final response to 790628,800609 & 0623 ltrs re embedded

11
(p neuq(o * UNITED STATES ' g NUCLtiAR REGULATORY COMMISSid ,, y .y, g g f. c WASHINGTON, D. C. 20sSS ~ r O g %.... * MAY 2 81981 Mrs. Leo A. Drey 515 West Point Avenue University City, MO 63130 Dear Mrs. Drey: This is in final response to your letters of June 28, 1979, June 9, 1980, and June 23, 1980, regarding the embedded steel anchor plates at the Callaway Nuclear Power Plant. Previous NRC letters that were sent to you on this subject were dated October 30, 1979 and July 8, 1980. In addition, a copy of IE Repsrt 50-483/80-14, dated September 16, 1980, was also sent to you. A final review of this matter by hRC Headquarters staff has now been completed. While that review was underway the Atomic Safety and Licensing Board for the OL proceeding issued a Special Prehearing Conference Order (dated April 21, 1981). That Order outlines the petitions submitted, defines the intervenors and describes the contentions that have been admitted for the hearing. Joint Intervenors' Contention lA stating that, " inadequate and incomp'ete inspection and testing on embedded plates were performed during the plant's construction" has been admitted. This contention will assure Board review of the resciution of the matter of embedded plates. This reply will provide you with the staff position on this issue. While preparing this response and the specific items in the enclosure, a review was made of the various questions and concerns that you had expressed in the past related to the embedded steel anchor plates that may not have been specifically addressed. These items are listed and a response or the reference to a document you have received previously is provided. We hope that this information will satisfactorily answer your questions and conce.ns. We are of the opinion that the questions and concerns related to thL concrete embeds installed prior to June 1977 at the Callaway facility have now been resolved to the satisfaction of the staff. Sincerely, , ,f ( _ A ,~ , o y j ,| I Victor Stello, Jr. , Director Office of Inspection and Enforcement Enclosure: 1 Specific Responses 8108210180 810604 PDR ADOCK 05000483 U ppg

Upload: others

Post on 19-May-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Final response to 790628,800609 & 0623 ltrs re embedded

(p neuq(o*

UNITED STATES'g

NUCLtiAR REGULATORY COMMISSid,,

y .y, gg f. c WASHINGTON, D. C. 20sSS~

rO g

%.... *

MAY 2 81981

Mrs. Leo A. Drey515 West Point AvenueUniversity City, MO 63130

Dear Mrs. Drey:

This is in final response to your letters of June 28, 1979, June 9, 1980, andJune 23, 1980, regarding the embedded steel anchor plates at the CallawayNuclear Power Plant. Previous NRC letters that were sent to you on this subjectwere dated October 30, 1979 and July 8, 1980. In addition, a copy of IE Repsrt50-483/80-14, dated September 16, 1980, was also sent to you. A final reviewof this matter by hRC Headquarters staff has now been completed. While thatreview was underway the Atomic Safety and Licensing Board for the OL proceedingissued a Special Prehearing Conference Order (dated April 21, 1981). That Orderoutlines the petitions submitted, defines the intervenors and describes thecontentions that have been admitted for the hearing. Joint Intervenors'Contention lA stating that, " inadequate and incomp'ete inspection and testingon embedded plates were performed during the plant's construction" has beenadmitted. This contention will assure Board review of the resciution of thematter of embedded plates.

This reply will provide you with the staff position on this issue. Whilepreparing this response and the specific items in the enclosure, a review wasmade of the various questions and concerns that you had expressed in the pastrelated to the embedded steel anchor plates that may not have been specificallyaddressed. These items are listed and a response or the reference to a documentyou have received previously is provided.

We hope that this information will satisfactorily answer your questions andconce.ns. We are of the opinion that the questions and concerns related tothL concrete embeds installed prior to June 1977 at the Callaway facility havenow been resolved to the satisfaction of the staff.

Sincerely,

, ,f ( _ A,~ , oy j ,|I

Victor Stello, Jr. , DirectorOffice of Inspection and Enforcement

Enclosure:1 Specific Responses

8108210180 810604PDR ADOCK 05000483U ppg

Page 2: Final response to 790628,800609 & 0623 ltrs re embedded

- ,

e

d

Enclosure

SPECIFIC RESPONSES

Q1. Isn't it possible that some anchor plates embedded prior to June 1977 aredefective?

A1. Yes. It was NRC's continuing concern about the integrity of the anchorplates embedded prior to June 1977 that caused the initiation of the randomin place test and representative test programs that were reported in IEInspection Report 50-483/80-14, dated September 16, 1980 (see 3rd paragraphon page 6). Considering the small number of defective embeds detected bythe re-inspection and testing effort, the NRC has concluded that an equalproportion of defects in installed plates would be well within the tolerancelimits of the system design and no more special efforts arerequired for the installed plates.'

Q2. Is it possible to find and replace defective anchor embedments alreadyinstalled into'the concrete?

A2. The use of a visual examination is precluded when embedments such asthese in question have, in fact, had the concrete placed around them,unless destruction of the surrounding concrete and reinforcing steelmatrix is accomolished. No nondestructive techniques we are aware ofcould, in this instance, be utilized to provide meaningful results.Therefore, in this case, the first action we deemed necessary was anexamination of anchors not already embedded. We concluded that the dataobtained in July and August 1977, supplemented by some later informationon embeds not yet cast in concrete, could be considered representative ofthose anchors already embedded. Consequently, a destructive programwould become necessary only after it was evident that the failure ratesin the ability to carry and respond satisfactorily under load were toohigh in a similar and representative sample. Wita high failure rates, itwould become necessary to execute extensive load tests or ccmplete theremoval of concrete to obtain samples on which to base a conclusion.Although removal of concrete and replacement of embedments is possible,it is a difficult task and requires close control and consideration ofthe potential for additional damage. In the past, NRC has required theremoval of some very complex concrete structural components consisting ofmany cubic yards of concrete. This situation was certainly not precludedin this case. ;;

Q3. What assurance is there that anchor embeds not already cast into concreteare renresentative of those niready embedded?

,

A3. From the records available revealing that the anchor embeds had beenfabricated, inspected, released, and accepted under the same specifica-tions, contract, and work procedures with the only variable being thetime the work was completed, we concluded that those units not yetembedded were representative of those already embedded.

Q4. With regard to the results of inspections performed on manually weldedanchor rods for embeds, did the NRC believe Daniel or Bechtel?

|

.

Page 3: Final response to 790628,800609 & 0623 ltrs re embedded

- . - . -.

i

*

.

|

-2- Enclosure

'

A4. The reinspection performed by a team of inspectors consisting of personnelfrom Daniel, Bechtel, and Union Electric Company, in order to identifythe cause for the original rejections made by Daniel, was accepted by |the NRC as representing the facts. The findings were discussed in IE :

tInspection Report 50-483/80-14, dated September 16, 1980 (see pages 8and 9).

Q5. Compare'ASME, AWS and Union Electric criteria on weld undersize for'accepting manual welding of anchor rods for anchor embeds.

AS. As noted in the March 10, 1978 letter from Union Electric to which you 1

referred, the ASME Code does not apply to this type of safety-relatedcomponent. In referring to the ASME Code, the licensee was addressingthe ASME Boiler and Pressure Vessel Code, Section III, Division 1 whichaddresses Class 1, 2 & 3 components, metal containments, component supportsand core support structures. These componeats do not include generalstructural framing supports, of which these manually welded anchor embedsconsisted.

The comparisons of AWS and Union Electric criteria were provided in IEReport 50-483/80-14, dated September 16, 1980 (see page 7). NRC acceptedthe criteria used by Union Electric.

Q6. What is the applicability of AWS D.1.1-75 for machine stud welding?

A6. As noted in Answers to Questions 6 and 7 of Attachment B, IE InspectionReport 50-483/80-14, dated September 16, 1980, the above standard wasintended for application to machine stud welding and acceptance testing.

Q7. Are the requirements for the acceptance of machine stud welding on bridgesmore stringent than those applied to nuclear power plants?

A7. The following comments are based on a comparison of specifications of theAmerican Welding Society (AWS D.1.1-75) and the American Association of t

' State Highway and Transportation Officials (AASHTO Interim Bridge Specifi-I cations for 1975). These listed items constitute the primary differences.1

| a. AASHTO allows welding when base metal is below 0"F but requires '

,

| preheating to 70*F and maintaining the base metal above 32*F duringi stud welding. Two additional 45" angle bend tests are required perj 100 studs.i

| AWS allows no welding when the base metal is 5elow 0*F and imposesi additional inspection / test requirements when the base metal is below

32*F.

b. AASHTO requires the contractor to submit the following informa-tion to the engineer for approval:

| (1) name of manufacturer,i

-(2) detailed description of the stud and arc shield,*

i

!

- . . _ . . , _ . . _ . m. . . . _ . ._ - _ - _ . _ _ _ _ _ . . _ . . . ,_

Page 4: Final response to 790628,800609 & 0623 ltrs re embedded

, .

-3- Enclosure

~

(3) certification from the manufacturer that the stud has metAASHTO qualification tests, and

(4) notarized copy of the qualification test report as certified bythe testing laboratory.

The purpose of the qualification testing is to prescribe weldabilityand strength tests for a given type, size, and arc shield. If all

factors that could affect stud performance remain unchanged, suchinitial qualification tests remain valid.

AWS does not require qualification testing, unless requested by theengineer. Such a request would typically be done in the writtenspecification. The number of tests to be performed is left to theengineer to specify.

c. AASHTO production acceptance inspection for the first two studs on abeam requires bending to 45*, whereas AWS requires only a 30 bend.

d. AASHTO, as you indicated, requires that "each stud shall be given alight blow with a hammer" ard "any stud which does not emit a ringingsound when given a light blow with a hammer.... shall be struckwith a hammer and bent 15 from the correct axis of installation.Studs that crack either in the weld or in the shank shall be replaced.".

In summary it can be stated that there are only minor differencesbetween the AASHTO Standard Specification for Highway Bridges andthe AWS Structural Welding Code and that the AASHTO specification isa bit more stingent, undoubtedly because of the need for fatique life.The two specifications / codes are intended for different types ofstructures which undergo distinct service conditions. Fatigue is amajor concern in the use of studs in composite bridge design as aresult of the many load repetitions a bridge receives as opposed toa building structure. It is NRC's position that the requirementsplaced on a licensee (in conjunction with use of the AWS Code) thatinclude operator training and qualification, quality control,inspection, and correction of identified deficiencies are more thanadequate to assure the proper level of safety.

,

Q8. Will manually welded anchor rods with undersized welds be able to withstandthe maximum design load, vibration, and durability requirements?

A8. The analytical calculations completed by the licensee as reported in IEInspection Report 50-483/80-14, dated September 16, 1980 (see page 8), aswell as the additional testing requested by NRC (see page 9 of the above-referenced report), demonstrate quite clearly that the maximum designload can be met. Tne load-strain curves that reflect the behavior of thesix specimens cut from actual anchor embeds clearly illustrate a ductilebehavior under load that provides the energy-absorbing capability forresponse to dynamic loading. Vibratory loads with respect to fatigue-related problems are not considered to be of sufficiently high numbers of

Page 5: Final response to 790628,800609 & 0623 ltrs re embedded

e -

<

-4- Enclosure

repetitions for these embedded elements to be of significance. Durability is

not a major problem with these anchors since the backs of the embedded plate,the weld and the anchor rods are embedded in concrete and are not subjected to |

an adverse environment. ;

.

Q9. Have specifications changed to meet the deviations which were found?

A9. As noted in IE Inspection Report 50-483/80-14, dated September 16, 1980(see page 7), certain revisions were made by the licensee as Revision 9 ,

to Specification C-131. We do not know the motive for the change, but we.iave establi-hed the technical validity of the revision as noted in theresponse to Qi.estion 8 herein.

Q10. A dangerous percentage of the manual and machine made welds are defective. ;,

A10. During the reinspection of over 81,500 machine-welded studs on 7543 anchorembedments not yet installed, only 0.08% of the studs failed the bend test.It was rlt? found that 0.13% of the anchor embedments had more than onestud failing during the bend test. Testing a sample of 2.5% of the embedded ,

anchors with machine-welded studs to design loads resulted in no signs ofdistress or indications of inadequacies. There was no evidence to suggesta difference in the frequency of studs failing the bend test on anchors thatwere embedded or on those anchors that were not einbeaded in concrete. Ourconclusion is that the failure rate to bend tests on individual machine-welded studs was low and would not cause technical questions related to thefunctioning of an individual anchor as shown by the in place testing program.

We determined that 10% of the manually welded anchorage rods remained inquestion and required further study. The further study included &ctualtesting of individual welds of the anchor rod to the embed plate that werecut from the group of anchor embeds that had been on hold since August of1977. The welds sustained the ultimate failure loads of the base material.Analysis of the weld deficiencies also indicated that the embedments asbuilt would sustain the design loads. There was no evidence to concludethat manually welded anchorage rod to anchor embeds already cast in concretein June 1977 contained any different or more frequent weld deficienciesthan the group examined and tested.

Our conclusion is that there is no danger in the manual or machine-madewelds in the anchors embedment cast into concrete prior to June 1977.

Q11. Does -telitel have a lack of faith in the ability of Daniel inspectors inareas other than the inspection of manually welded anchor rods?

All. In this case, the Daniel inspectors were being more cautious than necessary,so the problem they identified was brought to the attention of the licenseewho in turn obtained the design expertise of the engineering disciplineswho resolved any safety questions to the satisfaction of the NRC, We areunaware of any Bechtel concerns; however, we are certain that ;f therewere concerns, Bechtel would report them under 10 CFR 21.

,

Page 6: Final response to 790628,800609 & 0623 ltrs re embedded

. .

-5- Enclosure

Q12. Who bears the burden of proof regarding safety at the OL proceedings?

A12. As defined in the NRC regulations, the burden of' proof rests with thelicensee.

.

i

.)

!,

I

|'

. _ - _ _ _ _ - _ _ - . - _ . _ -__ _ - , _ _ _ _ . .

Page 7: Final response to 790628,800609 & 0623 ltrs re embedded

r . .s~ ~ + . - - ~ ~ -

u .o.- .- . -- ,,, g vf ,.

.} :f .-.. . , .~ .. a v.

t .~ p *.p 'p i - .~---, ,m, ~ ^e e .-4-;yf.;' ? , s s .:

-

.; _

' ' N. Q _ . .;* ~- ' ~ .Q=Q.,* ' '

.H'

0* ACTION CONTROL }- VATES ICON ROLN . ,,..

~'~ - p7QM: ' 6 . ,1 1. .c . r. p. '- y j. A.T.,. .

<~

oet oc^ouN E . I d =. . ,,=..2. , - . . . w. ._ v -

_ ,c. . ; .- % .

~7,) Q / hOD ATE,OF DOCUMENT . J -

Rdp; Psichard A. Gephardt. .:. ; .,

ACKN OWLEDGMENT..

G. ?.k'j . ''t . . , . - 6/25/80 -. . ~ . . '.f. # ... . . .[:.'.. .

.. .3 ,y,,,,,,E,uy.. (c':f,

.

* * . * , .PREPARE FOR SIGNATURE

.

*- .

. . .. . -; .c ~ ~. . " _ " FINAL REPLY'

OF' ' ~,.;; *""**-,.

TO:- -. c. O CHAIRMAN

Vi ctor. .SteTl o.' ' U| " J ' . . N .J . :A'. - f N. . .=

,, f| r FILE LOCATION . Q EXECLTTIVE DIRECTOR'

:s.:J y ; ' N.~. '.''.'-W'&@r.%.'?-3.Ch . .. orsERi -' ' v 2

...T '. M .-: % h . d .Z-;6 M- 73A2.1D(f-

D tETTE R * Q MEMO ,1Q RUCRT ' O OTHER. SPECI ALMTRUCT10NS OR REMARLS ., E.D..O-6772a g,. .---

.i---

- - - - .-

=. ' . -95. .-m. . , . ., a . ... - . . .;g.;.- N.4;i_:,. . -a ssCRamON .4..- .. -. . ,..u _.-

. 5. %. , .'.m .;.. . ..7 y. W N . Q. u. -Ltr-1 rom Kaf"Drey-concerning4enoedde'd.MM-J'q.p.@w'5."E .f,9 .E. . . '

~ sten. ed abplates si.t..h f.aul.tp stud'.weldsM.n,offyeview;Y .'; --~ ~ f 8 z.~ . . 4 :7. - ~/ ' , 7 ~2,: -

. . . , . . . =.~. . .g . f . y, - . . .r.. : ;s- ... .- .

. .,

the Callaway p'hntM. . req status; - .% '

.of the:. situation and :an..y finaPdetsmina6~

,

.- e.- w. n=~. ~- <v. :. - * ' ,, . ~ . - ,,

.i9 [ ' y - .

',{f)'- ,

I, . . . _

. .-CLASSIFIED DATA ':$g NN. [ [iO ^

, ,

I E'

, , g , ,, , . ' . . , ,,,.

j,

f[ , . . , . , ,

}, . . -[.k* ,( .30CUWENT/ COPY No. | r.W . Ct p6BCA180Nf - . . .d- ,

gy ,-NUM*,CR Ol' PAG ES .-

* '/ CATEGORY.Cgg*,O rRo. - - -

-- r

-<.'-v-1.-' ..

-O usi? O Ro''NSTAL R EC15T RY NO., f LEG AL REVIEW O FINAL 0 cor'y

A55tG N ED TO: f' D ATE . INFORMATION ROUTING NO LEGAL OBJECTIONS .,DATEAssicNEo m NOTIFY >.T. ---

.

Q 01 .' 7''7/80 J f- k c.:.5 .. ,

- gg.;. .- - :-d. - ."' .

.

O EDO ADMIN & CORRES BR-;.. '.g

-.% ' .~7 7 $0_ :' - a. c... . - w.

) N"1 Mf.A Q.fJ l .

L. ; . -- COMMENTS. NOTIFY: ..

. y ,. c, :. ,. " ~ Exp. _j. .

."

- .} [ - - r-v . . .O vEs O NO !'.I

. h..O.- M Gf_':.' N .JCAE NOT]FICATION RECOMMENDED:

EXECUTWE DIRECTOR FOR' OPERATIONS 7'

00 NOT REMOVE TN/S' COPY~

.., . . .. r

* 2.C F O R M ~132~ 6 '

.

PRINCIPAL. CORRESPONDENCE CONTROL .. . . . _ . . _(11-73)-

_ _ . . . . _ _ . . _ . . . . _ _ _ '---

- - . . .

. , _ .:_=.___.=._. c, , _ . . ._ #=-- . . . . = = . . _ . . - . . ...-.. . . . . . _

_ ' :~ 7:.---'- % ..u.- . . _ . . . . . . _ . , . . _ . . . _==;.,._..._... . . . . . . . . .

. . .. . . . . . _-

_ _ _ _ . . . __

,

i._. - - - . . . . _ . . -

- f=_ . _. m:. ..=. L. =:- = w. .._ . ..___ . .sz;%.3t:. . /--- _ . - . - - -

= = .. . . . . . -=g,....,-.--._ ._ -

_ . . . _ . -

-..:===---

-- : _ ;r__--

-~- - q._ ? __=-.=..=.y....._ _.

. ;.m5.~f - == =[_- -|-- 2 _ f- --- -.

. -?.:. .. ._ ._ .

.__

& -.;= 4 . W_ q =. p .. _..

= =z::.=C}.~E*E~.Gi=h .:, :K .._.:===| - -|m=1:: :-i 7= p- .

~% -% nR = =-.. d_p:..... " --f_=.........._g==-= - 'L q , .=} =/ 1.5 -- x- -- ---- 5

^

._

. =i' ?: === =~.^

..-.._...~J.. .--

; ..-;c== -

..

="-=== = =:==' . _ . .

. ._.. .- y2 t:== 4 ---

-~~-[H. ....-

. /= 11:== ;.4 .z.: == = - - - - -..,..=_..-- ..

r- y-.- . ~ . .- - - - = - - - n-

= . = . . _ = . - - _wW~=====.: == -"=--...x f..;=_ 2 = ... - - --.a _ j%y=r--=_. - ':

-

5~=..._.T~==p~.~=.=_=.=._.=...=. -? . z. ;. ==== =-.._...$=._.:-..... = . . ..

= . ..

- - - - -

.=..?''.... ----

-

-

/ = :== == = -. . w-

. . . . . . . . . 5j^

- - - - ~ "~~'4==P''

= =.. ... . ..-.."._._~.~.-..._"._..=*=.";:=55

-'

:~ [2': ? 5. .... ::. :::. %a*- -. |.

.* - ^ ~ ~ x. : ._... _ _t*_$ ~ % ry_;; I". =.'=p ^.~ ~_;~.~'=~~*. . . . . .~

_

' ' "

- - - ;; ..- . . " . - . . . . . _ ,= . ' " * . " .~'-...__"..;;=~'."::.'=- . . . .

;;;j; ;; , *$. ~k ---.|='. 5 ==L ..-. - = . ~ . . ~ ~ -_ -~;;;;. =_..._ . ,; ;- h1 . . . . _ , , _ , _ _ ,

^

.

~~"7 0_)p. %=_.r,.,; A.:

_......_-.-..__-.-.';;.-__".''.....-._' ,~-~__ :=.== ;~2 :." ~"

. . ,

- - - . . . ,- _ _

__

__

. . _ - ..

h5$ .r;== --- - -- ~ .. 3;.--. . . . . . _ . . . . . .

'= " I.~ ":^=::~.' _ - -" . ~ - ~ ' ' ~. - = -

__ s_i"~---.--- 1

y= : _= == == r- -

- :=y f ~==: :: = _ ._ y ----L .:_

_,,;-. ,,

__q ==.: = - --

- - ~ . . .:.; .. ; .:...;;_ .

..=:=_--- _f . _ . _ , , _ . .

}.|_ .5=2.==..

._.. . . . . . . _ . , . . , _ .

.-._.,.;._......._.;___._y

-{ .= . - _ _ _ . . _-

y ;*- ' --- -- ~ .==t*- . . . . . . _ . ., _ , , . - - ,

, . . .

- . _ . . . - - - - -; . _ . . . . . _ , . , ; - f .. __.;3

-.g....-- ... ... . . . . , . . . _ _ _ _ _

|f d .__. ----.~r __

, " ' - " - " - -. . .g ====:--. . ...

.-- ^

::--

.rf jf3_~^^=~~''~~~=__. ..-..._ -.

:s ..::y'AY.$:. .'TL.}2~ =.t~; ~= |j&~~ -. . :_

= :: = 2::- .. .: : _ :: . :== .. :_. . .._ ._ .: . . .~ $: - -- = = = - . - - - . . . . . . . . . . . . . -. .. _ = ;. --f. .f Y_ Y Y-===-giW- ....&.__.... .

. -.

:= :h=y-~..e-. ;_.. . ,, =..- -. ==

-- . _ . . . _ - . . - . . ;._

s.-__.

---_.+ .

.===t===...--- - = = .

=: : . . .- . . . _ - 4:.

. f. . = = = - ==. - L_ _u -_._ _ .= = _ . = . . =. .s.E: ..- = ===== ===-=====;:..n._-....

-t.=..._.____

.

:-..=====r=n="t::==== ,; . . .

t...... - " - - . . . . _ . . = . . .:=:: .. _.s - : .:

.f..._.::..... _ ._. _ _ ._ J_ . T. . .=.._--- : =_. =. . .. ._:::: = A_==. . .- , _-- :;;.... .. .... _.j: ":!=_L. A._3,;.;= =.. . - .

= = - - - - .::_

-.._ .f . .f., y.g : . - . . .

. .

.2 = .=-.

_ _ . . .

ff.. :====...: _ . ..

a .; " . . . . . R . : . . . . . . . . ~ . . = . . . . . . . . . . . . . . .= ._ - u.-_ . .;: : -. .r pm : - - ~= = . . . . - --: - . - ^rt :. - ~ . : _-= = . . . . = = = - - - -. . . . ...:. = . . = =

.=: . . . _ _ _ . _ = = = - - . =======_=r=====:==-===.

,n. . .

-

__=v. =.:1 .g _;p- ,. .. .=. =.. ._ _..=_. _ _=. -. .- ===. . c n. . . .. . .

- -..==.=:=---.z====:..==.====:======._u=_=.-.;;-.--;_. . . . ~ . . . '=."::.

__

: .-" -~':=- . :.- :::=:

.

_.

'-'''- "':: ' -';

-:= u :; _-- - - ~ - - -.2 .: . . = :. :-. -' ~ ~ ~

_.~===~;="=:".',-. -:=--::- ;: ,:y ~--''

.;-. . . . . . . . . . . . . . . _ . . . . , . . . _ . _ ~ ~ ~ ~ " " " ' - _

^ ~~ " 7 .. . _.; . . .

{,,,__,_" " ' ~ "

....:~=:.=~.='".='*'~.,.~_" . " _ . '

'C~l~.*_=''-~=.''-~~_=_....._-__.~!'.~~ . - . (.- i b['. _ . _-- _ _ . - . . . . . - . _ _ _ _ . . . . , _ _ _ _ , _, _

Page 8: Final response to 790628,800609 & 0623 ltrs re embedded

.

Qw mms,

!' ' 'fnD A. GEPH RDY \ (of ~ ~ ~

pm, y ,,_ . ( 21S Cu Houst Om air, |>A

.

f Waseenamnus D.C. 2:311

LF s6 ~ (*") =""'.r, ,,e -enas cow-rrrez-

CONGRESS OF THE UNITED STATES4_ (/*

.u cer co--n zz --

3 HOUSE OF REPRESENTATIVES *'"*","*''T,3,, , ,

WASHINGTON, D.C. 20515 "('")**'"'"

.

June 25, 1980

.

_

Mr. Victor Sra'lo, Jr., DirectorOffice of Inspecrion and EnforcementNuclear Regn12 tory Cu 4ssionWashington, D. C. 20555

Dear Mr. Stello:

Recently, you received a request from Mrs. Leo Drey of St. Louis,Missouri, requesti:g the status of a technical review of the CallawayNuclear Power Plzst, now under construction in Missouri, with regard tofixtures installed in the concrete valls known as embeds.

You had indicated to Mrs. Drey that this review had been re-scheduled. Tae efore, I an writing to request that you provide me withany fcher infor=ation you night have with regard to your review of thissituatica and any final deterrfrintions you have made.

Tnank you for your attention to this matter.

'

Yours very truly,

.k,Richard A. Gephardt

RAG:fc f

.

i

.

|

|

<

O

i - ,

; t \k,i - '

& OL d. * J

Page 9: Final response to 790628,800609 & 0623 ltrs re embedded

~ _ . ,U.iversity City, MD 63130

'

Juna 9,10SD, ,

. ,

F Victs: St,''n, Jr., Direct ==-

** O'fi_te =f Insp: tic.n and Enfc:= mentNaclear Regulate:y Concission

,

b' ashing'en, D.C. 2CSSS

Lear Mr. S+=11n:

Th:=e years ag: today an PEC inspect =: auditing con,struction re== ds at the Callawayplant here in Miss== i noticed that e= bedded plates with faulty stud welds had beenins',''rd. By that time app:cxis:stely five pe==ent of the plant construction had been,,.c:x::,leted, and an esti=ated 400 e: beds had been insta'1-d. To qucte from page one ofthe St. Louis Fes'-Dis: etch. Cctobe: 16, 1977:

"The most sericus c=mplaints, (Nuclee Re: ulatcry) c... lssion officials in-di=ated, involve the fixtures inst ='l-d in concrete walls, *.o, support the. ends

3cf load-b arin: =: teel bam-=. The fixtures - ter: red 'e= beds' because they areenbedded in ernfc=ced concrete - are steel plates with sh::t steel studswelded to cne face, like the bristles of a brush. They are mounted flush withwell surfaces, with the studs (or b=istles) extending into the concrete so that .their exposed faces can serve as peints of attach:ent for girders and otherst:urturel me=bers. Should an e=6ed tea: loose f tra a wall, ' the result couldbe the rm7': pse of an errtire flo== or reef, c xistruction experts say."

On June P8,1973, shortly after you be=a::s the dire =ter of the Office of Inspection andEnfc ___,_nt, and th:ee hectic r:enths after the Th ee File Island -a==ident began, I wroteto ask you about the e== beds. You answe..ed on Octche: 30 es follows:

"With rege d to the steel embeds at C=1'away we have no new information to for-*

werd to you on the matter until a technical review is ccrupleted by the staff.P-4dh on other work have prevented the ccrnpletion of the review. The == viewhas again been rescheduled and we hope to eceplete the project in the nearfuture. Ve will then respond to y=ur conce=ns." #'*

I ec writing today, seven acnths later, to ask for the status of that review, and tostate ance again the concern many of us here shar about the embeds:

.-

- If the embedded plates shipped in 1976 to the D'1away site from the Cives-

Steel Ccrepany (Gouverneur, New York: Pu =hase Orde # 10466-C-131-2) were in- one big "p ' " when constru::tien began; and3

- If hund:eds of embeds f: xa that p''- were installed pric: to June 9,1977, theday an tac inspetor found records indicating that faulty plates had alreadybeen insta''-d, and the day Union Electri= then issued ordertto stop insta115$gI additional plates; and

1#

- If, as the ssult of several m:nths of special inspecticns that su:ner, hundredsof e:6eds were : paired en site and hundreds m::e were shipped ba=k to Civesfer repti: c replacement;

| - D0iS IT TE FCU.De' that so=e of the e= beds installe:: pric: to June 9, 1977, mayalso c:ntain faulty stud welds?

That is, steel e= beds fabricated et the sare tice and place as those found defe=tive are'

s*#'' in the wi''c cf the Itwer levels at Cs'' =way, supposedly supp=-ting whcle fice:syst- and c .her dical structural me=bers. Of particular cen=ern a = those plates en.wt.i=h the studs were welded mechan #-*1'y - that is, in the faster

_ _ _ . - _ ~. .-e more _ e==np esw __J

Page 10: Final response to 790628,800609 & 0623 ltrs re embedded

-'

. . _ . _ . . . _ - . . _ _ _ . . , _ . - , . _ ,m_ ~ .

_

t..

.. ,, .

',/ "!.Wen the Operating License p_oceedings ft: the Calle-ey plant are held,w"' the burden of proof that the e-leds were fabri: ted and instelledes cesig .ed lie with Unien ilectric, Ee:htel/5ftJFF5, Deniel Interne-tic.el, c= the fiRC7

Th ce years of censtruction ere n:w resting en e-beds whose safety has been questioned.b'ill the questions be res=1ved only after the plant has been put into operation end theer. beds the_ shy subjected to the =sulting vibrate:y st:ssses?

Sin =e_- ely,

9M :. Leo Drey (Kay)

Dr. John Ahea ne, A: ting Chaiman,c=:

Atcx:ic Safety a.rd Licensing 3oard, NFCsnd Herabe:s, flu: lear Regulatory Cor.wissionAdvis==y Cercittee on Ree:to: Safeguards, 1i3.0.

Ecrve:ncr J=seph TeasdaleSenatc= Theces Eagleton _

Senatc= John Danferth-Congress =an VM'', Clay

.

Congressman Richard GephardtCong:=rsr.an Harold VolknerCongress .an Fobe:t YoungMr. Janes Keppler, Director, Region III, PGtC

.'

,/B''% H ,h. .

..

.

2._P

y.c. . . . -_

- . ... .. s.- ,

. . .p. .:. .

T'he average si2e cf a steel e=6ed N ,,[-"3Sf4/77 /4I/h.: .

'

at Cellaway is 14' uide, 4 feet _

long, and one inch thick - with g 3,f f,f /g 4\ 'g y + .

/ . [9 -! -',

twa ws af studs, ten in t ch rcw. t/CAYU, V/b, !*d,A/Df.$ '

.' .|,

o. ,.

A stup weld should be strmg enough j N- -

~ ''

te sh: vive being th::vn 1::xs an_

*

,. .,

airp#1ane. Tradition >''y ironw:-kers rr#

O.h a. :.oner-test eve ,y stud weld, and . k' ~

s .'

welds a e not repairable, the plate [N, // j $- .[./ *

reweld every defe::ive one. If the v,'

!*

''tIIO g* *'

\ .i's'=cie=ted. QhI g,

,

.'

}*

Cn many e:~ beds at Callaway 15% of g$4,!7 gjs/g 'y . .

' ' '

tWe welds were defe=tive; on scrae $ .

[ C J ,4G7'

!e ceds, 25,. 5:n-e studs b ':e off.

'

s.O'3 s v .

'- .

>-hen ee ely kicked. Cthers fell - .

=ff w!.thout appare::t cause, such as . fh$""

i 3f::= a 7 ft. high c: bed that was ,, .

~ . * . * .,

:eing insts''-d in February er_

y .,' ; ,d',.a ch 1977 as part =f a do:- frazie LCL " d '-

,

w ,

'_ m -

Page 11: Final response to 790628,800609 & 0623 ltrs re embedded

MWMkM A ccilia.:y / X/q')(Jg-O fp gdj TJ .~

.

;''ildin g s . I:cwc ka: Ic:==an 8 j*

'. ' .-1.

C Sr art =vp==ted t.h2 defectiva f.s i''

,.

t CGd to Rog2= 3enton, his h gi ;4 . O* *

,

> e cupe:intendent. Seyg:z g,y, b. ''*'

3enton t:1d k art that he, '

.r:C:.

,

e Ocn, had bee. di seted by Andy "h * ' <

ennsdy, a top Laniel efficia.1, to / **g.

a so 5 .e:: advise his een te handle /-.'

5e e lads mers carefull in the -@ '_

fu: s= that ec:s studs w:n.:1d no: __-

C eff! f1.

D. I,t

1

- . ~ . , , . - . . , , _ , - - _ - _ _ . . . , . - . ,_ . ,____.,_.,___,2.,m

I

.

d

. ,.

t, .. . . . .