stack Mnorail
Radwaste Building Sump Monorail
C Turbine Building Portable A Frame Mnorail C
MSIV Area Lifting Iug
* A Heavy Load has been defined (per NUREG 0612) as, any load carried in a given area after a plant becomes operational, that weighs more than the combined weight of a single spent fuel assembly and its associated handling tool for the specific plant in question. At Monticello Nuclear Plant this weight has been conservatively calculated to be 1500 lbs.
1
Location
50 lbs
ID No.
1500 lbs
1500 lbs
50 lbs
3
4
5
7
8
9
12000 lbs
4000 lbs
4000 lbs
6000 lbs
6000 lbs
6000 lbs
1500 lbs
1000 lbs
10
11
12
13
16
18
Location
Drywell
Steam Chase
Steam Chase
D.G. Building
*D.G. Building
Turbine Building
Turbine Building
R.W. Building
Hot Machine Shop
H2 Storage Building
Intake Structure
Intake Structure
Turbine Building
R.W. Building
Rx Building
Turbine Building
Turbine Building
Turbine Building
Handling Device
MSIV Area Lifting Lug
MSIV Area Mnorail
MSIV Area Monorail
Diesel Generator A Mnorail, A & B Lifting lugs
Diesel Generator B Monorail, A & B Lifting Lugs
Electric Breakers Bridge Hoist Room A
Electric Breakers Bridge Hoist Room B
Radwaste Storage Bridge Crane
Hot Machine Shop Monorail
CO2 & H2 Monorail
Screen House Bridge Crane
Trash Basket Jib Crane
Tube Pulling Pit Monorail & Lifting Tug
Radwaste Capping Station bnorail
WCU Filter Shield Block Mnorail
Condensate Drain Holding Pump A Hatch Monorail
Condensate Drain Holding Pump B Hatch Mnorail
Condensate Drain Holding Pump C Hatch Monorail
2
Capacity
1000 lbs
6000 lbs
6000 lbs
470 lbs
470 lbs
1000 lbs
1000 lbs
20000 lbs
4000 lbs
4000 lbs
10000 lbs
4000 lbs
2000 lbs
1000 lbs
10000 lbs
6400 lbs
6400 lbs
6400 lbs
I.D. No.
19
20
21
22
23
24
25
26
27
29
30
32
33
34
35
37
38
39
Location
Trbine Building
Turbine Building
R.W. Storage Bldg
Rx Building
Rx Building
R.W. Building
R.W. Building
O.G. Storage Bldg
O.G. Storage Bldg
Rx Building
Rx Building
Rx Building
Rx Building
Turbine Building
Turbine Building
Turbine Building
Handling Device
Condesnate Drain Holding Pump D Hatch Monorail
Condensate Drain Holding Pumrp E Hatch Mbnorail
New Shipping Building Crane
Rx Refueling Platform Handling Device
Reactor Vessel Service Platform
Radwaste Devices Entrance Monorail
Hot Machine Shop Jib Crane and Lifting Lug
Off Gas Storage Building Jib Crane
Off Gas Storage Building Monorails
CRD Rebuild Area Monorail
Drywell Equipment Hatch Monorail & Lifting Device
Low level Contamination Work Area Monorail
Rx Building Closed Cooling Water Heat Exchange Lifting Lugs
R Feedwater Pump A Mbnorail
Rx Feedwater Pump B Monorail
Miscellaneous Lifting Lugs
3
Capacity
6400 lbs
6400 lbs
20000 lbs
1000 lbs
1500 lbs
2000 lbs
2000 lbs
15000 lbs
1000 lbs
1000 lbs
3000 lbs
1000 lbs
6000 lbs
2000 lbs
2000 lbs
6000 lbs
I.D. No.
40
41
42
43
46
47
48
49
50
51
52
56
57
58
59
60
Table II
Heavy Loads Handled by the Reactor & Turbine Building Crane
Crane
Turbine Bldg
Load Weight
Turbine H.P. Hood Turbine L.P. Hood A Turbine L.P. Hood B L.P. Inner Closing A L.P. Inner Closing B L.P. Rotor A & B
108,420 60,515 60,515
103,280 103,280 226,000
H.P. Rotor
Lifting 'Device
lbs lbs lbs lbs lbs; lbs
82,583 lbs
L.P. Turbine Diaphrams L.P. Turbine Diaphrams Bypass Valves Shield Block Generator Rotor Generator Endbells Exciter Hood Exciter Rotor R.F.P. Motor Condensate Punp Shield Block Condensate Pump Condensate Pmp Motor HIP Heaters HP Heaters Turbine Gen Bearing Diaphrams Palets & Miscellaneous Material
Turbine Rotor Stands
9000-12000 lbs 12000-18000 lbs
2,700 lbs; 281,832 lbs 112,000 lbs 22,000 lbs 35,000 lbs 35,000 lbs 10,800 lbs 18,600 lbs 12,900 lbs 45,100 lbs 46,900 lbs 5,580 lbs 2,000 lbs
22,400 lbs
Slings Slings Slings Slings Slings
Strongback & Slings
Strongback & Slings Slings Slings Slings Slings Slings Slings Slings Slings Slings Slings Slings Slings Slings Slings
Palet Lifting Device Slings
1
Procedure
Yes Yes Yes Yes Yes Yes
Yes
Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
Yes
Weight
Rx Building Vessel Service Platform Stud Detentioner Carousel
Fuel Pool Shield Blocks (3) PRV Head
Drywell Head
Fuel Pool Skiirmr Tank Shield Blocks (3) Steam Separator
Steam Dryer
Rx Head Insulation Refueling Canal Shield Spent Fuel Shipping Cask New Fuel Storage Shield Block (3) GE Model 1600 Cask Equip Storage Pool Shield Block (3) Rx Cavity Shield Block (6) Fuel Pool Shield Blocks New Fuel Shipping Container Drywell Radiation Shield RPV Head Piping Fuel Preparaticn Machine RPV Invessel Work Platform
6,000 lbs 20,000 lbs
10,000 lbs 90,000 lbs
80,000 lbs
6,000 lbs
66,000 lbs
44,000 lbs
9,000 30,000 49,464 5,000
25,950 87,000
lbs lbs lbs lbs lbs lbs
100,000 lbs 10,000 lbs 2,000 lbs
30,000 lbs 2,000 lbs
10,000 lbs 100,000 lbs
Lifting Device
Slings RPV Head Strongback Slings
RPV Head Strongback DW Head Strongback
Slings
Procedure
Yes Yes
Yes Yes
Yes
No*
Dryer Separator Yes Strongback & Slings Dryer Separator Yes Strongback & Slings
Slings Yes Slings Yes
Special Device No* Slings tb*
Special Device Yes Slings Yes
Slings Slings Slings Slings Slings Slings Slings
Yes Yes Yes Yes Yes Yes No*
* Procedures will be written.prior to the handling of these heavy loads.
2
Crane Load
FIGURES
-4- ..-- -
Designated Safe Load Path for GE Model 1600 Cask Procedure 8111 Rev. 1
FIG.
- - ~---.---.,------
/ ( N
RAF P&oCA
/ /
... ~. ~c *o~
- - ~ * ~ ~ ~
r5~ 1-17V 11/\J1
k~ tt~ *uq. ~ATC~
Fzzr Li77iiii
I
* aCarra.
* JTCI
Dalwta "PO -.O Ita.s
- ____- - -1~--
Fig. --2 Designated Safe Load Path for the Removal of the Reactor Well Shield Block 5
Procedure No. 9203 Rev.4 --- -N
0OOL N.0
LIFId
L~J
'Woo
1
ZEI
1A~f.~
z~t.
-4- - -
- -___ - --- -W-I-- -- ---- - ------- - __- -
Fig. - 3 Designated Safe Load Path for theRemoval of the Drywell Head Procedure 9207 Rev. 4
04 ____- ---- 1OO -Tr
Pu oo, so1 ot w 9tt Aug Na' per
grw*
rM e
o
69* *~A,,*b(
/ /
/
~iI .
A4~~ / /1' F *~~'"
SUIt I9*~I OO. K > XI
\ ./ KrJ [2Z~~~
i ~ .1
I
.4~~.Cr ~'Oe,4 3'(PAS
W1TTT
-1
L1
-a W-
ff9
A4
-----------
l
os~~la .M~ "0 'C~
F-
----- ----
7 / (
:<fl
N N
flk tpvcd
/
/
J I - -
Fig 4 Designated Safe Load Path for Removal of 7 Shield Blocks on Refueling Floor Procedure- 9209 Rev. 5
lblit (~AMtthatL
.- I ~ - _ _ _ - - -1-
/
b U
F-1K 2' L.J
HI] ,Fks V4~71
II
~A~cu ~iM~em~
I
__ I
the -- --
the
.F .... -----
I
"lAO t'g t ~
4- - --.----- .- -1- - ___ -
Fig. 5 Designated Safe Load Path for the - -
Removal of the RPV Head Insulatio Procedure No. 9213 Rev. 4
1\\
AT]
riri. 'I.LJLJ
' 11
bs ow t e
s.oman
r ~~~~-1
* ~,t.
* ,r~n L~i
,4A0
El
3. TmA
Fig. -6 Designated S.fe Load Path for the rInstallation of the Carousel and Detension PPV Head Bolts Procedure No. 9214 Rev. 4
- -- - ---- _44 ru
.11z
ft,140 T0 P O 0 *G4PE0- i*i
S54To V ttt
Fa~a.5ra~ar.,Pcvt
1 T
- - - - - - - ---
I r AskA a Ive
Ia
-4-
---- 4-- - ---- I - *-*-- ______ - ____ -. ________ *- -. 4-------
Removal of the Carousel and Sl
Procedure No. 9218 Rev. 3
reastT
...... . .. 1LeL
[P[OO TO p Hf /Day -ML
M
At LA I
1 ['i I~AIFI)N
J1'A,_
the--- - ,
Ing
//
Puts. I'OtGO POOS.
'-i LI'
A
I; L~.
7I U
I
01
1
L19u11L1
J
Fig. 1--7 Designfated Safe Load Path for I
-1
St '~~S4 *55~4
2 II
2]
.-JJ C,.
I]
Fig.
ii ___ [~] L -___
TT - ---- T-- - - -- I
~d ~if~ T.o~c1 P~d-h for thpF~2TZT7TT2'1
* <
I
Removal of the RPV Head Procedure No. 9220 Rev. 4
ElL.- i
AAE.
-I--- - ---- I- *------.-- -- __- - - - __ -L
L L
.1 ii
112 II
no, Pooe 1oo0a rvo rie 5
L9LiJ *1
- .- ~
Fig. l 9 Designated Safe Load Path for the Removal of the Steam Dryer Procedure No. 9224 Rev. 3
Fig. ' -10 Designated Sake Load Path for the <-
Installation of the Drywell Radiation Shield Procedure No. 9226 Rev. 6
L 11 - ~ -*-. * I
7-
1
N
At ALTOA
'T
V!.-
II[I,:'
m lalIII~WWWIINMMII
i I
/ /
'-S A
7
~~1
£
- itt C*'O*
Fig. 11 L d Designated Safe Load Path for the ' Removal of the Steam Separator Procedure No. 9228 Rev. 4
-- C. ~ 3
Fr--
L~.
-I
*:f)
1
i I
Fig., Designate Safe Load Paths for th Removal of the Fuel Pool Gates Procedure No. 9229, Rev. 0 I
7 / (
- ~
N
/
o .. ~, ~, .&. S 'TWflft(r
.. V.-.,-.
O1
h~1tM
C..mon - M en
Fig. 1 Designated Safe Lo Wet Transfer of th Separator Procedure No. 9231
e Steam
, Rev. 3
V -- 3, 17 -.
N
/
I * 41
----------------------------.4
-----------------------
- l~4
jttRA
/
- --..------- ------i- - ______
4---- --- 1 - ____ __ --- 4-----.
Fig -- r -. Designated Safe Load Path for thf Installation of the Service Platform Procedure No. 9243, Rev. 3
0T
WW --. * *u L A P o A
SoF - o -p I
-, II AS
~to
II ( t
LI
LII LI
Fig. 15 Designated Safe Load Path for th Removal of the Service Platform ~ Procedure No. 9245, Pev. 3
$
I- -
'~1-j "L~i h-I ~LK1
~2I1 I ii LLJ
~-~=- I 'YTIWhl~W
1~
'-I
F7~-o. I _ 1-' 121
DI:,
I
II
1
>2
--p-
/ (
N
/ /
________ - - -_____ - --- ~----.---- - -- - - -. 4---- -. ---- - -I
r~7* -
Designated Safe Load Paths for the Installation of the Fuel Pool Gates Procedure No. 9250, Rev. 0
p --~K LI7Ii1i]
-I
lj
/L~ ~ /
L~] .77]
_ .~VL!ii K ~
Icp.,LIL
,2. £
-xl
(~ ~,CS 4 Id --4" '44
I, *,
I
LJLJ: I.
-4--- - -_
Figj. - _ _ - _-_
Desi.qnated Safe Load Path for the Installation of the Steam Separator Procedure No. 9253 Rev. 4
1
-------------------------------------------i
I!
I /
() ----- -- " - - - ..- - ir' L 9 ----- ' _._-__ _
A~rjt ~AIUO~~
Li
F ig. W Designated Safe Load Path for the Removal of the Drywell Radiation
Procedure No. 9256, Rev. 3 Apt u
- .L __ jI~Y -
/ (
7
L71
2
st tI 410
, -?
mQ 5f
Fig .: Designated Safe Load Path for the Installation of the Steam Dryer Procedure No. 9259, Pev. 3
N
I /
1 L m~~i] 1*
LI] n*~4
0I
.jI~ -
1
.--- -- ---- - - - T---- -
Fig. 1 20 Designated Safe Load Path for Installation of the RPV Head Procedure No. 9262 Rev. 4..
N
N
/
J 4- - - .
*Ut. ... t,4
-,IUD LAP40USOL
O
t.k~at 'C44 b
71 12 :311
T-
-- Of
711
Installation of the RPV Stud Tensioner Procedure No. 9267, Rev. 6
O. ..
-n
II
waga to
~PKW.
f *I
__- --zLi
D------------------------4
I
oA
- -r MIrj
5___
teA PoDp
*b..******1 -- Tr~r-a
44 -S 4r-.
I - --- -------.-- ~~------.-. .-.--~-~-.~r-- ---- - .------.--- - --4 -- .- -
Fig. Designated Safe Load Path for th
- ----------I-- - --T - -
-4- --_ - - ----- -*--
Designated Safe Load Path for t] Installation of the RPV Head Insulation Procedure No. 9269, Rev. 3
UN
-
o - M1 ~&.t. A9
~ 'C..,
, . Z ............ L ..........
MIA LpLN O hIP.e)LAIsep:1
I *IW *,jI, mAtt$
F~~71
-I- -
At *L" b
.L.
Fig. 22
I!
__ di -7 LF§W.
~~1)
1:
-- - 4--- -- -[------ - - -- -- -- -i 7 +C Fiq. 23 1 [)esicjnated Sfae Load Path for the I' Installation of the Drywel flead '"
Procedure--No. 9275 Rev. 4j
1 - j -----j -- ---
I~~ ~ L#]sotlo A r I t Fo
C.4.
4- -1 4 --
O
M -b 6 r *
urag Apr*
D(rnen re pp
newtkL .4ga *. '
IN
a Safe Load Path for the
lation of the Dryer/ tor Pit Shield Blocks ure No. 9279, Rev. 4 to Pt hildBi-k
Z71
- - -1
S.-.
I
4. -J
/1LrARWIAI.
K X
LI9U~~J
* ~Fig. 3 :
Safe Shutdown Equipmtent -Ardas.. A Special %Safe -Load Phath Mist: lie
* ~~~~Designated I A HayLa Gt IMoved over - These Areas.. Procodure No.; 811.7, Rev. 0'... r.
I....................__
*4 I, 7K I __
__AU___ F.I I-. BT~T .~ Ii ~ J.L Jt' j6"
I~~I I ,. I I
''Op j .'A
EI 11rI 1- 1
C'.'
I I t V
(3 . , * LI
----------
(7 / T ~AT 1 1 r . Js .1 .' I _ _ _ _ _
L 7 ..... ....
low .lTS
I~f 03 p T~ S)~.,' '~rr~T~Ic- I-IC'TT) T
3 t ~
K E Y PL-.N
SyirLSYMBOL
r/////A -mwCot%^"& IVALof
,
I _A,-T
Al(D .(p 1..0
- -. ~ T:301 i -p
~ik
k;A *UU
~~0
N!O. lyE
C-pm.
It.
EXCHl ACCES
iUFrING LUSFOR
VRtIR PUMP ROOM
ACCESS MATCH ITEM *SS
A
'4
~-
ACCI KIA'HA aUFTI
2MLy'&Ei MS7
LuCk FUR RE ILD Sum AREA
ITEMA-u WaLL rr
Tim P -=,.
PI.Am RECI
w GL)
-MLZ&
LA-z-on-A ul
Ae
wthr M444341I4w1I
IA Il
I,
9
i~4'
VJ~,','71ILE~EI __ *"
-+~-I-- 4 -44-4114 1-=4-;1%-'14
DRYWELL EQiIP
PolkS ADSUSI Aaftel .1. et & 1
WOUNTM6 P"
I -I.- 1 IIV
T
h
II
?ACCS KATCH'. 'MMORALL4ITEM5i
VA9 PAUbm
I-
P 0-O?~ -i I
cow
CRMWAOL S, %AMD MOT. &MPAL
Lo"CaNADOW rl[L. 94%"PT.
LOW-% %DM
Mao.CALlww
vagne"
P Zr-- -'--r-J EEEI
~L1M AT ~L 9ES-0
'AR4RPUMP M AkCCESS KiTH,-
NOTEiN.
o.
moms M % ASVWi APAX OU W& u-I TYPICAL bYMBOI
__________ IL~ DC.A4IAAh £,ISLaPS
a
PLAN4 AT EL.93S'-0*
PLAN AT It. 93SP-.O & OFF iCE BLDG EFIG 7I PLANS- l-EL-0~& EL.SW3O'
4''
r
Zf W"
M Soo XOM
cm
IP7
.7.,
M EF
w 1
94c" combiw
RM
I
1 ZN W:. . i rr-s- 2r.sl . . i I - r W M'. - i
Vo M, W-;: o , k 0, 0 P, t I i ,I-
lum-77 = 7 -;Oll:T Zrf I ML- wr-9D
Aw- - -- 1191
FL41F-4- - Msm--H i i - i - F!f A95f ; --pr IML0-4..l
;IT
eolM
4r-==t- at- - il .- Ju Q OL
.,--T , mb*
1± 1IL
CA" a
CANTI
Ir
I
Al
41 69
Eli "II -.-- FTj nt
t EAC TOR S6OACG / OPE
CXOTMINATED E9LIPMEWTrTW1F All. r 7 *
1,lYE2 E PSEPAQATIS .1). .1T P.1.1FO 5LAGt P;7L l'II
(BOTTOM)~ COTOM STEAM OTTM)NI/rTT
I SOO~ L J
79)
PAF.
OPEN~ "TWA,4ME
Wat6
I I -C V EUIPMENT I (40 aooa, ~VUAi((OPEN)
/ / 5 LEVTO
-- -- fT -
b.9.
L
PLAN AT EL. 985'-G"
r7=7 iFML~ftCrwD CotO-LAC.6 G:ivc%.ope
,d L~.0 a/a,,6. o snotI iv
Thk~
RE OVISED AS I00120102e
FRnCONSTI4ULT-uO.
~.9 BECHTEL ""oN.52 -1 M4
SEERiLOIIELETRIC RD tL ATWAIC POWOM W. DWT. sm SJoE.Cst
~IIEJ:PMENT LOCATION - EACTOR-BLOq.I 14NSAT E L. 98 5t-6- & 100 I 2."
I I I:
V-CF-17--
V OF-17A
V-FU-3 FILTER UNIT
PAN COFOOL
.1
N
31' 4,1,6 79
KK~ ~ FI LTERS E6 ' W406 ST' t2~
E N R , F - -El
7CENTQ.FAN -t21
0 1 1 F
4 F 2 4 M*
GAS SGTSj F,
a FAra~t OL
TERWAERnonFAt
woO L O 5 - , \OE R O S-,
Al. 11-ETON SL0 N.1
221-9' 22-3'4t 27.2
11
T IFY
u IT
91 tellf-U4
I-21AA
.31
- -T ~
4
KEY PLAN
2",
"LS OFC"HELUKSM
BRIDGE CRANE
IT-I-0-1.T
U.4 .STAIKL.009 - -- ,.L.174 a- -. IF-~*
.3 P tA
LEL -74 i~f -74Jd
A[A
t.S. LZ-le! 3- n-,-uY4 PLNALE.-0 OEAIN LO 4+ 4T
90
jF3&7pRrNGPORPLNA
E
j-
-~ ~-1 - - I -I
7
GEN
,>,GswL aew LFrl Gp Luers, TTem
Loiss OIL cetpActry w7o, i6s Mcw4citiNts- T-T6611A F IL.Takik tArictAlwa
vlIc_%TV &47 0 16 3. A, w - - 16!-G'_ soof, 71b L
ARK C.1" 1406 AA
P'taku .. ... ... ... .
J(p c I
T-4 5 1
. x -ruex Poww& Pir rG Memick
itdkl%
TIV.&Yyllyll 3S TAI%61 all, 1300GALA. P) I TOM) KEY PLAN
WORA&C A'R COMPRILA"A, S, P 5 Al (6) AIR WECE.Vilks- J -I ;
7-4 A EYWAUST FAN A IN amov 0)
-42 HIM. 6 E, CONSTKOCT
'Y"AUST
FAI
A, -0 0.4, spop UNIT I 1 - Z 11111mrsucrumm-I
L&MMER&U El) VATER Z M IC VA IN LI.I.ER.. ED IWE.
T T_ CA, F, S26,W) To LAGI -ws tK
T6RDG IF. F- TRANI tA ,W3.1 TAU! -SA 641 WZ7 CCAPOWCITY
4z Toms) J4
E U,
F LUGS
Lj E-, Pj COIJADG. [L.10W ;VE 11 r 1,3 -E,-C , .t5-- ALUM
-4
Dal STAIQ-2 CCAG.F0" -it Puup\
5g C,
S.ITCHGEAP C.1,5 I A4 I P-73 -- ,'.SPLfD-UMp
-AG '9 VIDA. T-5A TV. t
WPUATEI? F, L ATC. ps
_4 - M"' S.. LUGPS FILTERTICS,
"-T-61 CA c ,T ON ct.1 aj i 6,4* A MZSET t; V2 I, -
WI-PAIS BAJS EL. 93e 0' T NEC
It TEQ 16
CAUSTIC TANK
:12 QIGEIL
V AC-2 L MIT IACA 0 pr
ACID
mumo &US COOLER STA," -LfQ.EL.93,V
T a I.Ts FO& -T 9 ; 1, MAIN GA F:ILTOK Pilo TANK < %fUT2 I ND k e -12Y 1 . 6,jW_ AU ILI
W :UT <
A Fr..
tD 4t , V.AC-I 4'' 110 'AN -N-.FCOAT TANK FLR EL.91111
MAIN STEAM 9 CONTML VALY99 L 9ba.0
0 E STATIIN Ax
AE Aii
FIEDWAXI IL-ISA
E-Ibb
93 T-7, t
C J
met.,
4H M_ MIa M-115
2SW 214'
.. . .......... .... .. J" REVISC. M AS 8=7 1~1 CA,
C7, Ail) 01 gr I TURBINE BLDG. 4
REACTOP BLDG Al -1, El T!M41
BICHTIL IZI M-7 Pumps w mv 0 p r,
UD 7:Tems 3 7, 3 9) it 0 4 1 SENERAL40 ELECTRIC
IL ATOM KWU MW Wf WA MmL a".
LAD" M NTKIJAD WJILM 0111111RAIIIIIIIIII
49;- 1 1 1 ft LADHK1k
_PLA t AT MEZZANINE FL. ELATPOW DETAIL P11E 111- TIAMINIL kto 'P"Llk' AVILL-131 01 T,
W_ 3
®JK~ - - -~ -- ____ _______ I __________ I; ;.~Lj.
.-o.
LA IA....
K I ~- I j~J~o-j-~~+--L- tU. I.' uMENT
U
tLi
-4 - - LA.~. Pu...,:
(M~4ORAJL~ ITEM
HOSflL / A.11rj PL
Soo? - _
P-wo 7 '3
O.1<IC %.V9.~ \
- ok
( A, AAM WASTE SAMPLE TANK
T-
31 A
F-
3rP
'a I
-t
- - Liz±L~a .&'± .... ZZ~I AL
k A' T
LITM74
RA-WST
C-"~N
* A C4-", C" SOalkS
*2
14.11 M16
-- ___ - - * --.--~--- (RAW'STE CONVEA
I OfMOIST M. A NAT L9E4,0' ) r
S
i
tcj _ _
- -ROOF
P AjAC EL. 96Z-6'
47,
A'
/ A1
// j
-v
~.. I
U I
-LOW LIE'- .IRA;, STOR.4E ~
~~~~1I ~~419H LVEL AL. STORAGE _________
1 1; / .. - -ii 0 !
I.'.. 1f] j I IPLAN AT EL. 93S-O'
rT~'54
P 14
-l
4F S. I-I
a S
1*
C.C3UTU3I. ~Ah~L
TIPIC.AL.. YAAAL
lk4LAAM~ ~CVM~85 INVSLO~W
A, m-
[ZIZI .O HM(9JpN6 fi iastAD WASTE BLDG F P23IPLAN AT EL 935W.: 947:0 & 962-6
'1)
14!
-le .. I f
I i ,-V
iL-'W LIVEL OZIAGE
LL.EL 1 .14 Sl.^AA E
.-- - Gi T
I
is'-*- ,14A' 11 1 ta!TYjt,
-ff
-i
I I A-j I ill r i -.1:r-.
! I I .
RADNASTE CENTMF
N
N.'
K
N
KEY PLAN
M- 13
.5 '/
)
-U-_
I~j DIII
~C. PAUDL-
N L
cosa VAT PUMP
-iLMi
~~~lv ZIP 5 ~ ~ A ~ r
I26 Th28zhELm
WAIDSE DC
-52A
rf-To 60 9 Al
GZA - ENTIE"I
5T--Q'2
AZT. p JAPS
DEEM' .4,GOV.SWITCKGEA 46OV.SWITCM EAR Li I I AS t JE I i I A91 1
480
4% EL. 91I O
44
I A/1-2A
LGE, RUE!, !.8
3
sll 01 L. .1 0 15 7' UNIT
Ful. 3-3
L it
91
AIR E F. P, -t IT
MMT S7 EA
PACICINMG P". IA EKKAUSTLQ
- I I -Top CCNXN5ATE PLOAP
T'Ll V QUIR
MPV - I I su"P pu- w
5EAL',V PL I
SIMPIK.TW D..
sS OGALS.
C 12V
2! .0. to"IL I p A
m PW. T%&MV IK Pum
Ce*
CONDENISKTC
T CPTA.K 2210,
-:
23 6* 2 l L
V
LAUND)E
-- -t . IT-
AN
IAD DMINERALIZE 'LDING DUMAPIT0
Ad A-D
-COIAI NO
'PEWAY
-DE rrL
PARTIAL PLAWAT ELLY WSW
ORAIN COOL]
FLR.FL.48O
RD
1~
,05 c2OQ6T 42A -T-S,
S. LISLAO".I
CUSIS%1' T 41 I U A TDQEPAAT
T. .. T-5A
1WDCMiesI
MML~ec.p o'eDr~i
GROUND FLOOR PLAN
COWL 4szs~
21I6
BIll, I VIII I.' I I,.,
-. __________ MDI
AIII.I26vI4Ur LA I.JflCnrPlO :t1. lIlUDS
ICE MA NUDWEM K.0 IILId
FLTKS UM .
L.D CUE.TPMI -L
j-gDViCPssa Uta -4-.
7 296
RomeDASI UR
A 21tk
---p ID.
pWJSEo 7 A 211TCU PADTOpq w
CSSUEV FRgC n5 SUCTI3N i "
15SLED FCR OSFIDITIVE ESTIUTE
toM-1
tII
I
.I. I h. I - f4
l::---9
-L214" 21 6, 4 - .- 7:
: ECIT;06
kI
C2I50
PUW MCN
C". -T.QL TMK
-41
t
CAP 4± 1 I,
0
or
/ EK~
/ ~flk ~N~ 4r
vp v
* Icjj~ .~: '~/2' N ", -'
i~..j* ,
* 1W
FiG 34 PLAN AT EL. ~So
IC e-lf