for - welcome to environmentenvironmentclearance.nic.in/writereaddata/online/tor/08... ·...
TRANSCRIPT
![Page 1: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/1.jpg)
PRE-FEASIBILITY REPORT
For
Proposed 32 MW Power Plant and Expansion of Project of 2500 TCD to 10000
TCD Sugar Plant
By
M/s. Jarandeshwar Sugar Mills Pvt. Ltd., Post Chimangaon , Tal., Koregaon,
District Satara (MS).
Project Proponent
M/S. Jarandeshwar Sugar Mills Pvt. Ltd.
PREPARED BY
Mantras Green Resources Ltd., Hall No. 1, 1
st Floor, Nice Sankul, ITI Signal, Nasik-422007
ISO Certified and NABET/QCI Accredited Consultancy, ISO 9001:2008
(S.N. 100 -List of Accredited Consultant Organizations 8th
April 2016)
Email: [email protected]
MARCH 2017
![Page 2: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/2.jpg)
i
CONTENTS
ITEM NO PARTICULARS PAGE NO 1.0 Introduction
1
1.1 Project Proponent 1
1.2 Management of JSMPL 1
1.3 The Consultant 1
1.4 Project Details 2
1.5 Purpose of the Project 3
1.6 Estimated project cost 3
1.7 Justification for the project 4
1.8 Screening Category as per EIA Notification 2006 & Subsequent
Amendments
6
1.9 Project Location and Environmental Settings 6
1.10 Geography 12
1.11 Climate 12
1.12 Rainfall 12
1.13 Temperature 12
1.14 Land details 12
1.15 Raw material 13
2.0 Manufacture of Sugar Process 13
2.1 Cogeneration of Electrical Power: Process 15
2.1.1 Fuel Handling System 16
2.12 Ash handling system 17
2.1.3 Electrostatic precipitator (ESP)_ 19
2.1.4 Demineralization plant (DM Plant) 20
2.2 Magnitude of Operations 21
2.3 Utilities and Consumables 23
2.3.1 Water 23
2.3.2 Steam 24
2.3.3 Power 24
2.3.4 Manpower 24
3.0 Environmental Management Plan (EMP)
24
3.1 Wastewater Management 25
3.2 Emission Control 27
3.3 Environmental Impact and Mitigation measures 27
3.3.1 Air pollution 27
3.3.2 Water Pollution 30
3.3.3 Noise pollution 32
3.3.4 Solid Waste Pollution 33
3.3.5 Flora and Fauna 33
3.3.6 Environmental Monitoring Program 34
3.3.7 Monitoring Facilities and Schedule 35
3.3.8 Environmental Records 35
3.3.9 Budget Allocation for EMP 36
![Page 3: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/3.jpg)
ii
4.0 Project Benefits 36
5.0 CSR Activity 36
6.0 Conclusion 38
LIST OF FIGURES
FIGURE NO PARTICULARS PAGE NO 1. Google Imagery of the Project Location 8
2 Location of the project 9
3. Map of 10 km km Study Area Map 10
4. Plant layout map 11
5. Sugar Manufacturing Process 14
6. Refined Sugar Manufacturing Process 14
7. Cogen Power Plant Process Flow 15
8. Effluent Treatment Plant 26
LIST OF TABLES
ITEM NO PARTICULARS PAGE NO 1 Project Details 2
2 Environmental Setting within 10 km radius of the project site 7
3 Land Details 12
4 Typical Composition of Fuel: Bagasse 16
5 Technical Data of Boiler 17
6 Operating Parameter of Steam Generator 17
7 Raw Water Analysis 20
7 Parameters of Alternator 13
8 Magnitude of Operations 21
9 Utility Consumption Norms 23
10 Particulate emission from existing 32 TPH Boiler 27
11 Particulate emission from proposed 160 TPH Boiler 28
12 Ambient Noise Quality Standards w.r.t Noise 33
13 Budget allocation for EMP 36
14 CSR Activity 37
![Page 4: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/4.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 1
1.0 Introduction
1.1 Project Proponent
The Jarandeshwar Sugar Mills Pvt. Ltd. (JSMPL) formally known as
Jarandeshwar Sahakari Sakhar Karkhana was established in 1997-98 is a
private sugar factory situated at Chimangaon, Tal- Koregaon, District Satara,
Maharashtra State. JSMPL is registered under Companies Act, 1956
(Registration No. is U15421PN2010PLC13769) with an objective of setting of a
sugar mill for processing Sugarcane manufacturing of sugar & allied products.
The registered office of the company is located at Shop No. 105 & 106,
Atharva Fariyaz Plaza, Opp, Shankar Maharaj Math, Pune Satara Road,
Dhanakawadi Pune; Maharashtra Postal Code: 411043
The overall control and management of the Company is vested with the Board
of Directors. The Company is managed by experienced promoters-directors
with a long track record who will be instrumental in the growth of the
Company.
1.2 Management of JSMPL
The Jarandeshwar Sugar Mills Pvt. Limited (JSMPL) has a team of dynamic and
progressive members in the Management Board.
1. Mr. R.S. Ghadge Director.
2. Mr.P.D.Rakshe Managing Director.
3. Mr.P. D.Rakshe Plant head
Under their leadership, the sugar mill is functioning well and achieving its goals
consistently.
1.3 The Consultant
The project proponent is having sugar industry near Chimangaon, Karegoan,
Satara, Maharashtra with a capacity of 2500 TCD Sugar Plant. Now,
Jarandeshwar Sugar Mills Pvt. Ltd.’ Management is planning to expand the
sugar plant capacity 2500 TCD to 10000 TCD and proposing a New 32 MW
Cogen Power Plant. To seek the environment clearance, Jarandeshwar Sugar
![Page 5: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/5.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 2
Mills Pvt. Ltd. has appointed Mantras Green Resources Limited (MGRL) as
environment consultant.
Mantras Green Resources Limited (MGRL) is a group of professional associated
with the industries for past 30 years in highly diversified activities like
manufacturing, engineering and consultancy services, including import and
export etc. On 9th May 2013 the company having registered office at Nasik and
Branch Offices in India are at Kalyan, Pune, Hyderabad, Jaipur and Delhi.
MGRL is an ISO 9001-2008 certified company and QCI/NABET Accredited EIA
Consultant for the various sectors. They are exposed to various aspects to
environment and technology. The company is under leadership of CEO Dr. U. K.
Sharma whose visionary approach has made us one of the most prominent
consultants in the country.
1.4 Project Details
The company envisaged setting up of the following facilities in phase:
Byproducts of Existing and Proposed Expansion of Sugar and
Cogeneration Plants
Table 1: Project Details
Existing Activity
Proposed Activity
Total Capacity
After Expansion
2500 TCD
Sugar Mills
Commissioned 7500 TCD
Sugar Mill
Expansion 10,000 TCD
Sugar Mills
By Products
750 MTD
Bagasse
Useful as fuel 2250 MTD
Bagasse
Useful as
fuel
3000 MTD
Bagasse
130 TPD
Molasses
Sold to nearby
Distillery
390 TPD
Molasses
Sold to nearby distillery
520 TPD Molasses
23 TPD Press
Mud
Bio compost 70 TPD Press
Mud
Bio-compost 93 TPD Press Mud
![Page 6: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/6.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 3
Consent for operation of Exisitng 2500 TCD Sugar Mill :
The exiting 2500 TCD sugar mill has obtained Consent to Operate (Number
Format1.0/BO/CACCELL/uanno.0000009389/R/CAC1701000957,dated18/01/
2017) , under Section 26 of the Water (Prevention and Control of Pollution Act)
1974 & under Section 21 of Air (Prevention and Control of Pollution) Act and
Authorization under Rule 5 of the Hazardous Wastes (M, H & T M) Rules, 2008
which is valid for a period from 1/12/2014 to 31/07/2017. Copy attached as
Annexure II.
1.5 Purpose of the Project
JSMPL has decided for expansion of sugar plant from 2500 TCD to 10,000
TCD. Promoter is going for proposing to set a new 32 MW Cogeneration Power
Plant with 7500 TCD Sugar Plant.
The Ministry of Environment, Forests and Climate Change (MoEF&CC),
Government of India has issued an EIA Notification, S.O. 1533 dated 14th
September 2006 amended on 1st December 2009 vide No. 3067, under
Environmental (Protection) Act, 1986. Prior Environmental Clearance (EC) from
the EIA Authorities is mandatory for the establishment of projects/activities
listed in the schedule of above Notification Sugar Industry > 5000 TCD cane
crushing capacity. Therefore, the said Project categorized under 5 (j) of
schedule of activities Category “B1’ require prior environmental clearance from
the State Expert Appraisal Committee (SEIAA/SEAC). Similarly, Cogeneration
Power Projects of 32MW based on Biomass (Bagasse) and using auxiliary fuel
such as coal/lignite/petroleum products 15% are categorized under 1(d) of
schedule of activities, category ‘B1’.
1.6 Estimated Project cost:
The estimated project cost of Expansion of Sugar Mill and Cogeneration plant
is: - Rs. 24685.30 lac.
![Page 7: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/7.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 4
1.7 Justification for the project:
Power is the most essential input for industrialization and it is indeed the
fulcrum on which the future pace of growth & development of our country
rests. Demand for energy is rising exponentially all over the India. With
increased demand for energy, the existing infrastructure is unable to supply
the required quantum & quality of electricity. Various government & private
agencies are struggling to increase power supply capacities to meet these
demands. Most of power supply requirement in India is met through the fossil
fuel based thermal power stations. Again the sinking fossil reserves will not be
able to meet the future power demands. However these electric utilities
contribute greatly to emission of the green house gases (GHG) to the
atmosphere.
In India, nearly 70 % of installed power generation capacity is based on coal
and hence is one of the largest contributors of GHG emission. This aspect of
GHG emission in India is highly relevant as India is the sixth largest emitter of
GHGs, contributing to 2% global emission. More worrisome is that the rate of
growth in the GHG emission in India is more than double the world arrange at
46% annually. It is obvious that greater pressure will be brought will be
brought on India, form the word community, to take every possible step to
reduce the emission of GHGs. The Indian Society, the world community and
the future generation have the right to cleaner environment and even a small
effort in reducing the emission of the GHGs is positive step to towards better
future.
Therefore, the use of Non-conventional energy source has become the ultimate
option for sustainable development. From the various Non conventional energy
options, Cogeneration in Sugar Factories found to be the most viable
proposition to meet the existing power shortfall to some extent. The bagasse
based cogeneration projects fit very well into our objective of containing the
GHG emission to the atmosphere to achieve a clean sustainable development
without damage to the environment.
India is the second largest producer of sugar in the world having over 500
sugar mills. It is estimated that the potential for the surplus exportable power
from these Sugar Mills is around 5000 MW The Sugar Industry in Maharashtra
state having about one third share in the total sugar production of India has
potential of about 1250 MW of exportable surplus power.
The power situation in Maharashtra state indicates that there is a shortage
during the peak demand. The existing power shortage demands the necessicity
![Page 8: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/8.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 5
for the state to tap every possible alternate source of energy from biomass. This
is in view of the projections for requirement of power for sustained economic
development of the state and shortages of funds in implementing conventional
power projects. The government of Maharashtra has already acknowledged the
importance of power from renewable energy sources and has decided to
promote bagasse based cogeneration projects.
Bagasse based cogeneration in sugar mills eminently fits in as a desirable source of augmenting the power generation as it has following merits:
• It is environment friendly as it does not add to the existing pollution level of the environment due to carbon recycling.
• It is a renewable source of energy resulting into reduced dependence on fossil fuels.
• There is no need to transport the fuel to the generating stations as the sugarcane in any case is transported to the factories.
• It helps in bridging the gap between the demand and supply in the power sector to some extent.
• It has lower gestation period and lower installation & operating cost compared to the conventional utility thermal plants.
• The transmission and distribution losses are minimized as the plants are located invariably in the rural areas due to which the quality of power is also improved.
• It facilitates the sugar factories with increased viability and profitability to pay remunerative cane price to their cane grower members.
• It presents good business opportunities and benefits to the sugar factories through Clean Development Mechanism (CDM) for reduction in the emission levels of the GHGs. There are several financial institutes like Indian Renewable Energy Development Agency (IRSEDA), PTC Financial services Pvt. Ltd., Power Finance Corporation and Sugar development Fund (SDF) who are providing financial assistance for cogeneration power projects. Most of them provide Term Loan up to 70% total project cost except SDF. The Ministry of New and Reliable Energy (MNRE) giving back ended subsidy up to 50% for sugar factories developing co-generation power projects in co-operative sectors/public sectors/Government undertaking/SPV company after issuance of purchase order for large equipments like boiler, turbine etc. The remaining 50% subsidy could be availed after commissioning of the project. The benefits of switching over to combine heat and power system will be huge and rewarding.
.
![Page 9: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/9.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 6
1.8 Screening Category as per EIA Notification 2006 & Subsequent Amendments The Ministry of Environment, Forests and Climate Change (MoEF&CC),
Government of India has issued EIA Notification, S .O. 1533 dated 14th
September 2006. As per the EIA notification and its subsequent amendments,
Sugar & Cogen project projects are categorized under 5(j) & 1 (d) of schedule of
activities, respectively. As the proposed expansion project of Sugar & Proposed
Cogen Project is Bagasse based, it comes under category ‘B’ under Schedule
5(j) &1 (d). Therefore, the Projects require prior Environmental Clearance from
the State Expert Appraisal Committee / Authority (SEAC), Maharashtra.
However, at present there is no SEIAA or SEAC Committee existing in the
Maharashtra State. Therefore, as per EIA Notification dated 14th September,
2006, in the absence of a duly constituted SEIAA or SEAC in Maharashtra, this
Project may be treated as a Category ‘A’ Project.
1.9 Project Location and Environmental Settings
M/s Jarandeshar Sugar Mills Pvt. Ltd. is proposing for expansion of Sugar
Plant and setting up of Cogen Power Plant with the following facilities at Gut
No. 30, at post Chimangaon, Taluka- Koregaon, District-Satara (Maharashtra).
• About 25,855.81 m2 area of land is already available with Proponent.
• Koregaonand Chiamgaon cities are respectively 12 km and 2 km away
from the Project’ Site. The site is well connected with National Highway No. 4
and State Highways, Railway Station and Airport.
• The average rainfall of the District is 935.7 mm/year.
• Maximum temperature in summer is 340C and minimum temperature in
winter is less than 140 C.
• Water is available at a depth of 160-165 feet.
• Environmental conditions dusty and non-corrosive.
• Seismic zone III.
![Page 10: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/10.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 7
Table 2 : Environmental Setting within 10 km radius of the project site
Particulars Details
Project Location At-Cimangaon,Tal-Koregaon,
District-Satara, Maharashtra State
Latitude & Longitude Latitude: 170 24’ 20.49” N
Longitude: 74013’48.25” E
Survey of India Toposheet No. E4302 Scale: 1: 50,000
Estimated Project Cost Rs. 24685.30 Lacs
Nearest Highway State Highway: Satara- Pandharpur
: 2 Km
Nearest Village Bhatamwadi 0.2 km, (south)
Khirkhandi -- 1.7 km in South
Nearest Town Koregaon: 12 km
Nearest Railway station Koregaon : 12 km
Nearest Airport Pune : 146 km
Other Historical / Religious
places
None
Defense installations No
Ecologically sensitive areas
(National Parks / Wild life
sanctuaries / bio-sphere reserves,
migratory routes within).
None
Reserved / Protected Forest 2.3 km in North-East direction
Dhamanyachar Dongar RF : 5.5km
in NE direction
Nearest Water Bodies Ner talav : 8.4km in NE direction
Dhom Left bank canal : 5.9 km in
SW direction
The location of project site is depicted in Google Imaginary (Fig. 1), project site
(Fig. 2), map of study area (Fig.3) and Plant Layout map shown in (Fig. 4).
![Page 11: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/11.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 8
Fig. 1: Google Imagery of the Project Location
![Page 12: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/12.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 9
Fig. 2: Location of the Project
Project Site
![Page 13: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/13.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 10
Fig. 3: Map of 10 km Radius Study Area
![Page 14: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/14.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 11
Fig. 4: Plant Layout Map
Proposed Cogeneration Unit
![Page 15: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/15.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 12
1.10 Geography
Chimangaon is a village in Taluka Koregaon, Satara district of Maharashtra State. The entire area of the district is covered by basaltic lava, flows of upper cretaceous of lower Eocene age. The basalt is capped by laterite of younger age which is bound in the plateau above 900 MSL. Alluvium occurs in patches along banks of rivers Krishna, Venna, Kudali and Koyana with average thickness of 10 m and contains pebbles, boulders of trap and beds of sand. 1.11 Climate
The climate of the district on the whole is moderate. It does not show extremities. However, three distinct seasons are experienced. These are monsoons from June to September while in October and November are the post-monsoon months with warmer climate, winters from end of November up to middle of February followed by a warm to hot summer from mid February up to first or second week of June. 1.12 Rainfall The South-West monsoon, the main source of rainfall, begins about the middle of June and lasts till the end of September. Nearly 85 % of the rainfall occurs during these months only. These rains do not cross beyond 40 km east of Satara. 1.13 Temperature The winters start by about end of November and continue till middle of February, December being the coldest month. In this season the mean daily maximum temperature in the plains is 28.40 C, while the mean daily minimum temperature is 13.20C.
1.14 Land Details Table 3 : Land Details
S. No. Land Utilization
Existing Area (m2) Proposed Area
Proposed (m2)
1 Main factory building 8900
Mill house building 750
2 Sugar godowns {1&2} 6465.26
boiling house building 2000
3 Store building 1317.05 Molasses Tank 750
4 Main Gate & Alide structure 110 Boiler 1500
5 Weigh Bridge cabin 120 Power House 2250
6 Auxiliary Building 1550 Cane carrier 3000
7 Laboratory 180 - -
![Page 16: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/16.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 13
Building
8 Turbine Building 450 - -
9 Molasses Tank 1730 Internal Rods 90000
10 Chimney 13.5 Open Area 30500
11 Cantin Building 120 Green Belt 572561
12 E.T.P. 3900 Parking area 20000
13 DM Plant 1000 - -
Sub-Total 25,855.81 7,23,311
Total
749166.81 Please give an overall description as follows:
Total Plant Area: 7, 49,166.81m2
Area occupied by the Existing Sugar mill and cogen units: 25,855.81 m2
Area Proposed for the Expansion units: 7, 23,311 m2
Green belt description and percentage of green belt proposing: 572561 m2
Rainwater Harvesting Facility area will be provided
Area for ETP Expansion: 3900m2
1.15 Raw Material
� Total requirement of sugarcane is 15 lac MT for existing 2500 TCD and
proposed 7500 TCD sugar mills expansion.
� About 1632 bagasse will be required for 32 MW Co-gen Power plant.
2.0 Manufacture of Sugar Process
Sugarcane is weighed, washed, cut, shredded and fed to series of mills.
Sugarcane juice is extracted and bagasses are separated. Juice is heated and
clarified. Mud is separated out and clarified juice is subjected to multiple
effects evaporators. Concentrated syrup is fed to vacuum pan where syrup gets
super saturated and fine crystals and mother liquor are separated in
centrifuges. Raw sugar is dumped on moving belt where it gets dried before
moving to storage. In normal courses main sugar plant boiler will function and
fulfill steam requirement of distillery also.
Manufacturing Process is given below:
• Extraction of juice by pressing sugarcane and bagasse is separated
![Page 17: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/17.jpg)
M/s. Jarandeshwar Sugar M
Mantras Green Resources Ltd.
• Boiling the juice to
separation
• Creating raw sugar b
• Raw sugar to a refine
remaining non-sugar elem
• Crystallizations and d
• Packaging the ready s
The process flow diag
Fig.
Fig. 6: R
Mills Pvt. Ltd. Pre feas
td., Nasik
to obtained crystals and clarification
r by spinning crystals in extractor
inery for the process of filtering and wash
ements and hue
d drying sugar
y sugar
iagram is given in Fig.6 and Fig. 7.
Fig. 5: Sugar Manufacturing Process
: Refined Sugar Manufacturing Process
easibility Report
14
tion with mud
shing to discard
ess
![Page 18: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/18.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 15
2.1Cogeneration of Electrical Power: Process
• When a properly coiled wheel is rotated within magnetic field electricity is
generated
• To rotate the wheel mechanical, water or steam may be used
• Steam generated in a boiler is fed to a turbine coupled to an alternator
• Steam is produced in a boiler by burning of bagasse and coal as fuel
• Steam at high pressure moves the turbine which rotates alternator and
electricity is produced
• Part of steam is ejected at low pressure is used for heating requirement
of sugar mill, de-aeration of incoming water and balance is condensed and
recycled
• The management is planning to add 7500 TCD sugar mill along with
proposed 32 MW Co-gen Power Plant
• The proposed cogeneration project will be equipped with a new 160 TPH
Travelling Grate Boiler along with 32MW extractions cum condensing Turbine
with existing set up. The process Flow Sheet is given in Figure 5.
Fig. 7: Co-gen Power Plant Process Flow
![Page 19: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/19.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 16
2.1.1 Fuel Handling System
During crushing season 100 % Bagasse will be the source of fuel. The
quantity of bagasse required will be 1632 TPD. A belt conveyer system of
capacity of 160.00 TPH is to be installed such that with this capacity to
meet the fuel requirement for the boiler in both option. All the safety
precautions including fire hazards have also been considered in the belt
conveyor to avoid any untoward incident.
Bagasse Handling System
The Heaps of Bagasse shall be Scratched by the Heap Scratcher Crane
cum Double Conveyor (1 Sets – HS-1) and shall be fed on to the Bagasse
Slat Chain Feeder (SC-01) which is designed in a way to feed the Boiler
from the bottom end on return side. The excess of bagasse shall be
brought back to the Storage Area by Return Bagasse Conveyor RBC-
01/2. RBC-02 shall be equipped with movable plough feeder to
accommodate the new heap formation.
Typical Composition of Fuel: Bagasse
S. No.
Parameters Bagasse
1. Carbon (%) 33.50
2. Hydrogen (%) 3.25
3. Nitrogen (%) 0.01
4. Sulphur (%) 0.02
5. Moisture (%) 50.00
6. Ash (%) 1.50
7. Gross Calorific Value(kcal/kg) 2272
During crushing season 100 % bagasse will be used as fuel with bagasse
consumption of 1632TPD.
![Page 20: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/20.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 17
Table 5 : Technical Data of Boiler
S. No.
Item Description Value
1. No. of Boilers One
2. Type of Boiler Travelling Grate
3. Tube Type Water tube boiler
4. Type of draft Balanced draft system
5. Type of feeding system
Over-bed fuels are to be fed from fuel yard by conveyor belt
6. Type of circulation Natural circulation
7. Type of support Top supported
Table 6 : Operating Parameter of Steam Generator
S. No.
Item Description Value Unit
1. Type of Boiler Travelling Grate Boiler
-
2. Number of boiler One -
3. Maximum continuous rating (MCR)
160 TPH
4. Steam Temp outlet at MCR 540 ± 5oC
Steam pressure at outlet of SH 87 kg/cm2(g)
5. Feed water temp at economizer inlet
1650 0C
6. SH Steam temperature control range
60 - 100 %
7 Temp of flue gas at inlet of ID Fan 150 0C
2.1.2 Ash Handling System
The proposed 160 TPH, Travelling Grate Boiler is fired with bagasse in crushing
season and fuel. The fuel forms ash on combustion. Ash content of Bagasse is
1.5-2.0 %. Ash generated by Bagasse is approximately 56.67 kg/hr (1.36 MTD)
in 160 TPH Travelling Grate Boiler.
• In Travelling Grate Boiler the ash from the bed is drained for maintaining the
bed inventory and to maintain the bed pressure drop.
• Bed ash is drained through the eight drain points provided at the bottom
of the bed. It is practice in Travelling Grate Boiler that the bed drains from
![Page 21: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/21.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 18
these drain points are cooled and then sewed to get the recommended bed
material size to be used as bed material as and when required
• The rejected portion of this bed ash can be manually handled / collected
through Ash disposal system
• Hence the ash collection points shall be from economizer (at two points),
air heater (at two points) and ESP (at 3 points).
• These ash collected will be carried out through the Dense Phase System
proposed by vendor to ash silo.
• The ash collection points from economizer and air pre heater etc.
Compressed air for the Dense Phase Pneumatic Conveying system is
obtained from two (one working 100% and one stand bye) reciprocating
air compressors and a receiver.
Bottom Ash Disposal System
• Bottom ash from boiler (bottom ash and bank ash) shall be collected in
water impounded surge hopper. The ash so collected in surge hopper
will be evacuated by Dense Phase Pneumatic (vacuum) conveying
system
• One number water cool surge hopper shall be provided under the
bottom ash and boiler bank hopper.
• Under this hopper, 1 No transporting vessel will be connected to the
hoper through material cut off valve and expansion joint.
• The transporter shall be connected to a MS heavy duty ERW Pipe line
(as per IS: 1239) to dump the conveyed husk / ash into the silo through
an end receiver
Fly Ash Disposal System
• The fly ash from Economizer, Air pre-heater, ESP etc. shall be
transferred from each hopper via a transporting vessel under each
hopper shall be provided.
• The transporting vessel will be connected through hopper with the help
of adopter piece, valve and expansion joint
![Page 22: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/22.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 19
• The transporter shall be connected to a MS heavy duty ERW Pipe line
(as per IS: 1239) to pump the conveyed husk / ash into silo through an
end receiver
• It is also proposed to install 1 No. Silo with storage of 12 hrs for
unloading the fly ash
Compressed Air System
• Two numbers of reciprocating / rotary compressors with receiver are
required for operation of system. Air at 6- 7 kg /cm2 (g)
• For fluidizing of fly ash silo, two numbers of root blower (1+1) of
approximately shall also be required.
Silo Unloading
• For silo unloading one number each of plate valve, rotary feeder and
dust conditioner are provided the opening of silo for disposal of ash
through truck.
2.1.3 Electrostatic Precipitator (ESP)
• Thickness of the insulation shall be suitably designed in such a way
that the difference between the casing temperature and the ambient
temperature shall not be more than 20°C at still air condition
• Specific weight of ash may be taken as 650 kg/m3 (Rice husk) and 600
kg/m3 (for Bagasse) for calculating storage capacity and 1100 kg/m3 for
structural design
• Outlet size of the hopper bottom opening shall be 400 x 400 mm.
Straight length after the hopper shall be restricted to 50mm
• Bottom level of the ESP hopper (Rotary air lock valve outlet) shall have
2.5 m clearances from ground level
• All supporting steel structures required for ESP shall be provided in
accordance with IS: 800 including columns base plates, anchors, anchor
bolts, sleeves, inserts, beams, girders, hangers required for installation,
inspection / maintenance
![Page 23: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/23.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 20
• The structure shall be designed taking into consideration total
equipment weight, hopper dust load, live and dead loads and wind loads
in accordance with IS: 875. The design shall also take into account the
suitable seismic coefficient
• Local platform and ladder for approach to the ESP ash hoppers / access
doors shall be provided
• Precipitator main housing (all walls and roof, with required columns,
stiffeners, access door, etc)
• Thermal insulation LRB mattresses, (40 mm thickness and 100 kg/m3
density) complete with lagging, wire mesh fixing cleats and outer plain
aluminum cladding 24 SWG.
2.1.4 Demineralization Plant (DM Plant)
The DM plant shall be of indoor installation and mode of operation shall be
manual. All indicators, recorders, switches, push buttons, indicating lamps
and annunciated windows shall be mounted on local control panel.
Table 7: Raw Water Analysis
S. No. Parameters Value Unit
1. pH 7.6 -
2. Total hardness 221.0 mg/l
3. Alkalinity 'p' 384.0 mg/l
4. Total Dissolved Solids 432.0 mg/l
5. Chloride as Cl 10.0 mg/l
6. Silica as SiO2 1.8 mg/l
7. Potassium as K 2.2 mg/l
8. Calcium as Ca 67.0 mg/l
9. Magnesium as Mg 13.0 mg/l
10. Total Suspended Solids 18.0 mg/l
The output from the D.M / RO Plant should have the following requirement for
best feed water quality and Boiler operation.
Data Acquisition System (DAS)
The complete Power plant can be segmented by various systems such as:
o Boiler and its auxiliaries
o Turbine and its auxiliaries
o Over all electrical distribution system
![Page 24: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/24.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 21
o Fuel handling system
o Ash handling system
o DM water system
o Compressed air system
o Cooling water system and raw water system
In DAS system, the input and output process parameters such as pressure,
temperature, level, position indictor, flow etc. will be evaluated and
documented in a “data base” list which will contain:
o Analog input and output point
o Digital input and output point
The entire power plant will be divided as above systems and each will
contribute for smooth and healthy operation to get maximum availability of
the plant. The general input and output of analog nature will be as below:
o Pressure from pressure transmitter
o Level from level transmitter
o Flow from flow transmitter
o Temperature from temperature transmitter
Which acts on 4-20 mA signals to transmit to distributed processing unit
called DPU which ultimately worked as marshalling system of all the input /
output which contributes to DAS system. By using these inputs and outputs
the parameters can be changed to control the operation of the plant.
2.2 Magnitude of Operations
Following table clearly indicates all facets of proposed project to elaborate
magnitude of project:
Table 8: Magnitude of Operations
Sr.
No.
Feature Details
1. Area Statement
Land utilized for existing unit 25,855.81 m2
Land to be utilized for Proposed Unit 723311 m2
Total 7,49,166.81 m2
![Page 25: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/25.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 22
Sr.
No.
Feature Details
2. Working (days) 330
Season(days) 160
Off-season(days) 72
Non Working Season(days) 30
3. Existing Sugar Mill 2500 TCD
Proposed Sugar Mill with Cogen 7500 TCD 32 MW
Total Capacity Sugar Mill with Cogen. 10000 TCD 32 MW
4. Raw Material for Cogen. PP
Total Bagasse Generation after
Expansion
2700 TPD
Bagasse Requirement for 32 MW
Cogen. PP
1632 TPD
4. Water Resources
River Tailganga
5. Fresh Water Demand for full capacity
(10000 TCD)
3000 KLPD @30%
7. Backup power 1000 KVA
D G set rating 1000 KVA
Fuel used HSD
200 L/hour (at full load)
8. Man Power 577 Nos.
9. Total Investment Rs. 24685.30 lacks
10. Utilities 160 TPH boiler of sugar
mill (7500 TCD)
Steam generation capacity 87 ata pressure, 540oC
Boiler capacity (Cogeneration) 160 TPH
Fuel – Bagasse Requirement 1634 MT/day
11. Total Ash Generation 32.6 MT/day
Fly Ash expected 26.1 MT/day
Bottom Ash expected 6.5 MT/day
Fly Ash Dust collector ESP
![Page 26: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/26.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 23
Sr.
No.
Feature Details
Bottom ash & fly disposal Used as Manure &
Brick manufacturers
12. Height of chimney 82 m
Diameter chimney 4.5 m
Bottom Ash disposal Silo
ETP capacity (existing ETP of sugar
unit)
1000 m3/day
13. Solid waste
ETP Sludge from ETP/DM Plant
Fly ash : 26.1 MTD
Bottom ash: 6.5 MTD
36.92 m3/day
2.3 Utilities and Consumables
For phase II the utilities and consumables consumption norms is given below:
Table 9 : Utility Consumption Norms
S.
No.
Description Unit Consumption
Sugar Mill
1. Water % on Cane (30%)
2. Steam % on Cane (36%)
3. Power kWh/MT 30
• The Consultants have benchmarked the above utilities and consumables
consumption norms against industry standards and believe that these
norms are achievable
2.3.1 Water
• For fulfilling water requirement, the Company has taken on the bank of
the Tailganga river.
• The raw water so received will be stored in GSR tanks at site and will
be processed through DM/ RO plant for end use.
![Page 27: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/27.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 24
• Water requirement : Required water Quanity for existing & sugar unit :
2100 KLD and Required water Quanity for Proposed Cogen unit : 2688
m3/day
Source of water: The required water will be supplied from Tailganga
River. The required permission for extraction of water is given in
Annexure-III
2.3.2 Steam
• The steam turbine to be used in the project is extraction and
condensation type. The steam extracted from the turbine will be used in
process.
2.3.3 Power
• Power generated from the Co-gen will be used internally and the excess power
will be sold to grid.
• Any deficit of power will be met through grid purchase.
• Although the Company will be utilizing in-house power, still will have suitable
DG set with all the plants to safeguard any power failure situation.
2.3.4 Manpower
Manpower for phase II facilities is indicated as below:
• Sugar mill and Co-gen units will have 577 Nos. of employees and its
estimated annual manpower expenses shall be Rs. 13.83 Crores at
optimum capacity utilization.
• Indirect benefits of their projects are reaching too many people in the
area.
3.0 Environmental Management Plan (EMP)
JSMPL is an existing industry planning new unit and have well established
environmental management plan (EMP). The sugar plant and power plant
utilize resource such as water, cane sugar, bagasse etc. and discharge liquid,
gaseous and solid waste products. Mitigation measures are incorporated in the
project to protect environment against any harm. A comprehensive
![Page 28: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/28.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 25
environmental management plan is adopted consisting of proposed pollution
control measures and additional mitigation measures for abatement
undesirable impacts. Summary of these measures includes:
• Green belt and greenery development in the factory premises (about
33% of the plot area).
• Waste water management, Recycle and Reuse of condensate
• Paving and lining of roads, solid storage yards of ash etc.
• Self monitoring system is established in the industry with man power
and facilities to ascertain the compliances of environmental norms and
standards.
• Personal health care program, emergency management plan and safety
management systems will be implemented in the proposed project
activities.
• Operation and Maintenance of pollution control measures
• Establishment of waste reduction measure.
• The project is technically and financially viable, subject to the
assumptions made in this report found good.
3.1 Wastewater Management
Waste water management will include:
• Operation of ETP should be started at least one month before starting
of plant to achieve desired MLSS so as to meet the prescribed
standard from day one of the operation of the plant.
• Reduce waste generation
• Plant should achieve zero discharge to inland water surface
• Plant should provide 15 days storage capacity for treated effluent to
care for no demand for irrigation.
• Rain water harvesting scheme will be adopted.
![Page 29: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/29.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 26
Effluent Treatment Plant (ETP)
Effluent treatment is the process of removing contaminants from wastewater,
including household sewage and runoff (effluents). It includes physical,
chemical and biological processes to remove physical, chemical and biological
contaminants. Its objective is to produce an environmentally safe fluid waste
stream (or treated effluent) and a solid waste (or treated sludge) suitable for
disposal or reuse (usually as farm fertilizer). Fig. 8 gives an overview of a
typical effluent treatment plant.
Fig. 8: Effluent Treatment Plant (ETP)
The treatment processes are divided into stages:
• Pre-treatment: Pretreatment will consist of screening, oil & grease removal and Flow equalization.
Equalization
Tank
Bar
Screen
O&G
Removal
Secondary
Clarifier
Treated
Water Tank Sludge Drying Beds
Raw
Effluent
UASB Digester
Aeration Tank Clarified Water
Tank
PST
Cleaning Day Tank
Neutralization
Tank
Buffer Tank
IST Dual Media
Filter
![Page 30: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/30.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 27
• Primary or Chemical Treatment: Primary or chemical treatment will consist of neutralization, PST (Primary Settling Tank) and Buffer tank for neutralizing and pH correction of incoming effluent.
• Secondary / Biological Treatment: Secondary Treatment process will consist of UASB Digester and Clarification followed by recycle of anaerobic sludge. Anaerobic process is followed by Biological Aeration and Clarification. Aerobic sludge from Secondary Clarifier will be recycled to Aeration Tank
• Tertiary Treatment: process will consist of Sludge Drying Beds.
3.2 Emission Control
In order to control emission, the plant should provide ESP/Bag Filters/
high efficiency scrubbers to comply with the standards for particulate
matter emission to less than 150 mg/Nm3.
3.3 Environmental Impact and Mitigation measures
The plant can cause environmental pollution in the following forms:
• Air Pollution
• Water Pollution
• Noise Pollution
• Solid Waste Generation
3.3.1 Air pollution
Air Pollution Control :
Sources of Air pollution are: Boiler, Stack emissions, DG set emissions,
vehicular movement.
Table 12: Particulate Emissions from Existing 32TPH Boiler (2 Nos.)
S.No Particular Quantity
1. Existing boiler capacity of sugar mill 32 TPH
2. Fuel used Bagasse
3 Required Fuel Quantity 600 MT/day
4 Sulphur (%) (at max). 0.2 %
5 Fuel gas velocity 3.7 m/sec
6 Fuel gas flow rate 12 m/sec
7 Flue gas Temperature 150oC
8 SO2 Emission rate 100 kg/hr
![Page 31: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/31.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 28
9 Height of the stack required as per
CPCB standards
14 x (Q)0.3 = 55 m
10 Stack diameter 3.5 m
11 Existing stack height 52 m
Ash Emissions
12 Total Ash emissions 0.29 MT/hr
13 Fly ash Emissions 0.23 MT/hr
14 Bottom ash Emissions 0.058 MT/hr
Hence the stack height is adequate for effective dispersion of pollutants.
Table 11: Particulate emissions from Proposed 160TPH Boiler for
proposed expansion of Existing sugar mill and Cogen plants
S. No Particular Quantity
1. Proposed boiler capacity 160 TPH @ 87 kg.
2. Fuel used Bagasse
3 Required Fuel Quantity 1632 MT/day
4 Sulphur (%) (at max). 0.04%
5 NOx Kg/ton of Bagasse (at max) 0.02%
6 Stack Diameter 4.5 m
7. Flue gas Temperature 150oC
10. SO2 Emission rate 2.32 kg/hr
11. Height of the stack required as per CPCB
standards
74 H 0.27 based on particulate
emission= 76 m
12 Proposed stack height for expansion unit 82 m
Ash Emissions
9 Total Ash emissions 1.36 MT/hr
10 Fly ash Emissions 1.088 MT/hr
11 Bottom ash Emissions 0.272 MT/hr
![Page 32: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/32.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 29
Treatment Technology of Particulate emissions
The critical SPM concentration in the flue gas will be less than 150.0 mg/Nm3.
Majority of the particulates (about 60-70%) will have sizes in the range of 2-10 µm.
The emissions are expected to have temperature in the range of 140-150°C.
1. JSML has installed Electrostatic Precipitator (ESP) of 99.9% efficiency for control
of particulate emission for the existing sugar plant.
2. JSML is proposing Electrostatic Precipitator (ESP) of 99.9% efficiency for
proposed & expansion of sugar & cogen unit.
The proposed 32MW Cogeneration plant will cause environmental
pollution in the following forms:
The plant can cause air pollution due to the following activities:
• Particulate matter emission from steam boiler
• Dust emission from un-paved access roads
• Emission from D G sets
• The elements polluting the ambient air that are discharged from the
proposed cogeneration plant that are dust, fly ash, NOx, SO2 in flue
gases.
• There will be provision of ESP which will reduce dust emission from
plant to the level < 100 mg/Nm3
• There will be provision of one number MS Chimney/stack of 65m
height will be considered for Travelling Grate Steam Generator of 160
TPH, 72 kg/cm2, 510 0C steam pressure and temperature.
• The air quality monitoring will also be undertaken to ensure that the
dust pollution levels is within limits.
• Adequate sampling opening will be provided in the stack. The
sampling at the Stack will be done once in six months to check on
performance of ESP.
Mitigation Measures
The Consultants suggest the following mitigation measures for air
pollution:
![Page 33: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/33.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 30
• Flue gas cyclone, filter bags/ESP/wet scrubbers to capture ash due to
burning of bagasse for boiler fuel
• Providing well designed chimney with adequate height for proper
dispersion of pollutants
• Providing road surface with black toping to avoid dust emission due to
transportation
• Use wet scrubbers for removal of dust from drying and cooling of
sugar
• Dust catchers to collect sugar from sugar graders
• Periodic monitoring of stack and ambient air quality to keep a check
on pollution parameters as per the directives of MSPCB
3.3.2 Water Pollution
Existing Sugar Mill Effluent Treatment:
• Existing 2500 TCD sugar mill has an ETP of 250 KLD capacity for the
treatment of the effluent generated from the sugar mill and cogen plants.
• Existing 250 KLD ETP plant will be upgraded to a capacity of 1000 KLD
capacity (which is 20% more for 1200 KLD effluent generation) with
advance treatment technology.
• ETP sludge will be used as manure.
• The treated water will be used for gardening and flushing purpose.
Domestic Sewage treatment
• JSML will construct a Sewage Treatment Plant of 60 KLD capacity with
latest technology for treatment of domestic sewage from the sugar mill
and Distillery plant.
• Treated sewage will be used for Gardening and plantation purpose.
![Page 34: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/34.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 31
The plant can cause water pollution due to the following activities:
• Main plant house wastewater due to continuous cooling and
intermittent floor washing
• Wastewater due to washing of utilities
• Spirit/ molasses mixed water
• DM plant blow down
• Sewage generation due to domestic activities
The plant should ensure that the treated effluent quality shall comply
with the norms set by the pollution control board.
Mitigation Measures
The Consultants recommend the following measures to mitigate water
pollution:
Process wastewater from the plant should be treated in an effluent
treatment plant. The most commonly used treatment option consists the
following:
• Preliminary treatment consisting of screens and oil and grease trap
• Equalization tank for maintaining the flow and load
• Sedimentation tank for removal of suspended solids
• Biological treatment consisting of extended aeration tank followed by
settling tank or anaerobic lagoons, aerobic lagoon based on the
imperviousness of soil in the area
• Disinfection by chlorination or ultra-filtration as per the
recommendation of Pollution Control Board
• Sludge generated can be provided with sludge thickener followed by
sludge drying beds
• Sewage generated can be treated along with process water or can be
segregated and provided with septic tank followed by soak pits as
recommended in the consent from MPCB.
• Treated effluent from the ETP can be used for irrigation or discharged
to sewer or to the common effluent treatment plant if available in the
area as per the recommendation of the Pollution Control Board.
![Page 35: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/35.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 32
• Monitoring of inlet and outlet effluent quality from ETP to keep a
check on pollution parameters.
• Compressive Water Management plan has been planned with the site-
wide strategies for minimizing water use efficiency, minimizing
wastewater discharge and encouraging a policy of reuse and recycle to
control a plant’s water footprint
• The effluent will then be pumped into the effluent Treatment Ponds
which form a part of the power plant’s effluent disposal system
• The rejects form WTP which will be used for clean purposes in the
project activities and also for plantation
• The chlorine dose of 0.2 ppm done mainly to prevent biological growth
in the cooling tower system
• Process water from sugar plant is required to be treated in ETP and
inlet and outlet to be check regularly on pollution parameters
3.3.3 Noise pollution
• The proposed cogeneration plant cause noise pollution due to
presence of centrifugal pumps, motors, DG sets, EOT Crane etc.
• The Consultants believe that noise pollution can be controlled to a
considerable extent by providing proper maintenance to equipment
and providing suitable acoustic enclosure to DG sets.
• Providing thick green belt (33%) area in and around the plant
premises can also attenuate noise pollution.
• This noise pollution can be controlled up to a certain limits as per
pollution control boards norms
• There should be provision of acoustic enclosure to DG sets
• The plant should ensure that the ambient noise quality standards set
by the Pollution Control Board as indicated below
Table 12 :Ambient Noise Quality Standards w.r.t Noise
Area Category of Limits in dB(A) Leq
![Page 36: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/36.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 33
Code Area/Zone
Day Time Night Time
(A) Industrial Area 75 70
(B) Commercial Area 65 55
(C) Residential Area 55 45
(D) Silence Area 50 40
Source:CPCB Norms
3.3.4 Solid Waste Pollution
The plant can generate solid waste in the following form:
Mention the Quantities
• Press Mud: 23 TPD existing and expansion 70 TPD
• Sludge from DM Plant: 0.28 m3/day
• Sludge from ETP: 36.64 m3/day
• Fly ash and bottom ash : 26.1 MTD & 6.5 MTD respectively
• Press mud can be used as manure after composting.
• In case of double carbonation the press mud formed can be sent to
landfill.
• Sludge from ETP can also be send to landfill or used as manure as per
the direction of MSPCB
• Establishment of waste reduction measures will be adopted.
3.3.5 Flora and Fauna
Flora: Most dominant plant species found in this area are Kaju, Neem
/ Kadunimb, Palas, Pimpal, Adulsa, Lajalu, Nirgudi, Ashoka, Peepal,
Babul, Mango, Gulmohar, Bel, Neem, Eucalyptus globulus, Coconut,
Bor, Chinch, Sitafal, Tantani, Tarwad etc. The common grasses found in
this area are Marvel, Kusli, Kunda and Goshya.
Fauna: The common species of animals and birds found in the region
includes the following:
• Among the mammals found in the region are the jackal, Kolha or Sheal,
Canis aureus the hyena, the wild cat.
![Page 37: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/37.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 34
• The herbivorous animals commonly found are Indian Gazelle, monkey;
Harine
• Animals such as the Hare, Khargosh, Parempine are also found in
almost all the forest areas.
• Among the birds the peafowl, Grey and painted partridges, Tetar,
Pater, pigeons are found in some varieties of ducks, kingfisher etc. are
found near water bodies.
• There is no endangered flora or fauna or rare species plant or animal
existent at this location.
• Adequate environment protection systems will be put in place for the
treatment of all liquid, solid and gaseous discharges from the power
plant to achieve the required emission levels well within the permissible
limits of state pollution boards.
• As a result there shall be no adverse impact on either the air or water
quality in and around the sugar cogeneration complex
3.3.6 Environmental Monitoring Program
• JSMPL will ensure effectiveness of pollution control measures will be
ascertained by systematic monitoring of discharges at factory and
receiving levels.
• Environmental Management Cell (EMC) consisting of Departmental
Heads will be created to effectively manage the environmental activities
in the parent plant and the power plant.
• Environmental department will be formed with environmental scientist,
laboratory chemists and operators to implement and operate pollution
control and environmental protection measures.
• Third party monitoring will be carried out to double check
effectiveness of mitigation measures
![Page 38: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/38.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 35
• Proponent analysis report, third party report will be corroborated with
statuary body, so that results are in line with standards all time.
3.3.7 Monitoring Facilities and Schedule
• A laboratory will be established with manpower and facilities to
analyze water, wastewater, etc. Stack emission, ambient air
monitoring will be outsourced.
• The parameters monitored will be temperature, SPM, SO2
and NOX
for
gaseous emissions and RSPM, SO2
and NOX
ambient air. Analysis is
also carried out by competent third party for cross checking.
• The quality of discharges including wastewater, flue gas, and the
receiving bodies such as ambient air, water, surface water and soil
will be monitored for the desired parameters.
• Sampling locations and post project monitoring schedule have been
worked out.
3.3.8 Environmental Records
• Environmental department will maintain log sheets and manuals for
operation and maintenance of pollution control and related facilities
• Progress reports and statuary records as per environmental acts will
also be maintained
• JSMPL is an existing industry planning new unit and we have well
established environmental management plan (EMP)
• A comprehensive environmental management plan is adopted
consisting of proposed pollution control measures and additional
mitigation measures for abatement undesirable impacts
3.3.9 Budget Allocation for EMP
The EMP Budget is given below:
![Page 39: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/39.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 36
Table 13:Budget allocation for EMP
S. No.
Particulars
Capital cost
Annual Recurring cost
Rupees in lacs.
1. Air Pollution control equipments 49 16.50
2. Chimney 25.63 4.00
3. Ash collection system 8.75 2.45
4. Water pollution control treatment 100.00 14.00
5. Noise Pollution control 6.15 2.34
6. Solid waste Management 30.00 7.66
7. Occupational health 12.85 4.80
8. Safety Management 18.22 4.90
9. Development of green belt 28.95 1.00
10. Maintenance of pollution control devices
86.66 46.48
11. Expenses of CSR activities 617.13 50.50
Total 983.34 154.63
4.0 Project Benefits
• The industry on expansion will provide direct and indirect
employment to many local rural people.
• The project will be a boon as power will be fed to grid for other users
in a power deficit state as is ours.
5.0 CSR Activity
About 2.5 % of the capital cost will be earmarked for CSR activity the
approximate amount will be 617.00 lacks.
Give the Breakup of the CSR Fund Allocation and the activities, amount
spending in approximate quantities
Table 14: CSR Activity
S. No.
Activities Social Benefits Expenses (Rs. Lacs)
![Page 40: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/40.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 37
1 Education Development
a. Providing scholarships and prize amounts for merit students
b. Providing reimbursement of cost of uniform, notebooks for factory employee children’s.
c. Providing skill development trainings d. Conducting Art of Living classes to the
employees and villagers so as to create value in the lives of people.
90.00
2 Rural Road Development
a. Provide Road infrastructure facilities from the factory connecting to nearby villages.
b. Providing repairs for the damaged roads due to the vehicular movement.
115.00
2. Drip Irrigation
a. To save water, increase crop production b. Minimize use of water
45.00
3. Rain water Harvesting
a. Water collection from factory terrace b. Rain water for reuse, landscape
irrigation c. Greenbelt development
100.00
4. Plantation a. Greenery for ecological balance b. Enrich local biodiversity c. Control Air & Noise pollution, windbreak d. Helpful to control soil erosion e. Plan for plantations
85.00
5. Health Programme
a. Conducting frequent health Checkups for all the workers regularly.
b. Providing Personnel Protective Equipment (PPE) for all the workers
c. Providing safety training programs for all workers
d. Providing safe drinking water with RO Treatment facility.
e. Providing hygienic toilets to the workers and cane truck drivers.
125.00
6. Organic Farming: Supply of Bio-Fertilizer. Bio-compost distribution at subsidized rates to the farmers and cane growers
57.00
TOTAL FUND FOR CSR ACTIVITY 617.00
6.0 Conclusions
![Page 41: For - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/08... · 2017-03-08 · ii 4.0 Project Benefits 36 5.0 CSR Activity 36 6.0 Conclusion 38 LIST OF FIGURES](https://reader033.vdocuments.us/reader033/viewer/2022041917/5e6a0568fb4a7541d10d9339/html5/thumbnails/41.jpg)
M/s. Jarandeshwar Sugar Mills Pvt. Ltd. Pre feasibility Report
Mantras Green Resources Ltd., Nasik 38
• The raw material is bagasse produced in own sugar plant will be used as
fuel for boiler
• This industry is eco friendly and does not have adverse effect on the
quality of land, water and air.
• The industry will be taken all the necessary preventive measures to
mitigate even the small effects which may be caused by industrial
activities.
• The concept of Reduce, Recycle and Reuse is proposed in the industry.
This will result in reducing the water and air pollutants discharge to the
environment.
• The industry has adopted an effective environment management system
and environment management plan to protect the environment.
• The industry has given due priority for 33% green belt development
within and around the factory premises.
• In the vicinity of the factory there are no protected forests, sanctuary, or
any exotic flora and endangered fauna. Therefore, the proposed
expansion will not have adverse effect on the environment or the eco
system.
---------------------------