first installation of the bulldog™ pvc pipe-to-pipe restraint system occurred on august, 2006

9
• First installation of the BullDog™ PVC pipe-to-pipe restraint system occurred on August, 2006. Eliminated need for concrete thrust blocking Case History: City of McKinney, Texas

Upload: keelie-lancaster

Post on 01-Jan-2016

14 views

Category:

Documents


0 download

DESCRIPTION

Case History : City of McKinney, Texas. First installation of the BullDog™ PVC pipe-to-pipe restraint system occurred on August, 2006. Eliminated need for concrete thrust blocking. Case History : City of McKinney, Texas. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: First installation of the BullDog™ PVC pipe-to-pipe restraint system occurred on August, 2006

• First installation of the BullDog™ PVC pipe-to-pipe restraint system occurred on August, 2006.

• Eliminated need for concrete thrust blocking

Case History: City of McKinney, Texas

Page 2: First installation of the BullDog™ PVC pipe-to-pipe restraint system occurred on August, 2006

Case History: City of McKinney, Texas

The first Bulldog project was part of the City’s Annual Maintenance Program to Replace Substandard Water and Sewer Mains.

This project was prioritized because of red water complaints and because the City’s Paving Department was preparing to pave the street.

Page 3: First installation of the BullDog™ PVC pipe-to-pipe restraint system occurred on August, 2006

Case History: City of McKinney, Texas

Designed new 1,110 feet of 8” PVC water pipeline offset from existing main. The pipe was DR18, C900.

Joint restraint was needed at reducers, bends, and valves.

Page 4: First installation of the BullDog™ PVC pipe-to-pipe restraint system occurred on August, 2006

Case History: City of McKinney, Texas

New PVC water line paralleled the existing main. 45-degree offsets used instead of 90-degree bends because the smaller angle generates less thrust force.

Page 5: First installation of the BullDog™ PVC pipe-to-pipe restraint system occurred on August, 2006

• Successful installations• Less installation time

compared to the traditional method

• No wait for concrete to cure

• No concrete mess or expense

• Backfilled and ready for pavement repairs by the end of the day

Case History: City of McKinney, Texas

Using the Bulldog System resulted in:

Page 6: First installation of the BullDog™ PVC pipe-to-pipe restraint system occurred on August, 2006

City of McKinney, Texas: Fabricated Fittings

• Installation of BullDog™ PVC fabricated pressure fittings in April, 2007.

• Project connected new pipe line to existing pipeline.

Page 7: First installation of the BullDog™ PVC pipe-to-pipe restraint system occurred on August, 2006

City of McKinney, Texas: Fabricated Fittings

• PVC fabricated fittings are more easily handled than traditional iron fittings.

Page 8: First installation of the BullDog™ PVC pipe-to-pipe restraint system occurred on August, 2006

City of McKinney, Texas: Fabricated Fittings

• New water line alignment shown at the top of the photo. Existing water line alignment shown at the bottom of the photo.

Page 9: First installation of the BullDog™ PVC pipe-to-pipe restraint system occurred on August, 2006

City of McKinney, Texas: Fabricated Fittings

• Tying into the existing line.