final awv stakeholder group 3-16-15 · • three survey teams are collecting and analyzing data:...
TRANSCRIPT
![Page 1: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/1.jpg)
OrganizationDateAWV Stakeholder Group March 16, 2015
![Page 2: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/2.jpg)
General Updates
![Page 3: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/3.jpg)
Alaskan Way Viaduct Replacement Program Update
Placeholder for noise wall graphic
![Page 4: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/4.jpg)
Envisioning the NORTH PORTAL
![Page 5: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/5.jpg)
Building the NORTH PORTAL
North portal work zone in February 2015
![Page 6: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/6.jpg)
Feb. 26, 2015
Building connections between existing SR 99 lanes to the future surface Aurora
Avenue North, September 2014
Building the NORTH PORTAL
![Page 7: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/7.jpg)
Tunneling machine receiving pit, Dec. 2, 2014
Tunneling machine receiving pit, Feb. 26, 2015
Building the NORTH PORTAL
![Page 8: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/8.jpg)
Building the SOUTH PORTAL
The south portal work zone in February 2014
![Page 9: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/9.jpg)
Building the SOUTH PORTAL
South portal construction, Feb. 18, 2015
![Page 10: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/10.jpg)
Breaking through the cut‐and‐cover tunnel,
Feb. 3, 2015
Building the SOUTH PORTAL
![Page 11: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/11.jpg)
BUILDING THE HIGHWAYinside the tunnel
Southbound roadway construction, March 13, 2015
![Page 12: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/12.jpg)
Settlement
MONITORING
Jack Main
![Page 13: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/13.jpg)
South Jackson Street and First Avenue South(Secondary surface survey control point– JACK)
Settlement
MONITORING
• All readings shown are based on STP survey data.
• The blue points represent the net change in elevation detected at a single reading as compared to original baseline elevation.
• Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey control points require revised elevations to be established using the regional survey control network.
Settlemen
t (in)
‐1.164
‐1.164
‐1.176
‐1.236
‐1.176
‐1.152
‐1.140 ‐1.164
‐1.224
‐1.176
‐1.236
‐1.176
‐1.212
‐1.224
‐1.224
‐1.080
‐1.140
‐1.164
‐1.152 ‐1.140
‐1.140
‐1.164
‐1.128 ‐1.164
‐1.068(2/21)
‐1.50
‐1.25
‐1.00
‐0.75
‐0.50
‐0.25
0.00
20‐Nov 27‐Nov 4‐Dec 11‐Dec 18‐Dec 25‐Dec 1‐Jan 8‐Jan 15‐Jan 22‐Jan 29‐Jan 5‐Feb 12‐Feb 19‐Feb 26‐Feb
Survey Accuracy
![Page 14: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/14.jpg)
South Main Street and First Avenue South(Secondary Surface Survey Control Point – MAIN)
Settlement
MONITORING
• All readings shown are based on STP survey data.
• The blue points represent the net change in elevation detected at a single reading as compared to original baseline elevation.
• Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey control points require revised elevations to be established using the regional survey control network.
Settlemen
t (in)
‐1.044
‐1.080
‐1.152 ‐1.116
‐1.152
‐1.032
‐1.056
‐1.056
‐1.104
‐1.104
‐1.140
‐1.092
‐1.104
‐1.092
‐1.104
‐0.948‐0.996
‐0.984
‐1.008
‐0.984
‐0.996
‐0.996‐0.996
‐0.984
‐0.996
‐0.996
‐0.972
‐0.972(2/21)
‐1.50
‐1.25
‐1.00
‐0.75
‐0.50
‐0.25
0.00
20‐Nov 27‐Nov 4‐Dec 11‐Dec 18‐Dec 25‐Dec 1‐Jan 8‐Jan 15‐Jan 22‐Jan 29‐Jan 5‐Feb 12‐Feb 19‐Feb 26‐Feb
Survey Accuracy
![Page 15: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/15.jpg)
Repairing
BERTHAConceptual
![Page 16: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/16.jpg)
Access pit scoringFeb. 19, 2015
Repairing
BERTHA
![Page 17: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/17.jpg)
BERTHAreaches daylight
Bertha’s breakthrough, Feb. 19, 2015
![Page 18: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/18.jpg)
BERTHAreaches daylight
Bertha’s breakthrough,March 4, 2015
![Page 19: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/19.jpg)
Repairing BERTHAModular lift tower, Jan. 20, 2015
![Page 20: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/20.jpg)
Repairing
BERTHA
Building a better Bertha
![Page 21: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/21.jpg)
ELLIOTT BAY SEAWALL PROJECT
Alaskan Way Viaduct Stakeholder Group
March 16, 2015
![Page 22: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/22.jpg)
SCHEDULE PROGRESS
![Page 23: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/23.jpg)
TODAY’S AGENDA
1. Season 1 complete
2. Season 2 continues
3. Season 2.5 begun
4. Next steps
![Page 24: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/24.jpg)
SEASON 1SOUTH OF COLMAN DOCK
COMPLETE!
![Page 25: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/25.jpg)
SEASON 1: SOUTH OF COLMAN DOCKCOMPLETE
![Page 26: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/26.jpg)
SEAWALL ASSEMBLY COMPLETESOUTH OF COLMAN DOCK
Utilities
Jet grout
Back shoring wall
Cast in place slab
Mass excavation
Drilled shafts
Face panel
“Zee” panel
Habitat bench
Light PenetratingSurface
Sidewalk
Sheet pile
![Page 27: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/27.jpg)
LIGHT PENETRATING SURFACE / SIDEWALK INSTALLATION
![Page 28: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/28.jpg)
COMPLETED SEAWALL
![Page 29: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/29.jpg)
COMPLETED SEAWALL
![Page 30: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/30.jpg)
COMPLETED SEAWALL
![Page 31: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/31.jpg)
COMPLETED SEAWALL
![Page 32: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/32.jpg)
SEASON 2 UPDATEPIKE TO MADISON STREETS
![Page 33: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/33.jpg)
SEASON 2: PIKE TO MADISON STREETS
![Page 34: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/34.jpg)
SEAWALL ASSEMBLY PROGRESSPIKE TO MADISON STREETS
TemporaryUtilities
Jet grout
Back shoring wall
Cast in place slab
Mass excavationFace panel
Light PenetratingSurface
Sidewalk
Habitat bench
Drilled shafts
“Zee” panel
Sheet pile
![Page 35: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/35.jpg)
MASS EXCAVATION AND DEMOLITION
![Page 36: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/36.jpg)
JET GROUT
![Page 37: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/37.jpg)
FACE PANEL INSTALLATION
![Page 38: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/38.jpg)
MARINE MATTRESS INSTALLATION
![Page 39: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/39.jpg)
ZEE PANEL INSTALLATION
![Page 40: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/40.jpg)
SEASON 2.5 UPDATEMADISON STREET TO YESLER WAY
![Page 41: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/41.jpg)
SEASON 2.5: MADISON STREET TO YESLER WAY
![Page 42: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/42.jpg)
SIDEWALK REMOVAL
![Page 43: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/43.jpg)
SHEET PILE INSTALLATION
![Page 44: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/44.jpg)
MAINTAINING ACCESS TO AND FROM COLMAN DOCK
![Page 45: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/45.jpg)
– Continue installing pre‐cast elements near Waterfront Park
NEXT STEPS
![Page 46: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/46.jpg)
QUESTIONS?
Email: [email protected]
Website: waterfrontseattle.org/seawall
24‐hour hotline: 206‐618‐8584
![Page 47: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/47.jpg)
AWV Stakeholder Group MeetingEric TweitMarch 16, 2015
Mercer Corridor Project: West PhaseProject update
![Page 48: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/48.jpg)
Existing conditions (Vehicle)
![Page 49: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/49.jpg)
Recent work• Traffic shifted from temporary roadway on Mercer St.• North sidewalk on Mercer St. open• Sidewalk improvements along 5th Ave. N• Retaining wall installation on south side of Mercer St. • Bicycle pathway on Mercer St. and 5th Ave. N
![Page 50: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/50.jpg)
Recent work
![Page 51: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/51.jpg)
Upcoming construction
51
March• 5th Ave. N & Thomas St. – sidewalks and crosswalks• Mercer St. – sidewalk repairs in front of McCaw Hall• Mercer St. – continue sidewalk and retaining wall, south sideApril - May• Roy St. and Dexter Ave. N intersection – full closure for paving activities (late April)• Dexter Ave. N - sidewalks and pavement• Dexter Ave. N – remove shoefly• 5th Ave N & Thomas St. - Signal and driveway Later this year• Roy St. – storm water detention between 4th Ave. N and 5th Ave. N
![Page 52: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/52.jpg)
Project description• Connects I-5 & South Lake Union to Seattle Center, Queen Anne
& Interbay• Connects NW Seattle neighborhoods to the SR 99 Tunnel• Improves pedestrian and bicycle connections
![Page 53: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/53.jpg)
Questions?
[email protected] | (206) 419-5818http://www.seattle.gov/Transportation/mercercorridor.htm
![Page 54: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/54.jpg)
Thanks for joining us tonight!
http://www.seattle.gov/transportation
![Page 55: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/55.jpg)
Placeholder for noise wall graphic
ADAPTIVE SIGNAL CONTROL PROGRAM
![Page 56: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/56.jpg)
Placeholder for noise wall graphic
Mercer Street Eastbound AM
![Page 57: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/57.jpg)
Placeholder for noise wall graphic
Mercer Street Westbound AM
![Page 58: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/58.jpg)
Placeholder for noise wall graphic
Mercer Street Eastbound PM
![Page 59: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/59.jpg)
Placeholder for noise wall graphic
Mercer Street Westbound PM
![Page 60: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/60.jpg)
Placeholder for noise wall graphic
![Page 61: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/61.jpg)
WATERFRONT SEATTLEMarch 16, 2015
![Page 62: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/62.jpg)
![Page 63: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/63.jpg)
WATERFRONT PROGRAM UPDATE
63
• Cost estimates increased in 2014• Additions to program, including:
Seawall mitigation: historic, archeological, tribes, business
Pike/Pine corridor improvements into downtown
Light penetrating surfaces on promenade
Washington Street Boat Landing restoration
![Page 64: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/64.jpg)
MAYOR’S PROPOSED BUDGET
• Keep Waterfront Program at $1.07B, consistent with 2012 Strategic Plan
Preserve the overall vision
Modify program elements to fit within the budget
Phase expenditures to reflect SR 99 Tunnel completion schedule changes, and minimize near‐term spending
Continue to leverage public and private funding sources (LID, philanthropy, etc.)
![Page 65: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/65.jpg)
APPROACH TO PROGRAM GOING FORWARD
• Maintain quality first and foremost
• Prioritize the main corridor elements:
Waterfront Pedestrian Promenade
Alaskan Way and Elliott Way
Strong east/west connections, including Overlook Walk
Waterfront Park rebuild
• Phase over time to “grow into” the new waterfront
![Page 66: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/66.jpg)
PHASING APPROACH
![Page 67: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/67.jpg)
PROJECT SCHEDULE
![Page 68: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/68.jpg)
BUDGET AND FUNDING
![Page 69: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/69.jpg)
LOCAL IMPROVEMENT DISTRICT (LID)
![Page 70: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/70.jpg)
70
P i k e P l a c e M a r k e t F r o n t
![Page 71: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/71.jpg)
PIKE PLACE MARKETFRONT
• Close coordination with Office of the Waterfront
• More than 30,000 sq. ft. of public pathways, open space
• New connection via future Overlook Walk, retail core and waterfront
• Parking garage to provide ~300 new parking stalls
![Page 72: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/72.jpg)
OPERATIONS AND MAINTENANCE PLANGOAL: Create a safe, well‐maintained and actively programmed public place
MAINTENANCE • Cleaning• Gardening • Repairs (regular and major)
PROGRAMMING• Daily and special events• Arts/cultural• Concessions
SECURITY• Staff – enforcement and
ambassadors• Technology to
manage/close spaces
![Page 73: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/73.jpg)
![Page 74: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/74.jpg)
Stakeholder Group Feedback
![Page 75: Final AWV stakeholder group 3-16-15 · • Three survey teams are collecting and analyzing data: WSDOT, STP and the City of Seattle. These teams have determined that select survey](https://reader034.vdocuments.us/reader034/viewer/2022042314/5f0285677e708231d404acc1/html5/thumbnails/75.jpg)
How to REACH US