fmea report
DESCRIPTION
FMEA ReportTRANSCRIPT
document.xls Printed 04:28:26,04/22/2023 Page 1 of 3
Failure modes and effects analysis (FMEA)
Project: QUAD TORC Date: 23/05/2015
FMEA Team: 20150191 - THE CENTAURS Prepared by: VISHNU ROY
SEV = How severe is effect on the customer?
OCC = How frequent is the cause likely to occur?
DET = How probable is detection of cause?
RPN = Risk priority number in order to rank concerns; calculated as SEV x OCC x DET
Process step Potential failure mode Potential failure effects Potential causes Current process controls Actions taken
10 10 10 1000 10 10 10 1000
Chassis Driver at risk 10 6 2 120 3 2 2 12
A-arms Mechanical failure Serious injury 10 3 2 60 Proper maintainance 2 2 2 8
Steering column Mechanical failure Inability to steer 9 3 Final inspection 2 54 Proper maintainance Maintainance done 2 2 2 8
Engine Mechanical failure 10 Dirty air and fuel 3 N/A 2 60 Proper maintainance Maintainance done 2 2 2 8
SEV
OCC
DET
RPN
Actions recommended
Responsibility (target date)
New SEV
New OCC
New DET
New RPN
What is the step?
In what ways can the step go wrong?
What is the impact on the customer if the failure mode is not prevented or corrected?
What causes the step to go wrong? (i.e., How could the failure mode occur?)
What are the existing controls that either prevent the failure mode from occurring or detect it should it occur?
What are the actions for reducing the occurrence of the cause or for improving its detection? You should provide actions on all high RPNs and on severity ratings of 9 or 10.
Who is responsible for the recommended action? What date should it be completed by?
What were the actions implemented? Include completion month/year (then recalculate resulting RPN).
Structural failure - Frame bends
High load or shock / Poor material design
Simulation and Analysis using software / Final inspection
Proper maintainance / Careful designing
Jayasurya M and Vishnu Roy, will be completed by 15/06/2015
Frame analysis and simulation done / Maintainance done
High load/shock / Poor material design
Lotus Suspension Analysis software / Final inspection
Jayasurya M, will be completed by 12/05/2015
Suspension analysis and simulation done
External foreign material / damage in steering linkages
Abijith Menon, will be completed by 16/06/2015
Serious injury caused by explosion
Kiran Hareendran, will be completed by 10/06/2015
document.xls Printed 04:28:26,04/22/2023 Page 2 of 3
Failure modes and effects analysis (FMEA)
Project: QUAD TORC Date: 23/05/2015
FMEA Team: 20150191 - THE CENTAURS Prepared by: VISHNU ROY
SEV = How severe is effect on the customer?
OCC = How frequent is the cause likely to occur?
DET = How probable is detection of cause?
RPN = Risk priority number in order to rank concerns; calculated as SEV x OCC x DET
Process step Potential failure mode Potential failure effects Potential causes Current process controls Actions takenSEV
OCC
DET
RPN
Actions recommended
Responsibility (target date)
New SEV
New OCC
New DET
New RPN
Fuel tank Explosion in tank / Leakage 10 1 Final inspection 2 20 Maintainance done 1 1 1 1
Tires and wheels 10 2 Final inspection 3 60 3 2 2 12
Brakes 10 3 Final inspection 2 60 Proper maintainance Maintainance done 2 2 2 8
Transmission Mechanical failure Driver at risk 9 Loose chains / Gear slip 3 Final inspection 2 54 Proper maintainance 1 1 1 1
Seats Driver at risk 5 1 Final inspection 6 30 1 1 1 1
Serious injury caused by explosion
Sparks / Overpressure / Faulty canister
Replacement / Maintainance
Jaydat Goswami, will be completed by 12/06/2015
Insufficient grip on track due to tire tread wear
Vehicle skids when the brake is applied resulting in accident
Improper inflation pressure / Misalignment
Replacement / Maintainance
Hafeez K G, will be completed by 09/06/2015
Replaced / Maintainance done
Insufficient friction provided by the brake pads and wheels
Vehicle does not slow down when the brake is applied resulting in accident
External foreign material reduces friction / Damage in brake cables
Anand Sivasankar, will be completed by 14/06/2015
Vishnu Santhosh, will be completed by 10/06/2015
Replaced / Maintainance done
Loose seats causing vibrations and discomfort
Seat mounting bolts/nuts not fully tightened
Replacement / Maintainance
Godvin Abi Mathew, will be completed by 10/06/2015
Replaced / Maintainance done