Final FED Progress Report CMS Tracker Week 9th April 2003. FED FED-PMCs Status. Production of additional 40 FED-PMCs for Module Test setups. Identical to previous Mk3 cards. Some components on last time buy (Xilinx 4036 FPGAs.) PCBs are manufactured. Assembly is in progress. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

Final FED

Progress Report

CMS Tracker Week

9th April 2003

Page 2: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDFED-PMCs Status

•Production of additional 40 FED-PMCs for Module Test setups.

•Identical to previous Mk3 cards.

•Some components on last time buy (Xilinx 4036 FPGAs.)

•PCBs are manufactured.

•Assembly is in progress.

•Test and deliver in batches of 6-10.

•Expect to Start deliveries in June.

•Expect to Complete deliveries in July.

Page 3: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDFinal FED

“Primary” Side

2 PCBs assembled& now under test:

ser001 at Imperialser002 at RAL

“OptoRx”

CFlash

VME64x

34 xFPGAs

Analogue

TTC

9U FEDv1

FE Module

Power

Memories

96 channels

JTAG

Page 4: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDFE Module

• N.B. OptoRx is a mechanical sample & not soldered...• N.B. OptoRx is a mechanical sample & not soldered...

Front-End Module = 12 channels

DualADCs

OpAmps

DelayFPGAs

Duplicated onSecondary Side

“OptoRx”

“Primary” Side

TestConnector

Page 5: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FED Progress up to end Q1/03...

2 FEDv1 pcbs were assembled in January (without OptoRx).

Started with following preliminary tests done at RAL:

•Power sequencing.

•JTAG Boundary Scan (automated IC connection tests ; passed ok.)

•FPGA Configuration (>30 devices) from cable and System ACE Compact-Flash card.

•FE Module analogue Electrical tests using Electrical Cross-Point switch card.

(NB no VME readout yet, so data is captured in FPGA using Xilinx Chip-Scope embedded logic analysers read out via cable.)

•Digital tests with simple “Test Firmware” loaded in FPGAs.

Page 6: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FED Cross-Point Switch Electrical Test card

Cross Point Switch (AD8116) “plug on” test cardElectrical tests onlyMulti-channelNeeds external signal generator(s)Sits over OptoRx location (pre OptoRx assembly.)

16 x 16

12 Outputs

AD8116

ProgramFED TestConnector

3 Inputs

Page 7: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FED Early Electrical Data in FEDv1

0

200

400

600

800

1000

1200

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89

Series1

Series2

Series3

Series4

Series5

Series6

Series7

Series8

Series9

Series10

Series11

Series12

Chip-Scope logic analyser capture10 bit-raw data on 12 channels in FE FPGA

sine input (1 MHz) via Cross-Point Switch test card to 12 channels

first 100 (of 4k) samples @ 40 MHz

ADC count

preliminary

Page 8: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FED Progress up to end Q1/03...

2 OptoRx assembled on ser 001 in March

•Ser 001 now at Imperial for detailed characterisation studies of FED with Optical inputs (using Opto Test card Mk1).

•Ser 002 kept at RAL for Firmware development / Digital tests.

• Collaborative effort in UK between RAL and Imperial (with assistance from Brunel.)

Page 9: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FED Opto-Test card Mk1

VME interface logic

Analogue section

Sequence control logic

Sequence storage

DACAmplification+cmAnalogue opto-tx

Opto Test Card Mk1max 3 channelspattern generator(see 96 channel Mk2 card)

Page 10: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FED Opto Test Setup at Imperial

Page 11: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FED First Optical Data in FEDv1

Chip-Scope logic analyser capture10 bit-raw data

“APV frame” pattern on single channel

samples @ 40 MHz

0

200

400

600

800

1000

1200

1 29 57 85 113 141 169 197 225 253 281 309 337 365 393 421 449 477

Series1

Series2

Series3

Series4

Series5

Series6

Series7

Series8

Series9

Series10

Series11

Series12

ADC count

unsynchronised clocks

preliminary

Page 12: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FED Progress up to end Q1/03...

2 OptoRx assembled on ser 001 in March

•Ser 001 just arrived at Imperial for FED detailed characterisation studies with Optical inputs.

•Ser 002 kept at RAL for Digital function / Firmware tests.

• Collaborative effort in UK between RAL and Imperial (with assistance from Brunel.)

•FEDv1 Testing is progressing well…

No “show stoppers” yet for using FEDv1 pcb for Large Scale Assembly tests.

...but still a lot more to do.

Page 13: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FED Project Targets

•FED Project aiming to satisfy 2 targets in next 12 months:

I) FEDs for Large Scale Assembly (LSA) tests:

“July ‘03 (2?) / end ‘03 (2) / beg ‘04 (2) / mid ‘04 (6)”

96 chan Opto FED essential

only need to provide restricted FED functionality

assumes we can use existing design FEDv1 pcbs

II) FED Pre-Production Manufacture: Q1-2/04

to stay on final CMS installation schedule

need to demonstrate full FED functionality

assumes new design iteration FEDv2 pcbs

Page 14: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDLarge Scale Assembly Test Requirements 2003

Paraphrasing from note of Piero Verdini...

“To Readout Virgin Raw Data formatted as DAQ events via VME in response to TTC trigger and clock.”

Need 96 OptoRx chans. Trigger & Readout rates are not critical.

Functionality

Does require:

•Scope Mode and Software Triggers for set up.

•Controls from VME for run mode, clock source, clock skew, OptoRx offsets (with readback.)

•VME Event buffer with standard DAQ events. Counters for triggers & errors.

•System ACE loading, Clock/Trig/Resets on TTC Chan A, Hardware throttle output.

•FED delivered as a Package including Software Library to drive the Firmware.

Does not require:

S-LINK readout, Clustering mode, Spy Channel, TTC chan B, TCS (but maybe simple throttle), DAC control, pedestal/threshold data, System ACE interface, VME64x config EPROM…, VME Interrupts, Temp chip control…

Page 15: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDPre-Production FEDv2

Does require :

S-LINK readout, Clustering mode, Spy Channel, TTC chan B, TCS (but maybe simple throttle), DAC control, pedestal/threshold data, System ACE control and in situ-programming, VME64x config EPROM…, VME Interrupts, Temp chip control…

Tested with up to 20 FEDs in a crate.

All operating at target Trigger Rate of 100 kHz!

… FEDv1 has been designed for this.

•Assumption: have to demonstrate full functionality before pre-production FEDv2 (Q1-2/2004.)

Page 16: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

CMS Tracker FED Schedule

•FED x 450 installation at CERN expected to start Q3 2005

Design TestProduction& InstallationPre-Pro

FEDv3 (500)FEDv2 (20)FEDv1 (20)

Page 17: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDFirmware

Status:

Ready to start installing Final Designs on FED...

Delay FPGA: Final version synthesised and under test.

FE FPGA: Final version synthesised and “ready” for test.

BE FPGA: Data path up to QDR filling synthesised and ready for test. TTC chan A interface implemented. Read path to VME in progress incl DAQ formatting.

VME FPGA: External VME cycles tested. Serial comms to BE close to test. To do... parallel link to BE incl. readout interface.

Steps towards providing Module Test functionality...

Page 18: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FED FPGAs

Delay x 24 FE x 8

BE x 1

VME x 1

Page 19: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

Clocks

Data

FEDv1 Firmware Subtasks

SerialComms

VMELINK

VMEBus

VMESystemSystemACEACE

SystemACE

Clocks

EPROMEPROM

EPROM

TTCrxQDR Write

QDRs

QDR Read

SerialComms

Headers

TTCchanA

VME LinkRegs

S-LINKS-LINK S-LINK

Clocks

Data

SerialComms

ScopeMode

HeaderMode

FIFOs

Input

Regs

SerialComms

ScopeMode

HeaderMode

Output

Input

Regs

Opto Rx DACOpto Rx DAC

DELAY FPGA x 3 x 8

FE FPGA x 8

BE FPGA

VME FPGA

ADCADC

Simulated

Tested on FED

Not needed tilll FEDv2Not needed tilll FEDv2

Control

Data

Control

Throttle TriggerInput

ClusterClusterModeMode

EdEd

SaeedSaeed

Bill / IvanBill / Ivan

EdEd

Ed, John, MattEd, John, Matt

Saeed, Ivan, EmlynSaeed, Ivan, EmlynChan BChan B

I2CI2C

Temp

Implementation in progress

ExternalDevices

Page 20: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDFirmware Tasks in Q2/03

• Load Final Delay FPGA design. Test DDR to FE FPGA using ChipScope.

• Test Serial Comms and Readback: From VME -> BE -> FE -> Delay FPGA

Tests OptoRx controls, ADC clock skew. Requires software.

VME end nearly ready. BE take receiver block from FE design. Provide simple register map and test with software. (Later extend to other controls eg to test clock skewing.) NB Uses Final design of FE, Delay and VME. Test design in BE.

• Load Final FE FPGA design. Test DDR inputs, Scope Mode and FIFO outputs.

• Meanwhile Test Final BE design writing to QDR. Inputs from FE FPGA in Scope Mode.

• Extend BE to test QDR readout to VME.

• Add Event/Header formatting for readout.

• Test parallel link from BE to VME and readout protocol. Readout via CPU.

Page 21: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDFirmware Tasks in Q2/03

•Test Readout interface to CPU, poll on VME buffer with register for event length. Software needed.

•Use TTC to provide ext clock and trigger. Mostly implemented. But need TTC VME cards to do this test. Need clock and trigger select logic.

•Test Final FE Virgin Raw data mode (header finding.) Need APV frame generator (OptoTest Card?) Add synch clock and trigger inputs (TTC or backplane?). Need clock and trigger select logic.

•Add Control registers & Counters for nr triggers, (resets), errors…. In BE read by VME.

Page 22: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDDelivery Schedule ‘03

• We have 18 OptoRx in hand. Lots more coming in June?

• We have 4 extra pcbs in hand. We have necessary components in hand.

• Put 8 OptoRx on ser001 in May.

• Put 2 OptoRx on ser002 in May.

• Assemble another 4 PCBs without OptoRx in May.

• We are on schedule to deliver 1 FED (ser001) for LSA Tests by beginning of September.

• Delivery of 2nd FED (ser002) Q4 2003?

• Then further FEDv1’s according to schedule provided... “end ‘03 (2) / beg ‘04 (2) / mid ‘04 (6)”

• Availability of LHC crates in UK. (May?)

• Other Critical tests for FEDv2 Q3-4…

E.g. S-LINK “direct” tests with FED Kit.

Page 23: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDLarge Scale Assembly Setup Assumptions

Assumptions:

• Use 9U VME64x crates (LHC crates available for UK tests in May.)

• Clock and Trigger arrives on standard TTC Opto cable (on TTC chanA.)

• Sync/Bx counters Reset by ‘101’ on chanA.

• Hardware Throttle signal level on back-plane pin?

Comments:

• Caution should be exercised when using a FED that may not be fully characterised to make detailed measurements of other electronics systems.

• Basic FED training to be provided (in UK).

• Need well defined points of contact between LSA Testers and UK.

• Other FED related projects are being undertaken in UK.

Page 24: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDOther Projects in UK…

DACs

Fibre reels

8-way MU optical connectors

Clk & Control

Analogue Optical Hybrids (AOHs)

Cross-point switches

A 96 channel optical driver to test the FED has been designed at Imperial and is now in layout.

It is consists of four 9U VME cards running in parallel, each with 8 AOHs driving 24 optical fibres.

The 24 analogue inputs to the opto hybrids are fed from an analogue cross-point switch. The latter allows an AOH to receive a signal from any one of the three digital to analogue converters or an external source.

A temperature of the AOHs is maintained to ~0.2 °C to keep the laser output stable.

Page 25: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDv1 FEDv1 Provisional Memory Map

Reserved

Restrictions in 2003:

•A32 Slave only

•D32 access only.

•Single Access and Block Transfers (no BT to C&S regs)

•No Interrupts

Control & Status

Serial Commands

Test Memory

Serial Read Back

VME Buffer

Reserved

Reserved

Block RAMs

Read Only ID

8 x 8 KB blocks

Using a “poor man’s” Geographic Addressing scheme...Base Address: Bits 21-16 = Slot numberE.g. $0011’0000 - 0011’ffff for slot 17(Nb Doesn’t use VME64x CSR space.)

Offset

0000

2000

4000

6000

8000

A000

C000

E000

Currently FEDv1 has 64 KB in A32 address space

Page 26: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDTest Software

Software:

Up to now only peek & poke program to VME from Linux.

Good enough for really basic firmware tests.

But need to integrate FED software into the XDAQ system.

And we would like some easy (GUI driven) to use compatible test software.

Need FED Application Programming Interface API. A list of software functions FED responds to.

API to shield users from Basic low level code needed to...

1. Serial string commands to load and read back FE/Delay FPGA registers as described by Bill.

Still to add similar commands for BE FPGA registers.

2. Readout routine.

Need register map/list.

Page 27: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDv1 Event Readout Protocol

DAQ Trailer

FormattedFED Data

DAQ Header

Tracker Header

Readout (via VME) Formatted Events identical to those sent to S-LINK

•Load Parameters e.g. Peds, Clock skews

•Set run mode

•Select clock and trigger source

•Start Run and enable Triggers/Frames

•Poll on VME buffer status

•Get length of event

•Readout the event (in FPGA buffer sized chunks)

(Raw events > FPGA buffer size)

•Reset VME buffer status

•Repeat until Run stop

•Periodically look at local status registers and counters to check everything is OK

Event Formats:

Virgin Raw Data. Raw APV frames.

*Scope Mode or Software Trigger

Both are fixed event sizes within a Run.

(*Empty Tracker Header.)

Page 28: Final FED Progress Report CMS Tracker Week 9th April 2003

9th April 2003Tracker WeekJohn Coughlan et. al. FED-UK Group

FEDTest Equipment

• Cross-Point cards available for electrical inputs. Most useful in Scope modes.

• Second Opto Test card Mk1 for RAL (after Easter). Most convenient for APV patterns. Needed for Raw Data (header finding) readout tests with FE FPGA.

• Have TTC VME cards in hand at IC and RAL.

• FED Kits for S-LINK in hand at IC and RAL.

• New PC/VME Interface (SBS optical link card) by Easter?

• Standard LHC VME64x Crates in UK by May.

• Large number of OptoRx in UK by June.