FP7, from AC towards FC
Only one costs system for FP7
Additional Costs system is dead
Full Costs system incl. transition periods
FP7, structure (four pillars)
Cooperation (follow-up FP6), 32.4 billion €
Ideas (basic/frontier research), 7.5 billion €
People (Marie Curie fellowships), 4.75 billon €
Capacities (target groups), 4.1 billion €
See CORDIS website: http://cordis.europa.eu/fp7/home_en.html
Cooperation – Collaborative researchCooperation – Collaborative research
People – Human PotentialPeople – Human Potential
Ideas – Frontier ResearchIdeas – Frontier Research
Capacities – Research CapacityCapacities – Research Capacity
FP7, Specific Programmes
FP7, pillar Cooperation: ten themes
Health ( 6.1 billion €) Food, agriculture and biotechnology ( 1.9 billion €) Information & communication technologies ( 9.1
billion €) Nanosciences, nanotechnologies, materials & new
production technologies ( 3.5 billion €) Energy ( 2.3 billion €) Environment (incl. climate change) ( 1.9 billion €) Transport (incl. aeronautics) ( 4.2 billion €) Socio-economic sciences & humanities ( 0.6 billion €) Security (1.4 billion €) Space ( 1.4 billion €)
Cooperation – Collaborative researchCooperation – Collaborative research
People – Human PotentialPeople – Human Potential
Ideas – Frontier ResearchIdeas – Frontier Research
Capacities – Research CapacityCapacities – Research Capacity
FP7, Specific Programmes
Cooperation – Collaborative researchCooperation – Collaborative research
People – Human PotentialPeople – Human Potential
Ideas – Frontier ResearchIdeas – Frontier Research
Capacities – Research CapacityCapacities – Research Capacity
FP7, Specific Programmes
FP7, pillar People Initial Training
Marie Curie Research Training Networks (RTN) Marie Curie Host Fellowships for Early Stage Research Training (EST) Marie Curie actions-Large conferences (LCF) Marie Curie actions-Series of events (SCF) Marie Curie Chairs (EXC)
Life-long Training Marie Curie Intra-European Fellowships (EIF) Marie Curie European Reintegration Grants (ERG)
Industry academia Marie Curie Host Fellowships for the Transfer of Knowledge (TOK)
International dimension Marie Curie Outgoing International Fellowships (OIF)
Marie Curie Incoming International Fellowships (IIF)Marie Curie International Reintegration Grants (IRG)
Specific actions Specific Support Actions
Marie Curie Excellence Awards (EXA)
Cooperation – Collaborative researchCooperation – Collaborative research
People – Human PotentialPeople – Human Potential
Ideas – Frontier ResearchIdeas – Frontier Research
Capacities – Research CapacityCapacities – Research Capacity
FP7, Specific Programmes
FP7, pillar Capacities Research infrastructures NEW
Research for the benefit of SMEs
Regions of knowledgeNEW
Research potential of Convergence RegionsNEW
Science in society
Coherent development of research policies
International cooperation
Cooperation – Collaborative researchCooperation – Collaborative research
People – Human PotentialPeople – Human Potential
Ideas – Frontier ResearchIdeas – Frontier Research
Capacities – Research CapacityCapacities – Research Capacity
FP7, Specific Programmes
FP7, pillar Cooperation: ten themes
Health ( 6.1 billion €) Food, agriculture and biotechnology ( 1.9 billion €) Information & communication technologies ( 9.1
billion €) Nanosciences, nanotechnologies, materials & new
production technologies ( 3.5 billion €) Energy ( 2.3 billion €) Environment (incl. climate change) ( 1.9 billion €) Transport (incl. aeronautics) ( 4.2 billion €) Socio-economic sciences & humanities ( 0.6 billion €) Security (1.4 billion €) Space ( 1.4 billion €)
FP7, instruments
‘Traditional’ instruments Small and large collaborative projects Networks of Excellence Coordination and Support Actions SME instruments Various fellowships
Instruments for frontier research
Joint Technology Initiatives, ERA-net, article 169
FP7, activities
Research and technological development
Demonstration
Training
Management of the consortium
Other specific activities (coordination/support)
FP7, management of consortium
No maximum (as in FP6), but a practical ceiling This activity includes:
Maintenance of the consortium agreement Overall legal, ethical, financial and administrative
management Implementation of competitive calls (new
beneficiaries) Any other management activities foreseen by the
annexes
Please note: scientific coordination = RTD!
FP7, training activities
Internal and external groups
No salary costs of those being trained eligible
Funding schemes
Network of Excellence (NoE)
Collaborative project: Large-scale integrating project Small or medium-scale focused research project Project for specific cooperation action dedicated
to international cooperation (SICA)
Research project for the benefit of specific groups (SMEs)
Coordination and support action (CSA)
Funding principles
Grant Reimbursement of eligible costs Flat rate Lump sum
Co-financing
No profit
Full Cost
Eligible costs
Actual Incurred during the duration of the project In accordance with usual accounting and
management principles and practices of the beneficiary
Used only to achieve project deliverables Consistent with principles of economy,
efficiency and effectiveness Recorded in accounts of the beneficiary Exclusive of non-eligible costs
Non-eligible costs
Identifiable indirect taxes including VAT Levies for airplane tickets are eligible!
Duties Interest owed Provisions for possible future losses or charges Exchange losses, cost related to return on capital Costs declared or incurred, or reimbursed in
respect of another EC project Debt and debt service charges, excessive or
reckless expenditure
Eligible costs
Qualifications usual accounting system
One system for all funding schemes
Has to be audit proof to own auditor
Has to be European Commission audit proof
Direct costs
Attributed directly to the project
Personnel costs (incl. permanent staff) Actual hours worked Directly hired by the beneficiary, work under the sole
supervision and responsibility of the beneficiary and remunerated in accordance with the normal practices of the beneficiary
Individual Averages are allowed (certification needed)
Travel and subsistence, consumables, equipment, etc.
Indirect costs, definition
Not being identified as directly attributed to project
Accounted as being incurred in direct relationship with eligible direct costs, attributed to the project
Representing fair apportionment of overall overheads
Indirect costs, methods for identifying Real indirect costs (possible a simplified method)
Flat-rate of 20% of direct eligible costs (excl. subcontracts) (without any justification)
Flat-rate of 60% of direct eligible costs (excl. subcontracts) for calls before 1 January 2010; (non-profit public bodies, secondary and higher education establishments, research organisations and SMEs)
Flat-rate of 40% for calls after 1 January 2010
CSA: max. 7% of direct costs (excl. subcontracts)
Reimbursement rates of activities
Research and technological development Basic 50% Topping up 25% (some groups, such as higher education
and SMEs)
Demonstration 50%
Management, training, networking and dissemination 100%
Coordination and support actions (CSA) 100%
Reimbursement rates, an exampleResearch Managemen
tTotal
Personnel 100 5 105
Travel 20 20
Indirect costs
110 5,5
115,5
Total 230 10,5 240,5
EC contribution
172,5 10,5 183
Contracting phase, consortium agreement Internal organisation of the consortium, including
decision making procedures
Rules on dissemination, use, access rights
Distribution of the EC financial contribution
Settlement of internal disputes
Liability, indemnification and confidentiality arrangements
Executing phase, Guide to financial issues
Explanation by the EC
Many examples
Update every 6 months
Not legally binding
Executing phase, role of coordinator
Administer EC contribution
Review reports to verify consistency with the project tasks before transmitting them to the EC
Monitor the compliance by beneficiaries with their obligations under the grant agreement
Executing phase, payments
Pre-financing (budget/number of periods x 160%) Deduction of 5% x maximum EC grant (Guarantee Fund)
Interim payments following each reporting period
Maximum 85%
Final payment
Executing phase, reporting 1
Periods are in grant agreement (article 4)
Periodic report within 60 days: Overview of progress of work Explanation of the use of the resources Financial statement (form C) from each beneficiary Summary financial report
Executing phase, reporting 2
Final report within 60 days: Final publishable summary report (results, conclusions,
socio-economic impact) Report covering wider societal implications (gender, ethical,
plan to use and dissemination of foreground Report on distribution of the EC contribution
Certificate on the financial statements (form D) Only if EC contribution = or > € 375,000
Projects of >2 years: every € 375,000 per participant (cumulative)
Projects of max. 2 years: only at the end
Executing phase, transfer of budget
Transfer of budget between activities and beneficiaries allowed without an amendment
Condition: work carried out as foreseen in Annex I
Reimbursement rates of new activities and beneficiaries will apply
Maximum EC contribution cannot be increased
Transfer of funds to lump sum is not allowed
Costs systems Framework Programmes
Full Costs (FC) model system from FP1
Additional Costs (AC) system from FP3
AC to accommodate universities temporary
FC only cost model permitted from FP7
FP7, funding regimes
Full Costs Collaborative research projects
Transition period for AC users only Collaborative research projects
Lump sum Fellowships Frontier research
Full Costs system, possible advantages
Supportive to output funding
Transparency of costs calculation
Reimbursement of more indirect costs
Reimbursement of permanent staff costs
EC contribution FP6 versus FP7 (personnel)Cost
modelEligible personnel costs €
IndirectCosts%
TotalCosts €
ECContr.%
ECContr.€
FC FP6 100+10 80 198 50 99
AC FP6 100 20 120 100 120
FC FP7 100+10 80 198 75 148,5
FC FP7 100+10 60 176 75 132
FC FP7 100+10 40 154 75 115,5
FC system, how to implement?
How to calculate direct costs? Number of productive hours?
How to calculate indirect costs? Per university / faculty / department / project?
How to introduce time recording? Complete time writing all activities or project
activities? Everybody or project personnel?
Getting ready for Full Costs system
Preparing for transition now
Transfer to FC in 2007 or in 2010
Communication with all stakeholders
Be aware for psychological resistance