fortis empress 394s substation upgrade r1 · empress 394s substation in accordance with the...

16

Upload: others

Post on 15-Mar-2021

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required
Page 2: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Substation Upgrade R1

Project No 1679 AESO Functional Specification Page 2 of 16

Functional Specification Revision History

Revision Description of Revision Author Date

R0B0 For comments Henry Ng November 27, 2015

R0B1 For External Review Henry Ng December 3, 2015

R0 For Issuance Henry Ng December 14, 2015

R1 Revised the scope of work to include a new 25 kV breaker on bus 2.

Revised SLD in Appendix 7.3 & 7.4

Henry Ng June 6, 2016

Page 3: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Substation Upgrade R1

Project No 1679 AESO Functional Specification Page 3 of 16

TABLE OF CONTENTS 1 PURPOSE ............................................................................................................ 4

2 INTERPRETATION AND VARIANCES ................................................................ 4

3 PROJECT OVERVIEW ........................................................................................ 4

4 FORECAST OF FUTURE DEVELOPMENT IN THE PROJECT AREA ............... 5

5 SCOPE OF WORK ............................................................................................... 5

5.1 General ........................................................................................................... 5

5.2 Compliance with AESO Authoritative Documents .......................................... 5

5.3 Modeling Data Requirements ......................................................................... 6

5.4 Substation Equipment Specifications ............................................................. 6

5.5 Specific Scope of Work for the Legal Owner of the Transmission Facility ...... 6

5.6 Market Participant Scope of Work .................................................................. 8

6 TRANSMISSION SYSTEM OPERATING CHARACTERISTICS .......................... 8

6.1 Short Circuit Current Levels ............................................................................ 8

6.2 Voltage Levels .............................................................................................. 10

6.3 Insulation Levels ........................................................................................... 10

7 APPENDICES .................................................................................................... 12

7.1 Existing Transmission System in the project area ........................................ 12

7.2 Single Line Drawing – Empress 394S Substation – Prior to the Proposed Development ...................................................................................................... 13

7.3 Single Line Drawing – Empress 394S Substation – Proposed Development 14

7.4 SCADA Point Requirements ......................................................................... 15

7.5 SCADA Data Requirements ......................................................................... 15

Page 4: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Substation Upgrade R1

Project No 1679 AESO Functional Specification Page 4 of 16

1 PURPOSE (1) The purpose of this document (the “Functional Specification”) is to set out the technical specifications and requirements and approved variances issued by the AESO to the legal owner of the transmission facility, AltaLink Management Ltd., and the market participant, FortisAlberta Inc., related to the design, construction, development and commissioning of certain new or modified facilities (the “project”) that have been proposed for or are related to a physical facilities connection with the interconnected electric system (the "Purpose"). (2) This Functional Specification is issued for the Purpose only, and the legal owner of the transmission facility and the market participant must comply with the Functional Specification provisions. (3) The AESO is not responsible for any facilities designed by or for any third party, or installed on a third party behalf, to accomplish the connection of the project facilities. (4) This Functional Specification includes:

(i) Certain specific engineering, technical, and functional requirements for the project; (ii) The requirements to comply with ISO rules, including OPPs, reliability standards,

technical standards, and ISO tariff provisions (the “Authoritative Documents”);

(iii) The electrical system environment in which the connecting facilities must be designed and operated; and

(iv) Any approved variances from requirements set out in any applicable AESO Authoritative Documents.

2 INTERPRETATION AND VARIANCES (1) Subject to subsection (2), any revision or variance to any of the Functional Specification provisions by the legal owner of the transmission facility or the market participant is prohibited.

(2) The legal owner of the transmission facility or the market participant may make application in writing to the AESO requesting a variance to this Functional Specification, and the AESO may in writing approve of the variance after the AESO has completed an analysis of the implications to the interconnected electric system with respect to the requested variance.

(3) Words or phrases appearing in bold have the meanings set out in the Consolidated Authoritative Document Glossary. 3 PROJECT OVERVIEW On July 8, 2014, the market participant applied to the AESO for transmission system access to improve reliability at Empress 394S substation. The market participant’s request can be met by upgrading the existing Empress 394S substation, including:

• Install one(1) 138kV bus tie breaker • Install one (1) 25kV voltage regulator • Install a new 25 kV bus with one (1) 25 kV feeder breaker. • Relocate one (1) existing 25 kV feeder to the new 25kV bus.

Prior to this Project, the legal owner of the transmission facility will replace the existing 10 MVA DETC transformer T2 with a 25 MVA DETC transformer as part of its capital maintenance program in 2016.

Page 5: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Substation Upgrade R1

Project No 1679 AESO Functional Specification Page 5 of 16

The requested in-service date (ISD) for the Project is August 2017. 4 FORECAST OF FUTURE DEVELOPMENT IN THE PROJECT AREA Refer to AESO’s current Long Term Plan on AESO’s website (www.aeso.ca) for the details of future development in the project area.

5 SCOPE OF WORK 5.1 General (1) The legal owner of the transmission facility and the market participant must complete all engineering, design, land or land-use acquisition, siting, public consultation, applicable regulatory approvals and permits, material procurement, construction, commissioning, and associated permitting requirements for the project facilities.

(2) The legal owner of the transmission facility and the market participant must coordinate with each other as required on all project facility design details, including protection and control, grounding, insulation, point of connection, and site layout.

(3) The legal owner of the transmission facility and the market participant must develop joint operating procedures and any connection agreements as required such that all connecting transmission facilities will operate safely and reliably.

(4) The legal owner of the transmission facility must deliver to the AESO all final design and as-built project facility information and records in the format and content required by the AESO, to enable the AESO to update and maintain its technical records and system models.

(5) The legal owner of the transmission facility must submit the project information and records referred to in subsection (4) above, under the professional stamp and signature of a registered professional engineer in Alberta who assumes responsibility for the preparation and accuracy of the content of the information and records.

(6) The legal owner of the transmission facility and the market participant must ensure that their respective project facilities have been inspected by qualified personnel in accordance with industry standards and practices, so that the project facilities are declared to be:

(a) Safe for operation prior to energization; and

(b) In compliance with this Functional Specification, and any Authoritative Documents for which the project must comply

(7) No project facilities are to be energized until an energization authorization has been issued by the AESO in accordance with the ISO rules.

5.2 Compliance with AESO Authoritative Documents The legal owner of the transmission facility and the market participant must comply with the Authoritative Documents provisions which are applicable to the project and which requirements must be satisfied and incorporated in to the design, construction, development and operation of the connecting facilities and other connection project work, including but not limited to those provisions contained herein":

(1) Alberta Reliability Standards;

(2) AESO Measurement System Standard Rev. 1 (dated September 18, 2007)1

Page 6: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Substation Upgrade R1

Project No 1679 AESO Functional Specification Page 6 of 16

(3) AESO Generation and Load Interconnection Standard (dated September 19, 2006)1;

(4) ISO rules, including but not limited to:

Section 502.3, Interconnected Electric System Protection Requirements (effective March 27, 2015)

Section 502.4, Automated Dispatch and Messaging System and Voice Communication Systems Requirements (effective March 27, 2015)

Section 502.8, SCADA Technical and Operating Requirements (effective March 27, 2015)

Section 9.1, Transmission Facility Projects

5.3 Modeling Data Requirements All modeling data shall be provided per the Information Transmission Modeling Data Requirements (issued on February 6, 2014).

5.4 Substation Equipment Specifications All new substation equipment must meet the following minimum specifications:

• Temperature rating of -50ºC for all outdoor equipment.

• Equipment maximum and minimum continuous voltage ratings as indicated in Table 5 on page 10.

• Minimum continuous equipment current ratings as indicated in Table 1.

• Equipment maximum fault level: 31.5 kA for 138 kV.

Table 1

Minimum Continuous Equipment Current Ratings (A)

Component 25 kV 138 kV

Main Bus1) 1200 1200

Cross Bus2) 1200 600

Feeder3) or line terminal4) 600 600

1) Main bus includes all sections of ring bus scheme and single bus of simple bus scheme. 2) Cross bus includes diameter sections of breaker and a half or breaker and third schemes. 3) Feeder includes all equipment from the connection at the low voltage bus to the riser pole. 4) Line terminal includes all equipment and conductor from the transmission line to the line breakers.

5.5 Specific Scope of Work for the Legal Owner of the Transmission Facility (1) General Requirements

• Ensure project safety is appropriately managed through all stages of the project.

• Complete all site preparation, foundations, grounding, bus-work, support structures, termination structures and cabling as required for the proposed additions.

1 The AESO considers this standard to remain in effect notwithstanding the statement in clause 1.5 in the standard. Efforts to revise the standard are currently underway through an industry work group.

Page 7: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Substation Upgrade R1

Project No 1679 AESO Functional Specification Page 7 of 16

• Complete insulation coordination studies and coordinate with the market participant as required to establish appropriate insulation levels.

• Ensure all required grounding studies, testing, and mitigation are completed to make sure the connecting transmission facilities are safe.

• Coordinate all alignments with the market participant for the 25 kV feeder connections.

(2) Substation Empress 394S – Appendices 7.2 - 7.3

Substation Equipment and major construction Install one (1) 138 kV bus-tie circuit breaker with the associated disconnect switch.

Install one (1) new 25 kV bus, with one feeder breaker and associated disconnect switches.

Re-terminate 25 kV feeder 427L to the new 25 kV bus.

Install one (1) 25 kV voltage regulator with minimum capacity of 25 MVA.

Convert existing 25 kV 427L feeder breaker to a normally open bus tie breaker.

Install and/or modify all other 25 kV isolation devices as required.

Protection and Control Provide breaker failure functionality for the new 138 kV bus tie breaker.

Complete system protection coordination studies and coordinate with adjacent substations and the market participant as required to establish settings appropriate for the facility additions and Alberta Interconnected Electric System (AIES) operations.

Install appropriate protection for the new 25 kV bus and feeders.

Install Under Frequency Load Shedding (UFLS) relays to meet load shedding requirement as per AESO’s OPP-804.

Any frequency relays installed to protect equipment for off-nominal frequency operation must function at a transmission system voltage equal to or above 80% of the rated voltage.

Install all other required protection equipment for the safe and reliable operation at Empress 394S substation in accordance with the applicable ISO rules.

SCADA Establish or update communication interface points as required such that SCADA

data can be transmitted back to the AESO’s System Control Centre (SCC).

Provide Control Center data mapping and verification of SCADA information for the proposed transmission facility additions. See Sections 7.4 and 7.5.

Revenue metering Install demand/energy meters as detailed in the AESO Measurement System

Standard to measure power flow through the Measurement Point.

Page 8: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Substation Upgrade R1

Project No 1679 AESO Functional Specification Page 8 of 16

5.6 Market Participant Scope of Work (1) General Requirements

• Coordinate with the legal owner of the transmission facility as required to perform insulation coordination, grounding studies, protection coordination, supervisory control and data acquisition

• The market participant is required to participate in the AIES under-frequency load shedding program as per OPP-804. The market participant shall ensure that sufficient load is equipped with under-frequency load shedding relays that are capable of being armed in each frequency band to meet the program specifications, and have the scheme installed, tested, and commissioned appropriately as required

• Co-ordinate all alignments with the legal owner of the transmission facility as required to connect the market participant’s facility to the AIES.

• Ensure connection project safety is appropriately managed throughout the project

(2) Empress 394S Substation – Appendices 7.2 - 7.3 Protection and control Complete protection coordination studies and coordinate with the legal owner of the

transmission facility as required to establish settings appropriate for the market participant facility additions and AIES operations.

Revenue metering Provide the description of the measurement point location for the point of

delivery/point of supply, and the acceptable installation options for revenue metering in order to report on the measurement point.

6 TRANSMISSION SYSTEM OPERATING CHARACTERISTICS The legal owner of the transmission facility and the market participant must ensure all new facilities are capable of operating in the following electrical environment.

6.1 Short Circuit Current Levels (1) The short circuit current levels set out in Tables 2, 3 and 4 have been developed by the

AESO based on information provided by the legal owners of the transmission facility, any connecting generating units, and adjacent operating areas. Available fault current levels will continue to increase as generation, transmission, and system inter-ties are added to the interconnected electric system. The legal owner of the transmission facility and market participant must continue to review the fault levels and their equipment ratings for adequacy.

(2) Any future equipment upgrades or protection system setting changes required due to

increasing fault levels are the responsibility of the legal owner of the transmission facility or the market participant, as applicable.

(3) The following assumptions were incorporated into the AESO short circuit current models:

(i) All expected Alberta generation is dispatched.

Page 9: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Substation Upgrade R1

Project No 1679 AESO Functional Specification Page 9 of 16

(ii) All transmission elements are in service.

(iii) The proposed project facility is connected as per this document.

(iv) Vbase = Vbus, MVAbase = 100

Table 2: Summary of Short-Circuit Current Levels – Pre-Connection (2017WP)

Substation

Base Voltage

(kV)

Pre- Fault

Voltage (kV)

3-Φ Fault (kA)

Positive Sequence Impedance (R1 + j X1)

(p.u.)

1- Φ Fault (kA)

Zero Sequence Impedance (R0 + j X0)

(p.u.) Jenner 275S 240 262.3 7.20 0.006128+ j0.036080 4.68 0.022650+ j0.092934

Cypress 562S

138 140.7 8.67 0.005325+ j0.049044 8.67 0.004347+ j0.051206 240 263.2 5.73 0.006277+ j0.045673 6.22 0.003863+ j0.036021

Ware Junction 132S 240 260.8 12.33 0.003859+ j0.020894 11.55 0.004074+ j0.024345 Amoco Empress

163S 240 263.1 5.77 0.006167+ j0.045361 5.86 0.005979+ j0.044239 138 140.4 8.63 0.005728+ j0.049103 8.30 0.006893+ j0.057294

Empress 394S 138 140.4 8.50 0.006061+ j0.049818 8.20 0.007084+ j0.057652

25 25.8 4.18 0.075835+ j0.564695 4.14 0.046292+ j0.588806

Table 3: Summary of Short-Circuit Current Levels – Post-Connection (2017WP)

Substation

Base Voltage

(kV)

Pre- Fault

Voltage (kV)

3-Φ Fault (kA)

Positive Sequence Impedance (R1 + j X1)

(p.u.)

1- Φ Fault (kA)

Zero Sequence Impedance (R0 + j X0)

(p.u.) Jenner 275S 240 262.2 7.20 0.006126+ j0.036075 4.68 0.022650+ j0.092934

Cypress 562S 138 140.7 8.66 0.005319+ j0.049028 8.67 0.004347+ j0.051206

240 263.1 5.73 0.006273+ j0.045663 6.22 0.003863+ j0.036021 Ware Junction 132S 240 260.8 12.32 0.003858+ j0.020893 11.55 0.004074+ j0.024345

Amoco Empress 163S

240 263.0 5.77 0.006163+ j0.045351 5.86 0.005979+ j0.044239 138 140.3 8.63 0.005721+ j0.049086 8.29 0.006893+ j0.057294

Empress 394S 138 140.3 8.50 0.006054+ j0.049800 8.20 0.007084+ j0.057652

25 (T1) 25.9 4.15 0.073849+ j0.573492 4.10 0.047137+ j0.599548 25 (T2) 25.7 4.34 0.033271+ j0.547365 4.33 0.031684+ j0.556120

Page 10: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Substation Upgrade R1

Project No 1679 AESO Functional Specification Page 10 of 16

Table 4: Summary of Short-Circuit Current Levels – Post-Connection (2024WP)

Substation

Base Voltage

(kV)

Pre- Fault

Voltage (kV)

3-Φ Fault (kA)

Positive Sequence Impedance (R1 + j X1)

(p.u.)

1- Φ Fault (kA)

Zero Sequence Impedance (R0 + j X0)

(p.u.) Jenner 275S 240 256.5 7.63 0.005666+ j0.033228 4.78 0.022423+ j0.091251

Cypress 562S

138 142.2 8.80 0.005734+ j0.048668 8.65 0.004744+ j0.053478 240 256.0 6.01 0.005930+ j0.042306 6.39 0.003901+ j0.035727

Ware Junction 132S 240 256.9 14.03 0.003169+ j0.018081 13.46 0.003295+ j0.019642 Amoco Empress

163S 240 256.2 6.05 0.005832+ j0.042064 6.00 0.006020+ j0.043954 138 141.7 8.77 0.006099+ j0.048619 8.29 0.007260+ j0.059318

Empress 394S 138 141.7 8.63 0.006440+ j0.049357 8.19 0.007451+ j0.059735

25 (T1) 25.9 4.22 0.072364+ j0.563181 4.16 0.046690+ j0.591114 25 (T2) 26.0 4.38 0.033610+ j0.546923 4.36 0.032061+ j0.558257

6.2 Voltage Levels Table 5 provides the normal planned operating voltage range in the area of the proposed facility. Table 5: Planned Operating Range

Substation Name and Number

Nominal (kV)

Minimum Limit (kV)

Normal Operating

Minimum (kV)

Normal Operating

Maximum (kV) Maximum Limit (kV)

Empress 394S 138 124 135 145 150

Notes:

1. The Normal Operating Minimum and Normal Operating Maximum are generally associated with Category A events and system normal.

2. The Minimum Limit and Maximum Limit are generally associated with Category B, C, and D events and system abnormal.

3. The new facilities must be capable of continuous operation at voltages up to and including the Maximum Limit.

6.3 Insulation Levels (1) Table 6 provides the required basic insulation levels for the transmission facilities. The station equipment with lower insulation levels may be used provided that protection and coordination can be maintained with judicious insulation design and use of appropriate surge arresting equipment. (2) For 25 kV circuit breakers where there is a grounded wye transformer and surge arrestors are installed a basic insulation level of 125 kV is acceptable.

Page 11: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Substation Upgrade R1

Project No 1679 AESO Functional Specification Page 11 of 16

Table 6: Basic Insulation Levels (kV)

Nominal Voltage Classification (kV rms) 138 25

Station Post Insulators and Airbreaks 550 150

Circuit Breakers 650 150

Current and Potential Transformers 650 150

Transformer Windings (Protected by Surge Arresters) 550 125

Page 12: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Capacity Upgrade R1

Project No. 1679 AESO Functional Specification Page 12 of 16

7 APPENDICES 7.1 Existing Transmission System in the project area Note: This figure is intended to illustrate the electrical interconnection of the area transmission system. It is not to scale, nor does it depict the exact line routes or substation locations.

Page 13: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Capacity Upgrade R1

Project No. 1679 AESO Functional Specification Page 13 of 16

7.2 Single Line Drawing – Empress 394S Substation – Prior to the Proposed Development

Legend

Breaker

Ganged Air-Switch (Motor Operated)

Ganged Air-Switch (Manual Operated) Existing

Transformer

138 kV Bus T1138/24.94 kV15//16.8 MVA

5L128L - 25kV To ATCO

FORTISALBERTA

ALTALINK

This SLD is based on information provided by the legal owner of the transmission facility and illustrated here reflect the changes made at Empress substation 394S after the AltaLink Capaital Maintenance program planned for 2016.

Empress 394S SubstationExisting

1679-394S-SLD-01

Note:

N. O.

ALTALINK

FORTISALBERTA

11113T - 25kV To Empress Gas Plant

426L - 25kV To River

Pump

427L - 25kV

/ircuit Switcher

T2138/25 kV

15/20/25 MVA

VR124.94 kV

28/37.2 MVA

ALTALINK

ALTALINKCUSTOMER

CUSTOMER

T4130/13.8 kV

30/40/50 MVA

T3130/13.8 kV

30/40/50 MVA

25 kV Bus

668L – 138kVTo Cypress 562S

760L – 138kVAMOCO Empress

163S

Page 14: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Capacity Upgrade R1

Project No. 1679 AESO Functional Specification Page 14 of 16

7.3 Single Line Drawing – Empress 394S Substation – Proposed Development

Legend

Breaker

Ganged Air-Switch (Motor Operated)

Ganged Air-Switch (Manual Operated)

Existing

Transformer

138 kV Bus

668L – 138kVTo Cypress 562S

T1138/24.94 kV15//16.8 MVA

760L – 138kVAMOCO Empress

163S

5L128L - 25kV To ATCO

FORTISALBERTA

ALTALINK

Empress 394S SubstationProposed Development

1679-394S-SLD-02

Note:

N. O.

ALTALINK

FORTISALBERTA

11113T - 25kV To Empress Gas Plant

426L - 25kV To River

Pump

/ircuit Switcher

T2138/25 kV

15/20/25 MVA

VR124.94 kV

28/37.2 MVA

ALTALINK

ALTALINKCUSTOMER

CUSTOMER

T4130/13.8 kV

30/40/50 MVA

T3130/13.8 kV

30/40/50 MVA

25 kV Bus 1

troposed 5evelopment

427L - 25kV

N. O.

25 kV Bus 2

VR224.94 kV

This SLD provides an illustration of a functional arrangement that would meet the need of this project. Although the legal owner of the transmission facility is required to maintain the specified functionality, the exact configuration proposed by the legal owner of the transmission facility in its Facility Application may vary slightly based on more detailed engineering, routing and siting information while preparing for the Facility Application.

Page 15: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Capacity Upgrade R1

Project No. 1679 AESO Functional Specification Page 15 of 16

7.4 SCADA Point Requirements

Steven ShiAuthor:

DATA TO AESO

Transmission Facilities502.8 Appendix 4

3

LTC Tap Position (TAP)

Status

MW/Mvar Analogs

Voltage Analog (kV)

Frequency (Hz)

Automatic Voltage Regulation Setpoint

LTC Auto/Manual Status (AVR)

IED Ganged Failure Alarm

RTU Failure Alarm

1

2

3

4

5

6

15

16

8

Items in Green are required *Only if applicable

12 Reactive Power of Reactive Power Resource

13 Reactive Power Resource AVR Status

14 Reactive Power Resource Voltage Setpoint

Legend

Breaker

Ganged Air-Switch (Motor Operated)

Ganged Air-Switch (Manual Operated)

Existing

Transformer

138 kV Bus

668L – 138kVTo Cypress 562S

T1138/24.94 kV15//16.8 MVA

760L – 138kVAMOCO Empress

163S

5L128L - 25kV To ATCO

FORTISALBERTA

ALTALINK

Empress 394S SubstationProposed Development

1679-394S-SLD-02

Note:

N. O.

ALTALINK

FORTISALBERTA

11113T - 25kV To Empress Gas Plant

426L - 25kV To River

Pump

/ircuit Switcher

T2138/25 kV

15/20/25 MVA

VR124.94 kV

28/37.2 MVA

ALTALINK

ALTALINKCUSTOMER

CUSTOMER

T4130/13.8 kV

30/40/50 MVA

T3130/13.8 kV

30/40/50 MVA

25 kV Bus 1

troposed 5evelopment

427L - 25kV

N. O.

25 kV Bus 2

VR224.94 kV

This SLD provides an illustration of a functional arrangement that would meet the need of this project. Although the legal owner of the transmission facility is required to maintain the specified functionality, the exact configuration proposed by the legal owner of the transmission facility in its Facility Application may vary slightly based on more detailed engineering, routing and siting information while preparing for the Facility Application.

16

15

1

Page 16: Fortis Empress 394S Substation Upgrade R1 · Empress 394S substation in accordance with the applicable ISO rules. SCADA Establish or update communication interface points as required

Fortis Empress 394S Capacity Upgrade R1

Project No. 1679 AESO Functional Specification Page 16 of 16

7.5 SCADA Data Requirements

Facility / Location Device Element Indication Update

Rate/Mode Notes

349S Empress

138kV CB CB1 Status On Event 138kV bus tie circuit breaker CB1

(15) Comm

Communications Failure Alarm On Event

Communication failure indication between an intelligent electronic device (IED) and any remote terminal unit acting as a data concentrator, alarms from multiple IED's may be aggregated if desired and sent to the AESO.

(16) Comm RTU Failure Alarm On Event

Communications failure alarm from remote termail unit acting as a data concentrator for one or more generating units to a transmission faciltiy control center (if applicable)

Note 1. MW and MVAr SCADA data shall be gathered independently of the revenue metering data 2. An external GPS based signal shall be utilized to provide 1ms time stamped event accuracy

3. This list was prepared using the best available information. Final Scada point will be determined based on the applicable Scada Standard (502.8)