Pro ect Pro osal for EPCIC NPro ect Pro osal for EPCIC N--WHP,WHP,
Associated Pipelines and ReceivingAssociated Pipelines and Receiving
--
Presented by Abraham Imam MuttaqinStudent ID : 115151
-
7/25/2019 Final Exam 81.9020_AIM
2/23
Presentation Outlines :Presentation Outlines :
Key Milestone
Work Breakdown Structure
Project Schedule
Project Cash Flow Analysis
Conclusion and Way Forward
-
7/25/2019 Final Exam 81.9020_AIM
3/23
Project Name : Pad-Thai Field
Development Field Location : 100 NM, east of
,
Water Depth : 60 meter
Type of Contract : Lumpsum
-
7/25/2019 Final Exam 81.9020_AIM
4/23
Key locations which related to project execution activities.
-
7/25/2019 Final Exam 81.9020_AIM
5/23
, ,
Construction (C), Transportation & Installation (I) and
Hook-u & Commissionin C for Nick Wellhead
Platform (N-WHP)
1) 600 MT Topsides with 16 Slots Conductor
2) 700 MT Four-Legged Jacket
3) 1000 MT Piles and Conductors
Subsea Pipelines : 20 dia x 15 km Long
Tie-in to existin facilities E-WHP : new i launcher,deck extension and tie-in.
Primary Steel, Crane and Coated 20 Pipeline will be
supplied by Client
-
7/25/2019 Final Exam 81.9020_AIM
6/23
Schematic Interface between N-WHP and Existing E-WHP
-
7/25/2019 Final Exam 81.9020_AIM
7/23
-
Drillin on N-WHP : 1 Se t 30 Oct 2014
HUC Com letion : 30 Nov 2014
Total Project Duration : 14 Months
-
7/25/2019 Final Exam 81.9020_AIM
8/23
14 months which is safe, efficient and effective.
Meet or exceed Company expectations in
terms of HSE, technical content, quality andschedule.
Foster and maintain a ood workinrelationship with the Company throughout the
ro ect.
-
7/25/2019 Final Exam 81.9020_AIM
9/23
Pro ect Execution PlanPro ect Execution Plan Mobilize key-personel within one week after contract
Set-up Interface Process System among the disciplines (E,
P, C, I and C)
Review FEED deliverables and within 2-3 month
Engineering Team should issue AFC deliverables
Strong Procurement Team to be set-up at very beginningof the project phase to manage critical long lead items and
-
Fabrication Schedule
-
Transportation and Installation will be sub-contracted
- -
Seek financial funding in month 12 of project execution
-
7/25/2019 Final Exam 81.9020_AIM
10/23
.
2. Detailed Engineering (Process, Structure,
3. Procurement (Contractor Supplied and Client
Su lied
4. Fabrication (Jacket, Piles & Conductors and Topsides)
5. Trans ortation Pi eline acket and Pile & Conductor
Topsides)
6. Installlation, Hook U & Commissionin Pi eline,Jacket, Piles and Conductors, Topsides and Tie-in to
Receiving Facilities E-WHP)
-
7/25/2019 Final Exam 81.9020_AIM
11/23
Pro ect Or anization ChartPro ect Or anization Chart ProjectManager
Interface
Manager
ProjectControland
Risk
QAManager ProjectEngineer
HSEManager
Engineering
Manager
Procurement
Manager
Fabrication
Manager
T&IManager HUCManager
Structure
Mechanical/Piping
Structure
Mechanical/Piping
Fieldengineer
MarineCoordinator
Buyer
Procurement
Hookup Eng
CommisiongEng
Electrical/Instrument Electrical/Instrument
Safety
-
7/25/2019 Final Exam 81.9020_AIM
12/23
Project ScheduleProject ScheduleDuration
Year 2013 Year 2014
m m m m m m m m m w w w w w w w w w w w w w w w w w w w w m m m m m1 Contract Award 1d
2 Detailed Engineering
Stuctural 6m
Mechanical/Process 6m
Electrical 6m
(month)
Instrumentation 6m
3 Procurement
Client Supplied
Primary Steel 3m
Crane 6m
Coated line pipes & bends 10m
Contractor Suppli ed
Low grade steel 1m
CS piping material 2m
Duplex piping 6m
Valves, SP items 6m*
Vessels, Pump, Tanks 6m
Safety equipment 3m
E/I and Telecom equipment 6m*
an e ecom u s ma er a m
4 Fabrication
Topsides incl. deck extension/pig receiver 7mTesting and pre-commissioning for Topsides 1m
Jacket 6m
Testing for jacket 1w
Piles/Conductors 3m
N-WHP sail awa y
5 Transportation and Installation
Transportation
Pipeline
Jacket
TopsidesPiles/Conductors
Deck Ex tension and pig receiver
Installation
Pipeline
Jacket
Topsides
Piles/Conductors
Installation Completion
6 Hook-up and Commissioning
Install Deck extension @ E-WHP
Install Pig receiver @ E-WHPTie-in to existing E-WHP and commissioning
HUC Comple tion
7 Drilling Campaign on N-WHP
Early FacilityReadiness
-
7/25/2019 Final Exam 81.9020_AIM
13/23
Project Cost EstimationProject Cost EstimationUnit Price Lump Sum
(USD/unit) PRICE (USD)
1Project Management (Management,
Insurances, Services To Company, etc.)17 months 90,000 1,530,000
2 Engineering Lumpsum 2,000,000
3 Procurement
Structural Material 1 LS 600,000 600,000
Piping Material 1 LS 2,600,000 2,600,000
Mechanical Material 1 LS 1,700,000 1,700,000
E&I and Telecom. Material 1 LS 1,400,000 1,400,000
Procurement Services (Expedite/TPI/FAT) 1 LS 315,000
, ,
4 Fabrication
Topside 137,500 MH 20 2,750,000
Jacket & Appurtenances 56,000 MH 20 1,120,000
Piles & Conductor 20,000 MH 20 400,000
LoadOut & Seafastening 1 LS 300,000 300,000PMT,
4%Enginee
rin 6%
HUC,
7%, , na ocumen a on ,
4,670,000
5 Transportation & Instal la tion
Mob/Demob
- DP Vessel 1 time - 6,200,000
Operations
Procure
ment,
19%
T and I,
49%
- DP Vessel 31.5 Days 300,000 9,450,000
Barge & Tug
- Platform (2 nos) 49 Days 18,000 882,000
- Pipelines 15 Days 18,000 270,000
Crew Boat 14 Days 10,000 140,000
Fabricat
ion, 14%
16,942,000
6 Hook-Up and Commissioning
Flowlines Installation and Well HUC 1 LS
Header Fab and Installation 1 LS
Fab and Install Deck Extension 1 LS 2,500,000
Tie-in and Commissioning to E-WHP 1 LS
2,500,000GRAND TOTAL (BASE) 34,257,000
GRAND TOTAL (BIDDING PRICE) 41,108,400
-
7/25/2019 Final Exam 81.9020_AIM
14/23
Project Monthly Performance CostProject Monthly Performance Cost
Cost
(x1000 USD) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1 Project Management 1836 131 131 131 131 131 131 131 131 131 131 131 131 131 131
2 Engineering 2400 400 400 400 400 400 400
Project Activity DescriptionNo Month
3 Procurement (Material)
Low grade steel 756 756
CS piping material 756 378 378
Duplex piping 1008 168 168 168 168 168 168
Valves, SP items 1512 252 252 252 252 252 252
Vessels Pum Tanks 1890 315 315 315 315 315 315
Safety equipment 252 84 84 84
E/I and Telecom equipment 1386 231 231 231 231 231 231
E/I and Telecom bulks material 378 94.5 94.5 94.5 94.5
4 Fabrication 5244 583 583 583 583 583 583 583 583 583
5 Transportation and Installation 20330 6777 6777 6777
6 Hook-up and Commissioning (HUC) 3000 3000
Project's monthly progress cost 41108 531 531 1497 3392 2636 2258 1774 1680 714 714 714 7851 6908 9908
ro ec cumu a ve mon y progress cos
Notes :
1) Projects monthly performance cost will be the basis forClient payment
2) Monthly equal cost basis is assumed
-
7/25/2019 Final Exam 81.9020_AIM
15/23
Project Cash Flow ForecastingProject Cash Flow Forecasting
Project Cost
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1 Cash inflow (incl 20% profit) 531 531 1497 3392 2636 2258 1774 1680 714 714 714 7851 6908 9908
Project's Monthly CashflowNo Cashflow Forecasting - EPCI Project
- -
(based on project's monthly progress)
2 Cash outflow (incl profit)
a) Project Management -131 -131 -131 -131 -131 -131 -131 -131 -131 -131 -131 -131 -131 -131
b) Engineering -400 -400 -400 -400 -400 -400
c) Material
-
CS piping material 756 -756
Duplex piping 1008 -1008
Valves, SP items 1512 -454 -605 -454
Vessels, Pump, Tanks 1890 -567 -756 -567
Safety equipment 252 -252
or er, on s te,
30% commissioning
One month after
Pre-Comm
- . - -
E/I and Telecom bulks material 378 -76 -189 -113
d) Fabrication -583 -583 -583 -583 -583 -583 -583 -583 -583
Loadout and seafastening 360 -360
e Trans ortation and Installation
20% order, 50% on site,
30% commissioning
DP Vessel 18780 -9390 -9390
Boat, barge, vessel and tug service 1550 -1550
f) HUC 3000 -3000
Monthl Cash Inflow in x1000 USD
50% mob/demob, 50%
installation complete
One month credit
from Vessel Owner
Monthly Cash Outflow (in x1000 USD) -531 -1829 -1363 -1870 -1366 -1303 -3776 -714 -714 -2264 -10104 -10104 -2042 -3131
Net Project Cashflow (in x1000 USD) 0 -1298 134 1523 1271 956 -2001 966 0 -1550 -9390 -2253 4866 6777
-
7/25/2019 Final Exam 81.9020_AIM
16/23
Project Cash Flow ProfileProject Cash Flow Profile
8000
4866
4000
6000
0 134
15231271
956 966
00
2000
-1298
-2001-1550
-2253-2000
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
-6000
-4000
-9390-10000
-8000
-12000
Ordinate axis : in thousand USD
-
7/25/2019 Final Exam 81.9020_AIM
17/23
1) Integrity and condition of existing facilities (E-
WHP)
2) Sub-standard FEED deliverables from Client3) Inadequate integration between OTM Ltd and
Sub-Contractors
e ay n comp e on o e vera es ostart fabrication) and Long Lead items (material
of Client Supplied Material (i.e primary steel)
5 Limited resources for man ower and sub-contractors
6) Lack of cash in month 12 during projectexecution
-
7/25/2019 Final Exam 81.9020_AIM
18/23
EPCIC project based on following proposal :
1) Proposed project execution plan or method statement
3) Proposed Project Schedule
, ,
5) Twenty (20) percent profit margin
project cash flow analysis
-
7/25/2019 Final Exam 81.9020_AIM
19/23
Thank YouThank You
-
7/25/2019 Final Exam 81.9020_AIM
20/23
Backu SlidesBacku Slides
-
7/25/2019 Final Exam 81.9020_AIM
21/23
Procurement CostProcurement Cost
en oren or vsvs en oren orItem Description Price Leadtime Term
Month(s)
1 Low
grade
steel 600,000 1 CIFFabYard
2 CSPipingmaterials 600,000 2 CIF
Fab
Yard
3 Duplex
Piping 800,000 6 CIF
Fab
Yard , ,
5 E&I
and
Telecom
bulks
materials 300,000 4 CIFFabYard
6 Vessels,Pumps,Tanks 1,500,000 6 CIF
Fab
Yard
7 Valves,
SP
Items 1,000,000 8 CIFFabYard
8 SafetyEquipment 200,000 3 CIF
Fab
Yard
Total 6,000,000
Item Description Price Leadtime Term CIF Fab
Mont s yar r ce
1 Lowgradesteel 700,000 1 CIF
Fab
Yard
2 CS
Piping
materials 700,000 2 CIFFabYard
3 DuplexPiping 1,000,000 6 CIFFabYard
, ,6 ExWork 1,100,000
5 E&IandTelecombulksmaterials 300,000 4 CIF
Fab
Yard
6 Vessels,
Pumps,
Tanks
1,500,000 6 CIFFabYard
7 Valves,SPItems 1,000,0006 ExWork 1,200,000
8 SafetyEquipment 200,000 3 CIF
Fab
Yard
Total 6,400,000
-
7/25/2019 Final Exam 81.9020_AIM
22/23
Fabrication CostFabrication Cost
MT MH/MT MH USD/MH USD
ops e ee , , ,
Mech/Piping 150 300 45,000 20 900,000
E/I 100 400 40,000 20 800,000
, , ,
Piles/Conductors 1,000 20 20,000 20 400,000
2,300 213,500 4,270,000
-
7/25/2019 Final Exam 81.9020_AIM
23/23
T and I CostT and I Cost
Derrick
Lay
Barge
(DLB)Unit Price (USD) Day USD Remark
Opt1:8pointmooring,comeswith2AHTs,noSATsystem
5MMUSDLumpSummob/demob(onto/fromSite) 5,000,000
250,000USD/dayDayRate 250,000
PipelayRate:1km/day 15 3,750,000
JacketInstallation7days 7 1,750,000
Pile/ConductorInstallation7days 7 1,750,000
TopsidesInstallation3days 3 750,000
PostinstalledRiserInstallation4days 4 1,000,000
PipelineHydrotest
2days 2 500,000
DLBs eed3knots 38 14,500,000
Opt2:DPVessel,withSATsystem
6.2MMUSDLumpSummob/demob(onto/fromSite) 6,200,000
300,000USD/dayDayRate 300,000
PipelayRate:2km/day 7.5 2,250,000
JacketInstallation6days 6.0 1,800,000
e on u c or ns a a on ays . , ,
TopsidesInstallation2days 2.0 600,000
Postinstalled
Riser
Installation
3days 3.0 900,000
SubseaTiein2dayseachend 4.0 1,200,000
PipelineHydrotest2days 2.0 600,000
DPspeed3knots 32 15,650,000 Selected
DiverSupportVessel(DSV)DP2,withROVandSATsystem
2MMUSDLumpSummob/demob(onto/fromSite) 2,000,000
150,000USD/dayDayRate 150,000
SubseaTiein4daysbothends 4 600,000
Pipeline
Hydrotest
2
days 2 300,000, ,
Barge&TugareonlyavailableinJurong,Singapore
BareBargeTowSpeed5knots 18,000 15 270,000
BargewithfullloadTowSpeed3knots 30 540,000
Dayrateat18,000USD/day 19 342,000
1,152,000
Barge for pipeline
Barge for jacket & piles
Barge for topsides and deck
extension
CrewBoat&SupplyBoatareonlyavailable inSingapore -
Dayrateat10,000USD/day Supply boat 10,000 14 140,000
AverageSpeed
10
knots
16,942,000Total Installati on Cost in USD =