final report on lessons learned exercise on un:undp ......end of the second year of its...
TRANSCRIPT
![Page 1: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/1.jpg)
LessonsLearnedExerciseon
UN/UNDPPeacebuildingEffortsin
SriLanka
FinalReport
October2018
![Page 2: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/2.jpg)
2
Acronyms
APRC AllPartyRepresentativeCommittee
ACLG CommissionerofLocalGovernment
CAIP ConsolidatedAnnualImplementationProgramme
CLG CommissionerofLocalGovernment
CEPA CentreforPovertyAnalysis
CMO-C Conflict-Mechanism-OutcomeConfiguration
CTF ConsultativeTaxForce
DS DistrictSecretariat/Secretary
DS DivisionalSecretariat/Secretary
EPC EasternProvincialCouncil
EU EuropeanUnion
GLED GovernanceforLocalEconomicDevelopment
GoSL GovernmentofSriLanka
ILO InternationalLabourOrganisation
INGO InternationalNon-GovernmentalOrganisation
IRF ImmediateResponseFacility
LLRC LessonsLearntandReconciliationCommission
LTTE LiberationTigersofTamilEelam
LOGOPRO LocalGovernanceProject
MDTU ManagementDevelopmentandTrainingUnit
MFA` MinistryofForeignAffairs
MOJ MinistryofJustice
MOWCA MinistryofWomenandChildren’sAffairs
MPCLGS MinistryofProvincialCouncils,LocalGovernmentandSports
MRRHA MinistryofResettlement,Rehabilitation,NorthernDevelopment
NGO Non-GovernmentOrganisation
NIRO NationalIntegrationandReconciliation&OfficialLanguages
NPC NorthernProvincialCouncil
OECD-DAC OrganisationforEconomicCooperationandDevelopment
OHCHR OfficeoftheUnitedNationsHighCommissionerforHumanRights
ONUR OfficeforNationalUnityandReconciliation
PBF PeacebuildingFund
PBSO PeacebuildingSupportOffice
PC ProvincialCouncil
PCA PeacebuildingContextAssessment
PPP PeacebuildingPriorityPlan
RDS RuralDevelopmentSociety
RMS RevenueManagementSystems
RTI RighttoInformation
SCRM SecretariatforCoordinationofReconciliationMechanism
TOR TermsofReference
UNDP UnitedNationsDevelopmentProgramme
UNHRC UnitedNationsHumanRightsCouncil
UNPBF UnitedNationsPeacebuildingFund
UNRCO UnitedNationsResidentCoordinator’sOffice
UNV UnitedNationsVolunteers
WRDS Women’sRuralDevelopmentSociety
![Page 3: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/3.jpg)
3
TableofContents
Acronyms.................................................................................................................................2
ListofAnnexures......................................................................................................................4
ExecutiveSummary..................................................................................................................5
1. Introduction.....................................................................................................................8
1.1ContextAnalysis.............................................................................................................8
1.2UNResolutionHR30/1.................................................................................................10
1.3ThePeacebuildingPriorityPlan....................................................................................10
1.4 ScopeoftheStudy..................................................................................................13
2. MethodologicalApproach..............................................................................................14
2.1 RealistImpactEvaluation.......................................................................................14
2.2 OECD-DACAssessment(Relevance,EffectivenessEfficiency,GenderEquality)....16
2.3 LessonsLearned:UnderstandingImpactandSustainability..................................16
2.4 DataCollectionandSampling.................................................................................17
2.5 Limitations..............................................................................................................17
3. KeyFindingsandLessonsLearned.................................................................................19
3.1 Project1:SupporttotheSriLankaPBFSecretariatandGovernmentSecretariat
forCoordinationofReconciliationMechanisms....................................................19
3.1.1 ContextRelatedFindings................................................................................19
3.1.2 MechanismRelatedFindings..........................................................................20
3.1.3 OutcomesandLessonsLearned.....................................................................22
3.2 Project2:“SupporttoSriLankatopromotenationalunityandreconciliation
effortsthroughtargetedtechnicalassistancetotheONURandtheNorthern
ProvincialAdministrationandEasternProvincialAdministration.”......................27
3.2.1 Output1:KeyMechanismsandProcesses(ElementsofaRoadmap)for
NationalUnityandReconciliationCommencedUndertheGuidanceofthe
ONUR………………………………………………………………………………..………………………………….27
3.2.1.1 ContextRelatedFindings........................................................................27
3.2.1.2 MechanismRelatedFindings..................................................................28
3.2.1.3 OutcomeRelatedFindings.....................................................................32
3.2.1.4 LessonsLearned.....................................................................................33
3.2.2Output2:NorthernProvincialadministrationandEasternProvincial
administrationenabledtoproducestrategicplansandstrengthenrevenue
generationtosupportdevelopmentactivitiesthataddresstheprioritiesofconflict
affectedpeople…...........…………………………………………………………………………………..…37
3.2.2.1 ContextRelatedFindings........................................................................37
3.2.2.2 MechanismRelatedFindings..................................................................43
3.2.2.3 OutcomeRelatedFindings.....................................................................44
3.2.2.4 LessonsLearned.....................................................................................45
4. Recommendations.........................................................................................................47
References..............................................................................................................................50
Annexures..............................................................................................................................51
![Page 4: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/4.jpg)
4
ListofAnnexures
Annex01WorkPlan
Annex02 DocumentsRequestedandReceivedforEvaluation
Annex03 ActivityPlan
Annex04ProposedFlowofActivitiesandDataCollectionInstrument
Annex05 ListofInterviewees/ParticipantsattheWorkshop
Annex06 TermsofReference
![Page 5: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/5.jpg)
5
ExecutiveSummary
TheGeneva Resolution 30/1 and the change of government in 2015, provided amore conducive
platformforUN’sbroaderengagementwiththenewlyelectedpoliticalleaderswhilethecountryitself
embarked on a wide democratization process. The Peacebuilding Priority Plan (PPP), that was
formulatedasaresultoftheseconsequentialdevelopmentsconstitutesallprocessesofUN’scurrent
interventions in Sri Lanka. The Immediate Response Fund (IRF) of the UN’s Peacebuilding Fund
(UNPBF), from 2015 to 2016 is an initiative taken in this backdrop. The UN and the Sri Lankan
Governmentpartners,laterworkedonthreeIRFprojects,fundedbythePBF.One,ledbyOfficeofthe
UN High Commissioner for Human Rights (OHCHR) was in support of the accountability and
transitional justice process. The second one led by the UNDP and the United Nations Resident
Coordinator’s Office (UNRCO) is referred to herein as - Project 1: “Support to the Sri Lanka PBF
SecretariatandGovernmentSecretariatforCoordinationofReconciliationMechanisms”(SCRM).The
thirdprojectforthis‘lessons’learned’/evaluationexerciseisreferredtoasProject2:“SupporttoSri
Lankatopromotenationalunityandreconciliationeffortsthroughtargetedtechnicalassistanceto
theONURandtheNorthernProvincialadministrationandEasternProvincialAdministration.”Atthe
endofthesecondyearofitsinterventions,theUNDPcommissionedanevaluationofProjects1and
2asalessonslearnedexerciseconcerningongoingpeacebuildingeffortsundertakeninSriLanka.The
Evaluation Team carried out a ‘lessons learned’ exercise informed primarily by a realist impact
evaluation approach to derive reliable evidence in understanding the context and the underlying
mechanismofactionandoutputsfromtheproject,servicesandinterventions.
Detailedfindingshavebeendescribedinthedocument.Keylessonslearnedandrecommendations
emanatingfromthetwoprojectsareasfollows:
ThePeacebuildingPriorityPlanhasbeensuccessfullypositionedasananchoringframeworkfor
donors,developmentpartnersandtheUNcommunity.However,localpartnersexpressawishfor
amorehome-grown‘non-linear’framework.
TheUNPeaceBuildingFund(PBF)andtheSCRMhaveenjoyedagenerallypositiverelationship.
TechnicalassistanceprovidedtotheSCRMthroughtheUNPBFandthePeacebuildingPriorityPlan
(PPP)weregreatlyappreciated.
NeedtoAddressIncreasedPolarizationinSriLanka.Duringtheevaluationexercisecarriedout,
respondentssharedtheirobservationonhowSriLankaismorepolarizedthanitwasin2015.This
instability affects the positioning of mechanisms such as Secretariat for Coordinating
ReconciliationMechanisms(SCRM)andtheOfficeforNationalUnityandReconciliation(ONUR),
that are embedded within government agencies. It was also observed that much of the
peacebuildingandreconciliationworkfocusedon‘quickwin’initiativesandnotasresilientlong-
term interventions. Predisposition to economic development initiatives resulted in reduced
emphasisonmeetingrights-basedchallenges.Inthislight,itisimperativethattherebeafocused
anddecisive shift fromeconomicdevelopment toaddressing the increasedpolarization in the
country.TheUNPBFandthePPParewellpositionedtoencouragenationalactorstoaddressthese
challenges.
Alongertermstudytoassesstheeffectivenessofthetwomechanisms(SCRMandONUR)atthe
nationalandlocallevelsisalsorequiredrequired,toensurethattheyhaveapositiveimpactupon
onlong-termpeacebuildingeffortsinthecountry.
Relationship Management becomes crucial for projects working within more sensitive and
politically charged environments. Relationshipmanagement and communication between UN
![Page 6: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/6.jpg)
6
staffandstaffattheSCRMandONURrequiresfurtherimprovementinordertoensureeffective
project implementation.Better relationshipmanagementbetweenpartnerswill ensurebetter
deliveryoftheproject.Managingrelationships,buildingrapport,orientatinglocalcounterpartsto
UNwaysofworkingneedstobehandledformallyaswellasinformally.Peopletrustpeople,and
peoplearemorelikelytobesupportiveorcollaboratewithpeopletheycanrelateto.Thishuman
factorneedstobeconsidered inprojects lookingto influencepeopleand institutionalchange.
Therefore,itisrecommendedthatrelationshipbuildingapproachesandtechniquesbeutilisedto
ensureprojectresultsandthattheresponsibilityofprojecteffectivelydeliveredlieswithUNDP.
Local capacity, at the community level, as well as at higher levels of the transitional justice
process,requiresstewardshipandencouragementinordertosetasolidfoundationforthelonger
termgoalofreconciliation.
The UN Volunteers embedded in crucial governmental departments is a successful model
demonstratingpositiveimpact.Thisisrecommendedasausefulstrategytobereplicated.
Genderisacontentiousissue.ItissignificantlydiscussedintheoryintheprodocsandthePPP,
however, inpractice it seems tobedifficult toascertainwhat specificactivitiesaddressed the
genderdimension.Genderprogrammingcanbeenhancedbyensuringthatthegenderdimension
isnotreducedtoequalityofparticipationinworkshopsandprojectactivities.Thereneedstobe
clearerunderstandingaboutgender issuesandhowtheycanbepro-activelybuilt intospecific
programmes.
ProgrammingApproach/depth–WhilekeepinginmindtheboundariesthattheUNorprojects
suchasthesemustoperatewithin,itisrecommendedthatprogrammingtakesresponsibilityto
create lasting change especially where gaps are evident. Also in cases where the context
operationalinasituationposeslimitationstobringingaboutchanges,itisrecommendedthesame
degreeofproblemanalysisbecontinuedintodesigningtheexpectedresultsandhowitwouldbe
measured.Languageusedinthestatementofoutputsandintheresultsframeworkshouldnotbe
elusiveandbemoresubstantive.
LogicalDesignApproach–inretrospectivereflectionthestandardlogicalanalysisisprobablynot
themostappropriateapproachforthetypesofprojectsevaluatedhere,whereresultscannotbe
logicallypredictedowingtothesensitivepoliticalcontextunderwhichtheyoperate.Ifthetheory
ofchangeapproachisbeingused,thenitisrecommendedthatitisusedthroughoutthewhole
projectmanagementcycle,andnotonlyattheconceptual/designstage.PDIAapproachesare
alsorecommendedforstatecraftingworkdealingwithafluidcontextsuchasthisone.
ProactiveMonitoring and RiskManagement – Proactive and continuous project monitoring,
usageofmonitoringfindings,andstrategicadaptivemanagementtoensuretheprojectstayson
trackandiseffectivelydelivered,isfoundtobecriticalinadynamiccontext.
AdaptiveManagement–TheprojectactivitiesasdescribedfortheONURdeviatedsignificantly
fromtheoriginalplanandtheresultsframework.However,giventheinstablepoliticalcontext
withinwhichtheprojectoperated,itisexpectedthatthepredictedactivitypathwaymayneedto
beadjustedandadapteddependingontheavailableentrypointsandopportunities.Therefore,
evaluators feel that the project implementers should focus on the delivery of the originally
plannedresult,morethanafocusontheplannedactivities.Accordingly,insertionofcompletely
different activities, if its strategic enough, should be considered instead of simply redressing
activities.AnexampleofthisistheM&EactivityadjustmentortheWHOpsychosocialadjustment
![Page 7: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/7.jpg)
7
madebytheproject.Thesewereminorlevelsofchangetotheoriginalactivity,butnegatedthe
contributiontotheexpectedoutput.
ImplementationModality–InacontextlikeSriLankawheretheUNandNGO’sareconsidered
suspiciously,adirectlyimplementedprojectworkingonpeacebuildingmayhavehadlesstraction.
Also,giventheUN’sapproachofpeacebuildingfundsbeinga‘hinge’,andtheirworkonlybeing
facilitatory,itthenraisesthequestionaboutitsdirectimplementationmodality.
Documentation and Reporting; Inclusive Consultation/Internal Communication and
InformationSharingneedtobestrengthenedfurther.OntheUN’sside,limitedcommunication
isnotedbetweenthepoliticaldecisionmakinglevelandtheworkinglevel,duringthedesignphase
as well as the implementation phase. Improvement of the commitment to keep all parties
adequatelybriefedwherenecessaryisseenascriticalinreducingavoidablemisunderstandingand
improvingeffectivenessandefficiencyofdelivery.Thereportspellsoutrecommendationsonthe
lacunaeaddressedaboveto improveDocumentationandReporting;ReportingandKnowledge
management; ProactiveMonitoring and RiskManagement, and on Inclusive Consultation and
Communication from the UN RCO to the implementing agency and to the stake-holders.
RecommendationsaremadeonDocumentationandRecordkeepingtoo,especiallyinchallenging
programmaticareasofnon-performanceanddiversionofplans.
Introductionofgoodgovernancepracticesrelatingtocentre-peripheryrelationsmustaddress
existingdisconnectsthatdefeatgenuinepowerdevolutionencouraginglingeringdistrustatthe
periphery and their sense of marginalisation. As these grievances are often with an ethnic
undertoneintheNorthandEast,theycarrytheinherentriskofdeepeningfurther.Hence,the
urgencyand thepivotalneed tohandle these issueswitha carefully framedstrategy, (asalso
prudentlyrecognisedintheprojecttheory).Introducingmeaningfulmechanismstostrengthen
provincial and local authorities vis-a-vis the Central government’s authority remains an
imperative.Effortscouldhavebeenmadetoaddresssuchlacunastrategicallyundertherubricof
the specialisedPBF support, insteadof the general capacity developmentwork thathasbeen
carriedoutintheregionalcouncils.Suchstrategicinterventionswouldallowtheseinstitutionsto
function with a certain amount of autonomy strengthening the reconciliation process. Such
conflictsensitiveworkremainsanimperativeintheUNDP’sworkwiththetwoProvincialCouncils.
Nevertheless,thesuccessfulworkinimprovinginstitutionalfunctionsandstrengtheningcapacity
of local government bodies in the region is highly commended and remains important in the
regions recovering from thewar. The regional governments’ success storiesofownershipand
passionateachievementsoughttobesharedandreplicated.
This‘lessonslearned’documentendeavourstoencapsulatethehopesforthefuture,concernsofthe
presentandtheexperiencesofthepast,withtheviewofexpandingtheworthyreconciliationefforts
ofthePBFinterventionsonalargerscale,thatthecountryneeds.Recommendationsspeltoutindetail
in theendof this reportwouldhopefully serveascontextual informationandbecomepartof the
formalarchitectureofprojectsforsuccessfulfutureinterventions.
![Page 8: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/8.jpg)
8
1. Introduction
Attheendofasavagecivilwarfoughtforthreedecades,thepopulacesettledintoaquietwithdrawal
fromthewarpsychebut,thethengovernment,immediatelypost-war,foundtherulebydiktatmore
enticingthantherulebydemocraticconsent.Theylostanunprecedentedopportunitytoadoptan
inclusivestrategytobringaboutreconciliationamongstallcommunities,strengthenruleoflawand
affectconstitutionalreformstodevolveandsharepowerbetweenthemajorityandethnicminority
communities especially in the regions of the North and East. However, the commitment and the
intensionoftheincumbentgovernment,toachieveanall-embracingtransitionintoafullyfunctional
democratic process is evident, although painstakingly slow. It still remains a challenge for the
government to become a shining example of embedded democratic institutions that can be the
beacontootheradvanceddemocraciesintheregion.
Ontheotherhand,theUNHumanRightsCouncilresolutiononSriLankatabledatits30thsessionon
the24thofSeptember2015,maintainedthatpeace,securityandprosperitywithjustice,equalityand
freedomprevailforallcitizens.Thisresolutionandtheformationofanationalgovernmentcreateda
rare opening to set the course of the country on a transformative trajectory to address the core
grievancesofvictimsfromallcommunitiesandtackletherootcausesofconflict.Thesettingupof
institutionalmechanismsaspledgedbytheGovernmentofSriLanka,isanticipatedtoeventuallypave
thewaytoameaningfulreconciliation,restorativejusticeandreparationsforthevictims.TheUN’s
intervention in this context, with the resources from the Immediate Response Facility (IRF) and
PeacebuildingFund(PBF),forprimarilytransitionaljusticeandreconciliationrelatedworkobjectives
arewhatthetwoprojectsupforreviewsoughttoaccomplish.
This introductory section of the report provides a brief context analysis of the reconciliation and
transitionaljusticesituationinSriLanka,andintroducescertainkeypiecesandinformativesources
fortheUNPBF’sworkinSriLanka,suchasthePeacebuildingPriorityPlan(PPP)andUNResolutionHR
30/1.
1.1ContextAnalysis
Since the end of thewar in 2009, Sri Lanka has been inching forward towards reconciliation and
transformative justice, a process that involves amultiplicity of actors, voices, and a socio-political
historythatincludesnotonlytheethnicconflict,butinsurrectionsandlargescaledisasterslikethe
2004 Boxing Day Tsunami. As the National Policy on Reconciliation notes, it is a process that
necessarilyinvolvesattentiontoadiversehistoryandanongoingrealityofculturalpluralism.The
PeacebuildingPriorityPlanitselfnotesthat“peacebuildinginSriLankarequiresacomplexandmulti-
levelnationalpoliticalconsensusinordertoachievesustainablepeace”(PPP2016:6).In2018,Sri
Lankaisacountrythatisstillseekinganewidentity,lookinginmanydirectionsforthemeaningofits
existencewithoutadecadeslongwar. Ideologicaldebates,thereby,abound,andthecruxofthese
debates circle the tensions between development and reconciliation. The academic and policy
dialoguesurroundingthepost-warclimateinSriLankais,therefore,quitewide-ranging.Inarecent
talkattheInternationalCentreforEthnicStudies(ICES),Uyangoda(2017)notedtheuniquenessofSri
Lanka’sprocess,callingforahome-grownsolutionthatspeakstoapolitythatdoesnotasyethavea
singularideaofwhatreconciliationshouldmean.Thiranagama(2013)arguesthatreconciliationhas
notbeenlinkedtoethnicreconciliation,butis,instead,aresponsetointernationalpressureregarding
thelackofpoliticalreform.Kottegoda(2012),amongstothers,notesthatpervasivegenderinequity
is another aspect that troubles reconciliation. The terms ‘transitional justice’, ‘durable solutions’,
‘sustainablepeacebuilding’and‘reconciliation’havebeengainingtractionincommonpolicyparlance,
producingawealthofprogramming,government led interventions,andacademicandcivil society
discussion.
![Page 9: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/9.jpg)
9
However,asFonseka(2017)notes,theprocessinSriLankahasbeenbesetwithchallengessinceits
inception.Muchofthiscanbeattributedtothefactthattherehasbeen,forsignificantperiodsof
time, a lack of a coherent national strategy for transitional justice and reconciliation. There are a
varietyofdifferenteffortsbeingmade,buthowreconciliationandjusticeinthiscontextisdefined
andarticulatedis,asyet,difficulttoascertain.Indeed,itisthislackofcoherencethatledtheUNPBF
tosupporttheGovernment’seffortstoestablishtheSecretariatfortheCoordinationofReconciliation
Mechanisms,abodythatismeanttoactasacentralisedhubforreconciliationeffortsbetweenvarious
agencies,bothgovernmentalandnon-governmental.
TheoreticalandempiricalengagementonthesubjectofSriLanka’stransitionfromwartopost-war
suggests necessary engagementwith a host of considerations. Amongst them are, understanding
whatreconciliationmeansinagrowingpoliticsofresentment;innon-traditionalpoliticalnarratives;
in unrecognised minority voices; the complexity of identity; and the significant issue of double
alienation,wheretherearemanywho’sparticipationisunrecognisedandmadeinvisible.Colouring
allofthisisthefactthatthereisnoparticularsetofgoalsthatthecountryismovingtowardsinterms
of reconciliation. Several studies (Thaheeretal.2016,Fernando2014)note thatwhilstallparties
agreethatreconciliationisneeded,theydisagreeastoitssubstantivemeaning.Itisalsoimportant
tonoteatthisjuncturethatprogrammaticallyandpolicy-wisethereareaplethoraofformal,informal,
governmental andnon-governmental efforts that are seeking to ‘build’ reconciliation in Sri Lanka.
Therearealsomanyunresolved issueswith regards todiscrimination stemming from thepre-war
years,aswellashighlevelsofmilitarisationthatoccurredduringthewar,andintheimmediatepost-
warperiod.Forexample,anongoingCEPAstudyinJaffnaandTrincomaleeconfirmstheabovetrends
andparticularlyhighlightcastebaseddiscrimination,especiallyinaccesstoeducation,lackofsafety,
lackofemploymentopportunities forwomen-headedhouseholdsaspressing issues.At thepolicy
level,theOfficeofMissingPersons,isonlynowbeginningtooperationalise,andhasfacedaseriesof
politicalchallenges.Manyactivistsandfamiliesofthemissingandthedisappearedarestillengaging
in sit-ins and long-termprotests tonote their dissatisfactionwith the slownessof the transitional
justicemechanism.
Thereareperceptionsofpoliticalandeconomicpowerandpatronisation,assessedthroughinterviews
andnarrativesoflivedexperience,forthisevaluationandotherstudiesatCEPA,thatarealsolimiting
toreconciliation. There isalsothechallengeoftrust in institutions, leadershipandfellowcitizens,
offeringacriticalreflectionofthelevelstowhichindividualsandgroupsfeelexcludedfromorincluded
inthesocial,economicandpoliticalsystem.
Academicsandpolicyanalyststypicallybreakthepost-warperiodintotwophases.
The immediate post-war period: The first time period, 2009-2014, is seen as overwhelmingly
characterisedbyadefensiveapproachtotransitionaljusticeattheinternationallevelandalackof
commitmenttotransformativejusticeatthedomesticlevel(Uyangoda2010,Goodhand2013).Asthe
UNPeacebuildingPriorityPlannotes,althoughthe2009-2014periodcontainedmeasuressuchasthe
Lessons Learned and Reconciliation Commission (LLRC) and the Presidential Commission to
InvestigateMissingPersons,manyoftheseinitiativesfellshortofmeetingtheneedsandexpectations
of the affected. Neither did these efforts adhere to international standards of peacebuilding and
conflicttransformation(PPP2016:5).Theoverwhelmingfocusoneconomicdevelopmentatthistime
didlittletoaddressstructuralgrievances,andtheimmediatepost-warperiodisseenasoneof‘missed
opportunity’ (ibid). This is not only related to the economy, but also to the national policy on
languages,secondaryandtertiaryeducation,newandre-emergentsocialconflicts,andtheeffectof
along-termlackofacohesivetransitionaljusticeprocess,casesofthemissingandthedisappeared,
andthewidespreadmilitarisationthatmanifestedintheimmediateaftermathofthewar.Ideological
debates also abound, and the crux of these debates circle the tensions between economic
developmentandreconciliation(Ranawana2017).
![Page 10: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/10.jpg)
10
Thepost-2015period: Inthepost-2015oryahapalanayaperiod,thegovernmentisseenasbeing
comparativelyprogressivewithregardtoitscommitmenttotransitionaljusticeandhumanrightsat
the international level (Samaratne2017). The adventof the Sirisena-Wickremasinghe government
suggested a ‘window of opportunity’ for peacebuilding, and since, many different efforts and
initiativeshavetakenonnewlifeinthepost-2015period.
ItiswithintheimmediateadventoftheSirisena-WickremasinghegovernmentthatthePeacebuilding
SupportOffice(PBSO)committedtoprovideflexibleandstrategicPeacebuildingFunding(PBF)that
wouldsupportthegovernment’speacebuildingpriorityplan(PPP).ThePPPismeanttoserveasthe
framework for a “coordinated Government, UN and development partners’ response to secure
durablepeaceinSriLanka”(PPP2016:10).Anothersignificantinfluenceforthedevelopmentofthe
nationalandgovernment ledmechanismshasalsobeentheresultsoftheConsultativeTaskForce
(CTF)process.AlthoughtheCTF is separate to thePPPandthePeacebuildingContextAssessment
(PCA)process,ithasalsofedinsignificantlytothe‘on-the-ground’workdonebytheSecretariatfor
CoordinationofReconciliationMechanism(SCRM)andtheOfficeofNationalUnityandReconciliation
(ONUR). TheCTFwas awide ranging consultationwith victims/civil societyon Transitional Justice
processes and mechanisms. It recommended the following four bodies be set up: The Office of
Reparations, The Office of Missing Persons, Accountability Mechanisms, and a Truth and
ReconciliationCommission.
1.2UNResolutionHR30/1
UNResolutionHR30/1wasadoptedby thehumanrightscouncil inOctober2015withaviewto
promotereconciliation,humanrightsandaccountabilityinSriLanka.Itrecognisesandpromotesthe
Sri Lankan government’s September 2015 pledge to work toward a “meaningful reconciliation,
strengthening democratic institutions, good governance, the rule of law, and confidence building
amongcommunitiesaffectedbyconflictformanyyears”(PPP2016:12).Theprocessacknowledged
thefactthatdealingwiththepastandestablishinganewhumanrightscultureisanenormoustask
and that the GoSL, together with the guidance and support of the UN would work together to
strategicallymove forwardwithanationallyownedandvictim-centricprocess that addressed the
grievances of victims, allegations of systematic violations of international human rights and
internationalhumanitarianlawallthewhileadvancingaccountabilityandreconciliation.(PPP2016:
15). Theresolutionemphasisesthe importanceofacomprehensiveapproachtodealingwiththe
past,incorporatingthefullrangeofjudicialandnon-judicialmeasures,including,interalia,individualprosecutions,reparations,truth-seekingandinstitutionalreform.Theresolutionalsonotedtheneed
forconsultativeandparticipatorymethodsthatincludetheviewsofallrelevantstakeholdersinthe
transitionaljusticeprocess.
1.3ThePeacebuildingPriorityPlan
ThePeacebuildingPriorityPlanwasdesignedinordertoguidethewiderandlonger-termsupportfor
peacebuilding, and is a framework that was developed by United Nations Sri Lanka and the
GovernmentofSriLanka.Thisplanreflectsalsothecloseconsultationthatwasconductedwithcivil
societyandlocalandinternationaldevelopmentpartners.ThePPPisinformedbythePeacebuilding
ContextAssessment(PCA)of2016andisintendedtobeacommonframework,throughwhichtheUN
andotherdevelopmentpartnerscanaligntheirsupporttowardsnationallyidentifiedpriorities,and
insodoingensureacoordinatedapproachtopeacebuildingandreconciliationinthecountry.Keyto
the larger frameworkofthePPP is thePCA’sunderstandingthatSriLankarequiresacomplexand
multi-levelnationalpoliticalconsensusinorderforpeacebuildingandreconciliationtomanifestand
besustainable.Thereisthen,anecessityforconsensusbuildingacrosstheethnicdivideaswellasat
‘elite’intra-ethnicorcross-partylevel(betweenSinhalesepoliticalparties,andbetweenTamilpolitical
![Page 11: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/11.jpg)
11
leadership).Such‘horizontalconsensus’willneedtobebuttressedby‘verticalconsensus’,orsupport
for peacebuilding at the grassroots level, particularly the Sinhalese, without which it will ‘lack
legitimacyandriskbeingfragile’(ibid).ThePPPtherebyidentifiedaneedfortransformativereform
ofpoliticalculture.
Assuch,thePCAandthePPParecloselyattunedtogovernancereformasameansthroughwhichto
effect reconciliation. Such reform is seen to bedone throughbuilding the capacity of the various
mechanismsandorganisationsatlocalandnationallevelsofgovernment.Indeed,capacitybuilding
appears as a key element for UN assistance to the Government of Sri Lanka in affecting its
reconciliation plan. There are three strategic priorities articulated here. These are seen as vital
confidencebuildinginterventionsandalsocriticalenablersfordurablesolutions.
A) ThefirstistechnicalsupporttotheGovernmenttooperationalisethenewNationalPolicyon
DurableSolutionsforConflictAffectedDisplacement.ThepolicyarticulatestheGovernment’s
commitmenttore-buildthelivesofconflict-affectedfamiliesusingarights-basedapproach,
and provides direction for all relevant stakeholders towork collectively and coherently in
supportofresettlementprocesses.
B) Thesecondpriorityisinsupportofaccesstoland,andincludeshighlyfocusedandtargeted
supportforsurveyingthathasthepotentialtocatalysetheresolutionofuptoapproximately
40,000casesoverathree-yearperiod.Italsoincludesprovisionoflegalaidtoassistthemost
vulnerablefamilies,especiallythoseheadedbywomen,toresolveoftencomplexlegaland
documentationissues.
C) Thethirdfocusforislivelihoods.Withoutlivelihoodoptionsmanyfamiliesfindthemselvesin
a highly precarious situation in the newly released areas, or are forced to postpone their
return,andthusfurtherdelaygettingtheirlivesbackontrackandrealisingthedividendsof
peace.The focuson livelihoods linksdirectly to theproblemof indebtedness that isbeing
understoodbythePPP,aswellasactorsinthegovernmentandattheSCRMandONURasa
‘hotspot’foremergentconflict.“Nexttosecurity,socialandeconomicissuesareparamount,
inparticularaccesstolandandhousing,alackofsustainablelivelihoods,andindebtedness.”
(PPP2016:6).
Thereby, economic development, governance reform and trust restoration are understood as key
components of peacebuilding. The ‘restorative framework’ described by the PCA and the PPP
identifiesfourtargetgroupsinparticularforeconomicupliftment.Theyare:
• peopleofallcommunitieswhohavesufferedinthemaintheatreofwar;
• soldiersandfamiliesofsoldiers;
• victimsofLTTEatrocitiesoutsidethetheatreofwar;
• andthosedisplacedfromtheirhomesandforcedoutsidethetheatreofwar.
ThePPPalsonotestheneedforincludingmorewomenatdecisionmakinglevelsingovernanceand
policymaking processes. It highlights the need to, “include leveraging women’s capacities and
contributions, and developing strategies for inclusion which recognise their roles, and diverse
experiencesofconflict”as“withoutwomen’sengagementatthestagesofpeaceconsolidation,the
dangersofrelapsearegreatlyheightened”(PPP2016:16).
![Page 12: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/12.jpg)
12
Assuch,thePPPhasfouroverarchingoutcomes:
1.TransitionalJusticeimplementedtohelpreconcileandhealSriLankansociety;
2.SriLankansocietywithpeacefulco-existenceandasenseofbelonging;
3.AllSriLankanpeoplefeelsafe,andtrusttheGovernmenttoeffectively,efficiently,equitablyand
transparentlyrespondtotheirneeds;
4.Peopledisplacedbytheconflict(IDPs,IDPreturneesandrefugeereturnees)haveacoregrievance
addressedthroughaccesstolandandrebuildingoftheirlives.
Theprimaryfocusforconflicttransformation,drawingfromthePeacebuildingPriorityPlan(PPP),is
on Four Pillars: Transitional Justice, Reconciliation, Good Governance and Resettlement Durable
Solutions. Guiding this process then, are the following principles, as articulated in the
Peacebuilding Priority Plan. These principles are drawn up to be consistent and
supplementarytotheaccountability/transitionaljusticeagenda:
§ Victimcentric:reconciliationandtransitional justiceapproacheswillallaimatdealingwith
the consequences of the inter-ethnic conflict and legacies of systematic human rights
violationsandabusessoastoprovidehealingandredressforallvictims;
§ Nationalownership:thedesignandimplementationofboththereconciliationandtransitional
justice agenda is first and foremost an exercise for Sri Lankans, and has to be led by Sri
Lankans;
§ Holistic, comprehensive approach: the multidimensional nature of the transitional justice
agenda requires careful identification of linkages between interdependent and mutually
reinforcingprocesses,suchasjusticeandsecuritysectorreformsanddemocraticgovernance;
§ Coordinated: a strategic, coordinated and sequenced approach ensures that the limited
resourcesandcapacitiesareutilisedmosteffectivelyandhelpsustainlong-termmultilateral
and bilateral support to Sri Lanka’s transitional justice agenda, with the United Nations
CountryTeamplayingacentralrole;
§ CivilSociety:engagementwithcivilsocietywillbemainstreamedacrossthefourpillarsofthe
PPP, with civil society taking on an important role during the project development,
implementation and monitoring stages. The PPP will also include dedicated support for
strengtheningtheroleofcivilsocietyandvolunteerisminpeacebuilding;
§ Nationalfocus:ThePPPwilladoptanevidencebasedapproachtocoveringdifferentpartsof
thecountry,dependingontheissue;
§ Gendersensitive:throughoutallstages,itisimportanttorecognisethecriticalroleofwomen,
especiallythosefrommarginalisedcommunities,aswellasthespecificviolationstheyhave
sufferedandtheirspecificneedsofredress;
§ Periodicallyreviewed:it isessentialtoregularlyreflecttheevolvingSriLankancontextand
adoptmechanismsthatarecapableofrespondingtochangeandofproposingappropriate
adjustmentstoprioritiesandactivities;
§ ContributetoSustainableDevelopmentGoal(SDG)16onjustice,peaceandstronginstitutions
andSDG5ongenderequality:TheinitiativessupportedunderthePPPwillbeincludedina
widerframeworkofsupporttotheSDGs,andwillseektocoordinatewithother initiatives
contributingtothesamegoals.(PPP2016:15-16).
ThesupportthattheUNprovidestotheGovernmentofSriLankaisinfluencedbytheprioritiesand
overarching outcomes of the PPP and is, therefore intended to provide technical assistance and
capacitydevelopmentsupport,throughtheUNsystem,toidentifiedinstitutionsandprocessesand,
assuch,toreinforcepressurepointsthataddressobstaclestolong-termpeaceandreconciliationas
wellassustainingthecountryonthepathtosocialtransformation.
Asapartofthisoverallpeacebuildingplan,theUNPBFintervenedtooffersupporttotwoparticular
conflicttransformationandtransitionaljusticemechanisms.Theyare:
![Page 13: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/13.jpg)
13
a. TheOfficeforNationalUnityandReconciliation(ONUR),comesundertheagendafor‘non-
recurrence’, functions as a catalyst and aims towards long–term systematic change and
buildingprogrammaticagendasforpeace.TheprogrammaticaimsoftheONURincludeart
and culture, conflict transformation, interfaith dialogue, university engagement, livelihood
support, community development, public outreach, women for reconciliation and
psychosocialsupport.TheONUR’sprogrammesaremeanttobedesignedandimplemented
inacollaborativeprocessbetweenthegovernmentandaffectedcommunities.
b. The Secretariat for Coordinating Reconciliation Mechanisms (SCRM) is tasked with the
design,creationandcoordinationofmechanismstoachievetruth, justice,reparationsand
non-recurrence.TheSecretariatcomesunderthePrimeMinister'sOffice,andwasformedon
18December2015.TheSCRMisalsomeanttoliaiseandworkwithdevelopmentpartners,
UNagencies,relevantministriesandreconciliationarmssuchastheONURtoensurethatthe
fabricforTransitionalJusticemechanismspercolatethroughoutdifferenteffortsforeconomic
development and reconciliation in Sri Lanka. The Offices for the Missing Persons, the
Accountability Mechanisms and the Truth and Reconciliation Commissions fall under the
purviewofthisunit.
In2018, theUNdecided tocommissionan independent third-party lesson learnedexerciseof the
Projects’ performance, that would provide evidence of the project’s relevance, efficiency,
effectiveness,impactandsustainabilityinachievingitsobjectives.ThisalsofulfilsthePBF’smandate
of conducting periodic review of the outcomes and outputs of the UNPBF. Following a proposal
process,theCentreforPovertyAnalysis(CEPA)wonabidtoperformthisevaluationprocess. The
nextsectionsdetailthemethodology,analytical frameworkandotherparticularsoftheevaluation
thatCEPAdeployedincollatingthislessonslearneddocument.
1.4 ScopeoftheStudy
In July2018, theUNcommissionedan independent third-party lesson learnedexerciseof the two
peacebuilding projectsmentioned above that would provide evidence of the project’s relevance,
efficiency,effectiveness,impactandsustainabilityinachievingitsobjectives.ThisalsofulfilsthePBF’s
mandateofconductingperiodicreviewoftheoutcomesandoutputsoftheUNPBF.Theseprojects
wereimplementedbytheUNDPandincludedtheinstitutionalestablishmentoftheSecretariatfor
CoordinationofReconciliationMechanisms(SCRM),specialisedtechnicalassistancetotheOfficeof
National Unity and Reconciliation (ONUR), and each of the Northern and Eastern provincial
administrations. These projects were set up to support the State to ensure progress of its
peacebuildingandreformsagendainthecountry.
![Page 14: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/14.jpg)
14
2. MethodologicalApproach
Peacebuildingisacomplexandmultifacetedprocessofchange,andunderstandingtheeffectiveness
andsustainabilityofsuchworkinvolvesavarietyoftoolsofinquiry,aswellasabuilt-inframework
thatallowsforreflectivepractice.Reflectingonpeacebuildingandreconciliationactivitiesrequiresan
understandingofthecontextwithinwhichtheactivitieswereundertaken.Inspacesinwhichthere
aredeep-rootedandlong-standingconflictssuchasinSriLanka,violencecanunexpectedlyspiralout,
andtherefore,trustandpartnershipbuildingcantakesignificantamountsoftime.Whatthisrequires
oftheevaluativeprocessisthebuildingofknowledge,andalsotheunderstandingandimprovement
of practice through structured reflection and feedback. Therefore, embedded into the proposed
methodologyisathemeofongoingandcontinuedreflection,wheretheresearchtoolwillguidethe
evaluatorstoaskquestionssuchas‘howarefactorsconnectedandinterrelated?Whatarethevisible
and invisible factors, in this context?’ Such a reflective process also brings with it the additional
advantageofamethodthatisimplicitlyattunedtothevarietyofsocialfactors(ethnicity,class,caste,
religionandgender)affectingtheprocessofpeacebuilding.
To be able to evaluate the programmatic outcomes and the outputs referred to in Project 1 and
Project 2, the exercisedeployed a combinationof approaches specific for evaluating them. These
evaluationswereinformedbytheDevelopmentandCooperationDirectorateoftheOrganisationfor
EconomicCooperationandDevelopment(OECDDACapproach)toevaluate“relevance,”“efficiency”
“effectiveness”oftheprojectsmentionedintheTOR.However,themainapproachbeingadopted
fortheevaluationoftheproject’soutputswas,theRealistImpactEvaluationmethodfromacritical
realiststandpoint,(abranchofthe‘TheoryofChange’approach).Thishelpedcarryoutameaningful
evaluationofthe“impact”and“sustainability”aspectsoftheidentifiedprojects,wheredeployingthe
OECDDACapproachalonewasnothelpfultoappraisetheassumptionsandtheoriesbehindthese
aspects.Thetheoryunderlyingtheinterventionswaslocatedatthecentreoftheevaluationexercise
here.However,asWesthrop(2014)elucidates,theRealistImpactEvaluation“focusesoninterventionswhicharehardertoevaluatebecauseoftheirdiversityandcomplexityorwheretraditional impactevaluationapproachesmaynotbe feasible,with thebroaderaimof identifying lessonswithwiderapplicationpotential”.Thisapproachwasalso importanttoexplainwhyprojects failorsucceed in
differentsettingsbycomparingthe‘beforeandafter’effectsofinterventionsthroughthisapproach.
Eg:Ithelpedunderstand‘whatwerethecircumstancesinwhichtheprojectinterventionsworked?
Whatwere theunderlyingmechanisms thatbuilt trust,orestablishedaccess to servicesafter the
projectintervention?’
2.1 RealistImpactEvaluation
TheRealist ImpactEvaluationstrategy, isaspecificbranchofthe ‘theoryofchange’approachand
increasesthespecificityofourunderstandingofhowaprojectaccomplisheschange.Itintensifiesthe
understanding of a project’s ‘context’ that influences programme ‘mechanism’; and expands the
precisenessofforecastingproject‘outcomes’.This‘realisticexplanatorytriad’willhelpopenthe‘black
box’(the‘space’betweentheactualprojectinputsandtheeventualresult)ofprojectmechanism.
InaRealistEvaluationwhat isrevealedareelementsofacontextthatare,exceedingly important.
Suchknowledgeneedstobeimpartedandthoseelementsoughttobeincorporatedaspartofthe
formalarchitectureorbemadetheblueprintoftheprogrammeforfutureinterventions.Thiscould
especially include those elements thatwere under-theorized andwere not realised as imperative
partsofthecontextthathelpmakeadifference.
This method is based on the assumption that regularities in social actions are brought about by
underlying mechanisms that spring from people’s reasoning, and the resources they are able to
summoninaparticularcontextforthoseactions(ortheirprojectinterventions).Hence,anevaluation
![Page 15: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/15.jpg)
15
ofsuchprogrammesandprojectsneedstoinvolvethetaskoftestingtheunderpinnedtheoriesand
especiallythosetheorieswhichweremanifestlyappliedaswellastheoveralllessonslearned.
I. Context
First,theteamtriedtounderstandtheimpactoftheprojectsbyestablishingtheprogrammecontext.
Contextualconditionsunderwhichprojectsareimplementedarecritical,criticalsuchasthechange
of Government, the Human Rights Resolution (30/1) that was brought against Sri Lanka, etc.
Sometimes,there isnoawarenessoftheusageofpre-existingresourcesforthefunctioningaswe
onlyseethetipoftheiceberg.Hence,onehastotheorisethoseresourcesinapropermannerfrom
thecontext.Itwouldthenalsobehelpfultoscaleuptheprojectinacontextwherethoseresources
exist compared to another contextwhere the project failed. Implementers and evaluatorswould
prefertoknowwhyitfailedasonedoesnothaveanyreasontoexplainwhysomethingfailed.Thisis
why,itbecomesimperativetotheorisetheimpactofcontextandunderstandwhatisunder-theorised
withregardstoresources,inthecontextthatwouldhelpexplaintheoutcomebetter.
This is a lessons learnt exercise to understand that there are explicit/implicit conditions that
contribute towards either making or breaking “context-mechanism” association. Hence, the
evaluators, armed with appropriate tools attempted to elicit knowledge of such explicit/implicit
contextsthathelpedthemechanismtoproducepositive,negativeorneutraloutcomes.Theplanning
oftheevaluationofsuchprojectsisanattempttoelicitknowledgetoidentify‘whatworks’for‘whom’
in ‘what context’ and in ‘what respects?’ Contexts also influence the ways in which intended
beneficiaries respond to government or non-government projects. Variations within target
populationscaninfluencewhichmechanismsoperate(gender,class,caster,ethno-religiousculture
etc).“Arealistevaluationtherefore,hypothesiswhichfeaturesofcontextarelikelytoaffect‘how’,
and for ‘whom’, a project is expected towork and collects data about those features of context”
(Westhorp2014:7).Asthenextstep,itsetsofftoseekfordataandanalyticstrategiestoexamine
theinteractionbetweencontextandmechanism.
II. Mechanism
Understanding projectmechanisms is critical in understanding how projectswork. Understanding
how subjects interpret and act upon the intervention stratagem is known as the programme
‘mechanism’ and it is the pivot around which realist research revolves (Pawson et al., 2004).
Mechanisms can be intended or unintended (and ought not to be confused with project
strategies/resources/activities). Amidst other levels of concepts, the realist evaluation helps
understandandinterpretthe‘main’mechanismsgeneratingthemainpatternsofoutcomes.
Forthispurpose,theOECD-DACmethodwasusedasatooltostrengthentheprocessofknowledge
collection by probing deeper to elicit project-related information with regards to: relevance,
effectiveness and efficiency where this approach has proven to be successful in many other
evaluationsinthepast.Theevaluationincludedquestionssuchasi.e.whatmechanismsareneeded
fortheprogrammetowork?Didtheprogrammeincorporateknowledgeofsuchmechanismsinits
design?
III. Outcome(CMO-Configuration)
TheCMO-Configurationimpartsacertainaspectofknowledgethatwouldhelp1buildarepositoryof
success and failures, providing policymakers with theories and typologies of successful ‘context-
mechanism-outcome’configurationsorpatternsknownasCMO,bywayofaLessonsLearntExercise
forthispurpose.Thisapproacharticulatesassumptionsthatunderpinthework;uncoversdiffering
1Thiswouldalsohelpanalyse‘ImpactandSustainability’inthelexiconoftheOCED-DACapproach.
![Page 16: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/16.jpg)
16
viewsontheoriesofchange;theprinciplefactorsinfluencingtheachievementornon-achievements
of the project outputs, and most importantly helps find answers to the question “why”? The
applicationof thisevaluationmethodwouldhelpdistinguish the flawsand strengthof the theory
(open the black box) behind the implementation. It also helps identify, articulate and explain the
transformationprocess.
Theexerciselookedintopositiveandnegative,primaryandsecondary,directlyorindirectly,intended
orunintendedlong-termeffectsproducedbytheinterventions.Thus,thetheoriesofchangeapproach
withthecriticalrealistevaluationmethodinparticularwasappliedforgainingdeeperinsightsintoits
positiveornegativeimpactandtheirintendedoutcomes,impactandsustainability.
TheFlowofActivitiesandDataCollectionInstrument(Annex04),providesthedetailsofthequestions
askedundereachoftheabovecategoryfromrelevantstakeholdersoftheproject.
2.2 OECD-DACAssessment(Relevance,EffectivenessEfficiency,GenderEquality)
TheevaluationtookintoconsiderationanappraisaloftheResultsFrameworkoftheProjectdeveloped
for this exercise. The logical linkwith the activities and resultswere also assessed keeping to the
requirementsofthebeneficiariesandthelocaldevelopmentneeds.TheOECDDACevaluationcriteria
wasmostlyhelpfultoevaluaterelevanceandeffectiveness,efficiency.
• Relevance:Theevaluationattemptedtounderstandtheextenttowhichtheobjectivesofthe
interventionareconsistentwithbeneficiaries’requirements,countryneeds,globalpriorities
andpartners’anddonors’policies.Whathasbeendone?Weretherightthingsdone?What
istherelevanceorsignificanceoftheinterventionregardinglocalandnationalrequirements
andpriorities?
• Effectiveness: The extent to which the intervention’s objectives were achieved, or are
expected to be achieved, taking into account their relative importance will be analysed
throughthiscomponent.Theendeavoredtounderstandtheextenttowhichanintervention
hasattained,orisexpectedtoattain,itsmajorrelevantobjectivesefficientlyinasustainable
manner andwith a positive institutional developmental impact.Howproportional are the
resultsoftheprojectcomparedtotheobjectivesplanned?
• Efficiency:Theexercisehelpedestablishameasureofhoweconomicallyresources/ inputs
(funds, expertise, time, etc.) converted to results. Are the objectives achieved in a cost-
efficientmannerbythedevelopmentintervention?Wasitvalueformoney?Howbigisthe
efficiencyorutilisationratiooftheutilisedresources?
• GenderEquality:Theexercisealsotriedtounderstandwhethergenderequalitywasexplicitly
promoted through specific measures such as whether it a) reduced social, economic or
political power inequalities betweenwomen andmen; or ensured thatwomen benefited
equally with men from the activity, or were compensated for past discrimination; or b)
developed or strengthened gender equality or anti-discrimination policies or institution
systems. The exercise approached this aspect by analysing gender inequalities through
interventionsundertakenandasanintegralpartofagencies’standardprocedures.
2.3 LessonsLearned:UnderstandingImpactandSustainability
Theoverarchingaimofthisexerciseistosharelessonslearnedintheevaluationprocessofthegiven
projects,withtheUNPBF.The‘lessonslearned’exerciseinvolvedthepresentationofthesystematic
discoveryofhowcircumstantial influencesstimulatetheconnectionbetweenthe interventionand
the finaloutcome.Theteamendeavouredto learn ‘how’ theproject implementationscenariohas
actually taken place with a combination of approaches: i.e. Realist Impact Evaluation and some
aspectsoftheOCED-DACapproachtosupplementknowledgerelatedtomechanismsatwork.Italso
![Page 17: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/17.jpg)
17
endeavoredtounearththecausalpathleadingtooutcomes;unearthingthecontextualdeterminants;
comparecontexts;theorisemechanism;scopeouttheoutcomesandpresentthemaslessonslearnt.
The Realist Impact Evaluation findings are also helpful to informpolicy, practice and assist in the
effectivetailoringoffutureprogrammes/projectsofcertainrealistcontexts.Theknowledgetheyhelp
elicitonwhichprogrammesworkedunderwhatcontextand‘how’,willhelpmakerecommendations
onhowtorefinepoliciesandprojectsto improvetheireffectiveness,their impacts,andalsomore
importantlyinforminterventionsonhowtoadaptprojectstonewcontextsinfutureinterventions.
(PleaseseeAnnex4forProposedFlowofActivitiesandDataCollectionInstrument)
2.4 DataCollectionandSampling
Inordertofindresponsestothecomplexsetofquestionsundereachoftheaforementionedaspects
to be evaluated (i.e. relevance, effectiveness, efficiency etc.), qualitative and limited secondary
quantitativeworkwerecarriedout.Twostrategieswereusedfordatacollectiontosolicitknowledge
about mechanisms. Firstly, data from existing project documents at the organisational level was
utilisedtounderstandwhytheprojectwasexpectedtoworkdifferentlyforthestakeholdersidentified
intheprojecttheory.Forexample,asegregatedunderstandingofwhythisprojectwasexpectedto
workfortheNorthernandEasternProvincesdifferentlyfromtherestofthecountryasitwasoriginally
designedfortheregionsunderthePBF.
Secondly,throughkeystakeholderinterviewsinColomboandtheNorthernProvinceandthrougha
workshop with stakeholders in the Eastern Province, the team was able to reason if values and
prioritieschangedasaresultoftheprojectandtheresourcesprovidedthroughthe interventions.
Thiswasanintraprogrammaticexercisewithcomparisonsonprogramme-theoryconstructs.
Thequalitativemethodformedtheheartoftheexercisegiventheteamofresearcherswithrelevant
experienceinvolvedinthisprocess,toconductkeystakeholderinterviewsinColomboandtheregions
includingaworkshopwithstakeholdersintheEasternProvince.However,asforthequantitativedata-
collection,giventhetimeconstraints,thedatawassolicitedfromsecondarysourcesforanalysisof
opinionpollsandpilotstudies,basedonpreviousnationalpeaceandreconciliationworkcarriedout
intherelevantareas.
2.5 Limitations
Somelimitationsthattheprojectexperiencedwererelatedtomeetingtherelevantindividualswho
wereinvolvedintheprojectduringitsdesignandthereafterintheimplementationphase.Fromthe
initial review of documents, the team understood that there were changes in staff both at UN
RCO/UNDP as well as with Government partners i.e. the ONUR. However, the teamwas able to
interviewmostoftherelevantindividualstounderstandthecontext,aswellasthereasoningbehind
certain keydecisions and certainmechanisms thatwere adoptedormodified. The teammadeall
efforts to interviewthesekeyofficials togainanunderstandingof thebiggerpictureaswellas to
ascertain the C-M-O aspects of lessons that could be learnt and applied in future interventions.
Relevanttothisistheveryshorttimeframeforthisassignment,whichneedstoinactualfactevaluate
thelessonsofthreeseparateminiprojects.Therefore,thetimeframeinwhichtoidentify,contact
and obtain appointments for four separate sets of interviewswas also limited, especiallywhen it
comestomeetingsintheEastaswellastheNorth.Theabsenceofdocumentstoprovidecomplete
informationonsomeofthekeyaspects/turnofeventsintheprojectswasanotherchallengethatthe
teamfaced.Theyhowever,intensifiedtheneedtoholdmorestakeholderinterviewsthananticipated.
Hence, the teamcarriedoutasmanystakeholder interviewsaspossible toobtain information to
bridge the gap. As a result, the team required additional work days for the completion of data
collectionandanalyses.Oneoftheotherlimitationsisrelatedtohowknowledgeanddecisionmaking
![Page 18: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/18.jpg)
18
hasbeeninstitutionalizedaswellashowitcanbedocumented.Commentsthatwerereceivedonthe
report,post-validationmeetinghavebeenincorporatedinthisversiontothebestoftheteam’sability.
![Page 19: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/19.jpg)
19
3. KeyFindingsandLessonsLearned
3.1 Project1:SupporttotheSriLankaPBFSecretariatandGovernmentSecretariatfor
CoordinationofReconciliationMechanisms
AlthoughtheProject1comprises2Outcomes,thescopeoftheassignmentistoconductthelessons
learntexerciseofOutcome1ofthisproject,whichis:
Outcome1–UnitedNationsPeacebuildingSupportinSriLankaisstrategicallypositionedtosupport
nationalpriorities,arrivedatthroughafullyconsultativeandinclusiveprocess,andiseffectively
deliveredinacoordinatedandharmonisedmanner
• Output 1 – Peacebuilding Priority Plan developed andmechanism established to support
coordinatedprojectdevelopmentandimplementation.
• Output2–EffectiveimplementationoftheUN’sPeacebuildinginitiatives,withattentiontocoordination,evidencebasedinterventionsandhigh-impactresults.
• Output3–SecretariatforCoordinatingtheReconciliationMechanismsestablishedwithinthe
PrimeMinister’sOfficetoensurecoordinatedandcoherentGovernmentstrategytoprogress
reconciliationanddevelopandimplementtransitionaljusticemechanisms.
3.1.1 ContextRelatedFindings
a. WideconsultationinthearchitectureofthePPP:AtthedesignstageofthePeacebuilding
PriorityPlan,therewaswideconsultation,especiallythroughengagementwithgovernment
andcivilsocietyactorsatboththenationalandprovinciallevel.
b. DynamicnatureofthePPP:Thedynamismofrefocussingandopeningupthedocumentto
newcontextualrealitiesisappreciatedbythisevaluativereport.WhenthePPPwasinitially
designedandpulledtogether,itwasorientedtowardssecuringtheIRFfundingforSriLanka,
andsuggestedabroadbasedandambitiousdesignforSriLanka’sreconciliationprocess.In
2018,thedocumentasitnowsitsshowsamaturityofprocessandconsultation,notingthe
slowness of the Transitional Justice process overall, and the challenges brought about by
political instability in thecountry. Ithasalso takenonnewdimensions.Thisdidnotentail
changingthedynamicsofthePPP itself,butrefocusingonrapid impact initiatives(suchas
implementationoftri-lingual initiatives),moreeffectiveentrypoints (suchasmappingand
archiving efforts towards transitional justice), as well as non-recurrence initiatives. These
changes were made using results from Peacebuilding Surveys and ongoing stakeholder
consultations.However,itdoesraiseaquerywithregardstowhythefocusismoreattuned
to‘quick,highimpact’ratherthanlong-termhighimpactresults.
c. Polarised 2018 context: In terms of the 2018 context,many respondents highlighted the
problemofincreasingpolarisationandpolitical instability.Respondentsnotedthatpolitical
momentumsince2015hasdecelerated,thatthereisnowa‘paralysis’astoaccountabilityand
doubtsastowhethertherewillbeanytransformativeconstitutionalchangesatall.
d. SCRMprojectdesignandimplementation:SCRMwasestablishedinordertoensurethatthe
reconciliationagendachampionedbythenewgovernmentandtheUNwouldbecoordinated
andtakenforward.AccordingtointerviewswithSCRMstaff,SCRMdrawsguidancefromthe
fourpillarsofthePPPdocument,butreliesalsoonotherongoingconsultationsanditsliaising
withotherreconciliationrelatedgovernmentactorssuchastheMinistryforResettlement,
theONUR,MinistryforNationalIntegrationandReconciliationandsoon.
e. Generally positive relationship betweenUN and the SCRM: The SCRM officials and staff
provide a generally positive review of the UNPBF and the relationship between various
entities.ThePPPandthePBFwerenotedasprovidingsignificantassistancethroughforeign
![Page 20: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/20.jpg)
20
experts.RespondentsnotedthatthePBFandrelatedUNstaffareveryhelpfulandarealways
in constant dialoguewith them.Respondents noted their appreciation for assistancewith
conducting situational risk assessments that identify ‘hot spots’ for emergent conflict,
policymakingandgeneralperceptionsurveys.Thisgoodrelationshipisalsocorroboratedby
interviews with UN officials who note that when a request is made by the SCRM, it is
consideredbykeypersonsonthePBFandactionedifandwhenpossible.UNPeacebuilding
officialsalsonotedthatthesuccessoftheSCRMwasalso inthewaysthatUnitedNations
Volunteers(UNVs)hadbeenintroducedtoandabletoascendwithinthesecretariat,staffing
theSCRMinitiativessuchastheMediaUnit.
f. Relationshipmanagement and communication:When asked about the everydayworking
relationshipbetweentheSCRMandtheUN,respondentsfromwithintheSCRMnotedthat
someUNagenciesarechallengingtoworkwith.Assuch,theSCRMhasoftenreliedonthe
officeoftheRCOtolobbyontheSCRM’sbehalfatthePBFlevel.Itwasnotedthatassistance
andwillingness towork fluctuateddependingonwhichUNagencyonewasattempting to
workwith.
g. AcknowledgedlimitationsofSCRM:UNofficialsalsonotethatanacknowledgedlimitation
oftheSCRMisthatitoperateswithinasmallwindowofpoliticalopportunity.TheSCRM’s
mandateisonlyrenewedonayearlybasisduetothefluidnatureofthepoliticalscenarioin
SriLanka.ThiscertainlyraisesconcernswithregardstotheSCRM’slong-termeffectiveness.
h. Initialteethingissues:TheSCRMofficialsalsonotedthatwhiletheUNPBFandSCRMnow
enjoyapositiverelationship,therewereafewteethingissuesintheinitialsetupuntilsuch
timeasallpartieswereclearastowhatcameundertheUN’spurview,andwhatcameunder
theGovernment’spurview.TheSCRMofficialsalsonotedthedifficultiesassociatedwiththeir
ownlimitations.Asanexample,whenthereisaconflationsuchastheeventsinDiganain
March 2018, the SCRM felt constrained as theirmandate did not allow them to create a
preventiverole.TheSCRMwasnotenvisionedtoworkonthesematters,butthereiscapacity
tointerveneandworkwithministriesifthatissodesired.
i. Technicalassistancemorehelpfulthanfinancialassistance,‘gapsofuncertainty’:TheSCRM
and UN officials also noted that it is more difficult to ascertain the SCRM’s actual role,
especiallyincomparisontothemorespecificrolethattheONURoccupies.Assuch,theSCRM
officialsnotedthatthemostusefulassistancethattheyreceivedwastechnicalassistance,as
opposedtofinancialassistance.AstheSCRM’sroleisverydiverse,financialassistanceismore
difficult for the UN to operationalise. UN officials also noted ‘gaps of uncertainty’ and a
certainamountofflexibilitythatisrequiredinthisongoingrelationship.Flexiblefundsfrom
the IRFweredeployed for theSCRMdue to thisambiguity. It shouldbenoted thatSCRM
officialsnotedthattheydidnotreceivesignificantfinancialassistancefromtheUN.
3.1.2 MechanismRelatedFindingsa. Effectiveness of thePPP at national level: Itwas noted that the PPPwas very helpful in
initiatingdialoguewiththemilitaryandbuildingapartnershipwiththem,especiallyinterms
ofworktoanimatemilitaryofficerstowardspeacebuildingwork.Thereissustaineddialogue
betweenthePPPandSCRM,throughtheUNPBF.ThePPPisarticulatedandclearlyexistsasa
spacewherethingsgetanchored.Asanexample, the ideaof ‘victimcentredness’,directly
derivedfromthePPPisseenreflectedinpolicydocumentationattheSCRMlevel,aswellas
ininterviewswithcertainSCRMofficials.Itwasdifficulttoascertainifthiswasthesamefor
theONUR.Thisevaluationwasmethodologically limited inbeingunable tospeaktoother
reconciliationrelatedministries inordertogaugetheeverydayandrollingeffectsthatthe
PPPhaswithinthegovernmentmachinery.
![Page 21: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/21.jpg)
21
b. Catalyticfunding:CatalyticfundingfromthePBFhasbeenverygoodattriggeringquick‘high
impact’projectswiththeSriLankangovernment.
c. Effectiveness of the PPP at the donor and UN community level: The PPP is also a key
documentforexternal(foreign)donorsseekingtoprovidedevelopmentaidtoSriLanka.It
hasbeenleveragedbytheRCOasaconduitthroughwhichsuchdonorscanidentifyongoing
needs, as well as formulate criteria for deploying aid. As an example, the marrying of
economicdevelopmentneedstoreconciliationgoalsisacentralthematicinfluencingcurrent
donorpractice,and isat theheartof thePPP.Mappingdoneat the levelofdevelopment
actorsevidencesthatthefourpillarsofthePPPhaveaffectedthelanguageofmanydonors
nowprovidinglivelihoodandeconomicdevelopmentsupporttoSriLanka,ascanbeseenin
ILO,UNagencyandADBprojectsthatareinvestinginthecountry.Incomparisontothepre
2015politicalscenario,itcanbesaidthatthisisakeymilestoneoftheproject.
d. TheSCRMdesignandimplementationutilisesmanysources:SCRMofficialsnotedthatthey
drawfromthefourpillarsofthePPPintheirongoingwork,specificallyinguidingthe‘style
and contours’ of the work that the SCRM engages in. However, other documentation,
consultationandknowledgeproductsarealsonamedasplayingakeypartinmobilisingthe
work that the SCRMdoes. Named specifically in our key interviewswere the transitional
justice documents drawn up by Professor Savitri Goonesekere and Dr Manori
Mutthuwetugama, as well as the results of the consultative task force and the ongoing
dialoguewithcivil society leaders.SCRMofficialsnoted thata fulldayworkshopwithcivil
society leaders, as well as on-going and ad-hoc consultations as being key to planning
initiativesattheSCRM.Asmanyrespondentsnoted,itisdifficulttoidentifywhichdocument
isthe‘keyanchor’fortheSCRM.Someofthis,however,hastodowiththefactthattheactual
role of the SCRM itself took awhile to be defined. It is a strength of the design that the
peacebuildinginitiativesallowfortheSCRMtotakeonsuchautonomy.
e. CriticismofPPPassumptions:Thereiscriticismfromlocaldevelopmentactorsofoneofthe
assumptionswithinthePPP.Thisisinrelationtotheideathatwhenlivelihoodsareattended
to, reconciliation can be achieved. This is seen as ignoring the rights based and access
challengesthatarefacedonaquotidianlevel.Therewascriticismwithregardstotheamount
of money being poured into such livelihood development projects without enough
assessment of whether CSOs and cooperatives who eventually receive such funds from
externalagentshavethecapacitytoabsorbandmanagesuchmoney.Thislevelofcritique
alsochallengedwhatwas termedas the ‘project-based’natureofpeacebuilding initiatives
thatarelinkedtoasingularframework.
f. Aneedtoattendtotransformativechange:Itwasalsonotedthatabetterleveragingofthe
fundsfromthePBFcouldhavebeentowardsmore‘transformative’attitudinalchangerather
thaneconomicdevelopmentactivities.Toclarify,thisisbecausetherearemanydevelopment
actorsandfinancial investmentsthatarebeingmadetowardseconomicdevelopment,and
that the PBF’s connection and alliance with the state machinery could have been more
effectiveiffocussedtowardsaddressingrightsbasedandhorizontalinequalitiesexperienced
on theground. This isespeciallyurgentasmany respondents raised the fact that theSri
Lankanpolityisnowmorepolarisedthaneverbefore.
g. Short–termprojectsdonotcreatethespacefortrust–building:Therewerealsoconcerns
raised as to the need for more ‘trust building’. It was noted that building trust between
governmentactors(nationalandlocal),aswellasthedifferentcommunitiesinthecountryis
essentialforpeacebuilding.However,asfundsforpeacebuildingactivitiesareoftentiedto
thedurationofaproject,ortheprioritiesofinternationalgovernance,thereisnotenough
timegivenforsuchtrustbuildingtotakeplace.Trustbuildingcannotbeputintoatimeframe
orachievedwithinthelimitedframeworkofaprojectbasedactivity.Respondentsnotedthat
thelinearassumptionsofprojectbasedworkdonotmeetthecomplexrealitiesandcircularity
oftimeofthequotidianlevel.Therewascriticismofthefactthat‘complexrealities’donot
![Page 22: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/22.jpg)
22
fitinwiththeUNsystemicapproachtopeacebuildingsuchthatthereisa‘mismatchbetween
thetaskaheadandtheinstitutionsthataretaskedtodoit’.Toclarify,whatthisiscritiquing
is the imposition of a peacebuilding framework ‘from above’, and one which is allied to
universalisedstandards.
h. ‘Quick’decisionmaking:WhiletheSCRMandcertainkeydecisionmakersontheUNPBFenjoy
agoodrelationship,somedecisionsarenotmadebythefullboard.Muchofthisisbecause
theboardonlymeetseverythreemonthsandthereisaneedtotake‘quick’actiononcertain
items.Assuch,whenrequestsaremadeoftheUNPBF,therearethreekeypersonnelwhoare
consulted toprovideapprovalor refusal.However,boardmembers felt thatmakingquick
decisionshampersprojectchoicesthattrulyaddresstheneedswithintargetedcommunities.
i. Genderprogramming:Genderischallengingpointinthisevaluation.Accordingtointerviews
withUNofficials,theUNdidnothavemuchsaywhenitcametohowgenderprioritieswere
actionedthroughtheSCRM,buttheRCOofficeprovidedsupportforworkshopsandtrainings
toensurethattheyweregendersensitive.AccordingtoSCRMofficials,therewasnopushby
theUNto look into thegenderaspect.However,SCRMofficialsnote that, there isaclose
focusonreferring to thegenderdimension fromwithin thesecretariat,whenprojectsare
enacted. However, they say they were not provided with any specific examples. This
ambiguity also extends to project documents and log frames. According to a PBF board
member,gender issuesarenotsignificantlyhighlightedthrough theONURorSCRMinthe
overallprojectdesign,butthemembernotedthattheILOEMPOWERproject,fundedbythe
UNPBF, seems to be having strong positive results with regards to women’s economic
development.
j. Local capacity building:Therewasmuch discussion also,with boardmembers and SCRM
officials,abouttheneedtobuildlocalcapacity.Assuch,intheseconversations,therewasa
flagraisedabouttheleveloftechnicalassistancethatkeepscominginthroughtheUNPBF.
While it is appreciated and there are many lessons to be learned, ongoing reliance on
international experts was found to not build internal and local capacity for juridical and
monitoringprocesses.
3.1.3 OutcomesandLessonsLearneda. Methodological limitations: While PPP language can be seen in project and policy
documentationguides,thisevaluationwasnotabletomapactualeffectivenessofthePPP,
throughimplementationactors,tothe‘groundlevel’.Itisrecommendedthatasecondand
longerevaluationbedonetoascertainactual‘groundlevel’effectivenessofthepercolation
ofthePPPprinciplesandofthemobilisationcapacityofthePPPfromdesigntograssroots.
Understanding ‘effective implementation’ necessitates a more in-depth study of the key
ministries,developmentactorsanddonorsworkingalongsidetheUNPBFandtheSCRM.This
evaluationwasunabletodotriangulationwiththeministriesthattheSCRMworksalongside
tostudytherolloutoftheSCRMprogrammingandmobilisation.
b. Gender:Gender isakeyguidingprincipleofthePPP,andGenderscoring isprofessedasa
mainactivitywhendevelopingPPPasamainelementwasconsultationacrossfourpillarsso
there is sufficient female andmale participation. It has been difficult, however, for this
evaluationtoascertainwhatspecificprogrammesweredonefromagenderlensoutsideof
equal inclusion inworkshopsandotherevents.However, in the2018 iterationof thePPP
there seems to bemore attention paid to the specific challenges being faced by women
headedhouseholds.Genderprogramming,ifplacedasahighermarker,mustbehighlighted
notonlyassimply‘equalityofparticipation’,thereneedstobeactivemobilisationongender
![Page 23: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/23.jpg)
23
dimensions. It is concerning that replies from both UN officials and SCRM officials were
ambiguousatbestintermsofgenderprogramming.
c. DynamismofthePPP:ThisreportappreciatesthedynamicnatureofthePPP,inthatits’2018
iterationhaspickedupontheneedtoaddressindebtedness,workingwithvulnerablewomen
headed households, and also fast-tracking durable resettlement plans. The significant
effectivenessofthePPPasastandingframeworkhasbeenthatitallowsabasefromwhich
theUNcanmobiliseandrallygovernmentpartnersandotherdevelopmentpartnersaround
theidentifiedstrategicinterventions.
d. Quickwinapproaches:There isgeneralcriticismfromallpartieswithregards toadefault
approachtotakingon‘quick-win’‘highimpact’initiatives,ratherthaninvestinginlong-term
goals.Peacebuildingwasidentifiedoverandoveragainasacomplexprocess,andnotone
thatcanbeachievedthroughaplanthatisfocusedonforoneortwoyears.Assuch,thebest
thatcanbeenvisionedthroughtheentireprocessisoneof‘sowing’initialseeds.
e. Independence of the SCRM: This evaluation highlights the fact that making the SCRM a
national,butmoreindependentmechanismmayallowformorelong-termimplementation.
SCRMofficialsnotedthatanecessarynextstep for theSecretariatwouldbetobuild local
capacityforlongtermpeacebuildingandtransitionaljusticemechanisms.
f. Theprudenceof relyingon foreignexpertise: Respondentsacross theboardqueried the
usefulness and practicality of an international strategic expertwhen there aremany local
expertswhohavebeenimmersedintheSriLankansituationandwhohaveamoregrounded
intuition for localneeds.Nooneparticulargroupofexpertsorworkshopswereespecially
highlighted.Indeed,thisqueryisverymuchattunedtoongoingreflexivityonwhatismost
usefulandpertinenttodevelopingandutilisinglocalcapacityfortransitionaljustice,aswell
asasking,broadly,C is thisprocess too reliantonexternal assistance?’. Toquote froman
interviewwithamemberoftheUNPBFboard,“Peaceworkrequiresanintensivepresenceon
thegroundwithpeacestrategies,iftheUNDPisseriousaboutsomethingtheyneedtohave
strongpeoplewhounderstandtheculture,analyse,andunderstandthedifferentthingsthat
arehappeningthereandtogivesupportforsomethingtoevolve”.Respondentsfoundthat
reliance on foreign expertise detracted significantly from a ‘home-grown’ and community
groundedpeacebuildingprocess.Asanexample,SCRMofficialsnotedtheneedtotrainlocal
prosecutors on how to handle reparations and transitional justice cases, a need that will
manifestoncetruthcommissionsandotheraccountabilitymechanismsareoperationalised.
There was also concern with regards to the financial expenditure incurred in bringing in
expertsfromotherconflictrelatedcountriesas,inmanywaysthesearemoneysthatcould
beexpendedelsewhere,perhapsatthenecessarycommunitylevel.Therewasalsosustained
criticismofthe‘workshopculture’associatedwithbringinginforeignexpertise.
![Page 24: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/24.jpg)
24
EvaluationMatrix:
ProjectOne:“SupporttotheSriLankaPBFSecretariatandtheGovernmentSecretariatfor
CoordinationofReconciliationMechanisms”.
Output 1: Peacebuilding Priority Plan developed and mechanism established to support
coordinatedprojectdevelopmentandimplementation
Context-Mechanism-OutputConfiguration Category Remarks
Context Thetheoryatwork Relevantin2015basedonthecontextassessment.In2018therehasbeenarefocussingtowardsmoreresettlementandeconomicdevelopmentinitiatives.However,between2015and2018,thecountryhasbecomemorepolarisedandthereisaneedtorefocusonrightsbasedchallengesversusrapiddevelopmentinitiatives.
Mechanism Relevance
Theprojecthasmaintaineditsrelevanceasaprojectdocumentthroughincorporatinginformationfromsurveysandongoingcontextassessment.However,therearequeriesastowhethertheserefocusesadequatelyaddresstheeverydayneedsandwantsofcommunities.
Effectiveness
ThePPPisananchoringframeworkfortheUNcommunity,theSCRM,andthedonor/diplomaticcommunity.Itisdifficulttoaccessitseffectivenessoutsideofthesegroups.
Efficiency
ThePPPisananchoringframeworkfortheUNcommunity,theSCRM,andthedonor/diplomaticcommunity.Itisdifficulttoaccessitsefficiencyoutsideofthesegroups.
GenderDimension Genderisaguidingprincipleofthedocumentandthereisplentyoftheoreticalevidencefor
![Page 25: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/25.jpg)
25
‘gender’relatedmarkers.However,inpractice,theseeffectsarenotveryvisible.Gendermustbeunderstood,programmatically,asmorethanratesofparticipationandattendingtoWHHs.
Outcome(ImpactandSustainability)
Positive?Negative?Neutral?
ImpactscoresapositiveasthedocumenthaspositioneditselfasakeyframeworkfortheUN,SCRMandthedonor/diplomaticcommunity.Sustainabilityscoresaneutral.ThePPPhasincorporatednewchallengessuchasindebtednessandrapidresettlementneeds,butremainwithinaparticularlinearandsystematicframeworkthatcanbequeriedintermsofitsabilitytospeaktothecomplexitiesoftheSriLankansituation.
Output2–EffectiveimplementationoftheUN’sPeacebuildinginitiatives,withattentionto
coordination,evidencedbasedinterventionsandhigh-impactresults.
Output3–SecretariatforCoordinatingtheReconciliationMechanismsestablishedwithinthe
PrimeMinister’sOfficetoensurecoordinatedandcoherentGovernmentstrategytoprogress
reconciliationanddevelopandimplementtransitionaljusticemechanisms.
Context-Mechanism-OutputConfiguration Category RemarksContext Thetheoryatwork TheSCRMcurrentlyhasa
relevantroleincoordinatingstatelevelreconciliationmechanisms.However,it’sroleistiedtothisparticularpost-2015situation.Itisdifficulttoassesswhetheritwillhavearolepost-2019.
![Page 26: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/26.jpg)
26
Mechanism Relevance
TheSCRMoperatesandisrelevantatthelevelofthestateandtheUNcommunity.Italsodoesworkatthelocalgovernmentlevel.Wewereabletoassessrelevanceattheformerbutnotatthelatter.
Effectiveness
EffectivenessoutsidetheUNandwithlimitedstakeholderswasnotassessedin-depth.Communitylevelimpactisnotimmediatelyvisible.
Efficiency FlexiblefundingassistedtheSCRMtobuildstaffcapacities.Receivedwiderangingtechnicalassistance.TheSCRMalsohasthecapacityandautonomytoaccessspecialistassistancefromoutsidetheUNcommunity.TheSCRMhassetupdifferentunitssuchasResearchandMediathatareefficientonamediumscale.
GenderDimension Theoreticallyapparent.Practicallyambiguous.PleaseseecommentrelatedtothePPPintableabove.Equalparticipationatworkshopsisnotgenderfocussedprogramming.
Outcome Positive?Negative?Neutral?
Theresulthereisneutral.TheSCRMhasbeensuccessfulinpushingforwardcertainstatelevelactivitiesbuttherearequeriesastoitslongevitypolitically,andit’srelevanceoutsideofthestate,UNanddiplomatic/donorcommunity.
![Page 27: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/27.jpg)
27
3.2 Project2:“SupporttoSriLankatopromotenationalunityandreconciliation
effortsthroughtargetedtechnicalassistancetotheONURandtheNorthern
ProvincialAdministrationandEasternProvincialAdministration.”
Project2istobeconsideredfortheexercisecompletely.
Outcome1-“SriLankasocietywithawell-coordinatedandcoherentsystemtoadvancenational
unityandreconciliationamongitspeople.”
• Output 1:Keymechanisms andprocesses (elements of a roadmap) for national unity and
reconciliationcommencedundertheguidanceoftheONUR• Output2:NorthernProvincialadministrationandEasternProvincialadministrationenabled
to produce strategic plans and strengthen revenue generation to support development
activitiesthataddresstheprioritiesofconflictaffectedpeople.
3.2.1 Output1:KeyMechanismsandProcesses(ElementsofaRoadmap)forNationalUnityandReconciliationCommencedUndertheGuidanceoftheONUR
3.2.1.1ContextRelatedFindingsa. ProjectDesignandStrategy -TheOfficeofNationalUnityandReconciliation (ONUR)was
establishedundertheformerPresidentKumaratunga,anditsmainroleistocoordinateand
catalyseactiontoadvancenationalunityandreconciliation.Ithasprioritisedsocialcohesion,
peaceeducation,psychosocialsupport,livelihoodsandtrilinguallanguagepolicyasareasto
take forward. During the design stage of the project, officials at the ONUR were widely
consultedandtheprojectdocumentwasdevelopedbasedontheiridentifiedneeds.Efforts
to interview former President and Head of the ONUR, Chandrika Kumaratunga for the
evaluationwere unsuccessful. However, ONUR officials spoke positively about initial level
collaborationwiththeUNRCOandabouthowtheywereprovidedwithpeacebuildingrelated
knowledgeandskillsduringthatphase.
i. However, it seems that this initial levelof collaborationdidn’t continue frommid-
2016onwards.ONURofficialsalsofeltthattheirinputsandneedswhichweretaken
onboardin2015,beforetheprojectstarted,werenotwellreflectedinthefinaldesign
thatwassubmittedforPBFfunding.UNDPofficialsreportthatoncetheprojectdesign
wasformalisedtheywerebrought intothepictureandtheprojecthandedoverto
them. The UNDP reported, in terms of effectiveness, that they believed that the
project design phase didn’t adequately brief theONUR that the projectwould be
manageddirectlybyUNDP.Thereafteroncetheprojectwasinitiated,theUNDPand
ONUR were locked in detailed negotiations about working modalities for a long
duration,especiallybecausetheONURfeltthatthefundmanagementshouldhave
cometothem.TherewasalsoalackofawarenessofUNDPworkingmodalities,rules
andregulations,aswellaswhatadirectlymanagedprojectentailedwithintheONUR.
ii. UNDPofficialsreportthatcommunicationandcollaborationbetweentheUNRCOand
UNDP during the design phase was limited, limiting effectiveness of the project.
Misunderstandingand lackofclaritybecausethe implementingagencyUNDP,was
notas involvedasmuchas it thoughtnecessaryduringthedesignstage,seemsto
![Page 28: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/28.jpg)
28
havecritically influencedrelationsnegativelybetweenthetwoparties–UNDPand
ONUR.2
iii. TheUNDP reflects that theprojectdesign couldhave incorporatedmore strategic
supporttotheONURandbeenmorerelevant.TheyfeltthatsincetheONURwasa
newly set up body, support should have been laidmore squarely on institutional
building.This,theyfeltwouldhavehelpedsetuptheONURtoundertakeitsfunctions
moreeffectively.Thistheybelievewouldhavesupportedastrongerpartnershipwith
theUNDPandstrongabsorptionoftheprojectactivities.
b. ProjectDocument–Theprojectdocument iswellthoughtout,highlyrelevant,andclearly
describesthecontextandthewindowofopportunitythattheUNhopedtofurthercatalyse
withtimelysupportthroughtheIFRandPBFfunds.Thedesignutilisesthetheoryofchange
conceptandaresultsframeworkanalysistomeasureprojectsuccess.
i. Evaluatorsfindthatthehighlevelofexpectationsthataredescribedinthenarrative
of the project document and in the outcome and outputs, does not adequately
translate,with the same sort of intensity, into the design of the activities. For an
ambitious18monthproject,theactivitiesdescribedarenotsufficienttodeliverthe
expected result, limiting its effectiveness.While its understood that the activities
themselvesarereasonablegiventheUNDP’spositionandaccess,theoutputpromises
commencementofmechanismsandprocesses,whichismorethantheactivitiescan
deliver.
3.2.1.2MechanismRelatedFindingsa. Project Implementation -When the project came into being inmid 2016, theUNDPwas
chargedwithdirectlyimplementingit,whiletheONURbelievedtheprojectwasgoingtobe
implementedbythemselves.Thereafter,ONURofficialsfeltthattheywerenotwellinformed
abouttheproject,notclearlytoldwhattheirrolewas,whatfundsandsupportwasavailable
tothem,etc.Basedonthismisunderstanding,workingrelationsbetweenthetwopartners
werestrained,andtheeffectivenessoftheprojectreduced.
i. The UNDP project documentation shows the Letter of Agreement (LOA) signed
betweenUNDPandONUR,roughlyaccountingforabout200,000USD(dependenton
theexchangerateatthetimeoftransfer).ThesefundswereusedbytheONURfora
partofthequick-winactivitiessuchastheDialogueInitiative,thetrilinguallanguage
translationservice,andfortheinter-schoolpilotwork,withcredibleefficiency.The
incumbentofficialsattheONURclaimnottobeawareofthefullproject,butonly
aware ofwhatwas agreed and signedwith them – as per the LOA. This is not in
keepingwith the fulloutputof thisproject related todevelopingmechanismsand
processesfornationalunityandreconciliationundertheguidanceoftheONUR.
ii. Duringthisphase,evaluatorsfindthatthereweretwomainlevelsofcommunication
and working between the UNDP and ONUR. One between senior politicians and
decision makers and another between working level officials.While they worked
effectivelyateachlevel,withineachorganisationtherewasverylimitedcollaboration
2UN/UNDPOfficialsreviewingthisreport,post-validationmeeting,commentedonthisissueasfollows.(Itis
incorporated for the sake of providing more clarity on this issue): “UNDP were there at many of the
planning/designdiscussions.TherewereseveralworkshopsforexampleintheUNtodeveloptheRRFetcand
finalizethestrategy.UNDPwereverypresent…[The]issuewasmorethanUNDPandRCOwerenotmeetingthe
leadershipofONURtogether,andthisledtodifferentunderstandingsatthehigherlevel”
![Page 29: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/29.jpg)
29
and engagement vertically, between senior decision makers and working level
officers.Thisledtoalackofcoherencebetweendecisionsthatwerebeingmadeand
whatwasbeing implemented, aswell as tomisunderstandings. TheUNDP reports
thatsomeof itsworkingleveldecisionsweresometimescountermandedbasedon
politicalrequests,andonthewhole,theeffectivenessoftheprojectwasaffected.
b. ActivityonProvisionofTechnicalAssistance-Thefirstactivityrelatedtoprovidingtechnical
assistanceistosupporttheONURonpeacebuildingissues,andcommunicationandisofhigh
relevance. There are three key actions identified within: 1) on a communication strategy
whichisalsopartoftheriskmitigationwork;2)onimprovingthemonitoringcapacitytotrack
reconciliation work; 3) provision of conflict transformation and peacebuilding technical
expertise.
i. According to UNDP officers “ONUR failed to access UN technical and financial
support”;whiletheONURinturnclaimstonothavebeenawareoftheavailabilityof
such support. The UNDP in several meetings with the ONUR brought up the
availability of funds for securing technical assistance on peacebuilding,
communicationandMonitoringandEvaluation(MandE).Whiletheactivityisjudged
toberelevantbyallparties, itraisesthequestionastowhytheONURthendidn’t
makeuseoftheopportunityandresources.
ii. OntheM&Esupport,atrainingonmonitoringwasconductedforONURofficerswhich
they found very useful for their work. The UNDP however identifies that their
attempts to help reinforce the monitoring capacity within the ONUR was not
enthusiastically received. Thereafter the UNDP had made attempts to work with
anotherpartnertoundertakethemonitoringworkonreconciliation.However,due
tochangesingovernmentthistoohasnotbeensuccessfullycompleted.Whileagain
thereasoningbehindtheactionisrelevant,itisnotclearifitwastheeffectivenessof
deliverythatcausedittobeirrelevant.
iii. Onthecommunicationaspect,theprojectdocumentclearlydescribestheneedfora
communication strategy tomanage expectations about the reconciliation process.
However,duetonon-tractionontheONURside,thiswasnotcompleted,raisingthe
earlierquestiononeffectivenessandrelevance.
iv. Peacebuildingandconflicttransformationrelatedtechnicalassistancewasnotsought
bytheONURaccordingtotheUNDP.TheONURmaintains itwasnotawareofthe
availabilityofsupport;raisingearlierquestionsoneffectivenessofdelivery limiting
relevanceoftheactivity.
c. Activity on Quick-Win Confidence Building Initiatives – The logic and relevance for
confidence building activities is clearly justified. On the whole this activity was well
implementedbytheONUR.TheUNDPreportsthattheONURhadthebasicdesignsofthe
dialogueinitiative,developedwhentheprojectwasstarted.TheONURalsoworkedoninter-
school work and inter-cultural activities and a trilingual translation service called
Bashawa.com. These activitieswere assessed separately by theUNDP, and found tohave
beensatisfactorily completed.TheONUR isnowcontinuing thedialogue initiativeand the
inter-school/inter-culturalactivities.ThelanguageworkwastakenoverbythenewMinistry
of National Languages, however its reported to have not been utilised by the Ministry
thereafter. TheWHO ledpsychosocialworkwasalsodevelopedwhen theproject started.
Accordingly,theseactivitieswereimplementedsmoothlyonceUNDPworkingmodalitieswas
understood.Somedelayswereexperiencedthoughonthepsychosocialwork,contributingto
theneedforaNoCostExtensionoftheproject.Thisisexplainedbelow:
![Page 30: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/30.jpg)
30
Theprojectdocumentrecognisestheneedforpsycho-socialsupporttocommunitiesinthe
NorthernandEasternProvinces,AnuradhapuraandGalledistricts,andaimstotargeta100
peoplepertargetdistrict.TheoriginaldesignenvisagesthatWHOwillassisttheONURTask
Force on Psychosocial Well-being. In addition, a strategic plan to build the capacity of
Provincial authorities, government agencies and civil society to establish the long term
coordinatedpsychosocial supportmechanismwasalsopartof thedesign.Thisdesign is in
keepingwiththeoriginallyenvisagedgoalofsupportingthedevelopmentofmechanismsand
processesundertheguidanceoftheONUR,andfoundtobehighlyrelevant.
i. Evaluatorsfoundthatthepsychosocialworkconductedbytheprojectwasnotknown
totheONURorusedtobuildtheONURTaskForceonPsychosocialWellbeing.From
interviewswithmultiplepartiesandinternalreports3,itbecomesclearthattherewas
adisagreementbetweentheONURandWHO.Thereportreferstothedisagreement
beingaboutWHOworkingmodalitiesthroughtheMinistryofHealth(MoH).Dueto
thelackofclarityonthis,furtherinterviewswithpreviousONURstaffrevealedthat
the WHO had already identified subcontracted parties and were insistent upon
managing the psychosocial work as per their normal Ministry of Health working
modalities.Thereafter,theUNDPandWHOhadsignedanagreementandaproject
documentwhichby-passedtheONURanditsTaskForceonPsychosocialWellbeing.
ItisnotclearastowhytheUNDPwouldchoosetocontinuewiththeWHO,without
lookingforanotherpartnertosupportthestrengtheningoftheONUR’sTaskForce.
Thischangeofhowtheactivitywasdoneisfoundtoreducetherelevanceandthe
effectivenessoftheaction,aswellascontributetothestrainedrelationshipbetween
theONURandUNDP.
ii. Project document related deliverables were modified based on WHO working
modalitiesandamended inaLOAandattachedprojectdocument.Amendedtasks
were found to have been well conducted as per an assessment of the activity.
Activitieswerelimitedtotwodistricts,KillinochchiandMullaithivu,andthestrategic
planthatwastobeputinplacewasnotfulfilled.Theprocessesandmechanismswere
notput inplace,andthetargetofaminimum100peopleperdistrictwasalsonot
met.ThealternateactivitiesconductedbytheWHOneverthelessareofvalueinitself
andseemtoadequatelysupportMoHwithitswork.
iii. While the work is considered effective against the amended expectations; when
considered against the original expected output of strengthening processes and
mechanismsundertheguidanceoftheONUR,especiallyinasituationwhereithada
body to take forward thework - the results are considered to be less relevant or
effective.Theactionisnotinkeepingwiththisgoalandunderminestheusefulnessof
theirTaskForce.
d. ActivityonNationalReconciliationPolicy –TheUNDPhad informed theONURabout the
availabilityoffundstosecuretechnicalassistancetosupportthedevelopmentofthepolicy.
However,theONURdidnotaccessthesefunds,asisreportedbytheUNDP.ONURofficials
stated that funds were available from the national budget for the activity and they also
wanted it to be a nationally driven and developed policy. The ONUR official in charge of
developingthispolicycouldnotbecontactedforthisevaluationpurpose.
i. ItisnotclearastowhytheONURdidnotseektheavailabletechnicalandfinancial
supportfortheactivity.It’sprobabletheybelievedthatusageofnationalresources
wouldmakethepolicymorelegitimate,butthenthatraisesthequestionastowhy
3AnnualReport2016
![Page 31: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/31.jpg)
31
thisdecisionwasnotdirectlyconveyedtotheUNDP.TheUNDPwasunawarethatthe
ONURwasproceedingwith theactivityuntil thepolicywasalmost complete.This
raisesaquestionofbuy-infromtheONURtotheoverallproject,thetrustbetween
partnersandtheseeminglackofrequirement.
ii. TheUNDPreportsthattheyfindthePolicydevelopedbytheONURwasofadequate
standard. However, they judged that the policy does not seem to havemobilised
muchsupportor tractionbehind it. Therefore, theynoted that it isnoteffectively
steering the reconciliation work in the country. Different actors, civil society and
developmentpartnersinthesectorareworkingonreconciliationinapiece-meal/add
hocmannerandthereisnobroadlevelcoherencetothework.
e. ProjectMonitoring–Nodedicatedprojectmonitoringrecordsweremadeavailableforthe
evaluationbytheUNDP.Theprojectdocumentdesignclearlydescribestheplantosetuptwo
technicalcommittees,onefortheUNDP-ONURandtheotherfortheUNDP-MinistryofLocal
GovernmentandProvincialCouncils.WhiletheonewiththeProvincialAuthoritieswereset
up,theevaluatorsfindthattheUNDPdidnotsetupthistechnicalcommitteewiththeONUR
formally. The UNDP however did hold meetings with the ONUR to discuss project
implementation, as recorded in meeting minutes. However, the UNDP reported that
attendanceformeetingsaftertheinitialfew,werelimitedandonlyresponsibleofficialsfora
particular activitywould attend, basedon the agenda.Overall buy-inof thewiderproject
deliverableswaslow,withONURfocusbeingmainlyontheactionstheytookresponsibility
forintheLOA.
i. Thelackofadedicatedprojectofficertomanagethisdirectlyimplementedproject
may have affected the effectiveness and efficiency of implementation. From the
meetingminutes, it appears that the UNDP expected theONUR to lead and plan
activities for Activity 1 & 3 of the project and request support where needed.
However,theONURsawitsresponsibilityaslimitedtothequick-winsdelineatedin
theLOA.
ii. It is noted that the ONUR took responsibility for the quick-win activities. These
activitieswere thereafterdelivered, and its individual assessments show that they
wereimplementedwithsatisfactorylevelsofefficiency.
iii. ThoughtheUNDPwasdirectly implementingtheproject,theactivitiestheyhadto
implementweredependentonONUR.Thisappearstonotbeaneffectivemeansof
implementation.
iv. GiventhattheUNDPwasawareofthestrainedrelationshipwiththeONUR,itisnot
clear what proactive instruments the UNDP used to ensure that project delivery
stayedontrack,apartfromthemeetingsthatweresetupwiththeONUR.Thelackof
aformalprojectmanagementcommittee,wasalsooneofthekeymechanismsthat
contributedtothelowdeliveryandeffectivenessofexpectedprojectresults.Thus,
evaluators determine therewas limited effectiveness and efficiency in delivery of
projectresults.
f. Project Reporting – The UNDP reports that its’ ability to reportwas limited by the PBSO
template.Inaprojectwherealotofadaptivemanagement,riskmitigation,andothercontext
relatedissuesareprevalent,thereportingtemplatewasnotabletocapturethenuancesof
why certain actions were undertaken or not. This was found to be a limitation in
understandinghowtheprojectwasmanagedbetter.
i. Recordscapturingchangesincontext,issuesfaced,decisionsmade,activitychanges
andadaptivemanagementmeasurestaken,werenotavailable.TheUNDPdoesnot
seemtohavemaintainedanyinternalreportsapartfromthedonortemplates.
![Page 32: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/32.jpg)
32
ii. Onbothsides,theUNDPaswellastheONUR,therehasbeensomestaffturnover.
OntheUNDPside,thoughofficersreportedthattherewasasmoothhandoverof
functions from one to another, they were not aware of the reasoning behind
decisions,pastactionorpreviousgovernmentofficialsincharge.TheUNDPofficers
also identified that they considered this project “inherited from theUNRCO”and
thereforewerenotawareofthereasoningbehindsomeofthedesignaspects.The
approach fromUNDPofficerswas that theywerenotwilling to takeownershipor
responsibilityforthedesign,decisions,changes,adaptationsmadeduringthecourse
oftheproject.
iii. Senior staff changes in the case of the Government of Sri Lanka occur regularly.
Therefore,knowledgemanagement,maintainingprojectdocumentation,monitoring
andreportingfunctionstoensurethatnewstaffareadequatelybriefedisacritical
functionoftheresponsibleparty,theUNDP,inthiscase.
ThemaindocumentationrelatedtomonitoringseemedtobethroughtheuseofAnnualwork
plans and biannual donor reports. Limited monitoring, especially nuanced monitoring to
ensurethattheprojectwasontracktodelivertheexpectedoutput,furtherlimitingactivity
effectiveness,wasnoted.
3.2.1.3OutcomeRelatedFindingsa. OutcomeandOutputAchievement – The overall outcome ismeasured by two indicators
capturingperceptionsoflocalcommunitiesinprojectreports.Bothindicatorbaselinesquote
2014perceptions as thebaseline,whichwouldbeduring theprevious administrationand
before the project context materialised. The indicator progress is quoted from the 2016
(September)perceptionsurvey,whichisameasurementduringthebeginningphaseofthe
project.Thesefiguresarenotameasurementofthisproject’sprogress,andshouldnotbe
used.Inaddition,evaluatorsfeelthatgiventhereachofactivitiesconductedbythisproject,
it’sunlikelythat2017perceptionsurveyresultscouldhavebeeninfluencedbytheproject.
Under the output, the original results framework has five indicators clearlymeasuring all
aspect of the project design. However, in subsequent project biannual reports, only two
indicatorsarereported,relatedtotwoquickwinactivities,asubsetofActivity2oftheproject.
It’snotclearwhytheotherindicatorshavenotbeenreportedagainstinanyreports.
b. RiskMitigation - A riskmitigation strategy in a project like this is critical. The context is
dynamicandthereareinherentrisksintheproblemtheprojectistryingtoaddress.Thusthe
risks identified are not comprehensive, nor fully developed, nor themitigation strategies
adequatelyaddressedinthedesign.Risksrelatedtochangesinkeypeople,settingupofnew
institutions, political and contextual instability are not adequately thought through.
Thereafter, in thebiannual reporting, themitigation strategiesdonot seem tohavebeen
implementedthoughsomeoftherisksmaterialised.
UNDPofficersreportthatfundswerereprogrammeddependingonavailableopportunities,
andadmitthatinsomecasesitwasnotstrategic.GivenUNDPperceptionabouttheneedfor
better institutionalbuildingwork,or thecommunicationaroundtheusageof thepolicy, it
mayhavebeen amore strategic adaptation.On theother hand, the strained relationship
betweenthetwopartners,maynothaveprovidedthewindowsofopportunityfortheUNDP
totakeadvantageof.
c. UNDPImplementationModality–Thereisalackofclarityregardingthereasoningbehind
whythethreeactivitiesweredirectlyimplementedbytheUNDP.Giventhesuccessfulmanner
inwhichtheONURactuallydeliveredthefundsprovidedtoit,itmayhavebeenmorestrategic
![Page 33: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/33.jpg)
33
and sustainable to allow this project to be nationally implemented, contributing to its
institutionalcapacitybuildingaswell.
d. Gender Equality Focused Programming– The project has noted that gender equality is a
significantobjective(gendermarker2),requiringthat15%ofthebudgetbededicatedforthis
function.However, the evaluators did not notice any active programming to build gender
equalityexceptinthepsychosocialwork.Here,70femaleheadedhouseholdersweretargeted
andprovidedTrainingofTrainerstrainingonpsychosocialaspects.Itmustbenotedthatthis,
however, is a very targeted support, allowing these women to become key players in
supporting their own and their community’smanagement of psychosocial issues. Inother
componentsoftheproject,genderequalityrelatedprogrammingisrestrictedtoencouraging
participation,averypassivemethodofprogramming.Thefactthatofficersbelieveincreased
participationisadequate,indicatesalackofawarenessofgenderrelatedissuesandareasof
concern.
e. UNDPofficialsusedthemetaphorofa‘hinge’inrelationtothepeacebuildingfund.Thehinge
allows/facilitatesthewindows/doorsofopportunitytobeopenedbutdoesnotopenitby
itself.Theyexplainedthatit’snottheUN’splacetotellSriLankawhattodo,buttosupport,
facilitate,adviceandguideSriLankawhenrequestedandwhereopportunityexists.TheSri
Lankanpeacebuildingprocessneedstobeanationallydriven,nationallydesignedprocess.
AndtheUNhasdonewhatisinitspowertosupportsuchaprocess,andconsciouslyplanned
itssupportfromthatperspective.
i. TheUNisawareofthesuspicionwithwhichitandotherwesternideasareviewed,
andunderstandsthatanysortofovertmannerofengagingwithSriLankawillonly
undermine the effectiveness of government interventions and how its perceived.
Therefore,theyfocusonbeingasdiscreetaspossible,andlimitingtheirengagement
tofacilitatorysupportivefunctions.
3.2.1.4LessonsLearneda. LogicalDesignApproach-Lookingbackwardsfromtheendoftheproject,attheverydynamic
context that the projectwas immersed in, the type ofwindows of opportunities that the
projectwas trying tocatalyse, the risks inherent in this typeofwork,and the institutional
buildingworkattheheartofthisproject–standardlogicalanalysisisprobablynotthemost
appropriate approach. Its best used in a stable context, where results can be logically
predicted.Inadynamiccontext,withinherentrisksattachedtopoliticsandpowerplaysits
difficult for results to be predicted. In a sense, the results frameworkmay even limit the
activitiesoftheprojectbindingitmechanicallytoitstargetsandindicators.Toallowaproject
likethistheflexibilityandadaptabilitytomaneuverinthiscontext,theapproachisnotagood
match.TheTheoryofChangeapproachthoughusedinthedesign,doesn’tseemtohavebeen
usedeffectivelythereafter.Ifappliedintheprojectmanagementcycleitshouldhelptoadapt
to contextual issues. The Problem Driven Iterative Adaption (PDIA)4 approach is another
relevantandeffectivefit,especiallyforinstitutionalbuildinginunstablecontexts.
4PDIAdiffers fromotherdevelopmentapproaches in that itmoves fromcritiquetoresponse. It isprimarily
concernedwithbuildinggovernancecapabilitytodeliveroncomplexandpotentiallycontestedreformsinareas
likegovernanceandjustice.PDIAdifferentiatesfromothermethodsconcernedwithreformsimplementation,
alsoinitshigherfocusontheenablingbackgroundconditionsthatmakeitpossibleforsystemstobefunctional.
Theideaofadaptationwhichputsunderquestionthenotionofdoingreformsbyadoptingexternalrules–best
practices–isalsouniquetotheapproach.Formoredetailsrefer:MattAndrews,LantPritchett,SalimahSamji
and Michael Woolcock 2015. Building Capability by Delivering Results: Putting Problem-Driven Iterative
![Page 34: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/34.jpg)
34
b. RelationshipManagement-Theabilitytoinfluencechangerestsmuchmoreonthehuman
aspectsofprogramming,thanonthetechnical,especiallyforprojectsworkingwithinmore
sensitiveandpoliticallychargedenvironments.Therefore,managingrelationships,building
rapport,orientatinglocalcounterpartstoUNwaysofworking,needstobehandledformally
aswell as informally, if the UN is committed to ensuring the effectiveness of theirwork.
Review of meeting minutes especially showcase the very formal and distant relationship
betweenthedonorandtherecipient.TheUNDPapproachtoengagingcounterpartsneedto
bebroughtontoamoreequalplatformofpartnershipandcollaboration.Incaseswherethe
UNDP isdirectly implementingaproject, theonus toensure that theproject iseffectively
delivered lies with the UNDP. In complicated roles where delivery is dependent on the
partner,it’simperativethattheUNDPundertakemorehandsonrelationshipmanagementas
well.Withouttakingthisaspectintotheprojectmanagementactivities,it’sunlikelythatthe
UNDPwillbeabletoensureeffectivelydelivery.Giventhehighoverheadsof14%thatthe
UNDPchargesforprojectimplementation,itwouldbemoreefficientandeffectivetohavea
dedicatedpersonberesponsibleforanationallycritical,time-sensitivepeacebuildingproject.
c. Proactive Monitoring and Risk Management – It’s noted by evaluators that with more
proactivemonitoring,measurestomitigatethepoorrelationshipbetweenitsmainpartner
couldhavebeenimplementedeffectivelyandefficiently.Monitoringfromthepointofview
ofwhether the projectwas achieving its expected result, should have also prompted the
projecttore-programmeintomorestrategicactions.Rigorousprojectmonitoring,usageof
monitoringfindings,andstrategicadaptivemanagementtoensuretheprojectstaysontrack
andiseffectivelydelivered,isfoundtobecriticalinadynamiccontext.
d. AdaptiveManagement-Theprojectactivitiesasdescribedabovedeviatedsignificantlyfrom
the original plan and the results framework. However, given the instable political context
withinwhichtheprojectoperated,it’sexpectedthatthepredictedactivitypathwaymayneed
to be adjusted and adapted depending on the available entry points and opportunities.
Therefore,evaluatorsfeelthattheprojectimplementersshouldfocusonthedeliveryofthe
originallyplannedresult,morethanafocusontheplannedactivities.Accordingly,insertion
of completely different activities, if its strategic enough, should be considered instead of
simply redressingactivities.Agoodexampleof this, is theM&Eactivityadjustmentor the
WHOpsychosocialadjustmentmadebytheproject.Theseareminorlevelsofchangetothe
originalactivity,butnegatedacontributiontotheexpectedoutput.
e. DocumentationandReporting–Theprojectshiftedhandsbetweenagencies,andthereafter
betweenstaffbothwithintheUNDPandONUR.Therefore,theneedforveryclearprocess
leveldocumentation,meetinganddecisionmakingrecordsiscriticalforeffectiveandefficient
delivery.Thelackofdocumentationandclearexplanationsforchangesandamendmentsto
project actions, also disempowers incoming new staff who are then reluctant to take
responsibilityforaspectsthattheyareunawareof,whichwasevidentwithbothparties.While
thedonor/PBSOtemplatemaybelimiting,itwouldbewelladvisedfortheUNDPtomaintain
itsownmonitoringrecordsclearlydocumentingreasoningfordeviationsandamendments.
f. InclusiveConsultation/Collaboration–It’sclearthatoneofthekeycontributingfactorsto
thepoorrelationshipbetweentheUNDPandONUR,wasduetotheONURnotbeingbriefed
clearly about how the project would be implemented. Therefore, the ensuing
misunderstandingcausedtheONURtoadoptalessthancollaborativeapproachtotheaspects
oftheproject itwasnotdirectlyresponsiblefor.Thismisunderstandingandresultingpoor
Adaptation (PDIA) Principles into Practice. A Governance Practitioner’s Notebook: Alternative Ideas andApproaches©OECD2015.
![Page 35: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/35.jpg)
35
relationship could have been averted to an extent if the working modalities and other
implementation related matters were clearly conveyed to the partner. This in a sense
compromisedtheeffectivelydeliveryoftheproject.
g. Internal Communication and Information Sharing – Its observed that there was poor
communication and information sharing vertically, between different levels of both
organisations.OntheUNside,thisisnotedbetweenthepoliticaldecisionmakingleveland
theworkinglevel,duringthedesignphaseaswellastheimplementationphase.Improvement
ofthecommitmenttokeepallpartiesadequatelybriefedwherenecessary,isseenascritical
in reducing avoidable misunderstanding and improving effectiveness and efficiency of
delivery.
h. Implementation Modality – In a context like Sri Lanka, where the UN and NGO’s are
considered with suspicion, a directly implemented project working on peacebuildingmay
havehadlesstraction.AlsogiventheUNapproachofpeacebuildingfundsbeinga‘hinge’,and
theirworkonlybeingfacilitatory,itthenraisesthequestionaboutitsdirectimplementation
modality.However,ifthePBSOmodalityrequiresdirectimplementation,thenactivitiesneed
tobedesignedandimplementedfromthatunderstanding.Withintheproject,it’snotedthat
the component that the ONUR took responsibility for, was implemented effectively, as
demonstratedbythevariousassessmentreports.
i. Programming Depth – In a relative sense, it’s easier to understand the overall context
operationalinasituation,thanitistotrytochangeit.Inthissituation,it’simportantthatthe
samedegreeofanalysis in theproblemanalysisbecontinued intodesigning theexpected
results,andhowitwouldbemeasured.Dedicationandcommitmenttoensuringchangeson
thegroundshouldbeseenconcretelyinthedesignoftheexpectedresults.Languageusedin
thestatementofoutputsand intheresults frameworkshouldnotbeelusiveandbemore
substantive.
Aneg.isActivity3:InitiationoftheformulationofaNationalReconciliationPolicy.ThereinitappearsthattheUNwilltakeresponsibilityonlyfortheinitiationofthepolicyformulation
work,andnotthereafter.Wouldsimplytheinitiationofthepolicyworkhelpaddressthedire
contextualsituationandtakeadvantageofthewindowofopportunityinthecountry?This
callsintoquestionthecommitmentinreality,asopposedtowhatthein-depthdetaileddesign
narrativeshowcasedasareasofconcern.WhilekeepinginmindthattheUNalsocanonlybe
responsible for facilitating a process, it still needs to be able to take responsibility for
facilitatingaction inamorededicatedway.Are-writtenexampleoftheaboveactivitycan
possiblybe–Activity3–FacilitationofthedevelopmentandimplementationofaNationalReconciliationPolicy.
j. Gender Related Programming – When project programming does need to address how
womeninparticularareaffected,theresulttendstobethecontinuationofthestatusquo.
This means that their marginalisation and disempowerment continues to be further
institutionalised. In a peacebuilding context, it alsomeans that opportunities to empower
womenandsupportthechangeinstatusquoisnottakenadvantageof.It’simperativethat
the UN proactively utilises these opportunities available through its projects to promote
equality of women, and acknowledge that passive participation related approaches see
limitedeffectivenessandimpact.
![Page 36: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/36.jpg)
36
EvaluationMatrix:
Project Two: “Support to Sri Lanka to promote national unity and reconciliation efforts
through targeted technical assistance to the ONUR and the Northern Provincial
AdministrationandEasternProvincialAdministration.”
Output1:Keymechanismsandprocesses(elementsofaroadmap)fornationalunityand
reconciliationcommencedundertheguidanceofONUR
CMOCONFIGURATION Category RemarksContext Relevance Highlyrelevantandstrategic
interventiontosupporttheONURtoputinplacelongtermprocessesandmechanisms
Mechanism RelevanceEffectivenessEfficiencyGenderDimension
Relevantmechanicsofachievingtheoutputwasdesigned.However,theimplementationmodalitymayneedtobereconsidered.Only1of3keyactivities,thequick-winswereimplemented.Projectcyclemonitoringandriskmanagementwaslimited.Fundswerereprogrammedbutwithoutmuchcontributiontowardstheoveralloutput.Duetolimitedimplementationofactivities,theefficiencyintheuseofprojectfundswaslimited.Focuswasmainlylimitedtothepsychosocialworkwithinactivity2,whileotheractivitiesonlysupportedequalparticipationofwomen.Proactivegenderfocusedprogrammingwaslimited.
Outcome ImpactandSustainability Itisunlikelythattheimplementedquickwinactivitieshadmuchdepthinimpact,orthatitwouldbesustainable.SettingupprocessesandmechanismsundertheguidanceoftheONURtopromoteunityandreconciliationwasnotachieved.
![Page 37: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/37.jpg)
37
3.2.2 Output2:NorthernProvincialadministrationandEasternProvincialadministrationenabledtoproducestrategicplansandstrengthenrevenuegenerationtosupportdevelopmentactivitiesthataddresstheprioritiesofconflictaffectedpeople.
3.2.2.1ContextRelatedFindingsActivity 1: Fielding of technical experts to support the Northern Provincial Administration and
EasternProvincialAdministrationtodevelopmulti-sectordevelopmentplansandmechanismsto
strengthenrevenueraisingcapacities.
The PBF support and its proposed interventions weremade in the post-war context to facilitate
inclusivedialoguesonissuesofnationalunityandreconciliation.Itwasalsobuiltonthehypothesis
that “if the society can witness peacebuilding results on the ground then there will be greater
confidence,trustandrealisationinprospectsforasustainablepeace.”TheNorthernProvincewasthe
worstaffectedduringthelastthreedecadescomparedtotheotherprovinces.TheEasternProvince
isthenextwar-affectedregionrequiringfocusedassistance.
Thereseemstobeanunderstandingatthetheorisingleveloftheprojectthattheneeds,priorities,
peculiarities and their insecurities when reconstructing their lives after a devastating war is very
differentfromtheprioritiesoftherestofthecountry.However,theirreconciliation-relatedneedsare
somehowlostwhentranslatingtheimplementationoftheorytoproject-levelactivitiesontheground.
ThatthepeopleoftheNorthernprovince,continuetoholdthattheirrights-basedgrievancesareyet
tobeaddressedbythecentralstate, isanoverpoweringallegationthatsubsumestheir interest in
meredevelopmentprojects5.Thisisalongstanding,well-knownpleafromtheregion.Thattheywish
toaddress their rightsbased issuesalong-sidedevelopmentgoals, asa region recovering froman
ethnicconflictandacivilwariswidelyknown,inthepost-warcontext(FernandoandMoonesinghe,
(2012);Thaheer,Peirisetal.(2013);Frase(2017).Attheprojectimplementationlevel,itoughttohave
been informedbythisstronglyarticulatedgrievancethatprovides thecontextualbackdroptoany
interventionintheNorthincluding,thereferencestothis intheTOCnarrativesoftheUNsproject
documents.SomeactivitiesintheNorthernProvincialCouncil(NPC),analysedbelowseemtoreiterate
theneedforreflectiononthisaspect.ActivitieswiththeNorthernandEasternProvincialCouncilfor
improvinginstitutionalcapacities,werecarriedoutduringNovember2016toMay2018.
TheNorthernProvinceDevelopmentPlan–Thisactivityhasnot takenplace. Instead, fundshave
beendivertedtocarryouttheDistrictPlansofJaffna,MullaitivuandKilinochchi(tobecarriedoutin
concurrencetotheDistrictPlansofVavuniyaandMannarthathavebeenformulatedearlierwiththe
assistanceoftheUNDPandotherdonors).Hence,thethreeaforementionedDistrictSecretariatshave
been approached to develop their respective District Plans instead of the development of the
NorthernProvincialPlan,asplannedandenvisaged intheprojectdocument.Plans/decisiontoby-
pass this area ofworkwith theNorthern Provincial Council and to directly develop theNorthern
DevelopmentPlanwiththreeDistrictSecretariatshavenotbeendocumentedbytheUNDP.However,
theminutesofaProgressReviewMeetingoftheNorthernProvincialSecretariatofOctober16,2017
(almostayearafterthelaunchoftheproject),thatwassharedbytheUNDPprojectstaffnotesthus:
“[sic]Unavoidablecircumstances,theProvincialDevelopmentPlancouldnotbeprepared.TheChief
Secretaryinformedthatthisamountmaybetransferredtotheotherdepartmentsforfulfilltheurgent
5Informationbasedoninterviewswithsomestakeholdersandliteratureonreconciliationrelatedissuesin
theNorth.
![Page 38: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/38.jpg)
38
needs.”6
Project Implementation– Theassumption is that the funds allocated for thedevelopmentof the
NorthernProvincialPlanwouldbetransferredfortheDistrictPlans.Theseplansaretobeconsolidated
tocarryoutaProvincialPlannextyear.7TheDeputyChiefSecretary,Planningalsovalidatedthatthe
activitiesfortheimprovementofservicedeliveriesandstrengtheningofinstitutionalcapacitieswith
theassistanceofUNDPwillhelpdevelopprovincialdevelopmentplannextyear.8
TheDistrictSecretaryofJaffna,N.VethanayahaninaninterviewwiththeCEPAteamvalidatedthe
developmentoftheJaffnaDistrictPlanwhichisalreadyavailableinthepublicdomain.Hestatedthat
differentdistrictshavedifferentpotentialsandsoaretheirpatternsandpriorities.Withthehelpof
thedistrictplans theProvincialCouncilplans todevelop themasterplan for theProvince. “Itwas
discussedinthemeetingwiththeChiefSecretaryandthestaff.Itwasagreeduponatthemeeting,
wewillprepareaprovincialplan,butwill firstworkon thedistrictplansbeforeproceeding todo
that.”9TheDevelopmentPlansofKilinochchiandMullaitivuDistrictsarecurrentlyunderpreparation.
TheChiefMinisteroftheNorthernProvincialCouncilJusticeC.V.Wigneswaran,commentingonthe
PeacebuildingFundrelatedwork intheNorthexpressedhisdispleasureof itbeinganon-inclusive
process. His appeal to the UN Resident Coordinator (UNRC) requesting for the participation of a
member of the elected body of the council, in the Peacebuilding Boardmeetings (instead or) in
addition to theChief Secretaryof theNPC, a Stateofficial, (who, theybelieve cannotmakea fair
representationofthepeople’swar-relatedgrievances)hasyettobemet.10InhisletterstotheUNRCO
and during hismeetingwith the thenUNRC,UnaMcCauley, ChiefMinisterWigneswaran says he
appealedforthe inclusionofamemberoftheelectedbodyofthe“affectedpeopleforwhomthe
Peacebuildingmatrixwaspurportedlyprepared.”11Inhisletter,hestates,“Itisnottoolatetoallow
representativesofthepoliticalleadershipoftheNorthernProvincetohereafterparticipate...Notto
allow the representatives of the victims, the affected and the identified beneficiarieswould be a
travesty of justice”.12 He states in a letter to be delivered at the Peacebuilding Board meeting,
addressedtoMinisterofForeignAffairs,MangalaSamaraweeraandtheUNRC,UnaMcCauley,“on
ourparticipation...Hon.Ms.UnasaiditwasnotpossiblefortheNorthernProvincialCounciltobecome
amemberandparticipate…”13Inhisopinion,itisnotenoughtoinvitetheChiefSecretarywhoisa
publicservantundertheCentralGovernmenttoparticipateatthesePeacebuildingBoardmeetings.
SuchmisunderstandingsseemtohavecausedtheabsenceoftheNorthernProvincialDevelopment
Plan.
The funds that were meant to strengthen the Provincial Council with the formulation of a
6MinutesoftheProgressReviewMeetingonStrengtheningInstitutionalCapacityofSelectedDepartmentsand
Officeof theDeputyChief Secretary - Planning in theNorthernProvinceby Improving ServiceDelivery and
FacilitateDistrictDevelopmentPlan,October16,2017.7 Interview with the Chief Secretary, Northern Provincial Council, Mr. A. Pathinathan on August 29, 2018.
Although, thedecision to carryout theNorthernProvincial Planas a sequel to the fiveDistrict Plans is not
documentedanywhere,hesaidhewasdeterminedtoworkonitnextyear,byconsolidatingthefiveDistrict
Plans.8InterviewwiththeDirector,Planning,ProvincialCouncil,Mr.UmakanthanonAugust29,2018.9InterviewwiththeDistrictSecretaryofJaffna,N.Vethanayahanon29August,2018attheDistrictSecretariat,
Jaffna.10InterviewwithHon.JusticeC.V.Wigneswaran,ChiefMinister,NorthernProvincialCouncilon30August,2018,
Jaffna.11LetterwrittenonApril6,2017,addressedtoHon.MangalaSaamaraweera,MinisterofForeignAffairsand
Hon.Ms.UnaMcCauley,UNResidentCoordinatoretal.12Ibid.
13Ibid
![Page 39: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/39.jpg)
39
development plan of the Northern Province being diverted to the District Secretaries (who are
perceived as the agents of the Central Government; that are non-autonomous bodies, with a
constrictedmandate toserve the region,compared to thepeople’selectedbodyof theProvincial
Council),beliestheproject’swell-definedpurpose,describedinitsjustificationforassistancesought
throughaPBFsource.ItalsomakestherationalefortheUNPBF’sinterventionchallengingtofathom
fromanevaluator’spointofview.TherepeatedcontentionsfromtheNorthernProvincethattheUN’s
interventions are also circumspect if not are unremittingly turning a blind eye to meaningfully
strengtheningprovincialadministrationinthepost-warphase,whichwerehithertoundermined,may
not be entirely valid. Nevertheless, it is an imputation worth reflecting upon, in strategic
implementationofreconciliationprojects,withthe‘conflictsensitivity’itdeserves.
ProjectDocumentationandRecordKeeping–There isnodocumentedrecordtoexplainwhythis
Activityhadnotbeencarriedout.MeetingswiththeUNDPteamtoelicitinformationonthisproved
tobefutile,astherewasnoformalprojectdocument(i.e.projectmeetingminutes)availableonthe
UNDP’s decision/reasons to shift from this key Activity envisaged in the logframe of the project.
Project staff, however, did allude to the non-cooperation of the Chief Minister of the Northern
ProvinceasthereasonfornotdevelopingtheNorthernProvincialPlan.Interviewswithofficialsofthe
UNRCofficealsoverballyvalidatedthesame.Intheabsenceofanywrittendocumentonthismatter
ontheUNDP’spart,theCEPAteamisunabletomakeanyconclusiveobservationonthis,exceptfor
usingthisspacetoconveysentimentsofthedirectstakeholders/beneficiaries(asconveyedabove)on
thisactivity.
Theprojectdocumentunderscorestheneedfora“broad-basedconsultativeprocessanddrawingon
acomprehensivedevelopmentneedsassessmentbytheGovernment,UNandotherhumanitarian
partners…IntheNorth,themulti-sectordevelopmentplanwillbedevelopedincloseconsultationwith
theBoardofMinisters...whileworkingwiththeProvincialMinisters…”(UNPBSCOProjectDocument
2016). However, the team finds this main objective of the Project being circumvented. A formal
explanationbywayofprojectleveldocumentationorPeacebuildingBoard(PBB)minuteswouldhave
helpedtheevaluationteamtounderstandthereason/sbehindthedivergenceofthisactivity,from
theprojectdocument,whichisseeminglyaquintessentialpartofthePBF’ssupport14fortheregion.
StrengtheningRevenueRaisingCapacities– In theNorthernProvince, theactivities tostrengtheninstitutionalcapacityofselecteddepartmentsandtheOfficeoftheDeputyChiefSecretaryPlanning
by improvingservicedeliverieshavebeencarriedoutwell.Themainobjectiveofthisactivity isto
enhance skillsandknowledge to improve theHRcapacityofOfficesof theCommissionerof Local
Government (CLG) and the Assistant Commissioners for Local Government (ACLG) and local
authorities to ensure better service deliveries and resource utilisation. Activities have also been
carried out to improve institutional capacities and capability of the planning secretariat of the
Provincial Council to ensure better planning and implementation; systematise legal constitutional
provisionstomaximiseresourceusage.
SomeinterventionshavebeenmadeinkeyNorthernProvincialDepartments,andinclude:supportto
theDepartmentofCommissionerofLocalGovernmentandallACLGoffices;supporttodevelopthe
14Rationale forPBFSupport:“theprojectwillworkwith theNorthernProvincialadministrationandEastern
Provincial administration to enable them to produce strategic plans and strengthen revenue generation to
supportdevelopmentactivitiesthataddresstheprioritiesofconflictaffectedpeople”Projecttitle:Supportto
SriLankatopromotenationalunityandreconciliationeffortsthroughtargetedtechnicalassistancetotheONUR
and the Northern Provincial Administration and Eastern Provincial Administration. United National
Peacebuilding Support Office (PBSCO)/Peacebuilding Fund (PBF), IRF Project Document. Project Start Date
February1,2016.p.10.
![Page 40: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/40.jpg)
40
institutional capabilities of the Provincial Management Development and Training Unit (MDTU);
systematiserevenuegenerationservicesoftheDepartmentofMotorTrafficandtheDepartmentof
Provincial Revenue; support to establish a “one-stop service bureau” to improve industrial
developmentandalsotopromoteinvestmentwithintheProvince.
MonitoringandImplementation–InterviewswiththeHeadsofsomeoftheseDepartmentsrevealed
thesuccessfulcompletionoftheactivitiesthathaveenabledindividualsandinstitutionstoengagein
sustainablelocaleconomicdevelopment/revenuegenerationactivities.Officialsvouchforincreased
levelsofeffectivenessingovernanceinstitutionsforefficientservicedelivery.Thereisalsoincreased
levels of knowledge among policy makers and development partners on good practices of
transparency,localeconomyandlocalgovernance.Communitymemberstoofeelempoweredwith
skillsandabilitytoparticipateinlocalgovernanceactivities.
AttheMotorTrafficDepartmentforinstance,theynowpossessthesoftwarecomponentthatlinksall
theDSofficestooneplace,incomparisonwiththepast,whentheyhaddifficultiesgettingaccessto
computeraccessories,intheirdepartment.TheCommissionerforMotorTrafficclaimsthattheyhave
purchased41computersundertheProjectandprovidedthemtoeveryDSdivisionintheProvince.
“The technicalpackagesarealreadypreparedby the ICTAandare linkedwithall computers. The
softwareiseasytoaccessbythepublicinnotime.Therewasatimetheyhadtowaitlonghoursto
getamotorlicense.Thishaschangedthingsradicallyforthebetter.”15
TheDepartmentofLocalGovernmentalsocommendedtheobservablechangesthathavetakenplace
asaresultoftheUNDP’sProjectintervention.Speakingofacaseinpoint,itwaspointedoutthatthe
valuationexerciseinKarachiandKararaipatrudivisionsinKilinochchiwerequitesuccessfulbecause
thesetwolocalauthoritiesinthepast,lackedsystemstovaluatetheirsourcesforrevenues.Theywill
now be able to earn around Rs. 15million per annum from taxations. The introduction of these
revenuegenerationserviceshasenabledtheDepartmentofProvincialRevenuetovaluateproperties
andearntheduetaxes–aphenomenonthatwasnotavailableinpre-2016.Thereisinformationthat
taxeswerecollectedinthe1960s.ThisUNDPinterventionisbeingshowcasedasasuccessfulpioneer
project,oncegazetted.Thetaxcollectionprocesswillstartin2018or2019.AroundRs.2millionhas
beenspentonthevaluationexerciseofjustaboutsevenareas.Thereisagreatlackofresourcesto
evaluateallconflict-affectedareasintheProvince.Onlyfewlocalauthoritiescancarrythisworkout
withtheirownfunds,therestneedfinancialsupport.16
TheDepartment ofManagementDevelopment and TrainingUnit (MDTU), has conducted TOTs in
aboutfivemajoractivitiesofMDTU.About195frontlineofficersweretrainedincluding,89whowere
female officers.Gender participation is at least 50%, but thereweremorewomenparticipants in
general,inthesetrainings.ThecapacitybuildingtrainingincludedinformationonSDGgoals,howto
work with the grass root levels, how to incorporate SDG planning in the sessions, capacity
managementetc.17
TheCitizens’Charter introduced in somedepartments in theProvince too,hasbeena resounding
achievementintermsofempoweringthegeneralmasses.Thereisasharpdeclineincomplaintsafter
the public display of the charter. Such public awareness raising mechanisms helps mainstream
transparency,accountabilityandgoodgovernance.Thissentimentisintenseinareasrecoveringfrom
beingformerlyundertheLTTE’scontrol.Thevalueformoneyintermsofthecapacitydevelopment
15BasedoninterviewwithCommissioner,DepartmentofMotorTraffic,Ms.S.SujeevaonAugust29,2018.
16InformationbasedoninterviewwithCommissionerforLocalGovernment,Mr.PatrickDiranjan.
17 Information based on interview with Deputy Chief Secretary, Personnel and Training (MDTU), Mr. A
Sivabanasundaran.
![Page 41: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/41.jpg)
41
andskillsenhancementworkintheNorth,hasbeenfullyachieved.However,assistanceforfurther
workremainsadireneedinmanypartsoftheregion.
The Eastern Province Development Plan – The second medium term development plan was
developedbasedontheneedsofthedevolvedsubjectsoftheEastfrom2017to2020,(basedonthe
first plan thatwas developed in 2012 to 2016). Themedium term development plan includes all
subjectsdevolved to theprovince i.e. irrigation, agriculture, educationetc.UNDP fundswerealso
allocatedtodeveloptheTrincomaleeDistrictPlanwhichwasnotcoveredbyformerinterventions.
TheDistrictDevelopmentPlan2017hasbeenprepared andwill bepublished shortly.All sectoral
needshavebeenidentified.
In theProvincialCouncils in theNorthandEast, theoverallobjectiveof theGovernance for Local
EconomicDevelopmentprojectsunder theUNDP,PBFassistancewere carriedout todevelop the
institutional capacity for better service delivery and improvement of systems to establish good
governancepracticesinselectedinstitutionsoftheNPCandtheEPC.
ThestaffmembersoftheEPCfeltthattheyhaveexperiencedalargercapacitydevelopmentcourse
(justasmuchasthestaffoftheNorthernProvince),owingtotheirworkengagementondeveloping
theEasternProvincialPlanwiththeUNDP’ssupport.Thisdocumentisavailableinthepublicdomain.
MechanismstoStrengthenRevenueRaisingCapacities–Theseactivitieshavebeencommendably
implemented. IntheEast,theexperiencehasalsohelpedthemtopreparesectoralplans,financial
plansfortheMinistryofFinanceetc.basedonthisknowledge-enhancingexperience.Theynolonger
requireconsultantsforplanning.Thiswasasentimentendorsedcollectivelybyallseniorstaffwhom
theCEPAteammetwith,i.e.theDeputyChiefSecretary,PersonnelandTraining;AdditionalDirector,
Planning;ProvincialDirector,Dept.ofRuralDevelopment,CommissionersforMotorTrafficandLocal
Government. Similar gains and claims of the capacity development and knowledge gains were
endorsedbytheircounterpartsintheNorthernProvincialCouncili.e.byDepartmentofMotorTraffic,
CommissionerforLocalGovernmentandtheDeputyChiefSecretary,PersonnelandTraining(MDTU).
Theytoofeltthattheycaninfuture,runthesystemsandcarryouttheirowncapacitydevelopment
work,withtheknowledgegained.
Thiswasalsoalearningexperienceinmanyways.Officialsconductedaseriesofdiscussionspaving
thespaceforopeninteractionsandsystematiseddocumenting.Thisprocessincludescontributions
fromthecivilsocietyandpoliticalrepresentatives.
Avaluableoutcomeintheexposuretosystemsdevelopment/improvementintheEasternProvincial
Council istheirrealisationandtheirinsistenceontheneedtostreamlineaprovincialdevelopment
processforprovincialplanningandcoordination,engineeringservicesmanagementandfinancialand
procurementmanagement.Thetimingandbalancingofactivities intheworkonthesesectorsare
crucialforcoordinateddevelopmentwork.18
TheEasternProvincialCouncil’sConsolidatedAnnualImplementationProgramme,(CAIP)anditsweb-
baseddatabasesystem,asasingleofficialinformationsystemisapositiveoutcomeofthisventure.
Some of the noteworthy activities undertaken by the Provincial Planning Secretariats (PPS) are asfollows:18InformationbasedoninterviewwithformerDeputyChiefSecretaryPlanningoftheEPCN.Mahendrarajaand
fromtheslidepresentationofBalancedRegionalDevelopmentandSDG,ProvincialPlanningSecretariat,Eastern
ProvincialCouncil,Trincomalee.
![Page 42: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/42.jpg)
42
Fundsallocatedforthedevelopmentforumhadbeendivertedfordevelopingcapacityofseniorstaff
oftheEPCinstitutionsandstrengtheningtheinstitutionalcapacitiesforbetterservicedeliveryofthe
OfficeoftheChiefSecretaryandProvincialPlanningSecretariat.
ImprovementoftheexistingDivisionalResourceProfilehasalsotakenplacewiththeinstallationof
thesoftwareattheDistrictandDivisionalSecretariatswiththeimprovementofDigitizedDivisional
Resource Profile. Capacity development trainings to senior staff have ranged fromWorkshops on
LeadershipandChangeManagement;preparationofReportsonStreamliningProvincialDevelopment
ProcessandPracticesandProcurementManagementandalsoonStrengtheningPlanningCapacityof
EPC Officials. Some programmes have been carried out on Architectural and Drawings for Civil
StructuresandRegulationsandPracticesforConstructionofBuildings.
OneofthehighlycommendedactivitieswastheimprovementoftheCAIPweb-basedDatabasewith
additionalfeaturesandfacilitieswithmodificationsintroducedbyFinanceCommission.
StaffTrainingandSoftwareDevelopment–AwebbasedRevenueManagementSystem(RMS)has
been developed and installed at Provincial Departments of Revenue in theNorthern and Eastern
provincial councils. Staff have been trained to operate the software with the procurement of IT
equipment for the efficient running of the RMS. As for the training activities of theMDTU, staff
expressedhighsatisfaction for theTrainingofTrainers (TOT)Programmesconducted inTamiland
Sinhala.AsfortheProvincialTreasurysoftwareformanagingassetsbelongingtoinstitutionsunder
the Eastern Provincial Council (AssetManagement Software), it has been developed and relevant
Chief Accountants, Accountants and Development Officers have been trained on its usage. The
Department of Rural Development has benefitted with an IT based system known as “Rural
DevelopmentSocieties’ InformationManagementSystem”(RDSIMS).Thishelpsthemmonitorand
manage information on Community BasedOrganisation (CBOs) at provincial level, systemise their
registrationandupdatethesystemonaregularbasis.Aplethoraofactivitiesincapacitydevelopment
of skill and knowledge and also on Peacebuilding and Reconciliation related Training to Rural
DevelopmentSocieties(RDS)sandWomen’sRuralDevelopmentSocieties(WRDS)shavebeencarried
out.Womenhavebeenactiveparticipantsattheseworkshopsandborewitnessatourmeetingonto
howtheyhavedirectlybenefittedthroughthesetrainingsforbetterperformancesintermsofsystems
andfinancemanagementintheirvillages.Anotherinstitutionthatbenefittedthroughthisprojectis
theDepartmentof Rural Industries.A rangeof activities have takenplaceunder thisDepartment
including the Vocational training for youth; Support to establish a sales unit for selectedwomen
groupsi.e.modificationoftheSalesCentreinBatticaloatownwithnecessarycomputers,furniture,
fittingsandotherfacilities.
CAIPdatabaserelatedworkcontinuestobeupdatedbythevoluntarycontributionsoftheEPCstaff.
Acentraliseddatabasemanagementsystemhasbeenbeneficialinmanyways.i.e.tomaintainacadre
management system; identify the areas of strengths; the gaps etc. It has also increased their
partnershipandenabledthestafftoresolvepubliccomplaintsbywayofacollectiveeffort.TheCAIP
web based data base is attracting the attention of other Provincial Councils for its best systems
managementpractices.Theyfeel,theyneednoexternalconsultanttobehiredfortrainingpurposes.
Aroundthetimeoftheevaluation,atrainingindevelopingaCAIPdatabasewasbeingofferedtothe
staffoftheSabaragamuwaProvincialCouncilofficetostrengthentheirtechnicalcapacities.
AsfortheRevenueManagementsystem,ithashelpedsystematisetheavailabilityofdata/information
onpropertiesandownership;identifiedgapsandincreaserevenuesandreduceddelaysinpayment.
![Page 43: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/43.jpg)
43
3.2.2.2MechanismRelatedFindingsDedicatedofficersofbothProvincialCouncilsintheNorthandtheEastwereanevidentreasonfor
thesuccessofmostofthecapacitydevelopmentworkinservicedeliverywork.Conscientioussenior
andmid-rangeofficialsincludingtheCommissioners,DirectorsandtheirDeputiesintheDepartments
ofPlanning,LocalGovernment,MDTU,MotorTraffic,RuralDevelopmentetc.inthesetwoprovinces
were the ‘live-wires’ of resources that these projects have empowered. The evaluators identified
thesemotivatedindividualstobethecontributoryfactorsforsuccessamongallprojectstakeholders.
Without the innerwill and dedication of these Heads of Departments, therewould be very little
motivationfortherespectivedepartmentstoproduceremarkablework.
Beside other benefits that have accrued to the general public through the introduction of the
Governance for Local Economic Development (GLED) activities, the staff of these departments
believe,thattheprojectshavehelpeddeveloptheirownpoolofresourcepeoplewhocouldcarryout
furtherworkontheirown.Owingtothesystemsupdatethathasbeeninitiated,thereisnoneedin
futureforacostingforresourcepersonsandthedevelopmentofbasicinformationfortheregions,as
itisnowonlyamatterofupdatingexistingrecordswhenpublicisingnewinformationonrequest.
There isanoverall senseofsatisfaction intheadvancementofsystemsandprocessesset inplace
through theGLED project in the Eastern Provincial Council. The benefits range from a balance in
distributionoffunds;availabilityoftrainedstafftoactiveparticipationofRuralDevelopmentSociety
(RDS)andWomen’sRuralDevelopmentSociety(WRDS)andareductioninpaperwork.
Theofficialsacknowledgethedirectpositiveimpactontheenhancementofskillsandknowledgeof
thestaffinmorethanoneway,i.e.whenobtainingITknowledge,staffbydefaultalsoenhancetheir
knowledgeinEnglish,goodgovernance,accountabilityandtransparency.
TheleadershipprovidedbytheChiefSecretaryandDeputyChiefSecretaryPlanning;communication
andcoordinationbetweenagencies;cooperationoftheimplementingagenciesinfunallocationsetc.
andmostimportantlycommitmentofstaffwithapositiveapproachhavecontributedtothesuccess
storyoftheGLED2activities.
Challenges in implementation – Officials felt that the coordination with District and Divisional
Secretarieswouldbeneededinfutureimplementation.Thelackofsupportandcooperationfromthe
District and Divisional Secretariats for data entry was noted by the Provincial Council staff as an
obstacle.Theyalsosawpoliticalinterferenceasachallengetotheirworkaspertheirplans.Theytend
to disrupt the process by introducing resources to already benefitted areas of their constituency
causing imbalance in development and duplication in fund allocations, viz. Tamil areas remain
underdevelopedowingtolackofattentionofbothTamilandMuslimpoliticians.TheEPCisableto
rectifythistoagreatextentowingtotheavailabilityofthedatabaseandtheinformationobtained
throughit.
Theonlyareaofslowprogressaccordingtothem(inbothprovinces)wasthedevelopmentof the
Statute inturningthemintoa legallybindingprovisions.Multiple levelsofobstaclesseemtohave
sloweddownthisprocess.Althoughthiswasamajorrequirement,theywereunabletocompleteit
owingtothedepartureofaconsultantwhowashiredforthisactivity.Hence,thefundswerediverted
forotherareasofneeds.Thistoowaspossibleasstaffwereabletoforecastnon-productiveareasand
possessedtheagencyandknowledgetodivertfunds.
![Page 44: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/44.jpg)
44
Activity2:PublicConsultationwithCSOsandCommunityGroupstoestablishaCitizen’sCharterto
monitorservicedelivery
ImplementationoftheCitizen’sCharter–ThisismostwelcomeinboththeNorthernandtheEastern
Provinces.Thepublicwhootherwisedidnotknowwhatdocumentstheyhavetosubmit,bringthe
applicationandcomplainorgetswindledbythetoutswhomisleadtheminpublicplaces.Thishas
beenaperennialprobleminalmostallpartsoftheprovinceespeciallyintheNorth,i.e.inJaffnaand
KilinochchiPradeshiyaSabhasandtheMunicipalCouncil.Thepublicisinconveniencedandwereoften
turnedbacktobringtherequireddocuments.But,withtheintroductionoftheCitizen’sCharterin
whichinformationregardingrequireddocumentationfortheregistrationofbusinessesandlandetc.
ispubliclyavailable,peoplearenolongerharassed.Thisisevidentintheremarkablereductionofthe
comparative number of complaints that were received before and after the introduction of the
CitizensCharter.Publicawarenessondocumentationhasalsoarisenfollowingtheintroductionofthe
Citizens’ Charter and there is a remarkable reduction of corruption issues and the upholding of
professional ethics of transparency and accountability in achieving good governance related goals
throughthisactivityaswell.AhighlevelofcontentmentwaswitnessedintheNorthernandEastern
ProvincesduringtheinterviewsandtheworkshopintheprovinceontheCitizens’Charter.
Consideringthegenderaspectofthetraining,theofficialsofthetwoprovincesarewellawareofthe
minimum25%women’sparticipationthatisrequired.Hence,priorityisgiventowomen,intraining
programmes.Ataproject implementation levelandat the levelof thebeneficiariesof theWRDS,
womenexpressedhowtheirlevelsofconfidencehavearisenafterthetrainingstheyhavereceived.
Theyarealsoable toextendtheirknowledgetoefficientlymanagetheWRDSdatabaseand fund
transactionswithahighleveloftransparencytobenefitallwomenintheircommunities.
IntheEasternProvince,theCitizen’sCharterDevelopmentProjectthroughtheMDTUstaffhasfirst
andforemostenhancedtheskillsofthestaffbeforeservingthepublic.Citizen’sChartershavealso
beenpreparedbytheDept.ofLocalGovernmentfor02localauthorities,ProvincialDirectorHealth
SectorOffice,Dept.ofAnimalProductionandHealthandDept.ofAgriculture.Theyarealsoondisplay
ina)AgricultureOffice,Amparab)MCAkkaraipattuc)MOHOfficeAmpara,d)UCAmpara,e)District
OfficeofAnimalProductionandHealth,Ampara.Aveterinarysurgeonattheworkshopvalidatedthe
assistanceoftheequipmentfordisplayingCitizenChartersthathavebeeninstalledintheseplaces.
Assistancetoprocuremoresuchequipmentwasexpressed.
3.2.2.3OutcomeRelatedFindingsContextual factors in the Northern and Eastern Provinces have been well informed and well
considered in theconceptualisingof theprojectsand thedeliveryof someaspectsofOutput2of
Project2.The social, cultural, economicandpolitical contextual imperativesare recognisedunder
Activities1and2, i.e.theneedforstrengthening institutionalcapacityofselecteddepartmentsby
improvingservicedeliveryandharnessingsuccessful interventions thatwouldproducesustainable
andlongtermimpact.Theprojectgoalsforthispurposearealignedwiththecommunity’sneedsand
aspirations that have a bearing on the success of the interventions. The improving of service
components have occurred in a linear fashion and have been carried out systematically. The
implementationofcertainaspectsoftheOutputwereextremelysuccessfulcomparedtoothersowing
to some champions who believed in the need of their importance and armed with a sense of
commitmentversusindividualswhodidnotbelieveintheimportanceofdevelopment.Theyblamed
itonthedevelopmentofanon-inclusivepeacebuildingmatrixthatearmarkedtheregionforPBF’s
specialinterventions.
![Page 45: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/45.jpg)
45
TheUNDP’sassistancetostrengtheninginstitutionalcapacityofselecteddepartmentsbyimproving
servicedeliverieswiththeNPCandtheEPChaveinmostcaseshelpedthemintrinsicallystreamline
activitiesinmostoftheDepartmentsintheNorthernandtheEasternProvincialCouncilswhilstothers
followclosely.
Challengesinimplementation–StaffexpressedtheneedforthedirectinvolvementofsectorHeads
duringthepreparationstageoftheCitizen’sCharter.Theyalsoneedassistanceinselectingsuitable
consultantsespecially,fortranslatingintotheSinhalaandTamillanguages.Thereisgenerallyadearth
oftranslatorsinallsectorsespeciallyforthecreationofatrilingualwebsitefortheEPCcompletewith
alltheinformation.Lackofinterest/encouragementofthetopofficialsinimplementingthefindings
oftheconsultantsreportsinsomesectorswasnoted.
More fundingwas required for developingmore user-friendly digital display in all areas. Officials
noticedaproceduraldelayinthereleaseoffundsfortheEasternProvincialCouncilfromtheUNDP
sidetokeepuptheflowofactivities.
UNDPsupportisappealedforassistanceinpromotingtheCitizens’Charterinallpartsoftheregions
asitservesavitalpurposeintransformingwar-affectedpeoples’livestonormalcyespeciallyinareas
thatwerepreviouslyundertheLTTEwhichseveredtheirconnectionswiththeStatemechanismsand
institutions.
Withtherapidlychangingcontext,extensiveconsultationsatplanning,designingandimplementation
stages have taken place intermittently between the UNDP and the Provincial Offices in terms of
strategisingandreformulatingactivitiesrelatedtostrengtheningcapacity.Thiswasacommendable
featurewhichwasnotsoevident inotheractivities, i.e.workwiththeNPCforProvincialPlanand
aspectsoftheONUR’swork
3.2.2.4 LessonsLearnedReconciliation-related good governance – There is public demand for reconciliation by way of
meaningfuldevolutionthroughademocraticprocessofdecentralisationofpowerstotheprovincial
andlocalauthorities.TherearemanyareasofgovernancerelatedcontentionintheProvincevis-a-vis
theCentre,i.e.acaseinpointistheBusinessTurnoverTaxthatwascollectedbytheProvincialCouncil
which is now takenover by theCentre/lineministry. This deprives theprovince froma sourceof
incomefordevelopmentandcausesmuchdispleasure,aggravatingthecentre-peripherydifferences
in these regions. This also aggravates the negative perceptions of the Centre’s repressive tactics
amongthepeopleoftheregion.Effortscouldhavebeenmadetoaddresslacunaeinpeacebuilding
and Transitional Justice aspects of good governance by the strategic usage of PBF resources for
reconciliationingovernancerelateddimensionsoftheProvincialbodiesratherthanonthegeneral
governance-related activities already carried out. Such activitieswould allow these institutions to
functionwith a certain amount of autonomy, strengthening the reconciliation process, instead of
placingtotaldependencyontheCentre.TheCentre-peripherychasmremains.Givenanethnichue,
theycouldonlydeepenfurther.
Contextsensitivework–TheEasternProvincialCouncil(justasmuchastheNPC)hasbeenclamouring
in the past for Inclusive development and democratic decentralisation within the National Policy
FrameworkandtheneedforanintegrateddevelopmentplanfortheEasternProvince.Bythis,they
meanameaningfulcoordinationofnationalpoliciesandprioritiestogetherwiththeSDGtargets,to
worktowardsdevelopmentofthesocio-economicpotentialoftheregion.19TheNorthernProvincial
Councilhasalsovoicedtheirneedforinclusivedevelopment.Therefore,itisincumbentuponproject
19FromtheEPCslidepresentationofBalancedRegionalDevelopmentandSDG.
![Page 46: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/46.jpg)
46
implementers to be informed by local socio-economic and political contextual conditions of each
region,whenconsideringhowthefuturePBFfundrelatedactivitiescanbeadaptedtodiscernmere
governancerelatedworkversusPBF-supportedgoodgovernancethroughthelensofreconciliation.
It has missed an “…opportunity to build on this positive momentum and support the Northern
ProvinceandtheEasternProvincetosetoutitsdevelopmentvisionandstrategytoaddressitssevere
capacityconstraints…toadvancedevelopmentpriorities,”asspeltoutintheprojectdocument.
ItwasoverallappreciatedthattheUNDP’sGLED1and2projectsthatcameinasasequeltotheLocal
Governance Project (LOGOPRO) work of the UNDP, since 2008, addressedmost of the gaps and
requestsoftheEasternProvincialCouncilwhenidentifyingareasofinterventionsasdesiredbythe
ProvincialCouncil.Theyaregratifiedattheagencytheypossessedandtheknowledgetheyhadgained
throughthisproject,inbeingabletodirectthefundstowardtheiractualneed.
EvaluationMatrix:
Project Two: “Support to Sri Lanka to promote national unity and reconciliation efforts
through targeted technical assistance to the ONUR and the Northern Provincial
AdministrationandEasternProvincialAdministration.”
Output2:NorthernProvincialadministrationandEasternProvincialadministrationenabled
to produce strategic plans and strengthen revenue generation to support development
activitiesthataddresstheprioritiesofconflictaffectedpeople.
CMOConfiguration Category RemarksContext Relevanceofthetheory
atworkAnenablingbackdropandspaceforreconciliationthroughtechnicalassistanceremainsvalid.
Mechanism Relevance
Prioritiesofconflictaffectedpeopleneedfocus.Projectremainsrelevantandimportant.
Effectiveness
Overallplanning/implementationofachievingoverallpurposeofproject’sobjectivesofdevelopingmulti-sectordevelopmentplanstoaddresstheprioritiesofconflict-affectedpeopleisincomplete.However,theaspectwithregardstostrengtheninginstitutionswassuccessful.
Efficiency
Servicesandsupporttotheregionhavebeencost-effectiveandefficientlymanagedbyrespectivesectorsinthetwoProvinces.
GenderDimension Gender-parityandgender-sensitiveprojectinterventionsaremainstreamedininstitutionalpracticesinthetwoProvincialCouncils/UNDP’soverallactivities.
![Page 47: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/47.jpg)
47
OutcomeImpactandSustainability
Positive?Negative?Neutral?
-PositiveimpactandsustainabilityevidentintheregionontheoutputonstrengtheninginstitutionalcapacityandservicedeliveryworkrelatedtobothProvincialCouncils.-Negativeimpactintermsof‘enablingtheNorthernProvincialCounciltoproducestrategicplanstoaddressthepriorityofconflictaffectedpeople’.
4. Recommendations
ThisLessonsLearnedexercisehasbrought to light thesubstantiveundertakingofactivitiesby the
UNDPunderthePBFassistedprojectsandtheirpositiveandnegativeimpacts.Whilecommending
the overall interventionsmade by the UNDP in its sincere attempts to initiate reconciliation and
TransitionalJusticemechanisms,thefollowingsetofrecommendationsareofferedforconsideration,
hoping theywouldprovide contextual information for any future interventions, as overall lessons
learned.
1. TheoryofChangeApproach–Ifthisapproachisbeingused,thenitisrecommendedthatitis
usedthroughoutthewholeprojectmanagementcycle,andnotonlyatthedesignstage.The
theoriesbehindstrategicactionsshouldbeunderstood,monitoredandthecontextchanges,
beadaptedaccordingly.Itshouldnotbeusedasastaticapproach,similartothelogicalor
results framework approach. This would curb the usefulness of the approach for fluid
contexts.
2. ProblemDrivenIterativeAdaption(PDIA)Approach–Forprojectsworkingonpeacebuilding
orworkinginfluiddynamiccontexts,theuseofstaticprogrammingtoolssuchastheResults
BasedFrameworkisnotrecommended.Itslimitationshavebeendiscussedearlier.Instead,
theusageofaPDIAapproachisproposed.Thisthinkinghasgainedalotoftractionamongthe
development community and comes recommended for state crafting work dealing with
sensitivefluidcontexts.“Manyreforminitiativesfailtoachievesustainedimprovements in
performancebecauseorganisationsusemimicrytocamouflagetheabsenceofrealchange.
Thatis,theypretendtoreformbychangingwhatpoliciesandorganisationalstructureslook
likeratherthanwhattheyactuallydo”(Andrews,Pritchettetal:2012).PDIAisanchoredontransformation of institutionswith a focus on “what is actually done” to ensure sustainedperformanceimprovement,ratherthanfocusingonpolicychangeorhoworganisationslooklike(structure).
3. RelationshipManagement–Peopletrustpeople,andpeoplearemorelikelytobesupportive
orcollaboratewithpeopletheycanrelateto.Thishumanfactorneedstobeconsideredin
projectslookingtoinfluencepeopleandinstitutionalchange.Therefore,itisrecommended
that relationshipbuildingapproachesand techniquesbeutilised toensureproject results.
Specifically, in peacebuilding contexts its recommended that the UN prioritize the
developmentofstrongworkingrelationshipsbuiltontrust,understandingandpartnership,
movingawayfromdonor-beneficiaryapproaches.
4. ProgrammingApproach–WhilekeepinginmindtheinvisibleborderthattheUNorprojects
suchasthesemustoperatewithin,itisrecommendedthatprogramminginamorecommitted
![Page 48: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/48.jpg)
48
fashion,takesresponsibilitytocreatelastingchangeespeciallywheregapsareevident.Itis
aninherentimperativethatneedstobeaddressedasdescribedearlier.
a. ReportingandKnowledgeManagement–Projects,especiallythoseoperatinginfluid
and unstable contexts must undertake substantive documentation, reporting and
knowledgemanagement. Thepresenceofwhichwill empower stakeholders to take
holisticresponsibilityandownership.
b. ProactiveMonitoringandRiskManagement–Asstatedabove,activemonitoring,
usageoffindings,riskmanagementandstrategicadaptivemanagementneedstoform
theenginethatdrivesthesetypesofprojects.Itenablesprojectstorespondtochanging
situations,people,issues,whilestillaimingatachievingtheexpectedresults.
c. ProactiveGenderrelatedProgramming–Opportunitiesaboundindynamiccontexts
tochangethestatusquoofespeciallywomen,andtheseneedtobecapitalisedupon.
Clearerunderstandingaboutgenderissuesneedstobeactivelybuiltintoprogrammes,
anddedicatedactivitiesimplemented.
d. InclusiveConsultationandCommunication–WhiletheUNRCOundertakesstrategic
guidancetothepeacebuildingandreconciliationprocess,wheretheimplementationis
beinghandedovertoaspecificagency, itsimperativethatthatagencyis includedin
the design phase. It is understood though, that it may not be possible for the
implementingagencytotakepartinallhighlevelconsultationsandmeetings,orwhen
necessary. When persistent demands for inclusive dialogues and requests for a
participatoryexercisearemadebydirectstake-holders (whocouldalsobepotential
spoilers) and representatives from the war-affected zones, through formal lines of
communicationgiventhepeculiarityofthecircumstances,thecontextandthepurpose
of the Peacebuilding Fund’s rationale for intervention, an accommodative approach
would be desirable. This would save acute criticism undermining the PBF’s good
intentions. Inclusivity in the Peacebuilding Board set up with a particular purpose,
(unlikeforthepurposeofanyotherdevelopmentproject),isrecommended,insteadof
rigid exclusivity. This could have ensured success of programmatic interventions as
planned.Thepreponderantaccusationof ‘absenceof consultation’whenconceiving
especiallyapeacebuildingmatrixfortheaffectedpeople(whichisasimportantasany
othermeredevelopmentproject)couldhavebeenavoided. Ontheotherhand, it is
also necessary that means of internal communication and information sharing is
rigorouslypracticedsothatprojectsmaybeconsistentlyandeffectivelyimplemented.
e. Documentationandrecordkeeping–Programmestaffmustbeconsistentinkeeping
up the good practices of keeping/maintaining documentation evidence on
programmatic activities, especially in challenging programmatic areas of non-
performance-diversionofplansandpointsofdeparturefromtheactivitiesoriginally
envisaged in the log frames, to justify the new course of actions. i.e. minutes of
oversightcommitteemeeting,projectteammeetings,lettersofagreements.
f. Improvingservicedelivery–TheNorthernandEasternProvincialCouncils’,Planning
OfficersandHeadsofDepartmentswereintotalcommandoftheconcept.Allactivities
have been carried outwith personal commitment by all of them,with no poignant
condition that deserves attention, except for the appeal for the UNDP’s sustained
engagementinstrengtheningtheplanningunitsinthelocalgovernmentministriesand
departments–acurrentregionalrequirement.Providingassistanceforimprovement
ofservicedeliveryinotherpartsofthesetworegionstoowouldbeverybeneficial.The
success is attributed to the local adoption of the broader activity of “multi sector
![Page 49: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/49.jpg)
49
development” speltoutby theUNDPoffice (underProject2,Output2), to suit the
regionalimperativesontheground.TheflexibilityaccordedtotheProvincialCouncils
todoso,washighlycommended.Thisledtothecommunity’sownershipofthework
and bottom-up-approaches of people’s participation. Areas with multicultural
communities such as in Trincomalee, also had high participation in such peace-
dividends-relateddevelopmentactivities.
![Page 50: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/50.jpg)
50
References
Andrews,Matt,Pritchett,Lant,Samji,SalimahandWoolcock,Michael(2015).BuildingCapabilitybyDelivering Results: Putting Problem-Driven Iterative Adaptation (PDIA) Principles into Practice. AGovernancePractitioner’sNotebook:AlternativeIdeasandApproaches.UnitedKingdom:OECD.
Church, Cheyenne and Rogers. M. (2006). Designing for Results: Integrating Monitoring andEvaluationinConflictTransformationPrograms.WashingtonDC:SearchforCommonGrounds.
ConsultationTaskForceonReconciliationMechanisms(2016)“InterimReport,TheOfficeonMissing
PersonsBillandIssuesConcerningtheMissing,theDisappearedandtheSurrendered”Colombo:CTF.
Fernando,PriyanthiandSonaliMoonesinghe,(2012).“ResearchingLivelihoodsandServicesAffected
byConflict: Livelihoods,�Basic Services and Social Protection in Sri Lanka,” SLRCWorkingPaper 6,
August2012.London:ODI.
Fernando,R.(2014),‘ReconciliationandHumanRightsinSriLanka’.SpeechpresentedatTorontoin
CentreforAppliedHumanRights.January19.
Fonseka, B. (2017). Transitional Justice in Sri Lanka: Lessons So Far and the Long Road Ahead.
Retrieved February 15, 2018, fromhttp://groundviews.org/2017/01/11/transitional-justice-in-sri-
lanka-lessons-so-far-and-the-long-road-ahead/January11.
Frase,Elizabeth(2017),JusticeDenied:ARealityCheckonResettlement,DemilitarizationandReconciliationinSriLanka.February2017.Oakland:OaklandInstitute,USA.,.
Goodhand,Jonathan(2013)“SriLankain(2012):SecuringtheState,Enforcingthe“Peace”.53(1)AsianSurvey64,64–72.
Jagosh, J. et al. (2011)Assessing the outcomes of participatory research: protocol for identifying,selecting,appraisingandsynthesizingtheliteratureforrealistreview.Montreal:McGillUniversity.
Kottegoda,S.(2012).DoWomenPlayaRoleinSriLanka's'Reconciliation'?:GenderDynamicsinthe
TransitionfromWartoPeace.RetrievedFebruary15,2018,
fromhttp://groundviews.org/2012/08/21/do-women-play-a-role-in-sri-lankas-reconciliation-gender-
dynamics-in-the-transition-from-war-to-peace/August20.
LessonsLearntandReconciliationCommission(2011).ReportoftheCommissionofInquiryonLessons
LearntandReconciliation.Colombo:GovernmentofSriLanka.
Minutes of the Progress Review Meeting on Strengthening Institutional Capacity of Selected
Departments and Office of the Deputy Chief Secretary - Planning in the Northern Province by
ImprovingServiceDeliveryandFacilitateDistrictDevelopmentPlan,October16,2017.
Office forNationalUnity andReconciliation (ONUR) (2017) “National Policy onReconciliation and
Coexistence” Available at < http://www.onur.gov.lk/images/download/NationalPolicy-English.pdf>.
AccessedonAugust3,2018.
Office for Reparations Bill (Part 11) of 2018 (Supplement). Sri Lanka: Department of Government
Printing.
![Page 51: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/51.jpg)
51
OfficeoftheUnitedNationsHighCommissionerforHumanRights(2015).“ComprehensiveReportof
theOfficeoftheUnitedNationsHighCommissionerforHumanRightsonSriLanka”.
PawsonR.,GreenhalghT.,HarveyG.andWalsheK.(2004).RealistSynthesis:AnIntroduction.UnitedKingdom:UniversityofManchester.
Pawson,R.andTilley,N.(1997).RealisticEvaluation.London:Sage.
Perera,I.,andKrishnamoorthy,M.(2016).DemocracyinPost-WarSriLanka(Rep.No.3).Colombo:
CPA.
Prescription,SpecialProvisions,(20016).Act.No.5.SriLanka:DepartmentofGovernmentPrinting.
Ranawana,Anupama(2017).“TheLongandWindingRoad:Anevaluationofpeacebuildinginpost-
warAmpara”.ReportpreparedbyCEPAforHelvetas.
Samararatne, Dinesha (2017). “The Quest for Transitional Justice in Sri Lanka”. HarvardWorking
Papers.
Thaheer,Minna,PeirisPradeep.etal,ReconciliationinSriLanka:VoicesfromtheWarZones-2013(reprintedin2014).Colombo:InternationalCentreforEthnicStudies.
UnitedNationsDevelopmentProgramme(2016)."PeacebuildingPriorityPlan(2016-2018)”.Available
at <http://www.unpbf.org/wp-content/uploads/Sri-Lanka-Peacebuilding-Priority-Plan-August-2016-
final.pdf>.AccessedonAugust3,2018.
UnitedNationalPeacebuildingSupportOffice(PBSCO)/PeacebuildingFund(PBF),IRFProject
Document.ProjectStartDateFebruary1,2016.
Uyangoda,Jayadeva(2017).“ReconciliationandTransitionalJusticeinSriLanka”,Talkgivenatthe
InternationalCentreforEthnicStudies,Colombo.
Uyangoda,Jayadeva(2010).SriLankain2009:FromCivilWartoPoliticalUncertainties.50(1)AsianSurvey104,104–11.
Westhrop, Gill (2014). “Realist Impact Evaluation: An Introduction”. September 2014. London:
MethodsLab.
![Page 52: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/52.jpg)
52
AnnexuresAnnex01WorkPlan
Activity 08/1 08/2
08/3
08/4
09/1
09/2
09/3
09/4
10/1
10/2
SubmissionofInceptioneport 6th
UNinternalreviewofInceptionReport
Secondarydocumentationandpolicyreview*
FieldworkinColombo(KPIsonly)
FieldworkinNorthandEast(KPIsonlyWorkshops)
WritingandAnalysisofDraftLessonsLearntReport
SubmissionofDraftFinalReport 14th
UNInternalReviewofdraftFinalReport
UNSubmissionofFeedbackondraftFinalReport 26th
Validationmeetingandpresentationofresults 28th
SubmissionFinalreport 15th
![Page 53: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/53.jpg)
53
Annex02DocumentsRequestedandReceivedforEvaluation
DocumentsRequested Received Missing
ProjectDocumentsof1&2 30thJuly Allmid-termevaluationreportsofProject1and2
Notconducted
LogframeAnalysisintheproposal 30thJuly P1&2Annualworkplanandfinancialbudgets
1stAug(partialAWPprovided)
SCRM–AWP/BudgetsforDec2016-Apr2017ONUR–allAWP/BudgetsafterAug2016
P1&2Annualreportsanddonorreports
1stAug
P1&2SteeringCommitteemeetingminutesandassociatedreports
1stAug-PBFBoard1st&3rdmeetingminutes
AllTechnicalWorkingGrouporProjectSteeringCommitteeminutesforP1&P2
UNDP’sCountryProgrammeDocument
1stAug
MOUswithImplementingPartnerInstitutions
1AugReportsonLOAs
LOA/MOU
PeacebuildingPriorityPlan 1stAug StrategicPlansDevelopedbytheNorthernProvincialadministrationandEasternProvincialadministration(Project2Output1)&DistrictPlansofJaffna,Mullaitivu,Kilinochchi(North)andTrincomalee(East)
NorthernProvinceStrategicPlan:NotsubmittedEasterProvinceStrategicPlan:Submitted.DistrictPlans:OnlyJaffna-Submitted
AnydocumentationProofforProducingandstrengtheningrevenuegenerationtosupportdevelopmentactivities(Project2Output2)
Notsubmitted
ComprehensiveDistrictDevelopmentPlan(ONUR)
N/A
PowerPointpresentedtotheUNonthePPFfront.(SCRM)
Notsubmitted
CommunicationMaterial NotsubmittedNationalPBPerceptionSurvey 1stAug
![Page 54: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/54.jpg)
54
Annex03ActivityPlan
TheActivityPlanincludedsecondarydocumentreview;qualitativeandquantitativedatacollectionandtheanalysisbasedontheproposedframeworksofRealistImpactEvaluationandDACmethod.The findings from thevarious tools and the literature reviewwereused to triangulate theoverallconclusions, lessons learned, recommendations for moving forward and possibly guidelines forreplication.
i. SecondaryDocumentReview–This includedananalysisof theprojectdocuments,projectreports,steeringcommitteeminutes,monitoringandevaluationreports,consultationreportsetc.Dueconsideration to the time limitationswasgiven.TheTeamalsodrewuponCEPA’sinstitutionalknowledge,informationandunderstandingoftheresettlementandreconciliationworkintheNorthandtheEastundertakenonbehalfoftheUN,UNDPandUNICEFtofurthercontextualizeandbuildupontheanalysis.
ii. DataCollection – Thebasic project document reviewand thedata collection actionswereconducted simultaneously. Interviews with partners, stakeholder organisations and othercounterpartsusingtheagreedmethodology,toolsandquestionsintheinceptionphasewereconducted. These involved: Key partner interviewswith stakeholders and key project stafffromUNDP,SCRMandONUR.OneworkshopwasconductedintheEasternProvince(insteadoftwo,initiallyenvisagedtobecarriedoutinboththeNorthandtheEast)withtherelevantProvincialSecretariatstaff,Chief/DeputyChiefSecretaryPlanning,Secretary,FinancePlanning,relevant provincial councilors, District Secretariat staff i.e. Divisional Secretaries, DirectorPlanningandifrequiredwiththerelevantDistrictSecretariataswellascommunitymembersandbeneficiaries.Carewastakentosolicit theexperiencesof femalecommunitymembersandcouncilors.ItwasdecidednottoholdaworkshopintheNorthastheProvincialPlanandtwoDistrictPlanswerenotpreparedcontrarytotheinformationintheprojectdocuments.Hence,onlyKPIswerecarriedoutintheNorthwiththestakeholders.
iii. AnalysisandEvaluation–Thestudy teamcollated the information, secondaryquantitativedata,casestoriesandothermaterialcollected,toanalyzethefindingsofthestudyusingtheagreedmethodologicalframeworks.
iv. DraftReport –Thestudy teamdrafted the report for thispurpose, keeping inmindstatedexpectationsandmethodological frameworks.TheDraftReportwassubmittedfor informalpeerreviewatCEPAbeforethedraftwasfinalizedforsubmissiontoUNDP.
v. Validation–Followingfeedback,thestudyteampresentedthedocumentanditsfindingsatavalidationmeeting,hostedbytheUNDP’sJointteam.Themainfindingsandrecommendationswere presented in an elaborative interactive manner conducive for constructive lessonslearning.
vi. FinalLessonsLearntReport–ThedocumentwasfinalizedusingthefinalroundofcommentsreceivedfromthevalidationandsubmittedbacktoUNDP/ResidentCoordinator’sOfficeasperagreedstipulations.
![Page 55: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/55.jpg)
55
Annex04FlowofActivitiesandDataCollectionInstrument
DataCollectionInstrument:DraftSemi-StructuredQuestionsforInterviewwithProjectPartners/
Stakeholders
ForSCRM
ContextRelatedQuestions
• As youunderstand it, howdid SCRMcome intobeing? (Probe:Whatwas the contextbehindtheintervention?Whatwerethecontextualassumptionsmade?)
• Why did such a project architecture make sense?What other ideas were discarded?(Probe:Otherconflicttransformationtheoriesandthinking?Whatreallywenton?)
• Had the context for peacebuilding and reconciliationbeendifferent, (similar to2009),would these assumptions have been valid? (Probe: How would the mechanism havelookeddifferent?Whatwoulditlooklikein2020?)
• WasthePPPalignedwiththeSriLankangovernment’speacebuildingandreconciliationpriorities?
Ontology
Socialactionshaveanunderlyingmechanismthatspringfrompeoplesreasoningtomobilizeresourcesinaparticularcontextforthoseactions
Analysisofcontext-mechanismassociationhelps
• bringelementsintotheprogrammeblueprint/programmetheoryoffutureprojects
• Innovate/transformfutureinterventions
Epistemology
Testingthetheorybehindtheregularityofacourseofsocialaction
Activities
• SecondaryDocumentandPolicyReview
• KeyPersonInterviews• StakeholderWorkshop
Method
RealistImpactEvaluationFramework
+theOECD-DACApproach.
(Anevaluationofprogrammingtheoryto
understandthe“context-mechanism*-outcome”aspectsofProjects1and2.)
*
![Page 56: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/56.jpg)
56
• InthedesignoftheSecretariat,wasthesocio-politicalsituationofallprovincestakenintoaccount?(Probe:Howso?Canyoutellmeanyparticularities?Whatwasdiscarded?)
• What could have been the features (i.e. Individuals/Institutions) of the context thathelpedtheprojecttoachieveitsoutcome?
• Accordingtoyou,whatwerethreekeythingsthatworkedinthisgivencontext?
• Similarly,whatwas onemain thing that did notwork,when considering the context?(Probe:Perhapsmorethanonething?)
• InthedesignoftheSecretariat,inwhatparticularwaysweretheissuesofwomentakenintoaccount?Wasiteffective?
OutcomeRelatedQuestions
• Is there any generalizable knowledge that you wish to share based on this projectimplementationprocess?
ForONUR
ContextRelatedQuestions
• HowdidONURfirstinitiateitspartnershipwiththeUNPBF?(Probe:Whatwasthecontextbehindtheintervention?Whatwerethecontextualassumptionsmade?)
• WhatwasthevalueadditionthattheUNPBFbroughttoONUR?(Examples)
• Whydidsuchapartnershipmakesense?HowdiditaffectONUR’sapproachtoconflicttransformation?
• What could have been the features (i.e. Individuals/Institutions) of the context thathelpedtheprojecttoachieveitsoutcome?
• InthedesignoftheONUR-PBF,wasthesocio-politicalsituationofallprovincestakenintoaccount?
• InthedesignofONURwhatparticularwayswastheissuesofwomentakenintoaccount?Wasiteffective?
• Accordingtoyou,whatwerethreekeythingsthatworkedinthisgivencontext?
• Similarly,whatwas onemain thing that did notwork,when considering the context?(Probe:Perhapsmorethanonething?)
OutcomeRelatedQuestions
• Is there any generalizable knowledge that you wish to share based on this projectimplementationprocess?
• WouldONURbeabletocarryoutitsworkinadifferentcontext?
ForProvincialCouncils/DistrictSecretariats
ContextRelatedQuestions
• Whatwasthecontextin2015thatenabledPBFtoworkwiththeProvincialCouncils,thatwasnotconducivein2009?
• WhatwasthevalueadditionthattheUNPBFbroughttoProvincialCouncils?(Examples)
![Page 57: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/57.jpg)
57
• Whywas a development plan necessary in this context? How is it different fromUthuruVasantheya and Nagenahira Udanaya? Does the current development plan incorporateelementsfromoldernationalplans(i.e.formergovernmentinitiativesfortheprovinces)?
• Whatcouldhavebeenthefeatures(i.e. Individuals/Institutions)ofthecontextthathelpedtheprojecttoachieveitsoutcomesintheNorthandEast?
• In the design of the partnership between the Provincial Councils and the PBF, how wascontextualinformationgathered?
• Howwasthesituationofwomenfactoredin?
• Whatare theuniquechallenges thatwomen face in thisdistrict/province that theprojectattendsto?Areyousatisfiedwiththeinterventions?Doyoufeelitwaseffective?
• Accordingtoyou,whatwerethreekeythingsthatworkedinthisgivencontext?
• Similarly,whatwasonemainthingthatdidnotwork,whenconsideringthecontext?(Probe:Perhapsmorethanonething?)
OutcomeRelatedQuestions
• Is there any generalizable knowledge that you wish to share based on this projectimplementationprocess?
• Doyoufeelthatthecompetenciesofthestaffemployedwasadequatetocarryoutthiswork?
• Whatresourceswouldyouneedtocarryoutthisworkinotherprovinces?How?
ForProgrammaticStaffatONUR/SCRM
MechanismRelatedQuestions
• HavetheONUR,SCRMandMinistryofLocalGovernmentandProvincialCouncilsandotherpartnerinstitutionsachievedtheirintendedresultsofPROJCT1and2?
• Probebasedonresultsframeworkonimpactandsustainability(positive,negative,neutral)
• Inyouropinion,hasthePPPbeensuccessful?Didyoufeeladequatelyconsultedwithregardstoitsdevelopment?Didyoufeelitincorporatednationalinterestssufficiently?
• YoureceivedtechnicalandfinancialassistanceforavarietyofactivitiesthroughtheUNDP.(Probe:Illustratewaysinwhichitassistedyourprogrammingtobesuccessful?)
• Wasthisassistancehelpful?Relevant?Pleaseexplainhow
• What was the gender focused activities that were undertaken? Are you satisfied withconsultation/participationinactivities?Whatcouldhavebeendonebetter?
• Andhowitimpacteduponthecommunitiesyousupported?(positive/negative/neutral)
• Howwouldyoudothingsdifferentlynexttimearound?
• Did technical assistance adapt to the fluctuating conditions in the context? Please explainhow?
• Basedon thecontextwediscussed,doyou feel that the technicaland financialassistancereceivedwasadequatetocounterthecontextualbarriersanddeficiencies?
• TowhatextentdidUNDP’sinterventionstargetedpeacebuildinginthewar-affectedregionsandtherestofregionsofthecountryinachievingOutput1,2and3ofPROJECT1?
• Wereyousatisfiedwiththecostsandbenefitsoftheinterventions?
![Page 58: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/58.jpg)
58
• Was it in reasonable proportion to the expected outputs? (probe – use figures from resultsframework+financialreports,especiallyrelatedtogender)
• Wereyousatisfiedwiththeproportionalfinancialbreakdownbetweenvariousactivities;betweeninputcategories?(egcontractualservicesvsgrants)
• Weretechnicalassistanceandfinancesprovidedinatimelyandcosteffectivemanner?
• Did itallow/facilitatesequentialbuildingof interventions?Did itallowforsynergies?(probe–Howitworked)
ForUNDPStaff
ContextRelatedQuestions
• HavetheONUR,SCRMandMinistryofLocalGovernmentandProvincialCouncilsandotherpartnerinstitutionsachievedtheirintendedresultsofProject1and2?
• TheUNDPprovidedtechnicalassistanceforresearch,analysis,andawidevarietyofactivitiestoSCRM/ONUR/PCs.Howwerethesedelivered?Didyoufeeltheyweresuccessfullydone?Whatcouldhavebeenimproved?(Probe:Forexample,howwasthestrategicanalysisandtrackingofPBinitiativesmappingundertaken?)
• Howwellwouldyouevaluatetheflowofcommunicationbetweenthedifferentparties(ThePBFSecretariat,thePBFboard,ExecutiveBoardandIRF/PBFTechnicalCommittees)?
• Doyoufeeltheactivitiesdesignedwereadequatetomeettheexpectedoutputs?
• CouldyouexplainthecoordinationfunctionsandthecapacitydevelopmentthatIRFandPBFprovidedtoimplementingagencies?
• Could you explain theways inwhich the RCO communication unit disseminated the bestpracticesoftheIRFandPPPtothePBFpartners,especiallySCRM?
• Weunderstandthatanationalsurveyonpeacebuildingwasconducted. Howwelldidthisfeedintonationalpolicymakingand,inparticular,thedevelopmentandactivitiesofSCRM?
• What was the mechanism that you used to deliver the programme strategies (inputs/resources?)
• Howdidyouleverageprogrammemechanismagainstbarriersinthecontext?
• Wereresourcesprovidedadequatetotheexpecteddeliverablesoftheproject?
• TowhatextentdidUNDP’sinterventionstargetedpeacebuildinginthewar-affectedregionsandtherestofregionsofthecountryinachievingOutput1,2and3ofProject1?
• Towhatextentwerethecostsandbenefitsoftheinterventionsinreasonableproportiontothe expected outputs? (probe – use figures from results framework + financial reports,especiallyrelatedtogender)
• Were you satisfiedwith the proportional breakdown between various activities; betweeninputcategories?(egcontractualservicesvsgrants)
• Canyoudescribehowthegenderallocationwasutilized?Wasiteffective?
• Wereservicesprovidedinatimelyandcosteffectivemanner?
• Diditallow/facilitatesequentialbuildingofinterventions?
• Is there any generalizable knowledge that you wish to share based on this projectimplementationprocess?
![Page 59: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/59.jpg)
59
General
MechanismRelatedQuestions
• Whatwasthemechanisminyouropinion,thatinfluencedtheconfidenceofthecommunitiesthatyouworkedwith?
• Howdidthishappen?(Probe–onthings-people/places-outsidetheresources&strategies)
• Whatmechanismhasbeenusedtomeasuretheimpactoftheactivitiesonpeople?whatwerethefindings?
• Doyoufeelthetechnicalandfinancialassistanceprovidedforthetaskswereadequate?
• Weretheyqualifiedpersonneltocarryouttheinterventions?
• Howwouldyouevaluatetheimpactmadeongenderspecificissues?
• Whatweretheparticularprogrammingelementsthatfocusedonthesituationonwomenandgirls?(probe–howitworked)
OutcomeRelatedQuestions
• Doyoufeeltheproject(s)adaptedtothefluctuatingconditionsinthecontext?Pleaseexplainhow?
![Page 60: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/60.jpg)
60
ProvincialWorkshopFormat
Agenda:September6,2018(9am–1pmtobeconductedinTamilorEnglish)
• WelcomeandIntroductiontotheLessonsLearnedExercise(30minutes)
• FocusGroupDiscussionandGroupWork(3andahalfhours)
-FocusGroupDiscussion:(9:30:10:30a.m.)
-GroupExercise:(10:45a.m.to1:00p.m.)
• VoteofthanksandEndofSessionwithLunch
DetailsoftheAgendaoftheWorkshop
1. WelcomeandIntroductiontotheLessonsLearnedExercise(30minutes)
2. FocusGroupDiscussion
(ContextRelatedQuestions)
Ø TellusaboutthecontextinwhichyoustartedtoworkwiththeUNDP.
Ø Briefly explain work carried out for UNDP from your respective Depts? (How did yourrespectiveDepts.benefitfromtheseactivities?)Giveusexamples
Ø Howdiditfulfillyourcommunity’sneeds?Telluswhatchangeyouwitnessnowcomparedtobeforetheinterventions,withtheintroductionofTechnicalAssistance,Training?EnhancedITfacilities.Cross-regionalvisitsandlearnings?
(MechanismRelatedQuestions)
Ø HowhastheassistancereceivedfromtheUNDPhelpedtheProvincialAdministrationtoimprovecapacityforservicedelivery?
Ø Howdoyouthinkthisbenefitedthepeople?Giveusexamples.Ø Weretheseactivitiescosteffective?(Probe:Perhapsmorethanonething?)Ø Were the strategies helpful? Were theresources for the activities adequate?Were there
qualifiedstafftocarryontheinterventions?Ø Werethereadequatewomen’sparticipation?Howdidyouassesstheirinvolvement?
(Beneficiariescanbeencouragedtospeakmoreonthis)
Tea/CoffeeBreak
3. GroupWork
(OutcomeRelatedQuestions)
FOLLOWINGQUESTIONSAREBASEDONTHEFACILITIESEXTENDEDBYTHEUNDPTOTHEPROVINCIALCOUNCILSANDDISTRICTSECRETARIATS)
(Postitactivity–whereeachgroupmemberwritesoutthe3thingsthatworked(1color)and1thingthatdidn’twork(color2).Thenasagrouptheyprioritizethelesson;anddiscusswhythesearethepriorities.)
1. Accordingtoyou,whatwerethreekeythingsthatyouareawareofthatworkedwell(whenconsideringtheregionalcontext:funds;qualifiedstafforgenderparity)withtheUNDP’s interventionswithregardstoDevelopmentPlans,Strengthening InstitutionalCapacityenhancementsforgoodgovernance?
![Page 61: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/61.jpg)
61
2. Whatarethe3thingsthatdidnotwork,(whenconsideringtheregionalcontext:funds;qualified staff or gender parity) with the UNDP’s interventions with regards toDevelopmentPlans,StrengtheningInstitutionalCapacityenhancementsetc.?
3. Arethereanyotherlessonthatyouwishtosharewithusforfuturework?
EndofSessionwithLunch
![Page 62: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/62.jpg)
62
Annex05ListofIntervieweesandParticipantsattheWorkshop
UN/UNDP
1. ProgrammeCoordinationSpecialist,Ms.DushanthiFernando2. ProjectManager,Mr.MohamedMuzain3. TechnicalSpecialist,Ms.KrishaVelupillai4. AdvisorPeacebuildingandDevelopment,Ms.GeetaSabarwal5. ProgrammeAnalyst-Governance(former),Ms.AmanthiWickremasinghe6. UNPBSODeskOfficer,MrPatriceChiwota7. PeacebuildingSpecialist(former),MsZoeKeeler8. PsychosocialAnalyst(WHO),Ms.SandhaniRajapakse
SCRM
1. DirectorGeneral–Mr.ManoTittawela2. DirectorPBB-Mr.TharakaHettiarachchi
ONUR
1. DirectorGeneral-Mr.Jayasinghe2. FormerDG–Mr.Maliyadda3. Director–Mr.Amb.DaneshCasieChetty4. DeputyDirectorPeacebuilding-Ms.SanduniAriyawansa
MinistryofLocalGovernmentandProvincialCouncil
1. AdditionalSecretary–Mr.BoralessaNorthernProvincialCouncilandJaffnaDistrictSecretariat
1. ChiefMinister,NorthernProvincialCouncilHon.JusticeC.V.Wigneswaran,2. ChiefSecretary,NorthernProvincialCouncil,Mr.A.Pathinathan.3. Director,Planning,ProvincialCouncil,Mr.Umakanthan.4. Commissioner,DepartmentofMotorTraffic,Ms.S.Sujeeva.5. DeputyChiefSecretary,PersonnelandTraining(MDTU),Mr.A.Sivabanasundaran.6. CommissionerforLocalGovernment,Mr.PatrickDiranjan.7. DistrictSecretary,JaffnaDistrictSecretariat,Mr.N.Vethanayahan.
OtherStakeholderKPIs(CivilSocietymembers)
1. Independent Consultant, Member of the Board of Office on Missing Persons, Mr. MirakRaheem.
2. FormerDeputyChiefSecretaryPlanning,EasternProvincialCouncilMr.N.Mahendraraja.3. HeadofZOAinternational,INGORepresentative,UNPBFBoardMr.RagaAlphonsus.
ParticipantsattheWorkshopintheEasternProvincialCouncilonSeptember6,2018
1. AdditionalDirector,Planning,Mr.M.Munazir2. CommissionerLocalGovernment,Mr.M.YSaleem3. ProvincialDirector,Dept.ofRuralDevelopment,Ms.U.Kavitha4. DeputyChiefSecretary,ProvincialTreasury,Mr.I.MHuzain
![Page 63: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/63.jpg)
63
5. DeputyChiefSecretary–PersonnelandTraining,Ms.J.J.Muralitharan6. Commissioner,MotorTraffic,Mr.M.I.M.Mahir7. DeputyDistrictPlanningOfficer,DistrictSecretariat,Trincomalee-Ms.Vijayathasan8. FormerProjectCoordinatorUNDP-GLED,MsB.Sivapiragasam9. Director(MDTU),Ms.M.MHalida10. Govt.VeterinarySurgeon,Dept.ofAnimalProductionandHealth,Dr.Ms.N.S.M.Nawsath11. ChiefAccountant,ProvincialTreasury,Mr.B.Konesh12. FarmManager,DDA(Ext)office,Trincomalee,Mr.J.JeizelJazaad13. DirectorPlanning,PPS,Mr.P.Gunaretnam14. AssistantDirectorPlanning,PPS,Ms.V.I.G.Johnpillai15. Beneficiaries16. Women’sRuralDevelopmentSociety(WRDS),Kaluwanchikudy,Ms.S.Srimathy17. WRDS,Kaluwanchikudy,Ms.M.Sunitha18. WRDS,Kaluwanchikudy,Ms.S.Nivaharan19. WRDS,Thampalakamam,Ms.T.Vijayaluxmi
![Page 64: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/64.jpg)
64
Annex06TermsofReference
INDEPENDENT LESSONS LEARNED EXERCISE ON PEACEBUILDING EFFORTS IN SRI LANKA BY
ASSESSINGTWOPROJECTS;
Project1:“SupporttoSriLankatopromotenationalunityandreconciliationeffortsthroughtargetedtechnical assistance to ONUR and the Northern Provincial administration and Eastern Provincialadministration”
Project2:SupporttotheSriLankaPBFSecretariatandGovernmentSecretariatforCoordinationofReconciliationMechanisms.
Reportsto:TechnicalSpecialist–TransitionalJustice–UNDP�ProgrammeCoordinationSpecialist–Peacebuilding–UNRCO
DutyStation:Colombo,SriLanka.Suggestedtraveltotheprojectsitesnecessarytoimplementthelessonslearnedtobespecifiedintheproposal
TypeofContract:ContractforGoodsandServices
Languagerequired:English
DurationofAssignment:02Months
ContractStartDate:July/September2018
ApplicationDeadline:�6July/September2018
1.BACKGROUNDANDINTRODUCTION:
InJune2015,SriLankabeganaccessingtheImmediateResponseFacility(IRF)ofthePeacebuildingFund through a joint project developed and submitted by UNHCR and UNICEF to support theresettlementofIDPstolandreleasedbythenewGovernmentfromformerHighSecurityZones.Later,inlinewithanIRFconceptnotewhichisagreedbetweentheGovernmentandtheUNinApril2015,workbeganonthreemoreIRFprojects.Outofthesethreeprojects,onetobeledbyOHCHRinsupportoftheaccountabilityandtransitionaljusticeprocess,andasecondoneledbyUNDPandtheRCOin“support to the Sri Lanka PBF Secretariat and the Government Secretariat for Coordination of
ReconciliationMechanisms”(hereinreferredtoastheProject1),tosupportthejointpreparationofthePeacebuildingPriorityPlan.Thethirdprojecttitled“SupporttoSriLankatopromotenational
unityandreconciliationeffortsthroughtargetedtechnicalassistancetoONURandtheNorthern
ProvincialadministrationandEasternProvincialadministration”(hereinreferredtoastheProject2)was implementedbyUNDPand included specialized technical assistance to theOfficeofNationalUnityandReconciliation(ONUR),andeachoftheNorthernandEasternprovincialadministrations.Inthisassignment,theUNDPrequirestoconductacompleteindependentlessonlearntforsomeparts
![Page 65: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/65.jpg)
65
ofProject1andtheentireProject2.
Followingaseriesofeventsthattookplaceinthecountry’spoliticaltransition,theProjectsweresetuptosupporttheStatetoprogressitspeacebuildingandreformsagendainthecountry-apledgethat formed the basis of both the President’s electionmanifesto aswell as the campaigning thatpreceded the electionof theNationalUnityGovernment. This pledge also transpired into the co-sponsoringofUNHRCResolution30/1,“Promotingreconciliation,accountabilityandhumanrightsinSri Lanka.” Thus, through these projects, the UN aimed at supporting the State, across multipleinstitutionsthatweresetuporstrengthenedtopromotepeacebuildingandreconciliationinSriLanka.
2.SCOPEANDOBJECTIVES
THEPROJECTS:
The scope and objectives of the afore mentioned projects have been described in the “ProjectDocuments”asfollows;
Project1:
AlthoughtheProject1iscomprisedwith2Outcomes,thescopetoconducttheindependentlessonslearntexerciseinthisprojectislimitedonlytoOutcome1.
Outcome1–UnitedNationsPeacebuildingSupportinSriLankaisstrategicallypositionedtosupportnationalpriorities,arrivedatthroughafullyconsultativeandinclusiveprocess,andiseffectively
deliveredinacoordinatedandharmonizedmanner
The relevant Outputs to be considered are as follows:�Output 1 – Peacebuilding Priority Plandeveloped and mechanism established to support coordinated project development andimplementation�Output 2 – Effective implementation of the UN’s Peacebuilding initiatives, withattention to coordination, evidenced based interventions and high-impact results�Output 3 –SecretariatforCoordinatingtheReconciliationMechanismsestablishedwithinthePrimeMinister’sOffice to ensure coordinated and coherent Government strategy to progress reconciliation anddevelopandimplementtransitionaljusticemechanisms
Project2:
Project2hasonlyoneOutcomewhich shouldbe considered completely.�Outcome1 -“Sri Lankasocietywithawell-coordinatedandcoherentsystemtoadvancenationalunityandreconciliation
amongitspeople.”
The related Outputs are as follows:�Output 1: Key mechanisms and processes (elements of aroadmap)fornationalunityandreconciliationcommencedundertheguidanceofONUR
Output 2: Northern Provincial administration and Eastern Provincial administration enabled toproducestrategicplansandstrengthenrevenuegenerationtosupportdevelopmentactivitiesthataddresstheprioritiesofconflictaffectedpeople.
![Page 66: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/66.jpg)
66
THEASSIGNMENT:
Againstthebackground,theUNislookingtocommissionanindependentthird-partylessonlearnedexercise of the Projects’ performance, that would provide evidence of the project’s relevance,efficiency,effectiveness,impactandsustainabilityinachievingitsobjectives.
1.Relevance:Theexercisewillassess thedegreetowhichtheproject takes intoaccount the localcontext anddevelopmentproblems. Theexercisewill also review theextent towhich theprojectdesignwaslogicalandcoherent,anditwillassessthelinkbetweenactivitiesandexpectedresults,andbetweenresultsandobjectivestobeachieved.2. Effectiveness: The exercise will assess the extent to which the Project's objectives have beenachieved,comparedtotheoverallprojectpurpose.Inevaluatingeffectiveness,itisusefultoconsider:I) if theplanningactivitieswereconsistentwith theoverallobjectivesandprojectpurpose;2) theanalysisofprincipalfactorsinfluencingtheachievementornon-achievementoftheobjectives.��3.Efficiency:Usinga rangeof costanalysisapproaches, fromtheelaboratecost-effectivenessandcost-benefitanalysis,tocost-efficiencyanalysis,toaquickcostcomparison,theexercisewillassesshowwelldidtheprojectproducetheproductsandservicesitcommitteditselftodeliver;howdocostsaffectthesustainabilityoftheresults;4.Impact:TheexercisewillassessanycredibleevidenceandthemainimpacteffectivelyachievedbytheProjectinthecontextofreference.5.Sustainability:Theexercisewillassesstheprojectcapacitytoproduceandtoreproducebenefitsovertime.Inevaluatingtheprojectsustainability,itisusefultoconsidertowhatextentinterventionbenefitswill continueevenafter theproject is concludedand theprincipal factors influencing theachievementornon-achievementoftheprojectsustainability.Additionally, and outside of the core projects results frameworks, the exercise will also aim atassessing the design logic of the projects.�Particular emphasis should be set to includerecommendations thatwouldhelp informboththedesignof future interventionsaswellasguideongoingprogrammingundertheframeworkofthePPP.Specifically,inregardtointerventionsfundedbythePeacebuildingFund(PBF),whichhavebeendesignedtotakeforwardsomeoftheinitiativesandlogicbehindtheprojectunderreview.(Pleasereferthescopeofwork,enclosed)
3.RESPONSIBILITIES–EXPECTEDOUTPUTSANDDELIVERABLES
EXPECTEDOUTPUTS:
1.Aninceptionreportisproducedoutliningtheworkplan,methodologyandagreedon.Theconsultingcompany/firmshoulddevelopaverycomprehensiveinceptionreportwhichshouldincludetheworkplan,methodology,keyquestionsplannedtobeaskedtothestakeholdersandthejustificationfortheproposedapproach.Thereportshouldnotbemorethana10pagerwithfontsize11.2.AcompletefinallessonlearntreportisproducedandpresentedtotheUNjointteam.AdraftreportshouldbedevelopedandpresentedtotheUNDP/UNRCOfor initialcommentsandfeedbacks.Thereafter,avalidationsessiononthefindingsandrecommendations,usinganinteractivepresentationshouldbeconductedtotheUNJointteam.Thefinalreportshouldhaveincorporatedallthefeedbacksandcommentsandsubmitted.
![Page 67: Final Report on Lessons Learned Exercise on UN:UNDP ......end of the second year of its interventions, the UNDP commissioned an evaluation of Projects 1 and ... project management](https://reader034.vdocuments.us/reader034/viewer/2022042306/5ed25033e0d2e942d71afc17/html5/thumbnails/67.jpg)
67
DESCRIPTIONOFASSIGNMENT/DELIVERABLES:
Tasks EndProduct/ Approximate
deliverables Timeframe
InceptionReport:Workplanandmethodology/approachforthelessonslearnedexercisewithsufficientjustificationtobeincludedwithmethodsofdatacollection,keyquestionsandtimelines.
Inceptionreport
10August2018
DraftLessonsLearnedReportsharedforcomments/feedback. Draftreport14September
2018
ValidationsessionwithUNJointteam:Apresentationofmainfindingsandrecommendations,usinginteractivemethodology. Presentation
28September2018
Finallessonslearntreport–incorporatedfeedbacksfromValidation
FinalReport12October2018(made on 15October,2018)