form 1 aenvironmentclearance.nic.in/writereaddata/online/...from the project site while, new delhi...

69
“Human Care Medical Charitable Trust” Hospital project Sector-6, Dwarka, New Delhi FORM 1 A M/s Human Care Medical Charitable Trust 1 FORM 1 A CHECK LIST OF ENVIRONMENTAL IMPACTS SECTION 1- LAND ENVIRONMENT 1.1 Will the existing land use get significantly altered from the project that is consistent with the surroundings? (Proposed land use must conform to the approved Master Plan/Development Plan of the area. Change of land use, if any and the statutory approval from the competent authority are submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans. The Project site is proposed for hospital as per as per File No-F11(19) 93/1L of DDA in the lease deed. It is anticipated that the construction activities of the project was and will not have an adverse effect on the land use activities in the project area. The development of green avenue and other landscaping will enhance the visual aesthetics of the area.The project site has a good connectivity to Sector Road 201 which is adjacent to project site. Palam Railway Station is approx. 2.46 km (SE) from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro station is 2 km (SW) from the project site. Indira Gandhi International Airport is approx. 3.30 km (SSE) from the project site. The Latitude and Longitude of the project is 28°35'42.22"N, 77°04'09.01"E. 1.2 List out all the major project requirements in terms of the land area, built up area, water consumption, power requirement, connectivity, community facilities, parking needs etc. LAND REQUIREMENT The total plot area of the project site is approx. 9,545 m 2 . The detailed Area Statement of the project is provided below in Table-1 & 2.

Upload: others

Post on 08-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 1

FORM 1 A CHECK LIST OF ENVIRONMENTAL IMPACTS

SECTION 1- LAND ENVIRONMENT

1.1 Will the existing land use get significantly altered from the project that is consistent with

the surroundings? (Proposed land use must conform to the approved Master

Plan/Development Plan of the area. Change of land use, if any and the statutory approval from

the competent authority are submitted). Attach Maps of (i) site location, (ii) surrounding

features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours)

to appropriate scales. If not available attach only conceptual plans.

The Project site is proposed for hospital as per as per File No-F11(19) 93/1L of DDA in the lease

deed. It is anticipated that the construction activities of the project was and will not have an adverse

effect on the land use activities in the project area. The development of green avenue and other

landscaping will enhance the visual aesthetics of the area.The project site has a good connectivity to

Sector Road 201 which is adjacent to project site. Palam Railway Station is approx. 2.46 km (SE)

from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project

site. Dwarka Sec-11 Metro station is 2 km (SW) from the project site. Indira Gandhi International

Airport is approx. 3.30 km (SSE) from the project site.

The Latitude and Longitude of the project is 28°35'42.22"N, 77°04'09.01"E.

1.2 List out all the major project requirements in terms of the land area, built up area,

water consumption, power requirement, connectivity, community facilities, parking needs etc.

LAND REQUIREMENT

The total plot area of the project site is approx. 9,545 m2. The detailed Area Statement of the project

is provided below in Table-1 & 2.

Page 2: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 2

Table-1: Area Detail

Table:2 Built Up Area Detail

Total Built up Area =Total FAR+ Non FAR=30398.294+16555.667=46953.96

Sl

No. Particulars Area (in Sq.m)

1. Total Plot Area 9545 ( or 2.358 acres)

2. Permissible Ground Coverage 4293.12

3. Proposed Ground Coverage 3869.57

4. Permissible FAR 35,793.75

5. Proposed FAR (A) 30,398.29

6 Total Basement Area (B)

3 Nos. (Level 1, 2 & 3)

16,555.67

7 Proposed Green Area (@ 26.08% of plot area) 2488.33

8 Built-up Area (A+B) 46953.96

9 Height of tallest building (till terrace) 36.9 m

S.No Floors Constructed area asper

earlier sanction Total BUA

**Consolidated area for

Tower-I & Tower-II

1 Ground 2799.02 3471.353

2 First 2667.22 3094.955

3 Second 2762.73 3094.955

4 Third 2762.73 3094.955

5 Fourth 1438.33 3166.939

6 Fifth 1438.33 3166.939

7 Sixth 1438.33 2992.507

8 Seventh 1438.33 2920.451

9 Eight 1438.33 2920.451

10 Ninth 2474.789

Total FAR (A) 18183.35 30398.294

Atrium Area 398.219

Ist Basement 4698.94 5814.567

IInd Basement 3528.7 5077.939

IIIrd Basement 3528.7 5264.942

Non FAR (B) 11756.34 16555.667

Page 3: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 3

WATER REQUIREMENT

The total water requirement for the project will be approx. 445KLD. The water supply will be

provided through the Delhi Jal Board (DJB). The fresh water requirement will be 276 KLD.

Expected wastewater from bed will be treated in modular ETP and Discharge to STP for further

treatment. It is expected that domestic wastewater from the project will be approx. 188 KLD. The

wastewater will be treated in the ETP and STP having total capacity of 350 KLD generating 169

KLD of recoverable water from STP which will be used for HVAC Cooling.

Daily water requirement calculation and water balance diagram in detail are given below

Zero

Discharge

to sewer

sewer

Page 4: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 4

Solid Waste

Construction

Waste

Construction waste, Broken Bricks,

Waste Plaster

Empty Cement

Bags

Used in re-filling,

raising site level Sold to

agency for

recycling

Excavated Soil

Top soil conserved for

landscaping

POWER REQUIREMENT

The total demand power load requirement for the project will be 3,153.7 kVA which will be

provided by BSES Rajdhani Power Limited. To cater electricity supply during power failure, 3 Nos.

(2*1250 kVA & 1*750 kVA) of DG sets will be installed within the project site. It is envisaged that

operation of DG sets shall be for 6 hours/day. DG sets will be used during power failure only which

will be based on ultra low sulphur diesel (ULSD) fuel. The proposed DG sets will be equipped with

acoustic enclosure to minimize noise generation and adequate stack height for proper dispersion

SOLID WASTE GENERATED

Solid waste generated & expected to generate both during the construction as well as during the

operation phase. The solid waste expected to be generated during the construction phase will

comprise of excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The

following steps are proposed to be followed for the management solid waste:

Construction yards are proposed for storage of construction materials.

Remaining soil shall be utilized for refilling / road work / rising of site level at locations/

selling to outside agency for construction of roads etc.

Page 5: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 5

Solid Waste Management Scheme (Construction Phase)

Arrangements will be made at the site in accordance to Municipal Solid Wastes (Management and

Handling) Rules, 2000 & amended Rules, 2008 and Bio-Medical Waste (Management and

Handling) Rules, 1998.

PARKING FACILITIES

Adequate provision will be kept for car/vehicles parking of the project. The total parking provided

will be 611ECS. Parking Calculation are given below:

As per MoEF Norms:

For Medical Facilities = 190 ECS

As per DDA Norms:

For Public/Semi-Public facilities = 608 ECS

Parking Proposed:

Total Parking proposed = 611 ECS

1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to

the proposed site? (Such as open spaces, community facilities, details of the existing land use

and disturbance to the local ecology).

The project will be a well planned activity will result in organized open spaces and green areas.

About 2,488.33 m2 of the area is earmarked for landscaping. The project will have an overall positive

impact on the existing land use and will not cause any disturbance to the local ecology. Proposed

activity shall have no impact on surroundings rather contribute to the better standards and well being

of the people.

1.4 Will there be any significant land disturbance resulting in erosion, subsidence &

instability? (Detail of soil type slope analysis, vulnerability to subsidence, seismicity etc may be

given).

Page 6: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 6

There shall be no land disturbance resulting in erosion, subsidence and instability as it is a flat land.

The site falls under the zone IV as per the seismic zone map of India and indicating high damage

risk zone. The proposed project will be earthquake resistant taking into account the latest provisions

of Indian Standards Codes. Soil quality data is shown in the table below:

Soil Quality results

Human Care Medical Trust Hospital Project Sec-6 Dwarka New Delhi

Soil Quality Data (Dec-2014)

project site

1 Texture - Sandy Loam

Sand % 59.2

Silt % 22.1

clay % 18.7

2 pH (1:2) - 7.64

3 Electrical Conductivity (1:2) µmhos/cm 414

4 Cation exchange capacity meq/100 gm 14.4

5 Exchangeable Potassium mg/kg 92

6 Exchangeable Sodium mg/kg 136

7 Exchangeable Calcium mg/kg 2092

8 Exchangeable Magnesium mg/kg 378

9 Sodium Absorption Ratio - 0.72

10 Water Holding Capacity % 25.6

11 Porosity % 37.9

1.5 Will the proposal involve alteration of natural drainage system? (Give details on a

contour map showing the natural drainage near the proposed project site).

No perennial or non-perennial drainage system is found to exist in the project area obstructed by the

project. The surroundings comprise an urbanized stretch and well planned storm water drainage

system will be designed for internal storm water drainage. Thus, no impact on the natural drainage

system is anticipated.

Page 7: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 7

1.6 What are the quantities of earthwork involved in the construction activity-cutting,

filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill

materials from outside the site etc?)

The earthwork has include soil excavation and cutting 72708.516 m3 of the earth has been moved.

The cut and fill material in the project site is nearly at par and hence the need for movement of soil to

and from the proposed site is not anticipated.

1.7 Give details regarding water supply, waste handling etc during the construction

period.

Water requirement has been provided through Tanker. Wastewater generated during the construction

waste has been 3.6 KLD and waste water will be disposed off through soak pits. Waste handling

during the construction phase has done and will be done by the site contractor whose responsibility

lies with collection and storage of construction and demolition waste generated on the site. All

construction wastes generated during construction was used within the site itself for filling the

floors, roads, aggregate for mortar etc. to the extent feasible. Remaining will be sent to the agency

for proper disposal.

Page 8: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 8

Solid Waste

Construction

Waste

Construction waste,

Broken Bricks,

Waste Plaster

Empty Cement

Bags

Used in re-filling,

raising site level

Sold to agency for

recycling

Excavated Soil

Top soil conserved

for landscaping,

Solid Waste Management during Construction Phase

1.8 Will the low lying areas & wetlands get altered? (Provide details of how low lying and

wetlands are getting modified from the proposed activity).

No. The site area is a flat land and the surroundings are characterized by an urbanized stretch. No

low lying areas or wetlands are found in the region.

1.9 Whether construction debris & waste during construction cause health hazard? (Give

quantities of various types of wastes generated during construction including the construction

labor and the means of disposal).

No health hazards are expected during the construction phase. The laborers has been provided with

face masks to minimize dust inhalation.

A significant portion of the construction waste and wood scrap generated has been used on the site.

Page 9: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 9

The quantity of domestic waste generated has been very little, as mostly local laborers has been

employed. However, the wastes generated has been collected and disposed by an authorized agency.

SECTION 2- WATER ENVIRONMENT

2.1 Give the total quantity of water requirement for the proposed project with the

breakup of requirements for various uses. How will the water requirement be met? State the

sources & quantities and furnish a water balance statement.

Calculations for Total Daily Water Demand

The total water requirement for the project will be approx. 445KLD. The water supply will be

provided through the Delhi Jal Board (DJB). The fresh water requirement will be 276 KLD.

Calculation for the project is given below:

Water Requirement:

As per National Building Code 2005 following is the daily water requirement.

Hospital beds : 450 Litres/bed/day

Visitors : 15 Litres/head/day

Staff an attendants : 45 Litres/head/day

C) Daily water requirement:

No. of Beds, 380@450 Litre/bed/day : 1,71,000 Liters/day

Visitors 1250 @ 15 Litres/head/day : 18,750 Litres/day

Staff and attendants 1000

@ 45 Litres/head/day : 45,000 Litres/day

Total Domestic Water Required 2,34,750 Liters/day

Air conditioning makeup water 1350 tonne @ 12 Litres/tonne

for 12 hours per day : 1,94,400 Liters/day

Page 10: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

10

Horticultural Water 2488.33 m2 @ 5 Litres/sqm =

12441.65 Liters/day Say 15000 Liters/day : 15,000 Liters/day

:

Total water requirement 4,44,150 Liters/day

Say : 4,45,000 Liters/day

D) Sources of water: Two sources of water are considered as under:

1) City Supply from Govt./Local Authority.

2) Recirculation of treated sewerage effluent after treatment for HVAC cooling.

1) City supply will be supplying water to the complex when it is available from the local

authorities considering 100% demand availability of domestic demand.

2) Recirculation of Sewerage + Effluent : 80% of water supply will flow as Sewerage +

Effluent..

Total Sewerage Generation = 0.80 x 235 KL = 188 KL

Proposed STP Capacity =300 KL

Treated sewage : 90% of 188 KL : 0.90 x 188 = 169.2 KL

Flushing Water Requirement:

No. of Beds : 380 x 100 Litre/bed/day : 38,000 Litres/day

Visitors : 1250 x 7.5 Litres/head/day : 9,375 Litres/day

Staff and attendants : 1000 x 15 Litres/head/day : 15,000 Litres/day

Total : 62,375 Liters/day

Say : 63,000 Liters/day

Air conditioning : 1,94,400 Liters/day

Horticultural Water 2488.33 m2 @ 5 Litres/sqm =

12441.65 Liters/day Say 15000 Liters/day : 15,000 Liters/day

: 2,72,400 Litres/day

Total fresh daily water required : 445 KL – 169.2 KL : 275.8 KL

Page 11: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

11

Water Balance Diagram

Waste Water Generation & Treatment

During operation phase, It is expected that the project will generate approx. 188 KLD of

wastewater including treated effluent comes from ETP. The wastewater will be treated in the ETP

& STP having total capacity of 350 KLD provided within the premises generating 169 KLD of

recoverable water which will be used for HVAC Cooling.

Page 12: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

12

2.2 What is the quality of water required, in case, the supply is not from a municipal

source? (Provide physical, chemical, Biological characteristics with class of water quality).

The agency for supply of water will be DJB. The quality of water confirm to the desirable drinking

water standards as per IS 10500 and Manual on Water Supply and Treatment by the Central Public

Health and Environmental Engineering Organization (CPHEEO).

2.3 How much of water requirement can be met from the recycling of treated wastewater?

(Give the details of quantities, sources and usage)

The total treated wastewater generated will be approx. 188 KLD. The treated recovered water will be

169 KLD which will used for HVAC cooling.

2.4 Will there be diversion of water from other users? (Please assess the impacts of the

project on other existing uses and quantities of consumption).

No. There will not be any diversion of water from other users. Rise in water demand is a local

phenomenon but the project will only involve spatial shifting of water demand within a region.

2.5 What is the incremental pollution load from wastewater generated from the proposed

activity? (Give details of the quantities and composition of wastewater generated from the

proposed activity)

Approximately 188 KLD of a wastewater will be generated during the operational phase. This

wastewater generated will be treated in well-designed ETP and Sewage Treatment Plant having

capacity of 350 KLD and will be recycled as mentioned in the water balance diagram above within

the project premises.

2.6 Give details of the water requirements met from water harvesting? Furnish details of

the facilities created.

Page 13: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

13

The storm water disposal system for the premises shall be self-sufficient to avoid any

collection/stagnation and flooding of water. The amount of storm water run-off depends upon

many factors such as intensity and duration of precipitation, characteristics of the tributary area

and the time required for such flow to reach the drains. The drains shall be located near the

carriage way along either side of the roads. Taking the advantage of road camber, the rainfall run

off from roads shall flow towards the drains. Storm water from various buildings shall be

connected to adjacent drain by a pipe through catch basins. Therefore, it has been calculated to

provide 3 rainwater harvesting pits at selected locations, which will catch the maximum run-off

from the area.

1) Since the existing topography is congenial to surface disposal, a network of storm water

pipe drains is planned adjacent to roads. All building roof water will be brought down

through rain water pipes.

2) Proposed storm water system consists of pipe drain, catch basins and seepage pits at

regular intervals for rain water harvesting and ground water recharging.

3) The peak hourly rainfall of 35 mm/hr shall be considered for designing the storm water

drainage system.

Rain water harvesting has been catered to and designed as per the guideline of CGWA. Peak

hourly rainfall has been considered as 35 mm/hr. The diameter & depth of recharge pit will be 6

m x 3 m x 2.5 m will be constructed for recharging the water. Inside the recharge pit, a recharge

bore will be constructed having adequate diameter depth. At the bottom of the recharge well, a

filter media is provided to avoid choking of the recharge bore. Design specifications of the rain

water harvesting plan are as follows:

Catchments/roofs would be accessible for regular cleaning.

The roof will have smooth, hard and dense surface which is less likely to be damaged

allowing release of material into the water. Roof painting has been avoided since most

paints contain toxic substances and may peel off.

All gutter ends will be fitted with a wire mesh screen and a first flush device would be

installed. Most of the debris carried by the water from the rooftop like leaves, plastic bags

and paper pieces will get arrested by the mesh at the terrace outlet and to prevent

Page 14: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

14

contamination by ensuring that the runoff from the first 10-20 minutes of rainfall is

flushed off.

No sewage or wastewater would be admitted into the system.

No wastewater from areas likely to have oil, grease, or other pollutants has been

connected to the system.

Calculations for storm water load

Roof-top area = Ground Coverage = 3869.57 m2 Green Area = 2,488.33 m

2

Total plot area = 9,545 m2

Paved Area = Total Plot Area – (Roof-top Area + Green Area)

= 9,545 – (3869.57 + 2488.33)

= 3187.1m2

Runoff Load

Roof-top Area = 3869.57 × 0.035 × 0.8

= 108.34 m3/hr

Green Area = 2488.33 × 0.035 × 0.1

= 8.71 m3/hr

Paved Area = 3187.1× 0.035 × 0.75

= 83.66m3/hr

Total Runoff Load = 108.34 + 8.71 + 83.66 m3/hr

= 200.71 say 201 m3/hr

Taking 15 minutes Retention Time, Total volume of storm water = 201/4

= 50.25 m3

Taking the effective size of a Rain Water Harvesting pit = l x b x h = 6 x 3 x 2.5 = 45 m3. Hence

Rain Water Harvesting pit required = 50.25/45 = 1.12 say 1 pit

3 Nos Rain Water Harvesting pits have been proposed for artificial rain water recharge within

the project premises.

Page 15: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

15

2.7 What would be the impact of the land use changes occurring due to the proposed

project on the runoff characteristics (quantitative as well as qualitative) of the area in the post

construction phase on a long term basis? Would it aggravate the problems of flooding or water

logging in any way?

The project will include paved areas and thus the runoff from the project is expected to increase due

to reduced infiltration. However, the increased runoff will not cause flooding or water logging as a

Page 16: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

16

well designed storm water drainage will be provided. The runoff will finally be collected into

rainwater harvesting pits for groundwater recharging. The quality of the runoff is expected to

improve due to paved areas.

2.8 What are the impacts of the proposal on the ground water? (will there be tapping of

ground water; give the details of ground water table, recharging capacity and approvals

obtained from competent authority, if any) .

Water demand will be fulfilled by Delhi Jal Board (DJB). Hence, no adverse impact is expected,

and efforts will be made to recharge the aquifers using 3 rain water harvesting pit of 6m x 3m x2.5m

dimension proposed in the project. Ground water level is 30 m below ground level.

2.9 What precautions measures have been proposed to check the surface run-off, as well

as uncontrolled flow of water into any water body?

Adequate management measures are suggested to protect the water quality during construction

phase. Excavation during monsoon season has been avoided. Care has been taken to avoid soil

erosion. Community toilets have been constructed on the site during construction phase and the

wastewater has been channelized to the septic tank in order to prevent wastewater from entering the

water bodies. Any area with loose debris within the site shall be planted.

To prevent surface and ground water contamination by oil/grease, leak proof containers has been

used for storage and transportation of oil/grease. The floors of oil/grease handling area has been kept

effectively impervious. Collection and settling of storm water, prohibition of equipment wash

downs, and prevention of soil loss and toxic release from the construction site has been adhered to

minimize water pollution.

2.10 How is the storm water from within the site managed? (State the provisions made to avoid

flooding of the area, details of the drainage facilities provided along with a site layout

indication contour levels).

Most of the storm water produced on site will be harvested for ground water recharge. Thus proper

management of this resource is must to ensure that it is free of contamination. A detailed Storm

Page 17: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

17

Water Management Plan will be developed which will consider the sources of storm water. The plan

will incorporate best management practices which will include the following:

Regular inspection and cleaning of storm drains.

Installation of clarifiers or Oil/Water separators system of adequate capacity around

parking areas and garages as per requirement.

Cover waste storage areas.

Avoid application of pesticides and herbicides before wet season.

Conducting routine inspections to ensure cleanliness.

Preparation of spill response plans, particularly for fuel and oil storage areas.

Provision of silt traps in storm water drains.

Good housekeeping in the above areas.

2.11 Will the deployment of construction laborers particularly in the peak period lead to

unsanitary conditions around the project site (Justify with proper explanation).

No, mostly local laborers have been employed during the construction phase and thus a negligible

quantity of waste has been generated. Mobile Common toilet has been provided within the premises.

2.12 What on-site facilities are provided for the collection, treatment & safe disposal of

sewage? (Give details of the quantities of wastewater generation, treatment capacities with

technology & facilities for recycling and disposal).

Approximately 188 KLD of a wastewater will be generated during the operational phase. This

wastewater generated will be treated in well-designed ETP and Sewage Treatment Plant having

capacity of 350 KLD and will be recycled as mentioned in the water balance diagram above within

the project premises.

An external sewage network will collect the sewage from all units, and flow by gravity to the

proposed sewage treatment plant.

Following are the benefits of providing the Sewage Treatment Plant in the present circumstances:

Page 18: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

18

Reduced net daily water requirements, source for Horticultural purposes by utilization of

the treated wastewater.

Reduced dependence on the public utilities for water supply and sewerage systems.

Sludge generated from the Sewage Treatment Plant will be rich in organic content and an

excellent fertilizer for horticultural purposes.

Final discharge characteristics

(a) pH : 6.5 to 7.5

(b) Oil & Grease : < 10 mg/l

(c) B.O.D. : < 20 mg/l

(d) C.O.D. : < 30 mg/l

(e) Total suspended solids : <10mg/l

SBR TECHNOLOGY

Hospital generally has operation theatre, laboratories, etc., from which wastewater with chemicals

/ blood will generate. If this waste water is directly mixed with the domestic sewage, it interferes

with the sewage treatment process. It is therefore necessary to pre treat this effluent before

discharge into sewage equalization tank. Sludge from this ETP is not suitable for using as a

manure. Therefore it is disposed off separately.

Sewer System

The alignment and slope of the sewer line will follow the road network, drains or natural ground

surface and will be connected to the trunk sewers. The discharge point will be a treatment plant, a

pumping station, a water course or an intercepting sewer. Pumping stations would be provided at

places where the natural slope of the terrain is insufficient to permit gravity flow or the cost of

excavation is uneconomical to do the same.

Page 19: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

19

Schematic Diagram of STP

2.13 Give details of dual plumbing system if treated waste used for flushing of toilets or any

other use.

Dual plumbing system that utilizes separate piping systems for freshwater and recycled wastewater

will be adopted for the proposed project. The recycled water system shall utilize this treated

wastewater and serve 169 KLD for HVAC cooling.

SECTION 3-VEGETATION

3.1 Is there any threat of the project to the biodiversity? (Give a description of the local

ecosystem with its unique features, if any).

Page 20: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

20

No, there will not be any threat of the project to the biodiversity. All the parks/forests etc are far

away from the site i.e Pusa Hill Forest- approx. 7.49 km. in ENE direction, Aravali Biodiversity

Park- approx. 8.59 km. in East direction, & Mitraon Forest- approx. 12.36 km. in SE direction.

3.2 Will the construction involve extensive clearing or modification of vegetation? (Provide

a detailed account of the trees & vegetation affected by the project).

No. The site comprises of 2488.33 m2 landscape of open land area provided and does not support

any ecologically threatened vegetation.

3.3 What are the measures proposed to be taken to minimize the likely impacts on

important site – features (Give details of proposal for tree plantation, landscaping creation of

water bodies etc along with a layout plan to an appropriate scale?)

Green belt will be developed along the periphery of the project premises. 2,488.33m2 of open area

will be developed as green belt and organized green spaces. Landscape plan has been attached.

SECTION 4-FAUNA

4.1 Is there likely to be any displacement of fauna both terrestrial and aquatic or creation

of barriers for their movement? Provide the details.

No. The existing land use around the proposed site is urban and does not provide a habitat for wild

species. A few species of butterfly, avifauna and reptiles were recorded during the course of survey,

which are common and found abundantly in this region. The proposed multilayered peripheral

greenbelt will provide an excellent habitat for the native fauna.

4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.

Page 21: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

21

The project will not have any direct or indirect impacts on the avifauna of the area. However,

planting of trees in the proposed greenbelt will be an attraction to the local bird population which

will provide shelter and niche for the birds

4.3 Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on

fauna.

Not applicable

SECTION 5-AIR ENVIRONMENT

5.1 Will the project increase atmospheric concentration of gases & result in heat islands?

(Give details of background air quality levels with predicted values based on dispersion models

taking into account the increased traffic generation as a result of the proposed construction).

Negligible amount of pollutants will be emitted due to the increase in vehicles from the project and

from the DG sets. Since proponent is going to develop sufficient green belts, it will help

significantly to control air pollution.

The site will not lead to any heat islands, since the proponent will develop greenbelts and green

covers in the site. Air monitoring carried out during the environmental assessment is shown in the

table below:

Ambient Air Quality results

Human Care Medical trust Hospital Project sec-6 Dwarka New Delhi

Ambient Air Quality Data Location: AQ1(Project site)

S.No Date PM2.5,µg/m3 PM10,µg/m3 SO2 µg/m3 , NO2,µg/m3 CO, µg/m3

Gravimetric IS:5182:Pt-23 IS:5182:Pt-2 IS:5182:Pt-6 IS:5182:Pt-10

1 02.12.2014 94.6 165.4 10.1 34.2 1830

2 04.12.2014 111.2 171.2 12.1 35.4 2070

3 09.12.2014 100.7 190.2 11.2 30.7 1790

4 12.12.2014 98.9 236.5 13.4 37.1 2010

5 15.12.2014 111.4 225.5 9.9 41.0 1940

6 20.12.2014 104.6 194.1 9.6 31.6 1820

7 24.12.2014 115.9 202.5 9.7 32.2 1990

Page 22: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

22

8 28.12.2014 127.5 187.5 10.9 34.3 2220

Min 94.6 165.4 9.6 30.7 1790

Max 127.5 236.5 13.4 41.0 2220

Average 108.1 196.6 10.9 34.6 1959

98 Percentile 125.9 235.0 13.2 40.5 2199

NAAQS (For 24 hrly

monitoring except CO)CO

For one Hr

60 100 80 80 4000

Fugitive dust in the main pollutant envisaged from different construction activity that shall be

prevented by water spraying & screening the construction activity with the help of tarpaulin. The

other important source of pollution is D.G sets which will be used at the tune of power failure & the

emission like PM10, NOx, SO2, CO will be well within the prescribed limits. The total ground level

concentrations have been assessed with predicted incremental values based on dispersion model

tanking into the account of increased traffic load, which are within the prescribed limit.

5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous

gases? Give details in relation to all the meteorological parameters.

Prediction of Impacts

Vehicular emissions and DG sets emission will be major sources of air pollution from building

construction projects. During the post construction phase, cars, scooter/motorcycle will be owned

by the population of such project. Ground Level Concentration of pollutants (as added by the

project) will depend upon the following:

Emission of pollutants from additional traffic on the roads due to the project.

Meteorological conditions.

Emission sources from D.G. Sets.

PM, NO2, SO2 and CO will be the main pollutants of primary concern released from traffic

movement and DG sets. Assuming that under cross wind condition perpendicular to the road, the

dispersion of vehicular emissions would be confined within limited distance from the road and

concentration will decrease with the increase in distance from road. It was anticipated that the

contribution of vehicular emissions from the exhaust in ambient air quality will be marginal as

Page 23: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

23

Pollution under Control (PUC) Certified vehicles and branded make operated vehicle with low

sulphur diesel will be used. Ground Level Concentration (GLC) of pollutants is found to be well

within the stipulated National Ambient Air Quality Standards due to traffic movement and

vehicles used inside the premises. DG sets will be main source of Air Pollution in the project.

CPCB/ MoEF approved USEPA dispersion model -ISCST3 was used for prediction of impacts

caused by DG sets. Stack & emission data was used as per design value provided by standard

make and stipulated standards. Other primary data used as input for model were hourly

meteorological data of Wind speed & direction, temperature, cloud amount and mixing height.

Mixing height used in the model was taken from secondary data source “Atlas of Hourly Mixing

Height Assimilative Capacity of Atmosphere in India published in 2008 by IMD, Delhi”. Hourly

meteorological monitored at site during study period data was compared with long term data

available from the nearest India Meteorological station or any other authorized source/Govt.

agencies.

There was provision of 3no. of DG sets of total capacity 3,250 KVA (2X 1250 ,1X750)for power

back up in the Existing phase of residential plotted colony.

This will cause emission of PM, SO2, NO2 and CO in the Ambient Air Quality. Therefore,

incremental load in the ambient air environment will be found to be very low as given in the

report. An adequate stack height of D.G. sets will be provided as per the stipulated guidelines of

Central Pollution Control Board (CPCB)/ National Building Code Manual to facilitate proper

dispersion of pollutants and to minimize the impact on Ambient Air Quality under the influence

of local meteorology.

Meteorology - Hourly Meteorological data of wind speed & direction, temperature, cloud amount

and rainfall were monitored at site for 1month for the dispersion model. Wind rose was prepared

in sixteen directions as per standards. It was observed that westerly were prevalent wind during

the study period.

Page 24: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

24

WRPLOT View - Lakes Environmental Software

PROJECT NO.:

Human care

DATE:

1/13/2015

MODELER:

COMPANY NAME:

COMMENTS:WIND ROSE PLOT:

Human care

NORTH

SOUTH

WEST EAST

7%

14%

21%

28%

35%DATA PERIOD:

Start Date: 12/1/2014 - 00:00End Date: 12/31/2014 - 23:00

WIND SPEED

(m/s)

>= 11.1

8.8 - 11.1

5.7 - 8.8

3.6 - 5.7

2.1 - 3.6

0.5 - 2.1

Calms: 0.00%

AVG. WIND SPEED:

2.60 m/s

CALM WINDS:

0.00%

TOTAL COUNT:

744 hrs.

DISPLAY:

Wind SpeedDirection (blowing from)

Wind rose diagram

Model details and Frame work of Computation:

The predictions for air quality during operation phase were carried using CPCB/MoEF approved

“USEPA, Industrial Source Complex (Version - ISCST3)” Dispersion model developed by the

US Environmental Protection Agency (USEPA) for prediction of pollutants dispersion from

single or multiple point sources using emission and hourly meteorological data of the study

period. Assumptions used in the model were as follows:

The plume rise is limited to that of the mixing layer as published by IMD in the

Catalogue of Atlas of Mixing Heights in India for the site

Stack down-wash is not considered.

Flat terrain is used for computations;

It is assumed that the pollutants do not undergo any physico-chemical transformation.

Chemical and scavenging process occurred in the atmosphere in the pollutants released at

the stack exit is not considered.

Page 25: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

25

Prediction is based on single/multiple point sources, pollution released at stack exit and

dispersed on the ground under influence of local meteorological conditions during the

season.

ISCST3 dispersion model was used to predict GLC caused by a different point source ( 42.9as

highest stacks) at each receptor of 41 m x 41 m of grid network covering total area of 2000 m x

2000m around the proposed source with stack & emission values and 1-hourly meteorological

data. It was observed that SO2, NO2, Co and PM were significant pollutants released from the

fuel of the D.G. sets. Emission of PM, CO and SO2 were found insignificant with low values

compared to NO2. In this project, NO2 was the worst pollutant released into the atmosphere

(Table 8) with high emission value.

Stack and Emission Details

Note:-DG set will be operated during power failure for maximum 6-Hours.

24-h GLC were predicted for SO2, NO2, CO and PM but isopleth of the worst pollutant NO2 is

only presented in the report as GLC of other pollutants were low under similar meteorological

conditions.

Discussion of Results

ISCST3 - Dispersion model was used to predict GLC of all pollutants; SO2, NO2, CO and PM

with stack & emission and hourly meteorological data. 24-hours average maximum Incremental

GLC of NO2 was to be 2.95 µg/m3 occurred at (-600m, 600m) from the DG sets fitted with

chimneys of various height and. It was found that GLC of NO2 was less than the permissible limit

of 80µg/m3

(as per CPCB guidelines) under worst meteorological condition with meteorological

data monitored on site.

Stac

k

No.

DG set

Capacity

(kVA)

Stack & Flue details Pollutants Emission

Heig

ht

(m)

velocit

y

(m/s)

Temp

(C)

Diamete

r (m)

NO2

(g/s)

SO2

(g/s)

PM

(g/s)

CO

(g/s)

1. 2 x 1250

KVA

41

25

809.0 0.48 0.5 0.09 0.03 0.06

2. 1X750

KVA

41 25

773 0.33 0.3 0.04 0.01 0.1

Total Emission (from DG set capacity 3,250KVA) in

g/s 0.8 0.13 0.04 0.16

Page 26: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

26

Meteorological data for the 24-hour average maximum predicted Concentration under

worst meteorological condition

2014 12 14 1 135 5.1 288 6 50 50

2014 12 14 2 112.5 4.1 288 6 50 50

2014 12 14 3 135 3.1 288 6 50 50

2014 12 14 4 90 3.1 287 6 50 50

2014 12 14 5 112.5 5.1 287 6 50 50

2014 12 14 6 135 5.7 287 6 50 50

2014 12 14 7 135 4.6 287 5 50 50

2014 12 14 8 135 4.1 287 4 60 60

2014 12 14 9 135 3.1 287 3 100 100

2014 12 14 10 135 3.1 287 3 150 150

2014 12 14 11 135 3.6 287 3 300 300

2014 12 14 12 135 3.6 288 3 500 500

2014 12 14 13 157.5 3.6 288 3 700 700

2014 12 14 14 135 2.6 288 3 900 900

2014 12 14 15 157.5 2.1 288 3 1000 1000

2014 12 14 16 135 2.1 288 3 1200 1200

2014 12 14 17 135 2.6 288 4 800 800

2014 12 14 18 112.5 2.1 288 5 600 600

2014 12 14 19 135 2.1 288 6 400 400

2014 12 14 20 112.5 2.6 288 6 300 300

2014 12 14 21 112.5 1.5 288 6 200 200

2014 12 14 22 67.5 3.1 288 6 150 150

2014 12 14 23 67.5 4.1 286 6 100 100

2014 12 14 24 67.5 4.6 286 6 50 50

Spatial distribution of NO2 is shown here below in iso-pleth figure. It was observed that GLC

closed to the proposed source will be not significant due to high stack attached with DG sets. 24-h

maximum incremental GLC was 2.95µg/m3 occurred at the distance (-600,600) West of the

project site.

Conclusion

Maximum Incremental GLC of NO2 was 2.95µg/m3 due to DG sets in the project. High to

moderate wind speed and stack of various heights facilitates dispersion at the distance of (-

600,600)m, West under the influence of local meteorology. Low GLC of pollutants was predicted

due to high Stack height and limited DG sets running hours. Predicted GLC of all pollutants are

given here below:

Page 27: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

27

Predicted GLC of all pollutants

S.No. Pollutants Maximum Incremental

GLC (µg/m3)

Distance of occurrence

1 NO2 2.95 -600m, 600 West

Spatial distribution of 24-hours average NO2 maximum incremental GLC (2.95 µg/m3) at (- 600m, 600m)

West.

Mitigation Measures: The project proponent will develop a green belt inside the premises of the

project site and along the internal road, which will work as barrier for the movement of pollutants

and help in pollution control.

Page 28: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

28

5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of the

present level of transport infrastructure and measures proposed for improvement including

the traffic management at the entry and exit to the project site.

Adequate provision will be made for car/vehicle parking at the project site. There shall also be

adequate parking provisions for visitors so as not to disturb the traffic and allow smooth movement

at the site.

As per MoEF Norms:

For Medical Facilities = 190 ECS

As per DDA Norms:

For Public/Semi-Public facilities = 608 ECS

Parking Proposed: = 611 ECS

5.4 Provide details of the movement patterns with internal roads, bicycle tracks,

pedestrian pathways, footpaths etc, with areas under each category.

Internal roads of 06 m width, footpaths/pedestrian pathways have been well planned for the project.

5.5 Will there be significant increase in traffic noise & vibrations? Give details of the

sources and the measures proposed for mitigation of the above.

No significant impact of noise has been anticipated within and outside of the project site due to

provision of wide roads for smooth flow of traffic and greenbelt along the roads. Noise, due to the

traffic, within site, will result in a marginal increase in the noise levels, which will cause slight

increase in noise level.

5.6 What will be the impact of D.G. sets and other equipment on noise levels and vibration

in ambient air quality around the project site? Provide details.

Page 29: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

29

During operation, vehicular movement and operation of DG sets are the major sources of noise

pollution. But both these activities- DG set and vehicular movement will not have any significant

impact on the people residing in the area. Since DG set will not be operational continuously and

moreover it will be placed away from settlements and will be enclosed with suitable acoustic

enclosures, hence no or minimal impact will be anticipated. It is envisaged that the movement of the

motor vehicles will be restricted to designated carriageways only.

Noise and Vibration Control Measures for DG sets:

• DG sets will be installed with suitable acoustic enclosures to minimize the impact on

ambient noise.

• All DG sets will be mounted on vibration isolator pads. Hence the impacts of noise and

vibration will be insignificant.

• Adequate exhaust mufflers will be provided as per norms to limit the noise.

SECTION 6-AESTHETICS

6.1 Will the proposed construction in any way result in the obstruction of a view, scenic

amenity or landscapes? Are these considerations taken into account by the proponents?

The site lies in an urbanized settlement and is well planned. Thus, no obstruction of view or scenic

beauty or landscape is anticipated. Furthermore, the construction has been planned in such a way that

the organized open spaces and landscaped areas will render the plot aesthetically appealing.

6.2 Will there be any adverse impacts from new constructions on the existing structures?

What are the considerations taken into account?

Being a building and construction project, it has no impact on existing structures.

6.3. Whether there are any local considerations of urban form & urban design influencing

the design criteria? They may be explicitly spelt out.

Page 30: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

30

The project will strictly follow the Area Building Regulation of NBC. All norms on Ground

Coverage, FAR, Height, Setbacks, Fire Safety Requirements, Structural Design and other parameters

will be strictly adhered to.

6.4 Are there any anthropological or archaeological sites or artifacts nearby? State if any

other significant features in the vicinity of the proposed site have been considered?

No anthropological or archaeological sites or artifacts are found near the site area. The

archeological monuments of historical significance are far from the project site, hence there will

be no impacts on these monuments.

SECTION 7-SOCIO-ECONOMIC ASPECTS

7.1 Will the proposal result in any changes to the demographic structure of local

population? Provide the details.

No such changes anticipated.

Construction phase: Since local labourers has been engaged during construction phase, alteration to

the existing demographic profile of the area has not been anticipated.

Operation phase: The changing demography in the area is another impact that needs attention. The

project will mainly lead to spatial redistribution of local population and hence no considerable influx

of population is envisaged owing to the project.

7.2 Give details of the existing social infrastructure around the proposed project.

Being an area of Dwarka, New Delhi, the project site is adequately equipped with all essential

facilities. JM International School adjacent to North direction, Bensups Hospital-2.45km in West

direction, Shiv Mandir -1km in NE and Vardhman mall in 1.29km in South .

7.3 Will the project cause adverse effects on local communities, disturbance to sacred sites

or other cultural values? What are the safeguards proposed?

Page 31: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

31

The impact can be divided into two phases; a) Construction phase and; b) Operation phase, i.e.

medical facility starts in the Hospital. Based on the nature and type of impacts, the assessment has

been divided into three category i.e. positive, negative and negligible impacts. Positive impacts

include job creation, preservation of environment and benefits to local population by providing

medical facilities and through job opportunities. Long-term impacts include aspects such as

demography and aesthetics..

CONSTRUCTION PHASE

Positive Impacts

Job opportunity: During the consultation process, the locals raised question about job opportunities

related to supervisory positions during construction work and operation phase. Construction phase

has generate jobs that will be related to unskilled, semi skilled as well as skilled labor category in

addition to various specialist positions. As far as construction labor has been concerned, they has

been from surrounding areas in proximity to the construction site. Therefore, the construction phase

will be likely to have positive economic impacts. There will be also likelihood for small shops and

tea stalls to come up near the construction site to cater the demands of the construction workers,

leading to indirect economic benefit to the locals.

Appreciation in Land Value: The development of Hospital Project will be likely to cause

appreciation of real estate prices in the nearby areas. Locals with any holdings in neighboring areas

will be likely to benefit economically.

Significant Impacts

Traffic and Transport: With this Human Care medical charitable trust, the traffic in this area will

increase, particularly during the operation phase. Increase in traffic will be managed by adopting

traffic management plan. However the probability of inconvenience faced due to the movement of

trucks during construction phase has been negligible, since the trucks have been allowed to transport

construction materials during night and non-peak hours. The traffic study and management measures

Page 32: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

32

suggested in the environment management plan will further reduce the negative impacts of the

traffic increment during the operation phase.

Minor Impacts

Labor Population: Labours were & will be hired from local areas. Hence no impact on local

infrastructure is envisaged.

Demography: Immigration of certain number of work force from the surroundings cannot be

avoided during the construction phase. The movement of labor to this area is a temporary

phenomenon. It is not likely to alter the existing demographic profile of the area.

Impact on Historical, Archeological and Architectural Sites: There are no historical or

archeological monuments of significance within the project area and hence no negative impact in

this regard is anticipated.

OPERATION PHASE

Positive Impacts

Job Opportunity: Employment opportunities will be increased, such as jobs for doctors, nurses and

other hospital staff will be generated with the operation of the Hospital.

Economic Growth: This project will increase the economic activities around the area, creating

avenues for direct/indirect employment in the post project period. People will like get treatment in

the Hospital. Expenditure incurred by the patients will boost local economy in the region. Business

like movie theatres, amusement parks, clubs and shopping malls around the project site will get

enhanced.

Page 33: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

33

Impacts on accessing utilities: Utilities include water supply, electricity and sewage facilities.

Water will be required for construction and even more during operation phase. Water needed during

construction phase will be through Tankers from local authorized sources supply system.

DJB will provide water during operation phase. It is anticipated that Hospital Project will ask

Authorities to make necessary arrangements to confirm the supply of water, electricity and other

utilities, so as to satisfy the increased demands if any.

SAFEGUARDS

The social management plan has been designed to take proactive steps and at the same time adoption

of best practices, which are sensitive to the socio-cultural settings of the region.

a. Income Generation Opportunity

Locals will be given preferences for jobs created after commissioning of the project.

The main principle of employment is outlined below:

Employment strategy will provide for preferential employment during operation Phase.

General recruitment procedures will be transparent, public and open to all.

Recruitment procedures will be publicized at locally prominent locations in advance.

There will be no discrimination on basis of gender, caste or other factors.

b. Improved Working Conditions

The project has been provide safe working conditions for the labor and other workers employed at

the facility during construction and hospital staff during operation phase.

Infrastructure Development

Infrastructure is already developed.

c. Traffic Management

A traffic plan has been adopted to minimize traffic flow interference from construction activities and

obstructions are minimized through-traffic lanes.

Page 34: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

34

d. Waste Management

No open litter burning will be done during infrastructure improvements. Proper segregation of waste

will be done.

SECTION 8-BUILDING MATERIALS

8.1 May involve the use of building materials with high embodied energy. Are the

construction materials produced with energy efficient processes? (Give details of energy

conservation measures in the selection of building materials and their energy efficiency)

For the purpose of paved path, sun dried pavers has been used instead of baked pavers as they are

manufactured from energy efficient processes. Fly ash bricks were used & will be used.

8.2 Transport and handling of materials during construction may results in pollution,

noise and public nuisance. What measures are taken to minimize the impacts?

Mitigation Measures for Air Pollution during Construction Stage:

• Construction materials has been suitably covered with tarpaulin cover etc during transportation.

• Water sprinkling has been done on haul roads where dust generation is anticipated.

• Raw material storage and handling yard has been enclosed from all sides.

• To minimize the occupational health hazard, proper personal protective gears i.e. mask has been

provided to the workers working in the dust prone areas.

Mitigation Measures for Noise Pollution during Construction Stage:

• Administrative as well as engineering control of noise has been implemented.

• Isolation of noise generation sources and temporal differentiation of noise generating activities has

ensure minimum noise at receiver’s end.

• To prevent any occupational hazard, earmuff / earplug has been given to the workers working

around construction plant & machinery emitting high noise levels.

• Use of such plant or machinery shall not be allowed during night time. Careful planning of

machinery operation and scheduling of operations has been done to minimise such impact.

Page 35: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

35

8.3 Are recycled materials used in roads and structures? State the extent of savings

achieved?

Yes. Recycled materials will be bought from outside sources and will be used as fillers in base and

sub-base of the carriageway, footpaths pavements or pedestrian way, as needed.

8.4 Give detail of the methods of collection, segregation & disposal of the garbage

generated during the operation phases of the project.

The solid waste of the project will be segregated into biodegradable waste and non-biodegradable.

Biodegradable waste and non biodegradable waste will be collected in separate bins. The recyclable

wastes will be sent off to recyclabers.

As per our project the total estimated Bio-medical waste generation is 380 Kg/day from Hospital

Building which will be handed over to the CPCB approved Biomedical waste handlers for which

tenders will be floated and MoU will be made by the approved vendors.

Collection and Segregation of waste

1. For Hospital waste collection, adequate number of colored bins (Red, Blue, Green and

Black bins are proposed to be provided at the strategic locations of the Hospital area.

2. Microbiological and Biological wastes and solid wastes will be collected in Red bins.

3. Waste sharps and sold wastes will be collected in Blue bins.

4. Discarded medicines, Cytotoxic drugs and chemical wastes will be collected in Black

bins.

5. General waste such as official waste, food waste & garden waste will be collected in

Green bins.

6. Litter bin will also be provided in open areas like parks etc.

Treatment of waste

Bio-Degradable wastes

Page 36: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

36

1. Bio-degradable waste will be disposed-off through a govt. approved vendor for

decomposition.

2. STP sludge will be proposed to be used for horticultural purposes as manure.

3. Horticultural Waste is proposed to be composted and will be used for gardening purposes.

Recyclable wastes

i. Grass Recycling – The cropped grass will be spread on the green area. It will act as

manure after decomposition.

ii. Recyclable wastes like paper, plastic, metals etc. will be sold off to recyclables.

Disposal

Recyclable and non-recyclable wastes will be disposed through Govt. approved agency.

Hence, the Municipal Solid Waste Management will be conducted as per the guidelines of

Municipal Solid Wastes (Management and Handling) Rules, 2000 and amended Rules, 2008. Bio-

Medical waste will be disposed through the govt. approved vendors for Bio-Medical waste. Bio-

Medical waste management will be conducted as per the Bio-Medical Waste (Management and

Handling) Rules, 1998. AERB/BARC Guidelines will be followed for identification and operation

of any item or disposal of any waste containing or suspected to be containing radioactive

materials. A Solid waste management Scheme is depicted in the figure for the “Human Care

Charitable Hospital”. Hospital Waste generated will be collected in the color coded bins and will

be handed over to the government approved vendor for disposal.

Page 37: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

37

Solid Waste Management Scheme (Operation Phase)

Hospital Waste

Waste sharps and

Solid waste Discarded

medicines,

Cytotoxic drugs and

chemical waste

General waste such

as official waste,

food waste &

garden waste

Microbiological and

Biological wastes,

Soiled wastes, Solid

waste

Red Bins Blue Bins Black Bins Green Bins

Disposed-off by Govt. approved Vendors for

biomedical waste

Biodegradable

Waste

Non-Biodegradable

Waste

Disposed-off by

Govt. approved

Vendors

Disposed-off by

Govt. approved

Vendors

Page 38: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

38

SECTION 9-ENERGY CONSERVATION

9.1 Give details of the power requirements, source and supply, backup source etc. What is

the energy consumption assumed per square foot of built-up area? How have you tried to

minimize energy consumption?

The total power requirement for the project is 3,153.7 Kw which will be provided by BSES Rajdhani

Power Limited, Delhi. There is a provision of 3 DG sets of total capacity of 3,250 kVA (2*1250

kVA & 1*750 kVA) for power back up . The proposed DG sets will be equipped with acoustic

enclosure to minimize noise generation and adequate stack height for proper dispersion.

To minimize the energy consumption effective measures have been incorporated in following

manners:

• All external lighting shall be BEE star rated.

• All common spaces including street lights (where there is no use of light for reading

purposes), shall be of “LED”.

• A minimum of 50% hot water requirement shall be met by solar water heating systems.

• Integration of automated system to operate electrical equipment as per load requirement to

save energy.

9.2 What type and capacity of power backup do you plan to provide?

There is a provision of 3 DG sets of total capacity of 3,250kVA (2*1250 kVA & 1*750 kVA) for

power back up. The proposed DG sets will be equipped with acoustic enclosure to minimize noise

generation and adequate stack height for proper dispersion.

9.3 What are the characteristics of the glass you plan to use? Provide specifications of its

characteristics related to both short wave and long wave radiation?

Page 39: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

39

The proposed project will involve uses of clear & tinted glass having U-value of 2.67 to 3.97

W/m2K.

9.4 What passive solar architectural features are being used in the building? Illustrate the

applications made in the proposed project.

Passive solar design refers to use of the sun’s energy for the heating and cooling of living spaces.

Projections, façade elements, DGUs will be provided for sun shading to reduce the heat influx into

the building and thus reduce the air conditioning loads.

9.5 Does the layout of street & building maximize the potential for solar energy devices?

Have you considered the use of street lighting, emergency lighting and solar hot water systems

for use in the building complex? Substantiate with details.

Layout of buildings has been done as per the sun path analysis so that the design cuts off direct

radiations of critical hours which are specific to the orientation. Solar energy will be harnessed to

meet various energy requirements of the project such as:

Hot water requirement.

Street lightening

9.6 Is the shading effectively used to reduce cooling / heating lands? What principles have

been used to maximize the shading of walls on the East and the West and the Roof? How much

energy saving has been effected?

Projection, façade elements, DGUs will be provided to reduce cooling loads. Green area and open

areas will be so spaced that a reduction in temperature is achieved.

9.7 Do the structures use energy-efficient space conditioning, lightening and mechanical

systems? Provide technical details. Provide details of the transformers and motor efficiencies,

Page 40: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

40

lightening intensity and air conditioning load assumption? Are you using CFC and HCFC free

chillers? Provide specifications.

Yes. The roofs of top floor rooms will be insulated, heat shield paint on wall surfaces such that air

conditioning load is reduced. Well designed building structures will allow natural light to enter.

Measures prescribed in Energy Conservation Building Code 2007 will be adopted to reduce the heat

influx by walls, roofs and openings. Only prescribed quality of glasses will be used.

We are using CFC and HCFC free chillers from Career and using R-134a.

9.8 What are the likely effects of the building activity in altering the micro-climates?

Provide a self assessment on likely impacts of the proposed construction on creation of heat

island & inversion effects?

Heat emissions from the construction may be from the following sources:

Heat absorbed from the paved and concrete structures

Heat generated from equipment/appliances

Heat increase due to increase in the population of the project.

However, the heat generated will not be significant and will be dissipated in the greens and open

areas provided within the project area.

9.9 What are the thermal characteristics of the building envelope? (a) Roof (b) external

walls and (c) fenestration? Give details of the material used and the U value or the R values of

the individual components.

The roof tops of the buildings will be planned with puffing/bricks bat coba for water proofing and

thermal insulation.

External wall-external opening will have regular door, DGU(6-16-8) windows with SKN444 glass.

Regular walls have some cladding/fixture heat shield paints. The ECBC guidelines will be

considered as shown below:

Page 41: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

41

List of Construction Materials

Type of Construction U Values (in W/m2 deg C)

WALLS:

Bricks:

Plastered both sides-114mm 3.24

Solid, Unplastered-228mm 2.67

Plastered both sides-228mm 2.44

Concrete, ordinary, Dense:

-152mm 3.58

-203mm 3.18

Concrete block, cavity, 250mm (100mm + 50mm), outside rendered, inside plastered

Aerated concrete blocks 1.19

Hollow concrete block, 228mm, single skin outside rendered, inside plastered

Aerated concrete blocks 1.70

Roofs pitched:

Tiles, slates on boarding and felt with plaster

ceiling

1.70

Roofs flat:

Reinforced concrete slab, 100mm, screed 63-

12mm, 3 layers, bituminous felt

3.35

Floors:

Concrete on ground or hardcore fill 1.13

+Grano Terazzo or tile finish 1.13

+Wood block finish 0.85

WINDOWS:

Exposure South, Sheltered:

Single glazing 3.97

Double glazing 6mm space 2.67

9.10 What precautions & safety measures are proposed against fire hazards? Furnish

details of emergency plans.

Firefighting measures shall be adopted as per the guidelines of NBC. External yard hydrants shall be

installed around all buildings in the complex in galvanized steel fire house cabinet (weather proof).

All external yard hydrants shall be at one meter height from finished ground level as per NBC at a

distance of 45 m along the road. External fire hydrants will be located such that no portion of any

Page 42: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

42

building is more than 45 m from a hydrant and the external hydrants will not be vulnerable to

mechanical or vehicular damage.

9.11 If you are using glass as wall materials, provide details and specifications including

emissivity and thermal characteristics.

The project will be a Hospital project will involve use of glass as wall material. All fenestration with

U-factors, SHGC, or visible light transmittance determined, certified, and labeled in accordance ISO

15099 shall be adopted.

9.12 What is the rate of air infiltration in to the building? Provide details of how you are

mitigating the effects of infiltration.

It will be a air-conditioned Hospital; air infiltration will be kept to required minimum level.

9.13 To what extent the non–conventional energy technologies are utilized in the overall

energy consumption? Provide details of the renewable energy technologies used.

Solar energy will be variedly used as:

Green CFLs/LED will be used in buildings to minimize the energy consumption.

Solar water heating systems will be used to achieve minimum of 50% hot water

requirement.

Green area is provided along with tree plantation which will result in natural air cooling and

will reduce the load on conventional energy sources.

10. ENVIRONMENT MANAGEMENT PLAN

The Environment Management Plan (EMP) will consist of all mitigation measures for each

component of the environment due to the activities increased during the construction, operation and

the entire life cycle to minimize adverse environmental impacts resulting from the activities of the

Page 43: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

43

project. It will also delineate the environmental monitoring plan for compliance of various

environmental regulations. It will state the steps to be taken in case of emergency such as accidents

at the sites including fire. The detailed EMP for the project is given below.

10.1 Environmental Management Plan

The Environment Management Plan (EMP) is a site specific plan developed to ensure that

the project is implemented in an environmental sustainable manner where all contractors and

subcontractors, including consultants, understand the potential environmental risks arising from the

project and take appropriate actions to properly manage that risk. EMP also ensures that the project

implementation is carried out in accordance with the design by taking appropriate mitigation actions

to reduce adverse environmental impacts during its life cycle. The plan outlines existing and

potential problems that may adversely impact the environment and recommends corrective measures

where required. Also, the plan outlines roles and responsibility of the key personnel and contractors

who will be in charge of the responsibilities to manage the project site.

10.1.1 The EMP is generally

Prepared in accordance with rules and requirements of the MoEF and CPCB/ SPCB

To ensure that the component of facility will be operated in accordance with the design

A process that confirms proper operation through supervision and monitoring

A system that addresses public complaints during construction and operation of the facilities

and

A plan that ensures remedial measures is implemented immediately.

The key benefits of the EMP will offer means of managing its environmental performance thereby

allowing it to contribute to improved environmental quality. The other benefits include cost control

and improved relations with the stakeholders.

Page 44: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

44

EMP includes four major elements:

Commitment & Policy: The management will strive to provide and implement the

Environmental Management Plan that incorporates all issues related to air, water, land

and noise.

Planning: This includes identification of environmental impacts, legal requirements and

setting environmental objectives.

Implementation: This comprises of resources available to the developers, accountability

of contractors, training of operational staff associated with environmental control facilities and

documentation of measures to be taken.

Measurement & Evaluation: This includes monitoring, counteractive actions and record

keeping.

It is suggested that as part of the EMP, a monitoring committee will be formed by comprising of the

site in-charge/coordinator, environmental group representative and project implementation team

representative. The committee’s role will be to ensure proper operation and management of the EMP

including the regulatory compliance.

The components of the environmental management plan, potential impacts arising, out of the project

and remediation measures are summarized below:

Page 45: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 45

SUMMARY OF POTENTIAL IMPACTS AND REMEDIAL MEASURES

S.

No.

Environmental

components

Potential

Impacts

Potential

Source of

Impact

Controls Through

EMP & Design

Impact Evaluation Remedial Measures

1 Ground Water

Quality

Ground Water

Contamination

Construction

Phase

Waste

water

generated

from

temporary

labor tents.

Soak Pit has

been provided.

No impact as

majority of labors

has been locally

deployed

Operation

Phase

Dischar

ge from the

project

Proponent will

provide the STP &

ETP to treat the

discharge of

Hospital.

No negative impact

on ground water

quality envisaged.

Not significant.

In an unlikely event of

soil and ground water

contamination.

Remediation measures

shall be implemented.

2. Ground Water

Quantity

Ground Water

Depletion

Construction

Phase

Water

from Private

tankers

NA No significant

impact on ground

water quantity

envisaged.

Operation

Phase

Water will

be supplied

by DJB.

Rain water

harvesting scheme.

Storm water

collection for water

harvesting.

Percolation

well to be

introduced in

landscape plan.

No significant

impact on

surface/ground

water quantity

envisaged.

In an unlikely event of

non-availability of

water supply, water will

be brought using

tankers.

Page 46: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 46

Awareness

Campaign to

reduce the water

consumption

3. Surface Water

Quality

Surface water

contamination

Construction

Phase

Surface

runoff from

site during

construction

activity.

Silt traps and

other measures

such as additional

on site diversion

ditches has been

constructed to

control surface run-

off during site

development

No off site impact

envisaged as no

surface water

receiving body is

present in the core

zone.

Operation

Phase

Discharge

of domestic

wastewater to

surface water

body/land.

Wastewater will

be treated in STP

& ETP.

No off site impact

envisaged

There will be no

wastewater to be

discharged into the

surface water body.

4. Air Quality Dust Emissions Construction

Phase

All heavy

construction

activities

Suitable control

measures have

been adopted for

subsiding the SPM

level in the air as

per air pollution

control plan.

Not significant

because dust

generation has been

temporary and

settle fast due to

dust suppression

techniques (wet

scrubbers) used.

During construction

phase the contractor

have been advised to

facilitate masks for the

labors. Water sprinklers

have been used for

suppression of dust

during construction

phase.

Emissions of

PM, SO2, NO2

and CO

Operation

of

construction

equipment

Rapid on-site

construction and

improved

maintenance of

Not significant. Regular monitoring of

emissions and control

measures will be taken

to reduce the emission

Page 47: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 47

and vehicles

during site

development.

Runnin

g D.G. sets

(back up)

equipment levels.

5. Noise Environment Construction

Phase

Operation

of

construction

equipment

and vehicle

movements

during site

development.

Running

DG sets (for

power back

up)

Use of equipment

fitted with silencers

Proper

maintenance of

equipment

Provision of

noise shields near

the heavy

construction

operations and

acoustic enclosures

for DG sets

Construction

activity has been

limited to day time

hours only

There are no

sensitive receptors

located within the

vicinity of site.

Use of Personal

Protective Equipment

(PPE) like earmuffs and

earplugs during

construction activities.

Operation

Phase

Noise

from

vehicular

movement

Noise

from DG

sets

operation

Green Belt

Development

Development of

silence zones to

check the traffic

movement

DG set

rooms will be

equipped with

acoustic

enclosures.

No significant

impact due to

suitable width of

Greenbelt.

Page 48: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 48

6. Land Environment Soil

contamination

Constructio

n Phase

Disposal

of

construction

debris

Construction

debris has been

collected and

suitably used on

site as per the

solid waste

management plan

for construction

phase

No significant

impact.

Impact has been

local, as waste

generated has

reused for filling

of low lying

areas etc.

Operation

Phase

Dumpin

g of

municipal

solid waste

on land.

Used Oil

generated

from D.G.

sets

Hospital

Waste

It is proposed

that the solid

waste generated

will be managed

by an authorized

agency.

Collection,

segregation,

transportation and

disposal will be

done as per MSW

Management

Rule, 2000 by the

authorized agency

Used oil

generated will be

sold to authorized

recyclers

Hospital

waste will be

collected in the

color coded bags

and will be

handed over to the

Since solid waste

is handled by the

authorized

agency, waste

dumping is not

going to be

allowed. Not

significant.

Negligible

impact.

Page 49: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 49

government

approved vendor

for final disposal.

AERB/BAR

C Guidelines will

be followed for

identification and

operation of any

item or disposal of

any waste

containing or

suspected to be

containing

radioactive

materials

7. Biological

Environment (Flora

and Fauna)

Displacement of

Flora and Fauna

on site

Constructio

n Phase

Site

Developme

nt during

construction

Important species

of trees, will be

identified and

marked and will

be merged with

landscape plan

The proposed site

has no vegetation

at present

Operation

Phase

Increase

in green

covered

area

Suitable green

belts will be

developed as per

landscaping plan

in and around the

site using local

flora

Beneficial

impact.

8. Socio-Economic

Environment

Population

displacement

and loss of

income

Constructio

n Phase

Constructio

n activities

leading to

There will

be no relocation.

Project will

provide

employment

No negative

impact.

Page 50: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust 50

relocation opportunities to

the local people in

terms of labor

during

construction

Operation

Phase

Site

operation

Service

personnel

(Hospital staff,

securities,

gardeners etc)

during operations

Providing

quality-Integrated

medical facility in

Sec-6, Dwarka,

New Delhi

Public

services (hospital)

Beneficial impact

9. Traffic Pattern Increase of

vehicular traffic

Constructio

n Phase

Heavy

Vehicular

movement

during construction

Heavy Vehicular

movement has

been restricted to

daytime only and

adequate parking

facility will be

provided

No negative

impact

Operation

Phase

Traffic

due to

people

coming to

the hospital.

Vehicular

movement has

been regulated

inside the Hospital

with adequate

roads and parking

lots in the

Hospital.

No major

significant

impact

Page 51: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

51

10.2 ENVIRONMENT MANAGEMENT PLAN

An environmental management plan (EMP) will be required to mitigate the predicted adverse

environmental impacts during construction and operation phase of the project and these are

discussed in later subsections.

10.2.1 EMP for Air Environment

Construction Phase

To mitigate the impacts of PM2.5 and PM10 during the construction phase of the project, the

following measures have been implemented:

A dust control plan.

Procedural changes to construction activities.

Dust Control Plan

The most cost-effective dust suppressant is water because water is easily available on construction

site. Water can be applied using water trucks, handled sprayers and automatic sprinkler systems.

Furthermore, incoming loads could be covered to avoid loss of material in transport, especially if

material is transported off-site.

Procedural Changes to Construction Activities

Idle time reduction: Construction equipment has been commonly left idle while the operators will

be on break or waiting for the completion of another task. Emission from idle equipment tends to be

high, since catalytic converters cools down, thus reducing the efficiency of hydrocarbon and carbon

monoxide oxidation. Idle control technologies have been comprised of power saving mode, which

automatically off the engine at preset time and reduces emissions, without intervention from the

operators.

Page 52: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

52

Improved Maintenance: Significant emission reductions can be achieved through regular

equipment maintenance. Contractors have been asked to provide maintenance records for their fleet

as part of the contract bid, and at regular intervals throughout the life of the contract. Incentive

provisions will be established to encourage contractors to comply with regular maintenance

requirements.

Operation Phase

To mitigate the impacts of pollutants from DG sets and vehicular traffic during the operational phase

of the Hospital, following measures are recommended for implementation:

DG set emission control measures

Vehicular emission controls and alternatives

Greenbelt development

Diesel Generator Set Emission Control Measures

Adequate stack height will be maintain to disperse the criteria air pollutants generated from the

operation of DG sets to dilute the pollutants concentration within the immediate vicinity. Hence no

additional emission control measures have been suggested.

Vehicle Emission Controls and Alternatives

Use of clean Fuel by vehicles on-site: Low sulphur diesel will be used as clean fuel (if available

locally). This will reduce emissions on-site and in areas from where these vehicles pass.

Footpaths and Pedestrian ways: Adequate footpaths and pedestrian ways will be provided at the site

to encourage non-polluting methods of transportation.

Greenbelt Development

Increased vegetation in the form of greenbelt is one of the preferred methods to mitigate air and

noise pollution. Plants serve as a sink for pollutants, act as a barrier to break the wind speed as well

as allow the dust and other particulates to settle on the leaves. It also helps to reduce the noise level

Page 53: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

53

at large extent. The following table indicates various species of the greenbelt that can be used to act

as a barrier.

Trees that can be used as Barrier for Air Pollution

List of plants to be planted

S. No. Botanical Name

1 Phoenix dactylifera

2 Mimusops elengi (Maulshri)

3 Ficus religiosa (Peepal)

4 Azadirachta indica (Neem)

5 Antocephalus cadamba (Kadam)

6 Tabebuia argentia (Silver trumpet)

7 Plumeria alba (Champa)

8 Bauhinia (Kaniar)

9 Jacquemotia reclinata

10 Melia azaderach

11 Ficus Religosa(peepal)

12 Bauhinia vareigata (Kachnar)

13 Melia azaderach (Bakain)

10.2.2 EMP FOR NOISE ENVIRONMENT

Construction Phase

To mitigate the impacts of noise from construction equipment during the construction phase on the

site, the following measures have been implemented.

Time of Operation: Noisy construction equipment has not been allowed to use.

Job Rotation and Hearing Protection: Workers employed in high noise areas has been rotated.

Hearing protection such as earplugs/muffs has been provided to those working very close to the

noise generating machinery.

Page 54: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

54

Operation Phase

To mitigate the impacts of noise from diesel generator sets during operational phase, the following

measures will be recommended:

Adoption of Noise emission control technologies.

Greenbelt development.

Noise Emission Control Technologies

It will be ensured that the manufacturer provides acoustic enclosure as an integral part along with the

diesel generators sets. Further, enclosure of the services area with 4 m high wall will reduce noise

levels and ensure that noise is at a permissible limit for occupants of the site and surrounding

receptors.

Greenbelt Development

The name of species of plants to be used as in a greenbelt, to serve as noise breakers are mentioned

in table above.

10.2.3 EMP FOR WATER ENVIRONMENT

Construction Phase

To prevent degradation and to maintain the quality of the water source, adequate control measures

have been proposed. To check the surface run-off as well as uncontrolled flow of water into any

water body check dams with silt basins has been proposed. The following management measures are

suggested to protect the water source has been polluted during the construction phase:

Avoid excavation during monsoon season

Care has been taken to avoid soil erosion

Mobile toilets has been Placed on site during construction phase,

To prevent surface and ground water contamination by oil and grease, leak-proof

Containers have been used for storage and transportation of oil and grease. The floors of

Page 55: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

55

oil and grease handling area will be kept effectively impervious. Collection and settling of

storm water, prohibition of equipment wash downs and prevention of soil loss and toxic release

from the construction site are necessary measure

to be taken to minimize water pollution

All stacking and loading area has been provided with proper garland drains, equipped

with baffles, to prevent run off from the site, to enter into any water body

Operation Phase

In the operation phase of the project, water conservation and development measures will be taken,

including all possible potential for rain water harvesting. Following measures will be adopted:

Water source development

Minimizing water consumption

Promoting reuse of water after treatment and development of closed loop systems for

different water streams

Water Source Development

Water source development shall be practiced by installation of scientifically designed Rain Water

Harvesting system. Rainwater harvesting promotes self-sufficiency and fosters an appreciation for

water as a resource.

Minimizing Water Consumption

Consumption of fresh water will be minimized by combination of water saving devices and other

domestic water conservation measures. Further, to ensure ongoing water conservation, an awareness

program will be introduced for the hospital staff and patients. The following section discusses the

specific measures, which shall be implemented:

Page 56: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

56

Domestic and Commercial Usage

Use of water efficient plumbing fixtures (ultra flow toilets and urinals). Water efficient

plumbing fixtures uses less water with no marked reduction in quality and service

Leak detection and repair techniques

Sweep with a broom and pan where possible, rather than hose down for external areas

Meter water usage: Implies measurement and verification methods. Monitoring of water

uses is a precursor for management.

Horticulture

Spray irrigation system shall be used for the lawns and other green area. Spray

irrigation can save 15-40 % of the water, compared with other watering techniques

Plants with similar water requirements shall be grouped on common zones to match

precipitation heads and emitters.

Use of low-angle sprinklers for lawn areas.

Select controllers with adjustable watering schedules and moisture sensors to account

for seasonal variations and calibrate them during commissioning.

Place 3 to 5 inches of mulch on planting beds to minimize evaporation.

Promoting Reuse of Water after Treatment and Development of Closed Loop Systems

To promote reuse of wastewater and development of closed loop system for wastewater segregation.

Two wastewater schemes are suggested, namely:

1) Storm Water Harvesting 2) Waste water recycling.

Waste Water Treatment Scheme

Proponent will treat the wastewater of the project in well designed Sewage Treatment Plant capacity

based on SBR technology and the effluent generated from the Hospital activities will be treated in

the ETP before.

Page 57: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

57

Storm Water Management

Most of the storm water produced on site will be harvested for ground water recharge. Thus proper

management of this resource is a must to ensure that it is free from contamination.

Contamination of Strom Water is possible from the following sources:

Diesel and oil spills in the diesel power generator and fuel storage area

Waste spills in the solid / hazardous waste storage area

Oil spills and leaks in vehicle parking lots

Silts from soil erosion in gardens

Spillage of sludge from sludge drying area of sewage treatment plant

A detailed storm water management plan will be developed which will consider the possible impacts

from above sources. The plan will incorporate best management practices which will include

following:

Regular inspection and cleaning of storm drains

Clarifiers or oil / separators will be installed in all the parking areas. Oil / grease separators

installed around parking areas and garages will be sized according to peak flow guidelines. Both

clarifiers and oil / water separators will be periodically pumped in order to keep discharges within

limits

Covered waste storage areas

Avoid application of pesticides and herbicides before wet season

Secondary containment and dykes in fuel / oil storage facilities

Conducting routine inspection to ensure cleanliness

Provision of slit traps in storm water drains

Good housekeeping in the above areas.

Page 58: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

58

10.2.4 EMP FOR LAND ENVIRONMENT

Construction Phase

The waste generated from construction activity includes construction debris, biomass from land

clearing activities, waste from the temporary make shift tents for the labors and hazardous waste.

Following section discuss the management of each type of waste. Besides waste generation,

management of the topsoil will be an important area for which management measures will be

required.

Construction Debris

Construction debris is bulky and heavy, hence re-utilization and recycling of debris is an important

strategy for management of such waste. As concrete and masonry constitute the majority of waste

generated, recycling of this waste by conversion to aggregate can offer benefits of reduced landfill

space and reduced extraction of raw material for new construction activity. This is particularly

applicable to the project site as the construction is to be completed in a phased manner.

Mixed debris with high gypsum, plaster, shall not be used as fill, as they will be highly susceptible to

contamination, and will be send to designated solid waste landfill site.

Metal scrap from structural steel, piping, concrete reinforcement and sheet metal work shall be

removed from the site by construction contractors. A significant portion of wood scrap will be

reused on site. Recyclable wastes such as plastics, glass fiber insulation, roofing etc shall be sold to

recyclers.

Hazardous waste

Construction sites are sources of many toxic substances such as paints, solvents wood preservatives,

pesticides, adhesives and sealants. Hazardous waste generated during

construction phase shall be stored in sealed containers and disposed off as per the Hazardous Wastes

Management and Handling Act, Amendment Rules (MoEF, 2003).

Page 59: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

59

Some management practices to be developed are:

Herbicides and pesticide will not be over applied (small-scale applications) and not applied

prior to rain

Paintbrushes and equipment for water and oil based paints shall be cleaned within a

contained area and will not be allowed to contaminate site soils, water courses or drainage

systems

Provision of adequate hazardous waste storage facilities. Hazardous waste collection

containers will be located as per safety norms and designated hazardous waste storage areas

will be away from storm drains or watercourses

Segregation of potentially hazardous waste from non-hazardous construction site

debris

Well labeled all hazardous waste containers with the waste will be stored and the date of

generation

Instruct employees and subcontractors in identification of hazardous and solid waste

Bio- medical waste is the main type of waste generated from hospitals. The waste generated

will be handed over to the government approved vendor for the final disposal of waste.

AERB/BARC Guidelines will be followed for identification and operation of any item or

disposal of any waste containing or suspected to be containing radioactive materials.

Even with careful management, some of these substances will be released into air, soil and water and

many will be hazardous to workers. With these reasons, the best choice is to avoid their use as much

as possible by using low-toxicity substitutes and low VOC (volatile organic compound) materials.

Waste from Temporary Makes Shift Tents for Labors

Wastes generated from temporary make shift labor tents will mainly comprise of household

domestic waste, which will be managed by the contractor of the site. The wastewater generated will

be channelized to the STP provided within the premises.

Top Soil Management

Page 60: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

60

To minimize disruption of soil and for conservation of top soil, the contractor shall keep the top soil

cover separately and stockpile it. After the construction activity is over, top soil will be utilized for

landscaping activity. Other measures, which will be followed to prevent soil erosion and

contamination include:

Maximize use of organic fertilizer for landscaping and green belt development

To prevent soil contamination by oil/grease, leaf proof containers will be used for storage

and transportation of oil/grease and wash off from the oil/grease handling area shall be drained

through impervious drains and treated appropriately before disposal

Working in a small area at a point of time (phase wise construction)

Construction of erosion prevention troughs/ berms.

Operational Phase

The philosophy of solid waste management at the proposed Hospital will be to encouraging the four

R’s of waste i.e. Reduction, Reuse, Recycling and Recovery (materials & energy). Regular

awareness meetings will be conducted to involve the Hospital staff and patients in the proper

segregation and storage techniques.

The Environmental Management Plan for the solid waste focuses on three major components during

the life cycle of the waste management system i.e., collection and transportation, treatment or

disposal and closure and post-closure care of treatment/disposal facility.

Collection and Transportation

During the collection stage, the solid waste of the proposed project will be segregated into

biodegradable waste and non-biodegradable. Biodegradable waste and non biodegradable waste will

be collected in separate bins. The recyclable wastes will be sent off to recyclabers. Proper guidelines

for segregation, collection and storage will be prepared as per MSW Rules, 2000.

To minimize littering and odour, waste will be stored in well-designed containers/ bins that

will be located at strategic locations to minimize disturbance in traffic flow

Page 61: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

61

Care will be taken such that the collection vehicles will be well maintained and generate

minimum noise and emissions. During transportation of the waste, it will be covered to avoid

littering.

Disposal

With regards to the disposal/ treatment of waste, the management will take the services of the

authorized agency for waste management and disposal of the same on the project site during its

operational phase.

Bio-Medical waste generated will be approx. 380 kg/day and will be collected in the color coded

bags. The collected waste will be further handed over to the government approved vendor for the

final disposal of hazardous waste.

Detailed waste management program is given in the Conceptual plan, enclosed.

10.2.5 EMP FOR ECOLOGICAL ENVIRONMENT

Construction activity changes the natural environment. But Hospital also creates a built environment

for its patients and staff. The project requires the implementation of following choices exclusively or

in combination.

Construction Stage

Restriction of construction activities to defined project areas, which will be ecologically

sensitive

Restrictions on location of temporary labor tents and offices for project staff near the

project area to avoid human induced secondary additional impacts on the flora and fauna species

Cutting and uprooting of trees or small trees if present in and around the project site for

cooking, burning or heating purposes by the labors will be prohibited and suitable alternatives for

this purpose will be made.

Page 62: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

62

Along with the construction work, the peripheral green belt will be developed with

suggested native plant species, as they will grow to a full-fledged covered at the time of completion

Operation Stage

Improvement of the current ecology of the project site will entail the following measures:

Plantation and Landscaping

Green Belt Development

Avenue Plantation

The section below summarizes the techniques to be applied to achieve the above objectives:

Plantation and landscaping

Selection of the plant species will be done on the basis of their adaptability to the existing

geographical conditions and the vegetation composition of the forest type of the region earlier found

or currently observed.

Green Belt Development Plan

The plantation matrix adopted for the green belt development includes pit of 0.3 m × 0.3 m size with

a spacing of 2 m x 2 m. In addition, earth filling and manure may also be required for the proper

nutritional balance and nourishment of the sapling. It is also recommended that the plantation has to

be taken up randomly and the landscaping aspects could be taken into consideration.

Multi-layered plantation comprising of medium height trees (7 m to 10 m) and shrubs (5 m height)

has been proposed for the green belt. In addition creepers will be planted along the boundary wall to

enhance its insulation capacity.

Selection of Plant Species for Green Belt Development

The selection of plant species for the development depends on various factors such as climate,

elevation and soil. The plants will exhibit the following desirable characteristics in order to be

selected for plantation

1. The species shall be fast growing and providing optimum penetrability

Page 63: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

63

2. The species shall be wind-firm and deep rooted

3. The species shall form a dense canopy

4. As far as possible, the species shall be indigenous and locally available

5. Species tolerance to air pollutants like SO2 and NOx shall be preferred

6. The species shall be permeable to help create air turbulence and mixing within the belt

7. There shall be no large gaps for the air to spill through

8. Trees with high foliage density, leaves with larger leaf area and hairy on both the surfaces

9. Ability to withstand conditions like inundation and drought

10. Soil improving plants (Nitrogen fixing rapidly decomposable leaf litter)

11. Attractive appearance with good flowering and fruit bearing

12. Bird and insect attracting tree species

13. Sustainable green cover with minimal maintenance.

Avenue Plantation

Gardens maintained for recreational and ornamental purposes will not only improve

the quality of existing ecology at the project site but also will improve the aesthetic value.

Avenue Plantation

1. Trees with colonial canopy with attractive flowering

2. Trees with branching at 7 feet and above

3. Trees with medium spreading branches to avoid obstruction to the traffic

4. Fruit trees to be avoided because children may obstruct traffic and general movement of

public

10.2.6 EMP for Socio-Economic Environment

The social management plan has been designed to take proactive steps and adopt best practices,

which will be sensitive to the socio-cultural setting of the region. The Social Management Plan for

Human Care Hospital Project focuses on the following components:

Income Generation Opportunity During Construction and Operation Phase

Page 64: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

64

The project will be provide employment opportunity during construction and operation phase. There

will also be a wide economic impact in terms of generating opportunities for secondary occupation

within and around the Hospital. The main principles considered for employment and income

generation opportunities are out lined below:

Employment strategy will provide for preferential employment of local people

Conditions of employment will be address issues like minimum wages and medical care for

the workers during construction.

Contractors will be required to abide to employment priority towards locals and abide by the labor

laws regarding standards on employee terms and conditions.

Improved Working Environment for Employees

The proposed project will be provide safe and improved working conditions for the workers

employed at the facility during construction and hospital staff during operation phase. Following

measures will be taken to improve the working environment of the area:

Less use of chemicals and biological agents with hazard potential

Developing a proper interface between the work and the human resource through a system

of skill improvement

Provision of facilities for nature care.

Measures to reduce the incidence of work related injuries, fatalities and diseases

Maintenance and beautifications of the Hospital and the surrounding roads

10.2.7 EMP FOR ENERGY CONSERVATION

Energy conservation program will be implemented through measures taken both on energy demand

and supply.

Page 65: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

65

Figure – 8 : EMP for Energy Conservation

Energy conservation will be one of the main focus during the complex planning and operation

stages. The conservation efforts will be consist of the following:

Architectural design

Maximum utilization of solar light will be done.

Maximize the use of natural lighting through design.

The orientation of the buildings will be done in such a way that maximum daylight is

available.

The green areas will be spaced, so that a significant reduction in the temperature can take

place.

Energy Saving Practices

Energy efficient lamps will be provided within the complex.

Constant monitoring of energy consumption and defining targets for energy conservation.

Adjusting the settings and illumination levels to ensure minimum energy used for desired

comfort levels.

Supply Energy Conservation Demand

Utilize energy-efficient diesel

genetators

Exploring the possibilities of

introducing renewable energy

Reduce consumption

Use energy efficient appliances

Create Guest Awareness

Page 66: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

66

Behavioral Change on Consumption

Promoting resident awareness on energy conservation

Training staff on methods of energy conservation and to be vigilant to such opportunities.

10.3 ENVIRONMENTAL MANAGEMENT SYSTEM AND MONITORING PLAN

For the effective and consistent functioning of the proposed complex, an Environmental

Management system (EMS) will be established at the site. The EMS will be include the following:

An Environmental management cell.

Environmental Monitoring.

Personnel Training.

Regular Environmental audits and Correction measures.

Documentation – standards operation procedures Environmental Management Plan and

other records.

10.3.1 ENVIRONMENTAL MANAGEMENT CELL

Apart from having an Environmental Management Plan, it is also proposed to have a permanent

organizational set up charged with the task of ensuring its effective implementation of mitigation

measures and to conduct environmental monitoring. The major duties and responsibilities of

Environmental Management Cell shall be as given below:

To implement the environmental management plan.

To assure regulatory compliance with all relevant rules and regulations.

To ensure regular operation and maintenance of pollution control devices.

To minimize environmental impact of operations as by strict adherence to the EMP.

To initiate environmental monitoring as per approved schedule.

Page 67: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

67

Review and interpretation of monitored results and corrective measures in case

monitored results are above the specified limit.

Maintain documentation of good environmental practices and applicable environmental

laws for a ready reference.

Maintain environmental related records.

Coordination with regulatory agencies, external consultants, monitoring laboratories.

Maintenance of log of public complaints and the action taken.

Hierarchical Structure of Environmental Management Cell

Normal activities of the EMP cell will be supervised by a dedicated person who will report to the

site manager/coordinator of the project. The hierarchical structure of suggested Environmental

Management Cell is given in following Figure 9.

Environment Management Cell Structure

Rep from

Management

Planning group

Site Environmental

Coordinator

Waste water

Treatment

Plant

Operator

Greenbelt

Dev. Incharge

Site

Manager

Page 68: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

68

10.3.2 ENVIRONMENTAL MONITORING

The purpose of environmental monitoring is to evaluate the effectiveness of implementation of

Environmental Management Plan (EMP) by periodic monitoring. The important environmental

parameters within the impact area are selected so that any adverse affects are detected and time

action can be taken. The project proponent will monitor ambient air Quality, Ground Water Quality

and Quantity, and Soil Quality in accordance with an approved monitoring schedule.

Suggested Monitoring Program

S. No. S.N.

Type Locations Parameters Period and Frequency

1. Ambient Air

Quality

Project Site Criteria Pollutants:

SO2, NO2, PM10,

CO

Twice a year (24 hr

average samples) during

construction phase and

annual during operation

phase.

2. Groundwater

(Portability

testing)

Project site Drinking water

parameters as per

IS 10500.

Twice a year

3. Ambient

Noise

Project site dB (A) levels Twice a year (Hourly

day and night time leq

levels) during

construction phase and

every year during

operation phase.

4. Potable water

quality

Project Site As per IS 10500

potable water

standards

Twice a year

Page 69: FORM 1 Aenvironmentclearance.nic.in/writereaddata/Online/...from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project site. Dwarka Sec-11 Metro

“Human Care Medical Charitable Trust” Hospital project

Sector-6, Dwarka, New Delhi FORM 1 A

M/s Human Care Medical Charitable Trust

69

5. Soil quality Project site Organic matter,

C.H., N, Alkalinity,

Acidity, heavy

metals and trace

metal, Alkalinity,

Acidity.

Twice a year

6. Waste

Characterizati

on

Residential Physical and

Chemical

composition

Daily

7. Treated water Outlet of STP BOD, MPN,

coliform count, etc.

Daily

10.3.3 Awareness and Training

Training and human resource development is an important link to achieve sustainable operation of

the facility and environment management.

10.3.4 Environmental Audits and Corrective Action Plans

To assess whether the implemented EMP is adequate, periodic environmental audits will be

conducted by the project proponent’s Environmental division. These audits will be followed by

Correction Action Plan (CAP) to correct various issues identified during the audits.