fluvial hydraulic modelling report 1. basic model information · hydraulic model summary report –...
TRANSCRIPT
-
Hydraulic Model Summary Report – Ellington Brook 1
Fluvial Hydraulic Modelling Report
1. Basic Model Information
Model Name: Ellington Brook
Primary Watercourses / Water Bodies Ellington Brook/Alconbury Brook
Designation Main river
Model ID Scenario Flood Event
Alconbury_and_Ellington_JE2014.dat
Alc_Eli_0025yr_23hr_28_JE2014.ief
Alc_Eli_0025yr_23hr_28_JE2014.tcf
Existing Model 4% AEP (1 in 25 years)
Alconbury_and_Ellington_JE2014.dat
Alc_Eli_0100yr_23hr_28_JE2014.ief
Alc_Eli_0100yr_23hr_28_JE2014.tcf
1% AEP (1 in 100 years)
Alconbury_and_Ellington_JE2014.dat
Alc_Eli_0100yrCC_23hr_28_JE2014.ief
Alc_Eli_0100yrCC_23hr_28_JE2014.tcf
1% AEP +CC (1 in 100 years + 20%)
Alconbury_and_Ellington_JE2014_Design.dat
Alc_Eli_0025yr_23hr_28_JE2014_Design.ief
Alc_Eli_0025yr_23hr_28_JE2014_Design.tcf
Scheme Model 4% AEP (1 in 25 years)
Alconbury_and_Ellington_JE2014_Design.dat
Alc_Eli_0100yr_23hr_28_JE2014_Design.ief
Alc_Eli_0100yr_23hr_28_JE2014_Design _v3.tcf
1% AEP (1 in 100 years)
Alconbury_and_Ellington_JE2014_Design.dat
Alc_Eli_0100CCyr_23hr_28_JE2014_Design.ief
Alc_Eli_0100CCyr_23hr_28_JE2014_Design.tcf
1% AEP +CC (1 in 100 years + 20%)
2. Survey Data and Base Mapping
2.1 Base Mapping: 1 to 10,000 Scale Raster
Reference:
TL1070, TL2070
2.2 DTM for 2D Model domain:
As per Environment Agency 2014 Alconbury Brook model
2.3 River channel/Structures survey
As per Environment Agency 2014 Alconbury Brook model
-
Hydraulic Model Summary Report – Ellington Brook 2
3. Baseline Hydraulic Model Schematisation
3.1 Software: 1D domain: Isis Version 3.7.0.233 (64 bit - Single Precision)
2D domain(s): 2012-05-AE-iSP-w64
3.2 Baseline model: Environment Agency 2014
3.3 Baseline Model Reference
Alconbury_and_Ellington_JE2014.DAT
Alc_Eli_0025yr_23hr_28_JE2014.ief
Alc_Eli_0100yr_23hr_28_JE2014.ief
Alc_Eli_0100yrCC_23hr_28_JE2014.ief
Alc_Eli_0025yr_23hr_28_JE2014.tcf
Alc_Eli_0100yr_23hr_28_JE2014.tcf
Alc_Eli_0100yr_23hr_28_JE2014.tcf
3.4 Model area / extent: The Ellington Brook model covers the northwest extent of the Great Ouse model study area and includes Ellington Brook and Alconbury Brook watercourses, running along the A14 and A1 respectively. The 1D model includes the Ellington Brook for approximately 10 km and Alconbury Brook for 17 km. The 2D model boundary follows the shape of the two watercourses and includes the area of Huntingdon downstream of the 1D model boundary.
See Figures 1, 2 and 3 below for study area and model extents.
-
Hydraulic Model Summary Report – Ellington Brook 3
Figure 1: Areal Extent of Ellington Brook
-
Hydraulic Model Summary Report – Ellington Brook 4
Figure 2 Model Schematisation
Alconbury Brook
Ellington Brook
-
Hydraulic Model Summary Report – Ellington Brook 5
Figure 3: Model schematisation in the proximity of the proposed scheme
Alconbury Brook
Ellington Brook
Alconbury Brook Realignment
-
Hydraulic Model Summary Report – Ellington Brook 6
3.5 Model reaches: The following model reaches as shown on the maps above have been defined in the model:
Watercourse name Upstream model node Downstream model node
Ellington Brook E12.80 E0.00
Alconbury Brook Al_2050 Al_0000
Total model length (km): 10km (Ellington Brook), 17km (Alconbury Brook)
3.6 Scheme Structures: There are no structures in the baseline model which are affected by the proposed A14 scheme.
3.7 Floodplain schematisation
Floodplain areas have been modelled in 2D using a linked Isis – Tuflow schematisation.
3.8 Model Boundaries - Inflows
ReFH units ‘Al_2050’ and’E12.80’ are input into the model as point inflows at the upstream end of Alconbury Brook and Ellington Brook respectively. Re-FH units for downstream sub-catchments ‘13.2000hyd’ and ‘al_0481hyd’ on Alconbury Brook and ‘E5.00hyd’ on Ellington Brook are entered as distributed lateral type.
Peak runoff (m3/s) for each unit is provided in the table below.
Input Node in the Hydraulic Model
Re-FH peak runoff (m3/s)
4%AEP 1% AEP 1%AEP + CC
Al_2050 13.329 16.155 19.269
E12.80 18.121 21.902 26.123
13.2000hyd 28.807 33.904 40.429
al_0481hyd 4.515 5.175 6.210
E5.00hyd 13.097 15.783 18.831
3.9 Model Boundaries – Downstream Conditions
The outflow at the downstream end of the 1D model extent is modelled using a normal depth boundary applied at node ‘al_0000’. The boundary is significantly remote from the area of interest for the proposed scheme, and therefore is not considered to influence the scheme scenario results.
-
Hydraulic Model Summary Report – Ellington Brook 7
4. Model Build – Scheme Model
4.1 Scenario Definition
The proposed scheme involves the widening of the A1 adjacent to Alconbury Brook and Ellington Brook, as well as the addition of a link road between the A14 and A1 highways.
The proposed link road crosses the Ellington Brook watercourse and also spans over the A14, requiring a bridge crossing to be constructed. This road and surrounding embankments represent a significant increase in ground levels in this area where the road slopes down for 450 metres from the A14 flyover to tie into the level of the A1.
The widening of the A1 requires the minor realignment of a meander in the Alconbury watercourse. This is considered to have insignificant impact on the existing flood risk and therefore was not represented in the scheme model. In addition the channel realignment and the increase in A1 embankment footprint are too small to be captured effectively by the model grid.
The scheme components are shown in the figure below.
4.2 Model Extent of the Affected area
Figure 4 below shows the Preliminary Design model schematisation.
Figure 4: Proposed road layout and model schematisation
-
Hydraulic Model Summary Report – Ellington Brook 8
ISIS 1D Model
4.3 Modelling approach for the new structures
A Bridge (USBPR1978) unit was added to the ISIS model to represent the road bridge across Ellington Brook (ISIS unit E1.10u). The opening span and soffit level have been chosen based on design specifications and preliminary run results.
A soffit of 14mAOD was selected to allow 600mm of freeboard above the baseline 1%AEP + CC results. The parapets of the bridge were specified to be set back 2m from the banktops on either side, which resulted in the bridge opening spanning15m.
4.4 Model Units added/removed
Two copies of ISIS cross section E1.0 were created and named E1.1u and E1.1d. These cross section units were placed at the proposed Ellington Brook bridge crossing location, between E1.2 upstream and E1.0 downstream. A Bridge (USBPR1978) unit was placed between E1.1u and E1.1d.
4.5 Culvert Inverts N/A
4.6 Hydraulic Roughness of proposed units
The reach Manning’s roughness coefficient of n = 0.04 has been maintained for the added sections.
Tuflow 2D Model
4.7 Modelling approach for the new structures
The scheme is modelled in Tuflow using ‘z-lines (thick)’ to represent the road and ‘z-shapes’ to represent the embankments surrounding the road.
4.8 Design Detail Sources
Scheme location, extent, and design road levels were taken from:
‘design model 150814.dwg’
-
Hydraulic Model Summary Report – Ellington Brook 9
5. Hydraulic Model Outputs
5.1 Model Simulation Water level outputs have been extracted for the existing and scheme model.
5.2 1D Water Levels - Ellington Brook A1 link Road
Existing Model Maximum Stage values for the Existing Model are provided in the table below at key locations.
Location Model node
Peak Water level (mAOD)
4%AEP 1% AEP 1% AEP + CC
1.05km u/s of proposed link road
E2.2 14.175 14.182 14.187
454m u/s of proposed link road
E1.6 13.549 13.556 13.573
Immediately upstream of link road
E1.2 13.130 13.178 13.221
Immediately downstream of link road
E1.0 12.955 13.057 13.120
566m d/s of proposed link road
E0.58 12.620 12.738 12.815
Preliminary Design Maximum Stage values for the Design Model are provided in the table below at key locations. The change in water level between the Existing Model and the Preliminary Design Model are also included.
Location Model node
Peak water level (mAOD) and water level change (m)
4% AEP 1% AEP 1% AEP + CC
(mAOD) (m) (mAOD) (m) (mAOD) (m)
1.05km u/s of proposed link road
E2.2 14.175 0.000 14.181 -0.001 14.187 0.000
454m u/s of proposed link road
E1.6 13.562 0.013 13.574 0.019 13.604 0.031
Immediately upstream of link road
E1.2 13.157 0.027 13.216 0.038 13.281 0.060
Immediately downstream of link road
E1.0 12.955 0.000 13.064 0.007 13.133 0.013
566m d/s of proposed link road
E0.58 12.620 0.000 12.741 0.002 12.818 0.003
Long Section
Figures 5, 6 and 7 present a comparison between maximum stage for the Existing and Scheme Models for the 4%,1% and 1% + CC AEP.
-
Hydraulic Model Summary Report – Ellington Brook 10
5.3 1D Water Levels - Ellington Brook A1 culvert
Existing Model Maximum Stage values for the Existing Model are provided in the table below at key locations.
Location Model node
Peak Water level (mAOD)
4%AEP 1% AEP 1% AEP + CC
~530m upstream of A1,
u/s of proposed Ellington
Brook Bridge
E1.10u 13.016 13.090 13.142
Upstream of A1 culvert E0.58 12.620 12.738 12.814
Downstream of A1
culvert E0.48 12.556 12.657 12.705
176m downstream of A1 E0.40 12.476 12.585 12.635
Preliminary Design Maximum Stage values for the Design Model are provided in the table below at key locations. The change in water level between the Existing Model and the Preliminary Design Model are also included.
Location Model node
Peak water level (mAOD) and water level change (m)
4% AEP 1% AEP 1% AEP + CC
(mAOD) (m) (mAOD) (m) (mAOD) (m)
~530m upstream of A1,
u/s of proposed Ellington
Brook Bridge
E1.10u 13.02 0.004 13.098 0.008 13.154 0.012
Upstream of A1 culvert E0.58 12.620 0.000 12.740 0.002 12.817 0.003
Downstream of A1
culvert E0.48 12.556 0.000 12.658 0.001 12.706 0.001
176m downstream of A1 E0.40 12.476 0.000 12.586 0.001 12.636 0.001
-
Hydraulic Model Summary Report – Ellington Brook 11
5.4 1D Water Levels - Alconbury Brook at channel re-alignment location
Existing Model Maximum Stage values for the Existing Model are provided in the table below at key locations.
Location Model node
Peak Water level (mAOD)
4%AEP 1% AEP 1% AEP + CC
Alconbury Brook at
channel re-alignment
location
al_0760ds 11.312 11.288 11.252
al_0720 10.973 10.989 10.915
al_0680 10.587 10.649 10.550
Preliminary Design Maximum Stage values for the Design Model are provided in the table below at key locations. The change in water level between the Existing Model and the Preliminary Design Model are also included.
Location Model node
Peak water level (mAOD) and water level change (m)
4% AEP 1% AEP 1% AEP + CC
(mAOD) (m) (mAOD) (m) (mAOD) (m)
Alconbury Brook at
channel re-alignment
location
al_0760ds 11.312 0.000 11.288 0.000 11.252 0.000
al_0720 10.973 0.000 10.989 0.000 10.915 0.000
al_0680 10.587 0.000 10.649 0.000 10.550 0.000
-
Hydraulic Model Summary Report – Ellington Brook 12
Figure 5: Maximum Stage for Ellington Brook in ISIS 1D model – 4% AEP
-
Hydraulic Model Summary Report – Ellington Brook 13
Figure 6: Maximum Stage for Ellington Brook in ISIS 1D model – 1% AEP
-
Hydraulic Model Summary Report – Ellington Brook 14
Figure 7: Maximum Stage for Ellington Brook in ISIS 1D model – 1% AEP + Climate Change
-
Hydraulic Model Summary Report – Ellington Brook 15
5.5 2D Water Levels
The area surrounding the proposed road link has been interrogated in order to compare the effects of the proposed scheme. The location of the points where water levels have been extracted is shown in Figure 8.
Figure 8: Location of the Interrogation Points
For each point water levels have been extracted for the 4%AEP, 1%AEP and 1%AEP + CC flood events. Water levels extracted for all flood events are presented in the following tables:
-
Hydraulic Model Summary Report – Ellington Brook 16
4%AEP Flood Event
Point ID Baseline Water Level (mAOD)
Design Water Level (mAOD)
Change in Water Level (m)
1 13.258 13.259 0.001
2 13.249 13.250 0.001
3 12.964 13.270 0.306
4 13.060 13.086 0.026
5 12.947 12.981 0.034
6 12.909 12.910 0.001
7 12.963 12.960 -0.003
1%AEP Flood Event
Point ID Baseline Water Level (mAOD)
Design Water Level (mAOD)
Change in Water Level (m)
1 13.302 13.304 0.002
2 13.287 13.288 0.001
3 13.071 13.306 0.236
4 13.091 13.144 0.053
5 13.032 13.052 0.020
6 13.010 13.008 -0.002
7 13.069 13.073 0.004
1%AEP + CC Flood Event
Point ID Baseline Water Level (mAOD)
Design Water Level (mAOD)
Change in Water Level (m)
1 13.334 13.338 0.004
2 13.312 13.315 0.003
3 13.133 13.357 0.224
4 13.143 13.198 0.055
5 13.105 13.118 0.013
6 13.081 13.082 0.002
7 13.130 13.140 0.010
Flood Extents The flood extents for the Existing Model and the Scheme Model for each flood event are presented in Figures 9-11.
-
Hydraulic Model Summary Report – Ellington Brook 17
Figure 9: Flood extent for the Existing Model (blue) and the Scheme model (green) for the 4%AEP flood event.
-
Hydraulic Model Summary Report – Ellington Brook 18
Figure 10: Flood extent for the Existing Model (blue) and the Scheme model (green) for the 1%AEP flood event.
-
Hydraulic Model Summary Report – Ellington Brook 19
Figure 11: Flood extent for the Existing Model (blue) and the Scheme model (green) for the 1%AEP +CC flood event.
-
Hydraulic Model Summary Report – Ellington Brook 20
Effect of proposed Structures
The modelled scenario with the proposed scheme shows minor increases of in-channel water levels immediately upstream of the proposed scheme, in the order of 50mm for the 1%AEP event. There is little to no change in water level seen from approximately 800m upstream of the structure or for in channel water levels downstream of the structure (see Section 13.2).
The 2D scheme model results also show a general increase of water levels for the area surrounding the proposed road location. Little to no impact is observed on water levels beyond about 150 metres from the proposed road, and no change is present throughout most of the modelled area. The flood extent changes slightly upstream of the proposed structure, with a small number of additional cells wetted in the “with scheme” scenario.
A significant level change due to the scheme is observed on the right bank immediately upstream of the link road crossing. Here a small area (1000m
2)
adjacent to the A14 and the link road embankments sees significant interruption to the existing flood flow path. This interruption causes an increase in maximum level of approximately 240mm for the 1%AEP event (see inspection point 3 in Section 5.3).
The scheme does not cause any effect on water levels at the A1 crossing of Ellington Brook because the existing culvert extent is significantly greater than the full width of the proposed highway widening. Therefore no modification to the culvert will be required, and the design and existing simulation results in this location are seen to be almost identical
On Alconbury Brook where the watercourse runs next to the A1 highway widening, as stated previously in section 4.1, the extent of the topographic modification is too small to be represented in the hydraulic model. As such Design and existing simulation results in this location are identical.
6. Key model assumption and limitations
The supplied hydraulic models were assumed to be fit for purpose and no detailed review was undertaken for the purpose of Flood Risk Assessment of the A14 scheme.
A bridge unit of type USBPR1978 has been used assuming this is fit for purpose for the type of proposed bridge in the specifications (RC with abutment and wing walls). This bridge unit was accommodated using the cross section E1.2 and using the clearance level and length of the deck provided by the design team.
No calibration or sensitivity testing simulations were carried out as part of this hydraulic modelling exercise.