1 of 5 3C For owners corporations Written notice Project number: Project address: Strata plan number: Occupation certificate issue date: Contact details Business name Contact name Contact phone Email address for service Secretary Secretary Manager of Strata Building Bond and Inspections Scheme (SBBIS) Request if required. Email preferred. [email protected] Developer Builder Owners corporation Building inspector Report type and service 3C-1 Lot number in the strata plan to which notice is being provided 3C-2 Service address of the owner of the lot to which notice is being provided 3C-3 Type of report Interim inspection Final inspection 3C-4 Date report received 3C-5 How can an electronic copy of the report be obtained by the owner of the lot? The owners corporation must give written notice within 14 days of receiving the interim or final report of the building inspector to the owners of lots in the strata scheme when the report has been received and how it can be accessed electronically. Sections 202(2) and 202(3) of the Strata Schemes Management Act 2015

Upload: others

Post on 11-Jun-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Form 3C Written Notice for Owners Corporations Provide

1 of 5

3CFor owners corporations

Written notice

Project number: Project address:

Strata plan number: Occupation certificate issue date:

Contact details

Business name Contact name Contact phone Email address for service

Secretary Secretary

Manager of Strata Building Bond and Inspections Scheme (SBBIS)

Request if required. Email preferred.

[email protected]

Developer

Builder

Owners corporation

Building inspector

Report type and service

3C-1 Lot number in the strata plan to which notice is being provided

3C-2 Service address of the owner of the lot to which notice is being provided

3C-3 Type of report Interim inspection Final inspection

3C-4 Date report received

3C-5 How can an electronic copy of the report be obtained by the owner of the lot?

The owners corporation must give written notice within 14 days of receiving the interim or final report of the building inspector to the owners of lots in the strata scheme when the report has been received and how it can be accessed electronically.

Sections 202(2) and 202(3) of the Strata Schemes Management Act 2015

Page 2: Form 3C Written Notice for Owners Corporations Provide

2 of 5

SignatureMaking a false or misleading statement, giving false or misleading information, or producing false or misleading documents is a serious offence which may render you liable to prosecution for offences including under the Crimes Act which may result in penalties including a fine or imprisonment.

By signing you understand the requirement to provide true and correct information and you are agreeing to our Privacy Statement (https://www.fairtrading.nsw.gov.au/privacy)

Full Name of Individual

Capacity within Company

(if applicable)

Signature

Date

Page 3: Form 3C Written Notice for Owners Corporations Provide

3 of 5

For owners corporations 3CFact sheet

Strata building bond and inspections scheme (SBBIS) - process stages

OR

What do I do next?Form 3C satisfies the requirement to provide written notice when provided to every owner of a lot in the strata plan. This needs to be done within 14 days of receiving the report from the building Inspector. An electronic copy of the report must be available to the owners of the lots, if requested.

You are

here

STAGE 8Completingthe process

STAGE 1Building bondlodgement

STAGE 3Interim inspectionand report

STAGE 4Rectify defectivebuilding work

STAGE 5Final inspectionand report

STAGE 6Determine costof rectification

STAGE 7Paying thebuilding bond

STAGE 2Inspector appointment

Between 15–18 months of completion of building work: Interim inspection conducted & interim report provided

Between 18–21 months of completion of building work: Indicative period for builder to rectify defective building work

Between 21–24 months of completion of building work: Final inspection conducted and final report provided

After 24 months, but before 2 years & 90 days of completion of building work: Parties determine the cost to rectify the defective building work

After 2 years from completion of building work or within 90 days of final report (whichever is later) Secretary makes payment of amount secured by building bond

Within 3 years of completion of building work: Process must be completed

Within 12 months of completion of building work: Developer to appoint Building Inspector

Lodge bond for Secretary approval before application for OC

Bond = 2% of contract price

You are

here

STAGE 8Completingthe process

STAGE 1Building bondlodgement

STAGE 3Interim inspectionand report

STAGE 4Rectify defectivebuilding work

STAGE 5Final inspectionand report

STAGE 6Determine costof rectification

STAGE 7Paying thebuilding bond

STAGE 2Inspector appointment

Between 15–18 months of completion of building work: Interim inspection conducted & interim report provided

Between 18–21 months of completion of building work: Indicative period for builder to rectify defective building work

Between 21–24 months of completion of building work: Final inspection conducted and final report provided

After 24 months, but before 2 years & 90 days of completion of building work: Parties determine the cost to rectify the defective building work

After 2 years from completion of building work or within 90 days of final report (whichever is later) Secretary makes payment of amount secured by building bond

Within 3 years of completion of building work: Process must be completed

Within 12 months of completion of building work: Developer to appoint Building Inspector

Lodge bond for Secretary approval before application for OC

Bond = 2% of contract price

Page 4: Form 3C Written Notice for Owners Corporations Provide

4 of 5

See the illustrated process below.

Stage 3 - Interim inspection and report

Buildinginspector

Developer

Ownerscorporation

3E

3E

3E

14 days notice beforeentering strata scheme

Interim inspectionconducted 15-18 months

Developer canapply to

Secretary - nofinal inspection

required

Interim report prepared &provided 15-18 months

No defectsin report

Approved - stage 7Not Appoved - stage 4

Owners corpnotifies owners -

interim reportavailable

Form 3C

Secretary’s decision

3A

3A

3A

3B

3B

3B

3B

3B 3D

3D

Ownerof lot

3C

Builder

Secretary

5A

5A

5B

5B

Within 18 monthsof OC date

Dev re-appiontsbuilding insp

Building inspectornot available

14 days notice beforeentering strata scheme

Final inspection21-24 months

Final report prepared & provided 21-24 months

Notifies ownersreport available

Stage 5 - Final inspection and report

Buildinginspector

Developer

Ownerscorporation

Ownerof lot

Builder

3C

Form 3C

Secretary arrangesbuilding inspector

Developer notifies Secretary& Secretary to arrange

building inspector

5C

5C

5C

Secretary

3B

3B

3B

3B

3B

3A

3A

3A

OR

Page 5: Form 3C Written Notice for Owners Corporations Provide

5 of 5

Need further information? Please refer to the Strata Building Bond and Inspections Scheme webpage on Fair Trading’s website.

Privacy and Security of InformationProviding documents to developer/owners corporation/builder/building inspector/other

Provide the document in PDF format. This minimises the recipient’s ability to change the document.

Submitting documents to the Secretary

Supply the document in PDF format.

This form and the information provided remains the property of the NSW Government.

All parties have the requirement to provide true and correct information.

The Fair Trading Terms & Conditions and Privacy Statement can be accessed at https://www.fairtrading.nsw.gov.au/privacy

AnnexureDefinition: Section 202(2) of the Strata Schemes Management Act 2015:

“An owners corporation must give written notice to the owners of lots in the strata scheme of the receipt of an interim report or a final report on building work in connection with the scheme not later than 14 days after receiving the report.”

Definition: Clause 49 of the Strata Schemes Management Regulation 2016:

“A notice to owners of the receipt of an interim or final report by a building inspector must contain the following particulars:

(a) Whether the report is an interim or final report,

(b) How to obtain an electronic copy of the report.”