final report cie619
TRANSCRIPT
1
REPORT OF EXAMPLE 5 BRIDGE PLACED ON A SITE IN TACOMA
Eight-Span Continuous Steel Girder Curved Bridge
Group 6 Course: CIE 619
Structural Dynamics and Earthquake Engineering II
Report Prepared by: Lemuria Pathfinders
Supratik Bose
Sathvika Meenakshisundaram Sharath Chandra Ranganath
Sandhya Ravindran Amy Ruby
2
ACKNOWLEDGEMENTS Lemuria Pathfinders would like to acknowledge that this seismic bridge design
has been adapted from design example 5 in the US Department of
Transportation Federal Highway Administrations Seismic Design of Bridges,
from October 1996. In addition, the original nine span viaduct steel girder bridge
was prepared by BERGER/ABAM Engineers Inc.
-o-o-o-
3
TABLE OF CONTENTS
ACKNOWLEDGMENTS ................................................................................................. 2
LIST OF TABLES ................................................................................................................. 4
LIST OF FIGURES .................................... .......................................................... 5
CHAPTER
1. UNIFORM LOAD METHOD – ELASTIC ANALYSIS ............................................. 12
1.1 General Description of Bridge ............................................................................... 12 1.1.1 Structural System ................................................................................................. 13 1.1.2 Superstructure ...................................................................................................... 14 1.1.3 Substructure ......................................................................................................... 15 1.1.4 Location of Bridge................................................................................................ 17 1.1.5 Site Conditions ..................................................................................................... 18
1.2 Objectives .................................................................................................................. 18
1.3 Modeling Description ............................................................................................. 19 1.3.1 Superstructure ...................................................................................................... 19 1.3.2 Substructure ......................................................................................................... 22
1.4 Initial Elastic Analysis ............................................................................................. 27 1.4.1 Uniform Load Method ........................................................................................ 27 1.4.2 Results and Discussions ...................................................................................... 28
1.5 Summary and Conclusions .................................................................................... 37
2. MODAL ANALYSIS, DEVELOPMENT OF RESPONSE SPECTRA AND SCALING OF GROUND MOTIONS ........................................................................... 39
2.1 Introduction .............................................................................................................. 39
2.2 Eigen Value Analysis .............................................................................................. 39 2.2.1 Natural Periods and Mode Shapes of Structure .............................................. 42 2.2.2 Higher Modes associated with Vibration of Piers .......................................... 44 2.2.3 Comparison with Elastic Analysis Results in SAP 2000 ................................ 45 2.2.4 Analytical Calculations of Bridge Stiffness along local directions ............... 47 2.2.5 Analytical Calculations of Bridge Stiffness along global directions ............. 52
2.3 Response Spectra ..................................................................................................... 54 2.3.1 Seismic Design Spectra ....................................................................................... 55 2.3.2 Seismic Design Spectra of our Site .................................................................... 56
4
2.3.3 Ground Motion Selection ................................................................................... 58 2.3.4 Development of Response Spectra and Scaling of Ground Motions ........... 58
2.4 Development of SDoF Model ................................................................................ 60 2.4.1 Modeling Assumptions....................................................................................... 61 2.4.2 Analysis Procedure .............................................................................................. 62 2.4.3 Results and Discussions ...................................................................................... 62
2.5 Summary and Conclusions .................................................................................... 64
3. UNIFORM LOAD, DYNAMIC MULTIMODE AND PUSHOVER ANALYSIS . 65
3.1 General Overview ................................................................................................... 65
3.2 Uniform Load Method ............................................................................................ 65 3.2.1 Introduction .......................................................................................................... 65 3.2.2 Analysis Procedure .............................................................................................. 66 3.2.3 Results and Discussions ...................................................................................... 68 3.2.4 Summary ............................................................................................................... 72
3.3 Dynamic Multi-Mode Analysis ............................................................................. 72 3.3.1 Introduction .......................................................................................................... 72 3.3.2 Analysis Procedure .............................................................................................. 72 3.3.3 Results and Discussions ...................................................................................... 77
3.4 Push-Over Analysis................................................................................................. 81 3.4.1 Introduction .......................................................................................................... 81 3.4.2 Description of Model ........................................................................................... 82 3.4.3 Plastic Hinge Model ............................................................................................ 84 3.4.4 Non-linear models for pushover analysis ........................................................ 84 3.4.5 Analysis Procedure .............................................................................................. 89 3.4.6 Results and Discussions ...................................................................................... 93 3.4.7 Comparison of stiffness with analytical results ............................................ 101
3.5 Summary and Conclusions .................................................................................. 101
4. TIME HISTORY ANALYSIS ........................................................................................ 103
4.1 General Overview ................................................................................................. 103
4.2 Selected Ground Motions ..................................................................................... 103
4.3 Linear Elastic Time History Analysis ................................................................. 104 4.3.1 Analysis Procedure ............................................................................................ 104 4.3.2 Results 106 4.3.3 Summary ............................................................................................................. 108
4.4 Non Linear Dynamic Time History Analysis .................................................... 109 4.4.1 Introduction ........................................................................................................ 109 4.4.2 Code Specification ............................................................................................. 109
4.5 Non Linear SDoF Time History Analysis .......................................................... 109 4.5.1 Analysis Procedure ............................................................................................ 109 4.5.2 Results 110 4.5.3 Summary ............................................................................................................. 113
4.6 Non Linear MDoF Time History Analysis ......................................................... 113
5
4.6.1 Introduction ........................................................................................................ 113 4.6.2 Description of Model ......................................................................................... 113 4.6.3 Analysis Procedure ............................................................................................ 114 4.6.4 Results and Discussions .................................................................................... 117
4.7 Summary and Conclusions .................................................................................. 123
5. CAPACITY SPECTRUM AND FLOWCHARTS ...................................................... 124
5.1 General Overview ................................................................................................. 124
5.2 Capacity Spectrum Analysis ................................................................................ 124
5.3 Flowcharts .............................................................................................................. 127
5.4 Summary and Conclusions .................................................................................. 132
6. FINAL CONCLUSIONS................................................................................................ 133
6.1 General Overview ................................................................................................. 133
6.2 Comparison from Various Analysis Procedure ................................................ 133
6.3 Performance of Structure ...................................................................................... 135
6.4 Scope of Future work ............................................................................................ 138
6.5 Recommendations for Improvement of Performance ...................................... 138
7. APPENDIX A – VALIDATION OF MODEL ........................................................ 13340
Validation of Elastic Analysis in SAP 2000 ................................................................. 139 Validation of spring stiffness in SAP 2000 .................................................................. 141 Validation of equivalent concrete rectangular section in SAP 2000 ........................ 143 Calibration of Eigen Value Analysis in SAP 2000 ...................................................... 147 Validation of USGS Ground Motion Information and Response Spectra .............. 150 Calibration of SDoF Model in NONLIN Program ..................................................... 151 Calibration of the Program used for Response Spectrum Development ................ 153 Validation of Pushover Analysis and Fiber PMM hinge in SAP 2000 .................... 160
Validation of Time History Analysis .......................................................................... 1647
8. APPENDIX B – TEAM MANAGEMENT PLAN .................................................. 13368
REFERENCES …....................................................................................................................178
-o-o-o-
6
LIST OF TABLES
Table 1.1 Deflection, moment and shear force along the spans under gravity load 30
Table 1.2 Variation of axial forces in superstructure under gravity load .................. 30
Table 1.3 Deflection, moment and shear force along the spans under transverse load ...................................................................................................................... 33
Table 1.4 Maximum resultant forces along piers under transverse load ................... 34
Table 1.5 Maximum resultant forces along piers under longitudinal load on deck 35
Table 2.1 Natural periods and cumulative mass participation of different modes .. 41
Table 2.2 Modal mass participation of first three modes ............................................. 42
Table 2.3 Comparison of periods of the modified bridge and the FHWA original bridge .................................................................................................................. 44
Table 2.4 Calculation of period of bridge from uniform load method ....................... 47
Table 2.5 Deflected shape corresponding to 2nd mode (Transverse) .......................... 48
Table 2.6 Calculation of overall transverse stiffness analytically................................ 48
Table 2.7 Calculation of overall transverse stiffness analytically................................ 51
Table 2.8 Comparison of stiffness of the piers obtained analytically and in SAP 2000.............................................................................................................................. 52
Table 2.9 Calculation of overall stiffness analytically along global direction ........... 53
Table 2.10 Stiffness and mass used in the development of the SDoF model ............... 54
Table 2.11 Response Spectra parameters obtained from USGS .................................... 56
Table 2.12 Scaled ground motions selected from PEER Database ................................ 60
Table 2.13 Results of time history analysis in NONLIN using elastic linear SDoF models along local directions (longitudinal and transverse) ...................... 63
Table 2.14 Results of time history analysis in NONLIN using elastic linear SDoF models along global directions (X and Y) ...................................................... 63
Table 3.1 Summary of uniform load method results obtained from SAP 2000 ........ 69
Table 3.2 Forces, moments and displacements - 100% EE_Trans + 40% EE_long .... 70
Table 3.3 Forces, moments and displacement - 40% EE_Trans + 100% EE_long ..... 70
Table 3.4 Forces, moments and displacements - 100% MCE_Trans + 40% MCE_long.............................................................................................................................. 71
Table 3.5 Forces, moments and displacements - 40% MCE_Trans + 100% MCE_long.............................................................................................................................. 71
Table 3.6 Forces and moments under dead load ........................................................... 77
Table 3.7 Forces and moments for EE - 100% EE_Long + 40% EE_Trans .................. 78
Table 3.8 Forces and moments for EE - 100% EE_Trans + 40% EE_Long .................. 78
7
Table 3.9 Forces and moments for MCE - 100% MCE_Long + 40% MCE_Trans ..... 79
Table 3.10 Forces and moments for MCE - 100% MCE_Trans + 40% MCE_Long ..... 79
Table 3.11 Displacement under Expected Earthquake ................................................... 80
Table 3.12 Displacement under Maximum Credible Earthquake ................................. 80
Table 3.13 Comparison of stiffness .................................................................................. 101
Table 4.1 Selected Ground Motions .............................................................................. 104
Table 4.2 Mass and stiffness values ............................................................................... 104
Table 4.3 Scaled PGA (g) of respective GMs ................................................................ 106
Table 4.4 Resultant forces and displacements in local directions ............................. 106
Table 4.5 Resultant forces and displacements in global directions .......................... 107
Table 4.6 Resultant forces and displacements obtained in linear elastic time history analysis in SAP 2000 program at EE ............................................................. 107
Table 4.7 Resultant forces and displacements obtained in linear elastic time history analysis in SAP 2000 program at MCE......................................................... 108
Table 4.8 Comparison of maximum values recorded for linear time history analysis in SAP 2000 and NONLIN ............................................................................. 108
Table 4.9 Resultant forces and displacements in global directions .......................... 111
Table 4.10 Resultant forces and displacements in global directions .......................... 112
Table 4.11 Nomenclature used for defining the GMs ................................................... 116
Table 4.12 Maximum resultant forces and displacement recorded at piers during expected earthquake ....................................................................................... 119
Table 4.13 Maximum resultant forces and displacement recorded at piers during maximum credible earthquake ..................................................................... 121
Table 5.1 Comparison of results from various analysis procedure .......................... 126
Table 5.2 Summary of Cc values at EE ........................................................................... 127
Table 5.3 Summary of operational performance level at MCE ................................. 127
Table 5.4 Summary of life safety performance level at MCE ..................................... 127
Table 6.1 Comparison of results from various analysis procedure .......................... 134
Table 6.2 Calculation of R factor at EE and MCE ........................................................ 136
Table 6.3 Performance evaluation of the structure ..................................................... 137
-o-o-o-
8
LIST OF FIGURES
Figure 1.1 Plan View of 8-span continuous; [adapted from FHWA-SA-97-010 Figure 1a] ........................................................................................................................ 12
Figure 1.2 Elevation View of 8-span continuous; [adapted from FHWA-SA-97-010 Figure 1] .............................................................................................................. 13
Figure 1.4 Typical Cross Section; [adapted from FHWA-SA-97-010 Fig 1b] .............. 14
Figure 1.5 Section at Seat-Type-Abutment; [adapted from FHWA-SA-97-010 Fig 1c].............................................................................................................................. 15
Figure 1.6 Intermediate Pier Elevations; [adapted from FHWA-SA-97-010 Fig 1c] ... 16
Figure 1.8 Sliding action of the bearings [adapted from FHWA-SA-97-010 Figure 2].............................................................................................................................. 17
Figure 1.9 Location of the bridge (Source: Google Maps) .............................................. 18
Figure 1.10 Subsurface Soil Conditions; [adapted from FHWA-SA-97-010 Fig A1] .... 18
Figure 1.11 Stick element bridge model in SAP 2000 ....................................................... 19
Figure 1.12 Rigid link element connecting the pier to the superstructure in SAP ....... 21
Figure 1.13 Relationship between actual pier and stick model of 3-D frame elements [adapted from FHWA-SA-97-010] .................................................................. 22
Figure 1.14 Typical view of an intermediate pier in SAP 2000 ....................................... 23
Figure 1.15 Details of sliding bearings at piers [adapted from FHWA-SA-97-010 Figure 10] ............................................................................................................ 24
Figure 1.16 Releases provided in SAP 2000 at top of pier to simulate bearing action . 24
Figure 1.17 Typical plan view of the pile arrangements [adapted from FHWA-SA-97-010] ...................................................................................................................... 25
Figure 1.18 Details of support for spring foundation model [FHWA-SA-97-010 Figure 11] ........................................................................................................................ 26
Figure 1.19 Details of foundation springs in SAP 2000 .................................................... 26
Figure 1.20 Details of abutment supports [FHWA-SA-97-010 Figure 16] ..................... 27
Figure 1.21 Deflected shape of modeled bridge under gravity load .............................. 28
Figure 1.22 Bending moment diagram (major) of modeled bridge under gravity load.............................................................................................................................. 29
Figure 1.23 Shear force diagram (major) of modeled bridge under gravity load ........ 29
Figure 1.24 Settlement of the foundation under pier-1 .................................................... 31
Figure 1.25 Deflected shape of modeled bridge under transverse loading ................... 31
Figure 1.26 Bending moment diagram (major) of modeled bridge under transverse load ...................................................................................................................... 32
Figure 1.27 Shear force diagram (major) of modeled bridge under transverse load ... 32
9
Figure 1.28 Bending moment diagram of modeled bridge under longitudinal load on deck ..................................................................................................................... 35
Figure 1.29 Shear force diagram (major) of modeled bridge under longitudinal load on deck ................................................................................................................ 35
Figure 1.30 Deflected shape of modeled bridge under loangitudinal load ................... 36
Figure 1.31 Bending moment diagram of modeled bridge under longitudinal load on piers ..................................................................................................................... 36
Figure 1.32 Shear force diagram of modeled bridge under longitudinal load on piers.............................................................................................................................. 37
Figure 2.1 Mass source defined for modal analysis in SAP 2000 .................................. 40
Figure 2.2 3D view of the mode shape corresponding to first mode (Longitudinal) 42
Figure 2.3 Plan view of the mode shape corresponding to first mode (Longitudinal).............................................................................................................................. 43
Figure 2.4 3D view of the mode shape corresponding to second mode (Transverse)43
Figure 2.5 Plan view of the mode shape corresponding to second mode (Transverse).............................................................................................................................. 43
Figure 2.6 3D view of the mode shape corresponding to third mode (Torsional) ..... 43
Figure 2.7 Plan view of the mode shape corresponding to third mode (Torsional) .. 44
Figure 2.8 Mode shape corresponding to vibration of pier (4th Mode) ........................ 45
Figure 2.9 Mass Source considering only the weight of the superstructure ............... 46
Figure 2.10 Load applied in local directions for stiffness calculations of 50ft and 70ft piers ..................................................................................................................... 51
Figure 2.11 Displacement recorded in local directions at top of the piers .................... 52
Figure 2.12 Construction of design response spectra using 2-point method [MCEER/ATC 49] ............................................................................................. 54
Figure 2.13 Response Spectra used in the design example .............................................. 55
Figure 2.14 Response Spectra obtained for our site from USGS website for MCE and EE ......................................................................................................................... 57
Figure 2.15 Response Spectra in PEER Ground motion Database .................................. 58
Figure 2.16 Resultant ground motion spectra compared with target spectra in PEER 59
Figure 2.17 Comparison of the mean response spectra of the selected GMs with the target spectra and 85% of target spectra at EE .............................................. 59
Figure 2.18 Comparison of the mean response spectra of the selected GMs with the target spectra and 85% of target spectra at MCE .......................................... 60
Figure 3.1 Distribution of load Po in transverse direction ............................................. 66
Figure 3.2 Distribution of load Po in longitudinal direction .......................................... 66
Figure 3.3 Maximum displacement recorded in transverse direction ......................... 67
Figure 3.4 Maximum displacement recorded in longitudinal direction ...................... 67
Figure 3.5 Response Spectrum function for MCE ........................................................... 74
10
Figure 3.6 Response Spectrum function for EE ............................................................... 74
Figure 3.7 Load case 100 MCE - Long + 40 MCE - Trans ............................................... 75
Figure 3.8 Load case 100 MCE - Trans + 40 MCE - Long ............................................... 75
Figure 3.9 Load case 100 EE - Long + 40 EE - Trans ....................................................... 76
Figure 3.10 Load case 100 EE - Trans + 40 EE - Long ....................................................... 76
Figure 3.11 Column cross-section at base........................................................................... 83
Figure 3.12 Column reinforcement details ......................................................................... 83
Figure 3.13 Pushover Model of the 70 feet pier ................................................................. 84
Figure 3.14 Reinforcement detailing in section designer for the column top section .. 85
Figure 3.15 Reinforcement detailing in section designer for the column bottom section.............................................................................................................................. 85
Figure 3.16 Fiber model of column top in section designer ............................................. 86
Figure 3.17 Fiber model of column base in section designer ........................................... 86
Figure 3.18 Bilinear Stress strain model of concrete ......................................................... 86
Figure 3.19 Non-linear material property of concrete ...................................................... 87
Figure 3.20 Bilinear Stress strain model of rebar ............................................................... 87
Figure 3.21 Material Property input in SAP 2000.............................................................. 87
Figure 3.22 Plastic hinge definition in SAP 2000 program at pier bottom .................... 88
Figure 3.23 Fiber hinge model in SAP 2000 ....................................................................... 88
Figure 3.24 Triangular loading pattern used in SAP 2000 program............................... 89
Figure 3.25 Typical pushover load case in SAP 2000 program ....................................... 90
Figure 3.26 Cross section of the pier considered for Push over analysis ...................... 91
Figure 3.27 Typical plastic hinge assignment at pier bottom in SAP 2000 .................... 92
Figure 3.28 Typical plastic hinge assignment at the column neck in SAP 2000 ........... 93
Figure 3.29 Typical deflected shape of the 70 feet pier in transverse direction ............ 94
Figure 3.30 Force displacement relationship of the 70 feet pier in transverse direction.............................................................................................................................. 94
Figure 3.31 Moment rotation plot of the plastic hinge at the bottom of the 70 feet pier in transverse direction ...................................................................................... 95
Figure 3.32 Typical deflected shape of the 70 feet pier in longitudinal direction ........ 96
Figure 3.33 Force displacement relationship of the 70 feet pier in longitudinal direction .............................................................................................................. 96
Figure 3.34 Moment rotation plot of the plastic hinge at the bottom of the 70 feet pier in longitudinal direction .................................................................................. 97
Figure 3.35 Force displacement relationship of the 50 feet pier in transverse direction.............................................................................................................................. 97
11
Figure 3.36 Moment rotation plot of the plastic hinge at the bottom of the 50 feet pier in transverse direction ...................................................................................... 98
Figure 3.37 Force displacement relationship of the 50 feet pier in longitudinal direction .............................................................................................................. 98
Figure 3.38 Moment rotation plot of the plastic hinge at the bottom of the 50 feet pier in longitudinal direction .................................................................................. 99
Figure 3.39 Typical deflected shape of the pier in transverse direction ........................ 99
Figure 3.40 Force displacement relationship of the bridge in transverse direction ... 100
Figure 3.41 Typical deflected shape of the pier in longitudinal direction ................... 100
Figure 3.42 Force displacement relationship of the bridge in longitudinal direction 101
Figure 4.1 Inputs in NONLIN program for linear analysis along longitudinal direction ............................................................................................................ 105
Figure 4.2 Inputs in NONLIN program for nonlinear analysis along chord direction............................................................................................................................ 110
Figure 4.3 Definition of a time history function in SAP 2000 program ...................... 114
Figure 4.4 Typical Time History Load Case defined in SAP 2000 .............................. 115
Figure 4.5 Type of direct integration procedure followed in SAP 2000 ..................... 115
Figure 4.6 Mass and stiffness coefficients for damping ............................................... 116
Figure 4.7 Definition of mass source for time history analysis ................................... 116
Figure 4.8 Time history load cases defined in SAP 2000 .............................................. 117
Figure 4.9 Maximum displacement response recorded for pier 4 during North Ridge GM ..................................................................................................................... 117
Figure 4.10 Base shear in global X direction with time recorded during North Ridge GM ..................................................................................................................... 118
Figure 4.11 Hysteretic loop of the base shear observed during North Ridge GM ..... 118
Figure 4.12 Hysteretic loop of the plastic moment rotation observed at one of the bottom hinges during North Ridge GM ...................................................... 119
Figure 5.1 Flowchart as applicable to our bridge .......................................................... 131
-o-o-o-
12
CHAPTER 1 1. UNIFORM LOAD METHOD – ELASTIC ANALYSIS
UNIFORM LOAD METHOD – ELASTIC ANALYSIS
1.1 GENERAL DESCRIPTION OF BRIDGE
The bridge being evaluated here is an adapted version of a nine-span viaduct steel
girder bridge, totaling in 1488 feet, presented by a report via the FHWA. The afore-
mentioned bridge has varying span lengths on the left side of the bridge. In addition,
the bridge has expansion joints. The bridge being analyzed in this report is an eight-
span curved continuous bridge, having no expansion joints. The total length of this
bridge is 1384 feet. The eight-spans are a mirror image of the four spans to the right of
the original bridge. All of the properties of the original bridge are mirrored, such that
on each side there are four 173’ spans as shown below in Figure 1.1. The radius of this
curved bridge is 1300 feet. The superstructure consists of four steel plate girders and a
concrete composite cast-in-place deck. The substructure elements, abutments and piers
are all cast-in-place concrete and supported on steel H-piles. The plan and the elevation
views are shown in Figure 1.1 and Figure 1.2.
Figure 1.1 Plan View of 8-span continuous; [adapted from FHWA-SA-97-010 Figure 1a]
13
Figure 1.2 Elevation View of 8-span continuous; [adapted from FHWA-SA-97-010 Figure 1]
1.1.1 Structural System
The structural system of the bridge can be classified into two broader sections:
superstructure and the substructure. The superstructure consists of the deck and the
steel girders while the substructure comprises the abutments and pier columns, pile
foundations and bearings to connect the piers to the girders. The load from the deck is
transferred to the girders which transfer the entire load to the foundation through
bearings thus acting as a rigid element.
14
1.1.2 Superstructure
The two main components of the superstructure to be designed and analyzed are the
deck and the girder. The deck is simply the surface of the bridge on which the vehicles
run. It’s generally made of concrete covered with another layer of asphalt concrete or
pavement to account for the wearing of the surface due to friction and damage from the
vehicle loads. In the present project, also the bridge is made of concrete. The deck is
supported on steel girders which effectively take the loads of the vehicles running on
the deck and the self-weight of the deck itself. In this case the bridge has ‘I’ shaped steel
sections for girders.
The geometric properties of the superstructure are as follows:
The bridge consists of eight spans, with all the spans 173 feet long. The right four
spans are mirror image of the other four spans.
The width and thickness of the deck is 42 ft and 9 inch throughout the length of
the bridge.
The bridge slab is made of concrete of characteristic compressive strength 4 ksi
and supported by four steel girders.
Chevron bracings are provided to connect the girders to the deck. The bracings
are used to transfer the lateral internal load of the superstructure to the bearing.
The cross-section of the superstructure is shown below in Figure 1.3.
Figure 1.3 Typical Cross Section; [adapted from FHWA-SA-97-010 Fig 1b]
15
1.1.3 Substructure
The substructure of a bridge is mainly used to transfer the loads from the superstructure
to the soil through the foundation and is a combination of all the components that
support the superstructure. It mainly consists of abutments, piers, piles and bearings.
Abutments
Abutments are the part of the substructure which, in case of a multi-span bridge,
supports the ends near the approach slab. They are meant to resist and transfer loads
like the self-weight, lateral loads (wind loads) and the ones from the superstructure to
the foundation elements. The abutments are mainly provided in the design bridge to
accommodate the thermal movement of the superstructure which will also allow for a
tolerance of movement in the longitudinal direction, and restraint in the transverse
direction. A clearance of 4 in was provided at the end of the girder-abutment connection.
The typical cross-section of a seat-type abutment of the design bridge is presented in
Figure 1.4.
Figure 1.4 Section at Seat-Type-Abutment; [adapted from FHWA-SA-97-010 Fig 1c]
16
Piers
When bridges are too long to be supported by abutments alone, that is, in case of multi-
span bridges the intermediate support is provided by piers which are built like walls
shaped like girders. Piers are supported by elements called piles. These are slender
columns that are generally placed in a group to support loads transferred from the piers
via a pier cap. They are designed in such a way that they support loads through bearing
at the tip, friction along the sides, adhesion to the soil or a combination of all these.
Figure 1.5 shows the elevation of the piers of the design bridge.
Figure 1.5 Intermediate Pier Elevations; [adapted from FHWA-SA-97-010 Fig 1c]
Bearings
The devices that transfer the loads and movements from the deck to the substructure
and the foundation are called bearings. These movements are accommodated by the
basic mechanisms of internal deformation (elastomeric), sliding (PTFE) or rolling.
17
Conventional types of pinned bearings are assumed at the piers 2, 3, 5 and 6 to ensure
transfer of both longitudinal and transverse seismic forces to the substructure through
anchor bolts. For the piers 1, 4 and 7 bearings were provided to accommodate expected
displacements. Elastomeric bearing with provisions for sliding between the bearing and
girder under large displacements was used for this purpose. Polytetraflouralethylene
(PTFE) bearings were provided against the sliding surface (stainless steel). In addition,
no expansion joints are present in the modified bridge used in the present project.
Figure 1.6 Sliding action of the bearings [adapted from FHWA-SA-97-010 Figure 2]
Figure 1.6 shows the action of the bearings during longitudinal deflection. During
longitudinal loads only the pinned piers (Pier 2,3,5,6) participate and the piers with
elastomeric bearing will slide (Pier 1,4,7) without resisting any longitudinal forces.
However transverse shear will be transferred in all the bearings during transverse
loading.
It is also to be noted that the values and numbering systems in the figures taken from
the previous report done by the FHWA do not necessarily coincide with the numbering
system and calculated values for this configuration. The height of the middle five and
outer two piers will be 70’ and 50’, respectively and enclosed between two abutments,
one on either side.
1.1.4 Location of Bridge
The bridge is located at coordinates 47.2663 N and 122.395105 W, in Tacoma,
Washington. Figure 1.7 present the location of the bridge from google maps. Tacoma is
a mid-sized port city named after the nearby Mount Rainier, originally called Mount
Tahoma. Known as the ‘City of Destiny’ because it was chosen to be the western
terminal of the Northern Pacific Railroad in the late 19th century.
18
The Tacoma fault, is an active east-west striking north dipping reverse fault with close
to 35 miles of identified surface rupture, capable of generating earthquakes of atleast
magnitude 7.
Figure 1.7 Location of the bridge (Source: Google Maps)
1.1.5 Site Conditions
Although the soil in Tacoma, Washington is generally gravelly loam, for purpose of
analysis, the soil conditions will be taken as the same as the conditions given in the
FHWA report. Therefore, the soil profile will be taken as Type I- “Stable deposits of
sands and gravels where the soil depth is less than 200 feet.” The soil properties are
summarized in the Figure 1.8.
Figure 1.8 Subsurface Soil Conditions; [adapted from FHWA-SA-97-010 Fig A1]
1.2 OBJECTIVES
The bridge analyzed here is the fifth of seismic design examples developed using
AASHTO for the FHWA. The bridge was relocated in Tacoma nearby Mount Rainer
from Pacific Northwest to evaluate the seismic performance of the bridge. The analysis
19
presented in the present project was done in accordance with the provisions of MCEER-
ATC/49 document and AASHTO 2009 LRFD Seismic Design Guide Specifications.
The primary objective was to evaluate the bridge response using various analysis
procedures given in the codes and compare the results obtained from them and critical
assessments were made from the results. The elastic analysis approach based on
uniform load method is carried out in the present chapter and the results are presented.
1.3 MODELING DESCRIPTION
The bridge model was developed in a commonly used structural analysis program SAP
2000 v. 16.0.1 [CSI, 2009].
Figure 1.9 shows the stick model used to simulate its behaviour in SAP 2000 program in
which single line frame elements were used for both superstructure and intermediate
piers. The nodes and the work line elements were located at the center of gravity of the
superstructure, which is 8 feet above the top of the piers. Dimensions of the bridges are
presented earlier in the report.
Figure 1.9 Stick element bridge model in SAP 2000
1.3.1 Superstructure
Some the basic modeling assumptions are listed as follows:
Only bridges which subtend an angle of more than 30 degrees are required to be
analyzed as a curved structure, else they are allowed be analyzed as a straight
20
one. In our case, the bridge has a span of 1384 ft (173*8) and a radius of curvature
of 1300 ft, thus subtending an angle of theta= 1384/1300 = 1.065 radians = 60.097
degrees> 30 degrees. Therefore, the superstructure of the bridge was analyzed
using the actual curved geometry.
The bridge superstructure considered in this project has 8 spans over which a
uniformly distributed load (dead load) of 9.3 kips/feet was acting. The
calculations for the dead load are similar to the design example 5 and presented
as follows.
Weight of the superstructure is calculated as following:
concrete 0.15 kip/feet3 Unit weight of concrete
Deck 42’ X 9 “ Width and thickness of bridge deck
wslab 5 kip/feet Weight of concrete deck and girder pads
wsteel 1.9 kip/feet Weight of steel plate girders and cross
frames
wmisc 2.4 kip/feet Weight of barriers, stay-in-place metal
forms and future overlay
wsuper = wslab + wsteel + wmisc
wsuper 9.3 kip/feet Weight per length of the superstructure
The superstructure is a composite structure comprising of I shaped steel girders
and a concrete deck. To simulate this model in SAP 2000, we consider an
equivalent concrete cross-section which has the same Area and Moment of
Inertia as that of the composite cross section. The modifiers used to model the
superstructure is calculated in the succeeding sections
While analyzing ,the additional loads due to traffic barriers, wearing surface
overlay and stay-in-place metal forms are included and taken to be 2.4 kips per
lineal foot of superstructure.
To account for the height of the bearings and the levelling pedestal, the centroid
of the superstructure is taken at a height of 8 feet above the top of the pier. The
girders are modeled as rigid link element in SAP 2000 program which was done
21
by providing end length offset to the elements with rigid zone factor 1 indicating
full rigidity (Figure 1.10).
To compute the bending stiffness full composite action between deck and girder
was assumed. The slipping at higher levels of loadings were neglected.
The torsional properties are simulated considering that only the deck was
effective in providing torsional stiffness.
Strength of concrete was taken to be 4000 psi, while steel was assumed to be
A615Gr60. Uncracked section properties were used to determine area and
moments of inertia assuming full composite action between deck and girders.
Figure 1.10 Rigid link element connecting the pier to the superstructure in SAP
Mass and Stiffness property of superstructure
In the design example, the spans are divided into four parts and the masses are lumped
in the nodes based on tributary area consideration. However, in SAP 2000 program, the
superstructure is modelled as frame elements with each span divided into eight stations.
Also, the gravity load calculated as 9.3 kips/feet (same as the design example 5 as the
cross-section of the superstructure remains same) was applied as uniformly distributed
throughout the spans. So, masses were not needed to be lumped at the nodes in SAP
2000 model.
Calculation of modifiers used in SAP 2000 to model the superstructure
For analysis, the deck and girder are considered to be a composite concrete structure
which has the same Area and the moment of inertia as that of the composite beam. Also
the torsional constant of the deck alone was used to model the superstructure.
Rigid Link
22
For this we consider the composite section to be a square and thus calculate its width as
follows:
Area of the composite section = b2 = 60 ft2
Calculation was done by equating MIX of the transformed section to that of the actual
section
Moment of Inertia about horizontal axis= 518 ft4
= b^4/12
= b = 8.879 ft ~ 8.8 ft
Therefore, the Area modifier = 60 / 8.8792 = 0.76
The moment about the Y axis is given to be 9003 ft4.
The modifier used for Moment of Inertia along vertical axis = 9003/518 = 17.37.
1.3.2 Substructure
Piers
In both transverse and longitudinal directions the pier base was assumed to be fixed
against rotation at the pile cap to account for expected lack of foundation flexibility.
Gross moment of inertia was used for the modeling of pier sections. These assumptions
provide a conservative estimate of the foundation stiffness and hence can be used for
simplification of model in SAP 2000.
Figure 1.11 Relationship between actual pier and stick model of 3-D frame elements [adapted from FHWA-SA-97-010]
23
The intermediate piers are modeled as 3D frame elements that represent the represent
the individual columns. The relationship between the stick element and the actual pier
cross section is presented in Figure 1.11. Three elements were used to model the pier in
SAP 2000 to take into account the varying cross-section by interpolating between the
member end notes. All the properties are based on uncracked sectional details.
Foundation stiffness were attached to the bottommost nodes of the piers (2XX) by means
of spring supports. The intermediate pier modeled in SAP 2000 program is shown in
Figure 1.12.
Figure 1.12 Typical view of an intermediate pier in SAP 2000
Connection of piers to superstructure
In the actual bridge, the internal forces are transferred from the superstructure to the
piers through the bearings. In the SAP 2000 program, the forces are transferred through
a single point where the superstructure and the pier intersects, node 6XX in Figure 1.11.
At the pinned piers, node 6XX transfers shears in all directions from the superstructure,
but is released in moment along longitudinal direction. To account for this, the M3
moment is released at the top of the piers in SAP 2000 program (Figure 1.14). The other
sliding piers with elastomeric bearing are free to move longitudinally and hence only
transverse shear were transferred. So, in addition to M3, V2 are also released at the top
of those piers.
24
Figure 1.13 Details of sliding bearings at piers [adapted from FHWA-SA-97-010 Figure 10]
Translational and rotational releases were provided at the top of the piers with sliding
bearings to allow unrestrained longitudinal motion. The releases were made in local
coordinate system in SAP 2000 program to ensure its tangential orientation with respect
to the point of curvature at the center of the pier.
Figure 1.14 Releases provided in SAP 2000 at top of pier to simulate bearing action
Foundation Stiffness’s
Generally, soil contribution under a pile cap is not included because it is assumed that
soil will settle away from the cap. The piers are assumed to be located in flood plain of
a large river. The scour and loss of contact of soil around and beneath the pile cap, only
25
the stiffness of the pile group will be considered and the resulting forces at the
foundation level will only be applied to pile group to determine design loads to the pile.
Flexibility of pile cap is also neglected. To compute linear springs, elastic subgrade
approach is used as described in the seismic design, FHWA.
Since the relative stiffness of the foundation to the stiffness of the pier column is very
large, the resulting force for design of the pier and foundations will not vary
significantly, generally less than 5 percent. Generally, any reasonable development of
spring stiffness will produce acceptable results.
Considering he pile group, as shown in Figure 1.15, the foundation stiffness is calculated
in FHWA-SA-97-010. As the soil conditions are similar to the design example 5, the
spring stiffness obtained for foundation can be directly used in SAP 2000 model. Figure
1.16 and Figure 1.17 shows the modeling of foundation stiffness. The values of the
spring constants used in SAP 2000 program are as follows:
k11 2.66 × 104 Kip/ft
k22 7.847 × 105 Kip/ft
k33 1.70× 104 Kip/ft
k44 7.96 × 107 Kip-ft/rad
k55 4.785 × 106 Kip-ft/rad
K66 9.628 × 107 Kip-ft/rad
Figure 1.15 Typical plan view of the pile arrangements [adapted from FHWA-SA-97-010]
26
Figure 1.16 Details of support for spring foundation model [FHWA-SA-97-010 Figure 11]
Figure 1.17 Details of foundation springs in SAP 2000
Abutments
The abutments were modeled as simple nodes with a combination of full restraints
(vertical translation and superstructure torsional rotation) and an equivalent spring
stiffness along transverse direction as shown in Figure 1.18. The calculation of the spring
stiffness was based on the pile stiffness of the intermediate piles and it was similar to
the one calculated in design example 5. Spring stiffness of 4663.64 kips/feet was
provided in transverse direction to model the abutments in SAP 2000 program. The
restraints and the springs are all provided relative to the local coordinate geometry.
27
Figure 1.18 Details of abutment supports [FHWA-SA-97-010 Figure 16]
1.4 INITIAL ELASTIC ANALYSIS
1.4.1 Uniform Load Method
The objective of the uniform load method is to estimate the displacement demand for
the simplistic model of the superstructure done in SAP 2000 program. In this analysis
procedure, the structure was subjected to gravity load (9.3 kips/feet) only considering
the weight of the superstructure and an arbitrary distributed load (40 kip/feet) applied
both longitudinally and transversely, separately, to study the behaviour of bridge
subjected to longitudinal and transverse forces.
The following basic assumptions were made during elastic analysis in SAP 2000
The superstructure was subjected to uniformly distributed load of 40 kips/feet
to ensure high workable displacement.
Linear elastic analysis was done, no plastic hinges were assumed to be formed
throughout the analysis.
Lateral load along transverse direction was subjected only on the superstructure
while the lateral load along longitudinal direction was subjected both on the
superstructure and piers separately.
28
1.4.2 Results and Discussions
The bridge modeled in SAP 2000 program was subjected to both gravity load and lateral
loads and elastic analysis was performed. The results obtained from the analysis in
terms of deflected shapes, bending moment and shear forces are discussed in this
section. As seen from the Figure 1.19 to Figure 1.30, the bridge behave symmetrically
under the gravity load which further validate the model produced in SAP 2000 to
simulate the bridge behaviour.
Gravity Load
The deflected shape, bending moment and shear force diagrams under gravity load of
9.3 kips/feet are presented in Figure 1.19 to Figure 1.21. The deflection observed was
more along the end spans compared to the intermediate spans as expected. Maximum
displacement of 0.25 feet was observed under the gravity loads at the end spans. The
bending moment and shear force diagrams obtained for the bridge model are similar to
that obtained for a multi-span continuous beam, which was expected. Also, it was
observed that there was no deflection at the nodes of the superstructure, as rigid
elements were considered to model the girders thereby allowing zero displacement.
Table 1.1 shows the deflection, bending moment and shear force in the spans under
gravity load. As the bridge is symmetric in geometry only the first four spans were
considered for critical assessment of the bridge. The maximum values were also
obtained and presented in the Tables so that the critical sections can be identified.
Figure 1.19 Deflected shape of modeled bridge under gravity load
29
Figure 1.20 Bending moment diagram (major) of modeled bridge under gravity load
Figure 1.21 Shear force diagram (major) of modeled bridge under gravity load
30
Table 1.1 Deflection, moment and shear force along the spans under gravity load
Span Location Deflection
(feet)
Bending Moment
(Kips-feet)
Shear Force (Kips)
Gra
vit
y L
oad
ing
Span-1
Left 0 -2504.1 -694.4
Middle 0.25 22225.2 161.2
Right 0 -32125.2 1020.25
Maximum 0.25 32125.2 1020.25
Span-2
Left 0 -30325.3 -863.2
Middle 0.06 9555.0 -54.1
Right 0 -21050.7 756.0
Maximum 0.06 -30325.3 -863.2
Span-3
Left 0 -21213.5 -778.3
Middle 0.08 11290.3 12.3
Right 0 -21817.0 785.5
Maximum 0.08 -21817.0 785.5
Span-4
Left 0 -21799.2 -774.3
Middle 0.07 10381.2 -11.7
Right 0 -20944.8 763.9
Maximum 0.07 -21799.2 -774.3
It can be seen from the Table 1.1, that maximum deflection for all the spans were
observed at the middle with the value maximum for end span. Negative moments were
observed at all the supports, while positive bending moment were observed at the
middle, indicating double curvature bending of the spans. Also, it was observed that
for all the spans the bending moments and shear forces are maximum at the same
sections, mostly along the girder supports. Maximum shear force and moment was
observed at the right end of the first span.
Table 1.2 Variation of axial forces in superstructure under gravity load
Spans Span-1 Span-2 Span-3 Span-4
Axial Force (Kips) 12.7 24.9 17.1 17.9
Resultant Torsion (kips-feet) -4321.1 700.2 -342.2 261.1
31
Figure 1.22 Settlement of the foundation under pier-1
The variation of the axial forces under gravity load was not much, however it can be
seen from Table 1.2, that the superstructure was subjected to some amount of torsion
under gravity loading. Figure 1.22 shows the settlement of the foundation at the pier-1.
There was slight settlement observed in the foundations of the order of 0.0010 feet, as
they were not modelled as fixed supports. The restraints were provided in form of
spring constants as described earlier. Similar observations were also made with the
other foundation supports.
Transverse Load
A transverse load of 40 kips/feet was applied along the superstructure throughout the
entire length of the bridge. The deflected shape, bending moment and shear force
diagrams under transverse load are presented in Figure 1.23 to Figure 1.25. As it can be
seen from the deflected shape, the entire superstructure moves like a rigid body in the
direction of the force. Maximum deflection of 1.36 feet was observed at the center of the
bridge as expected.
Figure 1.23 Deflected shape of modeled bridge under transverse loading
32
Figure 1.24 Bending moment diagram (major) of modeled bridge under transverse load
Figure 1.25 Shear force diagram (major) of modeled bridge under transverse load
33
Table 1.3 Deflection, moment and shear force along the spans under transverse load
Span Location Absolute
Deflection (inch)
Bending Moment
(Kips-feet)
Shear Force (Kips)
Tra
nsv
erse
Lo
adin
g
Span-1
Left 0 0 -2055.9
Middle 0.87 71364.8 565.0
Right 0.81 -106905.9 3401.6
Maximum 0.87 -106905.9 3401.6
Span-2
Left 0.86 -106904.5 -2668.5
Middle 0.89 3298.9 133.1
Right 0.92 -137042.6 3140.7
Maximum 0.92 -137042.6 -2668.5
Span-3
Left 0.96 -137047.9 -3518.9
Middle 1.11 34346.2 -543.1
Right 1.22 -45548.6 2504.9
Maximum 1.22 -135047.9 -3518.9
Span-4
Left 1.24 -45555.2 -3076.3
Middle 1.35 81644.6 0
Right 1.36 -43980.1 3081.3
Maximum 1.36 81644.6 3081.3
As it can be observed from Table 1.3, the deflection of the superstructure was observed
to be more or less similar throughout the length of the beam with the maximum value
being observed at the end of span 4, which is actually the center point of the bridge. The
maximum bending moment and shear force was observed at same sections with one
exception in span 4. Again change in sign of bending moment and shear force was
observed indicating double curvature bending. In almost all the cases the maximum
resultant forces were recorded at the supports as also observed under gravity load. So
the sections near the girder support are critical sections and needs tension reinforcement
at the top as negative bending moment (hogging) was observed both during transverse
and gravity loading.
34
Table 1.4 Maximum resultant forces along piers under transverse load
Piers Shear(kips) Moment (kips-feet)
Displacement (feet) Axial force
(kips) Long Trans Trans Long Long Trans
Left Abut 285.3 3115.9 0.0 1095.3 0.60 0.65 51.8
Pier 1 0.0 7098.1 405837.3 0.0 0.49 0.97 797.6
Pier 2 1393.0 7502.9 490020.7 80793.5 0.35 1.11 1165.0
Pier 3 361.3 6218.5 509082.6 28182.6 0.19 1.39 782.3
Pier 4 0.0 6696.7 547189.6 0.0 0.00 1.50 253.6
Pier 5 35.0 6309.6 514862.2 2724.7 0.19 1.39 754.4
Pier 6 952.3 7518.7 491541.5 55232.9 0.35 1.11 1142.9
Pier 7 0.0 7105.7 406414.8 0.0 0.49 0.97 797.6
Right Abut 285.0 3115.4 0.0 1097.1 0.61 0.65 51.8
Table 1.4 presents the maximum resultant forces in the piers under transverse load both
in its weak and strong direction. The resultant forces were observed to be more in its
strong direction compared to weak direction, as the load was applied along transverse
direction. High negative moment was observed along the piers in strong direction with
the pier-4 having maximum value. The bending moment in the piers are much higher
than the superstructure as evident from Figure 1.24 and Table 1.4. The deflection of the
pier along the direction of loading increases from the ends to the center with a maximum
displacement of 1.00 feet at the center pier. However, along weak direction the
deflection of the pier is not varying much.
Longitudinal Load on Superstructure
Longitudinal load of 40 kips/feet was applied to the superstructure of the bridge to
investigate its behaviour under longitudinal forces. Thus it can be seen from the Figure
1.26 and Figure 1.27 that the siding piers (pier 1, 4 and 7) don’t participate in the
longitudinal direction which is in accordance with the assumption made in Figure 2 of
FHWA design example. In order to take into account the sliding action of those piers
only transverse shear was transferred and hence no shear and bending moment was
observed under longitudinal loading in the corresponding piers.
35
Figure 1.26 Bending moment diagram of modeled bridge under longitudinal load on deck
Figure 1.27 Shear force diagram (major) of modeled bridge under longitudinal load on deck
Table 1.5 Maximum resultant forces along piers under longitudinal load on deck
Piers Shear(kips) Moment (kips-feet)
Displacement (feet) Axial force
(kips) Long Trans Trans Long Long Trans
Left Abut 46.8 165.7 0.0 102.6 5.75 0.04 2.8
Pier 1 0.0 786.5 40110.1 0.0 5.72 0.12 280.0
Pier 2 19407.5 403.5 24143.2 1125633.3 5.65 0.07 84.3
Pier 3 8243.4 192.2 3540.7 642988.9 5.66 0.03 470.8
Pier 4 0.0 877.4 38889.6 0.0 5.68 0.00 1341.6
Pier 5 8192.2 2545.3 159735.9 638990.5 5.66 0.03 1917.7
Pier 6 19181.3 501.2 3814.0 1112512.6 5.65 0.07 1291.7
Pier 7 0.0 907.3 42467.7 0.0 5.72 0.12 573.3
Right Abut 82.3 231.2 0.0 102.6 5.75 0.04 3.8
36
Longitudinal Load on Piers
Longitudinal load of 40 kips/feet was applied to the piers to investigate the behaviour
bridge under longitudinal forces. The load was applied in SAP 2000 program in global
X direction along the piers, therefore, it was not applied in purely longitudinal direction
due to curved geometry. Hence, some transverse displacement was also evident from
the Figure 1.28. As it can be seen from the Figure 1.29 and Figure 1.30, the bending
moments and shear forces were maximum at the pier bottom, where the foundation
stiffness’s were provided. Also, the resultant forces (V and M) was more in the piers
compared to the superstructure. This was mainly because, the deflection of the
superstructure was much less compared to that of the piers.
Figure 1.28 Deflected shape of modeled bridge under loangitudinal load
Figure 1.29 Bending moment diagram of modeled bridge under longitudinal load on piers
37
Figure 1.30 Shear force diagram of modeled bridge under longitudinal load on piers
1.5 SUMMARY AND CONCLUSIONS
A uniform load method of analysis was used to get response of a simplified model of
the bridge in SAP 2000 program. The general description of the bridge and assumptions
made in the model are discussed in details and the results obtained from the analysis
are presented. The bridge used in the project is symmetric in geometry and hence
symmetry is also observed in the resultant forces. It can be observed that all the bending
moment and shear force diagrams are symmetric in nature. The behaviour of the bridge
under gravity and lateral loads can be summarized as follows:
The superstructure of the bridge almost behave as a rigid body under transverse
loading with partial restrain at both abutment and at pier location.
Maximum deflection was observed at the end spans under gravity loading, however
the deflection was maximum at the center of the bridge under transverse loading.
The bending moment diagrams indicated that the superstructure was under double
curvature bending both under gravity and transverse loads.
Maximum shear forces and bending moments were observed at the girder supports
for both gravity and transverse loading.
The maximum displacement of the superstructure observed in transverse direction
for 40 kips/feet of uniformly distributed load was 1.36 feet, while the maximum
deflection was observed to be 0.25 feet for gravity loading.
38
The maximum deflection of the substructure (pier 4) was 1.00 feet under transverse
direction along the direction of loading.
The variation in axial force in the superstructure was not much due to gravity load
along the length of the bridge. However, torsional moments were present in the
superstructure under the action of gravity loads.
It was also observed that the foundation nodes have undergone some settlement, as
springs were used for modeling.
-o-o-o-
39
CHAPTER 2 2. MODAL ANALYSIS, DEVELOPMENT OF RESPONSE SPECTRA AND SCALING OF GROUND MOTIONS
MODAL ANALYSIS, DEVELOPMENT OF RESPONSE SPECTRA AND SCALING OF
GROUND MOTIONS
2.1 INTRODUCTION
In the previous chapter, the general description of the bridge was presented and its
behaviour under generic lateral load, both transverse and longitudinal, was
investigated. Therefore, the two principle directions were considered for analysis. In
this chapter multimode analysis of the bridge is carried out in SAP 2000 program
considering all the modes which contribute significantly to the overall behaviour of the
structure. The response spectra for our site (Tacoma) has been obtained for both design
earthquake (DE) and maximum credible earthquake (MCE). A suite of ground motions
is selected for time history analysis and scaled by comparing their corresponding
response spectra to the design spectra for our site. Further, a simplified single degree of
freedom (SDoF) model of the bridge was developed in NONLIN software to examine
its behaviour and compared with the response obtained in SAP 2000 program.
2.2 EIGEN VALUE ANALYSIS
The model developed in SAP 2000 program for the analysis using uniform load method
(described in previous chapter) is also used for the multimode method of analysis and
therefore, the same modeling assumptions are valid. The load considered for the modal
analysis in SAP 2000 program is the total dead load of the superstructure coming from
the element self-weight. The live load and other miscellaneous loads are neglected in
40
modal analysis to avoid complications. The load of the structure is defined in SAP 2000
by defining mass source as shown in Error! Reference source not found..
Figure 2.1 Mass source defined for modal analysis in SAP 2000
The maximum number of modes were initially set to 12 in SAP 2000 program, as it was
expected that the modal participation factor of the first 12 modes will be greater than
90%. However, as the analysis was carried out, it was observed that about 83 Eigen
values were needed to capture 100% mass participation in both translation and rotation
along all the three directions. However, modal participation factor of 90% was observed
in the 27th mode for the principle directions (X and Y). Therefore, the results obtained
from the first 30 modes are shown in Table 2.1 to also demonstrate the contribution of
the higher modes on the structure. The natural periods and the corresponding mode
shapes are presented in the succeeding sections. It can be seen from Table 2.1, that the
cumulative modal mass participation had reached 90% first in rotation along vertical
axis at 13th mode, while for translational motion it is reached only after 20th and 27th
modes for transverse and longitudinal directions, respectively.
41
Table 2.1 Natural periods and cumulative mass participation of different modes
Mode Period
(s)
Cumulative Modal Mass Participation
SumUX SumUY SumUZ SumRX SumRY SumRZ
1.00 1.54 0.57 0.00 0.00 0.00 0.00 0.06
2.00 0.88 0.57 0.59 0.00 0.02 0.00 0.06
3.00 0.75 0.62 0.59 0.00 0.02 0.00 0.60
4.00 0.75 0.67 0.59 0.00 0.02 0.00 0.60
5.00 0.71 0.67 0.59 0.00 0.02 0.02 0.60
6.00 0.69 0.67 0.87 0.00 0.03 0.02 0.60
7.00 0.68 0.67 0.87 0.01 0.09 0.02 0.60
8.00 0.62 0.70 0.87 0.01 0.09 0.02 0.89
9.00 0.62 0.70 0.87 0.01 0.09 0.07 0.89
10.00 0.54 0.70 0.87 0.03 0.18 0.07 0.89
11.00 0.52 0.70 0.88 0.03 0.18 0.07 0.89
12.00 0.48 0.70 0.88 0.03 0.18 0.15 0.89
13.00 0.45 0.76 0.88 0.03 0.18 0.15 0.90
14.00 0.45 0.78 0.89 0.03 0.18 0.15 0.91
15.00 0.43 0.78 0.89 0.03 0.18 0.15 0.93
16.00 0.43 0.78 0.89 0.07 0.35 0.15 0.93
17.00 0.39 0.78 0.89 0.07 0.35 0.47 0.93
18.00 0.37 0.78 0.89 0.42 0.38 0.47 0.93
19.00 0.36 0.78 0.89 0.42 0.38 0.47 0.93
20.00 0.31 0.78 0.91 0.42 0.42 0.47 0.93
21.00 0.30 0.78 0.91 0.42 0.42 0.47 0.93
22.00 0.30 0.78 0.91 0.42 0.43 0.47 0.93
23.00 0.27 0.78 0.95 0.42 0.52 0.47 0.93
24.00 0.27 0.86 0.95 0.42 0.52 0.47 0.93
25.00 0.27 0.86 0.96 0.42 0.56 0.47 0.93
26.00 0.27 0.86 0.96 0.42 0.56 0.47 0.94
27.00 0.26 0.90 0.96 0.42 0.56 0.47 0.94
28.00 0.25 0.96 0.96 0.42 0.56 0.47 0.95
29.00 0.24 0.96 0.97 0.42 0.56 0.47 0.95
30.00 0.24 0.96 0.97 0.42 0.57 0.47 0.95
42
2.2.1 Natural Periods and Mode Shapes of Structure
The first three natural periods coming from the modal analysis are 1.54 s, 0.88 s and
0.75 s, respectively. First mode is primarily associated with translation in longitudinal
direction coupled with some rotation about vertical axis while the second mode is
associated with translation in transverse direction coupled with some rotation about
longitudinal axis of the bridge. It can be verified from the values of modal mass
participation presented in Table 2.2 for the first 2 modes. It must be noted that the
rotation present in the first two mode shapes are much less compared to the
translational components, and hence the period associated with the first and the second
modes can be considered as the period of the bridge for translational motion along
longitudinal and transverse directions, respectively. The third mode is predominantly
rotation about vertical axis.
Table 2.2 Modal mass participation of first three modes
Mode Period (s)
Cumulative Modal Mass Participation
Translational Rotational
UX UY UZ RX RY RZ
1.00 1.54 0.57 0.00 0.00 0.00 0.00 0.06
2.00 0.88 0.00 0.59 0.00 0.02 0.00 0.00
3.00 0.75 0.05 0.00 0.00 0.00 0.00 0.54
Figure 2.2 to Figure 2.7 show the mode shapes corresponding to first three natural
modes of vibration as obtained from modal analysis in SAP 2000 program.
Figure 2.2 3D view of the mode shape corresponding to first mode (Longitudinal)
43
Figure 2.3 Plan view of the mode shape corresponding to first mode (Longitudinal)
Figure 2.4 3D view of the mode shape corresponding to second mode (Transverse)
Figure 2.5 Plan view of the mode shape corresponding to second mode (Transverse)
Figure 2.6 3D view of the mode shape corresponding to third mode (Torsional)
44
Figure 2.7 Plan view of the mode shape corresponding to third mode (Torsional)
For comparison of the multi-mode analysis results obtained in SAP 2000 program with
the periods obtained in FHWA Design Example 5, the results are presented in Table 2.3.
It can be seen from the Table that the results obtained from SAP 2000 program are in
close agreement with the results obtained in the design example. The longitudinal
periods of unit-1 and unit-2 of the original bridge in the design example are 1.52 s and
1.20 s respectively. Since the modified bridge analyzed in this project is eight span
bridge similar to the unit-2 of the original bridge, therefore its longitudinal period
obtained from modal analysis in SAP 2000 matches closely with that obtained for Unit-2
of the design example. In addition, the period associated with translational motion in
transverse direction is also similar in both SAP 2000 and the design example. However,
the small difference is due to presence of expansion joints in the original bridge.
Therefore, the similarity in time periods of the bridge in principle directions obtained
from SAP 2000 with the periods of the original bridge presented in FHWA design
example further validates our model.
Table 2.3 Comparison of periods of the modified bridge and the FHWA original bridge
SAP 2000 Analytical Calculation in
Design Example Multimode analysis in
Design Example
Mode Period Mode Period Mode Period
1 Longitudinal 1.54 Longitudinal
Unit 2 1.55 1 Unit-2 Long 1.52
2 Transverse 0.88 Unit 1 1.26 2 Unit-1 Long 1.20
3 Torsion 0.75 Transverse 0.43 3 Transverse 0.80
2.2.2 Higher Modes associated with Vibration of Piers
Piers are rigid compared to the bearings provided at the top of the piers, as a result of
which, the initial modes of vibration are mostly dominated by the vibrations of the
bearings, particularly at the top of the piers 1,4 and 7, which allows sliding. The first
45
mode associated only with vibration of pier is the fourth mode with period of 0.75 s,
with vibration of pier 4 along longitudinal direction, as presented in Figure 2.8. The next
modes that are dominated by vibration of piers have natural period less than 0.4 s. Thus
it can be concluded that the vibration of pier was negligible in the first few modes and
hence the contribution of piers to the inertia forces can be neglected for those modes.
Therefore, for the simplified SDoF model that is developed to consider the vibration of
the bridge along its principal directions, it is safe to neglect the inertia of the piers and
only the weight of the superstructure is considered.
However, for better results it is recommended that the weight of the substructure should
also be considered and a comparative study is carried out in the later section. It can be
found that the period obtained by considering the weight of the superstructure and the
piers are in better agreement with the SAP 2000 results and actual period of the structure
obtained analytically.
Figure 2.8 Mode shape corresponding to vibration of pier (4th Mode)
2.2.3 Comparison with Elastic Analysis Results in SAP 2000
As stated in Chapter 1, the primary objective of the uniform load method is to estimate
the displacement demands of the superstructure under generic lateral loads. A
transverse and longitudinal lateral load of 40 kips/feet were applied along the
superstructure. Based on the following equation, the lateral stiffness of the bridge can
be estimated for longitudinal and transverse vibrations.
max
Lat
wLK
v
where, w = 40 kips/feet, L = total length of the superstructure along which the uniformly
distributed load is acting and vmax is the maximum displacement recorded in SAP 2000
program along longitudinal and transverse directions. So, once the lateral stiffness is
obtained, the periods can be calculated based on the following equation.
2m
Lat
WT
K g
46
The period of the bridge obtained from the above method is presented in Table 2.4. As,
it can be seen, the periods obtained from SAP 2000 was higher (almost 25%) than those
calculated based on displacement recorded during uniform load method. This was
probably because, the weight used to calculate the periods was the weight of the
superstructure alone, which is 9.3 kips/feet. Therefore, the modal analysis is repeated
in SAP 2000 by using the mass source as 9.3 kips/feet (Figure 2.9) and it was observed
that the periods exactly matches with those calculated based on uniform load method,
which further validates our model in SAP 2000.
Figure 2.9 Mass Source considering only the weight of the superstructure
The time period was also calculated considering both the weight of the superstructure
and piers. The weight of the 50 feet and the 70 feet piers are 690 and 880 kips,
respectively as reported in the design example. It can be seen that the periods along both
longitudinal and transverse direction are in good agreement with the values obtained
from SAP 2000 program considering the element weights. Therefore, the lumped mass
is considered as 18461.2 kips considering both the weight of the superstructure and the
piers half the height above the pile cap.
The stiffness of the bridge obtained from this simplified procedure is presented in Table
2.4. It can be seen later that the longitudinal stiffness calculated using fixed base is in
close agreement with the analytical calculations, but the transverse stiffness is much
lesser compared to the analytical solution. The possible reason is stated in the
succeeding section and a more rigorous calculation of mass and stiffness is presented
which is to be further used for the development of the SDoF model in NONLIN.
47
Table 2.4 Calculation of period of bridge from uniform load method
Notations
Considering only weight of superstructure
Considering the weight of superstructure and piers
Longitudinal Transverse Longitudinal Transverse
Un
ifo
rm L
oa
d
Me
tho
d
vmax (feet) 5.75 1.52 5.75 1.52
wL(kips) 55360 55360 55360 55360
KLat (kips/feet) 9629.5 36514.74 9629.5 36514.74
W (kips) 12871.2 12871.2 18271.2 18271.2
Tm (s) 1.27 0.66 1.52 0.79
SA
P
20
00 T (Element mass) 1.54 0.88 1.54 0.88
T (9.3 kips/feet) 1.27 0.66 1.27 0.66
2.2.4 Analytical Calculations of Bridge Stiffness along local directions
The stiffness of the bridge along the longitudinal and transverse directions are
calculated analytically and compared with the results obtained from the simplified
procedure presented in the preceding section. Two procedures were used for analytical
calculation of bridge stiffness and designated as method 1 and 2 in this report.
Method 1: The piers are assumed to be fixed at the base and the springs attached to the
foundation is neglected. The objective of such assumption is to check if this simplified
model can efficiently predict the stiffness of the bridge.
Method 2: The foundation springs are considered at the pier base and the stiffness of
the individual piers are calculated in local directions. It must be noted that this will
capture the bridge behaviour with more efficiency, however the calculations will be
more complex.
Method 1: Piers assumed fixed at base
Longitudinal
It can be seen from the mode shape corresponding to first mode, the entire
superstructure moves like a rigid body along longitudinal direction. The piers that will
contribute in the longitudinal direction are the pinned piers as the sliding piers are
taking only transverse shear. So the stiffness of the piers in longitudinal direction can
be calculated by considering the pinned piers in parallel. The values of the pier stiffness
are taken directly from the calculations presented in FHWA design example.
48
K50 3509 kips/feet
K70 1413 kips/feet
Klong = 2(K50 + K70) 9844 kips/feet
Transverse
In the transverse direction all the piers and the abutments participate, but it can be seen
from the corresponding mode shape that the superstructure does not move like a rigid
body. The maximum transverse displacement was observed at the center (Pier 4) of the
bridge. The mode shape corresponding to the 1st mode is used to calculate the
participation of each piers to the overall stiffness of the bridge along transverse
direction. Table 2.5 shows the deflection recorded at each piers in transverse direction
normalized with the maximum deflection observed at the center pier for mode shape
corresponding to 2nd mode.
Table 2.5 Deflected shape corresponding to 2nd mode (Transverse)
A P1 P2 P3 P4 P5 P6 P7 B
0.0024 0.0046 0.0216 0.0494 0.0628 0.0494 0.0216 0.0046 0.0024
0.038 0.073 0.344 0.787 1 0.787 0.344 0.073 0.038
So the stiffness of the bridge along the transverse direction is calculated by considering
the stiffness of the individual elements (piers and abutments) to be proportional to the
normalized displacement and calculated as follows:
Table 2.6 Calculation of overall transverse stiffness analytically
K50 Trans = 35928 kips/feet K70 Trans =14474 kips/feet
A P1 P2 P3 P4 P5 P6 P7 B
Factor 0.038 0.073 0.344 0.787 1 0.787 0.344 0.073 0.038
K 176.1 2622.7 12359.2 11391.0 14474 11391.0 12359.2 2622.7 176.1
Overall Transverse Stiffness 67572 kips/feet
The longitudinal stiffness calculated based on the displacement recorded in the uniform
load method in SAP 2000 program as shown in Section 2.2.3 is 9629.5 kips/feet, which
is in good agreement with the value calculated analytically (9844 kips/feet). In this
simplified procedure, the foundations were considered to be fixed at the base of the pile
49
cap while calculating the stiffness of the individual piers. So, it can be concluded that
assuming the foundations to be fixed at the base of the pile cap gives a close
approximation of the longitudinal foundation spring stiffness’s used in the modal
analysis. However, the transverse stiffness calculated analytically is much higher than
value reported in Section 2.2.3. This is mainly because, it is not correct to calculate the
pier stiffness in transverse direction considering it to be fixed at the base.
Method 2: Calculation of local stiffness: Considering foundation springs at pier bottom
Longitudinal Direction (Mode 1)
As mentioned in the previous chapter, the piers 1, 4 and 7 are sliding in nature and
hence does not contribute to the longitudinal stiffness of the bridge. The stiffness of the
individual piers are first calculated both analytically and in SAP 2000 program by
applying an unit load and then the total stiffness is obtained by considering the piers in
parallel. The stiffness of the individual piers are obtained analytically as follows by
considering the translational spring, the rotational spring and the stiffness of the
columns in series.
7
4
4503
470
7.96 10 /
2.67 10
3 3509 / ( 56.5 , 408 )
1414 / ( 76.5 , 408 )
rot
tran
pier pier
pier
k kip feet rad
k kip feet
EIk k kip feet h feet I feet
h
k kip feet h feet I feet
eff pier
rot tran pier
eff pier
rot tran pier
Lk L feet
k k k
kip feet
Lk L feet
k k k
kip feet
12
50
50
12
70
70
1 1, 56.5 6.5 63
2983 /
1 1, 76.5 6.5 83
1259 /
50 702 2
8484 /
long eff pier eff pierk k k
kip feet
50
sup
sup
50 70
9.3 1384 12871.2
Weight from half of the participating piers
2 2 2 690 2 880 3140
16011.2
long er sub
er
sub
long
W W W
W kips
W
W W kips
W kips
(Mode 1) 2 1.52 long
long
long
WT s
gK
Thus the period of the bridge obtained analytically in longitudinal direction (Mode 1) is
in good agreement with that obtained from SAP 2000 program.
Transverse Direction (Mode 2)
As mentioned in the previous chapter, all the piers contribute to the transverse stiffness
of the bridge. The stiffness of the individual piers are first calculated both analytically
and in SAP 2000 program by applying an unit load and then the total stiffness is
obtained by considering the piers in parallel along with the abutment stiffness. The
stiffness of the individual piers are obtained analytically as follows by considering the
translational spring, the rotational spring and the stiffness of the columns in series.
7
4
4503
70
9.63 10 /
1.71 10
3 35928 / ( 56.5 , 4166 )
14474 / ( 76.5 , 4166
rot
tran
pier pier
pier
k kip feet rad
k kip feet
EIk k kip feet h feet I feet
h
k kip feet h feet I feet
4 )
eff pier
rot tran pier
eff pier
rot tran pier
Lk L feet
k k k
kip feet
Lk L feet
k k k
kip feet
12
50
50
12
70
70
1 1, 56.5 6.5 63
7841 /
1 1, 76.5 6.5 83
5022 /
51
Table 2.7 Calculation of overall transverse stiffness analytically
A P1 P2 P3 P4 P5 P6 P7 B
Factor 1 0.073 0.344 0.787 1 0.787 0.344 0.073 1
K 4664 572.4 2697.3 3952.3 5022 3952.3 2697.3 472.4 4664
Overall Transverse Stiffness 28793 kips/feet
28793 / calculated based on the participation
factor in above Tabletransk kip feet
sup
sup 9.3 1384 12871.2
Weight from half of the piers calculated based on participation of each piers
2840.6
15711.8
trans er sub
er
sub
trans
W W W
W kips
W
kips
W kips
(Mode 2) 2 0.82 transtrans
trans
WT s
gK
Thus the period of the bridge obtained analytically in transverse direction (Mode 2) is
in good agreement with that obtained from SAP 2000 program.
A load of 40 kips, was applied in the longitudinal and transverse directions at the top of
the piers in SAP 2000 (Figure 2.10) and the maximum deflection was recorded for the 50
feet and 70 feet piers (Figure 2.11) based on which the effective stiffness of the individual
piers were obtained.
Figure 2.10 Load applied in local directions for stiffness calculations of 50ft and 70ft piers
52
Figure 2.11 Displacement recorded in local directions at top of the piers
The stiffness obtained based on this displacement was compared with those obtained
analytically and presented in Table 2.8. A good agreement was observed between the
results which further validate the analytical procedure for stiffness calculation.
Table 2.8 Comparison of stiffness of the piers obtained analytically and in SAP 2000
Direction 50 feet pier 70 feet pier
SAP 2000 Analytical SAP 2000 Analytical
Longitudinal 3478 2983 1476 1259
Transverse 8163 7841 5128 5022
The simplified procedure presented in Section 2.2.3 and simplified method 1 of section
2.2.4 gives a quick and good approximation of the actual periods of the structure in
longitudinal and transverse directions. However, for this project the stiffness obtained
according to method 2 in this section along the longitudinal and transverse directions
are used for development of the SDoF model in NONLIN program.
2.2.5 Analytical Calculations of Bridge Stiffness along global directions
However, it must be taken into account, that for better understanding of the behaviour
of the bridge during seismic activity, its response must also be investigated in the two
principal directions (X and Y) orthogonal to each other and hence the stiffness was also
calculated for global X and Y directions.
53
The stiffness obtained in the local directions were transferred to the global directions, as
shown in the Table 2.9, based on the angle of the respective piers with the global axes.
2
2
2
2
cos and siny long
x trans
y long trans
x long trans
k kc csc s
k kcs s
k c k csk
k csk s k
Table 2.9 Calculation of overall stiffness analytically along global direction
Piers Angle
(rad)
klong (kips/feet)
ktrans (kips/feet)
Ky (kips/feet)
Kx (kips/feet)
Abut A 0.53 0 4664 2034 1192
P1 0.41 2983 7841 5375 2336
P2 0.28 2983 7841 4838 1391
P3 0.13 1259 5022 1883 246
P4 0.00 1259 5022 1259 0
P5 0.13 1259 5022 1883 246
P6 0.28 2983 7841 4838 1391
P7 0.41 2983 7841 5375 2336
Abut B 0.53 0 4664 2034 1192
Total Global Stiffness 29521 10331
A uniformly distributed load was applied in the superstructure in SAP 2000 model
along global X and Y directions and a maximum displacement of 0.1343 and 0.0465 feet
was recorded, respectively. The stiffness, thus obtained was 10305 and 29763 kips/feet
along X and Y directions, respectively, and hence are in good agreement with the values
obtained analytically.
Therefore, the final values of mass and stiffness along the principal directions (both local
and global) that were used for development of the SDoF model is shown in Table 2.10.
54
Table 2.10 Stiffness and mass used in the development of the SDoF model
Direction Mass (kips) Stiffness (kips/feet)
Longitudinal (Local X) 16011.2 8484
Transverse (Local Y) 15711.8 28793
Chord (Global X) 18271.2 10331
Radial (Global Y) 18271.2 29521
2.3 RESPONSE SPECTRA
The ATC 49 report suggests to consider two level of earthquakes for analysis and design
of the structures. The design expected earthquake (EE) is considered to be the one
associated with 50% probability of exceedance in 75 years, while maximum credible
earthquake (MCE) corresponds to 3% probability of exceedance in 75 years (Table 3.2-1
of ATC-MCEER 49). The construction of the design response response spectra using the
two point method and the definition of the parameters as presented in the ATC 49 is
shown in the Figure 2.12.
Figure 2.12 Construction of design response spectra using 2-point method [MCEER/ATC 49]
The input Response spectra graph (as specified in FHWA 1996 design example 5) that
gives information about the effect of earthquake for the given bridge is shown below in
Figure 2.13. However, the site of the modified bridge being analyzed in the present
project differs from the one given in design example and hence the response spectra is
developed in USGS website as presented in the succeeding sections.
55
Figure 2.13 Response Spectra used in the design example
2.3.1 Seismic Design Spectra
Since the time histories with respect to ground acceleration vary for each earthquake,
the resulting response spectrum will also be different. Hence when a structure is
designed for earthquake, the design spectra is generated based on average values of the
previous earthquakes. In order to provide loading for the model, a design response
spectrum was created following the specifications in Article 3.6.2 of MCEER/ATC 49
for both transverse and longitudinal directions.
The parameters of seismic design spectra were obtained from the USGS website based
on the following assumptions:
The expected life span of the bridge is considered to be 75 years
Presence of any active fault in the nearby region is not considered
The bridge is expected to overcome the EE level ground motion with minimal
damage and the MCE level ground motion without collapse.
The soil profile is considered to be same as that reported in the design example
which is site class C.
56
2.3.2 Seismic Design Spectra of our Site
Using USGS Website
The spectral acceleration values for 0.2 second and 1 second time periods for the location
(Tacoma, WA) were obtained from the USGS website. The soil condition in the region
was assumed to be dense and hence classified as ‘site class C’ as mentioned earlier in
the report. Based on 2013 ASCE 41 Design Code reference document, the earthquake
hazard level was custom designed for the analysis. The percentage probability of
ground motion exceedance in 50 years was taken as 2% for MCE (Maximum Credible
Earthquake) and 37% for EE (Expected Earthquake). The calculation for probability of
exceedance of EE are shown below. The values obtained from USGS are presented
below. The 2 response spectra are shown in Figure 2.14.
For EE, the probability of exceedance in 75 years is 50%.
3
(9.24 03 50)
1 , where for T = 75 yrs, p = 50%
9.24 10
For T = 50 yrs, 1 37%
T
E
e p
p e
Table 2.11 Response Spectra parameters obtained from USGS
Hazard Latitude Longitude Ss S1 Site Class Fa Fv
MCE 47.24879 -122.442 1.298 0.527 C 1.0 1.3
EE 47.24879 -122.442 0.330 0.115 C 1.2 1.685
57
MCE EE
Figure 2.14 Response Spectra obtained for our site from USGS website for MCE and EE
Using PEER Ground Motion Database
The values of S1 and Sd obtained from USGS were input into PEER Ground Motion
Database to obtain the scaled design spectra. The target spectrum was generated based
on ASCE Spectrum. The long period transition period (TL) was taken as 6 second as
obtained from USGS website. The values for the site coefficients Fa (Short period range)
and Fv (long period range) were obtained from MCEER/ATC-49(Part 1) Table 3.4.2.3-1
and 2. The Sds and Sd1 values were calculated as follows.
MCE – 2% in 50 years
Fa = 1
Fv = 1.3
Sds = Ss *Fa= 1.298 * 1= 1.298
Sd1 = S1*Fv= 0.527 * 1.3= 0.685
EE – 37% in 50 years
Fa = 1.2 (Interpolated)
Fv = 1.685 (interpolated)
Sds = Ss *Fa= 0.330 * 1.2 = 0.396 g
Sd1 = S1*Fv= 0.115 * 1.685 = 0.193 g
58
MCE EE
Figure 2.15 Response Spectra in PEER Ground motion Database
2.3.3 Ground Motion Selection
Ground motion selection is one of the most important factors for performing time
history analysis and should not be affected by performance characteristics of the
structure. In the present project the ground motions were selected and scaled in PEER
ground motion database.
2.3.4 Development of Response Spectra and Scaling of Ground Motions
The selected ground motions are scaled w.r.t. MCE and EE level spectra according to
MCEER ATC 49 such that
The mean response spectra never lies below 15% of the design spectra for any
period and,
The average ratio of the mean spectra and the target spectra shall not be less than
unity over the period range of significance.
So these two considerations were made while scaling the ground motions to the target
spectrum in PEER database.
After generating the target spectrum with the above values in PEER Ground Motion
Database, a magnitude range of 6.5-8.5 was selected to generate a list of ground motions
in that range. The period of interest was given between 0.2 and 1.8 s which more or less
capture the first 30 modes of the structure to ensure better match between the response
spectra of the selected GMs and the target spectra. 3 locations were selected from the
list of records each for MCE and EE hazard level to scale the target spectrum using the
59
average of their spectral acceleration curves. The curves of the selected locations were
chosen so that the scaling factor would be 2.5 or less. In addition, the ground motions
already present in the NONLIN database was selected, so that scaling will be easy for
the time history analysis in NONLIN program, the result of which is presented in the
succeeding sections. The resultant ground motion average spectra is compared with the
target spectra in Figure 2.16 to Figure 2.18. The list of ground motions and their
corresponding scale factors are presented in Table 2.12. It can be seen from the Figures
that the mean response spectra of the selected ground motions after scaling never falls
below 0.85 times the target spectra and also the ratio of the mean spectra to the target
spectra is approximately 1.02 for both MCE and EE. Thus, both the considerations of
ATC 49 are duly met.
MCE EE
Figure 2.16 Resultant ground motion spectra compared with target spectra in PEER
Figure 2.17 Comparison of the mean response spectra of the selected GMs with the target spectra and 85% of target spectra at EE
60
Figure 2.18 Comparison of the mean response spectra of the selected GMs with the target spectra and 85% of target spectra at MCE
Table 2.12 Scaled ground motions selected from PEER Database
No Ground Motion NGA# Scale M Year Station
MC
E
1 Cape Mendocino 828 1.0 7.01 1992 Petrolia
2 North Ridge 960 1.0 6.69 1994 Canyon Country
-W Lost Cany
3 Loma-Prieto 753 1.0 6.93 1989 Corralitos
EE
1 North Ridge 1048 0.3788 6.69 1994 North Ridge 17645
Saticoy St
2 Imperial Valley 181 0.4671 6.53 1979 El-Centro #6
3 Kobe Japan 1116 0.7236 6.90 1995 Shin-Osake
2.4 DEVELOPMENT OF SDOF MODEL
A simple elastic SDoF analysis of the bridge was performed using the program
NONLIN, in which a lumped mass model was developed with the entire mass of the
superstructure and the piers lumped at the node. The piers of the bridge were modeled
as a single column with effective stiffness values in longitudinal and transverse
directions (local) and global X (chord) and Y (radial) directions. The primary objective
to carry out this simplified analysis was to get a preliminary idea about the response of
the bridge along two principal directions, when subjected to different level of ground
motions scaled with the design spectra of our site. The maximum resultant forces of the
piers in both strong and weak directions can also be obtained from this simplified
analysis.
61
2.4.1 Modeling Assumptions
Elastic analysis of the bridge was performed using NONLIN software with a simple
SDoF model in which representative mass and stiffness was assigned to evaluate its
performance in two orthogonal directions. The scaled ground motions were used for
analysis and the maximum resultant forces are reported. The modeling assumptions are
presented as follows:
Mass
As presented earlier in this Chapter, close to 80 modes of vibration are necessary to
entirely capture the overall response of the structure. The following assumptions were
made to consider the mass of structure in local directions (longitudinal and transverse)
and in the two orthogonal directions (chord and radial).
Local Directions: The mass lumped at the node of the SDoF model is the weight
of the superstructure and part of the weight of the participating piers based on
their participation in the respective directions. The masses considered in the
SDoF model in the longitudinal and transverse directions as shown in Section
2.2.4 is 16011.2 and 15711.8 kips, respectively.
Global Directions: The mass lumped at the node of the SDoF model is the weight
of the superstructure and half the weight of the piers, which is 18271.2 kips,
active in both the principal directions along global X and Y.
Stiffness
It is very difficult to characterize the bridge response with a single value of stiffness and
therefore the method 2 presented in Section 2.2.4 and Section 2.2.5 was used to calculate
the bridge lateral stiffness along local ( longitudinal and transverse) and global (chord
and radial) directions, respectively. Therefore, the key assumptions related to stiffness
of the bridge are as follows:
The stiffness of the bridge was calculated along the local and global directions
of bridge both analytically and based on the displacement recorded by applying
unit load in SAP 2000 program.
Local Directions: The values of the equivalent bridge stiffness in the transverse
and longitudinal directions are 28793 kips/feet and 8484 kips/feet, respectively.
62
Global Directions: The values of the equivalent bridge stiffness in the chord (X)
and radial (Y) directions are 10331 kips/feet and 29521 kips/feet, respectively.
Damping
The value of damping used for SDoF analysis was 5% of critical damping, which is
typical for concrete bridges.
2.4.2 Analysis Procedure
A series of time history analysis was performed in NONLIN program using the
simplistic SDoF model of the concerned bridge as described in the preceding sections.
The ground motions selected are scaled according to two seismic hazard levels as
described in Section 2.3.2. The elastic dynamic analysis was performed for the principal
directions, longitudinal and transverse direction (local X and Y), chord and radial
direction (global X and Y) which are corresponding to the weak and strong directions
of the piers respectively. In all there were twelve ground motions (6 for EE and 6 for
MCE) and so, in total, 48 time history analysis were run, 12 along each of the four
directions as described above.
2.4.3 Results and Discussions
The results of the time history analysis considering simplified elastic linear SDoF model
are presented in Table 2.13. Expected earthquakes has lesser demand on the structure
and hence impose smaller displacement on the piers as compared to the maximum
considered earthquake which impose a demand about 3 times of that of EE as far as
displacements and shear forces are concerned in both transverse and longitudinal
direction. This comes from the difference in response spectra itself. The spectral
acceleration of MCE at short period was 1.298g which is 3.3 times the spectral
acceleration at same period for EE and hence the difference in demands between MCE
and EE is justified.
63
Table 2.13 Results of time history analysis in NONLIN using elastic linear SDoF models along local directions (longitudinal and transverse)
Hazard Level
Ground Motion
Longitudinal Transverse Maximum
Shear (kips)
Disp. (feet)
Shear (kips)
Disp. (feet)
Shear (kips)
Disp (feet)
MC
E
NGA 753-FN 2108.23 .2485 6866.14 .2385
Lo
ng
7496.66 0.8464 NGA 753-FP 5494.80 .6477 21294.58 .7396
NGA 828-FN 3475.63 .4097 19715.00 .6847
NGA 828-FP 7181.12 .8464 20814.34 .7229
Tra
ns
21294.5 0.7396 NGA 960-FN 7496.66 .6738 8520.73 .2959
NGA 960-FP 3135.31 .3696 6486.10 .2253
EE
NGA 181-FN 2349.51 .2769 6424.55 .2231
Lo
ng
3669.45 0.4325 NGA 181-FP 2807.07 .3309 3862.65 .1342
NGA 1048-FP 2373.31 .2797 2698.36 .0397
NGA 1048-FP 2132.93 .2514 4507.14 .1565
Tra
ns
7075.49 0.2457 NGA 1116-FP 1748.23 .2061 4438.99 .1542
NGA 1116-FP 3669.45 .4325 7075.49 .2457
Table 2.14 Results of time history analysis in NONLIN using elastic linear SDoF models along global directions (X and Y)
Hazard Level
Ground Motion Global X Global Y Maximum
Shear (kips)
Disp. (feet)
Shear (kips)
Disp. (feet)
Shear (kips)
Disp (feet)
MC
E
NGA 753-FN 2757.22 .2669 7356.05 .2492
X
8426.75 .8157
NGA 753-FP 6905.20 .6684 20409.00 .6913
NGA 828-FN 4165.44 .4032 18875.97 .6394
NGA 828-FP 8426.75 .8157 20743.91 .7027
Y
20743.91
.7027
NGA 960-FN 6136.84 .5940 9195.69 .3115
NGA 960-FP 3801.43 .3680 7144.12 .2420
EE
NGA 181-FN 2950.20 .2856 6803.53 .2305
X
4051.63 .3922
NGA 181-FP 3160.45 .3059 4206.73 .1425
NGA 1048-FP 3048.14 .2950 3168.14 .1073
NGA 1048-FP 3105.05 .3006 5007.08 .1696
Y
6803.53 .2305
NGA 1116-FP 2296.96 .2223 5644.35 .1912
NGA 1116-FP 4051.63 .3922 6282.22 .2128
64
2.5 SUMMARY AND CONCLUSIONS
Multimode analysis of the bridge is carried out in SAP 2000 program considering all the
modes which contribute significantly to the overall behaviour of the structure. The
response spectra for our site (Tacoma) has been obtained for both design earthquake
(DE) and maximum credible earthquake (MCE). A suite of ground motions is selected
for time history analysis and scaled by comparing their corresponding response spectra
to the design spectra for our site. Further, a simplified single degree of freedom (SDoF)
model of the bridge was developed in NONLIN software to examine its behaviour and
compared with the response obtained in SAP 2000 program. The following observations
were made during the analysis process.
83 Eigen values were needed to capture 100% mass participation in both
translation and rotation along all the three directions.
The first three natural periods coming from the modal analysis are 1.54 s, 0.88 s
and 0.75 s, respectively.
First mode is primarily associated with translation in longitudinal direction
while the second mode is associated with translation in transverse direction. The
third mode is associated with torsion (rotation about vertical axis)
The longitudinal stiffness calculated based on the displacement recorded in the
uniform load method in SAP 2000 program is in good agreement with the value
calculated analytically (9844 kips/feet).
However, the transverse stiffness calculated analytically is much higher because,
it is not correct to calculate the pier stiffness in transverse direction considering
it to be fixed at the base.
Expected earthquakes has lesser demand on the structure and hence impose
smaller displacement on the piers as compared to the maximum considered
earthquake which impose a demand about 3 times of that of EE as far as
displacements and shear forces are concerned in both transverse and
longitudinal direction.
-o-o-o-
65
CHAPTER 3 3. UNIFORM LOAD, DYNAMIC MULTIMODE AND PUSHOVER ANALYSIS
UNIFORM LOAD, DYNAMIC MULTIMODE AND PUSHOVER ANALYSIS
3.1 GENERAL OVERVIEW
The bridge was subjected to a uniform load and the stiffness was calculated according
to uniform load method presented in MCEER/ATC 49 document. The previous chapter
deals with the modal analysis and development of the response spectra for the site. In
this chapter the response of the bridge is obtained by appropriately considering the
effects of all the natural modes of vibration significantly contributing to the overall
response according to multimode analysis. A nonlinear static analysis referred to as
pushover analysis is conducted to find out the force-displacement relationship of the
structure in global coordinate system. Triangular lateral load was applied to an
individual pier and to the entire bridge in both longitudinal and transverse directions.
The lateral load-displacement response and the moment curvature plots of the plastic
hinges developed are presented herein.
3.2 UNIFORM LOAD METHOD
3.2.1 Introduction
As stated previously in Chapter 1, the primary objective of uniform load method is to
determine the displacement demand of the superstructure of the bridge. This method is
based on fundamental mode of vibration in the longitudinal or transverse directions.
66
3.2.2 Analysis Procedure
The uniform load method was performed according to MCEER/ATC-49 section 5.4.2.2.
Unit load was applied laterally to the superstructure along longitudinal and transverse
direction and the maximum displacement was determined, based on which the stiffness
and the corresponding time periods were obtained. The elastic seismic response
demand coefficient was obtained from the MCE and EE response spectrum developed
for the site as presented in Chapter 2 corresponding to the period of the structure in
longitudinal and transverse directions.
STEP 1:-The maximum displacement is obtained by assigning uniform distributed load,
Po of 1 kip/ft on entire superstructure in both local transverse and longitudinal
directions respectively.
Figure 3.1 Distribution of load Po in transverse direction
Figure 3.2 Distribution of load Po in longitudinal direction
67
Figure 3.3 Maximum displacement recorded in transverse direction
Figure 3.4 Maximum displacement recorded in longitudinal direction
STEP 2:- Lateral stiffness of the bridge, K is calculated from the expression
o
s
s
P LK
v
v
L
max
maxwhere, Maximum value of displacement recorded on either direction
Length of the superstructure = 1384 ft
STEP 3:- The dead load, W acting on the superstructure was calculated by the following
equation and the weight of the participating piers was added to the self-weight of the
superstructure to get the total mass.
L
super
super
long super piers long
trans er piers trans
W W x dx
W kips
W W W kips
W W W kips
0
sup
( )
9.3 1384 12871.2
16011.2
18271.2
The calculations are based on the participation of the piers in either direction.
68
STEP 4:- Based on the stiffness and weight calculated in the previous steps, the time
period associated with the longitudinal and transverse vibration was calculated
according to the following expression.
2m
WT
Kg
STEP 5:- From the response spectra curve, the demand coefficient, Cd was obtained
corresponding to the longitudinal and transverse period, based on which the equivalent
static earthquake loading, Pe was calculated.
e d
WP C
L
STEP 6:- Finally, the load Pe was applied to the superstructure and the maximum
displacement, base shear and maximum moments were obtained
Following assumptions were made in the analysis
• The analysis was linear.
• The value for acceleration due to gravity, g is 32.174 ft/s2.
• Since linear elastic analysis was done, the results obtained in this section will be
proportional to those obtained in Chapter 1 due to application of a uniform load of 40
kips/feet.
3.2.3 Results and Discussions
Summary of the results obtained from the Uniform Load Method as extracted from SAP
2000 program is shown in Table 1.1.
69
Table 3.1 Summary of uniform load method results obtained from SAP 2000
Direction of applied load
Transverse Longitudinal
Max displacement (ft) 0.037 0.144
Lateral Stiffness (kip/ft) 36808.5 9631.17
Time Period (s) 0.78 1.43
Hazard level EE MCE EE MCE
Cd 0.2486 0.8825 0.133 0.47
Pe (kip/ft) 3.281 11.65 1.5386 5.437
Base Shear (kips) 4542.22 16124.33 2129.49 7525.26
Maximum Moment (kips-feet) 5698.64 20234.42 2704.91 9558.44
Max Displacement after Pe (ft) 0.124 0.442 0.228 0.775
The stiffness and the time period values are in close agreement with the modal analysis
results both in transverse and longitudinal direction which further validates the
uniform load method procedure followed in SAP 2000 program. For transverse
direction, corresponding displacements for EE and MCE are 0.124 feet and 0.442 feet
respectively which translates into base shear of 4542.22 kip and 16124.33 kip, and a
maximum bending moment of 5698.64 kip-ft and 20234.42 kip-ft. Similarly, for
longitudinal direction, corresponding displacements for EE and MCE are 0.228 feet and
0.775 feet, respectively which translates into base shear of 2129.49 kip and 7525.26 kip,
and a maximum bending moment of 2704.91 kip-ft and 9558.44 kip-ft, respectively. The
100%-40% combination rule was applied also to uniform load method, so that it can be
compared with the multimode analysis results. The shear force, bending moment,
displacement and axial force at the piers recorded for 40 kips/feet applied to the
superstructure in longitudinal and transverse directions as described in Chapter 1 is
used in this section for the 100-40 combination. Since the analysis is elastic, all the
resultant forces will be Pe/40 times of those presented in Table 1.4 and Table 1.5 of
Chapter 1. The results thus obtained are shown in Table 3.2 to Table 3.5.
70
Table 3.2 Forces, moments and displacements - 100% EE_Trans + 40% EE_long
Piers Shear(kips)
Moment (kips-feet)
Displacement (feet)
Axial force
(kips) Long Trans Trans Long Long Trans
Left Abut 24.12 258.13 0.00 91.42 0.05 0.14 4.29
Pier 1 0.00 594.34 33906.50 0.00 0.08 0.13 69.74
Pier 2 413.14 621.64 40565.75 23961.84 0.09 0.12 96.86
Pier 3 156.59 513.03 41812.02 12213.71 0.11 0.10 71.41
Pier 4 0.00 562.81 45482.13 0.00 0.12 0.09 41.46
Pier 5 129.03 556.75 44691.50 10063.95 0.11 0.10 91.41
Pier 6 373.50 624.44 40377.43 21663.17 0.09 0.12 113.64
Pier 7 0.00 596.82 33990.18 0.00 0.08 0.13 74.25
Right Abut
24.65 259.10 0.00 91.57 0.05 0.14 4.31
Table 3.3 Forces, moments and displacement - 40% EE_Trans + 100% EE_long
Piers Shear(kips)
Moment (kips-feet)
Displacement (feet)
Axial force
(kips) Long Trans Trans Long Long Trans
Left Abut 11.16 108.61 0.00 39.89 0.02 0.24 1.81
Pier 1 0.00 263.17 14859.76 0.00 0.04 0.24 36.95
Pier 2 792.89 261.70 17007.09 45987.72 0.04 0.23 41.47
Pier 3 329.23 211.43 16839.31 25679.75 0.05 0.22 43.79
Pier 4 0.00 253.50 19450.54 0.00 0.05 0.22 59.97
Pier 5 316.55 305.01 23042.46 24690.53 0.05 0.22 98.58
Pier 6 769.72 265.98 16274.32 44643.93 0.04 0.23 87.23
Pier 7 0.00 268.07 14969.48 0.00 0.04 0.24 48.24
Right Abut
12.52 111.12 0.00 39.95 0.02 0.24 1.85
71
Table 3.4 Forces, moments and displacements - 100% MCE_Trans + 40% MCE_long
Piers Shear(kips) Moment (kips-feet)
Displacement (feet)
Axial force
(kips) Long Trans Trans Long Long Trans
Left Abut 85.64 916.51 0.00 324.59 0.19 0.49 15.25
Pier 1 0.00 2110.12 120382.09 0.00 0.29 0.45 247.54
Pier 2 1461.48 2207.17 144031.92 84765.56 0.33 0.41 343.89
Pier 3 553.67 1821.60 148462.91 43186.79 0.41 0.36 253.44
Pier 4 0.00 1998.14 161484.56 0.00 0.44 0.31 146.83
Pier 5 455.85 1976.14 158643.25 35554.65 0.41 0.36 324.03
Pier 6 1320.82 2217.09 143368.95 76607.26 0.33 0.41 403.14
Pier 7 0.00 2118.90 120678.56 0.00 0.29 0.45 263.49
Right Abut
87.49 919.95 0.00 325.11 0.19 0.49 15.30
Table 3.5 Forces, moments and displacements - 40% MCE_Trans + 100% MCE_long
Piers Shear(kips) Moment (kips-feet)
Displacement (feet)
Axial force
(kips) Long Trans Trans Long Long Trans
Left Abut 39.61 385.54 0.00 141.55 0.08 0.85 6.41
Pier 1 0.00 933.90 52735.02 0.00 0.13 0.83 131.01
Pier 2 2801.70 928.96 60370.89 162498.57 0.14 0.81 147.19
Pier 3 1163.20 750.60 59789.65 90729.77 0.17 0.79 155.16
Pier 4 0.00 899.49 69036.57 0.00 0.18 0.77 211.99
Pier 5 1118.21 1081.23 81705.52 87220.14 0.17 0.79 348.69
Pier 6 2719.59 944.09 57783.29 157736.35 0.14 0.81 308.82
Pier 7 0.00 951.20 53122.94 0.00 0.13 0.83 170.88
Right Abut
44.40 394.39 0.00 141.76 0.08 0.85 6.56
72
3.2.4 Summary
The demand is higher for MCE than EE as expected. The maximum moment, shear and
displacement was observed to be approximately 3.5 times for MCE compared to EE,
similar to the results obtained for simplified SDoF model in NONLIN program as
presented in Chapter 2. The observed maximum displacements are 0.44 feet and
0.78 feet in transverse and longitudinal directions, respectively. Coupling of modes in
orthogonal directions are neglected for the analysis purpose. However, from the results,
it can be seen that there are some traces of coupling between the orthogonal modes
which is because there is some moment and shear generated in the direction orthogonal
to loading.
3.3 DYNAMIC MULTI-MODE ANALYSIS
3.3.1 Introduction
The seismic analysis for the bridge as modeled in SAP 2000 program is done by Dynamic
Multimode method. This method is used to obtain information about the contribution
of each mode towards the motion of the structure. The dynamic multimode behaviour
is investigated based on the participation of various modes. The various mode shapes
and corresponding periods obtained from modal analysis are used. According to
MCEER/ATC 49 report, the number of modes included in the analysis shall be atleast 3
times the number of spans in the model for regular bridges and a total mass
participation of 90%. This is achieved at the 27th mode for the bridge as presented in the
previous chapter.
3.3.2 Analysis Procedure
The response of the structure during a seismic event of MCE and EE level was
determined using the multimode method of analysis. EE and MCE response spectra
corresponding to 5% damping was constructed in Chapter 2. The spectra were assigned
in two principal orthogonal directions, longitudinal and transverse. As suggested in
Article 5.4.2.3 of MCEER ATC 49, the member forces and displacements due to a single
component of ground motion can be estimated by combining the respective response
quantities from the individual modes by Complete Quadratic Combination (CQC)
method. In addition, according to Article 3.6, the maximum force due to two or three
73
orthogonal ground motion components, shall be obtained by the 100%-40%
combination forces due to the individual seismic loads. Thus, in the present project the
modes were combined using CQC method and the directional effects were considered
by 100%-40% rule. Ambient damping of 5% was considered to be typical for concrete
bridges and hence used in the analysis.
The analysis procedure followed in SAP 2000 program is presented as follows:
The load case type was defined for response spectra in SAP2000 and calculations
are done based on CQC (Complete Quadratic Combination) rule.
The General Modal Combination (GMC) values for f1 and f2 are taken as 1 and
0 respectively, where f1 and f2 are frequencies that define the rigid response
content of the ground motion
The default value of f2 is taken as 0 indicating infinite frequency. For the default
value, GMC method gives results similar CQC method.
The response spectra for EE and MCE earthquakes are defined in SAP 2000
program.
The load combinations are calculated by 100%-40% rule as specified in MCEER
ATC 49. Based on this, for ‘Absolute’ Directional Combination the scale factor is
taken as 1. The SRSS directional combination was not considered.
The structure is analyzed for these load combinations of EE and MCE, in both
transverse and longitudinal directions.
75
Figure 3.7 Load case 100 MCE - Long + 40 MCE - Trans
Figure 3.8 Load case 100 MCE - Trans + 40 MCE - Long
76
Figure 3.9 Load case 100 EE - Long + 40 EE - Trans
Figure 3.10 Load case 100 EE - Trans + 40 EE - Long
77
3.3.3 Results and Discussions
The 2D stick model of the bridge was subjected to Expected Earthquake and Maximum
Considered Earthquake loads in SAP2000 program. The response of bridge was
computed in terms of joint displacement, shear force and bending moments for different
members. It should be noted that the effect of the dead load have been tabulated
separately in Table 3.6.Table 3.7 to Table 3.10 contain the resultant forces, Table 3.11 and
Table 3.12 presented the resultant displacements only due to seismic loading. The
discussion of the results in terms of force and displacement demands are presented
herein.
Table 3.6 Forces and moments under dead load
Forces and moments in Substructure
Longitudinal direction
Transverse direction Axial force
(kip) Support location
Shear
(kip)
Moment
(kip ft)
Shear
(kip)
Moment
(kip ft)
Left abutment 637.2 0 0.142 13.25 0
Pier 1 0 144.46 0.245 0 1818.00
Pier 2 4.85 181.49 0.247 248.08 1557.00
Pier 3 1.21 125.89 0.801 094.16 1623.19
Pier 4 0 172.58 0.840 0 1623.18
Pier 5 0 122.59 0.840 0 1623.18
Pier 6 7.692 177.98 0.310 446.11 1557.00
Pier 7 0 142.35 0.246 0 1818.78
Right abutment 637.196 0 0.143 13.4 0
78
Table 3.7 Forces and moments for EE - 100% EE_Long + 40% EE_Trans
Pier No.
Longitudinal Transverse Axial Force
(Kip) Shear
(Kip)
Moment
(Kip-ft)
Shear
(Kip)
Moment
(Kip-ft)
Abutment 1 8.135 344.809 168.917 7308.002 33.398
Pier 1 275.635 10352.7729 643.082 32312.918 15.568
Pier 2 375.995 19503.749 657.851 35476.902 9.087
Pier 3 196.118 10108.8446 650.734 44985.486 18.234
Pier 4 122.583 5739.428 761.313 52667.77 7.330
Pier 5 196.176 10110.4316 650.753 44987.154 18.236
Pier 6 376.003 19503.5557 657.840 35476.85 9.084
Pier 7 275.713 10355.72 643.078 32313.08 15.566
Abutment 2 8.134 344.6982 168.921 7308.2031 33.416
Table 3.8 Forces and moments for EE - 100% EE_Trans + 40% EE_Long
Pier No.
Longitudinal Transverse Axial Force
(Kip) Shear
(Kip)
Moment
(Kip-ft)
Shear
(Kip)
Moment
(Kip-ft)
Abutment 1 9.311 402.5184 128.528 5559.594 32.879
Pier 1 391.975 14722.46 447.424 22348.29 25.359
Pier 2 656.854 35290.76 444.287 23835.345 13.715
Pier 3 367.409 20216.915 387.613 25900.009 28.402
Pier 4 306.358 14478.88 304.634 21074.615 2.936
Pier 5 367.433 20218.201 387.649 25902.866 28.403
Pier 6 656.893 35292.95 444.364 23839.715 13.714
Pier 7 391.972 14722.38 447.513 22353.22 25.359
Abutment 2 9.310 402.4965 128.504 5560.6226 32.895
79
Table 3.9 Forces and moments for MCE - 100% MCE_Long + 40% MCE_Trans
Pier No.
Longitudinal Transverse Axial Force
(Kip) Shear
(Kip)
Moment
(Kip-ft)
Shear
(Kip)
Moment
(Kip-ft)
Abutment 1 28.907 1225.3025 600.342 25973.152 118.613
Pier 1 993.817 37327.497 2281.680 114662.0898 55.595
Pier 2 1322.079 68960.6176 2330.013 125658.266 32.422
Pier 3 699.845 35743.099 2301.748 159105.412 64.916
Pier 4 437.150 20518.7347 2692.952 186279.955 26.289
Pier 5 700.052 35748.710 2301.818 159111.3039 64.924
Pier 6 1332.109 68959.936 2329.973 125658.03 32.413
Pier 7 994.1 37338.153 2281.664 114662.62 55.589
Abutment 2 28.906 1224.8778 600.358 25973.854 118.677
Table 3.10 Forces and moments for MCE - 100% MCE_Trans + 40% MCE_Long
Pier No.
Longitudinal Transverse Axial Force
(Kip) Shear
(Kip)
Moment
(Kip-ft)
Shear
(Kip)
Moment
(Kip-ft)
Abutment 1 8.135 344.6892 168.917 7308.002 33.398
Pier 1 1413.287 53082.645 1587.481 79300.82 90.609
Pier 2 2325.673 124775.2836 1573.527 84425.745 48.969
Pier 3 1309.983 71479.3927 1371.968 91656.6892 101.202
Pier 4 1092.524 51280.258 1077.564 74358.529 10.529
Pier 5 1310.067 71483.940 1372.099 91666.7887 101.203
Pier 6 2325.81 124783.011 1573.801 84441.21 48.966
Pier 7 1413.278 53082.3679 1587.797 79318.310 90.609
Abutment 2 8.134 344.6892 168.921 7308.2031 33.416
80
Table 3.11 Displacement under Expected Earthquake
Location
100% EE_Long + 40% EE_Trans
100% EE_Trans + 40% EE_Long
Long (ft) Trans (ft) Long (ft) Trans (ft)
Left Abutment 0.0433 0.1095 0.0333 0.1813
Pier 1 0.0814 0.1053 0.0565 0.1813
Pier 2 0.0859 0.0975 0.0579 0.1766
Pier 3 0.1252 0.0852 0.0729 0.1721
Pier 4 0.1463 0.066 0.0586 0.1650
Pier 5 0.1252 0.0852 0.0729 0.1722
Pier 6 0.0859 0.0975 0.0579 0.1766
Pier 7 0.0814 0.1053 0.0565 0.1813
Right Abutment 0.0433 0.1095 0.0333 0.1837
Table 3.12 Displacement under Maximum Credible Earthquake
Location
100% MCE_Long + 40% MCE_Trans
100% MCE_Trans + 40% MCE_Long
Long (ft) Trans (ft) Long (ft) Trans (ft)
Left Abutment 0.1541 0.3873 0.0433 0.1095
Pier 1 0.2886 0.3723 0.2003 0.6410
Pier 2 0.3044 0.3447 0.2050 0.6245
Pier 3 0.4428 0.3013 0.2578 0.6068
Pier 4 0.5174 0.2335 0.2070 0.5835
Pier 5 0.4428 0.3014 0.2578 0.6087
Pier 6 0.3044 0.3447 0.2051 0.6426
Pier 7 0.2886 0.3723 0.2003 0.6411
Right Abutment 0.1541 0.3873 0.0433 0.1095
The following observations are made:
i. When the bridge is tested under pure dead load very large axial forces but small
shear and moment values are obtained.
ii. On application of Expected Earthquake, the axial force and shear values are
small but large moments are obtained in the piers as expected.
iii. As for Maximum Credible Earthquake load, very large shear and moment values
are observed compared to expected earthquake due to higher demand.
81
iv. The maximum displacement occur in the abutments during the application of
Earthquake load and it is 0.183 ft (2.196 inches) whereas on application of Maximum
Credible Earthquake load, the maximum displacement occur in the abutments and it is
0.6496 ft (7.795 inches).
It can be observed that the shear forces obtained in the two principal directions are
comparable for both EE and MCE, however, at certain locations higher shear forces was
recorded in the transverse direction (strong direction). This is because the bridge has
higher stiffness in transverse direction and hence attract larger seismic forces. On the
contrary, the deformation obtained in transverse direction was much smaller due to
higher stiffness in strong direction.
3.4 PUSH-OVER ANALYSIS
3.4.1 Introduction
Pushover analysis is a step-by-step analysis in which the lateral loads of constant
relative magnitude are applied to given structure and progressively increased until a
target displacement is reached to determine their displacement capacity [Bruneau et al.
2013]. The strength of the component is taken as a function of the displacement
component, which is found by performing a lateral load displacement analysis
accounting for the nonlinear behavior of the structure. It is a non-linear static analysis
that gives vital information regarding the behaviour of the structure in the inelastic
range. The primary purpose of performing pushover analysis is to determine the
ultimate lateral load resistance of the structure and the sequence of yielding events
needed to reach the ultimate load, or the magnitude of plastic deformations at the target
displacement. It involves monotonically “pushing” the structure at controlled steps and
the response of the structure at each of these steps is monitored.
It must be recognized that the information acquired from a pushover analysis is highly
dependent on the lateral load distribution pattern adopted [Lawson et al. 1994].
Therefore, it is recommended to consider multiple lateral-load distribution patterns in
order to capture the possible effects of dynamic excitation. The triangular loading
pattern capture the lower modes of the structure while the parabolic loading pattern
capture the effect of the higher modes. For the present structure, the lateral load resisting
82
system of the bridge (piers) were subjected to triangular load pattern and the response
was studied in details. In our case, out of the various components of the bridge, the
columns/piers designed are considered to be the weakest out of the lot and are thus
checked for their inelastic behavior under lateral loading. The analysis is performed on
individual pier in both longitudinal and transverse direction separately.
Section ATC-C5.4.3, states that the analysis determines the component which reaches
its inelastic deformation capacity first and the corresponding displacement for the
maximum allowable deformation defines the maximum displacement capacity.
Damages can be of various sorts, one of them being plastic hinge rotation. A plastic
hinge, in effect is defined as the part of an element which deforms inelastically as a result
of plastic bending at that point.
3.4.2 Description of Model
According to MCEER/ATC 49 Report, the displacement capacity verification analysis
(pushover analysis) shall be applied to the individual piers to determine the lateral load
displacement behaviour of the pier. The capacity evaluation was performed on
individual piers in the longitudinal and transverse directions separately. The pushover
response of the entire structure was also evaluated and presented in detail.
The model of the bridge developed in SAP 2000 program was used for this purpose. A
six member model is generated, with the top member representing the rigid link and
the bottom most member for the foundation. Four elements were used to model the pier,
to take into account the various cross-sections and reinforcement detailing. The
reinforcement and concrete detailing is imbibed into the structure based on the design
details presented in FHWA Design Example 5 and shown in Figure 3.11 and Figure 3.12.
The pushover model is as shown in the Figure 3.13 below.
84
Figure 3.13 Pushover Model of the 70 feet pier
3.4.3 Plastic Hinge Model
A variety of plastic hinge properties are available in SAP 2000 program. The fiber PMM
hinge was selected to be used for the present project as it is expected to give more
realistic results. This hinge is more “natural” than the Coupled PMM hinge, since it
automatically accounts for axial force-moment interaction, changing moment-rotation
curve, and plastic axial strain.
The Fiber P-M2-M3 (Fiber PMM) hinge models the axial behavior of a number of
representative axial “fibers” distributed across the cross section of the frame element.
Each fiber has a location, a tributary area, and a stress-strain curve. Axial force (P), major
axis moment (M2) and minor axis moment (M3) are calculated by numerically
combining the axial stresses. Similarly, the axial strains of each fiber element are
computed from the axial deformation (U1) and the corresponding rotations, R2 (major
axis) and R3 (minor axis). The nonlinear stress-strain properties of the individual fibers
are presented in the succeeding sections.
3.4.4 Non-linear models for pushover analysis
The reinforcement detailing was done using the Section Designer property of SAP 2000
program. Both the longitudinal bars and the transverse ties were provided as shown in
Figure 3.14 and Figure 3.15. In section designer the section was sub divided into various
fibers with 16 fibers along 2 axis and 90 fibers along 3 axis thus ensuring that each of the
fibers passes through one reinforcement bars in either directions as shown in Figure 3.16
85
and Figure 3.17. The fiber data of the various sections obtained from section designer
was directly copied to define the PMM fiber hinge model used in the present study.
Figure 3.14 Reinforcement detailing in section designer for the column top section
Figure 3.15 Reinforcement detailing in section designer for the column bottom section
86
Figure 3.16 Fiber model of column top in section designer
Figure 3.17 Fiber model of column base in section designer
Bilinear model
A simplified stress-strain model was used to incorporate the non-linear material
behaviour for both concrete and rebar. Perfectly bilinear behavior is assumed for
pushover analysis as shown in Figure 1.8 to Figure 3.21.
Figure 3.18 Bilinear Stress strain model of concrete
87
Figure 3.19 Non-linear material property of concrete
Figure 3.20 Bilinear Stress strain model of rebar
Figure 3.21 Material Property input in SAP 2000
-80
-60
-40
-20
0
20
40
60
80
-0.24 -0.12 0 0.12 0.24
Str
ess (
ksi)
Strain
88
Plastic Hinge Definition
The definition of the plastic hinge at the top of the pier is shown in Figure 3.22. The
fibers created at the section designer was copied to the fiber hinge as shown in Figure
3.23. The plastic hinge definition in the other locations are similar to the one shown in
Figure and hence not shown separately. Shear hinge was not added to the members as
it was checked manually that the shear capacity of the section won’t be reached before
reaching the maximum flexural capacity. Hence, only flexural hinges were considered.
Figure 3.22 Plastic hinge definition in SAP 2000 program at pier bottom
Figure 3.23 Fiber hinge model in SAP 2000
89
3.4.5 Analysis Procedure
The load patterns that are needed for the pushover analysis include the gravity load that
may be acting on the structure before the lateral seismic loads are applied [CSI 2009]
and the lateral loads that will be used to push the structure in the principal directions.
In SAP 2000 program a nonlinear load case is required to be defined and run in sequence
with the lateral pushover load case. Dead load was used in the present model to define
the initial static non-linear load at zero step and the lateral pushover load was assumed
to start from this case. The gravity load coming from the deck was applied as a point
load at the top of the pier. The pushover load case was applied in a displacement
controlled mode a pre-determined target displacement set at 2 feet. Triangular loading
pattern was used to study the pushover behaviour of the bridge as shown in Figure 3.24.
For the individual piers load was applied in local directions to investigate the behaviour
of the piers in longitudinal and transverse directions. However, for the pushover
analysis of the entire bridge the load is applied in global directions to study its
behaviour in radial and chord directions.
Figure 3.24 Triangular loading pattern used in SAP 2000 program
90
Figure 3.25 Typical pushover load case in SAP 2000 program
For the individual piers, the displacement monitored is the displacement of the node
located at the top of the respective piers, while for the pushover analysis of the entire
bridge the displacement of the center of the superstructure is monitored.
Plastic Hinge Length
The calculation of the plastic hinge length and the plastic rotation capacity was carried
out in accordance with the Article 7.8.6 of MCEER/ATC 49 document.
For life Safety Performance,
The plastic rotational capacity is determined by the following equation:
p = 0.11*𝐿𝑝
𝐷′∗ (𝑁f)-0.5 radians (ATC 49 – 7.8.6.1-1)
Where
Nf = Number of cycles of loading expected at the maximum displacement amplitude=
3.5 (Tn)-1/3
Lp = Effective plastic hinge length = 0.08 ∗𝑀
𝑉+ 4400 𝐸𝑌𝐷𝑏
D’ = center-to-center distance between the extreme reinforcement on opposite faces of
the member
91
Figure 3.26 Cross section of the pier considered for Push over analysis
Properties:
Young’s Modulus for steel reinforcement = 29000 ksi
Yield strength of the reinforcement = 60 ksi
€y = 0.0021
Db = main reinforcement diameter = 1.41 inches ( # 11 bars)
Tn = Natural time period = Longitudinal = 1.54 secs
= Transverse = 0.88 secs
Nf = 3.5 (Tn)-1/3
= Longitudinal = 3.031
= Transverse = 3.652
D’ = Longitudinal = 5.53 ft = 66.36 inches
= Transverse = 19.28ft = 231.36 inches
92
Tabulating the above results,
For Triangular Loading Lp (inches) ᶱp (radians)
For the 70 feet tall pier L T
Plastic hinge at the bottom 57.63 0.0548 0.0143
Plastic hinge at the neck 22.167 0.0210 0.0055
Plastic hinge at the top 12.83 0.0122 0.0032
For the 50 feet tall pier
Plastic hinge at the bottom 44.84 0.0427 0.0112
Plastic hinge at the neck 22.38 0.0211 0.0056
Plastic hinge at the top 12.83 0.0122 0.0032
Based on ATC 49-7.8.6.2, for Immediate Use Performance, the maximum rotational
capacity should be limited to 0.01 radians.
Location of Plastic Hinge
For the individual piers, plastic hinges were considered only at the bottom of the
members, as under lateral loading cantilever action is expected, and plastic hinges will
only be formed at the pier bottom. However, while performing pushover analysis of the
entire structure, plastic hinges were initially to be formed at the base of the pier above
the foundation, the neck and at the top of the pier. After the first analysis it was observed
that the plastic moment capacity was not reached at the top and hence the plastic hinge
at the top of the pier was not considered for further analysis.
In SAP 2000, the plastic hinge is assigned at a discrete point. In the present project the
hinges were assigned at a distance Lp/2 from the nodes, where Lp represent the effective
plastic hinge length calculated according to MCEER/ATC 49.
Figure 3.27 Typical plastic hinge assignment at pier bottom in SAP 2000
93
Figure 3.28 Typical plastic hinge assignment at the column neck in SAP 2000
3.4.6 Results and Discussions
70 feet pier
The 70 feet pier at the middle of the bridge was considered for pushover analysis. It was
subjected to both longitudinal and transverse directions and the behaviour observed is
presented in this section.
Transverse
The deflected shape of the 70 feet individual pier during pushover analysis in transverse
direction is shown in Figure 3.29. The transverse shear is transferred in the SAP 2000
model and hence the rigid link connecting the pier to the superstructure does not move
with the pier. However, the pier acts as a simple cantilever with plastic hinges formed
only at the bottom. The lateral force-displacement relationship of the individual 70 feet
pier in transverse direction is shown in Figure 3.30. Bilinear load –displacement
relationship was observed as the material properties considered for both steel and
concrete was bilinear in nature.
94
Figure 3.29 Typical deflected shape of the 70 feet pier in transverse direction
Figure 3.30 Force displacement relationship of the 70 feet pier in transverse direction
It was observed that the plastic moment capacity of 1.15 X 106 kips/inch was from the
moment rotation plot of the plastic hinge at the bottom of the pier, which was actually
the maximum capacity of the section as observed in section designer which further
validates our definition of plastic hinge. The typical bilinear behaviour of the 70 feet pier
is shown and the stiffness calculated from pushover curve was compared with the one
obtained in Chapter 2 analytically in succeeding section.
0
500
1000
1500
2000
2500
0 5 10 15 20 25
La
tera
l F
orc
e (
kip
s)
Displacement (inches)
95
Figure 3.31 Moment rotation plot of the plastic hinge at the bottom of the 70 feet pier in transverse direction
From the moment rotation plot, it can be seen that the plastic moment capacity of the
pier in the transverse direction is Mp = 1.15 * 106 kips-inches.
So based on the plastic moment capacity, the maximum shear reached in the pier section
considering cantilever action can be calculated according to the equation pV M L
which comes out to be approximately 1379 kips. The shear strength provided by the
concrete alone in the transverse direction was 2229 kips as reported in the FHWA
Design Example 5, which is much higher than the maximum shear reached. Also, it must
be noted that the actual shear capacity of the section at the bottom of the pier will be
even greater than 2229 kips due to the shear strength of the confining steel reinforcement
and hence, it will be much higher than the maximum base shear (2200 kips) observed
during this case.
Therefore, the shear capacity of the section is greater than the maximum base shear
achieved and shear hinging is thus not possible before flexural yielding along transverse
direction at the bottom of the pier. Similar checks were also carried out along
longitudinal and transverse directions at other plastic hinge locations. In all the cases
the shear capacity of the section was observed to be higher than the maximum base
shear and hence our assumption of not considering the shear hinges is validated.
Longitudinal
The deflected shape of the individual pier in longitudinal direction is shown in Figure
3.32. As the pier 4 was sliding in nature along longitudinal direction as described
0
5 105
1 106
1.5 106
0 0.005 0.01 0.015 0.02 0.025
Mo
me
nt
(kip
s-i
nch
es)
Rotation (radians)
96
previously, cantilever action was observed with plastic hinge being developed only at
the bottom of the pier. The lateral force-displacement relationship of the individual 70
feet pier in transverse direction is shown in Figure 3.33. Exactly bilinear load –
displacement relationship was observed as the material properties considered for both
steel and concrete was bilinear in nature.
Figure 3.32 Typical deflected shape of the 70 feet pier in longitudinal direction
Figure 3.33 Force displacement relationship of the 70 feet pier in longitudinal direction
It can be observed that much higher lateral strength was observed in the transverse
direction compared to longitudinal direction, mainly because of higher plastic moment
capacity in transverse direction.
0
200
400
600
800
1000
0 5 10 15 20 25
La
tre
al F
orc
e (
kip
s)
Displacement (inches)
97
Figure 3.34 Moment rotation plot of the plastic hinge at the bottom of the 70 feet pier in longitudinal direction
50 feet pier
The 50 feet pier at the middle of the bridge was considered for pushover analysis. It was
subjected to both longitudinal and transverse directions.
Transverse
Figure 3.35 Force displacement relationship of the 50 feet pier in transverse direction
0
1 105
2 105
3 105
4 105
5 105
0 0.005 0.01 0.015 0.02 0.025
Mo
me
nt
(kip
s-i
nch
es)
Rotation (radians)
0
600
1200
1800
2400
3000
0 5 10 15 20 25
La
tera
l F
orc
e (
kip
s)
Displacement (inches)
98
Figure 3.36 Moment rotation plot of the plastic hinge at the bottom of the 50 feet pier in transverse direction
Longitudinal
Figure 3.37 Force displacement relationship of the 50 feet pier in longitudinal direction
0
5 x 105
1 x 106
1.5 x 106
0 0.007 0.014 0.021 0.028 0.035
Mo
me
nt
(kip
s-i
nch
es)
Rotation (radians)
0
200
400
600
800
1000
0 5 10 15 20 25
La
tre
al F
orc
e (
kip
s)
Displacement (inches)
99
Figure 3.38 Moment rotation plot of the plastic hinge at the bottom of the 50 feet pier in longitudinal direction
Pushover analysis of entire bridge
Transverse
The deflected shape of the entire bridge during pushover analysis in transverse and
longitudinal direction is shown in Figure 3.39 and Figure 3.41, respectively.
Figure 3.39 Typical deflected shape of the pier in transverse direction
0
1 x 105
2 x 105
3 x 105
4 x 105
5 x 105
0 0.008 0.016 0.024 0.032 0.04
Mo
me
nt
(kip
s-i
nch
es)
Rotation (radians)
100
Figure 3.40 Force displacement relationship of the bridge in transverse direction
Hinges were observed to be formed at the bottom of the piers initially. The hinges at the
neck were formed at a much higher displacement thereby resulting in much higher
lateral strength in the transverse direction. The moment curvature plots were checked
in SAP 2000 program and it was observed that the maximum plastic capacity of the
section was reached at a plastic rotation of approximately in 0.005 radians, while plastic
hinges were formed at the top only after 0.02 radians approximately.
Longitudinal
Figure 3.41 Typical deflected shape of the pier in longitudinal direction
The lateral force displacement relationship of the entire bridge in longitudinal direction
is presented in Figure 3.42. It can be seen much higher capacity was achieved in the
transverse direction, primarily due to high plastic moment capacity along that direction.
0
5000
10000
15000
20000
25000
30000
0 2 4 6 8
La
tera
l F
orc
e (
kip
s)
Displacement (feet)
101
Figure 3.42 Force displacement relationship of the bridge in longitudinal direction
3.4.7 Comparison of stiffness with analytical results
The initial stiffness obtained from the pushover curves are compared with the stiffness
obtained in Chapter 2 analytically. It can be seen that the values are comparable which
further validates the pushover curves obtained.
Table 3.13 Comparison of stiffness
Stiffness (kips/feet) Longitudinal Transverse
Pushover Analytical Pushover Analytical
70 feet pier 5872 5022 1728 1259
50 feet pier 8100 7841 3375 2983
Stiffness (kips/feet) Chord Radial
Bridge 10500 10331 28889 29521
3.5 SUMMARY AND CONCLUSIONS
The results of uniform load method are as follows
A uniform load method of analysis was used to get response of a simplified
model of the bridge was calculated in terms of Max displacement (ft), Lateral
Stiffness (kip/ft) and Time Period (s). these values are observed to be higher
along the longitudinal direction than in transverse
0
1000
2000
3000
4000
5000
0 2 4 6 8
La
tera
l F
orc
e (
kip
s)
Displacement (feet)
102
The stiffness and the time period values are in close agreement with the modal
analysis results both in transverse and longitudinal direction which further
validates the uniform load method procedure followed in SAP 2000 program.
The force, base shear, bending moment and maximum displacement values
calculated along transverse and longitudinal directions for MCE are larger than
those of EE.
In multimode analysis, 27 modes are required to achieve a total mass
participation factor of 90% to comply MCEER/ATC 49 specification according
to which the number of modes included in the analysis shall be atleast 3 times
the number of spans in the model for regular bridges (presented in previous
chapter)
The results of multimode analysis are as follows
When bridge was tested only under dead load, very large axial forces but small
shear and moment values are obtained.
Very large shear and moment values are observed for Maximum Credible
Earthquake in contrast to Expected Earthquake.
The displacement due to MCE is higher than that of EE as expected.
The results of Pushover Analysis are as follows:
For the individual pier model, along both transverse and longitudinal directions,
the shear developed is much greater than the shear capacity of the section and
hence no shear hinge is formed. Hence a flexural plastic hinge is developed at
the base.
The moment curvature plots were checked in SAP 2000 and it was observed that
the maximum plastic capacity of the section was reached.
-o-o-o-
103
CHAPTER 4 4. TIME HISTORY ANALYSIS
TIME HISTORY ANALYSIS
4.1 GENERAL OVERVIEW
In the previous chapters linear static analysis was carried out which can estimate the
seismic demand of the structure when the material and geometric nonlinearity is not
considered. However, nonlinearity is most likely expected during a seismic event.
Therefore, it is not possible to capture the dynamic behaviour of the structure using
static methods of analysis. Therefore, time history analysis is carried out to investigate
the dynamic response of the bridge both at MCE and EE hazard levels. Initially linear
SDoF analysis was carried out on the bridge to get an idea of its elastic dynamic
response. Both nonlinear SDoF and MDoF analysis was then carried out to capture the
nonlinear dynamic response of the bridge according to MCEER/ATC 49 report. The
nonlinear behaviour of the structural components were included by assigning PMM
fiber hinges in the column elements as described in the previous chapter for pushover
analysis. This chapter deals with the response of the bridge obtained by Nonlinear
Dynamic Analysis. Ground motions scaled to the response spectra for both MCE and
EE hazard levels obtained in Chapter 2, is used for time history analysis. The resultant
forces and the maximum displacements recorded at various hazard levels are tabulated
and compared.
4.2 SELECTED GROUND MOTIONS
According to Cl. 3.4.1 of MCEER ATC 49 report, the design spectra for expected
earthquake (EE) and maximum considered earthquake (MCE) was constructed in USGS
website. Based on this, 3 ground motions were scaled in PEER at each hazard level as
104
described in Chapter 2. The final ground motions selected for time history analysis and
their corresponding scale factors are shown in Table 1.1.
Table 4.1 Selected Ground Motions
No Ground Motion NGA# Scale M Year Station
MC
E
1 Cape Mendocino 828 1.0 7.01 1992 Petrolia
2 North Ridge 960 1.0 6.69 1994 Canyon Country
-W Lost Cany
3 Loma-Prieta 753 1.0 6.93 1989 Corralitos
EE
1 North Ridge 1048 0.3788 6.69 1994 North Ridge 17645
Saticoy St
2 Imperial Valley 181 0.4671 6.53 1979 El-Centro #6
3 Kobe Japan 1116 0.7236 6.90 1995 Shin-Osake
4.3 LINEAR ELASTIC TIME HISTORY ANALYSIS
4.3.1 Analysis Procedure
For linear SDOF analysis, the program NONLIN was used. The bridge behavior was
considered in both local and global directions. The longitudinal and transverse were
considered first, followed by the chord and radial directions, also labeled Local X and
Local Y, and Global X and Global Y, respectively. The stiffness of the bridge was
calculated analytically in Chapter 2 of this report. The mass and stiffness values for
various directions are tabulated in Table 4.2.
Table 4.2 Mass and stiffness values
Direction Mass (kips) Stiffness (kips/feet)
Longitudinal (Local X) 16011.2 8484
Transverse (Local Y) 15711.8 28793
Chord (Global X) 18271.2 10331
Radial (Global Y) 18271.2 29521
To model the bridge in NONLIN, non-degrading linear analysis options were selected.
A value of 5% damping was used. The inputs for the longitudinal direction are
illustrated in Figure 4.1.
105
Figure 4.1 Inputs in NONLIN program for linear analysis along longitudinal direction
A total of 12 ground motions were applied for each of the four directions, totaling in 48
analyses. Three ground motions were considered for both MCE and EE, in two
directions. The ground motions were obtained from the PEER database. The MCE
ground motions obtained from the PEER database had a scale factor of 1.0, while the EE
ground motion scale factors varied. In order to use these ground motions in NONLIN,
the .acc files from PEER were inputted into an excel spreadsheet and the maximum
absolute value was found for each one. Then, this value was multiplied by the scale
factor to get the maximum acceleration in terms of g that would be used for NONLIN.
The ground motions were chosen specifically to match up with the ones already in
NONLIN so that no further inputs would be needed. When inputting the ground
motions for analyses, the motion with the corresponding NGA # was selected and then
the maximum acceleration was specified. The ground motions used, as well as their
PGAs scaled at various hazard levels are listed in Table 4.3.
106
Table 4.3 Scaled PGA (g) of respective GMs
EE MAX SCALED MCE MAX SCALED
181 FN 0.441714 0.206325 753 FN 0.484298 0.484298
181 FP 0.400183 0.186925 753 FP 0.513568 0.513568
1048 FN 0.413276 0.156549 828 FN 0.614812 0.614812
1048 FP 0.422155 0.159912 828 FP 0.629605 0.629605
1116 FN 0.186614 0.135034 960 FN 0.465964 0.465964
1116 FP 0.271347 0.196347 960 FP 0.336958 0.336958
4.3.2 Results
For each ground motion, maximum displacement, and base shear values were obtained
from NONLIN program. The base shear was taken as the maximum spring force from
the output file. These values are shown in Table 4.4.
Table 4.4 Resultant forces and displacements in local directions
Hazard Level
Ground Motion
Longitudinal Transverse Maximum
Shear (kips)
Disp. (feet)
Shear (kips)
Disp. (feet)
Shear (kips)
Disp (feet)
MC
E
NGA 753-FN 2108.23 .2485 6866.14 .2385
Lo
ng
7496.66 0.8464 NGA 753-FP 5494.80 .6477 21294.58 .7396
NGA 828-FN 3475.63 .4097 19715.00 .6847
NGA 828-FP 7181.12 .8464 20814.34 .7229
Tra
ns
21294.5 0.7396 NGA 960-FN 7496.66 .6738 8520.73 .2959
NGA 960-FP 3135.31 .3696 6486.10 .2253
EE
NGA 181-FN 2349.51 .2769 6424.55 .2231
Lo
ng
3669.45 0.4325 NGA 181-FP 2807.07 .3309 3862.65 .1342
NGA 1048-FP 2373.31 .2797 2698.36 .0397
NGA 1048-FP 2132.93 .2514 4507.14 .1565
Tra
ns
7075.49 0.2457 NGA 1116-FP 1748.23 .2061 4438.99 .1542
NGA 1116-FP 3669.45 .4325 7075.49 .2457
107
Table 4.5 Resultant forces and displacements in global directions
Hazard Level
Ground Motion Global X Global Y Maximum
Shear (kips)
Disp. (feet)
Shear (kips)
Disp. (feet)
Shear (kips)
Disp (feet)
MC
E
NGA 753-FN 2757.22 .2669 7356.05 .2492
X
8426.75 .8157 NGA 753-FP 6905.20 .6684 20409.00 .6913
NGA 828-FN 4165.44 .4032 18875.97 .6394
NGA 828-FP 8426.75 .8157 20743.91 .7027
Y
20743.9 .7027 NGA 960-FN 6136.84 .5940 9195.69 .3115
NGA 960-FP 3801.43 .3680 7144.12 .2420
EE
NGA 181-FN 2950.20 .2856 6803.53 .2305
X
4051.63 .3922 NGA 181-FP 3160.45 .3059 4206.73 .1425
NGA 1048-FP 3048.14 .2950 3168.14 .1073
NGA 1048-FP 3105.05 .3006 5007.08 .1696
Y
6803.53 .2305 NGA 1116-FP 2296.96 .2223 5644.35 .1912
NGA 1116-FP 4051.63 .3922 6282.22 .2128
Linear elastic time history analysis was also carried out in SAP 2000 program and the
results obtained are tabulated in Table 4.6 and Table 4.7. The comparison of the
maximum values obtained from elastic analysis in SAP 2000 and NONLIN is presented
in Table 4.8. The values obtained from NONLIN were different from those obtained
from SAP 2000. There is a difference of about 20% in the results with the values obtained
from SAP2000 being higher.
Table 4.6 Resultant forces and displacements obtained in linear elastic time history analysis in SAP 2000 program at EE
Load Case Moment (kips-feet)) Shear (kips)
Displacement (feet)
Trans Long Long Trans Long Trans
IV_FNU1+FPU2_EE 12916.67 22408.33 637.30 2058.00 0.18 0.35
IV_FNU2+FPU1_EE 78825.00 29700.00 645.90 1161.00 0.24 0.20
NR_FNU1+FPU2_EE 64891.67 39416.67 666.40 909.00 0.32 0.16
NR_FNU2+FPU1_EE 100000.00 17691.67 483.00 1639.00 0.14 0.27
KJ_FNU1+FPU2_EE 113333.33 32416.67 547.00 1800.00 0.26 0.31
KJ_FNU2+FPU1_EE 127500.00 42416.67 672.00 1950.00 0.34 0.34
108
Table 4.7 Resultant forces and displacements obtained in linear elastic time history analysis in SAP 2000 program at MCE
Load Case Moment (kips-feet)) Shear (kips)
Displacement (feet)
Trans Long Long Trans Long Trans
NR_FNU1+FPU2_MCE 227500.00 77416.67 1300.00 3820.00 0.62 0.63
NR_FNU2+FPU1_MCE 230833.33 83090.33 1450.00 3690.00 0.67 0.63
LM_FNU1+FPU2_MCE 259166.67 152500.00 2730.00 3790.00 0.12 0.65
LM_FNU2+FPU1_MCE 406666.67 68583.33 1820.00 5946.00 0.56 1.05
CM_FNU1+FPU2_MCE 495833.33 124166.67 2400.00 7810.00 1.16 1.33
CM_FNU2+FPU1_MCE 492500.00 133333.33 2850.00 7170.00 1.08 1.29
Table 4.8 Comparison of maximum values recorded for linear time history analysis in SAP 2000 and NONLIN
Hazard
Level
Base Shear (kips) Displacement (feet)
Long Trans Long Trans
NON SAP NON SAP NON SAP NON SAP
MCE 8426.75 12130 20743.9 32080 0.81 1.16 0.70 1.33
EE 4051.63 5731 6803.53 10250 0.39 0.34 0.23 0.35
4.3.3 Summary
As observed from the results of linear elastic SDoF analysis in NONLIN expected
earthquakes has lesser demand on the structure and hence impose smaller displacement
on the piers as compared to the maximum considered earthquake which impose a
demand about 3 times of that of EE as far as displacements and shear forces are
concerned in both local (longitudinal and transverse) and global (chord and radial)
directions. This comes from the difference in response spectra itself. The spectral
acceleration of MCE at short period was 1.298g which is 3.3 times the spectral
acceleration at same period for EE and hence the difference in demands between MCE
and EE is justified.
109
4.4 NON LINEAR DYNAMIC TIME HISTORY ANALYSIS
4.4.1 Introduction
Nonlinear Dynamic Analysis gives the displacement of each node of the structure, thus
giving a good approximation about the response of a structure towards an earthquake.
Ground motions for different locations are fed into NONLIN and SAP2000 program for
SDoF and MDoF, respectively and the structure is analyzed for each. In order to ensure
that the results obtained for each GM are stable, GMs for three different locations are
chosen and the results are compared. A nonlinear mathematical model of bridge has
been defined for the analysis and analysis has been performed for different load cases
to obtain the response quantities.
4.4.2 Code Specification
As mentioned in MCEER ATC 49 under section 5.1.2, “When required the Seismic
Design and Analysis Procedure use the following seismic demand and analysis and/or
seismic displacement capacity verification procedures in order of increasingly higher
level of ability to represent structural behavior. Nonlinear dynamic analysis using
earthquake ground motion records are used to evaluate the displacement and force
demands accounting for inelastic behavior of components”.
4.5 NON LINEAR SDOF TIME HISTORY ANALYSIS
4.5.1 Analysis Procedure
For the non-linear inelastic time history analysis, exact bilinear behavior was
approximated for simplicity. The mass and stiffness values used are the same as those
used for the Linear SDOF analysis, except that only the global directions were
considered. The second stiffness value was considered to be zero to model elastic
perfectly plastic behavior. To model the bridge in NONLIN, Simple Bilinear, nonlinear
analysis criteria were selected. In order to model the bridge this way, a strength value
was required. These values were obtained from the pushover analysis previously done
in SAP2000 and taken as the yield forces (the force until which the behavior of the bridge
is linear) in the global directions. For Global Y, a value of 26000 kips was used and for
Global X, 4250 kips was used as obtained from the pushover curves of the entire bridge
110
in radial and chord directions respectively. An example in the chord direction is
illustrated in Figure 4.2.
Figure 4.2 Inputs in NONLIN program for nonlinear analysis along chord direction
4.5.2 Results
The ground motions were inputted in the same way as they were previously done for
linear SDoF analysis. A total of 24 analyses were run, 12 each in chord and radial
directions and their results are shown in Table 4.9.
111
Table 4.9 Resultant forces and displacements in global directions
Hazard Level
Ground Motion
Global X Global Y Maximum
Shear (kips)
Disp. (feet)
Ductility Shear (kips)
Disp. (feet)
Ductility Shear (kips)
Disp (feet)
MC
E
NGA 753-FN 2757.22 0.2669 0.6488 7356.05 0.2492 0.2840
X
4250 0.915 NGA 753-FP 4250.00 0.7177 1.7447 20409.00 0.6913 0.7880
NGA 828-FN 4165.44 0.4032 0.9801 18875.96 0.6394 0.7288
NGA 828-FP 4250.00 0.915 2.2241 20743.91 0.7027 0.8009
Y
20744 0.703 NGA 960-FN 4250.00 0.5911 1.4369 9195.69 0.3115 0.3550
NGA 960-FP 3801.43 0.368 0.8945 7144.12 0.242 0.2758
EE
NGA 181-FN 2950.20 0.2856 0.6942 6803.53 0.2305 0.2627
X
4052 0.392 NGA 181-FP 3160.45 0.3059 0.7436 4206.73 0.1425 0.1624
NGA 1048-FP 3048.14 0.295 0.7172 3168.14 0.1073 0.1233
NGA 1048-FP 3105.05 0.3006 0.7306 5007.08 0.1696 0.1933
Y
6803 0.231 NGA 1116-FP 2296.96 0.2223 0.5405 5644.35 0.1912 0.2179
NGA 1116-FP 4051.63 0.3922 0.9533 6282.22 0.2128 0.2426
112
A comparison of the linear and non-linear analyses obtained in NONLIN program are shown in the Table 4.10 below:
Table 4.10 Resultant forces and displacements in global directions
Hazard Level
GM
Global X Linear Global X Non Global Y Linear Global Y Non
Shear (kips)
Disp. (feet)
Shear (kips)
Disp. (feet)
Shear (kips)
Disp. (feet)
Shear (kips)
Disp.(feet)
MC
E
NGA 753-FN 2757.22 .2669 2757.22 0.2669 7356.05 .2492 7356.05 0.2492
NGA 753-FP 6905.20 .6684 4250.00 0.7177 20409.00 .6913 20409.00 0.6913
NGA 828-FN 4165.44 .4032 4165.44 0.4032 18875.96 .6394 18875.97 0.6394
NGA 828-FP 8426.75 .8157 4250.00 0.915 20743.91 .7027 20743.91 0.7027
NGA 960-FN 6136.84 .5940 4250.00 0.5911 9195.69 .3115 9195.69 0.3115
NGA 960-FP 3801.43 .3680 3801.43 0.368 7144.12 .2420 7144.12 0.242
EE
NGA 181-FN 2950.20 .2856 2950.20 0.2856 6803.53 .2305 6803.53 0.2305
NGA 181-FP 3160.45 .3059 3160.45 0.3059 4206.73 .1425 4206.73 0.1425
NGA 1048-FP 3048.14 .2950 3048.14 0.295 3168.14 .1073 3168.14 0.1073
NGA 1048-FP 3105.05 .3006 3105.05 0.3006 5007.08 .1696 5007.08 0.1696
NGA 1116-FP 2296.96 .2223 2296.96 0.2223 5644.35 .1912 5644.35 0.1912
NGA 1116-FP 4051.63 .3922 4051.63 0.3922 6282.22 .2128 6282.22 0.2128
113
4.5.3 Summary
Lesser demands were also observed for expected earthquakes compared to maximum
credible earthquakes for nonlinear analysis as well, as expected. Similar results were
obtained in both chord and radial directions from linear and nonlinear SDoF analysis.
The maximum displacement recorded in EE from nonlinear analysis matches exactly
with those obtained from linear analysis for all the ground motions. It was because the
structure remains within the elastic range at this hazard level with the base shear
recorded being less than the yield forces obtained for the structure in both directions
and is also evident from the ductility values recorded. However in MCE for some of the
GMs, the structure reached the inelastic zone and hence the maximum base shear
recorded from nonlinear analysis for those ground motions are lesser than those
obtained from linear elastic analysis.
4.6 NON LINEAR MDOF TIME HISTORY ANALYSIS
4.6.1 Introduction
According to Cl. 5.1.2 of MCEER/ ATC 49, for evaluation of forces and displacement
demands, nonlinear dynamic analysis is required using earthquake ground motion
records especially for irregular structures like our bridge. For the expected earthquake
hazard level, the nonlinear dynamic analysis is not necessary. However, for this project
nonlinear time history analysis is performed both at MCE and EE to investigate the
seismic response at various hazard levels.
4.6.2 Description of Model
For non-linear dynamic analysis of the structure, hinges are required at discrete
locations to capture its nonlinear behaviour. The same model used for pushover analysis
of the entire bridge was used for this analysis as well.
114
4.6.3 Analysis Procedure
The load cases are defined for each GM corresponding to Time History Analysis.
Analysis type is nonlinear and solution type adopted is Direct Integration. Newmark
Beta method was used with values of and equal to 0.5 and 0.25, respectively, which
represent constant linear acceleration approximation of GM.
Figure 4.3 Definition of a time history function in SAP 2000 program
115
Figure 4.4 Typical Time History Load Case defined in SAP 2000
Figure 4.5 Type of direct integration procedure followed in SAP 2000
The Raileigh damping was used for this purpose with both the first and second periods
subjected to 5% damping as shown in Figure 4.6. The mass source used for time history
analysis was similar to the modal analysis as shown in Figure 4.7.
116
Figure 4.6 Mass and stiffness coefficients for damping
Figure 4.7 Definition of mass source for time history analysis
The nomenclature for a load case for EE and MCE is shown in the Table 4.11 below
Table 4.11 Nomenclature used for defining the GMs
Load type Load name Function Scale factor
Accel U1 IV_FN_EE g X SF = 180.48 (in)
Accel U2 IV_FP_EE g X SF = 180.48 (in)
Accel U1 LP_FN_MCE 32.2 (feet)
Accel U2 LP_FP_MCE 32.2 (feet)
117
Where, LP_FN_MCE stands for Loma Prieta Fault Normal Maximum Considered
Earthquake and LP_FP_MCE stands for Loma Prieta Fault Parallel Maximum
Considered Earthquake. Similarly load cases are defined for all the ground motions for
EE and MCE.
Figure 4.8 Time history load cases defined in SAP 2000
4.6.4 Results and Discussions
The response of the structure in terms of joint displacement, base shear, plastic hinge
rotation and hysteretic loops are shown in Figure 4.9 to Figure 4.12 for the North Ridge
Earthquake scaled to MCE hazard level.
Figure 4.9 Maximum displacement response recorded for pier 4 during North Ridge GM
118
Figure 4.10 Base shear in global X direction with time recorded during North Ridge GM
Figure 4.11 Hysteretic loop of the base shear observed during North Ridge GM
119
Figure 4.12 Hysteretic loop of the plastic moment rotation observed at one of the bottom hinges during North Ridge GM
The resultant forces and the displacements recorded at the piers during the different
ground motions are presented in Table 4.12 and Table 4.13. By direct comparison it can
be seen that the maximum displacement recorded from MDoF analysis in SAP 2000
program are in accordance with the results obtained from SDoF analysis in NONLIN.
Also, as expected, the maximum values recorded at expected earthquake was much
lesser than those obtained in maximum credible earthquake. Similar observations were
also made during NONLIN analysis.
Table 4.12 Maximum resultant forces and displacement recorded at piers during expected earthquake
IV_FN_U1 + FP_U2_EE
Moment (kips-ft) Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 43020 16390 496.1 968.2 0.097 0.118
P2 67820 47930 1150 1299 0.460 0.181
P3 84760 36240 666.6 1254 0.439 0.278
P4 104900 21180 576.3 1634 0.210 0.345
120
IV_FN_U2 + FP_U1_EE
Moment (kips-ft) Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 45280 11510 356.5 880.3 0.068 0.111
P2 56470 35150 858.2 999.3 0.259 0.134
P3 60950 24790 526.2 839.4 0.260 0.169
P4 71260 28210 617.3 1178 0.297 0.214
KJ_FN_U1 + FP_U2_EE
Moment (kips-ft) Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 86000 16400 440.1 1858 0.100 0.234
P2 65790 32000 598.8 1288 0.242 0.184
P3 68950 19920 394.6 1019 0.223 0.202
P4 86240 26730 538.3 1315 0.331 0.271
KJ_FN_U2 + FP_U1_EE
Moment (kips-ft) Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 65690 27380 722.5 1318 0.175 0.169
P2 101300 35830 619.9 1959 0.435 0.280
P3 104700 23790 444.8 1584 0.391 0.363
P4 93970 17300 435.1 1437 0.207 0.369
NR_FN_U1 + FP_U2_EE
Moment (kips-ft) Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 43160 27670 754.1 946.6 0.168 0.117
P2 45280 34330 681.7 894.4 0.261 0.128
P3 54110 22570 573 961.7 0.251 0.166
P4 59430 21780 509.5 952 0.220 0.168
121
NR_FN_U2 + FP_U1_EE
Moment (kips-ft) Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 52210 23940 646.2 1088 0.148 0.136
P2 49770 31980 607.8 923.6 0.250 0.126
P3 63100 22690 580.2 880.7 0.245 0.174
P4 83650 16400 475.2 1455 0.173 0.269
Maximum Moment (kips-ft) Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 86000 27670 754.1 1858 0.175 0.234
P2 101300 47930 1150 1959 0.460 0.280
P3 104700 36240 666.6 1584 0.439 0.363
P4 104900 28210 617.3 1634 0.331 0.369
Table 4.13 Maximum resultant forces and displacement recorded at piers during maximum credible earthquake
LP_FN_U1 + FP_U2_MCE
Moment (kips-ft) Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 102800 53740 1728 2260 0.451 0.338
P2 111000 44810 1413 2283 0.432 0.401
P3 110800 27280 1759 1728 0.436 0.466
P4 114700 31890 1559 1518 0.541 0.470
LP_FN_U2 + FP_U1_MCE
Moment (kips-ft) Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 122300 50910 1526 2834 0.484 0.463
P2 123100 31470 1224 2534 0.298 0.410
P3 99800 22720 2064 1361 0.312 0.411
P4 112200 30270 1824 1769 0.484 0.497
122
CM_FN_U1 + FP_U2_MCE
Moment (kips-ft) Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 138000 36590 1076 3302 0.543 0.492
P2 140600 56600 1340 3275 0.853 0.596
P3 128900 51320 1191 2122 0.915 0.654
P4 133400 43820 1147 1932 1.305 0.701
CM_FN_U2 + FP_U1_MCE
Moment (kips-ft) Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 141500 36090 892.8 3403 0.699 0.647
P2 145800 50600 1096 3003 0.720 0.801
P3 140700 35690 901.1 2325 0.633 1.106
P4 147300 34900 936.3 2462 0.988 1.124
NR_FN_U1 + FP_U2_MCE
Moment (kips-ft) Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 92380 42310 1284 1915 0.416 0.291
P2 95810 43890 1003 2066 0.614 0.356
P3 82020 34610 1123 1512 0.583 0.32
P4 99880 43620 980.8 1664 0.504 0.380
NR_FN_U2 + FP_U1_MCE
Moment (kips-ft) Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 123500 34280 1068 2577 0.467 0.387
P2 120700 39150 1075 2495 0.452 0.396
P3 133200 27660 959.2 2094 0.439 0.396
P4 144300 21350 870.8 2127 0.533 0.460
123
Maximum Moment (kips-ft) Shear (kips) Disp. (ft)
Trans Long Long Trans Long Trans
P1 141500 53740 1728 3403 0.699 0.647
P2 145800 56600 1413 3275 0.853 0.801
P3 140700 51320 2064 2325 0.915 1.106
P4 147300 43820 1824 2462 1.305 1.124
4.7 SUMMARY AND CONCLUSIONS
Lesser demands were also observed for expected earthquakes compared to maximum
credible earthquakes for both linear and nonlinear analysis in SAP 2000 and NONLIN
program, as expected. Similar results were obtained in both chord and radial directions
from linear and nonlinear SDoF analysis. The structure was observed to remain within
the elastic range at EE hazard level with the base shear recorded being less than the
yield forces obtained for the structure in both directions. However in MCE for some of
the GMs, the structure reached the inelastic zone. By direct comparison, it can be
observed that the maximum displacement recorded from MDoF analysis in SAP 2000
program was higher compared to SDoF analysis in NONLIN.
-o-o-o-
124
CHAPTER 5 5. CAPACITY SPECTRUM AND FLOWCHARTS
CAPACITY SPECTRUM ANALYSIS AND FLOWCHARTS
5.1 GENERAL OVERVIEW
Capacity Spectral method is one of the latest analysis procedures for seismic evaluation
of a structure. In This procedure the capacity obtained from pushover analysis are
balanced with the seismic demand represented by the response spectrum at that
location. The primary objective of capacity spectrum analysis is to predict the ability of
the structure to resist a seismic event. The capacity of the structure was obtained from
the nonlinear static pushover analysis. The base shear-pier top displacement obtained
from the pushover analysis was converted into equivalent spectral acceleration and
displacement on which the response spectra curves at MCE and EE were superimposed.
Calculations were carried out until the ductility of the capacity and demand curve
matches each other. The structure will be safe during the earthquake at required
performance level, if it is designed for the ductility thus obtained from this analysis.
The flow chart prescribed in MCEER/ATC 49 report as applicable to our bridge is
presented in this Chapter.
5.2 CAPACITY SPECTRUM ANALYSIS
Capacity spectrum method is essentially a nonlinear static analysis approach which
compares the force-displacement curve of the structure with the response spectra of the
site at various hazard levels. This method applies only to structures that essentially
behave as a single degree of freedom system.
125
5.2.1 Results and Discussions
Assumptions
1. To calculate the Seismic Capacity Coefficient Cc for the piers, the tributary
weight of the superstructure supported by the individual piers is the only
seismic load considered.
2. The abutments take very less seismic load, hence their contribution to seismic
resistance is considered negligible.
3. The Δy value is taken as 1.3 times the Seismic Capacity Coefficient Cc found
using the lateral strength and the weight of the structure.
Calculations
To check the applicability of the equations given in Commentary section 5.4.1.1(C4.4-1)
MCEER-ATC 49 , the natural time period of the structure is compared with the Ts of
both Expected and Maximum Considered Earthquake.
With a Tn of 1.54 secs in longitudinal direction and 0.88 secs in the transverse direction
which are greater than their corresponding Ts values of 1.42 secs and 0.77secs, the
structure was found to be in velocity sensitive region for both MCE and EE.
As per MCEER-ATC –C5.4.1 , bridges that have elastomeric or sliding bearings at each
pier shall be designed as an isolated structure using the provisions of Article 5.4.1.2 and
Article 15.
The BL factor was obtained from table 5.4.1-1, where BL values are for configurations
where the columns are primary resisting elements.
From MCEER-ATC 49-5.4.1.-1,
2
11
2
2v
C
L y
nc
gF SC
B
VC
W
The values for calculating the displacements were obtained from the Push over analysis
and are tabulated below for reference.
126
Table 5.1 Comparison of results from various analysis procedure
From Pushover
𝑽𝒏
(kips)
θp
(rad)
Trans Long Trans Long
50ft 2300 920 0.0112 0.0427
70ft 2250 720 0.0143 0.0548
Entire bridge 26000 4300 0.057 2.01
Sample calculation:
EE (Operational and Life safety)- Transverse direction
Cc *∆𝑦 = 2.02*4*1.3 = 21.84
(𝐹𝑣.𝑆1
2𝜋𝐵𝐿)
2. 𝑔 = (
1.685∗.0.115
2𝜋∗1)
2∗ 386.4 = 0.367 < 21.84 𝑆𝑎𝑓𝑒
The bridge is expected to meet the performance requirement for the expected
earthquake.
MCE – Life Safety –Longitudinal direction
∆𝑦 =1
Cc*(
𝐹𝑣.𝑆1
2𝜋𝐵𝐿)
2. 𝑔 =
1
0.334*(
1.3∗0.527
2𝜋∗1.6)
2∗ 386.4 = 5.372
θp*H = 0.035*50 = 1.75 < 5.372 Not safe
From MCEER-ATC 49 (Commentary),from equation C4.4-6,
We take ∆𝑦 = 1.75,
Required Seismic Coefficient Cc =1
∆𝑦*(
𝐹𝑣.𝑆1
2𝜋𝐵𝐿)
2. 𝑔 =
1
1.75*(
1.3∗0.527
2𝜋∗1.6)
2. 386.4 = 1.023
The required lateral strength is 𝑉𝑛 = Cc * W =1.023* 12871.2 = 13174.017 kips
MCE – Operational –Longitudinal direction
P – Δ check :
0.25 CcH = 0.25* 0.334* 50 = 4.175 < 13.728 (Not safe)
From MCEER-ATC 49 (Commentary),from equation C4.4-7,
We take ∆𝑦 = 13.728,
Required Seismic Coefficient Cc = 4*𝚫
H =1.098
EE (Operational and Life safety)
127
.Table 5.2 Summary of Cc values at EE
Limiting value = 0.367 Cc *∆𝒚
Longitudinal (L) 1.389 (safe)
Transverse (T) 21.84 (safe)
Table 5.3 Summary of operational performance level at MCE
Dir. ∆𝒚 θp*H 0.25 CcH Modified Cc
Modified Vn θp*H P–Δ
L 13.72 1.75 4.175 2.62 1.098 33722.54
T 2.27 1.75 25.25 2.62 - 33722.54
Table 5.4 Summary of life safety performance level at MCE
Dir ∆𝒚 θp*H 0.25 CcH Modified Cc Modified Vn
L 5.372 1.75 4.175 2.62 13174.017
T 0.888 1.75 25.25 - -
The bridge is expected to be safe for Expected earthquake. For MCE, the bridge was
found to be safe only for Life safety performance along the transverse direction and
unsafe for the rest of the cases. The required lateral strength for the unsafe cases was
calculated to be 33722.54 kips in transverse direction and 13174.017 kips in longitudinal
direction. As for the rest of the cases, the bridge seems to have enough capacity to
withstand the demand displacement for both Expected and Maximum Considered
earthquakes for Operational and Life safety performances as can be seen from the
calculations done based on MCEER-ATC(49) -5.4.1-1(C4.4-1).
5.3 FLOWCHARTS
The following design charts illustrate the process that should be followed for design
and analysis of a bridge project such as the one shown in this report. While the design
charts illustrate several different options for analysis, not all being necessary, please
note that LP has explored all of these options. The results from such analyses are shown
in further depth within the earlier chapters of this report.
132
5.4 SUMMARY AND CONCLUSIONS
It was observed from the results that the entire bridge wasn’t safe for Expected
earthquake in the longitudinal direction. The same was observed in the case of 70 feet
piers too. As for the rest of the cases, the bridge seems to have enough capacity to
withstand the demand displacement for both Expected and Maximum Considered
earthquakes for Operational and Life safety performances.
-o-o-o-
133
CHAPTER 6 6. FINAL CONCLUSIONS
FINAL CONCLUSIONS
6.1 GENERAL OVERVIEW
The bridge example 5 of Federal High Way Authority (FHWA) was analyzed at a
different site at Tacoma with certain modifications in the geometry of the bridge as
described in Chapter 1. However the material properties of the bridge along with the
soil conditions were taken directly from the original example. Various analysis as
mentioned in MCEER /ATC 49 report were performed on the bridge as a part of the
project including simple SDOF analysis to more sophisticated nonlinear MDOF time
history analysis. The resultant demand on the structure in terms of maximum bending
moment, shear force and displacement obtained from the various analysis procedure
are compared in this Chapter. The performance of the bridge at MCE and EE was
evaluated by comparing the demand with the capacity of the columns. The safety of the
bridge at MCE and EE and further recommendations are also stated.
6.2 COMPARISON FROM VARIOUS ANALYSIS PROCEDURE
The comparison of the uniform load method, multimode response spectrum analysis,
linear and nonlinear time history analysis were carried out with respect to the maximum
shear force, bending moment and displacement recorded at the piers and presented in
table. It must be noted that 100-40 combination was carried out in both uniform load
method and multimode method so that the results can be compared.
134
Table 6.1 Comparison of results from various analysis procedure
Maximum Values
Expected earthquake Maximum Credible earthquake
Shear (kips)
Moment (kips-feet)
Displacement (feet)
Shear (kips)
Moment (kips-feet)
Displacement (feet)
Long Trans Trans Long Long Trans Long Trans Trans Long Long Trans
Uniform Load method
793 624 45482 45988 0.24 0.12 2217 2802 161485 162499 0.85 0.44
Multimode analysis
761 657 52668 35293 0.18 0.15 2326 2693 186280 124783 0.64 0.51
Elastic Time History
Analysis 672 2058 127500 42417 0.34 0.35 2850 7810 495833 152500 1.33 1.16
Inelastic Time History analysis
1150 1959 104900 47930 0.46 0.37 2064 3403 147300 116600 1.31 1.12
135
The maximum shear force at MCE as obtained from uniform load method, multimode
analysis, linear and nonlinear time history analysis are 2217 kips, 2326 kips, 2850 kips
and 2064 kips, respectively considering all the cases. The maximum moment from the
analysis are 162499 kip-ft, 124783 kip-ft, 152500 kip-ft and 116600 kip-ft, respectively.
These results are for longitudinal direction of the piers. The maximum displacement
from these four analysis procedures at MCE in the longitudinal direction are 0.85 ft, 064
ft, 1.33 ft and 1.31 ft, respectively. The corresponding transverse displacements are 0.44
ft, 0.51 ft., 1.16 ft. and 1.12 ft. From direct comparison it can be concluded that the results
obtained from various procedures are in close agreement with each other, especially as
far as the shear force and displacements are concerned. However, bending moment in
some of the cases are different and the possible reason is the irregular curved geometry
of the bridge.
6.3 PERFORMANCE OF STRUCTURE
As it was observed from the response spectra curves at MCE and EE for our site, there
is a large difference in the hazard level, with the maximum spectral acceleration at short
periods is almost thrice for MCE compared to EE. So it is likely, that the designed bridge
should perform better during expected earthquake, but possibly cannot survive the
maximum credible earthquake hazard level.
The maximum demands obtained in the earlier chapters for multimode analysis,
uniform load method, elastic and inelastic time history analysis were compared with
the capacity of the piers from pushover analysis and the performance of the bridge is
investigated both at MCE and EE for operational and life safety performance levels. The
maximum demands obtained for the linear elastic analysis cases was to be divided by
the response reduction factor (R) as per MCEER/ATC 49 report based on the following
equation.
1 ( 1)1.25
B B
S
TR R R
T
where, RB can be obtained from Table 4.7.1 of the MCEER report and T is the period of
the structure in the respective direction. Detailed calculations were carried out for all
the four analysis cases and the safety of the bridge at various performance levels are
summarized in Table 6.2 and Table 6.3.
136
Table 6.2 Calculation of R factor at EE and MCE
Steps
EE MCE
Longitudinal Transverse Longitudinal Transverse
Life Safety Operational Life Safety Operational Life Safety Operational Life Safety Operational
Sd1 0.193 0.193 0.193 0.193 0.685 0.685 0.685 0.685
Sds 0.396 0.396 0.396 0.396 1.298 1.298 1.298 1.298
Ts 0.487 0.487 0.487 0.487 0.528 0.528 0.528 0.528
1.25Ts 0.609 0.609 0.609 0.609 0.660 0.660 0.660 0.660
T 1.54 1.54 0.88 0.88 1.54 1.54 0.88 0.88
T/(1.25Ts) 2.528 2.528 1.444 1.444 2.335 2.335 1.334 1.334
Rb 1.3 0.9 1.3 0.9 4 1.5 4 1.5
(Rb-1) 0.3 -0.1 0.3 -0.1 3 0.5 3 0.5
(Rb-1)*(T/1.25Ts) 0.76 -0.25 0.43 -0.14 7.00 1.17 4.00 0.67
R 1.76 0.75 1.43 0.86 8.00 2.17 5.00 1.67
Final R 1.300 0.750 1.300 0.860 4.000 1.500 4.000 1.500
137
Table 6.3 Performance evaluation of the structure
Analysis
Maximum Moments
EE MCE
Longitudinal Transverse Longitudinal Transverse
Life Safety Operational Life Safety Operational Life Safety Operational Life Safety Operational
ULM 45988 45988 45482 45482 162499 162499 161485 161485
ULM/R 35375 61317 34986 52886 40625 108332 40371 107656
ULM 35293 35293 52668 52668 124783 124783 186280 186280
MM/R 27148 47057 40514 61242 31196 83189 46570 124187
Elastic THA 42417 42417 127500 127500 152500 152500 495833 495833
Elastic THA/R 32628 56556 98077 148256 38125 101667 123958 330556
Inelastic THA 47930 47930 104900 104900 56600 56600 147300 147300
Capacity of the pier obtained from pushover analysis
Moment Capacity
35000 35000 100000 100000 35000 35000 100000 100000
Final Conclusion on the performance of the bridge
ULM Safe Unsafe Safe Safe Unsafe Unsafe Safe Unsafe
MM Safe Safe Safe Safe Unsafe Unsafe Unsafe Unsafe
Elastic THA Safe Unsafe Safe Safe Safe Unsafe Safe Unsafe
Inelastic THA Unsafe Unsafe Unsafe Unsafe Unsafe Unsafe Unsafe Unsafe
138
Therefore it can be concluded that performance of bridge remains operational in case of
EE but leads to possible failure in MCE.
6.4 SCOPE OF FUTURE WORK
The scope for future work is presented in this section
1. A more sophisticated model of the bridge (3D) with better computing capability
can improve the results obtained from MDOF nonlinear time history analysis
2. P-delta effects can be included to consider geometrical nonlinearity.
3. Time history analysis was carried out only according to seismic hazard as per
ATC MCEER 49 document. In future time history analysis can also be performed
with hazard level defined in AASHTO document.
6.5 RECOMMENDATIONS FOR IMPROVEMENT OF PERFORMANCE
The performance of the bridge was unsatisfactory at MCE. Therefore, recommendations
have been presented in this section to ensure collapse prevention of the existing bridge
at MCE.
1. The bearings used in the present model were simple bridge bearings, which
were good enough for small displacement demands at EE but cannot
accommodate the high displacement demand at MCE. Therefore, seismic
isolation bearings can be used to accommodate the excess displacement
demands during high seismic event. Sliding friction pendulum bearings can be
a good alternative to those used in the present model to ensure better
performance at MCE.
2. Use of dampers along with the isolators can also improve the performance of the
bridge at high earthquakes.
3. All the piers can be converted to sliding piers to accommodate the high
displacement demands expected at MCE.
-o-o-o-
139
APPENDIX A –C1
VALIDATION OF MODEL
The model of the bridge produced in the SAP 2000 program and some of the
assumptions made during modelling are validated using simpler examples. The
description of calibration examples used to verify elastic analysis modelling options of
SAP 2000 are discussed in this section. The model bridge is subjected to uniform lateral
load, hence an elastic analysis of a portal frame subjected to lateral load is carried out in
SAP 2000 program. Moment diagrams and shear forces obtained from the program are
compared with the known analytical results. In addition, multi span continuous beam
with spring supports are analyzed to validate the spring models which are used in SAP
2000 model to account for the foundation stiffness’s. In the present project, the
superstructure is a composite element with concrete deck and steel girders, however,
for simplicity equivalent transformed concrete section was used to model the
superstructure behaviour. For validation of the use of equivalent concrete section in the
bridge model, a simply supported steel bridge is transformed into an equivalent
concrete section and their deflections are compared.
Validation of Elastic Analysis in SAP 2000
A single story single bay frame as shown in Figure A1 was modelled in SAP 2000
[CSI, 2009] program to calibrate/validate the static analysis procedure used in this
project. The bending moment and shear force diagrams obtained from the SAP 2000
program was compared with the results obtained analytically. For simplicity, a statically
determinate portal frame (Figure A1) analyzed in the text book “Fundamentals of
Structural Analysis” (Example 5.5) was used for this purpose. The shear force and the
bending moment diagram obtained in SAP 2000 program are presented in Figures A2
and A3, respectively.
140
Figure A1 Simple portal frame
Figure A2 Shear force diagram obtained from SAP 2000
Figure A3 Bending Moment Diagram obtained from SAP 2000
Analytical results obtained from Text Book
The free body diagram of the frame members and the bending moment and shear force
diagram as presented in the text book is shown in Figure A4
141
Figure A4 Analytical results obtained from text book [Chakraborty et al. 2009, Example 5.5]
Thus it can be seen from the Figures, that the bending moment and shear force diagrams
obtained from SAP 2000 program and analytically from the text book matches with each
other. Hence, the static/elastic analysis procedure of SAP 2000 is validated.
Validation of spring stiffness in SAP 2000
A spring of K = 10 kN/m was modelled in SAP 2000 program and a load of 5kN (P) was
applied at the node. So, deflection, can be obtained analytically as,
P
K
From the above equation, the deflection of the node comes out to be 0.5 m, which was
also obtained in the SAP 2000 program as shown in Figure A4 and hence in agreement
with the analytical result. Therefore, spring supports can be used in the bridge model to
account for the foundation stiffness. A simple multi-span beam with spring at one
support was also analyzed in SAP 2000 program to further validate the spring model.
142
Figure A5 Spring model analyzed in SAP 2000
Multi span beam with spring at one support
A 12m two-span beam (Figure A5), with a spring of K = 1 kN/m at the middle and a
load of 20kN quarter point was analyzed in SAP 2000 program. The cross section of the
beam was considered as 5000 mm square and material was assumed to be concrete with
elastic modulus 25000 MPa. The deflection, and the reaction, R of the spring obtained
in SAP 2000 program was compared with the values obtained analytically.
Figure A6 Multi span continuous beam with spring support analyzed in SAP 2000
As can be seen from Example 10.6 of text book “Fundamentals of Structural Analysis”,
R and can be obtained according to the following equations.
3
3
11 768
48 1
PL EIR
L EI K
3 311
48 768
RL PL R
EI EI K
From these equations R comes out to be 147.12 N and deflection of spring comes out to
be 0.147 mm which is in good agreement with the values obtained in SAP 2000 program
as can be seen in Figures A7 and A8.
Figure A7 Reaction at supports of the multi span continuous beam obtained in SAP 2000
143
Figure A8 Deflection of the continuous beam at spring support obtained from SAP 2000
Hence it can be concluded, that spring model can be used in SAP 2000 program to take
into account the foundation stiffness.
Validation of equivalent concrete rectangular section in SAP 2000
A simply supported beam with 2 – 6 m spans (Figure A9) is analyzed in SAP 2000, first
considering the cross section to be steel I-section and then transforming the section as
shown in Figures A13 to A15 into an equivalent concrete section using modular ratio of
8. However, while transforming the steel section into concrete, the moment of inertia of
the concrete section was made equal to the transformed steel section, but the cross-
sectional area was not equal. Therefore, area modifier property in SAP 2000 was used
for proper transformation of the cross-section. The area modifier factor was calculated
as 0.416 as the ratio of the cross- sectional area of the actual transformed steel section to
that of the equivalent concrete section. The deflection under the point loads are
calculated and it was observed to be similar for both the cases.
Figure A9 Beam used for validation of transformed section in SAP 2000
144
Figure A10 Cross-section details of the actual steel section
Figure A11 Sectional properties of the actual steel cross-section
Figure A12 Deflection of the original steel beam
145
Figure A13 Cross-sectional details of the transformed steel section
Figure A14 Sectional properties of the transformed steel cross-section
146
Figure A15 Sectional properties of the transformed concrete cross-section
Figure A16 Deflection of the transformed equivalent concrete beam
As it can be seen from Figures A12 and A16, the maximum deflection of the beam is
same for both the original steel section and the transformed concrete section. Hence, the
equivalent transformed section concept is validated and therefore, used in the present
project to simulate the superstructure behaviour in SAP 2000.
-o-o-o-
147
APPENDIX A –C2
VALIDATION OF MODEL
The modal analysis procedure of the SAP 2000 program is validated using simpler
example. The response spectra parameters for our site was obtained from the ATC 49
report and matched with the design spectra obtained from the USGS website. A simple
lumped mass model with known spring stiffness was developed in NONLIN program
and its response obtained is matched with the analytical solution for calibration. The
response spectra obtained from PEER strong motion database was also matched with
the one obtained analytically.
Calibration of Eigen Value Analysis in SAP 2000
A three story single bay frame as shown in Figure A18 was modelled in SAP 2000
[CSI, 2009] program to calibrate/validate the modal analysis procedure used in this
project. The frame used in the validation of modal analysis was taken from the text book
“Dynamics of Structures: Theory and Applications to Earthquake Engineering”
[Chopra, 2005] and the sections and geometric dimensions were chosen arbitrarily to
get numerical values for comparison with SAP 2000 results. The natural frequencies and
the corresponding mode shapes obtained in SAP 2000 program was compared with the
analytical results and presented in this section.
Height (h) 12 feet
Weight 10 kips
Mass (m) 25.91 lbs-sec2/inch
Elastic Modulus (E) 29000 ksi
Moment of Inertia (I) 184 in4 [W 8 X 48 sections]
148
Figure A18 Mass Source considering only the weight of the superstructure
Analytical Solution
Stiffness from 2
columns
348EI h
Equation of motion 3 3
2 2
3 3
2 0 0 0
0 0 2 0
0 0 0 2
m u k k u
m u k k k u
m u k k u
Eigen Value
Problem 2 0M K
Solution
1
2
3
21.06 rad/s
57.54 rad/s
78.60 rad/s
2Period =
1 1
2 2
3 3
0.30 s 3.34 Hz
0.11 s 9.15 Hz
0.08 s 12.5 Hz
T f
T f
T f
149
Mode 1 Mode 2 Mode 3
Figure A19 Mode shapes obtained analytically
SAP 2000 Model
The three story frame presented in Figure A18 was modeled in SAP 2000 program and
the modal analysis was done along XZ plane to ensure planer behaviour. The column
sections were selected as W 8X48 with E = 29000 ksi and considered fixed at their base.
The beams were considered to be rigid elements and hence the E of beam was increased
to 2.9 X E10 ksi. The masses were assumed to be lumped at the center nodes of the beams
at each floor level. The comparison of the results obtained analytically and in SAP 2000
program is presented in Table A1. The mode shapes obtained are shown in Figure A20.
150
Mode-1 Mode 2 Mode 3
Figure A20 Mode Shapes obtained from SAP 2000
Table A1 Comparison of natural frequencies obtained from SAP with analytical results
Mode Analytical Solution SAP 2000
1 Freq. (Hz) 3.34 3.28
Period (s) 0.30 0.31
2 Freq. (Hz) 9.15 9.17
Period (s) 0.11 0.11
3 Freq. (Hz) 12.5 12.8
Period (s) 0.08 0.08
So it can be seen from Table A1 and Figures A2 and A3, the natural frequencies and the
corresponding mode shapes obtained from SAP 2000 program are in close agreement
with the analytical solution, which validates modal analysis procedure of the software.
Validation of USGS Ground Motion Information and Response Spectra
The response spectra was developed based on the procedure prescribed in MCEER
ATC 49, Section 3.4.1. For maximum credible earthquake, the values of spectral
acceleration at short period, SMS and the spectral acceleration at 1 s period, SM1, were
obtained according to the following equations,
MS a SS F S
1 1M vS F S
151
where, the values of SS and S1 were obtained from Fig. 3.4.1-2(a) and Fig. 3.4.1-2 (b)
[USGS Hazard Maps presented in ATC 49], and the values Fa and Fv were obtained from
Tables 3.4.2.3-1 and 3.4.2.3-2, respectively, of MCEER ATC 49 for our location [Latitude
= 47.25N and Longitude = 122.44W] and site class C [very dense soil and soft rock]. The
Table A2 presented the calculation of the values from ATC 49 and compared with the
values obtained from USGS website for Maximum Credible Earthquake (MCE). It can
be seen that the % variation from the ATC 49 document is even less than 1% and
therefore, the response spectra obtained from the USGS website can be used as the
design spectra for our site. The parameters for Expected Earthquake (EE) were also
obtained using the same procedure and hence, the calculations are not shown
separately.
Table A2 Comparison of response spectra parameters for MCE
Source Ss (g) S1 (g) Fa Fv SMS (g) SM1 (g)
ATC 49 1.30 0.53 1.0 1.3 1.30 0.689
USGS 1.298 0.527 1.0 1.3 1.298 0.685
Variation (%) 0.4 1.0 0 0 0.4 0.6
Calibration of SDoF Model in NONLIN Program
The example used to validate the calculations in NONLIN were taken from Example 6.2
[Chopra, 2008]. The problem is a SDOF system and important values are as follows:
𝑊𝑒𝑖𝑔ℎ𝑡 = 𝑊 = 5200 𝑙𝑏
𝑆𝑡𝑖𝑓𝑓𝑛𝑒𝑠𝑠 = 𝐾 = .211𝑘𝑖𝑝
𝑖𝑛
𝑀𝑎𝑠𝑠 = 𝑚 =𝑊
𝑔=
5.2
386= 0.01347 𝑘𝑖𝑝 ∗
𝑠𝑒𝑐2
𝑖𝑛
𝐷𝑎𝑚𝑝𝑖𝑛𝑔 = 𝜉 = 2%
Natural frequency and period: 𝜔𝑛 = √𝑘
𝑚= √
0.211
0.01347= 3.958 𝑟𝑎𝑑/𝑠𝑒𝑐
𝑇𝑛 = 1.59
From Response Spectrum Shown Below,
152
Figure A21 Response Spectrum of the GM considered [Chopra 2008, Figure 6.8.3]
For 𝜉 = 2%, 𝑇𝑛 = 1.59, 𝐷 = 5.0 𝑖𝑛𝑐ℎ𝑒𝑠, 𝑎𝑛𝑑 𝐴 = 0.2𝑔,
𝑀𝑎𝑥𝑖𝑚𝑢𝑚 𝐷𝑖𝑠𝑝𝑙𝑎𝑐𝑒𝑚𝑒𝑛𝑡 = 𝑢0 = 𝐷 = 5.0 𝑖𝑛𝑐ℎ𝑒𝑠
In order to run this analysis in NONLIN, the inputs were a lumped mass of 5200 lbs, 2%
damping, and 211 lb/in, run in linear, simple bilinear analysis. A ground motion at
Imperial Valley was implemented, to match the El Centro ground motion from the
above example, and a maximum of 0.2g was applied on the ground acceleration as
described in the Example.
The results of the analysis are 5.223 inches displacement. There is only 4.36% difference
between the calculated value in the textbook and NONLIN and is therefore acceptable.
These values can be seen in the following Figure. As an additional check, it is noted that
the period calculated in NONLIN is 1.587, therefore matching that of the example and
hence validated.
153
Figure A22 NONLIN output of the Example Problem
Calibration of the Program used for Response Spectrum Development
The target spectrum was scaled using the Ground Motion data for various places
obtained from the PEER Ground Motion database based on the magnitude range
specified. The validity of the time history- ground motion data /graphs extracted from
PEER was ensured by checking it against the already available ground motion data of
two sites,namely, Landers and Northridge in California, with the spectrums from PEER.
In PEER, we select the ‘Unscaled’ option to get the Response Spectrum for a particular
site whose vibrations were recorded from a station,which needs to be specified too.
Shown below is the procedure followed to subtantiate the results used .
154
The Landers Earthquake
Figure A23 Landers Earthquake Time history [Villaverde, Figure 5.31]
The Time history GM spectrum(Velocity v/s Time) for the Landers Earthquake : a)Fault
Parallel b) Fault Normal
Figure A24 Spectral Acceleration values
155
Components of ground horizontal velocity corresponding to the ground acceleration
records obtained at Lucerne Valley Station during the 1992 landers, California
earthquake.
Figure A25 PEER Output File
The Peak Ground Velocity values for both Fault Normal and parallel calculated from
the graphs in the text book are:
Normal : Close to 120 cm/s
156
Parallel : Close to 35 cm/s
From PEER : Normal : 142.878 cm/s
Parallel : 36.1024 cm/s
Figure A26 Northridge earthquake time history [Villaverde, Figure 5.32]
The time history graph (Acceleration v/s Time) for the Northridge Earthquake : a)Fault
Normal b) Fault Parallel
Figure A27 Spectral Acceleration Values
Components of ground horizontal acceleration corresponding to to the ground
acceleration records obtained at Rinaldi receiving station during the 1994 Northridge,
California earthquake.
We can clearly see that the graphs obtained from PEER match the ones from the
Textbook.
157
Figure A28 PEER Output for Northridge
The Peak acceleration values for both Fault Normal and parallel calculated from the
graph in the text book are:
Normal : Close to 425 cm/s2
Parallel : Close to 800 cm/s2
From PEER : Normal : 0.8698 g = 0.8698 * 9.8 * 100 = 852 cm/s2
Parallel : 0.4236 g = 0.4236 * 9.8 * 100 = 415 cm/s2
158
Calibration of Response Spectra
Figure A29 Response Spectrum in tripartite representation of Imperial Valley Earthquake (El Centro Station) [Villaverde, Figure 6.5]
Figure A30 Response Spectrum of Imperial Valley Earthquake from PEER ground motion database (El Centro Station Array#5)
159
Table A3: SA values obtained from Textbook
Period PEER GM database Textbook
SA (g) SA (g)
0.1 0.43 0.42
0.2 0.42 0.41
0.4 0.39 0.4
0.6 0.47 0.46
0.8 0.795 0.80
0.6 0.47 0.46
The response spectrum for Imperial Valley earthquake extracted from PEER GM
database is checked with figure A12 and we obtained the same results. Hence it’s
acceptable and validated.
-o-o-o-
160
APPENDIX A-C3
VALIDATION OF MODEL
The model of the bridge produced in the SAP 2000 program and some of the
assumptions made during modelling are validated using simpler examples. The
description of calibration examples used to verify elastic analysis modelling options of
SAP 2000 are discussed in this section. The model bridge is subjected to uniform lateral
Validation of Pushover Analysis and Fiber PMM hinge in SAP 2000
A single story single bay frame as shown in Figure A1 was modelled in SAP 2000
[CSI, 2009] program to calibrate/validate the static analysis procedure.
Plastic Hinge
In order to validate the pushover analysis performed in SAP 2000, the nonlinear static
displacement capacity verification, commonly known as ‘Pushover Analysis’ is
performed on a single degree of freedom structure. The strength of the component is
taken as a function of the displacement component, which is found by performing a
lateral load displacement analysis accounting for the nonlinear behavior of the
structure.
Here, we study a cantilever subjected to a point load of 1 KN which is increased
gradually until a target displacement of 1 feet is reached, thus determining its strength
capacity which is a function of the element’s displacement. The plastic hinge length is
assumed to be 0.1 times the length of the cantilever column.
Section used: W12 X 40.
Member length: 1 feet
161
Fig. A31 Resultant base shear Vs Monitored Displacement
The maximum shear developed during pushover by the element is 23.04 kips.
Fig. A32 Hinge Result: Plastic Moment Capacity of the pier
162
Fig. A33 Moment curvature of the section used.
From the moment curve of the section, we see the moment capacity is 276 kips-ft.
For the cantilever section considered the maximum shear capacity of the section
is 276
12 = 23 kips .
From the pushover graph we can see that , the maximum shear developed
is 23.04 kips ~ 23 kips.
The plastic moment capacity of the pier = Mp = 274 kips-ft
The corresponding plastic shear developed = 𝑀𝑃
12 =
274
12 = 22.833 kips
This shows that the base shear developed during push over almost reaches the shear
carrying capacity of the section and thus results in the development of a plastic hinge at
the base of the cantilever.
Sensitivity of Plastic Hinge Length
The plastic hinge length of the calibration example was changed from 0.1 to 0.2 and 0.3
times the length of the member to see the effect of hinge length on the lateral load
displacement capacity of the member. As it can be seen from the Figure, there is not
much difference in the ultimate lateral strength of the structure with variation of the
plastic hinge length. However, the stiffness decreases as the plastic hinge length
increases along with a slight increase in lateral strength. Therefore, the plastic hinge
163
length in the present project was calculated in accordance with the equation given in
Article 8.8.6 of MCEER/ATC 49.
Fig. A34 Effect of hinge length on force displacement relationship.
-o-o-o-
0
5
10
15
20
25
30
0 0.2 0.4 0.6 0.8 1 1.2
Lp=0.1 Lp=0.2 Lp=0.3
164
APPENDIX A – C4
VALIDATION OF TIME HISTORY ANALYSIS
The following example from “Fundamental Concepts of Earthquake Engineering” by
Roberto Villaverde was analyzed in SAP 2000 and the results were compared with those
given in the text book to validate the time history analysis procedure followed in SAP
2000 program. The braces are only considered to be yield with the other members
remaining elastic. The frame considered for analysis and the time history used are given
in the following Figures.
Figure A35 Calibration frame and time history [Villaverde]
Area of the brace 1.25 in2
Masses 1.0 kips-s2/in
Em 37500 ksi
y 0.002
The SAP model is shown in the following Figure. Pinned connections were used as
stated in the example. The beams were made rigid with respect to the braces by
increasing the moment of inertia and the area to a large value. Masses were lumped at
the middle of the beam.
165
Figure A36 Calibration frame and time history
The ground motion was inputted into the SAP 2000 program as shown in the Figure
A37. The nonlinear behaviour of the braces were given in form of discrete hinges using
default PMM fiber hinges as defined for the time history analysis in the present project.
The hinge definition is shown in the following Figure A38. Hinges were provided at the
middle of the braces. The nonlinear time history analysis case was then run in SAP 2000
following the same procedure as described in Chapter 5 and the results obtained are
presented in the following Table.
Figure A37 Time history defined in SAP 2000
166
Figure A38 Hinge definition in SAP 2000
Table A4 Comparison of the results obtained in SAP 2000 with textbook
Time Steps U1 (SAP) (in) U2 (Book) (in)
2 0.0684 0.0685
4 0.6048 0.6050
6 -2.5123 -2.4738
8 -6.9781 -6.6135
10 -14.4231 -13.2758
12 -22.1234 -21.4458
14 -30.1256 -29.3837
16 -38.1123 -36.3561
18 -42.1132 -41.9192
20 -45.8978 -45.7438
So the results obtained in SAP 2000 program are in accordance with those given in text
book and hence the procedure followed for non linear time history analysis is validated.
-o-o-o-
167
APPENDIX B – TEAM MANAGEMENT
Table B1 Worksheet for the Project
Weeks Amy Sandhya Sathvika Sharath Supratik
Week 2 Management plan Management plan Management plan Management plan Management plan
Week 3
Peer review of team management plan
Write up review
Peer review of team
management plan
Peer review of team
management plan
Peer review of team
management plan
Peer review of team
management plan
Week 4
Development of final team management plan
Write up for final team management plan
General description of bridge
Calculations related to stiffness values for substructure
Development of SAP2000 model of the bridge
Established the assumptions made for the analysis of the bridge
Calculations related to the various elements in the superstructure
Development of final team management plan
Calculation of stiffness values of substructure
Report for week four work
Calculation of stiffness values of superstructure
Development of SAP2000 model of the bridge
Uniform load method analysis in SAP2000
critical assessment of bridge behavior under UDL
Calibration of SAP2000
Formatting of report
168
Week 5 Report for peer team
Development of peer team bridge model in SAP2000
General bridge analysis by SAP for peer team
Modal analysis for peer review team using SAP2000
Development of peer review bridge in SAP2000
Critical assessment of the peer bridge behavior
Week 6
Maximum ground motion acceleration values
NONLIN SDOF analysis trials and final model
Time history analysis in NONLIN
Validation trials and final model in NONLIN
Response to the peer review report of the reviewer
Generation of design spectra by USGS and PEER GM Database
Generating and scaling of GM spectra for EE and MCE
Seismic design spectra of the site
Generation of design spectra by USGS and PEER GM Database
Scaling of GM
Report for review 3
Generating and scaling of GM spectra
Calibration of response spectral analysis developed by PEER
Response to the peer review team of our reviewer
Modal analysis of SAP2000 model
Review of design spectra and scaling of GMs
Development of SDOF model in NONLIN
Time history analysis in NONLIN program
Calibration of modal analysis in SAP2000
Calibration of response spectra developed from USGS
169
Week 7 Peer Review of NONLIN Analysis
Peer review of time history and response spectra
Peer review of ground motion scaling
Peer Review Report
Peer review of time history and response spectra
Peer review of ground motion scaling
Peer review of eigenvalue analysis
Week 8 Spring Break Spring Break Spring Break Spring Break Spring Break
Week 9
Elastic Analysis Multimode Dynamic Method
Multimode Validation
Hour Sheets for Appendix B
Uniform Load Method
Uniform Load Validation
Elastic Analysis Multimode Dynamic Method
Pushover Analysis
Elastic Analysis Multimode Dynamic Method
Uniform Load Method
Pushover Analysis
Week 10
Peer Review of Pushover Analysis
Report Writeup
Peer review of multimode method
Peer review of multimode method
Peer review of uniform and multimode methods
Help with peer review of pushover analysis
Formatting
Week 11
Time History Analysis for Nonlinear and linear SDoF systems by NONLIN
Hour sheets for Appendix B
Time History Analysis for Nonlinear and linear dynamic analysis of SDoF systems by SAP2000
Time History Analysis for Nonlinear and linear dynamic analysis of SDoF systems by SAP2000
Time History Analysis for Nonlinear and linear dynamic analysis of MDoF systems by SAP2000
Time History Analysis for Nonlinear and linear dynamic analysis of MDoF systems by SAP2000
Week 12
Help with Nonlin for Peer Review
Report Writeup
SDOF nonlinear analysis in NONLIN for peer review
SDOF linear analysis in NONLIN for peer review
MDOF nonlinear in SAP for peer review
Help with peer review of MDOF in SAP
170
Week 13
Drawings for Report 2
Flow Charts
Appendix B
Drawings for Report 2
Capacity Spectrum
Autocad “tutorial”
Capacity Spectrum
Fix errors in Multimode analysis
Autocad “tutorial”
Conclusions and final recommendations
Fix errors for 40-100 Combination for Uniform Load Method for Report 4
Fix errors for Time History Analysis MDOF for nonlinear analysis for report 5
Fix errors for Time History Analysis MDOF for elastic analysis for Report 5
Final Report Writeup
Longitudinal Diagram and Table for Report 2
Conclusions and final recommendations
Time History Analysis Validation
171
Minutes
Week 2
Action Items:
Everyone will discuss what to put in team management plan, review bridge
options and pick their favorite bridge
Amy will do team management plan writeup
Week 3
Action Items
Everyone will review the management plans from the three teams and make
note of what they like and don’t like
Amy will do peer review writeup
Week 4
Action Items
Everyone will discuss final management plan
Amy will do final management plan writeup and general description of the
bridge
Amy and Sathvika will do stiffness calculations for substructure
Sandhya and Sharath will do stiffness calculations for substructure
Supratik and Sharath will do critical assessment of bridge behavior and elastic
analysis
Sharath will do report 4 writeup
Supratik will do report formatting
Everyone will review each other’s work
Week 5
Action Items
Amy will do peer review report
Sandhya and Supratik will develop peer team bridge model in SAP
Sathvika will do peer review of general bridge analysis
Supratik will review critical assessment of bridge
172
Everyone will review each other’s work
Week 6
Action Items
Supratik will work on Eigenvalue Analysis and structural periods and
validation and formatting/consolidation of report
Sandhya, Sathvika and Sharath will work on Seismic Design Spectra, Suite of
ground motions, scaling of ground motions and validations
Amy will work on SDOF analysis and validation
Everyone will review each other’s work
Week 7
Action Items:
Supratik will do peer review of eigenvalue analysis
Sathvika will do peer review report
Amy will do peer review of NONLIN analysis
Sharath and Sandhya will do peer review of time history and response spectra
and scaling of ground motions
Everyone will review each other’s work
Week 8
Spring Break
Week 9
Action Items:
Sharath will work on Uniform Load Method
Amy and Sathvika will work on Multimode Analysis with help from Sharath
Supratik and Sandhya will work on Pushover Analysis
Everyone will review each other’s work
Week 10
Action Items:
Amy will peer review pushover analysis and do report writeup
173
Sharath will do peer review of uniform and multimode methods
Sandhya and Sathvika will help with review of multimode method
Supratik will do report formatting
Everyone will review each other’s work
Week 11
Action Items:
Sharath and Supratik will work on Time History Analysis of MDoF systems by
SAP2000
Sandhya and Sathvika will work on Time History Analysis of Linear and
Nonlinear of SDoF systems by SAP2000
Amy will work on Time History Analysis of Linear and Nonlinear SDoF
system by NONLIN
Everyone will review each other’s work
Week 12
Action Items:
Sandhya will do peer review of nonlinear SDOF
Amy will help Sandhya with NONLIN and do report writeup
Sathvika will do peer review of linear SDOF
Sharath will do peer review of MDOF analysis in SAP
Supratik will help Sharath with MDOF analysis and do report formatting
Everyone will review each other’s work
Week 13
Action Items:
Previous week’s work:
R2
Bridge Figures - Amy and Sandhya
Longitudinal Diagram and Table - Supratik
R4
Multimode Validation - Sathvika
Multimode Correction - Sathvika
174
40-100 combination for ULM - Sarath
R5
THA-MDOF- Nonlinear - Sarath
THA-MDOF-Elastic - Sarath
THA Validation - Supratik
This weeks work:
Capacity Spectrum - Sathvika and Sandhya
Flowchart - Amy
Comparison - Supratik and Sarath
Convert into final one report – Supratik
Everyone will review each other’s work
Table B2 Spread Sheet of hours spent
177
REFERENCES
CSI., 2009. Integrated Software for Structural Analysis and Design, SAP 2000. CSI.
FHWA-SA-97-010. Seismic Design of Bridges, Design Example No. 5, Nine Span Viaduct Steel Girder Bridge. BERGER/ABAM Engineers. Federal Highway Administration. 1996.
MCEER/ATC 49. Recommended LFRD Guidelines for the Seismic Design of Highway Bridges, Part I: Specifications. ATC MCEER Joint Venture. 2003
MCEER/ATC 49. Recommended LFRD Guidelines for the Seismic Design of Highway Bridges, Part II: Commentary and Appendices. ATC MCEER Joint Venture. 2003
Bruneau, M., Uang, C. M. and Sabelli, R. 2010. Ductile Design of Steel Structures. Second Edition
Lawson, R.S., Vance, V. and Krawinkler, H. 1994. Nonlinear static pushover analysis: Why, When and How?. Proceedings of 5th US National Conference on Earthquake Engineering, July 10-14, 1994, Chicago.
Chopra, A. K. (2012). Earthquake Response of Linear Systems. Dynamics of Structures: Theory and Applications to Earthquake Engineering (). Upper Saddle River, NJ: Pearson Education Inc.
Villaverde, R., 2009. Fundamental Concepts of Earthquake Engineering.
-o-o-o-