for personal use only - asx · 7/28/2015  · • bypass pipeline completed 2013 » 8.7km, 450mm...

20
To Company Announcements Office Facsimile 1300 135 638 Company ASX Limited Date 28 July 2015 From Helen Hardy Pages 20 Subject CEN Taranaki Site Tour Presentation Attached herewith is a copy of an announcement released to the NZX by Contact Energy today. Origin Energy holds 53.09% of quoted ordinary shares in Contact Energy Limited. Regards Helen Hardy Company Secretary 02 8345 5000 – [email protected] Origin Energy Limited ACN 000 051 696 Level 45 Australia Square, 264-278 George Street, Sydney NSW 2000 GPO Box 5376, Sydney NSW 2001 Telephone (02) 8345 5000 Facsimile (02) 9252 1566 www.originenergy.com.au For personal use only

Upload: others

Post on 15-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

To Company Announcements Office Facsimile 1300 135 638

Company ASX Limited Date 28 July 2015

From Helen Hardy Pages 20

Subject CEN Taranaki Site Tour Presentation

Attached herewith is a copy of an announcement released to the NZX by Contact Energy today. Origin Energy holds 53.09% of quoted ordinary shares in Contact Energy Limited. Regards

Helen Hardy Company Secretary 02 8345 5000 – [email protected]

Origin Energy Limited ACN 000 051 696 • Level 45 Australia Square, 264-278 George Street, Sydney NSW 2000 GPO Box 5376, Sydney NSW 2001 • Telephone (02) 8345 5000 • Facsimile (02) 9252 1566 • www.originenergy.com.au

For

per

sona

l use

onl

y

1

Taranaki site tour 28 July 2015 James Kilty, Chief Generation and Development Officer

Peter Kane, General Manager Operations

Fraser Gardiner, Head of Investor Relations and Strategy

For

per

sona

l use

onl

y

2

Cautionary statement

This presentation may contain projections or forward-looking statements regarding a

variety of items. Such forward-looking statements are based upon current expectations

and involve risks and uncertainties.

Actual results may differ materially from those stated in any forward-looking statement

based on a number of important factors and risks.

Although management may indicate and believe that the assumptions underlying the

forward-looking statements are reasonable, any of the assumptions could prove

inaccurate or incorrect and, therefore, there can be no assurance that the results

contemplated in the forward-looking statements will be realised.

EBITDAF and underlying earnings after tax are non-GAAP (generally accepted accounting

practice) profit measures. Information regarding the usefulness, calculation and

reconciliation of EBITDAF and underlying earnings is provided in the supporting material.

Furthermore, while all reasonable care has been taken in compiling this presentation,

Contact accepts no responsibility for any errors or omissions.

This presentation does not constitute investment advice.

Taranaki site tour 28 July 2015

For

per

sona

l use

onl

y

3

Today’s presentation

• Welcome James Kilty

• Safety briefing Paul Fougere - Head of Generation Taranaki

• Thermal update Fraser Gardiner

• Operational overview Peter Kane

Taranaki site tour 28 July 2015

For

per

sona

l use

onl

y

4

For

per

sona

l use

onl

y

5

0%

20%

40%

60%

80%

100%

FY12 FY13 FY14 FY15

% g

en

era

tio

n (

GW

h)

Generation mix

Thermal Hydro Geothermal

The investment in renewable generation has lowered Contact’s cost of energy and requires limited ongoing capital expenditure

Capital expenditure on CCGTs will be determined by

market conditions : $40-$50m for every major outage

with an 18 month lead time

-

100

200

300

400

500

600

700

FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18

$m

Capital expenditure

For

per

sona

l use

onl

y

6

Thermal assets role is changing from baseload operation to providing hydrology risk management and optionality

Taranaki site tour 28 July 2015

• Extension to gas supply agreement completed with Maui Developments Limited

» 22 and 26 petajoules over 2015-2017

» Able to move volumes between years combined with 11.3PJ of gas stored provides significant flexibility

• New long-term peaker maintenance agreement covering support and component replacements including a spare engine on-site

• Focus for the CCGTs is on managing remaining operating hours and improving operating flexibility

» 15,500 equivalent operating hours remaining between Otahuhu and TCC before major maintenance required

» Otahuhu and TCC capacity factor in FY15 24%

» Otahuhu min load improved from 220MW to 180MW

0

5

10

15

20

25

30

35

CY14 CY15 CY16 CY17

PJ

Contracted gas volumes

OMV (take-or-pay)

Maui (max)

Maui (min)

Swap

Genesis

Max contract volume only applies if min volumes taken CY15 & CY16

Peak take or pay

was 52 PJ in CY10

For

per

sona

l use

onl

y

7

Contact’s low cost renewable business combined with gas storage and peakers can support a retail business of around 7.1 TWh

Taranaki site tour 28 July 2015

0

200

400

600

800

1,000

1,200

1,400

1,600

Jan

Feb

Mar

Ap

r

May

Jun

Jul

Aug

Sep

Oct

No

v

Dec

MW

Generation and load profile

Whirinaki Peakers Hydro (50th percentile inf lows) TeRapa Geothermal Purchase position

Contact’s CCGTs are optional depending on the availability of alternative supply or the ability to secure a spark spread and recover maintenance costs

For

per

sona

l use

onl

y

8

0

400

800

1,200

1,600

2,000

0

200

400

600

800

1000

YT

D T

Js

Mo

nth

ly T

J's

FY15 gas injections and extractions

Monthly injections Monthly extractions

YTD injections YTD extractions

The role of Ahuroa gas storage is developing, adding value to the thermal operations

Taranaki site tour 28 July 2015

• Initial investment (excl Cap interest) $197m

» Assets $111m

» Gas rights $35m

» Cushion gas $51m

» Benefits realisation broken in to three stages

» Cost: avoided take-or-pay gas

» Transition: market education supporting new gas contracts

» Trading : Seasonal gas shaping and sale of gas and electricity capacity products

For

per

sona

l use

onl

y

9

The role of large thermal plants in New Zealand is likely to reduce over time, with Contact well positioned to support flexible development when it is needed

Taranaki site tour 28 July 2015

• Stratford

» Up to 400 MW of new peaking or CCGT operation consented

• Otahuhu

» Up to 400 MW of new CCGT capacity consented; consents to open-cycle Otahuhu B ~$20m

• Whirinaki

» Potential to expand or relocate and convert to gas ~$60m

• New Plymouth

» Option to repurchase land between 2023 and 2038 for electricity generation

• Ahuroa

» 2 stage options to expand injection and extraction capacity at 50 TJ/day increments ($60 - $80m)

For

per

sona

l use

onl

y

10 Thermal operations – Peter Kane

For

per

sona

l use

onl

y

11

Gas turbine: The Brayton Cycle Typical efficiency: 33% - 45%

Taranaki site tour 28 July 2015

Air inlet Compressor blades

Stator blades

Fuel in

Turbine blades

For

per

sona

l use

onl

y

12

Steam turbine – The Rankin Cycle Typical efficiency: 33 – 38%

Taranaki site tour 28 July 2015

For

per

sona

l use

onl

y

13

Combined Cycle Typical efficiency: 55% - 60%

Taranaki site tour 28 July 2015

For

per

sona

l use

onl

y

14

LMS 100 gas-fired peakers

Taranaki site tour 28 July 2015

Air Intake

Cooling Tower

Exhaust Stack

Air-to-water Intercooler

VBV Silencer

Generator

Gas Turbine Auxiliary Skid

For

per

sona

l use

onl

y

15

Ahuroa gas storage facility

Taranaki site tour 28 July 2015

For

per

sona

l use

onl

y

16

AGS provides Contact with up to 17 PJ of gas storage capacity

Taranaki site tour 28 July 2015

• ~17 PJ max working volume

• 11.3 PJ working volume as at 30 June 2015

• Connected to Stratford power stations by 2 pipelines

• Operated by NZEC (from Waihapa Production Station)

• Max reservoir pressure 3,450 psi

• 45TJ/day extraction rate (single train)

• 27 TJ/day injection rate (via Waihapa Production Station) (single train)

For

per

sona

l use

onl

y

17

AGS is connected to the Stratford power stations by two pipelines

Taranaki site tour 28 July 2015

Contact bypass

450mm dia pipeline

NZEC 200mm dia pipeline

Ahuroa

Well-site

Waihapa

Production Station

Stratford

Gas Yard

Vector Gas

Transmission Network

Stratford

Power Station

Site (TCC and

Peakers)

Piakau

Well-site

Transpower Grid

Connection

Permit 52278

NZEC

• Bypass pipeline completed 2013

» 8.7km, 450mm diameter pipeline between Ahuroa and Stratford

» Purpose to bypass Waihapa Production Station to eliminate costs, and allow for storage development of up to 170 TJ/day

» Option of 2 pipeline routes to Stratford

» Increased line-pack to support Peaker start-up

For

per

sona

l use

onl

y

18

OSIP programme – redefining process safety

Taranaki site tour 28 July 2015

For

per

sona

l use

onl

y

19

Bow tie diagrams are used to visualise the hazard being assessed

Taranaki site tour 28 July 2015

For

per

sona

l use

onl

y