Final MajorProject

Unit 4

Planning andProduction

Name: Freddie Goring

7/15/2019 Final Major Project Pre Production

http://slidepdf.com/reader/full/final-major-project-pre-production 2/12

 

Production Title:

Paolo Nutini Music Video – New Shoes

Submission of Production:

Monday 24th

June

Length of production:

My production will last 3 minutes 21 seconds (The same length as the song).

Crew names:

Freddie Goring

Dave Emery

Piers Cox

Actor’s names:

Oliver Mayer

Production roles for crew

Name Role

Freddie Goring

Dave Emery

Piers Cox

Director, Producer, Editor, Sound Op, Floor

Manager.

Camera Man

Lighting

7/15/2019 Final Major Project Pre Production

http://slidepdf.com/reader/full/final-major-project-pre-production 3/12

 

Deadlines

Crew responsibility Deadline for completion

Dave Emery - Camera Operator

Freddie Goring - Editing

18th

June

24th June

Agreed Content

The content of my production involves a male teenager wearing his new shoes. The musicvideo will start with him waking up in the morning in a glum mood. As he’s getting dressed

he decides to wear his new shoes for the first time. This instantly picks up his day and

brightens up the atmosphere of the video. During the video there will be frequent shots of 

the actor singing the song and playing a guitar.

Final Proposal / Detailed Outline of Production

I’ve chosen to create a music video as this is the area where my skills have developed andimproved the most over the last two years. I’ve had experience creating a music video and

have learnt lots of things whilst making it. Overall, the last music video I made was a

success; this gives the knowledge and confidence to do well during this production.

My music video will start in black and white whilst the main protagonist is waking up. His

day starts in a miserable and glum way until he’s getting dressed. He decides that it will be a

good day to wear his brand new shoes. He ventures under his bed and grabs a shoe box. The

next scene will be of him outside wearing his shoes and walking along the street. As the

camera focuses on his shoes the camera cross dissolves from the black and white effect to

colour. From then on, the camera will focus on the actor singing and playing the guitar

whilst walking down the street. The next day, the camera pans across him with his shoes

being worn in bed. He wakes up in a much more jolly fashion. Then the video will include

lots more shots of him singing with his guitar again. This continues until just before the end

of the video, where he puts his shoes back in the box, ready for another glum day.

The message of the video is that if you feel good within yourself, you are able to conquer

and trouble you may face throughout the day. This contrasts with the original song

meaning, relating to Paolo Nutini’s dark and terrifying heroin addiction.

7/15/2019 Final Major Project Pre Production

http://slidepdf.com/reader/full/final-major-project-pre-production 4/12

Team meetings, meetings with actors and crew

Date Location Attendees Discussion Topics

Friday 14th

June

Saturday 15th

June

Sunday 16th

June

Henley College

Shiplake

Henley

Dave Emery, Piers

Cox, Freddie Goring

Oliver Mayer,

Freddie Goring

Dave Emery, Piers

Cox, Oliver Mayer,

Freddie Goring

Making sure that the

equipment is

available for thechosen dates.

Going through the

style and dances he

needs to learn for

the video. Also, the

parts of the song to

learn on guitar.

An overview of the

whole production.

Including a talked

run through.

Equipment required

Equipment Date needed

Camera

Tri-pod

Premier pro

Editing Suite (Cloudy Lemonade Studio)

Monday 17th

June

Monday 17th

June

Thursday 21st

June

Wednesday 19th

June

7/15/2019 Final Major Project Pre Production

http://slidepdf.com/reader/full/final-major-project-pre-production 5/12

Locations used

Locations Date To film

Shiplake (House)

Shiplake (Various roads in the

village)

15th

June

15th

June

Footage of the morning

scenes. Dancing andplaying guitar in the house.

Dancing and Playing the

guitar.

Contingency / back up plans

A lot of the filming is outside. If there is bad weather (rain, snow etc.), I will film the scenes

at Shiplake train station. There is an overhead cover there that will keep the crew and

equipment dry, as well as keeping an outdoor effect.

7/15/2019 Final Major Project Pre Production

http://slidepdf.com/reader/full/final-major-project-pre-production 6/12

Risk Assessment

Programme title: Paolo Nutini Music Video  – New Shoes

Client: Vibe Productions

Writer : Freddie Goring

Producer : Freddie Goring

Director : Freddie Goring

Date: 06/05/2013

Major issues: No major issues. Minor slips and trips hazards. These includewires, cables, tripods, lighitng equipment.

Electricals being used outside.

Solutions: Incase of rain on an overcast day of filming, the equipment will becovered over to prevent them getting wet.

Contacts: Oliver Mayer  – 07*********

Dave Emery  – 07*********

Piers Cox  – 07*********

Emergency services:

Henley – On  – Thames Police Services - 0845 850 5505

Reading Fire Services - 0118 945 2888Townlands Hospital  – Henley – On  – Thames - 01491 637 400

RISK ASSESSMENT FORM 

7/15/2019 Final Major Project Pre Production

http://slidepdf.com/reader/full/final-major-project-pre-production 7/12

 

Production Management

Managing the pre-production roles

I took on all the pre-production roles; It was made very clear and in an organised fashion. All

the pre-production really helped in during the production stages, especially the storyboard.

It was drawn out clearly with detailed notes as to what the camera angle and movement

was necessary for each scene.

Managing the production phase

All the members of the cast and crew met at the location in Shiplake for the first day of 

filming. We had a 15 minute meeting where we discussed the plan for the day. All the

filming went swiftly without needing too many takes. Oliver (the actor) worked very

professionally for an amateur actor, which made filming much less stressful. Fortunately the

weather remained warm but not sunny. In the initial idea I wanted the sun to come to be

out for all the outdoor shots. However, I will be able to create this effect by changing the

contrast of the clip during the editing stages of the production.

Post production phase

Because of a really successful production stage, the process of editing the clips was made a

lot easier. However, before I could begin editing I needed to import the actual song. This

was the only problem that I came across during the editing process as the song wasn’t

compatible for Adobe Premiere Pro. This meant that a lot of time was lost as I had to record

the audio from the song on to an external source to create a new MP3 file. After all the

audio was sorted I was then able to begin editing the footage. The hardest part of making

the video was getting the lip syncing in time. This was the most time consuming part of theprocess, the colour contrast for the outdoor scenes only took a short while after the clips

had all been placed.

7/15/2019 Final Major Project Pre Production

http://slidepdf.com/reader/full/final-major-project-pre-production 8/12

Detail How You Solved Problems

For the first shoot, the camera ran out of battery which meant we had to put filming on hold

whilst the camera charged. Due to this we managed to miss some of the good weather

outside. However, time wasn’t completely wasted as we filmed some of the interior shots

whilst the camera charged. To resolve this I decided to charge all the cameras over nightbefore the next shoot.

Prioritising (How and what did you prioritise during your producing)

When filming, we prioritised the outdoor shots. This was so that we could get the best

natural lighting for the video. I also wanted to make sure I filmed all the scenes from the

bedroom at the same time. This was because the lighting from the window may have

changed over time giving the video an unnatural and unprofessional look.

Modifications (Why did you modify your work and what was changed during post-

production)

The only significant modification I made to the production during the editing stages was the

timing of the black and white effect turning to colour. The effect was originally going to

happen when the shoe box was opened. However, it didn’t fit in to the flow of the video and

looked a lot more natural when he began to walk in the shoes.

7/15/2019 Final Major Project Pre Production

http://slidepdf.com/reader/full/final-major-project-pre-production 9/12

 

7/15/2019 Final Major Project Pre Production

http://slidepdf.com/reader/full/final-major-project-pre-production 10/12

Additional information

7/15/2019 Final Major Project Pre Production

http://slidepdf.com/reader/full/final-major-project-pre-production 11/12

Shooting Script for Advert:

Int.Bedroom.Day

1. The Morning

Oliver wakes up in a daze. He looks around the room as hebegins to sing. He jumps out of the bed towards the

cupboard and opens it. He kneels down and throws clothes

behind his shoulder. After finishing his outfit with a

pair of tatty shoes he decides to pull out his new box of

shoes from under his bed.

Ext.Road.Day

2. The Day

He begins to walk down the street feeling better about

himself. As he walks through the street he is playing

guitar and singing.

Int.Bedroom.Day

3. The Next Day

Oliver is wearing his new shoes in bed as he wakes up the

next day. He gets out of bed with more of a spring this

time and heads to the kitchen.

When at the kitchen he continues to play the guitar and

sing.

He is then in the garden with his guitar showing off his

new shoes. After being in the garden he then heads back

out to the street to play the guitar and sing.

Int.Bedroom.Evening

4. The End

At the end of the day he puts his new shoes back in the

box and puts them back under the bed.

7/15/2019 Final Major Project Pre Production

http://slidepdf.com/reader/full/final-major-project-pre-production 12/12

Sound table: Sounds needed for my advert

Paolo Nutini – New Shoes (Song Track)

Prop Reason

Guitar For Oliver to play while miming the song

Shoes For filming

Shoe Box For filming (to be filmed)