final sbc & iecc std appartments thermel analysis

Upload: mani-kandan

Post on 09-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    1/57

    THERMAL ANALYSIS FOR

    RESIDENTIAL BUILDING

    (APPARTMENTS)

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    2/57

    S.No. Contents

    Page

    1. Introduction

    3

    2. Methods to evaluate the thermal performance ofbuilding materials 4

    3. Procedures for using the Total VA alternative method

    5

    4. Procedures for using the Performance approach

    method 9

    5. Analysis of the studies as per both codes

    13

    6. Solution for compliance to code requirements

    14

    7. Recommendation

    17

    8. Appendix 1

    189. Appendix 2

    27

    10. Appendix 3

    38

    2

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    3/57

    1. Introduction:

    The intension of the report is to verify and evaluate existing U values of wall,

    roof, and glass for the apartment building in comparison with requirements

    prescribed in the IECC 2009 and SBC 2007. Also to come up with proper

    recommendations in the existing constructions to satisfy the above mentioned

    code requirements.

    3

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    4/57

    2. Methods to evaluate the thermal

    performance of building materials:

    a. Prescriptive package approach

    b. Trade off approach

    c. Software approach

    a. Prescriptive package approach

    A prescriptive packages approach lists the minimum R value or

    maximum U factor requirements for each building component such as

    windows, wall and roofs. The prescriptive package approach requires

    minimal calculations and is the simplest method for demonstrating

    compliance with the insulation and window requirements for residential

    buildings.

    b. Trade off approach: This approach allows for trade off s between all buildings envelope

    components, heating and cooling equipment efficiencies. When applying

    the trade-off approach to multifamily buildings the buildings can be

    considered as a whole or a separate work sheet can be completed for each

    individual dwelling unit.

    4

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    5/57

    c. Software approachAn approved software program or calculation based methodology that

    projects the hour -by-hour loads and annual energy use of a building.

    d. Selected method in this analysis:Out of the above three methods, Trade-Off approach is selected to perform

    this analysis. Two different trade off approaches are utilized due to the

    differences in the prescribed U values of the various building envelope

    components between IECC2009 and SBC2007. Following are the methods

    as per IECC 2009 and SBC-2007:

    a. Total VA alternative method (Trade-off method as per IECC

    2009)

    b. Performance method (Trade-off method as per SBC 2007)

    1. Procedures for using the Total VA

    alternative method (as per IECC 2009)

    This VA alternative method determines whether this building as a whole

    meets the code requirements. The following steps are implemented to

    perform the analysis as per IECC - 2009.

    3.1 Finding the climate zone

    Determination of the degree days of the climate zone in which the

    building is located. As per the SBC standard (Appendix 3, Table 2.2.2)

    the degree days for DHARHAN is 3500 DD (As value for Jubail is not

    specifically mentioned, this value is used).

    As per the IECC 2009 Table no: 301.3(2) Zone number 2 is selected.

    (See APPENDIX -3)

    Degree day, Cooling Definition:

    A unit, based on temperature difference and time, used in estimating

    cooling energy consumption and specifying nominal cooling load of a

    building in summer. For any one day, when the mean temperature is

    more than 18C, there are as many degree days as there are degrees

    Celsius difference in temperature between the mean temperature for

    5

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    6/57

    the day and 18C. Annual cooling degree days (CDD) are the sum of

    the degree days over a calendar year.

    3.2 Evaluation of the PROPOSED VA values as

    per given details:

    The combined thermal transmittance value (V) of the gross area of the

    exterior wall shall be calculated as follows.

    a) Wall with insulation ( Details see Appendix 1.1)

    b) Wall without insulation( Details see Appendix 1.2)

    c) Windows( Details see Appendix 1.3)d) Window Aluminum frame ( Details see Appendix 1.3)

    e) Doors ( Details see Appendix 1.4)

    Definition of V Factor (Thermal

    transmittance): The coefficient of heat transmission (air to air) through a building

    component or assembly, equal to the time rate of heat flow

    per unit area and unit temperature difference between the

    warm side and cold side air films. (W/m2.k)(as per IECC 2009 std, Chapter-

    2, page no: 7, see appendix 3)

    VA for walls is calculated as follows:

    VA = (V1 x A1) + (V2x A2) + (V3 x A3) + (V4 x A4) + (V5 x A5) (as per IECC

    2009 std page no : 28, chapter no : 402.1.4), (see appendix - 3)

    V = The average thermal transmittance of the gross area of the

    exterior

    Walls. (W/m2-k)

    A = The gross area of exterior walls. (m2)

    6

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    7/57

    V1= The combined thermal transmittance of the various paths of heat

    transfer through the opaque exterior insulation wall area. (W/m2-k)

    A1= Area of exterior insulation walls that are opaque. (m2)

    V2= The combined thermal transmittance of the various paths of heat

    transfer through the opaque exterior non - insulated wall area. (W/m2-k)

    A2= Area of exterior non - insulated walls that are opaque. (m2)

    V3 = The combined thermal transmittance of all glazing within the gross

    area of exterior Walls.(windows) (W/m2-k)

    A3 = The area of all glazing within the gross area of exterior walls.

    (windows) (m2)

    V4 = The combined thermal transmittance of all opaque aluminum frame

    within the gross area of Exterior walls. (W/m2-k)

    A4 = The area of all opaque aluminum frame within the gross area of

    exterior walls. (m2)

    V5 = The combined thermal transmittance of all opaque doors within the

    gross area of Exterior walls. (W/m2-k)

    A5 = The area of all opaque doors within the gross area of exterior walls.

    (m2)

    VA for roof is calculated as follows:

    a) Roof ( details see appendix 1.5)

    V A = (VR X AR) (as per IECC 2009 std page no: 28, chapter no:

    402.1.4),

    (See appendix 3)

    V = The average thermal transmittance of the gross roof/ceiling

    area,( W/m2-k)

    A = The gross area of the roof /ceiling assembly, m2.

    7

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    8/57

    VR = The combined thermal transmittance of the various paths of heat

    transfer through The opaque roof /ceiling area. (W/m2-k)

    AR = Opaque roof / ceiling assembly area. (m2)

    3.3: Evaluation of the REQUIRED VA values as per IECC -

    2009standard:

    The requirement of the wall and roof V factors for various component can

    be found From appendix 2, 3 as will be multiplied with

    corresponding areas. V values as follows.

    Vfactor roof/ ceiling = 0.18 (W/m2-k) (see appendix 2.4, 3, IECC

    2009 Table no 402.1.3)

    Vfactor for exterior wall = 0.655 (W/m2-k) (see appendix 2.1, 3,

    IECC 2009 Table no 402.1.3)

    Vfactor for exterior Fenestration = 3.69(W/m2-k) (see appendix

    2.2, 3, IECC 2009 Table no 402.1.3)

    3.4: VA method worksheet envelope calculation asper IECC - 2009:

    8

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    9/57

    As per the building constructions As per the IECC - 2009

    Roof

    Descriptioninsulation

    R- value

    VFactor

    W/m2-k

    Area

    (A) m2 VA

    Required 'V'

    Factor

    W/m2-k

    Area (A)

    m2 VA

    Roof R30 0.172 575 98.9 0.18 575 103.5

    575 98.9

    see details

    appendix -2,3

    see details appendix -

    walls,windows and doors

    Description

    insulation

    R- value

    V Factor

    W/m2-k

    Area

    (A) m2 VA

    Required 'V'

    FactorW/m

    2-k

    Area (A)

    m2 VA

    Insulated wall R13 0.39 1084.5 422.960.655 1084.5 710.3475

    un - insulated wall 3.19 413.5 1319.1 0.655 413.5 270.8425

    Windows(glass) 3.8 326 1238.8 3.69 326 1202.94

    Aluminum frame 4.62 81 374.22 3.69 81 298.89

    Doors (glass) 3.8 4.8 18.24 3.69 4.8 17.712

    Aluminum frame 4.62 1.2 5.544 3.69 1.2 4.428

    Metal door 2.5 9 22.5 3.69 9 33.21

    1920 3373.3 1920 2538.37

    see details appendix -

    see details

    appendix - 2,3Total proposed VA= 3472.2 Total required VA= 2642

    PROPOSED REQUIRED

    Roof total area

    Wall total area

    Building Name : Residential Building (Apartments)

    The Total PROPOSED VA must be less than or equal to the total REQUIRED VA for

    compliancewith IECC -2009.

    In this case the existing building construction Does Not Comply with the code VA

    requirements.

    9

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    10/57

    1. Procedures for using the performanceapproach method as per SBC 2007

    standard:

    This method determines whether this building as a whole meets the

    code requirements. The following steps are implemented to perform the

    analysis as per SBC-2007.

    4. 1: Finding the climate zone & CDDAs per the SBC standard (Table 2.2.2) the degree days for DHARHAN is

    3500 DD. (See APPENDIX -3)

    4.2: Evaluation of the PROPOSED UoAo values as

    per SBC -2007 std:

    The combined thermal transmittance value (UO) of the gross area of the

    exterior wall shall be calculated as follows.

    a) Wall with insulation ( Details see Appendix 1.1)b) Wall without insulation( Details see Appendix 1.2)

    c) Windows( Details see Appendix 1.3)

    d) Window Aluminum frame ( Details see Appendix 1.3)

    e) Doors ( Details see Appendix 1.4)

    UoAo for walls is calculated as follows:

    Uo Ao = (U1 x A1) + (U2x A2) + (U3 x A3) + (U4 x A4) + (U5 x A5) (SBC std

    equation no 4-1), (see appendix - 3)

    U0 = The average thermal transmittance of the gross area of the

    exterior Walls. (W/m2-k)

    Ao = The gross area of exterior walls. (m2)

    U1= The combined thermal transmittance of the various paths of heat

    transfer through the opaque exterior insulation wall area. (W/m2-k)

    A1= Area of exterior insulation walls that are opaque. (m2)

    10

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    11/57

    U2= The combined thermal transmittance of the various paths of heat

    transfer through the opaque exterior non - insulated wall area. (W/m2-k)

    A2= Area of exterior non - insulated walls that are opaque. (m2)

    U3 = The combined thermal transmittance of all glazing within the gross

    area of exterior Walls.(windows) (W/m2-k)

    A3 = The area of all glazing within the gross area of exterior walls.

    (windows) (m2)

    U4 = The combined thermal transmittance of all opaque aluminum frame

    within the gross area of Exterior walls. (W/m2-k)

    A4 = The area of all opaque aluminum frame within the gross area ofexterior walls. (m2)

    U5 = The combined thermal transmittance of all opaque doors within the

    gross area of Exterior walls. (W/m2-k)

    A5 = The area of all opaque doors within the gross area of exterior walls.

    (m2)

    UoAo for roof is calculated as follows:

    a. Roof (details see appendix 1.5)

    UO AO = (UR X AR) (SBC std equation no 4-5), (see appendix - 3)

    UO = The average thermal transmittance of the gross roof/ceiling

    area,( W/m2-k)

    AO = The gross area of the roof /ceiling assembly, m2.

    UR = The combined thermal transmittance of the various paths of heat

    transfer through The opaque roof /ceiling area. (W/m2-k)

    AR = Opaque roof / ceiling assembly area. (m2)

    11

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    12/57

    4.3: Evaluation of the REQUIRED UoAo values as per

    SBC standard:

    The requirement of the wall and roof Uo factors can be found from

    appendix 3.

    UO factor roof/ ceiling = 0.15 (W/m2-k) (see appendix 3, SBC STD

    figure NO:4.2.2(2))

    UO factor for exterior wall = 1.2 (W/m2-k) (see appendix 3, SBC

    STD figure NO:4.2.2(1))

    12

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    13/57

    13

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    14/57

    4.4: The performance method worksheet envelope

    calculation as per SBC 2007 std:

    As per the building constructions As per the SBC - 2007 std

    Roof

    Description insulationR- value

    U FactorW/m

    2-k

    Area(A) m

    2 UA

    Required 'U'

    Factor

    W/m2-k

    Area (A)m

    2 UA

    Roof R30 0.172 575 98.9 0.147 575 84.525

    575 98.9

    see details

    appendix - 3

    see details appendix -

    walls,windows and doors

    Descriptioninsulation

    R- value

    U Factor

    W/m2-k

    Area

    (A) m2 UA

    Required 'U'

    Factor

    W/m2-k

    Area (A)

    m2 UA

    Insulated wall R 13 0.39 1084.5 422.96 1.2 1920 2304

    un - insulated wall 3.19 413.5 1319.1 see etai sappendix - 3

    Windows(glass) 3.8 326 1238.8

    Aluminum frame 4.62 81 374.22

    Doors (glass) 3.8 4.8 18.24

    Aluminum frame 4.62 1.2 5.544

    Metal door 2.5 9 22.5

    1920 3373.3

    see details appendix -

    Total proposed U0A0= 3472.2 Total required U0A0= 2389

    PROPOSED REQUIRED

    Roof total area

    Wall total area

    Building Name : Residential Building (Apartments)

    14

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    15/57

    The Total PROPOSED UoAo must be less than or equal to the total REQUIRED UoA

    ofor compliancewith SBC -2007.

    In this case the existing building construction Does Not Comply with the code UA

    requirements.

    1. Analysis of the studies as per both codes:

    A careful analysis of the above worksheets for the VA method as per IECC 2009

    or UA method as per SBC-2007, the biggest contributor to the high VA or UA

    values is the un-insulated portion of the precast walls. Even though the un-

    insulated wall area is only 413 m2 the thermal-bridging effect of this portion is

    quite significant and it is almost off-setting the benefits of insulation in the other

    portions of the precast wall.

    15

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    16/57

    2. Solution for compliance to Code

    requirements:Two possible solutions can be considered to enhance the existing construction to

    meet the code requirements.

    Solution 1:

    Providing insulation to the un-insulated portions of the wall so as to have equivalent

    performance matching with the insulated portions of the wall. Appropriate

    insulation coverage shall be provided considering the thermal-bridging effect.

    Solution 2:

    Increase the insulation R values from R13 to R19 in the insulated portions of the

    existing wall. Replace the existing glass with new glass having a U value 2.27

    W/Sq.m-DegC.

    16

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    17/57

    Solution : 1(considering all exterior non insulated wallinto insulated wall)

    17

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    18/57

    As per the building constructions

    Roof

    Descriptioninsulation

    R- value

    U Factor

    W/m2-k

    Area

    (A) m2 UA

    Roof R30 0.172 575 98.9

    575 98.9

    see details appendix -

    walls,windows and doors

    Descriptioninsulation

    R- value

    U Factor

    W/m2-k

    Area

    (A) m2 UA

    Insulated wall R13 0.39 1498 584.22

    Windows(glass) 3.8 326 1238.8

    Aluminum frame 4.62 81 374.22

    Doors (glass) 3.8 4.8 18.24

    Aluminum frame 4.62 1.2 5.544

    Metal door 2.5 9 22.5

    1920 2215.5

    see details appendix -

    Total proposed U0A0= 2314.4

    PROPOSED

    Roof total area

    Wall total area

    Building Name : Residential Building (Apartments)

    REQUIRED

    As per the SBC - 2007 std

    UoAovalues =2389

    As per the IECC - 2009 st

    VA values =2642

    Based on the above worksheet, it is obvious that the building

    construction can meet both the code requirements by implementing

    solution 1.

    18

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    19/57

    Solution: 2(considering R19 insulation and change thefenestration U values in

    the PROPOSED values)

    As per the building constructions

    Roof

    Descriptioninsulation

    R- value

    U Factor

    W/m2-k

    Area

    (A) m2 UA

    Roof R30 0.172 575 98.9

    575 98.9

    walls,windows and doors

    Descriptioninsulation

    R- value

    U Factor

    W/m2-k

    Area

    (A) m2 UA

    Insulated wall

    (R13+6)R19 0.277 1084.5 300.41

    un - insulated wall 3.19 413.5 1319.1

    Windows(glass) 2.27 326 740.02

    Aluminum frame 2.96 81 239.76

    Doors (glass) 2.27 4.8 10.896

    Aluminum frame 2.96 1.2 3.552

    Metal door 2.5 9 22.5

    1920 2610.1

    Total proposed U0A0= 2709

    PROPOSED

    Roof total area

    Wall total area

    Building Name : Residential Building (Apartments)

    REQUIRED

    As per the SBC - 2007 std

    UoAovalues =2389

    As per the IECC - 2009 st

    VA values =2642

    Implementation of solution 2 does not satisfy any of the code

    requirements.

    19

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    20/57

    3.Recommendation:

    7.1 Existing Construction

    1. Provide insulation to the un-insulated portions of the wall so as to have

    equivalent performance matching with the insulated portions of the

    wall.

    2. Appropriate insulation coverage shall be provided considering thethermal-bridging effect.

    3. Proper details to provide appropriate insulation shall be developed by

    the architect.

    4. The SHGC of glass shall not exceed 0.3 as per IECC 2009.

    7.2 Future Construction

    1. Insulated pre-cast wall is not recommended. This walls do not have

    complete insulation coverage throughout the entire area of the panels.

    In each panel the edges of the panel are not insulated, which results inheavy thermal bridging effect almost nullifying the effect of the

    insulated portions of the wall.

    2. It is recommended to utilize standard pre-cast wall panels and to

    provide separate insulation to provide complete coverage to the entire

    area of the wall to satisfy the insulation requirements as per the code

    requirements.

    3. The Glass can be selected with a U factor of around 2.0 W/Sq.m-Deg.C.

    4. The SHGC of glass shall not exceed 0.3 as per IECC 2009.

    20

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    21/57

    APPENDIX: 1

    21

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    22/57

    1.1 Proposed 50mm Thick Insulated wall:Construction details:

    U value calculation:

    22

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    23/57

    layersThickness of

    layers (mm)

    R value

    (m2-k/w)

    Inside surface resistance0.12

    Precast concrete120 0.0845

    R13 Thermal insulation 2.29

    Precast concrete60 0.0422

    Outside surface resistance0.03

    Total 2.5667

    U value 0.390 W/m2-k

    see details appendix -3(as per ASHRA

    2009 chapter 26, table no :1)

    Remarks

    see details appendix -3(as per ASHRA2009 chapter 26, table no :1)

    see details appendix -3(as per ASHRA

    2009 chapter 26, table no 4)

    see details drawings

    see details appendix -3(as per ASHRA

    2009 chapter 26, table no 4)

    Total area of the insulated wall = 1084.5 m2

    1.2 Proposed Un insulated wall:Construction details:

    430

    23

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    24/57

    U Value calculation:

    layers Thickness of

    layers (mm)

    R value

    (m2-k/W)

    Inside surface resistance0.12

    Precast concrete230 0.163

    Outside surface resistance0.03

    Total 0.313

    U value 3.1949 W/m2-k

    Remarks

    see details appendix -3(as per

    ASHRAE 2009 chapter 26, table no :1)

    see details appendix -3(as per

    ASHRAE 2009 chapter 26, table no 4)

    see details appendix -3(as per

    ASHRAE 2009 chapter 26, table no :1)

    Total area of the un - insulated wall = 277 m2

    1.3 Proposed Windows:Construction details and types:

    24

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    25/57

    1200

    50

    2000

    11200

    1200

    50

    2000

    1200

    50

    2000

    1200

    50

    50

    1600

    50 725 50 725 50

    25

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    26/57

    26

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    27/57

    Windows details and U value:

    Tag no QtyArea of the

    glass (m2)

    Area of the

    aluminum

    frame (m2)

    U' value glass

    (W/m2-k)

    U' value of aluminum frame(W/m2-k)(as per ASHRAE

    2009 chapter 15,table no:4,

    see details appendix - 3)

    W1 32 169.6 41.6 3.8 4.62

    SC1 8 112.4 31 3.8 4.62

    SC2 4 24.6 6 3.8 4.62

    SC3 1 19.4 2 3.8 4.62

    407Total areas

    Total window areas = 407 m2

    1.4 Proposed Doors:

    Construction details and types:

    27

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    28/57

    F.F.L.

    28

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    29/57

    F.F.L.F.F.L.

    Doors details and U value:

    Tag no Qty

    Area of

    the glass

    (m2

    )

    Area of the

    aluminum

    frame (m2

    )

    Area of

    the metal

    (m2

    )

    U' value of

    glass

    (W/m2

    -k)

    U' value of aluminum

    frame (W/m2-k)(as per

    ASHRAE 2009 chapter

    15,table no:4, see detailsappendix - 3)

    U' value of aluminum

    frame (W/m2-k)(as per

    ASHRAE 2009 chapter

    15,table no:6, seedetails appendix - 3)

    DO 1 1 4.8 1.2 - 3.8 4.62 -

    DO6 2 - - 4.26 - - 2.5

    DO7 2 - - 4.5 - - 2.5

    15Total areas

    29

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    30/57

    Total door areas = 15 m2

    1.5 Proposed Roof:

    Construction details:

    500

    350

    1200

    30

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    31/57

    RoofU Value calculation:

    layersThickness of

    layers (mm)

    R value

    (m2-k/W)

    Inside surface resistance0.162

    hollow core roof slab250 0.266

    structural concrete topping50 0.053

    Thermal insulation(extrudepolystyrene)

    150 5.28

    Loose laid roof tiles40 0.0088

    Outside surface resistance0.03

    Total 5.7998

    U value 0.1724 W/m2-k

    see details appendix -3(as per ASHR

    2009 chapter 26, table no :1)

    Remarks

    see details appendix -3(as per ASHR

    2009 chapter 26, table no :1)

    see details appendix -3(as per ASHR

    2009 chapter 26, table no 4)

    see details appendix -3(as per ASHR

    2009 chapter 26, table no 4)

    see details drawings

    see details appendix -3(as per ASHR

    2009 chapter 26, table no 4)

    Total roof areas = 575 m2

    31

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    32/57

    APPENDIX: 2

    32

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    33/57

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    34/57

    layersThickness of

    layers (mm)

    R value

    (m2-k/w)

    Inside surface resistance0.12

    Precast concrete120 0.0845

    R7 Thermal insulation1.25

    Precast concrete60 0.0422

    Outside surface resistance0.03

    Total 1.5267

    U value 0.6550 W/ m2-k

    see details appendix -3(as per ASHRA

    2009 chapter 26, table no :1

    Remarks

    see details appendix -3(as per ASHRA2009 chapter 26, table no :1)

    see details appendix -3(as per ASHRA

    2009 chapter 26, table no 4)

    see details appendix -3(as per IECC

    2009 table no 402.1.3)

    see details appendix -3(as per ASHRA

    2009 chapter 26, table no 4)

    Total area of the insulated wall = 1498 m22.2 Required Windows:

    Construction details and types:

    34

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    35/57

    1200

    50

    2000

    11200

    1200

    50

    2000

    1200

    50

    2000

    1200

    50

    50

    1600

    50 725 50 725 50

    35

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    36/57

    36

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    37/57

    Windows details and U value:

    Tag no QtyArea of the

    glass (m2)

    Area of the

    aluminum

    frame (m2)

    U' value of aluminumframe (W/m2-k)(as per

    IECC 2009 std,table

    no:402.1.3,see details

    appendix - 3)

    U' value of aluminumframe (W/m2-k)(as per

    IECC 2009 std,table

    no:402.1.3,see details

    appendix - 3)

    W1 32 169.6 41.6 3.69 3.69

    SC1 8 112.4 31 3.69 3.69

    SC2 4 24.6 6 3.69 3.69

    SC3 1 19.4 2 3.69 3.69

    407Total areas

    Total window areas = 407 m2

    2.3 Required Doors:

    Construction details and types:

    37

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    38/57

    F.F.L.

    38

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    39/57

    F.F.L.F.F.L.

    Doors details and U value:

    39

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    40/57

    Tag no QtyArea ofthe glass

    (m2)

    Area of thealuminum

    frame (m2)

    Area of

    themetal

    (m2)

    U' value of aluminum

    frame (W/m2-k)(as

    per IECC 2009std,table

    no:402.1.3,see detail

    appendix - 3)

    U' value of

    aluminum frame

    (W/m2-k)(as perIECC 2009 std,table

    no:402.1.3,see

    details appendix - 3)

    U' value of

    aluminum frame

    (W/m2-k)(as perIECC 2009 std,table

    no:402.1.3,see

    details appendix - 3)

    DO 1 1 4.8 1.2 - 3.69 3.69 -

    DO6 2 - - 4.26 - - 3.69

    DO7 2 - - 4.5 - - 3.69

    15Total areas

    Total door areas = 15 m2

    2.4 Required Roof:

    Construction details:

    40

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    41/57

    500

    3

    50

    1200

    41

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    42/57

    RoofU Value calculation:

    layersThickness of

    layers (mm)

    R value

    (m2-k/W)

    Inside surface resistance0.162

    hollow core roof slab250 0.266

    structural concrete topping50 0.053

    Thermal insulation(extrudedpolystyrene) 5.03

    Loose laid roof tiles40 0.0088

    Outside surface resistance0.03

    Total 5.5498

    U value 0.1802 W/m2-k

    see details appendix -3(as per

    ASHRAE table no 4.3

    Remarks

    see details appendix -3(as per

    ASHRAE table no 4.3

    see details appendix -3(as per

    ASHRAE table no 4.1

    see details appendix -3(as per

    ASHRAE table no 4.1

    As per IECC - 2009 ,see appendix -

    see details appendix -3(as per

    ASHRAE table no 4.1

    Total roof areas = 575 m2

    42

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    43/57

    APPENDIX 3

    43

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    44/57

    44

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    45/57

    45

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    46/57

    46

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    47/57

    47

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    48/57

    48

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    49/57

    49

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    50/57

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    51/57

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    52/57

    52

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    53/57

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    54/57

    54

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    55/57

    55

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    56/57

    56

  • 8/8/2019 Final Sbc & Iecc Std Appartments Thermel Analysis

    57/57