florida gas transmission section #1 hydrostatic test 14-inch saint petersburg lateral pipeline from...
TRANSCRIPT
Florida Gas TransmissionSection #1 Hydrostatic Test
14-Inch Saint Petersburg Lateral PipelineFrom Compressor Station 30 (Plant City West) to Main Line Valve 26-10 (Tampa East Regulator)
Hillsborough County
Who is Florida Gas Transmission (FGT)?
Why is FGT testing?What is the test exactly?When will the test occur?Where will the test take place?How will the test be conducted?How will the test affect me?
Today’s Outline
1
Natural gas transmission company operating a 5,000 mile pipeline system along the Gulf
Provide majority of the natural gas for power generation in Hillsborough County
14-inch diameter pipeline serving Tampa area
Customers include: Electric utility companies Local distributors Industrial clients
Florida Gas Transmission Company
2
The U.S. Department of Transportation regulates all interstate pipelines
Testing is federally mandatedBest practice to confirm the safety
and reliability of the pipeline Safety is our #1 priority Ensure continued superb client service
Need for the Test
3
Hydrostatic Test Remove the natural gas from the line• Controlled release vents harmlessly into
atmosphere
• Service is maintained on another system
Test the integrity of the pipeline by filling the line with water• Put the water under pressure for a fixed
period of time
Nature of the Test
4
Hydrotesting the 14-inch lateral systemStandard, common pipeline test
procedureRecent, successful pipeline tests were
completed in: Saint Lucie Palm Beach
Hillsborough testing began in September 2014
Background
Miami-Dade
Martin Broward
5
Public Awareness Campaign
Project Process
Begin Project
Obtain Permits
Prepare System for
Testing
Conduct Hydrotest
End Project
6
TASK DATE
Community Awareness July – October
Permit Applications June – July
System Preparation July – August
Test Preparation August – September
Conduct Hydrotest 3 October 2014
Test window is set: Friday, 3 October 2014 Early morning, midnight – 4:00 a.m.
Project Schedule
7
Total Project Length = 17.0 miles Begin: West Plant City End: Tampa By-Pass Canal
Generally follows 3 roadway alignments: East Fowler Avenue (SR 582) US 301 (SR 41) West Knights Griffin Road
Within Plant City and Unincorporated Hillsborough County
Project Location
8
Project Location (con’t)
9
Remove natural gas from the pipeline Completed the week before the hydrotest
Fill the line with waterPressurize the system
Normal operating pressure is 888 PSI Test pressure is up to 1,500 PSI• Relatively short duration (approx. 30 minutes)
Reduce to intermediate pressure at 1,357 PSI•Maintain for 8 hours
How the Test is Performed
10
De-pressurize the lineDrain the water from the systemIf any integrity issues are found:
They are corrected as soon as possible The hydrotest is performed again• Any re-testing will be performed as soon as
possible, during the same hours
Resume normal natural gas service
How the Test is Performed (con’t)
11
Safety is our #1 priorityPerformed extensive test
preparations, including an inspection of the entire system
Any pipe anomalies will be repaired in advance of conducting the hydrotest
For the duration of the high pressure test, as a safety consideration, we plan to isolate sections of the pipeline route from people and traffic
Safety During the Test
12
Advance Preparations Make all key stakeholders aware• Adjacent property owners
• Emergency service providers
•General driving public
Announcements• Flyers, newspaper, website, etc.
Dynamic message signs• 2 weeks in advance
Conducting the Test
13
Night of the Test Begin at midnight Close roads/lanes with barricades Law enforcement support Confirm all-clear along the 17.0-mile
corridor Conduct hydrotest Reopen roadways at approximately 4:00
AM
Conducting the Test (Con’t)
14
General Utility Permit from the Florida Department of Transportation is in process
Officers will be stationed at road and lane closures
Emergency responders will be able to cross as needed
Detours will include signs and officer support
Traffic Control During the Test
15
Detours During the Test
For Northbound US 301: E Fowler
Ave Main St Ft King Hwy Stacy Rd
16
Detours During the Test (Con’t)
For West Knights Griffin Road: Cooper Road
Thonotosassa Road
McIntosh Road
Fort King Highway
17
Project Location – District 2
18
Project Location – District 4
19
Please visit our website:www.fgthydrotest.com
Or contact FGT:Mr. Terry Coleman
2405 Lucien Way, Suite 200Maitland, FL 32751
Toll Free – 844-FGT-INFO (844-348-4636)
Office – 407.838.7054Fax – 407.838.7052
Email – [email protected]
For More Information
20
FGT Section #1 Hydrotest Summary
Federal mandate Testing with water Test will be Friday,
3 October 2014 Midnight – 4:00 AM US 301 lane closure NB West Knights Griffin
Road full road closure With law enforcement Emergency vehicles
can always cross
21
Thank You