FLAO commissioning with InfraRed Test Camera (IRTC)
S. Esposito, G. Brusa, A. Riccardi
FLAO system external review, Florence, 30/31 March 2009
Commissioning campaign activity rationale
FLAO system external review, Florence, 30/31 March 2009 3
Phase I
Phase II
From FLAO_07 TOC
The two main phases of the commissioning campaign follow the idea to proceed in the test advancing in all system aspects (HW, control SW,data reduction SW) at the same time. So, the first phase milestones is a closed loop on-sky test with 200 modes and a bright star. This to recognize any serious problem in any of the components or procedures used.
The second phase will then optimize the system in all aspects and will contains the final test of the system on sky.
FLAO system external review, Florence, 30/31 March 2009 4
FLAO commisioning task list
Task name Duration (days)
Description Milestone Success criteria
LBT672a & W#2 re-integration
10 Reintegration of LBT672 and W unit. Alignment check. Units & FLAO system functional checks
FLAO sub-system re-integrated. Functional check passed
FLAO System compliance to requirements (compliance matrix)
FLAO functional test
Telescope installation of FLAO system
12 a) Telescope Installation of LBT672a, W#2, retro-reflecting optics. IRTC.
b) FLAO aligned with retro-reflector.
FLAO system aligned. IRTC aligned.
FLAO system alignment in specifications. (FLAO_09,FLAO_06)
FLAO initial test and 1st light on sky
15 days
5 nights
a) Control SW test.
b) 1st light on sky in closed loop
1st corrected images
Closed loop done with 200 modes for high flux.
FLAO closed loop test.
20 days
17 nights
Closed loop test with FLAO with different fluxes:
a) Engineering mode
b) Observing modes
FLAO closed loop achieved in engineering and observing modes.
SR values >= baseline values defined in FLAO_01.
Final system test
14 nights System performance test FLAO system commissioned with IRTC
FLAO performance >= baseline performance defined in FLAO_01
Commissioning campaign duration:-total time 93 days-days 57-nights 36
FLAO system external review, Florence, 30/31 March 2009 5
FLAO re-integration & alignment
1. System and sub-system functional test completed (compliance matrix). 2. LBT672, W#2 and IRTC installed at the telescope.3. FLAO aligned with retro-reflecting optics (including IRTC). (see
FLAO_06, FLAO_09)
Total duration: 22 days, daytime 22 days
FLAO system external review, Florence, 30/31 March 2009 6
FLAO system 1st light
1st corrected images on sky with 200 modes (engineering mode).
Task summary: verification of system performance at the telescope site in daytime. On sky test of source acquisition, pupil geometry verification, close loop with high flux (engineering mode).
Total duration: 25 days, daytime 20 days, nighttime 5 nights
FLAO system external review, Florence, 30/31 March 2009 7
Observing modes daytime & on sky test
On sky system performance vs. star mag, r0, v0: -engineering mode (baseline) -observing mode (ACE/ICE) (baseline) - ACE with on sky parameters optimization (goal)
[SR >= baseline performance (FLAO_06)]
Task summary: daytime fine calibration of system. Daytime closed loop test with verification of system performance in engineering and observing modes. On-sky test of system performance (both modes).
Total duration: 37 days, daytime 20 days, nighttime17 nights
FLAO system external review, Florence, 30/31 March 2009 8
Final on-sky FLAO test
SR better then baseline performance (FLAO_06):
Total duration: 14 days, nighttime14 nights
FLAO final test on sky:repetition of a specific set of tests already done in phase II (see FLAO_06)
Test list:Closed loop test with:
-Engineering mode-Observing modes
a) SLM, FSMb) ACE
FLAO system external review, Florence, 30/31 March 2009 9
FLAO commissioning resuming table
The required manpower is found compatible with the available resources of the group. The group relevant personnel is composed by 17 persons. About 5-7 personnel units will be available in Arcetri to progress with FLAO#2 test in solar tower (13/01/10-06/07/10).
FLAO system external review, Florence, 30/31 March 2009 10
Conclusion
The FLAO system telescope
commissioning plan with IRTC
has been formulated.
Main tasks of commissioning
campaign have been identified.
Duration of each task and
required manpower has been
evaluated.
The schedule of the
commissioning campaign has
been shown.