form 1 aenvironmentclearance.nic.in/writereaddata/online/...from the project site while, new delhi...
TRANSCRIPT
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 1
FORM 1 A CHECK LIST OF ENVIRONMENTAL IMPACTS
SECTION 1- LAND ENVIRONMENT
1.1 Will the existing land use get significantly altered from the project that is consistent with
the surroundings? (Proposed land use must conform to the approved Master
Plan/Development Plan of the area. Change of land use, if any and the statutory approval from
the competent authority are submitted). Attach Maps of (i) site location, (ii) surrounding
features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours)
to appropriate scales. If not available attach only conceptual plans.
The Project site is proposed for hospital as per as per File No-F11(19) 93/1L of DDA in the lease
deed. It is anticipated that the construction activities of the project was and will not have an adverse
effect on the land use activities in the project area. The development of green avenue and other
landscaping will enhance the visual aesthetics of the area.The project site has a good connectivity to
Sector Road 201 which is adjacent to project site. Palam Railway Station is approx. 2.46 km (SE)
from the project Site while, New Delhi Railway station is approx. 15.03 km (NE) from the project
site. Dwarka Sec-11 Metro station is 2 km (SW) from the project site. Indira Gandhi International
Airport is approx. 3.30 km (SSE) from the project site.
The Latitude and Longitude of the project is 28°35'42.22"N, 77°04'09.01"E.
1.2 List out all the major project requirements in terms of the land area, built up area,
water consumption, power requirement, connectivity, community facilities, parking needs etc.
LAND REQUIREMENT
The total plot area of the project site is approx. 9,545 m2. The detailed Area Statement of the project
is provided below in Table-1 & 2.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 2
Table-1: Area Detail
Table:2 Built Up Area Detail
Total Built up Area =Total FAR+ Non FAR=30398.294+16555.667=46953.96
Sl
No. Particulars Area (in Sq.m)
1. Total Plot Area 9545 ( or 2.358 acres)
2. Permissible Ground Coverage 4293.12
3. Proposed Ground Coverage 3869.57
4. Permissible FAR 35,793.75
5. Proposed FAR (A) 30,398.29
6 Total Basement Area (B)
3 Nos. (Level 1, 2 & 3)
16,555.67
7 Proposed Green Area (@ 26.08% of plot area) 2488.33
8 Built-up Area (A+B) 46953.96
9 Height of tallest building (till terrace) 36.9 m
S.No Floors Constructed area asper
earlier sanction Total BUA
**Consolidated area for
Tower-I & Tower-II
1 Ground 2799.02 3471.353
2 First 2667.22 3094.955
3 Second 2762.73 3094.955
4 Third 2762.73 3094.955
5 Fourth 1438.33 3166.939
6 Fifth 1438.33 3166.939
7 Sixth 1438.33 2992.507
8 Seventh 1438.33 2920.451
9 Eight 1438.33 2920.451
10 Ninth 2474.789
Total FAR (A) 18183.35 30398.294
Atrium Area 398.219
Ist Basement 4698.94 5814.567
IInd Basement 3528.7 5077.939
IIIrd Basement 3528.7 5264.942
Non FAR (B) 11756.34 16555.667
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 3
WATER REQUIREMENT
The total water requirement for the project will be approx. 445KLD. The water supply will be
provided through the Delhi Jal Board (DJB). The fresh water requirement will be 276 KLD.
Expected wastewater from bed will be treated in modular ETP and Discharge to STP for further
treatment. It is expected that domestic wastewater from the project will be approx. 188 KLD. The
wastewater will be treated in the ETP and STP having total capacity of 350 KLD generating 169
KLD of recoverable water from STP which will be used for HVAC Cooling.
Daily water requirement calculation and water balance diagram in detail are given below
Zero
Discharge
to sewer
sewer
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 4
Solid Waste
Construction
Waste
Construction waste, Broken Bricks,
Waste Plaster
Empty Cement
Bags
Used in re-filling,
raising site level Sold to
agency for
recycling
Excavated Soil
Top soil conserved for
landscaping
POWER REQUIREMENT
The total demand power load requirement for the project will be 3,153.7 kVA which will be
provided by BSES Rajdhani Power Limited. To cater electricity supply during power failure, 3 Nos.
(2*1250 kVA & 1*750 kVA) of DG sets will be installed within the project site. It is envisaged that
operation of DG sets shall be for 6 hours/day. DG sets will be used during power failure only which
will be based on ultra low sulphur diesel (ULSD) fuel. The proposed DG sets will be equipped with
acoustic enclosure to minimize noise generation and adequate stack height for proper dispersion
SOLID WASTE GENERATED
Solid waste generated & expected to generate both during the construction as well as during the
operation phase. The solid waste expected to be generated during the construction phase will
comprise of excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The
following steps are proposed to be followed for the management solid waste:
Construction yards are proposed for storage of construction materials.
Remaining soil shall be utilized for refilling / road work / rising of site level at locations/
selling to outside agency for construction of roads etc.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 5
Solid Waste Management Scheme (Construction Phase)
Arrangements will be made at the site in accordance to Municipal Solid Wastes (Management and
Handling) Rules, 2000 & amended Rules, 2008 and Bio-Medical Waste (Management and
Handling) Rules, 1998.
PARKING FACILITIES
Adequate provision will be kept for car/vehicles parking of the project. The total parking provided
will be 611ECS. Parking Calculation are given below:
As per MoEF Norms:
For Medical Facilities = 190 ECS
As per DDA Norms:
For Public/Semi-Public facilities = 608 ECS
Parking Proposed:
Total Parking proposed = 611 ECS
1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to
the proposed site? (Such as open spaces, community facilities, details of the existing land use
and disturbance to the local ecology).
The project will be a well planned activity will result in organized open spaces and green areas.
About 2,488.33 m2 of the area is earmarked for landscaping. The project will have an overall positive
impact on the existing land use and will not cause any disturbance to the local ecology. Proposed
activity shall have no impact on surroundings rather contribute to the better standards and well being
of the people.
1.4 Will there be any significant land disturbance resulting in erosion, subsidence &
instability? (Detail of soil type slope analysis, vulnerability to subsidence, seismicity etc may be
given).
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 6
There shall be no land disturbance resulting in erosion, subsidence and instability as it is a flat land.
The site falls under the zone IV as per the seismic zone map of India and indicating high damage
risk zone. The proposed project will be earthquake resistant taking into account the latest provisions
of Indian Standards Codes. Soil quality data is shown in the table below:
Soil Quality results
Human Care Medical Trust Hospital Project Sec-6 Dwarka New Delhi
Soil Quality Data (Dec-2014)
project site
1 Texture - Sandy Loam
Sand % 59.2
Silt % 22.1
clay % 18.7
2 pH (1:2) - 7.64
3 Electrical Conductivity (1:2) µmhos/cm 414
4 Cation exchange capacity meq/100 gm 14.4
5 Exchangeable Potassium mg/kg 92
6 Exchangeable Sodium mg/kg 136
7 Exchangeable Calcium mg/kg 2092
8 Exchangeable Magnesium mg/kg 378
9 Sodium Absorption Ratio - 0.72
10 Water Holding Capacity % 25.6
11 Porosity % 37.9
1.5 Will the proposal involve alteration of natural drainage system? (Give details on a
contour map showing the natural drainage near the proposed project site).
No perennial or non-perennial drainage system is found to exist in the project area obstructed by the
project. The surroundings comprise an urbanized stretch and well planned storm water drainage
system will be designed for internal storm water drainage. Thus, no impact on the natural drainage
system is anticipated.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 7
1.6 What are the quantities of earthwork involved in the construction activity-cutting,
filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill
materials from outside the site etc?)
The earthwork has include soil excavation and cutting 72708.516 m3 of the earth has been moved.
The cut and fill material in the project site is nearly at par and hence the need for movement of soil to
and from the proposed site is not anticipated.
1.7 Give details regarding water supply, waste handling etc during the construction
period.
Water requirement has been provided through Tanker. Wastewater generated during the construction
waste has been 3.6 KLD and waste water will be disposed off through soak pits. Waste handling
during the construction phase has done and will be done by the site contractor whose responsibility
lies with collection and storage of construction and demolition waste generated on the site. All
construction wastes generated during construction was used within the site itself for filling the
floors, roads, aggregate for mortar etc. to the extent feasible. Remaining will be sent to the agency
for proper disposal.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 8
Solid Waste
Construction
Waste
Construction waste,
Broken Bricks,
Waste Plaster
Empty Cement
Bags
Used in re-filling,
raising site level
Sold to agency for
recycling
Excavated Soil
Top soil conserved
for landscaping,
Solid Waste Management during Construction Phase
1.8 Will the low lying areas & wetlands get altered? (Provide details of how low lying and
wetlands are getting modified from the proposed activity).
No. The site area is a flat land and the surroundings are characterized by an urbanized stretch. No
low lying areas or wetlands are found in the region.
1.9 Whether construction debris & waste during construction cause health hazard? (Give
quantities of various types of wastes generated during construction including the construction
labor and the means of disposal).
No health hazards are expected during the construction phase. The laborers has been provided with
face masks to minimize dust inhalation.
A significant portion of the construction waste and wood scrap generated has been used on the site.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 9
The quantity of domestic waste generated has been very little, as mostly local laborers has been
employed. However, the wastes generated has been collected and disposed by an authorized agency.
SECTION 2- WATER ENVIRONMENT
2.1 Give the total quantity of water requirement for the proposed project with the
breakup of requirements for various uses. How will the water requirement be met? State the
sources & quantities and furnish a water balance statement.
Calculations for Total Daily Water Demand
The total water requirement for the project will be approx. 445KLD. The water supply will be
provided through the Delhi Jal Board (DJB). The fresh water requirement will be 276 KLD.
Calculation for the project is given below:
Water Requirement:
As per National Building Code 2005 following is the daily water requirement.
Hospital beds : 450 Litres/bed/day
Visitors : 15 Litres/head/day
Staff an attendants : 45 Litres/head/day
C) Daily water requirement:
No. of Beds, 380@450 Litre/bed/day : 1,71,000 Liters/day
Visitors 1250 @ 15 Litres/head/day : 18,750 Litres/day
Staff and attendants 1000
@ 45 Litres/head/day : 45,000 Litres/day
Total Domestic Water Required 2,34,750 Liters/day
Air conditioning makeup water 1350 tonne @ 12 Litres/tonne
for 12 hours per day : 1,94,400 Liters/day
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
10
Horticultural Water 2488.33 m2 @ 5 Litres/sqm =
12441.65 Liters/day Say 15000 Liters/day : 15,000 Liters/day
:
Total water requirement 4,44,150 Liters/day
Say : 4,45,000 Liters/day
D) Sources of water: Two sources of water are considered as under:
1) City Supply from Govt./Local Authority.
2) Recirculation of treated sewerage effluent after treatment for HVAC cooling.
1) City supply will be supplying water to the complex when it is available from the local
authorities considering 100% demand availability of domestic demand.
2) Recirculation of Sewerage + Effluent : 80% of water supply will flow as Sewerage +
Effluent..
Total Sewerage Generation = 0.80 x 235 KL = 188 KL
Proposed STP Capacity =300 KL
Treated sewage : 90% of 188 KL : 0.90 x 188 = 169.2 KL
Flushing Water Requirement:
No. of Beds : 380 x 100 Litre/bed/day : 38,000 Litres/day
Visitors : 1250 x 7.5 Litres/head/day : 9,375 Litres/day
Staff and attendants : 1000 x 15 Litres/head/day : 15,000 Litres/day
Total : 62,375 Liters/day
Say : 63,000 Liters/day
Air conditioning : 1,94,400 Liters/day
Horticultural Water 2488.33 m2 @ 5 Litres/sqm =
12441.65 Liters/day Say 15000 Liters/day : 15,000 Liters/day
: 2,72,400 Litres/day
Total fresh daily water required : 445 KL – 169.2 KL : 275.8 KL
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
11
Water Balance Diagram
Waste Water Generation & Treatment
During operation phase, It is expected that the project will generate approx. 188 KLD of
wastewater including treated effluent comes from ETP. The wastewater will be treated in the ETP
& STP having total capacity of 350 KLD provided within the premises generating 169 KLD of
recoverable water which will be used for HVAC Cooling.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
12
2.2 What is the quality of water required, in case, the supply is not from a municipal
source? (Provide physical, chemical, Biological characteristics with class of water quality).
The agency for supply of water will be DJB. The quality of water confirm to the desirable drinking
water standards as per IS 10500 and Manual on Water Supply and Treatment by the Central Public
Health and Environmental Engineering Organization (CPHEEO).
2.3 How much of water requirement can be met from the recycling of treated wastewater?
(Give the details of quantities, sources and usage)
The total treated wastewater generated will be approx. 188 KLD. The treated recovered water will be
169 KLD which will used for HVAC cooling.
2.4 Will there be diversion of water from other users? (Please assess the impacts of the
project on other existing uses and quantities of consumption).
No. There will not be any diversion of water from other users. Rise in water demand is a local
phenomenon but the project will only involve spatial shifting of water demand within a region.
2.5 What is the incremental pollution load from wastewater generated from the proposed
activity? (Give details of the quantities and composition of wastewater generated from the
proposed activity)
Approximately 188 KLD of a wastewater will be generated during the operational phase. This
wastewater generated will be treated in well-designed ETP and Sewage Treatment Plant having
capacity of 350 KLD and will be recycled as mentioned in the water balance diagram above within
the project premises.
2.6 Give details of the water requirements met from water harvesting? Furnish details of
the facilities created.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
13
The storm water disposal system for the premises shall be self-sufficient to avoid any
collection/stagnation and flooding of water. The amount of storm water run-off depends upon
many factors such as intensity and duration of precipitation, characteristics of the tributary area
and the time required for such flow to reach the drains. The drains shall be located near the
carriage way along either side of the roads. Taking the advantage of road camber, the rainfall run
off from roads shall flow towards the drains. Storm water from various buildings shall be
connected to adjacent drain by a pipe through catch basins. Therefore, it has been calculated to
provide 3 rainwater harvesting pits at selected locations, which will catch the maximum run-off
from the area.
1) Since the existing topography is congenial to surface disposal, a network of storm water
pipe drains is planned adjacent to roads. All building roof water will be brought down
through rain water pipes.
2) Proposed storm water system consists of pipe drain, catch basins and seepage pits at
regular intervals for rain water harvesting and ground water recharging.
3) The peak hourly rainfall of 35 mm/hr shall be considered for designing the storm water
drainage system.
Rain water harvesting has been catered to and designed as per the guideline of CGWA. Peak
hourly rainfall has been considered as 35 mm/hr. The diameter & depth of recharge pit will be 6
m x 3 m x 2.5 m will be constructed for recharging the water. Inside the recharge pit, a recharge
bore will be constructed having adequate diameter depth. At the bottom of the recharge well, a
filter media is provided to avoid choking of the recharge bore. Design specifications of the rain
water harvesting plan are as follows:
Catchments/roofs would be accessible for regular cleaning.
The roof will have smooth, hard and dense surface which is less likely to be damaged
allowing release of material into the water. Roof painting has been avoided since most
paints contain toxic substances and may peel off.
All gutter ends will be fitted with a wire mesh screen and a first flush device would be
installed. Most of the debris carried by the water from the rooftop like leaves, plastic bags
and paper pieces will get arrested by the mesh at the terrace outlet and to prevent
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
14
contamination by ensuring that the runoff from the first 10-20 minutes of rainfall is
flushed off.
No sewage or wastewater would be admitted into the system.
No wastewater from areas likely to have oil, grease, or other pollutants has been
connected to the system.
Calculations for storm water load
Roof-top area = Ground Coverage = 3869.57 m2 Green Area = 2,488.33 m
2
Total plot area = 9,545 m2
Paved Area = Total Plot Area – (Roof-top Area + Green Area)
= 9,545 – (3869.57 + 2488.33)
= 3187.1m2
Runoff Load
Roof-top Area = 3869.57 × 0.035 × 0.8
= 108.34 m3/hr
Green Area = 2488.33 × 0.035 × 0.1
= 8.71 m3/hr
Paved Area = 3187.1× 0.035 × 0.75
= 83.66m3/hr
Total Runoff Load = 108.34 + 8.71 + 83.66 m3/hr
= 200.71 say 201 m3/hr
Taking 15 minutes Retention Time, Total volume of storm water = 201/4
= 50.25 m3
Taking the effective size of a Rain Water Harvesting pit = l x b x h = 6 x 3 x 2.5 = 45 m3. Hence
Rain Water Harvesting pit required = 50.25/45 = 1.12 say 1 pit
3 Nos Rain Water Harvesting pits have been proposed for artificial rain water recharge within
the project premises.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
15
2.7 What would be the impact of the land use changes occurring due to the proposed
project on the runoff characteristics (quantitative as well as qualitative) of the area in the post
construction phase on a long term basis? Would it aggravate the problems of flooding or water
logging in any way?
The project will include paved areas and thus the runoff from the project is expected to increase due
to reduced infiltration. However, the increased runoff will not cause flooding or water logging as a
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
16
well designed storm water drainage will be provided. The runoff will finally be collected into
rainwater harvesting pits for groundwater recharging. The quality of the runoff is expected to
improve due to paved areas.
2.8 What are the impacts of the proposal on the ground water? (will there be tapping of
ground water; give the details of ground water table, recharging capacity and approvals
obtained from competent authority, if any) .
Water demand will be fulfilled by Delhi Jal Board (DJB). Hence, no adverse impact is expected,
and efforts will be made to recharge the aquifers using 3 rain water harvesting pit of 6m x 3m x2.5m
dimension proposed in the project. Ground water level is 30 m below ground level.
2.9 What precautions measures have been proposed to check the surface run-off, as well
as uncontrolled flow of water into any water body?
Adequate management measures are suggested to protect the water quality during construction
phase. Excavation during monsoon season has been avoided. Care has been taken to avoid soil
erosion. Community toilets have been constructed on the site during construction phase and the
wastewater has been channelized to the septic tank in order to prevent wastewater from entering the
water bodies. Any area with loose debris within the site shall be planted.
To prevent surface and ground water contamination by oil/grease, leak proof containers has been
used for storage and transportation of oil/grease. The floors of oil/grease handling area has been kept
effectively impervious. Collection and settling of storm water, prohibition of equipment wash
downs, and prevention of soil loss and toxic release from the construction site has been adhered to
minimize water pollution.
2.10 How is the storm water from within the site managed? (State the provisions made to avoid
flooding of the area, details of the drainage facilities provided along with a site layout
indication contour levels).
Most of the storm water produced on site will be harvested for ground water recharge. Thus proper
management of this resource is must to ensure that it is free of contamination. A detailed Storm
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
17
Water Management Plan will be developed which will consider the sources of storm water. The plan
will incorporate best management practices which will include the following:
Regular inspection and cleaning of storm drains.
Installation of clarifiers or Oil/Water separators system of adequate capacity around
parking areas and garages as per requirement.
Cover waste storage areas.
Avoid application of pesticides and herbicides before wet season.
Conducting routine inspections to ensure cleanliness.
Preparation of spill response plans, particularly for fuel and oil storage areas.
Provision of silt traps in storm water drains.
Good housekeeping in the above areas.
2.11 Will the deployment of construction laborers particularly in the peak period lead to
unsanitary conditions around the project site (Justify with proper explanation).
No, mostly local laborers have been employed during the construction phase and thus a negligible
quantity of waste has been generated. Mobile Common toilet has been provided within the premises.
2.12 What on-site facilities are provided for the collection, treatment & safe disposal of
sewage? (Give details of the quantities of wastewater generation, treatment capacities with
technology & facilities for recycling and disposal).
Approximately 188 KLD of a wastewater will be generated during the operational phase. This
wastewater generated will be treated in well-designed ETP and Sewage Treatment Plant having
capacity of 350 KLD and will be recycled as mentioned in the water balance diagram above within
the project premises.
An external sewage network will collect the sewage from all units, and flow by gravity to the
proposed sewage treatment plant.
Following are the benefits of providing the Sewage Treatment Plant in the present circumstances:
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
18
Reduced net daily water requirements, source for Horticultural purposes by utilization of
the treated wastewater.
Reduced dependence on the public utilities for water supply and sewerage systems.
Sludge generated from the Sewage Treatment Plant will be rich in organic content and an
excellent fertilizer for horticultural purposes.
Final discharge characteristics
(a) pH : 6.5 to 7.5
(b) Oil & Grease : < 10 mg/l
(c) B.O.D. : < 20 mg/l
(d) C.O.D. : < 30 mg/l
(e) Total suspended solids : <10mg/l
SBR TECHNOLOGY
Hospital generally has operation theatre, laboratories, etc., from which wastewater with chemicals
/ blood will generate. If this waste water is directly mixed with the domestic sewage, it interferes
with the sewage treatment process. It is therefore necessary to pre treat this effluent before
discharge into sewage equalization tank. Sludge from this ETP is not suitable for using as a
manure. Therefore it is disposed off separately.
Sewer System
The alignment and slope of the sewer line will follow the road network, drains or natural ground
surface and will be connected to the trunk sewers. The discharge point will be a treatment plant, a
pumping station, a water course or an intercepting sewer. Pumping stations would be provided at
places where the natural slope of the terrain is insufficient to permit gravity flow or the cost of
excavation is uneconomical to do the same.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
19
Schematic Diagram of STP
2.13 Give details of dual plumbing system if treated waste used for flushing of toilets or any
other use.
Dual plumbing system that utilizes separate piping systems for freshwater and recycled wastewater
will be adopted for the proposed project. The recycled water system shall utilize this treated
wastewater and serve 169 KLD for HVAC cooling.
SECTION 3-VEGETATION
3.1 Is there any threat of the project to the biodiversity? (Give a description of the local
ecosystem with its unique features, if any).
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
20
No, there will not be any threat of the project to the biodiversity. All the parks/forests etc are far
away from the site i.e Pusa Hill Forest- approx. 7.49 km. in ENE direction, Aravali Biodiversity
Park- approx. 8.59 km. in East direction, & Mitraon Forest- approx. 12.36 km. in SE direction.
3.2 Will the construction involve extensive clearing or modification of vegetation? (Provide
a detailed account of the trees & vegetation affected by the project).
No. The site comprises of 2488.33 m2 landscape of open land area provided and does not support
any ecologically threatened vegetation.
3.3 What are the measures proposed to be taken to minimize the likely impacts on
important site – features (Give details of proposal for tree plantation, landscaping creation of
water bodies etc along with a layout plan to an appropriate scale?)
Green belt will be developed along the periphery of the project premises. 2,488.33m2 of open area
will be developed as green belt and organized green spaces. Landscape plan has been attached.
SECTION 4-FAUNA
4.1 Is there likely to be any displacement of fauna both terrestrial and aquatic or creation
of barriers for their movement? Provide the details.
No. The existing land use around the proposed site is urban and does not provide a habitat for wild
species. A few species of butterfly, avifauna and reptiles were recorded during the course of survey,
which are common and found abundantly in this region. The proposed multilayered peripheral
greenbelt will provide an excellent habitat for the native fauna.
4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
21
The project will not have any direct or indirect impacts on the avifauna of the area. However,
planting of trees in the proposed greenbelt will be an attraction to the local bird population which
will provide shelter and niche for the birds
4.3 Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on
fauna.
Not applicable
SECTION 5-AIR ENVIRONMENT
5.1 Will the project increase atmospheric concentration of gases & result in heat islands?
(Give details of background air quality levels with predicted values based on dispersion models
taking into account the increased traffic generation as a result of the proposed construction).
Negligible amount of pollutants will be emitted due to the increase in vehicles from the project and
from the DG sets. Since proponent is going to develop sufficient green belts, it will help
significantly to control air pollution.
The site will not lead to any heat islands, since the proponent will develop greenbelts and green
covers in the site. Air monitoring carried out during the environmental assessment is shown in the
table below:
Ambient Air Quality results
Human Care Medical trust Hospital Project sec-6 Dwarka New Delhi
Ambient Air Quality Data Location: AQ1(Project site)
S.No Date PM2.5,µg/m3 PM10,µg/m3 SO2 µg/m3 , NO2,µg/m3 CO, µg/m3
Gravimetric IS:5182:Pt-23 IS:5182:Pt-2 IS:5182:Pt-6 IS:5182:Pt-10
1 02.12.2014 94.6 165.4 10.1 34.2 1830
2 04.12.2014 111.2 171.2 12.1 35.4 2070
3 09.12.2014 100.7 190.2 11.2 30.7 1790
4 12.12.2014 98.9 236.5 13.4 37.1 2010
5 15.12.2014 111.4 225.5 9.9 41.0 1940
6 20.12.2014 104.6 194.1 9.6 31.6 1820
7 24.12.2014 115.9 202.5 9.7 32.2 1990
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
22
8 28.12.2014 127.5 187.5 10.9 34.3 2220
Min 94.6 165.4 9.6 30.7 1790
Max 127.5 236.5 13.4 41.0 2220
Average 108.1 196.6 10.9 34.6 1959
98 Percentile 125.9 235.0 13.2 40.5 2199
NAAQS (For 24 hrly
monitoring except CO)CO
For one Hr
60 100 80 80 4000
Fugitive dust in the main pollutant envisaged from different construction activity that shall be
prevented by water spraying & screening the construction activity with the help of tarpaulin. The
other important source of pollution is D.G sets which will be used at the tune of power failure & the
emission like PM10, NOx, SO2, CO will be well within the prescribed limits. The total ground level
concentrations have been assessed with predicted incremental values based on dispersion model
tanking into the account of increased traffic load, which are within the prescribed limit.
5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous
gases? Give details in relation to all the meteorological parameters.
Prediction of Impacts
Vehicular emissions and DG sets emission will be major sources of air pollution from building
construction projects. During the post construction phase, cars, scooter/motorcycle will be owned
by the population of such project. Ground Level Concentration of pollutants (as added by the
project) will depend upon the following:
Emission of pollutants from additional traffic on the roads due to the project.
Meteorological conditions.
Emission sources from D.G. Sets.
PM, NO2, SO2 and CO will be the main pollutants of primary concern released from traffic
movement and DG sets. Assuming that under cross wind condition perpendicular to the road, the
dispersion of vehicular emissions would be confined within limited distance from the road and
concentration will decrease with the increase in distance from road. It was anticipated that the
contribution of vehicular emissions from the exhaust in ambient air quality will be marginal as
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
23
Pollution under Control (PUC) Certified vehicles and branded make operated vehicle with low
sulphur diesel will be used. Ground Level Concentration (GLC) of pollutants is found to be well
within the stipulated National Ambient Air Quality Standards due to traffic movement and
vehicles used inside the premises. DG sets will be main source of Air Pollution in the project.
CPCB/ MoEF approved USEPA dispersion model -ISCST3 was used for prediction of impacts
caused by DG sets. Stack & emission data was used as per design value provided by standard
make and stipulated standards. Other primary data used as input for model were hourly
meteorological data of Wind speed & direction, temperature, cloud amount and mixing height.
Mixing height used in the model was taken from secondary data source “Atlas of Hourly Mixing
Height Assimilative Capacity of Atmosphere in India published in 2008 by IMD, Delhi”. Hourly
meteorological monitored at site during study period data was compared with long term data
available from the nearest India Meteorological station or any other authorized source/Govt.
agencies.
There was provision of 3no. of DG sets of total capacity 3,250 KVA (2X 1250 ,1X750)for power
back up in the Existing phase of residential plotted colony.
This will cause emission of PM, SO2, NO2 and CO in the Ambient Air Quality. Therefore,
incremental load in the ambient air environment will be found to be very low as given in the
report. An adequate stack height of D.G. sets will be provided as per the stipulated guidelines of
Central Pollution Control Board (CPCB)/ National Building Code Manual to facilitate proper
dispersion of pollutants and to minimize the impact on Ambient Air Quality under the influence
of local meteorology.
Meteorology - Hourly Meteorological data of wind speed & direction, temperature, cloud amount
and rainfall were monitored at site for 1month for the dispersion model. Wind rose was prepared
in sixteen directions as per standards. It was observed that westerly were prevalent wind during
the study period.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
24
WRPLOT View - Lakes Environmental Software
PROJECT NO.:
Human care
DATE:
1/13/2015
MODELER:
COMPANY NAME:
COMMENTS:WIND ROSE PLOT:
Human care
NORTH
SOUTH
WEST EAST
7%
14%
21%
28%
35%DATA PERIOD:
Start Date: 12/1/2014 - 00:00End Date: 12/31/2014 - 23:00
WIND SPEED
(m/s)
>= 11.1
8.8 - 11.1
5.7 - 8.8
3.6 - 5.7
2.1 - 3.6
0.5 - 2.1
Calms: 0.00%
AVG. WIND SPEED:
2.60 m/s
CALM WINDS:
0.00%
TOTAL COUNT:
744 hrs.
DISPLAY:
Wind SpeedDirection (blowing from)
Wind rose diagram
Model details and Frame work of Computation:
The predictions for air quality during operation phase were carried using CPCB/MoEF approved
“USEPA, Industrial Source Complex (Version - ISCST3)” Dispersion model developed by the
US Environmental Protection Agency (USEPA) for prediction of pollutants dispersion from
single or multiple point sources using emission and hourly meteorological data of the study
period. Assumptions used in the model were as follows:
The plume rise is limited to that of the mixing layer as published by IMD in the
Catalogue of Atlas of Mixing Heights in India for the site
Stack down-wash is not considered.
Flat terrain is used for computations;
It is assumed that the pollutants do not undergo any physico-chemical transformation.
Chemical and scavenging process occurred in the atmosphere in the pollutants released at
the stack exit is not considered.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
25
Prediction is based on single/multiple point sources, pollution released at stack exit and
dispersed on the ground under influence of local meteorological conditions during the
season.
ISCST3 dispersion model was used to predict GLC caused by a different point source ( 42.9as
highest stacks) at each receptor of 41 m x 41 m of grid network covering total area of 2000 m x
2000m around the proposed source with stack & emission values and 1-hourly meteorological
data. It was observed that SO2, NO2, Co and PM were significant pollutants released from the
fuel of the D.G. sets. Emission of PM, CO and SO2 were found insignificant with low values
compared to NO2. In this project, NO2 was the worst pollutant released into the atmosphere
(Table 8) with high emission value.
Stack and Emission Details
Note:-DG set will be operated during power failure for maximum 6-Hours.
24-h GLC were predicted for SO2, NO2, CO and PM but isopleth of the worst pollutant NO2 is
only presented in the report as GLC of other pollutants were low under similar meteorological
conditions.
Discussion of Results
ISCST3 - Dispersion model was used to predict GLC of all pollutants; SO2, NO2, CO and PM
with stack & emission and hourly meteorological data. 24-hours average maximum Incremental
GLC of NO2 was to be 2.95 µg/m3 occurred at (-600m, 600m) from the DG sets fitted with
chimneys of various height and. It was found that GLC of NO2 was less than the permissible limit
of 80µg/m3
(as per CPCB guidelines) under worst meteorological condition with meteorological
data monitored on site.
Stac
k
No.
DG set
Capacity
(kVA)
Stack & Flue details Pollutants Emission
Heig
ht
(m)
velocit
y
(m/s)
Temp
(C)
Diamete
r (m)
NO2
(g/s)
SO2
(g/s)
PM
(g/s)
CO
(g/s)
1. 2 x 1250
KVA
41
25
809.0 0.48 0.5 0.09 0.03 0.06
2. 1X750
KVA
41 25
773 0.33 0.3 0.04 0.01 0.1
Total Emission (from DG set capacity 3,250KVA) in
g/s 0.8 0.13 0.04 0.16
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
26
Meteorological data for the 24-hour average maximum predicted Concentration under
worst meteorological condition
2014 12 14 1 135 5.1 288 6 50 50
2014 12 14 2 112.5 4.1 288 6 50 50
2014 12 14 3 135 3.1 288 6 50 50
2014 12 14 4 90 3.1 287 6 50 50
2014 12 14 5 112.5 5.1 287 6 50 50
2014 12 14 6 135 5.7 287 6 50 50
2014 12 14 7 135 4.6 287 5 50 50
2014 12 14 8 135 4.1 287 4 60 60
2014 12 14 9 135 3.1 287 3 100 100
2014 12 14 10 135 3.1 287 3 150 150
2014 12 14 11 135 3.6 287 3 300 300
2014 12 14 12 135 3.6 288 3 500 500
2014 12 14 13 157.5 3.6 288 3 700 700
2014 12 14 14 135 2.6 288 3 900 900
2014 12 14 15 157.5 2.1 288 3 1000 1000
2014 12 14 16 135 2.1 288 3 1200 1200
2014 12 14 17 135 2.6 288 4 800 800
2014 12 14 18 112.5 2.1 288 5 600 600
2014 12 14 19 135 2.1 288 6 400 400
2014 12 14 20 112.5 2.6 288 6 300 300
2014 12 14 21 112.5 1.5 288 6 200 200
2014 12 14 22 67.5 3.1 288 6 150 150
2014 12 14 23 67.5 4.1 286 6 100 100
2014 12 14 24 67.5 4.6 286 6 50 50
Spatial distribution of NO2 is shown here below in iso-pleth figure. It was observed that GLC
closed to the proposed source will be not significant due to high stack attached with DG sets. 24-h
maximum incremental GLC was 2.95µg/m3 occurred at the distance (-600,600) West of the
project site.
Conclusion
Maximum Incremental GLC of NO2 was 2.95µg/m3 due to DG sets in the project. High to
moderate wind speed and stack of various heights facilitates dispersion at the distance of (-
600,600)m, West under the influence of local meteorology. Low GLC of pollutants was predicted
due to high Stack height and limited DG sets running hours. Predicted GLC of all pollutants are
given here below:
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
27
Predicted GLC of all pollutants
S.No. Pollutants Maximum Incremental
GLC (µg/m3)
Distance of occurrence
1 NO2 2.95 -600m, 600 West
Spatial distribution of 24-hours average NO2 maximum incremental GLC (2.95 µg/m3) at (- 600m, 600m)
West.
Mitigation Measures: The project proponent will develop a green belt inside the premises of the
project site and along the internal road, which will work as barrier for the movement of pollutants
and help in pollution control.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
28
5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of the
present level of transport infrastructure and measures proposed for improvement including
the traffic management at the entry and exit to the project site.
Adequate provision will be made for car/vehicle parking at the project site. There shall also be
adequate parking provisions for visitors so as not to disturb the traffic and allow smooth movement
at the site.
As per MoEF Norms:
For Medical Facilities = 190 ECS
As per DDA Norms:
For Public/Semi-Public facilities = 608 ECS
Parking Proposed: = 611 ECS
5.4 Provide details of the movement patterns with internal roads, bicycle tracks,
pedestrian pathways, footpaths etc, with areas under each category.
Internal roads of 06 m width, footpaths/pedestrian pathways have been well planned for the project.
5.5 Will there be significant increase in traffic noise & vibrations? Give details of the
sources and the measures proposed for mitigation of the above.
No significant impact of noise has been anticipated within and outside of the project site due to
provision of wide roads for smooth flow of traffic and greenbelt along the roads. Noise, due to the
traffic, within site, will result in a marginal increase in the noise levels, which will cause slight
increase in noise level.
5.6 What will be the impact of D.G. sets and other equipment on noise levels and vibration
in ambient air quality around the project site? Provide details.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
29
During operation, vehicular movement and operation of DG sets are the major sources of noise
pollution. But both these activities- DG set and vehicular movement will not have any significant
impact on the people residing in the area. Since DG set will not be operational continuously and
moreover it will be placed away from settlements and will be enclosed with suitable acoustic
enclosures, hence no or minimal impact will be anticipated. It is envisaged that the movement of the
motor vehicles will be restricted to designated carriageways only.
Noise and Vibration Control Measures for DG sets:
• DG sets will be installed with suitable acoustic enclosures to minimize the impact on
ambient noise.
• All DG sets will be mounted on vibration isolator pads. Hence the impacts of noise and
vibration will be insignificant.
• Adequate exhaust mufflers will be provided as per norms to limit the noise.
SECTION 6-AESTHETICS
6.1 Will the proposed construction in any way result in the obstruction of a view, scenic
amenity or landscapes? Are these considerations taken into account by the proponents?
The site lies in an urbanized settlement and is well planned. Thus, no obstruction of view or scenic
beauty or landscape is anticipated. Furthermore, the construction has been planned in such a way that
the organized open spaces and landscaped areas will render the plot aesthetically appealing.
6.2 Will there be any adverse impacts from new constructions on the existing structures?
What are the considerations taken into account?
Being a building and construction project, it has no impact on existing structures.
6.3. Whether there are any local considerations of urban form & urban design influencing
the design criteria? They may be explicitly spelt out.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
30
The project will strictly follow the Area Building Regulation of NBC. All norms on Ground
Coverage, FAR, Height, Setbacks, Fire Safety Requirements, Structural Design and other parameters
will be strictly adhered to.
6.4 Are there any anthropological or archaeological sites or artifacts nearby? State if any
other significant features in the vicinity of the proposed site have been considered?
No anthropological or archaeological sites or artifacts are found near the site area. The
archeological monuments of historical significance are far from the project site, hence there will
be no impacts on these monuments.
SECTION 7-SOCIO-ECONOMIC ASPECTS
7.1 Will the proposal result in any changes to the demographic structure of local
population? Provide the details.
No such changes anticipated.
Construction phase: Since local labourers has been engaged during construction phase, alteration to
the existing demographic profile of the area has not been anticipated.
Operation phase: The changing demography in the area is another impact that needs attention. The
project will mainly lead to spatial redistribution of local population and hence no considerable influx
of population is envisaged owing to the project.
7.2 Give details of the existing social infrastructure around the proposed project.
Being an area of Dwarka, New Delhi, the project site is adequately equipped with all essential
facilities. JM International School adjacent to North direction, Bensups Hospital-2.45km in West
direction, Shiv Mandir -1km in NE and Vardhman mall in 1.29km in South .
7.3 Will the project cause adverse effects on local communities, disturbance to sacred sites
or other cultural values? What are the safeguards proposed?
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
31
The impact can be divided into two phases; a) Construction phase and; b) Operation phase, i.e.
medical facility starts in the Hospital. Based on the nature and type of impacts, the assessment has
been divided into three category i.e. positive, negative and negligible impacts. Positive impacts
include job creation, preservation of environment and benefits to local population by providing
medical facilities and through job opportunities. Long-term impacts include aspects such as
demography and aesthetics..
CONSTRUCTION PHASE
Positive Impacts
Job opportunity: During the consultation process, the locals raised question about job opportunities
related to supervisory positions during construction work and operation phase. Construction phase
has generate jobs that will be related to unskilled, semi skilled as well as skilled labor category in
addition to various specialist positions. As far as construction labor has been concerned, they has
been from surrounding areas in proximity to the construction site. Therefore, the construction phase
will be likely to have positive economic impacts. There will be also likelihood for small shops and
tea stalls to come up near the construction site to cater the demands of the construction workers,
leading to indirect economic benefit to the locals.
Appreciation in Land Value: The development of Hospital Project will be likely to cause
appreciation of real estate prices in the nearby areas. Locals with any holdings in neighboring areas
will be likely to benefit economically.
Significant Impacts
Traffic and Transport: With this Human Care medical charitable trust, the traffic in this area will
increase, particularly during the operation phase. Increase in traffic will be managed by adopting
traffic management plan. However the probability of inconvenience faced due to the movement of
trucks during construction phase has been negligible, since the trucks have been allowed to transport
construction materials during night and non-peak hours. The traffic study and management measures
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
32
suggested in the environment management plan will further reduce the negative impacts of the
traffic increment during the operation phase.
Minor Impacts
Labor Population: Labours were & will be hired from local areas. Hence no impact on local
infrastructure is envisaged.
Demography: Immigration of certain number of work force from the surroundings cannot be
avoided during the construction phase. The movement of labor to this area is a temporary
phenomenon. It is not likely to alter the existing demographic profile of the area.
Impact on Historical, Archeological and Architectural Sites: There are no historical or
archeological monuments of significance within the project area and hence no negative impact in
this regard is anticipated.
OPERATION PHASE
Positive Impacts
Job Opportunity: Employment opportunities will be increased, such as jobs for doctors, nurses and
other hospital staff will be generated with the operation of the Hospital.
Economic Growth: This project will increase the economic activities around the area, creating
avenues for direct/indirect employment in the post project period. People will like get treatment in
the Hospital. Expenditure incurred by the patients will boost local economy in the region. Business
like movie theatres, amusement parks, clubs and shopping malls around the project site will get
enhanced.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
33
Impacts on accessing utilities: Utilities include water supply, electricity and sewage facilities.
Water will be required for construction and even more during operation phase. Water needed during
construction phase will be through Tankers from local authorized sources supply system.
DJB will provide water during operation phase. It is anticipated that Hospital Project will ask
Authorities to make necessary arrangements to confirm the supply of water, electricity and other
utilities, so as to satisfy the increased demands if any.
SAFEGUARDS
The social management plan has been designed to take proactive steps and at the same time adoption
of best practices, which are sensitive to the socio-cultural settings of the region.
a. Income Generation Opportunity
Locals will be given preferences for jobs created after commissioning of the project.
The main principle of employment is outlined below:
Employment strategy will provide for preferential employment during operation Phase.
General recruitment procedures will be transparent, public and open to all.
Recruitment procedures will be publicized at locally prominent locations in advance.
There will be no discrimination on basis of gender, caste or other factors.
b. Improved Working Conditions
The project has been provide safe working conditions for the labor and other workers employed at
the facility during construction and hospital staff during operation phase.
Infrastructure Development
Infrastructure is already developed.
c. Traffic Management
A traffic plan has been adopted to minimize traffic flow interference from construction activities and
obstructions are minimized through-traffic lanes.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
34
d. Waste Management
No open litter burning will be done during infrastructure improvements. Proper segregation of waste
will be done.
SECTION 8-BUILDING MATERIALS
8.1 May involve the use of building materials with high embodied energy. Are the
construction materials produced with energy efficient processes? (Give details of energy
conservation measures in the selection of building materials and their energy efficiency)
For the purpose of paved path, sun dried pavers has been used instead of baked pavers as they are
manufactured from energy efficient processes. Fly ash bricks were used & will be used.
8.2 Transport and handling of materials during construction may results in pollution,
noise and public nuisance. What measures are taken to minimize the impacts?
Mitigation Measures for Air Pollution during Construction Stage:
• Construction materials has been suitably covered with tarpaulin cover etc during transportation.
• Water sprinkling has been done on haul roads where dust generation is anticipated.
• Raw material storage and handling yard has been enclosed from all sides.
• To minimize the occupational health hazard, proper personal protective gears i.e. mask has been
provided to the workers working in the dust prone areas.
Mitigation Measures for Noise Pollution during Construction Stage:
• Administrative as well as engineering control of noise has been implemented.
• Isolation of noise generation sources and temporal differentiation of noise generating activities has
ensure minimum noise at receiver’s end.
• To prevent any occupational hazard, earmuff / earplug has been given to the workers working
around construction plant & machinery emitting high noise levels.
• Use of such plant or machinery shall not be allowed during night time. Careful planning of
machinery operation and scheduling of operations has been done to minimise such impact.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
35
8.3 Are recycled materials used in roads and structures? State the extent of savings
achieved?
Yes. Recycled materials will be bought from outside sources and will be used as fillers in base and
sub-base of the carriageway, footpaths pavements or pedestrian way, as needed.
8.4 Give detail of the methods of collection, segregation & disposal of the garbage
generated during the operation phases of the project.
The solid waste of the project will be segregated into biodegradable waste and non-biodegradable.
Biodegradable waste and non biodegradable waste will be collected in separate bins. The recyclable
wastes will be sent off to recyclabers.
As per our project the total estimated Bio-medical waste generation is 380 Kg/day from Hospital
Building which will be handed over to the CPCB approved Biomedical waste handlers for which
tenders will be floated and MoU will be made by the approved vendors.
Collection and Segregation of waste
1. For Hospital waste collection, adequate number of colored bins (Red, Blue, Green and
Black bins are proposed to be provided at the strategic locations of the Hospital area.
2. Microbiological and Biological wastes and solid wastes will be collected in Red bins.
3. Waste sharps and sold wastes will be collected in Blue bins.
4. Discarded medicines, Cytotoxic drugs and chemical wastes will be collected in Black
bins.
5. General waste such as official waste, food waste & garden waste will be collected in
Green bins.
6. Litter bin will also be provided in open areas like parks etc.
Treatment of waste
Bio-Degradable wastes
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
36
1. Bio-degradable waste will be disposed-off through a govt. approved vendor for
decomposition.
2. STP sludge will be proposed to be used for horticultural purposes as manure.
3. Horticultural Waste is proposed to be composted and will be used for gardening purposes.
Recyclable wastes
i. Grass Recycling – The cropped grass will be spread on the green area. It will act as
manure after decomposition.
ii. Recyclable wastes like paper, plastic, metals etc. will be sold off to recyclables.
Disposal
Recyclable and non-recyclable wastes will be disposed through Govt. approved agency.
Hence, the Municipal Solid Waste Management will be conducted as per the guidelines of
Municipal Solid Wastes (Management and Handling) Rules, 2000 and amended Rules, 2008. Bio-
Medical waste will be disposed through the govt. approved vendors for Bio-Medical waste. Bio-
Medical waste management will be conducted as per the Bio-Medical Waste (Management and
Handling) Rules, 1998. AERB/BARC Guidelines will be followed for identification and operation
of any item or disposal of any waste containing or suspected to be containing radioactive
materials. A Solid waste management Scheme is depicted in the figure for the “Human Care
Charitable Hospital”. Hospital Waste generated will be collected in the color coded bins and will
be handed over to the government approved vendor for disposal.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
37
Solid Waste Management Scheme (Operation Phase)
Hospital Waste
Waste sharps and
Solid waste Discarded
medicines,
Cytotoxic drugs and
chemical waste
General waste such
as official waste,
food waste &
garden waste
Microbiological and
Biological wastes,
Soiled wastes, Solid
waste
Red Bins Blue Bins Black Bins Green Bins
Disposed-off by Govt. approved Vendors for
biomedical waste
Biodegradable
Waste
Non-Biodegradable
Waste
Disposed-off by
Govt. approved
Vendors
Disposed-off by
Govt. approved
Vendors
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
38
SECTION 9-ENERGY CONSERVATION
9.1 Give details of the power requirements, source and supply, backup source etc. What is
the energy consumption assumed per square foot of built-up area? How have you tried to
minimize energy consumption?
The total power requirement for the project is 3,153.7 Kw which will be provided by BSES Rajdhani
Power Limited, Delhi. There is a provision of 3 DG sets of total capacity of 3,250 kVA (2*1250
kVA & 1*750 kVA) for power back up . The proposed DG sets will be equipped with acoustic
enclosure to minimize noise generation and adequate stack height for proper dispersion.
To minimize the energy consumption effective measures have been incorporated in following
manners:
• All external lighting shall be BEE star rated.
• All common spaces including street lights (where there is no use of light for reading
purposes), shall be of “LED”.
• A minimum of 50% hot water requirement shall be met by solar water heating systems.
• Integration of automated system to operate electrical equipment as per load requirement to
save energy.
9.2 What type and capacity of power backup do you plan to provide?
There is a provision of 3 DG sets of total capacity of 3,250kVA (2*1250 kVA & 1*750 kVA) for
power back up. The proposed DG sets will be equipped with acoustic enclosure to minimize noise
generation and adequate stack height for proper dispersion.
9.3 What are the characteristics of the glass you plan to use? Provide specifications of its
characteristics related to both short wave and long wave radiation?
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
39
The proposed project will involve uses of clear & tinted glass having U-value of 2.67 to 3.97
W/m2K.
9.4 What passive solar architectural features are being used in the building? Illustrate the
applications made in the proposed project.
Passive solar design refers to use of the sun’s energy for the heating and cooling of living spaces.
Projections, façade elements, DGUs will be provided for sun shading to reduce the heat influx into
the building and thus reduce the air conditioning loads.
9.5 Does the layout of street & building maximize the potential for solar energy devices?
Have you considered the use of street lighting, emergency lighting and solar hot water systems
for use in the building complex? Substantiate with details.
Layout of buildings has been done as per the sun path analysis so that the design cuts off direct
radiations of critical hours which are specific to the orientation. Solar energy will be harnessed to
meet various energy requirements of the project such as:
Hot water requirement.
Street lightening
9.6 Is the shading effectively used to reduce cooling / heating lands? What principles have
been used to maximize the shading of walls on the East and the West and the Roof? How much
energy saving has been effected?
Projection, façade elements, DGUs will be provided to reduce cooling loads. Green area and open
areas will be so spaced that a reduction in temperature is achieved.
9.7 Do the structures use energy-efficient space conditioning, lightening and mechanical
systems? Provide technical details. Provide details of the transformers and motor efficiencies,
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
40
lightening intensity and air conditioning load assumption? Are you using CFC and HCFC free
chillers? Provide specifications.
Yes. The roofs of top floor rooms will be insulated, heat shield paint on wall surfaces such that air
conditioning load is reduced. Well designed building structures will allow natural light to enter.
Measures prescribed in Energy Conservation Building Code 2007 will be adopted to reduce the heat
influx by walls, roofs and openings. Only prescribed quality of glasses will be used.
We are using CFC and HCFC free chillers from Career and using R-134a.
9.8 What are the likely effects of the building activity in altering the micro-climates?
Provide a self assessment on likely impacts of the proposed construction on creation of heat
island & inversion effects?
Heat emissions from the construction may be from the following sources:
Heat absorbed from the paved and concrete structures
Heat generated from equipment/appliances
Heat increase due to increase in the population of the project.
However, the heat generated will not be significant and will be dissipated in the greens and open
areas provided within the project area.
9.9 What are the thermal characteristics of the building envelope? (a) Roof (b) external
walls and (c) fenestration? Give details of the material used and the U value or the R values of
the individual components.
The roof tops of the buildings will be planned with puffing/bricks bat coba for water proofing and
thermal insulation.
External wall-external opening will have regular door, DGU(6-16-8) windows with SKN444 glass.
Regular walls have some cladding/fixture heat shield paints. The ECBC guidelines will be
considered as shown below:
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
41
List of Construction Materials
Type of Construction U Values (in W/m2 deg C)
WALLS:
Bricks:
Plastered both sides-114mm 3.24
Solid, Unplastered-228mm 2.67
Plastered both sides-228mm 2.44
Concrete, ordinary, Dense:
-152mm 3.58
-203mm 3.18
Concrete block, cavity, 250mm (100mm + 50mm), outside rendered, inside plastered
Aerated concrete blocks 1.19
Hollow concrete block, 228mm, single skin outside rendered, inside plastered
Aerated concrete blocks 1.70
Roofs pitched:
Tiles, slates on boarding and felt with plaster
ceiling
1.70
Roofs flat:
Reinforced concrete slab, 100mm, screed 63-
12mm, 3 layers, bituminous felt
3.35
Floors:
Concrete on ground or hardcore fill 1.13
+Grano Terazzo or tile finish 1.13
+Wood block finish 0.85
WINDOWS:
Exposure South, Sheltered:
Single glazing 3.97
Double glazing 6mm space 2.67
9.10 What precautions & safety measures are proposed against fire hazards? Furnish
details of emergency plans.
Firefighting measures shall be adopted as per the guidelines of NBC. External yard hydrants shall be
installed around all buildings in the complex in galvanized steel fire house cabinet (weather proof).
All external yard hydrants shall be at one meter height from finished ground level as per NBC at a
distance of 45 m along the road. External fire hydrants will be located such that no portion of any
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
42
building is more than 45 m from a hydrant and the external hydrants will not be vulnerable to
mechanical or vehicular damage.
9.11 If you are using glass as wall materials, provide details and specifications including
emissivity and thermal characteristics.
The project will be a Hospital project will involve use of glass as wall material. All fenestration with
U-factors, SHGC, or visible light transmittance determined, certified, and labeled in accordance ISO
15099 shall be adopted.
9.12 What is the rate of air infiltration in to the building? Provide details of how you are
mitigating the effects of infiltration.
It will be a air-conditioned Hospital; air infiltration will be kept to required minimum level.
9.13 To what extent the non–conventional energy technologies are utilized in the overall
energy consumption? Provide details of the renewable energy technologies used.
Solar energy will be variedly used as:
Green CFLs/LED will be used in buildings to minimize the energy consumption.
Solar water heating systems will be used to achieve minimum of 50% hot water
requirement.
Green area is provided along with tree plantation which will result in natural air cooling and
will reduce the load on conventional energy sources.
10. ENVIRONMENT MANAGEMENT PLAN
The Environment Management Plan (EMP) will consist of all mitigation measures for each
component of the environment due to the activities increased during the construction, operation and
the entire life cycle to minimize adverse environmental impacts resulting from the activities of the
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
43
project. It will also delineate the environmental monitoring plan for compliance of various
environmental regulations. It will state the steps to be taken in case of emergency such as accidents
at the sites including fire. The detailed EMP for the project is given below.
10.1 Environmental Management Plan
The Environment Management Plan (EMP) is a site specific plan developed to ensure that
the project is implemented in an environmental sustainable manner where all contractors and
subcontractors, including consultants, understand the potential environmental risks arising from the
project and take appropriate actions to properly manage that risk. EMP also ensures that the project
implementation is carried out in accordance with the design by taking appropriate mitigation actions
to reduce adverse environmental impacts during its life cycle. The plan outlines existing and
potential problems that may adversely impact the environment and recommends corrective measures
where required. Also, the plan outlines roles and responsibility of the key personnel and contractors
who will be in charge of the responsibilities to manage the project site.
10.1.1 The EMP is generally
Prepared in accordance with rules and requirements of the MoEF and CPCB/ SPCB
To ensure that the component of facility will be operated in accordance with the design
A process that confirms proper operation through supervision and monitoring
A system that addresses public complaints during construction and operation of the facilities
and
A plan that ensures remedial measures is implemented immediately.
The key benefits of the EMP will offer means of managing its environmental performance thereby
allowing it to contribute to improved environmental quality. The other benefits include cost control
and improved relations with the stakeholders.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
44
EMP includes four major elements:
Commitment & Policy: The management will strive to provide and implement the
Environmental Management Plan that incorporates all issues related to air, water, land
and noise.
Planning: This includes identification of environmental impacts, legal requirements and
setting environmental objectives.
Implementation: This comprises of resources available to the developers, accountability
of contractors, training of operational staff associated with environmental control facilities and
documentation of measures to be taken.
Measurement & Evaluation: This includes monitoring, counteractive actions and record
keeping.
It is suggested that as part of the EMP, a monitoring committee will be formed by comprising of the
site in-charge/coordinator, environmental group representative and project implementation team
representative. The committee’s role will be to ensure proper operation and management of the EMP
including the regulatory compliance.
The components of the environmental management plan, potential impacts arising, out of the project
and remediation measures are summarized below:
Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 45
SUMMARY OF POTENTIAL IMPACTS AND REMEDIAL MEASURES
S.
No.
Environmental
components
Potential
Impacts
Potential
Source of
Impact
Controls Through
EMP & Design
Impact Evaluation Remedial Measures
1 Ground Water
Quality
Ground Water
Contamination
Construction
Phase
Waste
water
generated
from
temporary
labor tents.
Soak Pit has
been provided.
No impact as
majority of labors
has been locally
deployed
Operation
Phase
Dischar
ge from the
project
Proponent will
provide the STP &
ETP to treat the
discharge of
Hospital.
No negative impact
on ground water
quality envisaged.
Not significant.
In an unlikely event of
soil and ground water
contamination.
Remediation measures
shall be implemented.
2. Ground Water
Quantity
Ground Water
Depletion
Construction
Phase
Water
from Private
tankers
NA No significant
impact on ground
water quantity
envisaged.
Operation
Phase
Water will
be supplied
by DJB.
Rain water
harvesting scheme.
Storm water
collection for water
harvesting.
Percolation
well to be
introduced in
landscape plan.
No significant
impact on
surface/ground
water quantity
envisaged.
In an unlikely event of
non-availability of
water supply, water will
be brought using
tankers.
Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 46
Awareness
Campaign to
reduce the water
consumption
3. Surface Water
Quality
Surface water
contamination
Construction
Phase
Surface
runoff from
site during
construction
activity.
Silt traps and
other measures
such as additional
on site diversion
ditches has been
constructed to
control surface run-
off during site
development
No off site impact
envisaged as no
surface water
receiving body is
present in the core
zone.
Operation
Phase
Discharge
of domestic
wastewater to
surface water
body/land.
Wastewater will
be treated in STP
& ETP.
No off site impact
envisaged
There will be no
wastewater to be
discharged into the
surface water body.
4. Air Quality Dust Emissions Construction
Phase
All heavy
construction
activities
Suitable control
measures have
been adopted for
subsiding the SPM
level in the air as
per air pollution
control plan.
Not significant
because dust
generation has been
temporary and
settle fast due to
dust suppression
techniques (wet
scrubbers) used.
During construction
phase the contractor
have been advised to
facilitate masks for the
labors. Water sprinklers
have been used for
suppression of dust
during construction
phase.
Emissions of
PM, SO2, NO2
and CO
Operation
of
construction
equipment
Rapid on-site
construction and
improved
maintenance of
Not significant. Regular monitoring of
emissions and control
measures will be taken
to reduce the emission
Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 47
and vehicles
during site
development.
Runnin
g D.G. sets
(back up)
equipment levels.
5. Noise Environment Construction
Phase
Operation
of
construction
equipment
and vehicle
movements
during site
development.
Running
DG sets (for
power back
up)
Use of equipment
fitted with silencers
Proper
maintenance of
equipment
Provision of
noise shields near
the heavy
construction
operations and
acoustic enclosures
for DG sets
Construction
activity has been
limited to day time
hours only
There are no
sensitive receptors
located within the
vicinity of site.
Use of Personal
Protective Equipment
(PPE) like earmuffs and
earplugs during
construction activities.
Operation
Phase
Noise
from
vehicular
movement
Noise
from DG
sets
operation
Green Belt
Development
Development of
silence zones to
check the traffic
movement
DG set
rooms will be
equipped with
acoustic
enclosures.
No significant
impact due to
suitable width of
Greenbelt.
Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 48
6. Land Environment Soil
contamination
Constructio
n Phase
Disposal
of
construction
debris
Construction
debris has been
collected and
suitably used on
site as per the
solid waste
management plan
for construction
phase
No significant
impact.
Impact has been
local, as waste
generated has
reused for filling
of low lying
areas etc.
Operation
Phase
Dumpin
g of
municipal
solid waste
on land.
Used Oil
generated
from D.G.
sets
Hospital
Waste
It is proposed
that the solid
waste generated
will be managed
by an authorized
agency.
Collection,
segregation,
transportation and
disposal will be
done as per MSW
Management
Rule, 2000 by the
authorized agency
Used oil
generated will be
sold to authorized
recyclers
Hospital
waste will be
collected in the
color coded bags
and will be
handed over to the
Since solid waste
is handled by the
authorized
agency, waste
dumping is not
going to be
allowed. Not
significant.
Negligible
impact.
Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 49
government
approved vendor
for final disposal.
AERB/BAR
C Guidelines will
be followed for
identification and
operation of any
item or disposal of
any waste
containing or
suspected to be
containing
radioactive
materials
7. Biological
Environment (Flora
and Fauna)
Displacement of
Flora and Fauna
on site
Constructio
n Phase
Site
Developme
nt during
construction
Important species
of trees, will be
identified and
marked and will
be merged with
landscape plan
The proposed site
has no vegetation
at present
Operation
Phase
Increase
in green
covered
area
Suitable green
belts will be
developed as per
landscaping plan
in and around the
site using local
flora
Beneficial
impact.
8. Socio-Economic
Environment
Population
displacement
and loss of
income
Constructio
n Phase
Constructio
n activities
leading to
There will
be no relocation.
Project will
provide
employment
No negative
impact.
Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust 50
relocation opportunities to
the local people in
terms of labor
during
construction
Operation
Phase
Site
operation
Service
personnel
(Hospital staff,
securities,
gardeners etc)
during operations
Providing
quality-Integrated
medical facility in
Sec-6, Dwarka,
New Delhi
Public
services (hospital)
Beneficial impact
9. Traffic Pattern Increase of
vehicular traffic
Constructio
n Phase
Heavy
Vehicular
movement
during construction
Heavy Vehicular
movement has
been restricted to
daytime only and
adequate parking
facility will be
provided
No negative
impact
Operation
Phase
Traffic
due to
people
coming to
the hospital.
Vehicular
movement has
been regulated
inside the Hospital
with adequate
roads and parking
lots in the
Hospital.
No major
significant
impact
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
51
10.2 ENVIRONMENT MANAGEMENT PLAN
An environmental management plan (EMP) will be required to mitigate the predicted adverse
environmental impacts during construction and operation phase of the project and these are
discussed in later subsections.
10.2.1 EMP for Air Environment
Construction Phase
To mitigate the impacts of PM2.5 and PM10 during the construction phase of the project, the
following measures have been implemented:
A dust control plan.
Procedural changes to construction activities.
Dust Control Plan
The most cost-effective dust suppressant is water because water is easily available on construction
site. Water can be applied using water trucks, handled sprayers and automatic sprinkler systems.
Furthermore, incoming loads could be covered to avoid loss of material in transport, especially if
material is transported off-site.
Procedural Changes to Construction Activities
Idle time reduction: Construction equipment has been commonly left idle while the operators will
be on break or waiting for the completion of another task. Emission from idle equipment tends to be
high, since catalytic converters cools down, thus reducing the efficiency of hydrocarbon and carbon
monoxide oxidation. Idle control technologies have been comprised of power saving mode, which
automatically off the engine at preset time and reduces emissions, without intervention from the
operators.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
52
Improved Maintenance: Significant emission reductions can be achieved through regular
equipment maintenance. Contractors have been asked to provide maintenance records for their fleet
as part of the contract bid, and at regular intervals throughout the life of the contract. Incentive
provisions will be established to encourage contractors to comply with regular maintenance
requirements.
Operation Phase
To mitigate the impacts of pollutants from DG sets and vehicular traffic during the operational phase
of the Hospital, following measures are recommended for implementation:
DG set emission control measures
Vehicular emission controls and alternatives
Greenbelt development
Diesel Generator Set Emission Control Measures
Adequate stack height will be maintain to disperse the criteria air pollutants generated from the
operation of DG sets to dilute the pollutants concentration within the immediate vicinity. Hence no
additional emission control measures have been suggested.
Vehicle Emission Controls and Alternatives
Use of clean Fuel by vehicles on-site: Low sulphur diesel will be used as clean fuel (if available
locally). This will reduce emissions on-site and in areas from where these vehicles pass.
Footpaths and Pedestrian ways: Adequate footpaths and pedestrian ways will be provided at the site
to encourage non-polluting methods of transportation.
Greenbelt Development
Increased vegetation in the form of greenbelt is one of the preferred methods to mitigate air and
noise pollution. Plants serve as a sink for pollutants, act as a barrier to break the wind speed as well
as allow the dust and other particulates to settle on the leaves. It also helps to reduce the noise level
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
53
at large extent. The following table indicates various species of the greenbelt that can be used to act
as a barrier.
Trees that can be used as Barrier for Air Pollution
List of plants to be planted
S. No. Botanical Name
1 Phoenix dactylifera
2 Mimusops elengi (Maulshri)
3 Ficus religiosa (Peepal)
4 Azadirachta indica (Neem)
5 Antocephalus cadamba (Kadam)
6 Tabebuia argentia (Silver trumpet)
7 Plumeria alba (Champa)
8 Bauhinia (Kaniar)
9 Jacquemotia reclinata
10 Melia azaderach
11 Ficus Religosa(peepal)
12 Bauhinia vareigata (Kachnar)
13 Melia azaderach (Bakain)
10.2.2 EMP FOR NOISE ENVIRONMENT
Construction Phase
To mitigate the impacts of noise from construction equipment during the construction phase on the
site, the following measures have been implemented.
Time of Operation: Noisy construction equipment has not been allowed to use.
Job Rotation and Hearing Protection: Workers employed in high noise areas has been rotated.
Hearing protection such as earplugs/muffs has been provided to those working very close to the
noise generating machinery.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
54
Operation Phase
To mitigate the impacts of noise from diesel generator sets during operational phase, the following
measures will be recommended:
Adoption of Noise emission control technologies.
Greenbelt development.
Noise Emission Control Technologies
It will be ensured that the manufacturer provides acoustic enclosure as an integral part along with the
diesel generators sets. Further, enclosure of the services area with 4 m high wall will reduce noise
levels and ensure that noise is at a permissible limit for occupants of the site and surrounding
receptors.
Greenbelt Development
The name of species of plants to be used as in a greenbelt, to serve as noise breakers are mentioned
in table above.
10.2.3 EMP FOR WATER ENVIRONMENT
Construction Phase
To prevent degradation and to maintain the quality of the water source, adequate control measures
have been proposed. To check the surface run-off as well as uncontrolled flow of water into any
water body check dams with silt basins has been proposed. The following management measures are
suggested to protect the water source has been polluted during the construction phase:
Avoid excavation during monsoon season
Care has been taken to avoid soil erosion
Mobile toilets has been Placed on site during construction phase,
To prevent surface and ground water contamination by oil and grease, leak-proof
Containers have been used for storage and transportation of oil and grease. The floors of
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
55
oil and grease handling area will be kept effectively impervious. Collection and settling of
storm water, prohibition of equipment wash downs and prevention of soil loss and toxic release
from the construction site are necessary measure
to be taken to minimize water pollution
All stacking and loading area has been provided with proper garland drains, equipped
with baffles, to prevent run off from the site, to enter into any water body
Operation Phase
In the operation phase of the project, water conservation and development measures will be taken,
including all possible potential for rain water harvesting. Following measures will be adopted:
Water source development
Minimizing water consumption
Promoting reuse of water after treatment and development of closed loop systems for
different water streams
Water Source Development
Water source development shall be practiced by installation of scientifically designed Rain Water
Harvesting system. Rainwater harvesting promotes self-sufficiency and fosters an appreciation for
water as a resource.
Minimizing Water Consumption
Consumption of fresh water will be minimized by combination of water saving devices and other
domestic water conservation measures. Further, to ensure ongoing water conservation, an awareness
program will be introduced for the hospital staff and patients. The following section discusses the
specific measures, which shall be implemented:
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
56
Domestic and Commercial Usage
Use of water efficient plumbing fixtures (ultra flow toilets and urinals). Water efficient
plumbing fixtures uses less water with no marked reduction in quality and service
Leak detection and repair techniques
Sweep with a broom and pan where possible, rather than hose down for external areas
Meter water usage: Implies measurement and verification methods. Monitoring of water
uses is a precursor for management.
Horticulture
Spray irrigation system shall be used for the lawns and other green area. Spray
irrigation can save 15-40 % of the water, compared with other watering techniques
Plants with similar water requirements shall be grouped on common zones to match
precipitation heads and emitters.
Use of low-angle sprinklers for lawn areas.
Select controllers with adjustable watering schedules and moisture sensors to account
for seasonal variations and calibrate them during commissioning.
Place 3 to 5 inches of mulch on planting beds to minimize evaporation.
Promoting Reuse of Water after Treatment and Development of Closed Loop Systems
To promote reuse of wastewater and development of closed loop system for wastewater segregation.
Two wastewater schemes are suggested, namely:
1) Storm Water Harvesting 2) Waste water recycling.
Waste Water Treatment Scheme
Proponent will treat the wastewater of the project in well designed Sewage Treatment Plant capacity
based on SBR technology and the effluent generated from the Hospital activities will be treated in
the ETP before.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
57
Storm Water Management
Most of the storm water produced on site will be harvested for ground water recharge. Thus proper
management of this resource is a must to ensure that it is free from contamination.
Contamination of Strom Water is possible from the following sources:
Diesel and oil spills in the diesel power generator and fuel storage area
Waste spills in the solid / hazardous waste storage area
Oil spills and leaks in vehicle parking lots
Silts from soil erosion in gardens
Spillage of sludge from sludge drying area of sewage treatment plant
A detailed storm water management plan will be developed which will consider the possible impacts
from above sources. The plan will incorporate best management practices which will include
following:
Regular inspection and cleaning of storm drains
Clarifiers or oil / separators will be installed in all the parking areas. Oil / grease separators
installed around parking areas and garages will be sized according to peak flow guidelines. Both
clarifiers and oil / water separators will be periodically pumped in order to keep discharges within
limits
Covered waste storage areas
Avoid application of pesticides and herbicides before wet season
Secondary containment and dykes in fuel / oil storage facilities
Conducting routine inspection to ensure cleanliness
Provision of slit traps in storm water drains
Good housekeeping in the above areas.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
58
10.2.4 EMP FOR LAND ENVIRONMENT
Construction Phase
The waste generated from construction activity includes construction debris, biomass from land
clearing activities, waste from the temporary make shift tents for the labors and hazardous waste.
Following section discuss the management of each type of waste. Besides waste generation,
management of the topsoil will be an important area for which management measures will be
required.
Construction Debris
Construction debris is bulky and heavy, hence re-utilization and recycling of debris is an important
strategy for management of such waste. As concrete and masonry constitute the majority of waste
generated, recycling of this waste by conversion to aggregate can offer benefits of reduced landfill
space and reduced extraction of raw material for new construction activity. This is particularly
applicable to the project site as the construction is to be completed in a phased manner.
Mixed debris with high gypsum, plaster, shall not be used as fill, as they will be highly susceptible to
contamination, and will be send to designated solid waste landfill site.
Metal scrap from structural steel, piping, concrete reinforcement and sheet metal work shall be
removed from the site by construction contractors. A significant portion of wood scrap will be
reused on site. Recyclable wastes such as plastics, glass fiber insulation, roofing etc shall be sold to
recyclers.
Hazardous waste
Construction sites are sources of many toxic substances such as paints, solvents wood preservatives,
pesticides, adhesives and sealants. Hazardous waste generated during
construction phase shall be stored in sealed containers and disposed off as per the Hazardous Wastes
Management and Handling Act, Amendment Rules (MoEF, 2003).
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
59
Some management practices to be developed are:
Herbicides and pesticide will not be over applied (small-scale applications) and not applied
prior to rain
Paintbrushes and equipment for water and oil based paints shall be cleaned within a
contained area and will not be allowed to contaminate site soils, water courses or drainage
systems
Provision of adequate hazardous waste storage facilities. Hazardous waste collection
containers will be located as per safety norms and designated hazardous waste storage areas
will be away from storm drains or watercourses
Segregation of potentially hazardous waste from non-hazardous construction site
debris
Well labeled all hazardous waste containers with the waste will be stored and the date of
generation
Instruct employees and subcontractors in identification of hazardous and solid waste
Bio- medical waste is the main type of waste generated from hospitals. The waste generated
will be handed over to the government approved vendor for the final disposal of waste.
AERB/BARC Guidelines will be followed for identification and operation of any item or
disposal of any waste containing or suspected to be containing radioactive materials.
Even with careful management, some of these substances will be released into air, soil and water and
many will be hazardous to workers. With these reasons, the best choice is to avoid their use as much
as possible by using low-toxicity substitutes and low VOC (volatile organic compound) materials.
Waste from Temporary Makes Shift Tents for Labors
Wastes generated from temporary make shift labor tents will mainly comprise of household
domestic waste, which will be managed by the contractor of the site. The wastewater generated will
be channelized to the STP provided within the premises.
Top Soil Management
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
60
To minimize disruption of soil and for conservation of top soil, the contractor shall keep the top soil
cover separately and stockpile it. After the construction activity is over, top soil will be utilized for
landscaping activity. Other measures, which will be followed to prevent soil erosion and
contamination include:
Maximize use of organic fertilizer for landscaping and green belt development
To prevent soil contamination by oil/grease, leaf proof containers will be used for storage
and transportation of oil/grease and wash off from the oil/grease handling area shall be drained
through impervious drains and treated appropriately before disposal
Working in a small area at a point of time (phase wise construction)
Construction of erosion prevention troughs/ berms.
Operational Phase
The philosophy of solid waste management at the proposed Hospital will be to encouraging the four
R’s of waste i.e. Reduction, Reuse, Recycling and Recovery (materials & energy). Regular
awareness meetings will be conducted to involve the Hospital staff and patients in the proper
segregation and storage techniques.
The Environmental Management Plan for the solid waste focuses on three major components during
the life cycle of the waste management system i.e., collection and transportation, treatment or
disposal and closure and post-closure care of treatment/disposal facility.
Collection and Transportation
During the collection stage, the solid waste of the proposed project will be segregated into
biodegradable waste and non-biodegradable. Biodegradable waste and non biodegradable waste will
be collected in separate bins. The recyclable wastes will be sent off to recyclabers. Proper guidelines
for segregation, collection and storage will be prepared as per MSW Rules, 2000.
To minimize littering and odour, waste will be stored in well-designed containers/ bins that
will be located at strategic locations to minimize disturbance in traffic flow
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
61
Care will be taken such that the collection vehicles will be well maintained and generate
minimum noise and emissions. During transportation of the waste, it will be covered to avoid
littering.
Disposal
With regards to the disposal/ treatment of waste, the management will take the services of the
authorized agency for waste management and disposal of the same on the project site during its
operational phase.
Bio-Medical waste generated will be approx. 380 kg/day and will be collected in the color coded
bags. The collected waste will be further handed over to the government approved vendor for the
final disposal of hazardous waste.
Detailed waste management program is given in the Conceptual plan, enclosed.
10.2.5 EMP FOR ECOLOGICAL ENVIRONMENT
Construction activity changes the natural environment. But Hospital also creates a built environment
for its patients and staff. The project requires the implementation of following choices exclusively or
in combination.
Construction Stage
Restriction of construction activities to defined project areas, which will be ecologically
sensitive
Restrictions on location of temporary labor tents and offices for project staff near the
project area to avoid human induced secondary additional impacts on the flora and fauna species
Cutting and uprooting of trees or small trees if present in and around the project site for
cooking, burning or heating purposes by the labors will be prohibited and suitable alternatives for
this purpose will be made.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
62
Along with the construction work, the peripheral green belt will be developed with
suggested native plant species, as they will grow to a full-fledged covered at the time of completion
Operation Stage
Improvement of the current ecology of the project site will entail the following measures:
Plantation and Landscaping
Green Belt Development
Avenue Plantation
The section below summarizes the techniques to be applied to achieve the above objectives:
Plantation and landscaping
Selection of the plant species will be done on the basis of their adaptability to the existing
geographical conditions and the vegetation composition of the forest type of the region earlier found
or currently observed.
Green Belt Development Plan
The plantation matrix adopted for the green belt development includes pit of 0.3 m × 0.3 m size with
a spacing of 2 m x 2 m. In addition, earth filling and manure may also be required for the proper
nutritional balance and nourishment of the sapling. It is also recommended that the plantation has to
be taken up randomly and the landscaping aspects could be taken into consideration.
Multi-layered plantation comprising of medium height trees (7 m to 10 m) and shrubs (5 m height)
has been proposed for the green belt. In addition creepers will be planted along the boundary wall to
enhance its insulation capacity.
Selection of Plant Species for Green Belt Development
The selection of plant species for the development depends on various factors such as climate,
elevation and soil. The plants will exhibit the following desirable characteristics in order to be
selected for plantation
1. The species shall be fast growing and providing optimum penetrability
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
63
2. The species shall be wind-firm and deep rooted
3. The species shall form a dense canopy
4. As far as possible, the species shall be indigenous and locally available
5. Species tolerance to air pollutants like SO2 and NOx shall be preferred
6. The species shall be permeable to help create air turbulence and mixing within the belt
7. There shall be no large gaps for the air to spill through
8. Trees with high foliage density, leaves with larger leaf area and hairy on both the surfaces
9. Ability to withstand conditions like inundation and drought
10. Soil improving plants (Nitrogen fixing rapidly decomposable leaf litter)
11. Attractive appearance with good flowering and fruit bearing
12. Bird and insect attracting tree species
13. Sustainable green cover with minimal maintenance.
Avenue Plantation
Gardens maintained for recreational and ornamental purposes will not only improve
the quality of existing ecology at the project site but also will improve the aesthetic value.
Avenue Plantation
1. Trees with colonial canopy with attractive flowering
2. Trees with branching at 7 feet and above
3. Trees with medium spreading branches to avoid obstruction to the traffic
4. Fruit trees to be avoided because children may obstruct traffic and general movement of
public
10.2.6 EMP for Socio-Economic Environment
The social management plan has been designed to take proactive steps and adopt best practices,
which will be sensitive to the socio-cultural setting of the region. The Social Management Plan for
Human Care Hospital Project focuses on the following components:
Income Generation Opportunity During Construction and Operation Phase
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
64
The project will be provide employment opportunity during construction and operation phase. There
will also be a wide economic impact in terms of generating opportunities for secondary occupation
within and around the Hospital. The main principles considered for employment and income
generation opportunities are out lined below:
Employment strategy will provide for preferential employment of local people
Conditions of employment will be address issues like minimum wages and medical care for
the workers during construction.
Contractors will be required to abide to employment priority towards locals and abide by the labor
laws regarding standards on employee terms and conditions.
Improved Working Environment for Employees
The proposed project will be provide safe and improved working conditions for the workers
employed at the facility during construction and hospital staff during operation phase. Following
measures will be taken to improve the working environment of the area:
Less use of chemicals and biological agents with hazard potential
Developing a proper interface between the work and the human resource through a system
of skill improvement
Provision of facilities for nature care.
Measures to reduce the incidence of work related injuries, fatalities and diseases
Maintenance and beautifications of the Hospital and the surrounding roads
10.2.7 EMP FOR ENERGY CONSERVATION
Energy conservation program will be implemented through measures taken both on energy demand
and supply.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
65
Figure – 8 : EMP for Energy Conservation
Energy conservation will be one of the main focus during the complex planning and operation
stages. The conservation efforts will be consist of the following:
Architectural design
Maximum utilization of solar light will be done.
Maximize the use of natural lighting through design.
The orientation of the buildings will be done in such a way that maximum daylight is
available.
The green areas will be spaced, so that a significant reduction in the temperature can take
place.
Energy Saving Practices
Energy efficient lamps will be provided within the complex.
Constant monitoring of energy consumption and defining targets for energy conservation.
Adjusting the settings and illumination levels to ensure minimum energy used for desired
comfort levels.
Supply Energy Conservation Demand
Utilize energy-efficient diesel
genetators
Exploring the possibilities of
introducing renewable energy
Reduce consumption
Use energy efficient appliances
Create Guest Awareness
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
66
Behavioral Change on Consumption
Promoting resident awareness on energy conservation
Training staff on methods of energy conservation and to be vigilant to such opportunities.
10.3 ENVIRONMENTAL MANAGEMENT SYSTEM AND MONITORING PLAN
For the effective and consistent functioning of the proposed complex, an Environmental
Management system (EMS) will be established at the site. The EMS will be include the following:
An Environmental management cell.
Environmental Monitoring.
Personnel Training.
Regular Environmental audits and Correction measures.
Documentation – standards operation procedures Environmental Management Plan and
other records.
10.3.1 ENVIRONMENTAL MANAGEMENT CELL
Apart from having an Environmental Management Plan, it is also proposed to have a permanent
organizational set up charged with the task of ensuring its effective implementation of mitigation
measures and to conduct environmental monitoring. The major duties and responsibilities of
Environmental Management Cell shall be as given below:
To implement the environmental management plan.
To assure regulatory compliance with all relevant rules and regulations.
To ensure regular operation and maintenance of pollution control devices.
To minimize environmental impact of operations as by strict adherence to the EMP.
To initiate environmental monitoring as per approved schedule.
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
67
Review and interpretation of monitored results and corrective measures in case
monitored results are above the specified limit.
Maintain documentation of good environmental practices and applicable environmental
laws for a ready reference.
Maintain environmental related records.
Coordination with regulatory agencies, external consultants, monitoring laboratories.
Maintenance of log of public complaints and the action taken.
Hierarchical Structure of Environmental Management Cell
Normal activities of the EMP cell will be supervised by a dedicated person who will report to the
site manager/coordinator of the project. The hierarchical structure of suggested Environmental
Management Cell is given in following Figure 9.
Environment Management Cell Structure
Rep from
Management
Planning group
Site Environmental
Coordinator
Waste water
Treatment
Plant
Operator
Greenbelt
Dev. Incharge
Site
Manager
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
68
10.3.2 ENVIRONMENTAL MONITORING
The purpose of environmental monitoring is to evaluate the effectiveness of implementation of
Environmental Management Plan (EMP) by periodic monitoring. The important environmental
parameters within the impact area are selected so that any adverse affects are detected and time
action can be taken. The project proponent will monitor ambient air Quality, Ground Water Quality
and Quantity, and Soil Quality in accordance with an approved monitoring schedule.
Suggested Monitoring Program
S. No. S.N.
Type Locations Parameters Period and Frequency
1. Ambient Air
Quality
Project Site Criteria Pollutants:
SO2, NO2, PM10,
CO
Twice a year (24 hr
average samples) during
construction phase and
annual during operation
phase.
2. Groundwater
(Portability
testing)
Project site Drinking water
parameters as per
IS 10500.
Twice a year
3. Ambient
Noise
Project site dB (A) levels Twice a year (Hourly
day and night time leq
levels) during
construction phase and
every year during
operation phase.
4. Potable water
quality
Project Site As per IS 10500
potable water
standards
Twice a year
“Human Care Medical Charitable Trust” Hospital project
Sector-6, Dwarka, New Delhi FORM 1 A
M/s Human Care Medical Charitable Trust
69
5. Soil quality Project site Organic matter,
C.H., N, Alkalinity,
Acidity, heavy
metals and trace
metal, Alkalinity,
Acidity.
Twice a year
6. Waste
Characterizati
on
Residential Physical and
Chemical
composition
Daily
7. Treated water Outlet of STP BOD, MPN,
coliform count, etc.
Daily
10.3.3 Awareness and Training
Training and human resource development is an important link to achieve sustainable operation of
the facility and environment management.
10.3.4 Environmental Audits and Corrective Action Plans
To assess whether the implemented EMP is adequate, periodic environmental audits will be
conducted by the project proponent’s Environmental division. These audits will be followed by
Correction Action Plan (CAP) to correct various issues identified during the audits.