final report

Upload: ibrahim-nashid

Post on 12-Oct-2015

29 views

Category:

Documents


1 download

DESCRIPTION

Final Report

TRANSCRIPT

  • 5/21/2018 Final Report

    1/96

    MURDOCH UNIVERSITY

    FACULTY OF SCIENCE AND ENGINEERING

    SCHOOL OF ENGINEERING AND ENERGY

    Engineering Internship Final ReportAn Internship with Fortescue Metals Group Limited

    Prepared by Daniel Paino

    On 4th

    June 2012

    For Dr. Gregory Crebbin and Dr. Gareth Lee

    A final year report submitted to the School of Engineering and Energy, Murdoch University, in partial

    fulfillment of the requirements for the degree of Bachelor of Engineering.

  • 5/21/2018 Final Report

    2/96

    i

    Executive Summary

    Over the period from August 2011 to May 2012, the intern was placed at Fortescue Metals

    Group Limited in Perth Western Australia to carry out his final year engineering project, which

    would fulfil the requirements of his degree studied at Murdoch University. The internship

    placement was an accelerated learning experience which gave the intern the unique

    opportunity to apply all his knowledge gained through studying the Bachelor of Engineering

    degree.

    The intern worked under the supervision of the Principal Electrical Engineer and was assigned

    various projects and tasks that would transform him from a student to a professional engineer.

    The intern was exposed to engineering practice, planning, design, reporting, operations,

    research, testing, project management and business development. The intern worked in the

    Corporate Engineering Group who are responsible for all engineering standards, processes and

    developments across the entire business.

    This report outlines the major projects that the intern was directly involved in and that relate

    directly to the field of Electrical Engineering. This report documents the purpose of each

    project, the engineering approach, summary of outcomes and the current status of the work.

    The four projects covered in detail in this report are the following:

    Cloudbreak Expansion Load Flow and Short-Circuit Study Cloudbreak Dragline Excavator Dynamic Study Solomon LED Lighting Pilot Project Transformer Factory Acceptance Testing

    The final year engineering internship program between Murdoch University and Fortescue

    Metals Group Limited was successful and worthwhile. The intern gained relevant industry

    experience and the skills to carry out engineering based work professionally.

  • 5/21/2018 Final Report

    3/96

    ii

    Disclaimer

    The collection of material contained within this report is independently the work of the author

    unless otherwise referenced.

    All work completed during the internship placement was carried out under the supervision of

    industry supervisor, Cobus Strauss, and therefore remains the property of Fortescue MetalsGroup Limited.

    I declare the following work to be my own work, unless otherwise referenced, as defined by

    Murdoch Universitys Plagiarism and Collusion Assessment Policy.

    Mr. Daniel Paino

    Signed: Date:

    Engineering Intern Murdoch University and Fortescue Metals Group Limited

  • 5/21/2018 Final Report

    4/96

    iii

    Acknowledgements

    The Internship has been honestly a life changing experience and will successfully transform my

    position from a student to a professional engineer. I feel very privileged to have work with the

    following bodies and people and would like to take this opportunity to thank them.

    Principal Electrical Engineer at Fortescue Metals Group, Cobus Strauss, who supervisedmy internship, provided great learning experiences, gave me the opportunity to

    manage and work on my own projects, demonstrated what it takes to be a

    professional engineer and supported me throughout the placement.

    Corporate Engineering Group Manager at Fortescue Metals Group, Mark Botes, firstlyfor accepting the internship, providing support and managing my position over the

    placement.

    The Corporate Engineering Group at Fortescue Metals Group, for making me feelwelcome and part of the team.

    Academic Chair and Senior Lecturer at Murdoch University, Dr. Gregory Crebbin, firstlyfor teaching and providing support over the 4 years of my engineering degree.

    Secondly for supervising my internship and providing great assistance during the time

    of my placement at Fortescue Metals Group.

    My family and friends for understanding and supporting me over the past four years. Iunderstand that putting up with someone with an unpredictable lifestyle can be quite

    challenging and I appreciate it.

    Last but not least, my colleagues at Murdoch University who I have had the privilege ofworking and studying with over the past four years into the early hours of the

    morning. You have all aided in my development in becoming a professional engineer.

  • 5/21/2018 Final Report

    5/96

    1

    Table of ContentsExecutive Summary ....................................................................................................................... i

    Disclaimer .................................................................................................................................... ii

    Acknowledgements ..................................................................................................................... iii

    List of Figures ............................................................................................................................... 3

    List of Tables ................................................................................................................................ 4

    1 Introduction ......................................................................................................................... 5

    1.1 The Internship .............................................................................................................. 5

    1.2 Fortescue Metals Group Limited .................................................................................. 5

    1.3 Corporate Engineering Group ...................................................................................... 6

    1.4 Report Limitations ........................................................................................................ 6

    2 Internship Projects ............................................................................................................... 7

    3 Cloudbreak Expansion Load Flow and Short-Circuit Study ................................................... 7

    3.1 Background .................................................................................................................. 7

    3.2 Methodology ................................................................................................................ 8

    3.3 Results ........................................................................................................................ 12

    3.4 Conclusion .................................................................................................................. 25

    3.5 Current Status ............................................................................................................ 25

    4 Cloudbreak Dragline Excavator Dynamic Study .................................................................. 27

    4.1 Background ................................................................................................................ 27

    4.2 Methodology .............................................................................................................. 28

    4.3 Results ........................................................................................................................ 34

    4.4 Conclusion .................................................................................................................. 41

    4.5 Current Status ............................................................................................................ 42

    5 Solomon LED Lighting Pilot Project .................................................................................... 43

    5.1 Background ................................................................................................................ 43

    5.2 Methodology .............................................................................................................. 44

    5.3 Conclusion .................................................................................................................. 48

    6 Transformer Factory Acceptance Testing ........................................................................... 49

    6.1 Background ................................................................................................................ 49

    6.2 Methodology .............................................................................................................. 51

    6.3 Conclusion .................................................................................................................. 56

    7 Internship Review .............................................................................................................. 57

    Bibliography .............................................................................................................................. 58

    Abbreviations ............................................................................................................................. 60

  • 5/21/2018 Final Report

    6/96

    2

    Appendices ................................................................................................................................ 61

    Appendix A - Cloudbreak Mine Power Distribution Single Line Diagrams .............................. 61

    Appendix B - SCADA Cloudbreak Load Demand Information (15/08/2011 - 17/08/2011) ..... 62

    Appendix C - AVK Alternator Specification Frame HV 80W Winding 83 .............................. 63

    Appendix D - Cloudbreak PTW Load Flow and Short-Circuit Simulation Results................... 64

    Appendix E - Cloudbreak PTW Short-Circuit Simulation Result for MC435 (SC-1)................ 65

    Appendix F - SL-001 Power Station Expansion Switchboard Interconnection ..................... 66

    Appendix G - Bucyrus 8750-81 Dragline Product Specification Sheet .................................... 67

    Appendix H - Bucyrus 8750-81 Dragline Typical Real Power vs. Time Curve .......................... 68

    Appendix I - Christmas Creek Power System General Single Line Diagram ............................ 69

    Appendix J - Dragline Typical Real Power vs. Time Curve Modelling ...................................... 70

    Appendix K - Cloudbreak Power System Dragline Excavator Study Single Line Diagrams .... 71

    Appendix L - Cloudbreak Power System Dragline Excavator Study Results.......................... 72

  • 5/21/2018 Final Report

    7/96

    3

    List of FiguresFigure 1-1 Fortescue Metals Group Limited Operations Map ..................................................... 5

    Figure 1-2 Production Execution Strategy T155 for June 2013 ................................................... 6

    Figure 2-1 Bucyrus 8750-81 Dragline Typical Real Power vs. Time Curve .................................. 27

    Figure 2-2 Construction of PowerStore Flywheel ..................................................................... 29

    Figure 2-3 PowerStore Flywheel Substation Layout................................................................ 30Figure 2-4 Case Study 1 Dragline Voltage (p.u) vs. Real Power Consumption (MW) ............... 34

    Figure 2-5 Case Study 2A Dragline Voltage (p.u) vs. Real Power Consumption (MW) ............. 35

    Figure 2-6 Case Study 2B Flywheel Voltage, Power and SOC Dynamic Response .................... 36

    Figure 2-7 Case Study 2C Power Stations Dynamic Response .................................................. 37

    Figure 2-8 Case Study 3A Dragline Voltage (p.u) vs. Real Power Consumption (MW) ............. 38

    Figure 2-9 Case Study 3A Power Stations Dynamic Response ................................................. 39

    Figure 2-10 Case Study 3B Power Stations Dynamic Response ................................................ 40

    Figure 2-11 Case Study 3B 66kV Interconnection Loading ....................................................... 41

    Figure 2-12 LED Lighting Pilot Project Communication ............................................................ 47

    Figure 2-13 Cloudbreak Mine LED Lighting versus HPS Lighting ................................................. 48

    Figure 2-14 5MVA 3-winding VSD transformer at ABB Singapore .............................................. 50

    Figure 2-15 52MVA 2-winding power transformer at ABB Vietnam .......................................... 51

    Figure 2-16 Ratio and Voltage Vector Relationship Test Circuit............................................... 52

    Figure 2-17 Separate Source Voltage Withstand Test Circuit.................................................. 53

    Figure 2-18 Measurement of No-Load Loss and No-Load Current Test Circuit........................ 54

    Figure 2-19 Measurement of Winding Resistance................................................................... 55

    Figure 2-20 Measurement of Load Loss and Impedance Voltage Test Circuit......................... 55

  • 5/21/2018 Final Report

    8/96

    4

    List of TablesTable 2-1 Case Studies for Load Flow Analysis ........................................................................... 12

    Table 2-2 LF-1 Switchgear Results............................................................................................ 12

    Table 2-3 Cable Current De-rating Approach............................................................................ 14

    Table 2-4 LF-1 Cable Loading Results........................................................................................ 14

    Table 2-5 LF-1 Transformer Loading Results............................................................................. 14Table 2-6 LF-2 Switchgear Results............................................................................................ 15

    Table 2-7 LF-2 Cable Loading Results........................................................................................ 17

    Table 2-8 LF-2 Transformer Loading Results............................................................................. 17

    Table 2-9 Additional Generation Calculation Information ......................................................... 18

    Table 2-10 Case Studies for Load Flow Analysis ......................................................................... 20

    Table 2-11 Switchgear Fault Currents Results for SC-1............................................................. 20

    Table 2-12 Three-phase short-circuit variables .......................................................................... 22

    Table 2-13 Peak Short-Circuit Current Calculation Variables ..................................................... 22

    Table 2-14 Line-to-Earth Short-Circuit Current Calculation Variables ........................................ 23

    Table 2-15 Switchgear Fault Currents Results for SC-2............................................................. 24

    Table 2-16 Bucyrus 8750-81 Dragline Electrical Details for Typical Excavation Cycle ................ 27

    Table 2-17 PowerStore Flywheel Specification........................................................................ 30

    Table 2-18 Dynamic Study details of Case Studies ................................................................... 33

    Table 2-19 Dragline Dynamic Case Study 2A Results ............................................................... 35

    Table 2-19 Dragline Dynamic Case Study 2A Results ............................................................... 35

    Table 2-20 Dragline Dynamic Case Study 2B Results ............................................................... 36

    Table 2-21 Dragline Dynamic Case Study 2C Results ............................................................... 37

    Table 2-22 Dragline Dynamic Case Study 3A Results ............................................................... 39

    Table 2-23 Dragline Dynamic Case Study 3B Results ............................................................... 40

    Table 2-24 Lighting Technology Comparison........................................................................... 43

    Table 2-25 Project Stakeholders and Responsibilities .............................................................. 45

    Table 2-26 Transformer Details for FAT at ABB Singapore ......................................................... 49

    Table 2-27 Transformer Details for FAT at ABB Vietnam ........................................................... 50

    Table A-1 Abbreviations ............................................................................................................. 60

  • 5/21/2018 Final Report

    9/96

    5

    1 Introduction1.1 The InternshipThe purpose of the Internship is to enable the intern to satisfy the requirements of the

    Bachelor of Engineering (Double Major in Electrical Power Engineering and Renewable Energy

    Engineering) degree at Murdoch University. The intern will be exposed to the world of applied

    engineering design, operations, development, projects and management which relate directly

    to the engineering degree the intern is completing. The intern will gain experiences and skills

    which will allow a smooth transition into the career of a professional engineer.

    Over the period from August 2011 to May 2012, the intern carried out his internship

    placement at Fortescue Metals Group Limited in Perth, Western Australia, in the Corporate

    Engineering Group under the supervision of the Principal Electrical Engineer. The intern

    worked both full-time and part-time over this period.

    1.2 Fortescue Metals Group LimitedFortescue Metals Group Limited is the fourth largest iron ore producer in the world and only

    shipped its first ore in May 2008. They have operations located in the Pilbara Region of

    Western Australia comprising mine, port and rail infrastructure, as shown in Figure 1-1 below.

    They hold tenements of over 88,000 square-kilometres and have a permanent workforce of

    3,000 workers and 5,000 contractors. At present the iron ore production is carried out through

    the Chichester Hub, specifically the Cloudbreak and Christmas Creek mines, and exported

    through the Herb Elliot Port. This current mine process allows FMGL to successfully produce

    55Mtpa.

    Figure 1-1 Fortescue Metals Group Limited Operations Map

  • 5/21/2018 Final Report

    10/96

    6

    FMGL is currently undertaking a major expansion, which will increase the production rate from

    55Mtpa to 155Mtpa. This major expansion is known as project T155, and is scheduled to be

    completed in June 2013. This will be achieved by increasing the production rate at the

    Chichester Hub from 55Mtpa to 95Mtpa, and introducing another site called the Solomon Hub

    comprising two mines sites, Firetail and Kings, which will produce 60Mtpa collectively. As a

    result, the aggregate production capacity will be 155Mtpa. This production strategy is

    indicated in Figure 1-2 below.

    Figure 1-2 Production Execution Strategy T155 for June 2013

    Future developments include introducing another site called the Western Hub, a second port

    called Anketell, and a third mine within the Chichester Hub called Nyidinghu. These future

    developments can potentially bring the FMGL iron production rate to 355Mtpa.

    1.3 Corporate Engineering GroupThe Corporate Engineering Group is responsible for engineering standards, processes,strategies and development. The group consists of engineering management, principal

    engineers through to graduate engineers and drafters covering civil, electrical and mechanical

    disciplines. The group manages their own internal projects as well as being involved in the

    expansion projects and business development.

    1.4 Report LimitationsThis report documents the experiences, learning outcomes and project work carried out by the

    intern during the course of the internship placement at Fortescue Metals Group Limited. The

    report has been produced in accordance with the requirements of the ENG450 Final YearEngineering Internship Study Guide (H-period). Note that supplementary non-print material

    and work has been attached to this report.

  • 5/21/2018 Final Report

    11/96

    7

    2 Internship ProjectsOver the course of the Internship program, the intern was assigned a number of projects and

    tasks. Due to word limitations not all projects and tasks carried out during the internship

    placement are described in this report. The projects below relate directly to the majors of the

    interns degree, and played a pivotal role in expanding the interns engineering knowledge and

    skills:

    Cloudbreak Expansion Load Flow and Short-Circuit Study Cloudbreak Dragline Excavator Dynamic Study Solomon LED Lighting Pilot Project Transformer Factory Acceptance Testing

    3 Cloudbreak Expansion Load Flow and Short-Circuit Study3.1 BackgroundIn September 2009 FMGL were planning to expand the Cloudbreak mine from 35Mtpa to

    45Mtpa and finally to 55Mtpa in a two stage expansion. This expansion would introduce new

    mine equipment, infrastructure and processes, and as a result increase the electrical load of

    the mine which would affect the loading on the power station, transformers and distribution

    cables as well as the fault levels on the existing switchboards. In order to plan, evaluate and

    execute this expansion and its electrical impact, FMGL engaged the Worley Parson Power

    Division to carry out a load flow and short-circuit study, which they completed. However, this

    two stage expansion plan did not go ahead as the Cloudbreak current and proposed T155production rate is only 40Mtpa.

    In August 2011, the Corporate Engineering group engaged Worley Parson Power Division to

    again carry out a new load flow and short-circuit study,as FMGL were introducing a new iron

    ore processing facility called the Wet Front End. The Wet Front End Project is one of many

    expansion projects FMGL are undertaking to ramp up production from 55Mtpa to 155Mtpa in

    the Chichester Hub. The Wet Front End Project will allow direct processing of iron ore below

    the water table and optimisation of the ore grade and volume, which will in turn extend the

    life of the Cloudbreak Mine by approximately 3.5 years.

    The purpose and objectives of this study are to determine the implications of this expansion

    on the existing electrical infrastructure, specifically the loading and fault levels on the power

    station, switchgear, main cables and distribution transformers in the Cloudbreak power

    system.

    The Cloudbreak power system generation and distribution arrangement is shown in Appendix

    A in single line diagrams CB-10016-DR-EL-0003 Sheet 1 to 3.

    The Cloudbreak power system is supplied by 18 reciprocating diesel engines (MTU 20V 4000

    G62) directly coupled to individual alternators (AvK HVS1803W2). This also conforms with the

    operating philosophy of the power station, which is n+2, meaning that at any given time one

    generator will be out in maintenance and one will be redundant, resulting in 16 available

  • 5/21/2018 Final Report

    12/96

    8

    generators. This arrangement allows the power station to have a continuous output rating of

    27.9MW and prime output rating of 31.8MW (as defined by AS4594 Internal Combustion

    Engines). This electrical power is generated at a voltage of 11kV, which is distributed through

    three HV transformers (TF03, TF11 and TF12) at 22kV, a direct cable line to the camp at 11kV

    and one power station auxiliary transformer (TF02) at 400V. The main 11kV station

    switchboard is earthed by a 15.7zig-zag earthing transformer (TF01).

    The generated power is distributed through TF11 and TF12 are transmitted through overhead

    and underground cables, which connect to the main OPF switchboard, SW411, which

    contributes to the largest portion of electrical loads and is where the Wet Front End loads will

    be connected. The switchboard is segregated into two buses, SW411A and SW411B (incomers

    from TF12 and TF 11 respectively), which are connected by a bus tie that is normally-closed.

    SW411 distributes electrical power to Lump Stockpile, Crushing, Screening, Desand, Facilities

    and ROM substations.

    TF03 supplies power to the mine services, which has admin and workshop loads connected.

    The camp O/H line transmits power to two workshops, a sewage-bore treatment plant and the

    accommodation village, which consists of nine ring main units in a completed radial topology.

    The Cloudbreak average load demand is 19.1MW and maximum load demand is 23.2MW. The

    Wet Front End Project will introduce 3 new scrubbing/screen modules to wash clay from the

    ore feed, redirect process conveyors and add capacity to the thickeners to handle higher water

    loads. According to the project load list, this enhancement will add electrical loads to the

    Lump (SW454), Screening (SW421) and Desands (SW426) switchboards at a net magnitude of

    13.5MW running load.

    3.2 MethodologyConsignment with Worley Parsons

    From start to finish, the intern was on a consignment with Worley Parson Power Division,

    which involved the data collection, modelling, simulation, reporting and project management

    of the load flow and short-circuit study. This arrangement allowed the intern to communicate

    the project developments between the FMGL Principal Electrical Engineer and Worley Parsons

    project team, which consisted of two Senior Electrical Engineers. The intern met on a daily

    basis with the Worley Parsons project team and had a workstation at their office.

    Software and Existing ModelThe site Electrical Utilities group kept an as-built model using the power system software

    Power*Tools for Windows (PTW) v6.5.0.0 from SKM, which was maintained by site electrical

    engineers. However the load flow and short-circuit study will only use this as-built model as a

    reference to ensure that all inputs and modelling are reliable and as accurate as possible.

    Fortunately, the Worley Parsons Power Division principally use Power*Tools for Windows

    (PTW) v6.5.0.0 from SKM for power system modelling. The intern was trained on the software

    by one of the senior electrical engineers over a period of a day. This involved how to input data

    for generators, transformers, cables and loads (motors, VSD, UPS and feeder) and how to

    simulate load flow and short-circuit calculations as well as output results.

  • 5/21/2018 Final Report

    13/96

    9

    Data Collection

    The intern collected as-built drawings from the FMGL document management system, PIMS.

    The intern collected all asbuilt single line diagrams from generation through to load

    distribution, cable schedules, load lists and manufacturer equipment specifications.

    The intern had the opportunity to visit the Cloudbreak mine over a three day period, which

    involved a supervised tour of power station, distribution line route and the OPF substations.

    This allowed the intern to further verify and collect the following information:

    Plant operating strategy Generation, distribution and equipment single line diagrams Cable schedules Cable sizing calculations Load list for existing and future loads Load and generation dynamics Protection settings All major equipment specifications including generators, transformers, switchgear,

    variables speed drives and motors.

    The intern had previously worked as a Vacation Student for FMGL at port operations the

    summer before, and had knowledge of the SCADA/process control software that FMGL

    utilized. The SCADA software that FMGL has installed is CimView by General Electric. This prior

    knowledge allowed the intern to collect the power systems loading magnitudes for the four

    main HV feeders (TF03, TF11, TF12 and the Camp O/H line) from the power station and the

    main substations (SW454, SW435, SW451, SW431, SW421 and SW426) below switchboard

    SW411. This load demand data (attached in Appendix B) was then inserted in the Microsoft

    Excel and organised to aid in inputting the data into the power system model on PTW.

    Building the Model

    The total connected loads for each busbar in the model were calculated based on as-built

    single line diagrams, and then the equivalent load factor was applied to loads connected to

    each busbar to ensure it will match the readings collected from SCADA. An additional diversity

    factor of 87.5% has been applied to the loads below SW411. This diversity factor has been

    applied to simulate the reality that it is highly unlikely for each feeder to experience maximum

    demand simultaneously and for the plant overall loading to match the power station SCADA

    loading. Once the existing loads magnitudes were added to the model the WFE project loads

    were added based on the WFE project load list, with a diversity factor of 90%.

    Transformer impedance values were based on transformer nameplate inspection from the site

    visit. However, where confirmation was not achieved site as-built single line diagrams were

    used. Voltage ratio and power capacity values were added to the model as per as-built single

    line diagrams. All tap positions of transformers were modelled at position zero, meaning 0%

    tap. The Wet Front End project transformers capacity, voltage ratio and impedance values

    were supplied through communication with design and construct project teams during the site

    visit.

    All cables were added to the power system model with respect to material, size, length, and

    quantity as per site as-built single line diagrams. The WFE Projects new cables have been

  • 5/21/2018 Final Report

    14/96

    10

    added to the power system software as per Cloudbreak Enhancement Project Cable Schedule,

    with impedances obtained from Olex manufacturer catalogues.

    Generator Reactance

    As stated in the background section 3.1, the generation is provided by 18 reciprocating diesel

    engines (MTU 20V 4000 G62) directly coupled to individual alternators (AvK HVS1803W2). The

    reciprocating diesel engine acts as the prime mover which produces rotating mechanical

    power to the rotor of the alternator. This arrangement is known as a synchronous generator

    where the main magnetic field is set up by dc current called the field current, which flows

    through the rotor windings. As the rotor rotates, it forces the magnetic field to rotate, causing

    the windings on the stator (armature) to experience a time-varying flux that induces an

    alternating voltage across the output terminals of each of the stator (armature) windings.

    When modelling generators for fault analysis we are concerned with a temporary difference

    between the rotor speed and voltage frequency. This effect is modelled by the alternators sub-

    transient reactance Xd. The manufacturers alternator specification is attached as Appendix C.

    However, while the Cloudbreak power station synchronous generators have an individual

    power rating of 2,607kW, they only operate in continuous mode at 1,742 kW (data collected

    from site visit), and because the load flow and short-circuit analysis will be simulated with the

    generators in continuous mode, the sub-transient reactance Xd need to be re-calculated. This

    calculation is shown below.

    . = 0.8

    = 3259

    "() = 0.163

    = . = 3259 0.8 = 2607

    = 1742

    (%) =

    =17422602

    = 66.95%

    "() = 66.95% "() = 66.95% 0.163 = 0.109

    This operating calculation also applies to the synchronous generators transient reactance, Xd,

    which is shown in the calculation below.

    () = 66.95% () = 66.95% 0.221 = 0.148

    Assumptions

    The overall power system network model was based on the following assumptions:

    Average power output for each generator is assumed to be 1742kW. Peak power outputfor each generator is assumed to be 2123kW;

    The X/R ratio for transformer impedances have been assumed as per AS3851; Transformer taps have been modelled as per site verification, and if unavailable a tap

    setting of 3 (i.e. 0%) has been assumed; VSDs have been modelled with a power factor of 0.93 as per the ABB ACS800 catalogue; Motor loads have been modelled to have a power factor of 0.85;

  • 5/21/2018 Final Report

    15/96

    11

    Feeder loads have been modelled to have a power factor of 0.9; UPS loads have been modelled to have a power factor of 0.95; Lumped motor loads have been assumed to have a R/X ratio of 0.42 and a I(locked

    rotor)/I(full load) ratio of 5 as perAS3851: The calculation of short-circuit currents in

    three-phase a.c. systems;

    Load factor for MC441 connected loads has been assumed to be 0.5863, approximatingoverall load factor from load list with a diversity factor applied;

    DB717 Main Sewage Treatment Plant is assumed to have a motor load of 50kWconnected and the SS711 package substation assumed to have a lumped 200kW motor

    load connected to simulate the worst case power demand for transformer TF03 as per

    SCADA profile;

    Package substation SS714 is assumed to have a 750kW lumped load connected toSW714, as previously modelled in the existing as-built model;

    HPGR circuit is assumed to have a 2500kW lumped load connected to CSI_HPGR_02, aspreviously modelled in existing as-built model;

    Railcar unloading package substation SS718 is assumed to have a 66kW lumped motorload as previously modelled in existing as-built model;

    Camp load has been simplified as a 1400kW lump motor load, and 450kW lump feederload connected to RM700, to simulate worst case load demand as per SCADA profile. As

    a result of this, no load has been modelled connected to RM721 and further

    downstream;

    Emergency Generators shown on FMG Cloudbreak as-built single line diagrams are notmodelled for the purpose of the study, due to unavailability of data;

    The average Wet Front End Project load is assumed to be equal to the peak load of theWet Front End Project load.

    The load flow analysis was based on the following test criteria and assumptions:

    Minimum and maximum voltage levels for all busbars and consumer terminals duringnormal running operation shall be within 90% to 110% of system nominal voltage;

    The synchronous generators were lumped and modelled with an operational voltage atthe 11kV generation busbar with 1pu;

    The largest DOL motor on each switchboard is modelled and the remaining DOL motorloads are aggregated into a lumped motor load;

    Feeder, VSD and UPS loads are aggregated into separate lumped loads for eachswitchboard;

    Typical data are used for simulating some equipment due to the lack of sufficient vendortest reports and data sheets for specific parameters;

    VSDs are modelled as an equivalent constant kVA load.The short circuit analysis was based on the following test criteria and assumptions:

    The IEC 60909 method was selected for the short circuit calculations; For calculation of maximum and minimum short circuit currents, voltage factor c as per

    IEC 60909: Short-circuit currents in three-phase a.c. systemsis applied; All LV motors, with the exception of the largest motor on each bus are modelled without

    cables with a locked rotor current of 5 times rated full load current, as specified in

    AS3851 The calculation of short-circuit currents in three-phase a.c. systems;

    The zero sequence impedance was assumed to be 90% of the transformers positivesequence impedance.

  • 5/21/2018 Final Report

    16/96

    12

    3.3 ResultsLoad Flow Analysis

    The purpose of the load flow analysis is to assess the voltage regulation and loading based on

    acceptable tolerances for switchgear, equipment and conductors. The load flow analysis was

    carried out separately through two different power system scenarios as listed in Table 2-1.

    Table 3-1 Case Studies for Load Flow Analysis

    Case Study Description Plant Loading

    LF-1 Existing Load and Generation 23.2MW

    LF-2 Existing Load and Wet Front End Project 35.65MW

    Load Flow 1 Existing Load and Generation

    LF-1 was performed to determine the minimum steady state voltages for the Cloudbreak mine

    power system for existing plant operating conditions. All results should be acceptable as the

    Cloudbreak mine power system is currently operating. The Cloudbreak mine power system

    configuration for LF-1 is as follows:

    Sixteen 1.742MW (average) 11kV generators operating and all bus-ties are open; TF11 and TF12 tapping are set at 0% Overall plant loading is based on 23.2MW electrical load demand, which corresponds

    to the peak maximum electrical demand during normal operation of the Cloudbreak

    Mine.

    Cloudbreak PTW LF-1 Simulation Results are attached in Appendix D.

    The results for the main switchboards voltage loading are outlined in Table 2-2 for case study

    LF-1.

    Table 3-2 LF-1 Switchgear Results

    Switchgear Nominal Voltage (kV) Steady State Voltage (%) Acceptability

    SW411A 22.000 97.2 Acceptable

    SW411B 22.000 96.1 Acceptable

    SW454 22.000 97.2 Acceptable

    SW451 22.000 97.1 Acceptable

    SW435 22.000 97.2 Acceptable

    SW431 22.000 96.1 Acceptable

    SW426 22.000 96.1 Acceptable

    SW421 22.000 96.0 Acceptable

    MC454 0.400 100.3 Acceptable

    SW455 0.690 100.8 Acceptable

    SW456 0.690 101.1 Acceptable

    MC451 0.400 99.6 Acceptable

    SW452 0.690 97.9 Acceptable

    MC435 0.400 98.4 Acceptable

    SW433 0.690 99.9 Acceptable

    CSI-HPGR 22.000 95.9 Acceptable

    TX02_LV 0.400 95.9 Acceptable

    TX03_LV 0.400 95.9 Acceptable

  • 5/21/2018 Final Report

    17/96

    13

    TX04_LV 0.400 95.9 Acceptable

    MC431 0.400 97.8 Acceptable

    SW432 0.690 98.7 Acceptable

    SW437 () 0.690 99.3 Acceptable

    SW437 (Y) 0.690 99.3 Acceptable

    SW442 0.690 99.2 Acceptable

    MC426 0.400 98.7 Acceptable

    SW427 () 0.690 99.5 Acceptable

    SW427 (Y) 0.690 99.5 Acceptable

    MC428 0.400 98.8 Acceptable

    SW429 () 0.690 98.7 Acceptable

    SW429 (Y) 0.690 98.7 Acceptable

    MC430 0.400 98.9 Acceptable

    SW439 () 0.690 99.6 Acceptable

    SW439 (Y) 0.690 99.8 Acceptable

    SW714 0.400 98.2 Acceptable

    MC421 0.400 98.8 Acceptable

    MC422 0.400 98.4 Acceptable

    SW423 () 0.690 97.3 Acceptable

    SW423 (Y) 0.690 97.3 Acceptable

    CAMP 11.000 97.3 Acceptable

    SB-731 0.400 107.8 *Acceptable

    SB-732 0.400 106.7 *Acceptable

    MC441 0.400 97.5 Acceptable

    * High voltage levels for SB-731 and SB-732 are due to simulation of no load or very small load

    on the busbar.

    The LF-1 Switchgear results indicate that voltage levels for all switchgear busbars in the

    Cloudbreak Mine network, under existing operating conditions, are within the allowable limits.

    However, as mentioned in the methodology section, a diversity factory of 85.7% has been

    applied against the loads to simulate realistic load magnitudes, therefore it is possible that

    these voltages could be higher. If load data was available from SCADA at every MCC and VSD

    switchboard, then the results would be more accurate. However, obtaining this amount of

    information would be quite time consuming, and the project schedule did not allow time to

    carry this out.

    The results for the loading of the major 22kV cables in case study LF-1 are summarised in Table

    2-4. All major 22kV cables are operating below the rated thermal capacity. The thermal

    capacity of the cables has been calculated in PTW using the approach followed in Table 2-3

    regarding de-rating factors. The de-rating factors correspond to those specified inAS3008.1

    Selection of Cable for Alternating Voltages up to and including 0.6/1 kV.

  • 5/21/2018 Final Report

    18/96

    14

    Table 3-3 Cable Current De-rating ApproachMajor Cable De-rating Factor for SW421-P-01 in PTW Model as per AS3008.1

    Cable Arrangement and Type 1 x 1C 240mm Cu XLPE/AWA

    Buried Direct Trefoil for 342m

    Conductor Temperature 90

    Soil Temperature 35

    Ambient De-rating in Ground 0.93

    Depth of Laying in Ground 2m

    De-rating of Depth of Cable in Ground 0.88

    Distance Between Cables 0.45m

    Number of Circuits 1

    Total Number of Circuits in Trench (Worst Case) 6

    De-rating of Multiple Circuits 0.72

    Total De-rating Factor = 0.93 x 0.88 x 0.72

    = 0.59

    Cable Current Rating 450A

    De-rated Cable Current Rating 265A

    (as outlined in Table 2-4)

    Table 3-4 LF-1 Cable Loading Results

    Cable ID From To Capacity (A) Loading (%)OPF2-1 618 59.1

    OPF1-1 618 44.0

    OPF1 OPF1-1 OPF1-4 1226 22.2

    OPF2 OPF2-1 OPF2-14 1226 29.8

    SW411-P-03 OPF1-14 SW411 918 28.0

    SW411-P-04 OPF2-14 SW411 918 39.9

    SW421-P-01 SW411 SW421 265 38.1

    SW426-P-01 SW411 SW426 313 34.8

    SW431-P-01 SW411 SW431 648 16.8

    SW435-P-01 SW411 SW435 648 20.4SW451-P-01 SW411 SW451 274 35.0

    SW454-P-01 SW411 SW454 378 7.7

    The results for the loading of the major transformers for LF-1 are summarised in below Table

    2-5. All major transformers loadings are acceptable and below the rated power capacities.

    Table 3-5 LF-1 Transformer Loading Results

    Transformer ID Transformer Rating (kVA) Transformer Loading (%)

    TF03 3000 11.0

    TF11 27000 51.6TF12 27000 38.4

    TF413 2000 34.9

  • 5/21/2018 Final Report

    19/96

    15

    TF414 2500 43.1

    TF421 2000 22.6

    TF422 2000 28.7

    TF423 5000 56.4

    TF426 2000 22.8

    TF427 5000 14.5

    TF428 2000 20.3

    TF429 5000 27.9

    TF430 2000 16.9

    TF431 2000 46.0

    TF432 5000 28.0

    TF433 5000 27.7

    TF435 2000 60.2

    TF437 5000 18.5

    TF439 5000 9.5

    TF441 2000 25.2

    TF442 5000 18.6

    TF451 2000 28.3

    TF452 5000 61.8

    TF453 5000 24.7

    TF454 2000 12.8

    TF455 5000 11.2

    TF456 5000 5.6

    Load Flow 2 Existing Load and Wet Front End Project

    LF-2 was performed to determine the minimum steady state voltages for the Cloudbreak mine

    power system for existing plant operating conditions plus the addition of the Wet Front End

    project loads. An extra four generators have been added the power station switchboard to

    handle the Wet Front End load requirements. The Cloudbreak mine power system

    configuration for LF-2 is as follows:

    Twenty 1.742MW (average) 11kV generators operating and all bus-ties are open; TF11 and TF12 tappings are set at -2.5%; Overall plant loading is based on 35.65MW electrical load demand, which corresponds

    to the peak maximum electrical demand expected during normal operation when the

    Wet Front End Project becomes operational at the Cloudbreak Mine.

    Cloudbreak PTW LF-2 Simulation Results are attached in Appendix D.

    The results for the main switchboards voltage loading are outlined below in Table 2-6 for case

    study LF-2.

    Table 3-6 LF-2 Switchgear Results

    Switchgear Nominal Voltage (kV) Steady State Voltage (%) Acceptability

    SW411A 22.000 97.0 Acceptable

    SW411B 22.000 97.2 Acceptable

    SW454 22.000 97.0 Acceptable

    SW451 22.000 97.0 Acceptable

    SW435 22.000 97.0 Acceptable

  • 5/21/2018 Final Report

    20/96

    16

    SW431 22.000 97.2 Acceptable

    SW426 22.000 97.2 Acceptable

    SW421 22.000 97.2 Acceptable

    SW505** 22.000 97.0 Acceptable

    TF505A/B/C** 0.690 97.6 Acceptable

    SW506** 0.690 97.3 Acceptable

    MC-507** 0.400 98.7 Acceptable

    MC-508** 0.400 98.9 Acceptable

    MC454 0.400 100.1 Acceptable

    SW455 0.690 100.6 Acceptable

    SW456 0.690 100.9 Acceptable

    MC451 0.400 99.5 Acceptable

    SW452 0.690 97.7 Acceptable

    MC435 0.400 98.2 Acceptable

    SW433 0.690 99.7 Acceptable

    CSI-HPGR 22.000 95.8 Acceptable

    TX02_LV 0.400 95.8 Acceptable

    TX03_LV 0.400 95.8 Acceptable

    TX04_LV 0.400 95.8 Acceptable

    MC431 0.400 99.0 Acceptable

    SW432 0.690 100.0 Acceptable

    SW437 () 0.690 100.5 Acceptable

    SW437 (Y) 0.690 100.5 Acceptable

    SW442 0.690 100.5 Acceptable

    SW440** 0.690 99.4 Acceptable

    MC426 0.400 100.1 Acceptable

    SW427 () 0.690 100.2 Acceptable

    SW427 (Y) 0.690 100.7 Acceptable

    MC428 0.400 99.0 Acceptable

    SW429 () 0.690 100.7 Acceptable

    SW429 (Y) 0.690 100.7 Acceptable

    MC430 0.400 99.8 Acceptable

    SW439 () 0.690 99.3 Acceptable

    SW439 (Y) 0.690 99.1 Acceptable

    SW714 0.400 99.4 Acceptable

    SW443 ()** 0.690 100.4 Acceptable

    SW443 (Y)** 0.690 100.5 Acceptable

    MC421 0.400 100.0 Acceptable

    MC422 0.400 99.7 Acceptable

    SW423 0.690 98.6 Acceptable

    SW423 0.690 98.5 Acceptable

    CAMP 11.000 97.3 Acceptable

    SB-731 0.400 107.8 *Acceptable

    SB-732 0.400 106.7 *Acceptable

    MC441 0.400 97.4 Acceptable

    * High voltage level is due to simulation of no load or very small load on the busbar.

    ** New Wet Front End project switchgear

  • 5/21/2018 Final Report

    21/96

    17

    The LF-2 Switchgear results indicate that the voltage levels for all switchgear busbars in the

    Cloudbreak Mine power system under existing operating conditions plus the additional Wet

    Front End project loads are within the allowable limits. However, in order to maintain

    allowable voltage levels at switchgear SW411A and SW411B, tapping for both TF11 and TF12

    need to be set at -2.5%.

    The results for the loading of the major 22kV cables in case study LF-2 are summarised in Table

    2-7. All major 22kV cables are operating below the rated thermal capacity. The thermal

    capacity of the cables was calculated using the same approach as outlined in LF-1.

    Table 3-7 LF-2 Cable Loading Results

    Cable ID From To Capacity (A) Loading (%)

    TF11 OPF2-1 618 80.0

    TF12 OPF1-1 618 82.0

    OPF1 OPF1-1 OPF1-4 1226 41.4

    OPF2 OPF2-1 OPF2-14 1226 40.3

    SW411-P-03 OPF1-14 SW411 918 53.6

    SW411-P-04 OPF2-14 SW411 918 53.8

    SW421-P-01 SW411 SW421 265 37.7

    SW426-P-01 SW411 SW426 313 77.0

    SW431-P-01 SW411 SW431 648 16.7

    SW435-P-01 SW411 SW435 648 20.4

    SW451-P-01 SW411 SW451 274 35.0

    SW454-P-01 SW411 SW454 378 69.8

    The results for the loading of the major transformers for LF-2 are summarised in Table 2-8. All

    major transformer loadings are acceptable and are below the rated power capacity.

    Table 3-8 LF-2 Transformer Loading Results

    Transformer ID Transformer Rating (kVA) Transformer Loading (%)

    TF03 3000 11.0

    TF11 27000 71.6

    TF12 27000 73.5

    TF413 2000 34.5

    TF414 2500 42.6

    TF421 2000 23.1TF422 2000 28.3

    TF423 5000 55.7

    TF426 2000 18.6

    TF427 5000 18.6

    TF428 2000 43.2

    TF429 5000 13.7

    TF430 2000 23.5

    TF431 2000 45.4

    TF432 5000 27.7

    TF433 5000 27.8

    TF435 2000 60.2

  • 5/21/2018 Final Report

    22/96

    18

    TF437 5000 18.2

    TF439 5000 41.6

    TF440 5000 37.8

    TF441 2000 25.2

    TF442 5000 18.4

    TF443 5000 31.1

    TF451 2000 28.4

    TF452 5000 61.9

    TF453 5000 24.8

    TF454 2000 12.8

    TF455 5000 11.2

    TF456 5000 5.6

    TF505A 1750 78.0

    TF505B 1750 78.0

    TF505C 1750 78.0

    TF506 5000 66.5TF507 2000 41.5

    TF508 2000 37.5

    Additional Generation Calculation

    The load flow simulations in PTW indicate that the additional Wet Front End Project loads

    increase the maximum demand to 35.65MW from an existing demand of 23.2MW. As the

    Cloudbreak power station operates on an n+2 configuration with 18 generators, it is not

    capable of supplying this load. The determination of the minimum number of additional

    generators required to meet the additional load demands will consider both the peak and

    average load demands.

    Each diesel generator is capable of supplying an average load of 1.742MW, with a peak of

    2.123MW. The average load experienced at the power station in the existing load scenario (LF-

    1) has been calculated from the SCADA outputs (Appendix B) and is 18.3MW. However this

    magnitude excludes the operation of the Lump Circuit (SW454), which was not operating

    during the period that the SCADA outputs were taken. The Lump Circuit (SW454) average load

    was calculated from separate SCADA outputs to be 0.45MW. No data was available for the

    average load of the Wet Front End Project, so the conservative assumption was made that the

    average of the Wet Front End Project load is equal to the peak load of 12.43MW.

    Table 3-9 Additional Generation Calculation Information

    Variable Type Magnitude Comments

    () Average GeneratorPower

    1.742MW Confirmed with

    power station

    operators.

    () Peak GeneratorPower

    2.123MW Confirmed with

    power station

    operators.

    () Average Existing Load 18.75MW Addition of ExistingLoad 18.3MW and

    Lump Circuit Load

    0.45MW.

  • 5/21/2018 Final Report

    23/96

    19

    () Average WFE Load 12.42MW Same as peakmagnitude

    conservative.

    () Peak Existing Load 23.22MW Load Flow 1 powerstation supply.

    () Peak WFE Load 12.42MW Load Flow 2 power

    station supply.() Spinning Reserve 1.9MW From power station

    due diligence report.

    The calculation of the minimum number of generators required()to supplythe additional average WFE load demand and spinning reserve is outlined below.

    () =() + () + ()

    () = 18.75 + 12.42 + 1.9

    () = 33.1

    () =()()

    =33.11.742

    = 19.0

    The calculation of the minimum number of generators required()to supply theadditional peak WFE load demand and spinning reserve is outlined below.

    () =() + () + ()

    () = 23.22 + 12.42 + 1.9

    () = 37.55

    () =()()

    =37.552.123

    = 17.7

    The power station is therefore required to supply an average load of 31.18MW and a peak load

    of 35.65MW. The minimum number of generators at 1.742MW required to supply the average

    load is 19. With the current configuration of 16 available (2 generators out of service) an extra

    3 generators are required to be installed at the power station. However, it was agreed

    internally that one additional generator would be included, as the change in operating

    philosophy at the power station was based on machine maintenance, and an n+3 configurationwould suit better (2 in maintenance and 1 redundant). As a result, the power station will need

    an extra 4 generators (22 in total) installed o satisfy the increase load demand from the WFE

    expansion.

    Short-Circuit Analysis

    The short-circuit analysis is concerned with the currents that flow as a result of a short circuit,

    and is calculated at each switchgear as per IEC 60909 standard for three phase balanced and

    unbalanced short circuit conditions. IEC 60909 short-circuit calculation methodology complies

    with requirements ofAS3851 The calculation of short-circuit currents in three-phase a.c.

    systems. The calculation of short circuit currents includes the short circuit currentcontributions from the generators and from induction motors.

  • 5/21/2018 Final Report

    24/96

    20

    The minimum and maximum fault currents have been calculated considering the following

    fault scenarios:

    Three-phase to ground fault (LLLE) Single-phase to ground fault (LE) Line-to-line fault (LL) Line-to-line to ground fault (LLE)

    For each of the fault scenarios above, a voltage c-factor was applied in accordance with IEC

    60909. The voltage factor (c) represents a conservative method of taking into account the

    effects of variation of voltage, changing transformer taps, capacitance and the loads.

    Earth fault currents on 11kV and 22kV systems are limited by the earthing zig-zag transformer

    TF01. LV systems are solidly earthed at the system star point and can generate very high

    currents.

    The short-circuit analysis was carried out separately through two different power system

    scenarios as listed in Table 2-10.

    Table 3-10 Case Studies for Load Flow Analysis

    Case Study Description Comments

    SC-1 Maximum Short-Circuit Current for

    Existing System SW411 bus tie is closed 18 generators are in service Plant loading 23.2MW (LF-1)

    SC-2 Maximum Short-Circuit Current for

    Wet Front End Project

    SW411 bus tie is closed 22 generators are in service Plant loading 35.65MW (LF-2)

    Short-Circuit 1 - Short-Circuit Current for Existing System

    Cloudbreak PTW SC-1 Simulation Results are attached in Appendix D.

    The results regarding the maximum (LLLE Short-Circuit) and minimum (LE Short-Circuit) fault

    currents for existing switchgear in case study SC-1 are outlined in Table 2-11.

    Table 3-11 Switchgear Fault Currents Results for SC-1

    Switchgear

    Operating Scenario SC-1 Switchgear Rating

    Acceptability

    Ik" LLLE Ip Ik" LE ib ip1/2

    cycle

    Sym

    Current

    (kA)

    Peak

    Asym

    Current

    (kA)

    1/2

    cycle

    Sym

    Current

    (kA)

    Symm

    Breaking

    Current

    Max

    Asym

    Current

    (kA)

    Station HV Switchboard 22.8 55.6 0.4 25kA 3s 62.5kA

    Station LV Switchboard 25.1 60.5 26.2 50kA 1s 105kA

    SW411A 6.6 15.8 0.5 25kA 3s 62.5kA

    SW411B 6.6 15.9 0.5 25kA 3s 62.5kA

    SW454 6.6 15.7 0.5 25kA 3s 62.5kASW451 6.6 15.3 0.5 25kA 3s 62.5kA

    SW435 6.6 15.8 0.5 25kA 3s 62.5kA

  • 5/21/2018 Final Report

    25/96

    21

    SW431 6.6 15.8 0.5 25kA 3s 62.5kA

    SW426 6.6 15.7 0.5 25kA 3s 62.5kA

    SW421 6.6 15.5 0.5 25kA 3s 62.5kA

    SW455 25.4 59.9 50kA 1s 105kA

    SW456 25.5 60.5 50kA 1s 105kA

    MC451 44.1 101.2 44.3 50kA 1s 105kA

    SW452 25.2 59.7 50kA 1s 105kA

    MC435 55.9 123.2 52.1 50kA 1s 105kA Unacceptable

    SW433 25.3 60.3 50kA 1s 105kA

    MC431 53.8 119 50.4 50kA 1s 105kA Unacceptable

    SW432 25.4 60.3 50kA 1s 105kA

    SW437 () 25.5 60.7 50kA 1s 105kA

    SW437 (Y) 25.5 60.7 50kA 1s 105kA

    MC426 46.8 105.9 45.9 50kA 1s 105kA Unacceptable

    SW427 () 25.5 60.6 50kA 1s 105kA

    SW427 (Y) 25.5 60.6 50kA 1s 105kAMC428 43.2 99.1 43.5 50kA 1s 105kA

    SW429 () 25.5 60.3 50kA 1s 105kA

    SW429 (Y) 25.5 60.3 50kA 1s 105kA

    MC430 44.1 101 44.1 50kA 1s 105kA

    SW439 () 25.6 60.7 50kA 1s 105kA

    SW439 (Y) 25.6 60.7 50kA 1s 105kA

    MC421 43.1 99.3 43.6 50kA 1s 105kA

    MC422 48.5 109.3 44.1 50kA 1s 105kA Unacceptable

    SW423 () 26.9 63.6 50kA 1s 105kA

    SW423 (Y) 26.9 63.6 50kA 1s 105kA

    MC441 40.7 92.9 41.7 50kA 1s 105kA

    The Switchgear Fault Currents Results for SC-1 indicate that the majority of the HV & LV

    switchgear ratings in the Cloudbreak Mine substations are appropriate for the maximum

    system short circuit currents. The results indicated that MC431, MC435, MC426 and MC422

    exceed the equipment rating and require further investigation and possible corrective action.

    The unacceptable fault ratings are listed below:

    MC431 (107.6% of the rating)

    MC435 (111.8% of the rating)

    MC426 (100.9% of the peak rating)

    MC422 (104.1% of the peak rating)

    Calculation of Fault Currents for MC435

    The PTW Short-Circuit Simulation Results for MC435 (SC-1) are attached in Appendix E.

    The fault levels on the switchgear have been calculated in PTW model using the approach

    given below. This approach corresponds toAS3851: The calculation of short-circuit currents in

    three-phase a.c. systems.

  • 5/21/2018 Final Report

    26/96

    22

    Three-phase short-circuit (LLLE) Clause 8.4.2 (A20) of AS3851

    " =

    3

    Table 3-12 Three-phase short-circuit variables

    Three-phase short-circuit variables

    " Initial symmetrical short-circuit current amplitude (r.m.s.)

    Voltage factor as per section 5.2 of AS3851 Base three-phase apparent power

    Per unit symmetrical short-circuit impedance Nominal system voltage, line-to-line (r.m.s.)

    = 1.1

    = 100

    = 2.84

    = 400

    " () =1.1 100 106

    2.84 400 3= 55.905

    " () = 55.860

    (%) =" () " ()

    " ()

    55.905 55.86055.860

    = 0.081%

    Peak short-circuit current for LLLE - Section 8.5.2.1 of AS3851

    = " 2

    = 1.02 + 0.983/

    Table 3-13 Peak Short-Circuit Current Calculation Variables

    Peak short-circuit current for LLLE variables

    Peak short-circuit current contribution a three-phase short-circuit" Initial symmetrical short-circuit current amplitude (r.m.s.)

    Factor for the calculation of the peak short-circuit current

    Resistance to Reactance Ratio of the system

    " () = 55.860

    = 0.20

    = 1.02 + 0.9830.20 = 1.5578

  • 5/21/2018 Final Report

    27/96

    23

    () = 1.5578 55.860 103 2 = 123.07

    () = 123.16

    (%) =123.07 123.16

    123.16=0.07%

    Line-to-earth short-circuit - Clause 8.4.5 (A33) of AS3851

    " = 3

    (0) + (1) + (2)

    Table 3-14 Line-to-Earth Short-Circuit Current Calculation Variables

    Line-to-earth short-circuit variables

    " Initial symmetrical short-circuit current amplitude (r.m.s.)

    Voltage factor as per section 5.2 of AS3851 Base three-phase apparent power

    Nominal system voltage, line-to-line (r.m.s.)() Per unit zero-sequence impedance() Per unit positive-sequence impedance() Per unit negative-sequence impedance

    = 1.1

    = 100

    = 2.84

    = 400

    (0) = 3.43

    (1) = 2.84

    (2) = 2.88

    " () =1.1 100 106 3

    400 (3.43 + 2.84 + 2.88)= 52.06

    " () = 52.05

    (%) =52.06 52.05

    52.05= 0.081%

  • 5/21/2018 Final Report

    28/96

    24

    For the following HV and LV switchgear, the apparent short circuit current levels are very high

    and exceed 90% of the equipment rating:

    11kV Main Switchboard (91.2% of the rating)

    MC421 (94.6% of the peak rating)

    MC428 (94.4% of the peak rating)

    MC430 (96.2% of the peak rating)

    MC451 (96.4% of the peak rating)

    Short-Circuit 2 - Short-Circuit Current for Wet Front End Project

    Cloudbreak PTW SC-2 Simulation Results are attached in Appendix D.

    The results regarding the maximum (LLLE Short-Circuit) and minimum (LE Short-Circuit) fault

    currents for WFE switchgear in case study SC-2 are outlined in Table 2-15.

    Table 3-15 Switchgear Fault Currents Results for SC-2

    Switchgear

    Operating Scenario SC-2 Switchgear Rating

    Acceptability

    Ik" LLLE Ip Ik" LE ib ip

    1/2 cycle

    Sym

    Current

    (kA)

    Peak Asym

    Current

    (kA)

    1/2 cycle

    Sym

    Current

    (kA)

    Sym

    Breaking

    Current

    Max

    Asym

    Current

    (kA)

    Station HV

    Switchboard

    27.9 67.8 0.41 25kA 3s 62.5kA Unacceptable

    SW411A 7.6 17.9 0.45 25kA 3s 62.5kA

    SW411B 7.6 17.9 0.45 25kA 3s 62.5kA

    SW506 25.2 59.4 50kA 1s 105kA

    MC507 48.5 107.3 48.6 65kA 1s 143kA

    MC508 48.7 107.8 48.7 65kA 1s 143kA

    SW427* 25.7 60.9 50kA 1s 105kA

    SW440 26.1 61.3 50kA 1s 105kA

    MC428* 43.4 99.4 43.6 50kA 1s 105kA

    MC430* 44.3 101.4 44.3 50kA 1s 105kA

    SW443 () 44 99.6 50kA 1s 105kA

    SW443 (Y) 43.7 95.4 50kA 1s 105kA

    * Existing switchgear with direct WFE loads connected.

    As the power station switchboard now has 22 generators connected, the fault levels have

    exceeded the switchboard rating and because this arrangement is not practical the

    downstream switchgear results are not relevant. This issue can be potentially resolved by

    installing a current limiting device between the existing power station switchboard and a new

    switchboard with the new generators connected. The solution to this problem is covered later

    in this report.

  • 5/21/2018 Final Report

    29/96

    25

    3.4 ConclusionThe Cloudbreak expansion load flow and short-circuit study was carried out to evaluate firstly

    the existing operation of the power system and the effect of the additional loads due to the

    Wet Front End Project on the power system. This evaluation involved determining the required

    ratings of major electrical equipment and acceptable power generation capacity.

    The load flow analysis indicated that under the existing operation scenario (LF-1) a maximumoverall load of 23.2MW is expected with 16 generator units running and 2 standby generators

    in n+2 configuration. The addition of the Wet Front End Project will add a loading of 12.43MW

    to the Mine power system. This additional load requires a minimum of three 1.742MW

    (average) generators, which will need to be added to the plant power generation. It was

    recommended that a minimum of four 1.742MW (average) generators be added to the plant

    power generation which will further provide a minimum spinning reserve of 1.9MW for an n+3

    configuration and ensure acceptable electrical system stability. The load flow analysis results

    indicate that the voltage magnitudes and loadings on all major equipment are acceptable.

    The short-circuit analysis indicated that the 11kV power station HV switchboard with fouradditional generators will result in potential fault levels on the switchboard that are above the

    switchgear ratings and are therefore unacceptable. The existing scenario short circuit analysis

    (SC-1) indicated that some switchgear ratings are unacceptable specifically MC431, MC435,

    MC426 and MC422, as the short-circuit currents exceeded the switchgear rating. Furthermore,

    the short-circuit currents experienced on switchgear MC421, MC428, MC430 and MC451 are

    greater than 90% of the switchgear rating. As a result it was recommended by the Worley

    Parsons Power Division that these particular busbars to be further analysed and corrective

    measures to be put in place if needed.

    Taking into account the issues identified above in the load flow and short-circuit study, the

    following recommendationswere revised:

    Installation of four 1.742MW (average) generators as per existing type on a new 11kVswitchboard, with a current limiting device between the switchboard and the existing

    11kV HV power station switchboard to reduce and eliminate fault contribution. Also,

    to further balance the number of generators connected by having an even quantity of

    generators on both the existing (11 generators) and proposed (11 generators) power

    station switchboards.

    The PTW Cloudbreak mine power system model needs to be updated specifically toeliminate the applied load factor and to determine the operational loading on each

    MCC and busbar to improve the accuracy for future simulations.

    Determine the operational short circuit values of switchgear exceeding or within 90%the equipment rating (i.e. MC431, MC435, MC422, MC426, MC421, MC428, MC430,

    and MC451).

    3.5 Current StatusAs outlined above, the load flow and short-circuit study identified three issues that FMGL

    needed to resolve in order to carry out the Wet Front End Expansion. The following actions are

    currently being carried out to rectify these issues. These actions correspond to therecommendations identified from the load flow and short-circuit study.

  • 5/21/2018 Final Report

    30/96

    26

    Power Station additional generation requirements and switchgear rating

    As outlined in the additional generation calculation section of the results, a further four

    generators need to be installed in order to supply the extra 12.42MW peak load from the WFE

    expansion and to satisfy the spinning reserve requirement of 1.9MW . Also, the 11kV power

    station switchboard will exceed its current switchgear rating if four generators are connected.

    Attached in Appendix F is the proposed FMG approved generation arrangement for the power

    station. The proposed design includes an additional four generators and three existing

    generators to be installed on a new 40kA rated switchboard which is connected to the existing

    switchboard by a current limiting fuse. Also, feeder TF12 will be disconnected from the existing

    HV power station switchboard to be connected directly to the new HV power station

    switchboard, as well as a new earthing transformer and auxiliary switchboard.

    Various downstream Motor Control Centre switchgear ratings

    The determination of the operational short circuit values for various motor control centre

    switchgear which exceed or are within 90% the equipment rating (i.e. MC431, MC435, MC422,

    MC426, MC421, MC428, MC430, and MC451) are currently being studied using power system

    software PowerFactory by DIgSILENT. This involves a more detailed short-circuit calculation

    where the model will include more accurate input information such as specific line lengths,

    manufacturer specified motor contributions which include realistic de-rating factors, and load

    magnitude which related operational behaviour and data. This study is currently being carried

    out, and based on the results the decision will be made on whether the motor control centre

    switchgear rating needs to be upgraded or not.

  • 5/21/2018 Final Report

    31/96

    27

    4 Cloudbreak Dragline Excavator Dynamic Study4.1 BackgroundFMGL is interested in deploying a dragline excavator as it will increase the productivity of their

    Cloudbreak mine site. A dragline is an excavating machine that can perform strip mining at a

    very productive rate. Draglines offer the lowest material removal cost and are the most

    versatile excavating system in the mining industry. The particular dragline to be implemented

    into the FMG mining environment has a dynamical power cycle profile and the power is to be

    supplied through high voltage trailing cables from Cloudbreak Power Station. The dragline

    manufacturer is Bucyrus; the product specification sheet is attached in Appendix G. The

    dragline performs the following five exercises outlined in Table 2-16 during its excavation

    cycle, which takes 60 seconds.

    Table 4-1 Bucyrus 8750-81 Dragline Electrical Details for Typical Excavation Cycle

    Bucyrus 8750-81 Dragline Electrical Details for Typical Excavation Cycle

    Exercise State of DraglinePower

    Peak PowerMagnitude (kW)

    Exercise duration/period(seconds)

    Load Bucket Drag Consumption 23,970 13.2/0 13.2

    Hoist and Swing Consumption 28,600 24.0/13.2 37.2

    Stop Swing and Dump Regeneration 4,100 4.2/37.2 41.4

    Swing Back and Lower Consumption 12,200 11.4/41.4 52.8

    Stop Swing Back and

    Position for next cycle

    Regeneration 17,160 7.2/52.8 60

    This typical excavation cycle is graphically represented in Figure 2-1.

    Figure 4-1 Bucyrus 8750-81 Dragline Typical Real Power vs. Time Curve

    -18000

    -15000

    -12000

    -9000

    -6000

    -3000

    0

    3000

    6000

    9000

    12000

    15000

    18000

    21000

    24000

    27000

    30000

    0 5 10 15 20 25 30 35 40 45 50 55 60

    RealPower

    (kW)

    Time (sec)

    Bucyrus 8750-81 Dragline Typical Real Power vs. Time Curve

  • 5/21/2018 Final Report

    32/96

    28

    Given the draglines high power consumption, regenerative behaviour and dynamic cycle,

    FMGL engaged DIgSILENT Pacific to perform a study to evaluate the dynamic stability of the

    Cloudbreak Mine Power System and to see if the technology is electrically practical.

    The works of the dynamic study were to evaluate the effects of operating the dragline on the

    Cloudbreak power system carry out, dynamic performance analysis, determine system stability

    and propose options for power system control. The study also evaluated the interconnection

    of the Cloudbreak and Christmas Creek power stations, as this would be an effective solution

    to potential high voltage connection issues of the dragline and also enhance the integrity of

    both power systems.

    4.2 MethodologyConsignment with DIgSILENT

    From start to finish, the intern was on a consignment with DIgSILENT Pacific, which involved

    the data collection, modelling and project management of the dynamic study. This

    arrangement allowed the intern to communicate the project development during theexecution of the project between the FMGL Principal Electrical Engineer and DIgSILENT Pacific

    project team, which consisted of one Principal Electrical Engineer and one Senior Electrical

    Engineer. The intern met on a daily basis with the DIgSILENT Pacific project team and had a

    workstation at their office.

    Software

    The steady state and dynamic modelling was done through the company owned software

    DIgSILENT PowerFactory v14.0.523. The intern had previously used DIgSILENT PowerFactory

    during his studies at University and was familiar with the power system software. The team at

    DIgSILENT also provided on the job training during the course of the project to help familiarisethe intern with procedures that DIgSILENT practiced.

    Building the Model and Input Data

    The existing Cloudbreak power system PowerFactory model was modelled similar to the

    system identified in Section 4.1, and the load data used in the model is relevant to the SCADA

    Cloudbreak load demand information from 15/08/2011 - 17/08/2011, as attached in Appendix

    B. In order to satisfy the load requirements of the dragline peak power magnitude of 28.6MW,

    an additional six 2.42MW generators were connected to the Cloudbreak power station

    switchboard. This results in 21 x 2.42MW peak generation capacity and three 2.42MW

    generators not in service to satisfy the power station operating philosophy of (n+3). Buildingthe Cloudbreak model was a straightforward process, as the power system had already been

    modelled in SKM PTW software, as mentioned in section 4.1, and all the necessary

    documentation was available.

    The 11kV Christmas Creek power system model includes 23 x 2.42MW peak generation

    capacity and three 2.42MW generators not in service to satisfy the Christmas Creek power

    station operating philosophy of (n+3). The current Christmas Creek peak load demand is

    24.4MW and was obtained from the site load-demand list schedulefrom the site electrical

    engineers. However the T155 expansion includes an additional future peak load of 27MW and

    as a result this increases the total future maximum load demand to 51.4MW. A diversity factorof 0.9 was applied, resulting in a total future maximum load demand of 46.3MW.

  • 5/21/2018 Final Report

    33/96

    29

    The intern was heavily involved in building the Christmas Creek Model. The data collection

    process was quite extensive due to the fact that the Christmas Creek Mine only finished

    construction in 2011, the as-built drawings were not documented, and the T155 expansion of

    the mine was currently being implemented. This gave the intern an excellent opportunity to

    work alongside the Christmas Creek principal electrical engineer in drafting up the entire

    Christmas creek power system and incorporating the T155 expansion. The general Christmas

    Creek power system layout is attached in Appendix I which outlines the generation,

    distribution and load arrangements.

    Flywheel

    One of the power system control implementations used in the dynamic study was to utilize a

    Flywheel Energy Storage System, which will allow peak shaving and further stability support

    to the power system. The primary function of the FESS is to provide real and reactive power

    support to a power system. Traditionally extra spinning reserve is the method used to handle

    large cyclic loads. However this is quite an expensive approach (increased fuel consumption),

    and in some cases diesel generator response to fluctuating loads does not occur in an

    acceptable time period.

    A flywheel energy storage system has the following benefits:

    Smoothes out cyclic and transient loads Masks load fluctuations from the power supply Voltage compensation through reactive power injection Highly dynamic with response in 5 milliseconds from zero to nominal power Modular design with no limit to the number of units paralleled Very low harmonic content

    The brand and model of the flywheel used in the dynamic study to provide power system

    control was the PowerStore 1800. The construction of the flywheel is shown in Figure 2-2.

    Figure 4-2 Construction of PowerStore Flywheel

    Flywheels store mechanical energy which can be transferred to and from the flywheel by an

    electrical machine (generator/motor) and power electronics. The kinetic energy stored in a

    flywheel is proportional to the inertia and the rotational speed squared. The main components

    of the flywheel include a power converter (AC-DC-AC), controller (control and SCADA system),

    stator, bearing and a rotor. The flywheel unit rotates at a rated speed of 3600 rev/min anduses a pressurised helium environment to reduce frictional losses. The generator/motor is

    driven by a variable speed drive converter that varies the voltage and frequency to control the

  • 5/21/2018 Final Report

    34/96

    30

    power coming into or out of the flywheel. The complete flywheel energy storage system is

    installed in an eighteen tonne 12000mm x 2480mm x 3330mm shipping container as shown

    in Figure 2-3.

    Figure 4-3 PowerStore Flywheel Substation Layout

    The electrical details of the PowerStore 1800 flywheel is outlined in Table 2-17 below.

    Table 4-2 PowerStore Flywheel Specification

    PowerStore Flywheel Electrical Specification

    Nominal Voltage Rating 380VAC 440VAC

    Nominal Current Rating 2500A

    Energy Storage (@ 3600rpm) 18MW.sec

    Nominal Apparent Power Rating 1800kVA

    Nominal Real Power Rating 1650kW

    Nominal Reactive Power Rating 1800kvar

    Power Conversion Efficiency >90% (charge or discharge)

    Dragline

    The electrical system within the dragline excavator comprises an installed capacity of 1.47MW.

    There are 30 main motors (10 swing motors, 8 hoist motors, 8 drag motors and 4 propel

    motors) which are distributed by 4 x 5MVA 22/0.9kV transformers and controlled on a 900VDC

    interface including 42 IGBT inverters and 36 IGBT rectifiers. The converters allow power factor

    control between 0.8 and 0.93 leading, however for the purposes of this dynamic study the

    dragline power factor is set at 1.0 for all conditions.

    Cooling System

    Flywheel

    Control System Inverters Transformer

  • 5/21/2018 Final Report

    35/96

    31

    The intern was involved in calculating the total energy consumption and regeneration of the

    dragline. This calculation would aid in both sizing and determining the number of flywheels

    required to control the power load from the dragline. It also assisted in the dynamic modelling

    of the dragline in the study. The intern firstly had to convert the dragline typical real power

    versus time curve from the manufacturer to MSExcel. As this was the only source of

    information and the manufacturer was unable to provide reasonable data on the curve, the

    intern converted the information from the manufacturer specification to electronic data using

    graphing software Digitizelt v1.5. This software scans the profile of the curve and a scaling

    factor is then applied which produces the data points (x-time, y-real power) in an MSExcel

    (.csv) format. The intern then applied the trapezoidal method to the data to calculate the

    approximate area under the curve. The dragline MSExcel data, method and calculations are

    attached in Appendix J.

    The required number of flywheels was calculated based on peak shaving the energy

    consumption of the dragline with magnitudes above 21MW (value decided by FMG Principal

    Electrical Engineer). The calculations was done using the dragline model in MSExcel. The

    MSExcel spreadsheet for flywheel calculation is attached in Appendix J.

    The dragline is to be supplied by an OHL supply circuit incorporating 15 x 2km sections with 16

    drop points. This power supply is distributed through a 20MVA 11/22kV step-up transformer

    connected to the Cloudbreak power station. The purpose of this drop point arrangement is

    because over time the dragline will move over a distance of 30km as it removes overburden

    from various sections of the mine pit. At each drop point, power is supplied through a 2km

    trailing cable to the dragline. This arrangement is covered in more detail later in this report.

    Future Interconnection

    As this is only a feasibility study, the interconnection between the two power stations was only

    a simple 66kV design, that incorporated two 40MVA 11/66kV step-up transformers and a

    40km (approximate distance between Cloudbreak and Christmas Creek) single circuit ACSR/GZ

    Lemon as the phase conductors and a 24 fibre OPGW as the earth conductor. The

    interconnection arrangement was decided through exploring three different possible options

    that incorporated both redundancy and reliability. The three possible interconnection options

    were the following:

    1. One 40km 66kV single circuit with two 40MVA 11/66kV step-up transformersconnecting both 11kV power station switchboards.

    2. Two 40km 66kV single circuits with two 40MVA 11/66kV step-up transformers percircuit connecting both 11kV power station switchboards.

    3. Two 40km 66kV single circuits with one 40MVA 11/66kV step-up transformer (CC) andone 40MVA 22/66kV step-up transformer (CB) per circuit connecting a new 22kV

    Cloudbreak switchboard (between the 11kV power station switchboard and SW411)

    and the Christmas Creek 11kV power station switchboard.

    Option 1 was selected for this study, as it was the simplest design and would be the cheapest

    reliable arrangement.

    Dynamic Models

    The study assumed that the generators at both Cloudbreak and Christmas Creek are identical

    in terms of machine and controller parameters. The total inertia of the engine, generator

  • 5/21/2018 Final Report

    36/96

    32

    flywheel, rotor and coupling is 0.7s/MW. It is assumed that all generators at both Cloudbreak

    and Christmas Creek operate less than 3% frequency droop. The dynamic and excitation model

    was not available for the Cloudbreak and Christmas Creek engines; instead an appropriate

    model was suggested, tested and used in the study.

    The flywheel dynamic model was developed by DIgSILENT and used the following control

    strategy and assumptions, which were discussed with a PowerCorp representative organised

    by the intern. The interns dragline line energy modelling aided in this process.

    Maximum import/export power of 1.65MW within 5ms. Grid converter has a rating of 1.8MVA. Capability of control output/input active power according to set points. Capability of performing voltage control. Rated at maximum 18MWs of storage energy. Identify the draglines peak consumption duration, utilising flywheel MW capacity to

    supply the draglines peak demand.

    Identify the regeneration duration of the dragline and utilise the flywheels capacity toconsume the regeneration energy.

    MW utilisation of flywheel is the first priority, the remaining MVA capacity of the gridconverter side is used to stabilise the flywheels terminal voltage.

    The state of charge set point is set at 80%, which is controlled by a slow outercontroller loop to compensate for the possible differences between the generation

    and consumption cycle.

    Test Criteria

    To assess the voltage stability, the PV curve method was used to evaluate the voltage versus

    power consumption at the dragline point of common coupling. This assessment provides an

    estimation of the supply circuits power transfer capability. The power systems dynamic

    behaviour was simulated over a 180 second period which is equivalent to three typical cycles

    of the draglines operation as shown in Figure 2-1. The dynamic study was evaluated over

    various operating scenarios and was assessed on the following limits:

    +/-2% frequency deviation and +/-5% voltage variation at each of the power stations. -20/+10% voltage variation at the dragline connection to the trailing cable. Maintaining generators MVA loading below 85% rating.

    The power loading at each power station is assumed to be at maximum demand to model the

    worst case scenario for each case study.

  • 5/21/2018 Final Report

    37/96

    33

    Case Studies

    The system arrangement for each case study is outlined in Table 2-18.

    Table 4-3 Dynamic Study details of Case Studies

    Study

    Case

    #Cloudbreak

    Genset

    #Christmas

    Creek Genset

    66kV

    Interconnection

    Dragline

    Supply

    #Flywheel

    1 15 N/A No 22kV single

    circuit

    0

    2A 21 N/A No 22kV double

    circuit

    0

    2B 21 N/A No 22kV double

    circuit

    5

    2C 21 23 Yes 22kV double

    circuit

    5

    3A 21 23 Yes 66kV single

    circuit

    0

    3B 21 23 Yes 66kV single

    circuit

    0

    In regards to dragline supply connection the following four arrangements were used for the

    respective case study and are shown in Appendix K.

    22kV single circuit 1

    This 22kV supply option, a 20MVA 11/22kV transformer is connected to Cloud Break power

    station 11kV switchboard to supply a 30km dragline single supply circuit. The cable selected for

    this circuit is a single ACSR Phosphorus phase conductor from the OLEX catalogue.

    22kV double circuit 2A

    The 22kV dragline supply connection for 2A is the same as case study 1, however two 30km

    dragline supply circuits are modelled between the Cloud Break power station 11kV

    switchboard and the dragline.

    22kV double circuit with flywheel power control system 2B

    The 22kV dragline supply connection for 2B is the same as case study 2A however the flywheel

    power control system which consists of five parallel flywheels as specified in this report is

    connected at drop point 11.

    22kV double circuit with interconnection and flywheel power control system 2CThe 22kV dragline supply connection for 2C is the same as case study 2B however the 66kV

    interconnection as specified earlier between the Cloudbreak and Christmas Creek power

    station is used in this case study.

    66kV single circuit with interconnection 3A/3B

    For the 66kV supply option, the 66kV 30km dragline supply circuit is connected to the

    Cloudbreak side interconnection gantry. A 20MVA 66/22kV transformer is apparent between

    the 66kV dragline single supply circuit and the dragline. The cables selected for this circuit are

    single ACSR Grape phase conductors from the OLEX catalogue.

  • 5/21/2018 Final Report

    38/96

    34

    4.3 ResultsThe results examine the effect of transient disturbances from the dragline on the power

    system. The objective was to determine whether or not the power system would return to

    synchronous frequency, sustain acceptable voltage levels and generator loading after

    experiencing a transient disturbance produced by the dragline. PowerFactory dynamic

    simulation results for all case studies are attached in Appendix L.

    Case Study 1

    The effect of the dragline operation was performed on the existing Cloudbreak power system:

    the power system was unable to supply the required 28.6MW peak load. As seen in figure 2-4

    the dragline PCC voltage falls below 0.80pu at 16.086MW (dragline first power consumption

    peak), which, as a result fails, the testing criteria of acceptable voltage limits during dragline

    operation. As seen in Appendix K for case study 1, the Cloudbreak generators fail to supply the

    power system demand at 4 seconds, which, as a result, the synchronous frequency decays to

    zero and the power station voltage decreases to 0.20pu, which is unacceptable.

    Figure 4-4 Case Study 1 Dragline Voltage (p.u) vs. Real Power Consumption (MW)

    Case Study 2A

    As seen in Figure 2-5 the expanded Cloudbreak power station of 21 generators is unable to

    supply the required power to the dragline at an acceptable voltage. The dragline PCC voltage

    reaches 0.80pu at only 26.221MW, which again fails the testing criteria of acceptable voltage

    limits during dragline operation. As seen in Appendix K for case study 2A, the Cloudbreak

    generators exceed the 80% loading criteria by approximately 115% of test criteria and the

    synchronous frequency falls just below 0.98pu which is unacceptable. The results are outlined

    in Table 2-19.

  • 5/21/2018 Final Report

    39/96

    35

    Table 4-4 Dragline Dynamic Case Study 2A Results

    Minimum

    Fluctuation

    Maximum

    Fluctuation

    Test Criteria

    Limits

    Acceptability

    Power Station

    Voltage (p.u)

    0.61 1.08 0.95 1.05 Fail

    Power Station

    Frequency (p.u)

    0.978 1.016 0.98 1.02 Fail

    Power Station

    Loading (p.u)

    0.30 1.15

  • 5/21/2018 Final Report

    40/96

    36

    Table 4-6 Dragline Dynamic Case Study 2B Results

    Minimum

    Fluctuation

    Maximum

    Fluctuation

    Test Criteria

    Limits

    Acceptability

    Power Station

    Voltage (p.u)

    1.017 1.041 0.95 1.05 Pass

    Power Station

    Frequency (p.u)

    0.983 1.010 0.98 1.02 Pass

    Power Station

    Loading (p.u)

    0.33 0.76

  • 5/21/2018 Final Report

    41/96

    37

    Table 4-7 Dragline Dynamic Case Study 2C Results

    Minimum

    Fluctuation

    Maximum

    Fluctuation

    Test Criteria

    Limits

    Acceptability

    CB Power Station

    Voltage (p.u)

    1.022 1.039

    0.95 1.05

    Pass

    CC Power Station

    Voltage (p.u)

    1.030 1.037 Pass

    CB Power Station

    Frequency (p.u)

    0.990 1.005

    0.98 1.02

    Pass

    CC Power Station

    Frequency (p.u)

    0.990 1.005 Pass

    CB Power Station

    Loading (p.u)

    0.39 0.64

  • 5/21/2018 Final Report

    42/96

    38

    due to the relatively large distance between Christmas Creek and the PCC of the dragline. Also,

    case studies 3A and 3B are modelled to understand the best generator dispatch strategy

    between the two power stations in regards to voltage regulation and generator loading.

    Case Study 3A

    Case Study 3A was modelled using no loa