final fall senior design presentation

47
BRAYS BAYOU + BRIDGE Fall 2015 Concept Presentation Presented by: Julianne Crawford, Avi Gori, Kasia Nikiel

Upload: julianne-crawford

Post on 19-Mar-2017

224 views

Category:

Engineering


1 download

TRANSCRIPT

Page 1: Final fall senior design presentation

BRAYS BAYOU + BRIDGEFall 2015 Concept Presentation

Presented by:

Julianne Crawford, Avi Gori, Kasia Nikiel

Page 2: Final fall senior design presentation

Project Description + Goals

➔ Design Brays Bayou channel modifications

➔ Reconstruct of Greenbriar Bridge between Braeswood & Main

➔ Consider of additional stormwater flow from 7200 Main

➔ Coordinate with 7200 Main development for other features

➔ Protect Meyerland area from future flooding

Page 3: Final fall senior design presentation

Brays Bayou between Fannin St. and Greenbriar St.

Page 4: Final fall senior design presentation

Greenbriar Bridge

Page 5: Final fall senior design presentation

Background Research + Modeling

Page 6: Final fall senior design presentation

Project Brays➔ Funded by US Army Corps and HCFCD➔ Comprehensive re-design of Brays Bayou

◆ Channel Modifications◆ Bridge Replacement/Renovation◆ New Detention Area

➔ Aimed at mitigating riverine flooding throughout Brays Bayou Watershed ➔ Status:

◆ Upper Reach: Completed◆ Middle Reach: In Progress◆ Lower Reach: In Progress

➔ Scheduled to be completed in 2021

Page 7: Final fall senior design presentation

Project Brays Proposed Improvements

Page 8: Final fall senior design presentation

100-year Floodplain (TSARP Model - 2004)

Page 9: Final fall senior design presentation

100-year Floodplain (Current Conditions - 2010)

Page 10: Final fall senior design presentation

100-year Floodplain (Post Project Brays - 2021)

Page 11: Final fall senior design presentation

100-year Floodplain (TSARP) at Site Location

Page 12: Final fall senior design presentation

100-year Floodplain (Post Project Brays) at Site Location

Page 13: Final fall senior design presentation

Bridge - Current Conditions

Page 14: Final fall senior design presentation

Concept Design

Page 15: Final fall senior design presentation

OPTION 1: Widen the Channel

Page 16: Final fall senior design presentation

HEC-RAS Geometry for Greenbriar Section

Main Street

Greenbriar Street

Fannin Street

Page 17: Final fall senior design presentation

Cross Section Comparison - Downstream (RS 56478)

Current 100-yr Level (44.07 ft)

PPB 100-yr Level (43.47 ft)

PPB Geometry

Current Geometry

Page 18: Final fall senior design presentation

OPTION 1: Widen the Channel -- BRIDGE

Page 19: Final fall senior design presentation

OPTION 2: Retaining Wall

Page 20: Final fall senior design presentation

HEC-RAS Geometry for Greenbriar Section

Main Street

Greenbriar Street

Fannin Street

Page 21: Final fall senior design presentation

Cross Section Comparison - Upstream (RS 59882)

Current 100-yr Level (45.70 ft)

PPB 100-yr Level (44.96 ft)

PPB Geometry

Current Geometry

Page 22: Final fall senior design presentation

OPTION 2: Retaining Walls -- BRIDGE

Page 23: Final fall senior design presentation

Existing Plan View of Bridge Deck

Page 24: Final fall senior design presentation

87.0’

Bridge Tie-Ins With Existing Roads

87.0’

5% Grade 4.35’

Page 25: Final fall senior design presentation

Proposal

Page 26: Final fall senior design presentation

Modified Scenario

➔ Retaining walls and some

widening on both banks

from Main to Greenbriar

➔ Retaining walls and

substantial widening on the

right bank from Greenbriar

to Fannin

Page 27: Final fall senior design presentation

Modified HEC-RAS Geometry Examples (Upstream - RS 58740 )

Modified Geometry

PPB Geometry

Page 28: Final fall senior design presentation

Modified HEC-RAS Geometry Examples (Downstream - RS 57958)

Modified Geometry

PPB Geometry

Page 29: Final fall senior design presentation

Modified Scenario Results - RS 59882

Modified Geometry

PPB Geometry

Modified 100-yr LevelPPB 100-yr Level

44.71 ft 44.96 ft

Page 30: Final fall senior design presentation

Modified Scenario Results - RS 56478

Modified Geometry

PPB Geometry

Modified 100-yr LevelPPB 100-yr Level

43.47 ft 43.37 ft

Page 31: Final fall senior design presentation

Proposed Bridge Cross-Section

Page 32: Final fall senior design presentation

Proposed Plan View of Widened Bridge Deck

Page 33: Final fall senior design presentation

Impact of Proposed Modifications

➔ Modifications along the Main to Fannin portion of the channel should not have

drastic adverse effects on downstream sections.

➔ According to the 100-year floodplains, both current and post project brays, the

areas downstream of our site already face a much lower inundation hazard

than the middle and upper reaches.

Page 34: Final fall senior design presentation

Moving Forward

Page 35: Final fall senior design presentation

Brays Bayou

➔ Finalize channel modifications for Main to Fannin segment

➔ Add additional cross sections to existing HEC-RAS geometry

➔ Perform unsteady state HEC-RAS analysis

➔ Incorporate additional flow from hotel if necessary

Page 36: Final fall senior design presentation

Proposed HEC-RAS Geometry Modification

Page 37: Final fall senior design presentation

Bridge

➔ Finalize aesthetic design with 7200 Main St. group

➔ Determine appropriate foundations

➔ Superstructure/Substructure design of the bridge

Page 38: Final fall senior design presentation

Meyerland

Page 39: Final fall senior design presentation

May 2015 Storm - Comparison of Flooding to Current 100-year Floodplain

Page 40: Final fall senior design presentation

May 2015 Storm - Damage Reports in Meyerland

Page 41: Final fall senior design presentation

100-year Floodplain (Post Project Brays) at Meyerland

Page 42: Final fall senior design presentation
Page 43: Final fall senior design presentation

Appendix

Page 44: Final fall senior design presentation

Channel Profile

Fannin Greenbriar Main

Direction of Flow

Page 45: Final fall senior design presentation

Construction

Page 46: Final fall senior design presentation

Green Space

➔ Finalize design for green space with hotel

➔ Ensure that all trails are integrated smoothly

Page 47: Final fall senior design presentation

Meyerland 100-yr Floodplain - Current Conditions v. Post Project Brays