21/4/2014 1 FINAL presentation 21 st APR 2014 Team zora Tan Yun Xi Business Analyst Tan Mei Zhen Quality Analyst (Assistant PM) Fiona Woo Project Manager Lee Yi Xian System Analyst Lim Ken Khoon Lead Developer Darryl Leong Lead Designer

Upload: others

Post on 28-Sep-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

1

FINAL presentation 21st APR 2014

Team zora

Tan Yun Xi Business Analyst

Tan Mei Zhen Quality Analyst (Assistant PM)

Fiona Woo Project Manager

Lee Yi Xian System Analyst

Lim Ken Khoon Lead Developer

Darryl Leong Lead Designer

Page 2: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

2

overview

• About the Sponsor

• Project Overview

• Demo

• Project Management

• Stakeholder Management & Scope/Risk

• Quality Attributes (Design)

• Technical complexity

• User testing

• X – Factors

• Handover to Client

• Learning Outcomes

OUR CLIENT – sterling engineering

• Construction Industry

• Supply, fabrication and installation of structural steel works and metal works

• Small company, size of ~ 30 employees

Page 3: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

3

Problem highlights

• Manual

• Long and tedious process

• Time consuming and inefficient

Hard copy forms

Reimbursement Form

Payment Voucher

Page 4: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

4

Project description

• A web portal for all employees to access

• Aid HR personnel and higher management in their business activities

• System customised to company’s needs

Organization structure

Higher Management (HM)

System Administrator

Managing Director (MD)

HR Personnel (HR)

Page 5: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

5

june

modules

Training and Development

Remuneration And Claims

Leave Performance Management And Appraisal

System Administration

Remuneration june

Leave

Performance Management And Appraisal

System Administration

Claim entitlement

Claim

Employee’s salary Race, nationality CPF contribution

Allowance entitlement

Leave entitlement

Appraisal metrics

Value to sponsor: extensive scope

Page 6: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

6

Training and Development

june

Leave

Performance Management And Appraisal

Remuneration

Claim

Reimbursement with salary

Unpaid Leave

Check leave taken

VWS Bonus Salary Increment

View past appraisal scores

Value to sponsor: extensive scope

Deployment

Actual Server (Live)

Hosting Server Bluehost (Client - Web Hosting Server)

URL http://hrms.sterling-portal.com

Development Server

Hosting Server Bluehost (Client - Web Hosting Server)

URL http://hris.sterling-portal.com

User Testing Server

Hosting Server Bluehost (Client – Web Hosting Server

URL http://hruat.sterling-portal.com

Page 7: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

7

Demo

Employee Username System Role

leo Employee

noel Line Manager

angeline HR Personnel

LC Higher Management

spg Managing Director

marc System Administrator

Demo URL: http://hris.sterling-portal.com

Claim

1. Submit Claim

Submit Claim

3. Validate Claim

Employee (Leo) HR Personnel (Angeline)

2. Receive pending claim

email

4. Receive pending claim

email

Higher Management (LC)

5. Approve/Reject Claim

6. Receive pending claim

email

7. Approve/Reject Claim

Managing Director (SPG)

8. View Claim Status

Employee (Leo)

Page 8: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

8

Claim

Edit Payment Method

1. Edit Payment Method

HR Personnel (Angeline)

Leave

3. Receive pending leave email

1. Apply unpaid leave

4. Approve leave

Apply Unpaid Leave

Line Manager (Noel)

2. View & Edit leave

5. View approved & rejected leave

Employee (Leo)

Page 9: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

9

Remuneration

Generate payslip for employees & drivers

2. View Payslip 1. Generate payslip

HR Personnel (Angeline)

Generate worker costing

1. Generate worker costing

HR Personnel (Angeline)

Performance management & appraisal

Create Employee Appraisal

Higher Management (Noel)

1. Create Regular Appraisal

Page 10: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

10

Training & Development Propose a training

Line Manager (Noel)

1. Propose a training for a

employee

2. Receive pending proposed training

email

HR Personnel (Angeline)

Internal

3. Approve/Reject proposed training

Managing Director (SPG)

External

2. Receive notification of the

nomination

Employee (Leo)

5. Approve/Reject proposed training

6. Manage External Training

HR Personnel (Angeline)

4. View Nominated

Training

Training & Development

Manage External Training

1. Receive Approved training

email

HR Personnel (Angeline)

2. Fill the payment details

3. Set the training as completed

4. Fill in the course completion details

1. Fill up and submit the training

feedback

Employee (Leo)

Page 11: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

11

Training & Development Training Feedback

2. Review Feedback HR Personnel (Angeline)

1. Fill up and submit the training

feedback

Employee (Leo) Line Manager (Noel) 2. Review Feedback

View Training Record

HR Personnel (Angeline)

1. Select Employee 2. View Training

Details

Administration

1. Manage Remuneration

Manage Remuneration

HR Personnel (Angeline)

1. Manage Claim

Manage Claim

HR Personnel (Angeline)

Page 12: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

12

Administration

Claim Fraud Notification

1. Manage Claim Fraud

Manage Claim Fraud

2. Add Simulated Claim

Employee (Leo)

System Administrator (Marc)

1. Submit Fraudulent Claim

2. Receive email notification

3. Verify claim fraud

System Administrator (Marc)

SCOPE

Page 13: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

13

NO CHANGE

CHANGE

Iteration 12

Page 14: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

14

CHANGE

Change of features • New good-to-have feature: fraud detection • Enhance core & secondary features

PROJECT SCHEDULE (ACTUAL)

Page 15: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

15

Project schedule

70% Completion of Core Features • Remuneration

(Core) • Leave • Claim • Administration • ACL • User Testing 1 • Heuristic 1 • Acceptance

90% Completion of Core Features, 40% Completion of Secondary Features • Remuneration

(Core) • Leave • Claim • Administration • Performances

Management & Appraisal

• Training & Development

100% Completion of Core Features, 70% Completion of Secondary Features • Remuneration (Core) • Claims (Core) • Leave • Performances Management &

Appraisal • Training & Development • User Test 2 • Live Deployment

23 Sep – 8 Nov 9 May– 22 Sept 9 Dec– 5 Jan 6 Jan – 16 Feb

Gathering of Requirements & Preparation for subsequent Development phases

PROJECT SCHEDULE (PLANNED)

Iteration 9 (17 Feb ~ 2 Mar) • Claims Analysis Report

• Mid-Term Presentation

17 Mar– 27 Apr

Iteration 11 (17 Mar ~ 30 Mar) • User Test 3

Iteration 10 (3 Mar ~ 16 Mar) • Remuneration (Secondary) • Training & Development • Administration • Portal Notification (Other

features)

17 Feb – 16 Mar

Iteration 12 (31 Mar ~ 13 Apr) • Live Deployment 2 • Buffer • Final Presentation • Poster Day

Page 16: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

16

PROJECT SCHEDULE (ACTUAL)

Iteration 9 (17 Feb ~ 2 Mar) • Claims Analysis Report

• Mid-Term Presentation

17 Mar– 27 Apr

Iteration 11 (17 Mar ~ 30 Mar) • Fraud Detection (Algorithm &

Email notification)

• User Test 3 Iteration 10 (3 Mar ~ 16 Mar) • Remuneration (Secondary) • Training & Development

(Training session) • Administration • Research on Fraud Detection • Portal Notification (Other

features)

17 Feb – 16 Mar

Iteration 12 (31 Mar ~ 13 Apr) • Training & Development

(Completed) • Fraud Detection (Completed)

• Live Deployment 2 (14 Apr) • User Manual Guide • Buffer • Final Presentation • Poster Day

• Addition of new feature: Fraud detection

• Splitting of Training & Development: Create more buffer time to test before UT3

Milestone completed

Page 17: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

17

Schedule metric

Score Description Action

SM < 0.9

The team is ahead of planned schedule. There is a

substantial number of days when members are not

working on any task.

- PM to re-estimate and schedule lesser time for similar tasks in future

iterations.

0.9 <= SM <= 1.1 Estimations for planned

schedule are fairly accurate. The team is roughly on track.

- No readjustments on schedule needed.

SM > 1.1

The team is behind schedule. Deadlines are not met. PM

has underestimated the duration of most tasks in this

iteration.

- PM has to re-estimate tasks for future iterations.

- Incomplete task to be rescheduled to the next iteration and deduct the

number of buffer days at the end of the phase if required.

Schedule metric

Actual Number of Days / Estimated number of days

How it is measured

• Micro view Average score is calculated for each task.

• Macro View Score calculated using the start date and end date for both the estimated and actual number of days for the entire iteration.

Page 18: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

18

Iteration1

Iteration2

Iteration3

Iteration4

Iteration5

Iteration6

Iteration7

Iteration8

Iteration9

Iteration10

Iteration11

Iteration12

Micro 1.05 0.99 0.94 1.00 1.00 0.97 0.94 0.95 1.02 0.99 1.03 1.00

Macro 1.00 1.21 1.00 0.95 0.98 1.00 1.29 1.00 1.00 1.07 1.00 0.93

0.00

0.20

0.40

0.60

0.80

1.00

1.20

1.40

Iter

atio

n S

core

Iteration Score

Micro Macro

Schedule metric Reschedule incomplete

task

No readjustments needed

No readjustments needed

Schedule metric

Iteration1

Iteration2

Iteration3

Iteration4

Iteration5

Iteration6

Iteration7

Iteration8

Iteration9

Iteration10

Iteration11

Iteration12

Micro 1.05 0.99 0.94 1.00 1.00 0.97 0.94 0.95 1.02 0.99 1.03 1.00

Macro 1.00 1.21 1.00 0.95 0.98 1.00 1.29 1.00 1.00 1.07 1.00 0.93

0.00

0.20

0.40

0.60

0.80

1.00

1.20

1.40

Iter

atio

n S

core

Iteration Score

Micro Macro

Reasons behind delay 1. Apply Leave: • More complex than we thought: • Different way of handling different

leaves 2. Upload file for leave & claim: • High difficulty level for our team

Action taken 1. Shifted incomplete tasks to other

iterations 2. Review all future tasks and break it

down further to simpler tasks

Delay in Iteration 2

Reasons behind delay 1. User Test 2 in iteration 8: • Intensive test and deployment using

Task Instructions

Action taken 1. Allocate time to do intensive testing

with task instructions before user testing 3

Delay in Iteration 7

Page 19: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

19

Total Bug Severity Points = 1 x no (low) + 5 x no (medium) + 10 x no (high)

Bug Metric Severity Value

(points) Bug Description

Low Impact (1)

Typo error or basic user interface alignment issues. Application still works on a whole.

Medium Impact (5)

Some non-critical functionalities do not work as expected. Application still works on a whole

High Impact (10)

Entire application is down or is not usable after a short period of time. Team has to stop and fix bugs before continuing.

Bug Metric

End of the iteration

Points Action Required

points < = 15 Safe: Program does not require immediate attention. Bugs to be

solved during planned debugging time.

15 < points < 30 Caution: Program has issues that require fixing. Coders to use the

planned debugging time in the iteration to solve the issue.

points > = 30 Danger: Team to meet and review project scope. Stop all current

development and resolve the bug immediately.

Page 20: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

20

5

16

25

20

11 10

8

10 11 10

12 12

0

5

10

15

20

25

30

1 2 3 4 5 6 7 8 9 10 11 12

Total Bug Score Value in each Iteration B

ug

Sco

re V

alu

e

Iteration

Caution

Safe

Mid-Term Finals

Reasons behind increase in bugs • Lack of integration testing before

System testing on server.

Action taken • Implemented a more systematic

testing protocol

Number of bugs Increase in bugs in iteration 4

Functionality Testing Integration Testing System Testing

Systematic Testing Protocol

Page 21: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

21

Change management

Feature Description

How does it value add? Implementation period

Priority level (1 – Highest to 4 – Lowest)

Additional features in Leave: - Generate Leave Report

- HR can view the different leave of all employees at one go.

Iteration 11: Together with UT3

changes

3 (Discuss with sponsor to reduce additional change scope)

Update of change tracker

Edited Change on Access Rights: - Enable HR personnel to access to feature “View

Approved & Rejected Leave”

Change management

Feature Description

How does it value add? Implementation period

Priority level (1 – Highest to 4 – Lowest)

Additional features in Claim: - Claim summary report

- Allow HR to view the breakdown of claims (claim type/claim status) in a selected period of time

- 4 (Rejection of change)

Update of change tracker

Page 22: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

22

Risk management

Likelihood Low Medium High

Impact

High B A A

Medium C B A

Low C C B

Past Activated risk

Risk Statement Consequence Lvl Mitigation Strategy /Contingency Plan

Major Changes in Client Requirement

Overall project Schedule is Delayed.

A

• Re-plan coding tasks • Re-negotiate project scope with

sponsor. • Further changes to be documented by

business analyst • Activation of Change Management Plan

Inconsistent and missing real data to be incorporated into the system

Overall project schedule is being Delayed. System becomes buggy with new data.

A

• Assign a member to clean the data before live deployment

• Set aside time to do sufficient testing before live deployment

Users are not familiar with the application when it is fully deployed.

Functionalities of the system not utilized fully

A

• Ensure sponsor (Marc) has a clear idea of the use of functionalities

• Create a user guide • Hold a HRMS training session

Page 23: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

23

Meet their needs - Engage & consult on

interest area

Key player - Focus efforts on this group - Engage & consult regularly

Least Important - Inform via general communications

Show consideration - Potential supporter - Make use of interest to

improve project

Infl

uen

ce o

f sta

keh

old

ers

Interest of stakeholders

Stakeholder management priority metric

Meet their needs • Prof Benjamin Gan (IS480 Course coordinator) • Prof Jiang Lingxiao

(Reviewer 1) • Prof Alan Megargel

(Reviewer 2) • Fiona Lee (Instructor)

Key player • Mr. Marc Sim

(Client/Sponsor) • Ms. Angeline (Key user) • Prof David Lo (Supervisor) • Team Zora

Least Important NIL

Show consideration • Fellow course mates • Family & Friends

Infl

uen

ce o

f sta

keh

old

ers

Interest of stakeholders

Stakeholder management priority metric

Page 24: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

24

Key player stakeholders Stakeholder Name Mr. Marc Sim Ms. Angeline

Project Role Sponsor & Client Key Client

Needs – Key interests and issues

• Sterling Engineering HR System (HRMS) Vision and Objective

• Fulfilment of user needs on the system and requirements

• Fulfilment of user needs on the system and requirements

Communication Approach

• Manage closely Manage closely

Engagement • Have frequent meeting (at least once a month)

• Demonstration of progress on application

• Constant update of progress • Change management

• Have frequent meeting (at least once a month)

• Demonstration of progress on application

• Change management

Key player stakeholders Stakeholder Name Prof David Lo Team Zora

Project Role Supervisor Contributing team

Needs – Key interests and issues

• Team’s fulfilment of the objective of IS480

• Evaluate IS480 criteria • Learning outcomes

• Completion of IS480 project

• Work balance (with other modules)

• Appropriate allocation of time and type of tasks

Communication Approach

• Manage closely • Manage closely

Engagement • Have fortnightly meeting and emails (Tue)

• Demonstration & update on project progress

• Update of Wiki & Documents

• Have frequent weekly meeting (Mon)

• Open communication • Conflict management • Constant communication

via email and Whatsapp group

Page 25: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

25

QUALITY OF PROJECT: Design considerations

Twitter Bootstrap

• Error prevention • Help users recognize, diagnose, and recover

from errors

• User control and freedom

Nielsen's Heuristics

Colour Scheme

Typeface

Trebuchet MS

Arial

• Aesthetic and minimalist design

Nielsen's Heuristics

QUALITY OF PROJECT: Design considerations

Page 26: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

26

System Architecture

OVERALL ARCHITECTURE

• Application – Codeigniter Framework

– PHP 5.2.17

– Apache

• Browser – Javascript

• Jquery Library

• Jquery Validation

– HTML

– CSS

• Database – MySQL 5.1.66

– phpMyAdmin

Page 27: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

27

Controller View

MySQL

Model

Service DataAccess

Object

Object

Maintainability

Maintainability • Codeigniter Style guide

Page 28: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

28

QUALITY OF PROJECT: Security considerations

• Password salting and hashing

• Cross Site Scripting Validation

QUALITY OF PROJECT: Security considerations

• Dynamic Access control

Page 29: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

29

QUALITY OF PROJECT: INTEGRATION with other libraries

• TCPDF – Open source PHP library for PDF generation

• PHPass – Password hashing for PHP applications

TECHNICAL COMPLEXITY: INTEGRATION oF VARIOUS MODULES

• Need to ensure consistency among various modules – Technical documents to ensure consistency of database

Page 30: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

30

TECHNICAL COMPLEXITY: Managing live deployment data

• Inconsistency in structure of database tables – Major changes in database structure

– Identify and migrate changes

– Need to ensure current data is compatible with new structure

TECHNICAL COMPLEXITY: KNN algorithm

• User of k-nearest neighbor algorithm (kNN) to determine if a claim is fraudulent

New Claim

Fraudulent Claim

Non- Fraudulent claim

Page 31: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

31

TECHNICAL COMPLEXITY: KNN algorithm

• Classify the distance based on the following attributes with the different weights

– Claim Amount (30%)

– Income of claimer(30%)

– Claim Type (20%)

– Department of claimer (10%)

– Day of claim incurred (10%)

• Euclidean distance for numerical attributes

(𝑎 − 𝑏)2

• Distance normalized: 𝑛

𝑛 + 1

• Lazy Classifier

Test Plan

Update Results in

Test Cases

Update Bug Log

after resolving bugs

Create Test

Cases

Perform functionality

testing

Perform

integration testing

Fix all bugs

Perform

system testing

Update Bug

Metric

Record Bugs found in

Bug Log Fix all bugs

Update Results in

Test Cases

Fix all bugs

Regression Testing

Page 32: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

32

Test Cases

Login &

Logout (7)

Claim (95)

Leave (71)

Remuneration (42)

Performance &

Appraisal (45)

Training &

Development (75)

Administration (63)

Integration (35)

User Tests

1st 2nd 3rd

20 Oct 2013 25 Jan 2014 21~22 Mar 2014

COMPLETED COMPLETED COMPLETED

Page 33: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

33

Our Goal:

User Test (UT)\

Observe user activity and system load

Provide users with an early look and feel of

the system

Improve our system based on the feedback

gathered

Ensure developed functionalities are in

line with client’s requirements

Gather feedback from future users of the system so that we are able to:

UT1 participants

Marc (32)

Business Development

Manager

Ching Png (24)

Student

Pei Wen (26)

Accountant

Jasmine (50)

Administrator

Page 34: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

34

UT1 – Qualitative Analysis Positive Negative “Interface of the application is simple” “Mouse-over for the navigation bar is too

sensitive”

“Inconsistencies in the page header and the navigation bar tabs”

Navigation bar is not very nice and not

intuitive

UT1 - Qualitative Analysis Positive Negative “Interface of the application is simple” “Mouse-over for the navigation bar is too

sensitive”

“Inconsistencies in the page header and the navigation bar tabs”

Consistent wordings in page header and

navigation bar

Page 35: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

35

UT2 participants

Marc (32)

Business Development

Manager

Angeline (45)

HR Personnel

Fredinand (50)

Quantity Surveyor

Rhoylan (50)

Structural Draftsman

Elysee (26)

Contract Manager

UT2 - Qualitative Analysis Positive Negative “Interface of the application is simple with not too much of information in a page and easy to navigate”

“Some font size are quite small to see”

“Application is user-friendly with nothing too overwhelming”

“Links are not obvious enough”

Links not obvious

Fonts too small

Page 36: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

36

UT3 participants

Marc (32)

Business Development

Manager

Angeline (45)

HR Personnel

Fredinand (50)

Quantity Surveyor

Rhoylan (50)

Structural Draftsman

Elysee (26)

Contract Manager

Lady Ching (30)

Quantity Surveyor

Mikhael (28)

Design Engineer

Rupert (20)

Student Intern

Rashid (30) Work & Safety

Health Manager

UT2 VS UT3

UT2

UT3

0

1

2

3

4

Strongly

Disagree

Disagree Neutral Agree Strongly

Agree

System was Intuitive & easy to navigate

0

1

2

3

4

5

6

7

8

Strongly

Disagree

Disagree Neutral Agree Strongly

Agree

System was Intuitive & easy to navigate

3 2

2

7

0

1

2

3

4

Strongly

Disagree

Disagree Neutral Agree Strongly

Agree

Like the overall layout of the system

0

1

2

3

4

5

6

7

8

Strongly

Disagree

Disagree Neutral Agree Strongly

Agree

Like the overall layout of the system

1

2 2

1

8

Page 37: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

37

Based On The Same 5 Participants – Quantitative Analysis

0

50

100

150

200

Validate Submitted

Claim

Edit Payment Method Apply Other Leave

Average Timing Taken to Perform One Functionality

UT2

2m 35s

0

50

100

150

200

Validate Submitted

Claim

Edit Payment Method Apply Other Leave

Average Timing Taken to Perform One Functionality

1m 14s

3m 1s

UT3

1m 19s

35s

1m 45s

Most users are not able to locate the

“view” claim receipt link

Confirmation message was not displayed

Most users was unsure how to upload

2 files as no instruction was stated

Reasons for changes in timing: 1. Changes on the

application was useful

2. Live Deployment + Used the system before

UT3 – Quantitative Analysis

50

100

150

200

Approve/Reject Training by HR

Average Timing Taken to Perform One

Functionality

2m 50s

Of the 2m 50s, approximately 1 min was

used to accept the training.

This was resulted from the confusion of the button

Page 38: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

38

UT3 - Qualitative Analysis Positive Negative “Well-designed application. Easy to handle and user-friendly”

“Color scheme easy on the eye. Functions and rationale are clear cut and not complicated”

UT3 – Response Plan S/N Functionality Feedback Proposed Solution Proposed Decision

CLAIM

1 Submit Claim Tedious to record receipt numbers of the claim receipts by HR

Have an addition field "Receipt No." for employee to key in their own receipt number and HR will just validate instead of having to input it herself'

Implementing

2 Validate Claim Did not know need to update the edited amount before continuing to validate the claim

To include a "message" whenever the edit button is click to remind the user that update button must be hit before the changes can be made

Implementing

LEAVE

1 Record Leave Not obvious that employee's name is able to be selected by keying the alphabet

Enable filtering for user's to type employee's name

Implementing

2 Emailing for all leave Leave approval emails did not CC HR personnel CC HR personnel for all leave emails Implementing

TRAINING & DEVELOPMENT

1 Approve/Reject Proposed Training

UI Changes for select the training to be approve/reject - Accept / Reject button unclear, user was not sure she needs to click the button to proceed.

Change the name of the button Implementing

2 Manage External Training

Training Status Training Status from Completed change to Course Completed

Change from completed to Course Completed

Implementing

Page 39: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

39

UT3 – Response Plan S/N Functionality Feedback Reason for not implementing Proposed Decision

LEAVE

1 Record medical leave Did not check for duplicate medical series no. There is a possibility that 2 person can have the same medical series no. Hence, this will not be checked

Not Implementing

2 Validate Claim Did not know need to update the edited amount before continuing to validate the claim

To include a "message" whenever the edit button is click to remind the user that update button must be hit before the changes can be made

Not Implementing

REMUNERATION

1 Worker payslip Timesheet to include dinner breakdown (3h x 2) instead of giving the total ending sum

Dinner is allocated $3 for each dinner, if necessary. The payslip in the system is mirroring the current payslip they are using.

Not Implementing

2 Input worker timesheet

user tend to miss out the days but will notice when see days

The timesheet in the system is mirroring the current worker timesheet they used. Others may not be familiar but the HR personnel who is in charged of inputting the timesheet will be familiar if it is the same format as the one she is using.

Not Implementing

UT3 – Changes

Space for signature too small

Claim slip too small

Page 40: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

40

UT3 – Changes

Not obvious that the employee’s name is able to be

selected by keying the alphabet

UT3 – Changes

Accept/Reject button is misleading and caused confusion

Page 41: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

41

X FACTOR: fraudulent claim detection

• Automatically identify fraudulent claims via email • Reduce losses associated with fraudulent claims • Identify dishonest employees

X FACTOR: Highly configurable controls

Remuneration: • Dates to generate payslip (employee, driver

OT) • Default OT times • Minimum Wage

Page 42: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

42

X FACTOR: Highly configurable controls

Leave • Leave Entitlement

Claim: • Generated Date

X FACTOR: Highly configurable controls

Performance Management & Appraisal: • Appraisal Score /NWC Weightage • Increment Metrics

Page 43: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

43

june

Claims Leave System

Administration

Deployment URL : http:// hrms.sterling-portal.com

X FACTOR: Early Live deployment & usage tracking

41 Claims Submitted

15 Leave Applications

Usage

X FACTOR: Early Live deployment & usage tracking - Heat map

Live deployment 1 (19 Feb 2014)

Live deployment 1 update (31 Mar 2014)

Page 44: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

44

X FACTOR: Early Live deployment & usage tracking

Display Project names in alphabetical order

Allow user to past dates more efficiently

Remuneration Performance Management

& Appraisal

Training & Development

Deployment URL : http:// hrms.sterling-portal.com

Live deployment

Page 45: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

45

Value to sponsor: improving productivity

Time taken for specific function

Improvement in productivity (%) (UT2)

Improvement in productivity (%) (UT3)

Claim (submit, process, approve/reject)

73 90

Leave (Apply, edit/cancel, inform

department)

91 92

Remuneration (gather info, generate payslip)

92 92

System Administration (create, update profile)

52 83

Handover to client

• User guide for different user roles

• Conduct HRMS Workshop @ Kranji on 17 April

Page 46: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

46

Clients’ Feedback on HRMS Elysee: HRMS has indeed taken a streamlined approach for the claim process.

Roy: I have already applied 2 leave with HRMS. It is extremely convenient!

Generoso Jr. Baring: HRMS is faster, easier, non-manual and much more synchronised compared to our current way of doing things.

Ching: HRMS is effective, has fast access and easy to understand.

Ferdinand: HRMS is very good and helpful. Our work becomes easier. Now we can check our leave balance faster.

Goot Cheng: HRMS is indeed effective for applying leave and remuneration. It is also easy to use.

Learning outcomes

• Importance of documenting business requirement proposal properly

• Business requirement serves only as a guideline

• Be a trailblazer by researching on new technologies, weigh their cost and benefits in order to decide whether to implement them.

• More versatile as I become more receptive towards unexplored technologies.

• Understand the importance in seeking common consensus from my fellow group mates in whatever decision I have made.

• Maintaining the morale and camaraderie of the team is essential for the success of the team.

YUN XI

KEN

KHOON

FIONA

Page 47: FINAL presentation - wiki.smu.edu.sg€¦ · FINAL presentation 21st APR 2014 Team zora Tan Yun Xi Tan Mei Zhen Business Analyst Quality Analyst (Assistant PM) Fiona Woo Project Manager

21/4/2014

47

Learning outcomes

• Learn the important of having building a system with well-design backend.

• Striking a balance between ease of accessing the system information and data redundancy in database design.

• Testing is an essential procedure that should not be eliminated or avoided when developing an application

• Cannot fully understand the real needs of the user until they tried the system themselves

• Learnt that system UI design requires deep, intimate understanding of the client’s business processes and environment .

• Realize the usefulness of prototyping.

YI XIAN

MEI

ZHEN

DARRYL

Team Learning outcomes

Time Management

Change Management

Effective Communication

Stakeholder Management