first single-storey bungalow project after 9 years since 2008

102
HC PRECAST SYSTEM IBS Superstructure In Malaysia 3in1 Load Bearing Wall + Modular Shear Keys Wet Joint + Box System Completed In 10 Days With 6 Workers : Speed, Quality & Environment INDUSTRIALISED BUILDING SYSTEM (IBS) It is a system which suits all architectural demands & not a machine or component - The wall is designed to provide adequate fire resistance according to demand (with minimum 2hours as per BS8110) - The system is designed and approved by PE and endorsed by independent checker - Thickness of the wall can be customized according to requirement - Our design and casting are following strictly to British Standard ONE OF THE WAYS TO IMPROVE THE OUTFLOW OF CURRENCY IS THE UTILIZATION OF INDUSTRIAL BUILDING SYSTEM ( IBS ) Part 1

Upload: teow-beng-hur

Post on 09-Jan-2017

478 views

Category:

Technology


0 download

TRANSCRIPT

Page 1: First Single-storey Bungalow Project after 9 years since 2008

HC PRECAST SYSTEM IBS Superstructure In Malaysia 3in1

Load Bearing Wall + Modular Shear Keys Wet Joint + Box System

Completed In 10 Days With 6 Workers : Speed, Quality & Environment

INDUSTRIALISED BUILDING SYSTEM (IBS)

It is a system which suits all architectural demands & not a machine or component

- The wall is designed to provide adequate fire resistance according to demand (with minimum 2hours as per BS8110)

- The system is designed and approved by PE and endorsed by independent checker

- Thickness of the wall can be customized according to requirement

- Our design and casting are following strictly to British Standard

ONE OF THE WAYS TO IMPROVE THE OUTFLOW OF CURRENCY IS THE

UTILIZATION OF INDUSTRIAL BUILDING SYSTEM ( IBS ) Part 1

Page 2: First Single-storey Bungalow Project after 9 years since 2008

TRAINING UNIT

8 years expose precast wall, precast staircase,

half slab & precast beam with in-situ column.

- No touch-up - No water proofing

- No leaking - No crack

Page 3: First Single-storey Bungalow Project after 9 years since 2008

FACTORY CAPACITY : 21 ACRES

Existing production 8 acres : 1,800 to 2,500 units

of single storey (1000 ft2) per year

Future development 13 acres : 2,500 to 3,500 units of

single storey (1000 ft2) per year

Page 4: First Single-storey Bungalow Project after 9 years since 2008

Mobilization To Site

Page 5: First Single-storey Bungalow Project after 9 years since 2008

Mobilization To Site

Page 6: First Single-storey Bungalow Project after 9 years since 2008

Proper Storage Precast Panel & Column Mould On Site

1. 2.

Page 7: First Single-storey Bungalow Project after 9 years since 2008

Proper Storage Precast Panel & Column Mould On Site

1. 2.

Page 8: First Single-storey Bungalow Project after 9 years since 2008

Setting Out & Levelling Panel Location

1. 2.

Page 9: First Single-storey Bungalow Project after 9 years since 2008

Panel Wall Guide

1. 2.

Page 10: First Single-storey Bungalow Project after 9 years since 2008

Panel Installation

Page 11: First Single-storey Bungalow Project after 9 years since 2008

Temporary Wall Prop Installation

Page 12: First Single-storey Bungalow Project after 9 years since 2008

Temporary Panel Guide & Wall Support

Guide

Page 13: First Single-storey Bungalow Project after 9 years since 2008

Temporary Wall Support

Page 14: First Single-storey Bungalow Project after 9 years since 2008

Wall Plug Installation

1. 2.

3. 4. 3.

Page 15: First Single-storey Bungalow Project after 9 years since 2008

Panel Wall Verticality

1. 2. 3.

Page 16: First Single-storey Bungalow Project after 9 years since 2008

Modular Wet Joint Shear Keys

Page 17: First Single-storey Bungalow Project after 9 years since 2008

Modular Wet Joint Shear Keys

Page 18: First Single-storey Bungalow Project after 9 years since 2008

Modular Wet Joint Shear Keys

Page 19: First Single-storey Bungalow Project after 9 years since 2008

Modular Wet Joint Shear Keys

Page 20: First Single-storey Bungalow Project after 9 years since 2008

Wet Joint Shear Keys

Page 21: First Single-storey Bungalow Project after 9 years since 2008

Modular Wet Joint Shear Keys

Page 22: First Single-storey Bungalow Project after 9 years since 2008

Expanding Cement Motar

Page 23: First Single-storey Bungalow Project after 9 years since 2008

Expanding Cement Motar

Page 24: First Single-storey Bungalow Project after 9 years since 2008

Wet joint View After Casting

Page 25: First Single-storey Bungalow Project after 9 years since 2008

Expanding Cement Motar

Page 26: First Single-storey Bungalow Project after 9 years since 2008

Wet Joint Shear Keys Rebar Installation

Page 27: First Single-storey Bungalow Project after 9 years since 2008

Wet Joint Shear Keys Rebar Installation

Page 28: First Single-storey Bungalow Project after 9 years since 2008

Wet Joint Shear Keys Rebar Installation

1. 2.

Page 29: First Single-storey Bungalow Project after 9 years since 2008

Wet Joint Shear Keys Rebar Installation

Page 30: First Single-storey Bungalow Project after 9 years since 2008

Wet Joint Modular Mould Installation

Page 31: First Single-storey Bungalow Project after 9 years since 2008

Wet Joint Modular Mould Installation

Page 32: First Single-storey Bungalow Project after 9 years since 2008

Wet joint modular mould installation

Page 33: First Single-storey Bungalow Project after 9 years since 2008

Wet Joint Modular Mould Installation

Page 34: First Single-storey Bungalow Project after 9 years since 2008

Precast Beam & In-Situ Beam Installation

Page 35: First Single-storey Bungalow Project after 9 years since 2008

Wet Joint Modular Mould, Precast Beam & In-Situ Beam Installation

Page 36: First Single-storey Bungalow Project after 9 years since 2008

Precast Beam & In-Situ Beam Installation

1. 2.

Part 2

Page 37: First Single-storey Bungalow Project after 9 years since 2008

Precast Beam & In-Situ Beam Installation

1. 2.

Page 38: First Single-storey Bungalow Project after 9 years since 2008

Precast Beam & In-Situ Beam Installation

Page 39: First Single-storey Bungalow Project after 9 years since 2008

Precast Beam & In-Situ Beam Installation

1. 2.

Page 40: First Single-storey Bungalow Project after 9 years since 2008

Precast Beam & In-Situ Beam Installation

1. 2.

Page 41: First Single-storey Bungalow Project after 9 years since 2008

Wet Joint Concreting

Page 42: First Single-storey Bungalow Project after 9 years since 2008

Wet Joint Concreting

1. 2. .

Page 43: First Single-storey Bungalow Project after 9 years since 2008

Beam Concreting

Page 44: First Single-storey Bungalow Project after 9 years since 2008

Watering Before Mould Dismantle

1. 2. 3.

Page 45: First Single-storey Bungalow Project after 9 years since 2008

Wet Joint Mould Dismantle

1. 2. 3.

Page 46: First Single-storey Bungalow Project after 9 years since 2008

Wet Joint Mould Dismantle

1. 2. 3.

Page 47: First Single-storey Bungalow Project after 9 years since 2008

Column Mould Dismantle

Page 48: First Single-storey Bungalow Project after 9 years since 2008

Verticality Of Column

1. 2. 3.

Page 49: First Single-storey Bungalow Project after 9 years since 2008

Verticality Of Wall

1. 2. 3.

Page 50: First Single-storey Bungalow Project after 9 years since 2008

Installation Of Scaffolding For Half Slab

Page 51: First Single-storey Bungalow Project after 9 years since 2008

Installation Of Scaffolding For Half Slab

Page 52: First Single-storey Bungalow Project after 9 years since 2008

Installation Of Scaffolding For Half Slab

Page 53: First Single-storey Bungalow Project after 9 years since 2008

Installation Of Scaffolding For Half Slab

Page 54: First Single-storey Bungalow Project after 9 years since 2008

Installation Of Scaffolding For Half Slab

Page 55: First Single-storey Bungalow Project after 9 years since 2008

Grinding Uneven Surface “ If Any”

1. 2. 3.

Page 56: First Single-storey Bungalow Project after 9 years since 2008

Grinding Uneven Surface “ If Any”

1. 2.

Page 57: First Single-storey Bungalow Project after 9 years since 2008

RC Flat Roof Half Slab Installation

1.

2.

3.

4.

5.

6.

Page 58: First Single-storey Bungalow Project after 9 years since 2008

Cantilever Corridor Modular Mould Installation

1.

2.

Page 59: First Single-storey Bungalow Project after 9 years since 2008

Cantilever Corridor Modular Mould Installation

1.

2.

Page 60: First Single-storey Bungalow Project after 9 years since 2008

Cantilever Corridor Modular Mould Installation

1.

2.

Page 61: First Single-storey Bungalow Project after 9 years since 2008

Cantilever Corridor Modular Mould Installation

4.

5.

6.

1.

2.

3.

Page 62: First Single-storey Bungalow Project after 9 years since 2008

RC Flat Roof Rebar Installation

Page 63: First Single-storey Bungalow Project after 9 years since 2008

RC Flat Roof Rebar Installation

Page 64: First Single-storey Bungalow Project after 9 years since 2008

RC Flat Roof Rebar Installation

1. 2. 3.

Page 65: First Single-storey Bungalow Project after 9 years since 2008

RC Flat Roof Conduit Installation

Page 66: First Single-storey Bungalow Project after 9 years since 2008

RC Flat Roof Conduit Installation

1. 2. 3.

Page 67: First Single-storey Bungalow Project after 9 years since 2008

RC Flat Roof To Receive Concrete

Page 68: First Single-storey Bungalow Project after 9 years since 2008

RC Flat Roof Concreting Level Checking

1. 2.

Page 69: First Single-storey Bungalow Project after 9 years since 2008

RC Flat Roof Concreting Level Checking

1. 2.

Page 70: First Single-storey Bungalow Project after 9 years since 2008

RC Flat Roof

Page 71: First Single-storey Bungalow Project after 9 years since 2008

RC Flat Roof

Part 3

Page 72: First Single-storey Bungalow Project after 9 years since 2008

RC Flat Roof

Page 73: First Single-storey Bungalow Project after 9 years since 2008

RC Flat Roof

Page 74: First Single-storey Bungalow Project after 9 years since 2008

Cantilever Corridor

1.

2.

Page 75: First Single-storey Bungalow Project after 9 years since 2008

Cantilever Corridor

1.

2.

Page 76: First Single-storey Bungalow Project after 9 years since 2008

Corner & Edge

1. 2.

Page 77: First Single-storey Bungalow Project after 9 years since 2008

Internal View

1. 2.

Page 78: First Single-storey Bungalow Project after 9 years since 2008

Internal View

1. 2.

Page 79: First Single-storey Bungalow Project after 9 years since 2008

Cantilever Corridor

1. 2.

Page 80: First Single-storey Bungalow Project after 9 years since 2008

Cantilever Corridor After Mould Dismantle

1. 2.

Page 81: First Single-storey Bungalow Project after 9 years since 2008

Cantilever Corridor After Mould Dismantle

1. 2.

Page 82: First Single-storey Bungalow Project after 9 years since 2008

Cantilever Corridor

1. 2.

Page 83: First Single-storey Bungalow Project after 9 years since 2008

Chequer Plate To Receive Tiling Work

Page 84: First Single-storey Bungalow Project after 9 years since 2008

Chequer Plate To Receive Tiling Work

1. 2.

Page 85: First Single-storey Bungalow Project after 9 years since 2008

Internal Edge

Page 86: First Single-storey Bungalow Project after 9 years since 2008

Internal Edge

1. 2.

Page 87: First Single-storey Bungalow Project after 9 years since 2008

Internal Edge

1. 2.

Page 88: First Single-storey Bungalow Project after 9 years since 2008

Internal Edge

Page 89: First Single-storey Bungalow Project after 9 years since 2008

Internal Edge

Page 90: First Single-storey Bungalow Project after 9 years since 2008

Precast Panel With RC Coping

1. 2.

Page 91: First Single-storey Bungalow Project after 9 years since 2008

Precast Panel With RC Coping

1. 2.

Page 92: First Single-storey Bungalow Project after 9 years since 2008

Cement Mortar To Cover The Form Tile Hole & Prop Hole

1. 2.

Page 93: First Single-storey Bungalow Project after 9 years since 2008

Precast Panel With Electric Socket

1. 2.

Page 94: First Single-storey Bungalow Project after 9 years since 2008

Precast Panel With Electric Socket

1. 2.

Page 95: First Single-storey Bungalow Project after 9 years since 2008

Completed Demobilise Back To Rasah Factory

Page 96: First Single-storey Bungalow Project after 9 years since 2008

Skim Coat & Smooth Surface

1. 2.

Page 97: First Single-storey Bungalow Project after 9 years since 2008

Skim Coat & Smooth Surface

1. 2.

Page 98: First Single-storey Bungalow Project after 9 years since 2008

Skim Coat & Smooth Surface

1. 2.

Page 99: First Single-storey Bungalow Project after 9 years since 2008

Skim Coat & Smooth Surface

1. 2.

Page 100: First Single-storey Bungalow Project after 9 years since 2008

Skim Coat & Smooth Surface

1. 2.

Page 101: First Single-storey Bungalow Project after 9 years since 2008

Skim Coat & Smooth Surface

1. 2.

Page 102: First Single-storey Bungalow Project after 9 years since 2008

DESIGNED BY YOU

PRODUCED BY

HC PRECAST SYSTEM

THANK YOU