flowchart procedure to assess the condition

Upload: jessica-sanders

Post on 07-Jul-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 Flowchart Procedure to Assess the Condition

    1/7

    5 6

    IEEE Transactions on Energy Conversion, Vol.

    5 No.

    3, September

    1990

    FLOWCH RT PROCEDURE TO

    ASSESS

    THE CONDITION

    OF TURBINE GENER TOR INSUL TION

    G.C. Stone,

    I.

    C u l b e r t a n d H. Dhiran i

    O n t a r i o H y d r o

    Toronto

    C a n a d a

    KEY

    WORDS: Rotating machines, Wind ing insulation, Life

    ABSTRACT Maintenance planning and life extension programs require

    that the condition o the insulation in the rotor and stator windings of

    generators be assessed. Unfortunately the large number of insulation

    deterioration processes w hich can aflict windings together with the lack

    o

    a universal diagnostic test which is sensitive to all these deterioration

    processes m akes condition assessment dincult . Th b paper presents a

    method using lowcharts which indicate a step-by-step procedure to assess

    insulation condition o turbine generators. Information on likely

    deterioration processes which arise fro m the insulation system

    characteristics and operating practice is firs t collected. Then on-line

    monitoring and off-line tests are done to determine ifproblems could be

    occurring. Finally depending on the outcome

    of

    the previous steps

    more

    extensive tests and detailed inspections usually requiring a significant

    outage are performed. Although the procedure itself is stmighrfonvard it

    is best implemented by engineers with considerable experience in this

    field. The lowcharts

    w ll

    indicate to nonexperts the complexity o reliably

    assessing insulation condition.

    I N T R O D U C T I O N

    Planning maintenance for turbine generators requires that the condition of

    the stator and

    rotor

    winding insulation systems used in

    these

    machines

    be

    known. Recently, the desire to extend the life of generating stations has

    increased the need for insulation system condition assessment procedures.

    Although general assessment procedures

    are

    available from machine

    manufacturer maintenance manuals and IEEE uidelines [l] , many utilities

    must depend on experts from machine manufacturers or other consultants

    to help perform detailed insulation assessments on a particular machine.

    In order to make assessment techniques more generally available to

    utilities, and to indicate to maintenance engineers the complexity

    of

    the

    task, flowcharts have been prepared

    as

    part

    of

    EPRI project

    Rp

    2577-1.

    These flowcharts present a logical process for assessing machine

    insulation condition. Although considerable experience is still required to

    interpret information collected as part of the assessment procedure, the

    flowcharts will

    be

    instructive

    to

    the nonexpert in understanding the wide

    variety of information required before a realistic assessment can

    be

    made.

    This paper presents flow charts for assessing the condition of the rotor and

    stator winding insulation system s of large turbine generators and is largely

    taken from Reference [2], which presents further details, and procedures

    for other types of machines. Although space limitations preclude the

    inclusion of examples of the use of these flowcharts here, four practical

    examples are contained in [2].

    The procedure for assessing insulation condition is not simple since

    several dozen possible failure mechanisms may occur in stator and

    rotor

    windings [21. The large number of deterioration mechanism s results from:

    90

    W M

    OQL 2 EC

    b y t h e I EE E R o t a t i n g M a c h in e r y C o m mi t te e of t h e

    IEEE P ow er E n g i n e e r i n g S o c i e t y f o r p r e s e n t a t i o n

    a t

    t h e IE EE /P ES 1 9 9 0 W i n t e r M e e t i n g , A t l a n t a , G e o r g i a ,

    F e b r u a r y 4 - 8 1 9 9 0 .

    A u g u s t

    30

    1 98 9; m ade a v a i l a b l e f o r p r i n t i n g

    December

    6, 1989.

    A p per r e co m m e n de d a n d a p p r o v e d

    Manuscript s u b m i t t e d

    the wide variety of insulation systems dcveloped over the years,

    which often respond quite differently to various thermal,

    mechanical and electrical stresses.

    the differing design philosophies of the major manufacturers on

    the same

    or

    different insulations which result in different design

    stress levels being placed on the insulation.

    the different operating (for example base-load and peaking) and

    maintenance (no maintenance to proactive maintenance) policies

    of the utilities.

    Assessing insulation condition is further complicated because there is no

    single test

    or

    simple inspection which can easily track the condition of the

    insulation under all possible deterioration mechanisms

    [3]

    When

    combined, the abov e factors result in a large number of possible insulation

    deterioration mechanisms, and the symptoms which are used to gauge the

    insulation condition are often very diverse and difficult to measure.

    ASSESSMENT SEQUENCE

    The procedun: embodied in the flowcharts is based on collecting and

    assessing information in a sequence which requires increasing levels of

    effort and cost. The proposed sequence is:

    collect information a) to determine likely deterioration

    mechanisms and average lifetimes (b) from on-line monitoring

    determine if deterioration is occurring

    -

    analyzc the above information

    perform off-line tests and inspections which require only a min or

    outage

    -

    do a detailed asscssment, if required, including an in-depth

    inspcction and special tests. This requires a major outage.

    Collecting background information is

    a

    critical step which allows the

    maintenance enginecr to select the

    tests

    and inspections which will

    be

    most sensitive

    to

    the likely failurc mechanisms . The insulation systems

    and operating environment in

    a

    particular machine should

    be

    identified,

    since each generic t y p and operating mode can give r ise

    to

    particular

    failure mechanisms

    [2, 41

    lndustry databases compiled by the NERC

    Generator Availability Data System and Edison Electric Institute

    committees can warn of generic problems and reliability of particular

    machine types. By carefully reviewing background information, the

    relevant tests and inspcctions can be selected from those presented in the

    flowcharts to identify problem s specific to the machine being examined.

    Oncc background information has been collected and assessed, the specific

    procedurc to follow is shown in the flowcharts in Figures and 2. The

    assessment techniques provide two altemative results which are

    "Condition Acceptable" and "Correctivc Action is Required".

    The

    latter

    refers to conditions where failure has occurred,

    or

    significant aging has

    been detected. No attempt has been made to indicate how quickly

    correctivc action should

    be

    taken. This will be dictated by the particular

    circumstances under which the assessment is being made, the degree of

    detcrioration, and the future operating mode of

    the

    machine.

    Thc flowcham have thrcc subscctions (On-Line Monitoring, Off-Line

    Tests, and Detailcd Asscssmcnt) which are cntered by making use of the

    appropriatc logic lor ;I particular typc of asscssment. The assessment

    0885-8%9/90~-0546$01.00 990 IEEE

    I 7

  • 8/18/2019 Flowchart Procedure to Assess the Condition

    2/7

    547

    START

    SSESSMENT

    PARTUL

    DISCHAROE

    ESTS

    S E E FE U R E l l b )

    Figure

    l a )

    Sequence for collecting on-line monitoring and off line est results for .stator uindings.

    process is relevant for turbine generators

    as

    well as motors

    and

    hydrogenerators.

    This

    procedures outlined in

    the

    charts should preferably be determined by

    always commencing at the START point and following the logic

    appropriate for a particular situation since this will ensu re that no test or

    inspection technique has been ignored. Note that not all techniques may

    be necessary to assess the condition of a machine and completion of all

    possible tests will not necessarily result in a definitive assessment. The

    general logic that determines which of the major subsections is entered

    first is mainly influenced by inspection and maintenance strategies and

    intcrprctations made from on-line monitoring results.

    Many t a ts and inspcctions arc refcrcnced in the flowcharts. For the most

    part, these tests and inspcctions can bc don e with commercially available

    apparatus and have bccn dcmonstrdtcd to provide useful information.

    Further details on wcll-establishcd tests and inspections can be found in

    Rcfcrcncc

    I 1

    . Descriptions of morc modem tests, as wcll as a critical

    rcvicw of the usefulness and applicability

    of

    all the

    tests

    referred to in

    the

    flowcharts, are contained in Reference

    [2].

    The proper evaluation of

    winding condition requires correct interpretation of the results of tests and

    inspections. IEEE Standard

    56

    [11 and other associated standards,

    machinc manufacturer’s data, as wcll as Reference [2] can be used

    to

    aid

    intcrprctation. Only with cxpcriencc can the maximum amou nt of

    infonnatio n hc extracted from visual inspections.

    Note that for experienced insulation cxperts, the best information on

    insulation condition comes from a careful visual inspection

    of

    the

    componcnts which makc up the insulation system. Unfortunately,

    a

    good

    visual inspcction is intrusive and oltcn requires significant disassembly

    of

    thc stator or rotor winding, laking morc timc than most tests. Thu s when

    suikible

    tcsts

    arc avail;rblc, (hey arc usually

    less

    costly and mo re desirable

    tlim dctailcd inspcctions.

  • 8/18/2019 Flowchart Procedure to Assess the Condition

    3/7

    548

    E S T Y A T EEPNRS

    R W R D

    bNDO S T S

    I

    UROELUCS

    W N D l f f i

    SloE

    C L E A R I N C E

    bNDICY(TNES.5

    C H E C K S

    E S T U A T E

    RPNRG

    W R D

    AND

    O S T S

    Figure

    l b )

    Detailed assessment procedurefor

    stator

    windings

    ASSESSMENT OF S T A T O R W I N D I N G C O N D I T I O N

    The genera l logic for the assessm ent of stator winding insulation systems

    is shown in Figure 1. The detailed assessment procedures cover the

    following subsystems for large turbine generators:

    Groundwall and Phase Insulation

    -

    Slot Wedging

    Endwinding Bracing

    Groundwall an d Phase Insulat ion

    Winding groundwall and phase insulation condition can be assessed, to

    some extent, at any of the three levels indicated in the flow charts, i.e., by

    On-line Monitoring, Off-line Tests and by the procedures defined in the

    Detailed Assessment section. However,

    a

    Detailed A ssessment is usually

    required to obtain a reliable evaluation

    of

    groundwall and ph ase insulation

    condition, since existing on-line monitoring and off-line tests are not

    comprehensive enough.

    Only very general assessments can be made with On-Line Monitoring, but

    the collected information allows decisions

    to be

    made on the need

    for Off-

    Line Tests,

    or

    Detailed Assessments. The amount

    of

    information collected

    depends on the

    type

    number, loca tion and sophistication of the monitoring

    devices fitted. Most generators are equipped only with voltage and current

    relays, hydrogen leak detectors and embedded tem perature

    sensors ore

    extensive diagnostic information is available if the ge nerator is equipped

    with condition

    or

    core) monitors (GCMs),

    or

    on-line partial discharge

    testing is possible.

  • 8/18/2019 Flowchart Procedure to Assess the Condition

    4/7

    549

    I

    MEASURE

    INSUL TION

    RESISTANCE AND

    PCi RIZITIOh

    INDEX

    DETNLED

    ASSESSMENT

    Sea Fgure qb)

    SURGE TEST

    IMPEDANCE

    TEST

    AN YO R AL L

    SEOUENCE OPTIONAL

    TURN AND

    ACCEPTABLE

    Figure

    2 a) Sequence for collecting on-line monitoring

    and

    off-line test results fo r turbine generator rotor

    windings

    More

    information on the groundwall insulation condition can be obtained

    from off-line tests. Thcs e tcsts will indicate eithcr that the groundwall

    insulation is generally in good condition, or that significant deterioration,

    or failure, has occurred and a detailed assessment is required. One

    or

    more

    of thc tests indicated in Figure 1 can be performed to provide such

    information.

    A

    satisfactory insulation condition may be indicated by the

    following rcsults:

    withstanding an ac or dc or very low frequency hipot test

    - high insulation resistance 100 M R or more) and, in gencral, a

    polarization indcx of

    2.0

    or more

    low partial discharge lcvels, and if prcvious partial discharge tests

    wcrc performed, no significant increasc in partial discharge

    activity

    no significant incrcasc in dissipation factor and/or tip-up valucs

    from those obtaincd in previous tests

    A dctailcd asscssment may

    bc

    prudent if onc

    or

    a combination of the above

    tcst results arc not achicvcd. Sincc of'[-line tests may not detect aging

    during the ca rly svagcs or dcterioration, it is important to appreciate that

    such tests cannot givc complete assurance

    of

    long term reliability. For this

    reason, periodic (c.g., cvery 5 ycars) detailed assessmcnts should be m ade.

  • 8/18/2019 Flowchart Procedure to Assess the Condition

    5/7

    550

    NO  

    RETNNINO

    0

    R

    MdMYENT

    SLOT WEDGE

    UID

    P M I K

    OR

    CRICKS

    C l

    VISUALNSPECTION

    FOR GING

    INSULATION

    RESISTINCE

    INDEX

    TESTS

    AW EPTABL

    4

    lNSULATION

    pq

    EST

    mO W VO L TME

    mURGE

    ESTIMATE

    R E W IR E DEPAIRS

    AND COSTS

    ASSESS ALL

    REPAIRSAND

    OSTS

    R E P U R W

    E P U C E

    Figure

    2 b)

    Detailed assessment procedure for rotor windings

    As

    implied in Figure 1, a detailed assessment requires that the rotor be

    removed

    to

    permit

    a

    visual cxamination of the groundwall insulation

    condition in the slot to dctermine if the insulation is puffy, discolored or

    has been eroded. In the cndwinding

    area,

    there should be no signs of

    clcctrical tracking,

    or

    insulation powdering

    as

    a result of partial

    discharges. Partial discharge tests can help localize the most severe

    dctcrioration sites. If partial dischagc tests can not be performed easily,

    individual groups of bars can be isolatcd to permit dissipation factor tip-up

    testing.

    Slot Wedging

    Where on-line partial discharge testing is fcasible,

    a

    comparison of

    the

    output signals obtained with various loads on the machine

    [2]

    makes it

    possible, with expcricncc, to identify

    loose

    slot wedging

    and

    packing.

    Whcn loose slot wcdging and/or packing is detectcd by such techniques, a

    dctailcd assessment is required to determine the cxtcnt of such

    deterioration and the necessary corrective action.

    For a detailed assessment of the slot wedging condition, the machine must

    bc

    disassembled and carefully examined visually for abrasion, cracking,

    migration, fretting, or powdery residues from relative movement betwecn

    slot

    components. In addition

    to using the

    visual symptoms, the following

    tcsts [2]will check

    for

    coil tighincss in the slot for large machines:

    stator wedge "tap"

    t a t to

    sec

    i f

    some wedges are loose

    (commercial wcdgc tighincss

    tcstcrs

    could also be employed)

    a side-clcnnncc

    test

    pcrfoonncd with a fceler gauge

    to

    determinc if

    the bars arc tightly hcld against the sidc of the

    slot

    a rcsistance tcst to dcicrminc the contact resistance

    of

    thc bar to

    thc iron.

  • 8/18/2019 Flowchart Procedure to Assess the Condition

    6/7

     

    The condition of the slot wedging and packing can he considered

    ;icccptahlc i f thcrc arc no visual symptoms

    of

    serious looseness, and the

    test rcsults arc acccptahlc. Detailed assessments are recommended every

    live years, or sooner,

    i

    on-line partial discharge monitoring indicates

    cvidcncc of bar looscncss.

    Endwinding Hrac ing

    At present there are two available approaches for

    a

    of cndwinding bracing: (1) on-line endwinding vibra

    gives

    a

    general indication,

    (2)

    impact resonance tests and a visual

    inspection that require the machine

    io be

    disassemhlcd.

    The k s t means of cffcctivcly assessing the condition of the cndwinding

    bracing in an operating machine is to install vibration sensors on the

    cndwindings and monitor their outputs. The present state-of-the-art

    approach is to install a few strategically located non-metallic transducers

    on the cndwindings of a machine with a bracing system that is in good

    condition. Significant increases in the vibration levels over time may

    indicate that thcrc is substantial dctcriordtion in the bracing system,

    requiring a detailed assessment lo determine ihc cause.

    Access to the cndw inding area is needed

    to

    perform

    a

    detailed assessment.

    Although fairly sophisticated test equipment and expertise is required,

    cndwinding vibration signature analysis is an effective means

    of

    detecting

    dctcrioralion in large gcncl.ators. Signilican t changes in resonant

    Ircqucncics bctwccn successive tcs ts can idcntily

    the

    prcscncc of aging in

    its carly stiigcs.

    The endwinding bracing sysicm is c;ipablc

    of

    providing acccptable support

    to the stator windings for at least the next few years if the following

    critcri;i arc met .

    thcrc arc no signs of broken, cracked, loose or dislodged

    components.

    thcrc is no cvidcncc

    of

    dusting from abrasion or partial discharge,

    or cracking 1 comp onent intcrCnccs.

    . thcrc h as bccn no signilicanl change in endwinding structural

    rcsonani frcqucncics and nonc of llicsc f'rcqucncics is close io the

    predominant forcing lrcqucncics o f 120 Hz and rotational speed.

    Signs of minor deterioration arc often difficult io assess, especially in thc

    case of hairline cracks at component interfaces. Therefore, some

    cxpcricncc is rcquircd

    to dctcrminc

    whcthcr any corrective action is

    required when minor deterioration is

    detected.

    ASSESSMENT

    OF

    ROTOR INSULATION CONDITION

    The importance

    of

    keeping turbine generator outages to

    a

    minimum has

    led

    to

    the develo pment of fairly reliable on-line and off-line techniques to

    detect faults in rotor windings. Unfortunately there are no effective on-

    line or off-line assessment method s ihat will detect deterioration prior to

    failure. The presen ce of aging in its early stages can therefore only bc

    obtained by

    a

    direct visual examination of the insulation system.

    In most

    cases this requires machine disassembly and rotor removal. Figure 2

    outlines the procedu re for assessing turbine generator rotor windings.

    Both turn-to-turn shorts and ground insulation failures can be detected

    from on-line monitoring. Rotor tum insulation failures are indicated by

    the following symptoms:

    variations in rotor shaft and/or bearing housing vibration levels

    with varying excitation current, while holding the terminal voltage

    approximately constant,

    unusual magnetic flux patterns in

    the

    air gap, which can be

    detected by air gap search coil measurements during normal

    machine operation [2].

    Thc most dclinitc indiciition of thc prcscncc and numhcr

    of

    short circuited

    turns is given by iiir gap sciii-ch coil mc;isurcmcnts. A machine

    fitled

    with

    such coils allows the rotor t u rn insulation to he monitored to determine

    whcthcr the number

    of

    tum shorts is increasing. If an air gap search coil is

    not l i l t ed or on-line search coil measurements are not conclusive, then it

    may

    bc

    necessary to pcrlonn an off-line test to vcrify the prcscncc ofturn-

    io- urn shon circuiis. The urgency with which corrective action should

    be

    taken depends on

    th e

    number

    of.

    short-circuited turns and ,

    to some

    extent,

    the cause. If. only a few turns arc shon cd, it may he possible to run the

    machine until the next scheduled outage, if no additional shorts develop

    within

    this

    time and if the shaft and bearing vibration levels and the rotor

    temperature continue to be satisfactory.

    The prcscncc of rotor winding ground faults can

    bc

    detected by monitors

    that arc fitted on most turbine generators. A single ground fault does not

    usually result in a need for immediate shutdown unless

    past

    expcrience

    indicates that this is required

    to

    reduce consequential damage.

    Even if

    immediate shutdown is not considered nccessary, the machine should be

    made available for off-line tests and

    a

    possible detailed assessment of rotor

    insulation condition at the earliest opportunity. The major concern is that

    ;I second ground Pault, with resulting severe rotor forging or endwinding

    retaining ring dam age, may develop.

    Rotor tum-to-turn short circuits and ground faults can often

    be

    verified by

    off-line tests. Some of thcsc icsts may also detect general deterioration of

    ground insulaiion. Off-line tests listed below and summarized in [21, are

    available:

    -

    an open circuit

    test to

    mciisurc generator output voltage versus

    licld

    current

    ;I roior winding impcdancc test with rotor installed

    - 3 iimc dom ain rcllcctomciry (TDR) surge test for shorted tums

    an air gap llux test with

    the

    stator winding open- or short-

    circuited.

    f thc

    rotor is

    llttcd

    with sliprings that allow the measurement of

    impcdancc o r surge tcsring w hile

    the

    rotor speed is varied, then the imp-

    cdancc

    and

    TDR

    tests

    will give more reliable resulis. Also, the use

    of.

    an

    air gap search coil with the stator winding short circuited and excitation

    applied

    to

    the licld winding

    can

    provide i more dcfiniic indication of

    shorted turns. shorted turns arc confirmed by one or more of thcsc tests,

    then

    a

    detailed assessment will be required to determine the likely cause

    of

    the

    shorted

    turns, their localion and the condition of the remaining turn

    insulation . Note that

    some types of tum

    short circuits may disappear when

    the machine is

    shut

    down.

    I

    the rotor winding Icads arc readily acccssihlc through sliprings, or by

    disconncction, some g eneral indicators of the ground insulation condition

    can bc obtained from insulation resistance, polarization index and hipot

    tests.

    When

    one or all 1 he above tests indicate deterioration or failure of the

    ground insulation, a detailed assessment of insulation condition should he

    conducted. The rotor must he removed and ai least partiaUy disassembled

    to allow sullicicnt access for a dchilcd assessment

    of

    turn insulation,

    ground insulation,

    slol

    wcdging and cndwinding bracing condition.

    f a failure o f thc tuin insulation

    has

    heen indicated hy on-line monitoring

    and/or oll-line

    tests,

    then the location can he confirmed by one of the

    following tests 121, and m a y also verily an unconfirmed turn fault.

    low voltage ilc

    test

    low voltagc dc tcst

    surge

    test

  • 8/18/2019 Flowchart Procedure to Assess the Condition

    7/7

    552

    The

    ac

    and dc tests measure the voltage drops across the various

    turns,

    and 2. Culbcrt,

    I .M . ,

    Dhirani, H., and Stone, G.C., "Handbook to

    thus permit localization of any fault. If the repair of a fault and/or a

    Assess thc Insulation Condition of Largc Rotating Machines",

    detailed assessment

    of tum

    insulation condition is required, the rotor EPRI EL-SO36, Volum c 16, Junc 1989.

    endwinding retaining rings and so me of the winding slot wedges must be

    removed to allow a visual examination for signs of discoloration, burning, Stone, G.C., et

    al.

    "The Ability of Diagnostic Tests to Estimate

    abrasion, buckling, copper

    rub

    marks

    or

    copper dust.

    Removing the the Remaining Lifc of Stator Insulation", IEEE Trans EC, Dec

    3 .

    retaining rings may create new problems.

    1988, p833.

    The condition of the groundwall insulation can only be roughly assessed

    with insulation resistance or polarization index tests.

    A

    thorough visual

    examination for the signs of deterioration described above is required.

    4.

    Culbcrt, I., et al, "A Mcthod to Estimate the Insulation Condition

    of High Voltage Stator Windings", Proc

    1989

    IEEE Electrical

    Insulation Confcrencc, Chicago, October 1989.

    CONCLUSION

    Flowcharts have been presented which will indicate to the nonexpert the

    information, testing and cxperience required to assess the condition of the

    insulation systems used in turbine generator rotor and stator windings.

    This process is intuitively followed by many experts. Exam ples of the use

    of the flowcharts are in Rcferencc [2]. Although great progress has been

    madc in developing diagnostic tests to evaluate insulation condition, there

    is still no substitute for a carcful visual examination by an experienced

    cngineer. This is especially important for rotor windings where few tests

    arc available to assess condition. The flowc harts illustrated in this paper

    may aid in distinguishing between good, slightly deteriorated and severely

    deterioratcd windings. The prccision of the condition assessm ent depends

    on the expertise and expcrien ce of the engincer. Unfortun ately, firm

    cstimates of the remaining winding life are not yet possible due to the wide

    range of insulation failure mechanisms which can occur, and the lack of a

    diagnostic test sensitivc to all thcse mechanisms.

    ACKNOWLEDGEMENT

    This work was sponsorcd by EPRI project RP2577-1, Mr. B.S. Bemstein

    projcct manager. The authors would like to thank J.C. Botts, D.

    Harrington, J. K apler, L. Brdun, H. Sedding,

    R.

    Dal Mina, B. Lloyd and

    many others who providcd useful comments on the flowchart procedure.

    REFERENCES

    1. IEEE Standard 56-1977, "Guidc for Insulation Maintenance of

    Large Allcm aling Current Roldling Machines.

    BIOGRAPHIES

    G.C. Sto ne graduated from the University of Waterloo with a B.A.Sc.

    and M.A.Sc. in electrical engineering in 1975 and 1978, respectively.

    Since joining the Research Division

    of

    Ontario Hydro in 1975, he has been

    active in developing test methods for insulation systems. Greg Stone has

    participated in the creation of several IEEE Standards. He is presently

    President

    of the

    IEEE Dielectrics and Electrical Insulation Society. He is a

    registered professional engineer in Ontario, Canada.

    I.

    Culber t

    He

    received a B.S. Honour Degree in Electrical Engineering from Dundee

    College of Technology in 1965. From 1966 to 1977 he worked as an

    induction motor designer.

    In this

    time period he spent

    7

    years with Parson

    Peebles in Edinburgh, Scotland and 4 years with Reliance Electric in

    Stratford, Ontario, Canada. In 1977 he joined Ontario Hydro as a M otors

    and Small Generators Specialist and his current title is Design Engineer

    Specialist - Generators, Motors and Exciters. Mr. Culbert is a registered

    professional engineer in Ontario, Canada.

    was

    bom in

    Perth, Scotland on February 10, 1943.

    H.

    Dhirani was

    born

    n Tanzania in 1945 and received his B.E. degree in

    Electrical Engineering from the University of Poona, India in 1969. He

    came to Ontario Hydro in

    1978 after having worked in the utility,

    consulting and construction fields.

    Mr.

    H. Dhirani is currently involved

    with the analysis and application of large generators for hydraulic, thermal

    and nuclear stations. M r Dhirani is a registered professional engineer in

    Ontario.