filming schedule & editing schedule 4 d productions

6

Click here to load reader

Upload: jamsjamsjams

Post on 16-May-2015

702 views

Category:

Art & Photos


2 download

TRANSCRIPT

Page 1: Filming Schedule & Editing Schedule   4 D Productions

Filming Schedule

Filming Schedule Date

Planning the days to film 16/12/09

Film first scene – (Subway, Anchor scenes for beginning of song plus the first verse)

17/12/09 The first scene of our actor

entering the subway and setting up will be shot with two cameras and 4 different shots.

A point of view shot A shot in the mirror Close up Long shot. The filming will begin at

10am The scenes should be

filmed by 1pm.Film anchor scene for end of song (last verse and actor leaving subway)

18/12/09 The scene of the actor

leaving will also be shot with two different cameras and from the 4 shots used for the beginning of the song. This will ensure a similar beginning and ending

The filming will begin at 1pm

Chorus scene in subway 18/12/09 Filming will start at 3.30pm

after a break from finishing the above scene. The chorus will be filmed with a:

Close up of actor singing and playing guitar

A mid shot and from two angles. One from the left and one from the right.

Scene in Kingsway Bar & Restaurant

1. Actor getting congratulated2. Actor drinking at the table

19/12/09 Filming will begin at 11am. All scenes will be shot from

two angles with 2 cameras. One camera filming the actor and one camera

Page 2: Filming Schedule & Editing Schedule   4 D Productions

filming the location. Both scenes will be shot

from a high angle and low angle with the camera positioned on the left and the right.

Other shots to be included.. Long shot Zoom in to bottle Extreme close up Establishing shot, allows

the audience to see that the location is a bar

Scene In office of actor getting sacked

19/12/09 All filming to start 1pm

because of the lighting in mid-day. (good lighting)

Over the shoulder shot from both actor’s perspective.

Street scenes1. Walking towards tree2. Walking after tree3. Drinking scene on park

bench (tramp scene)

20/12/09 All filming need to be

completed before 4pm due to lighting outside.

Filming will be begin at 9:30am

Shots will include – Point of view Over the shoulder of actor.

Close up of actor. Mid-shot of actor Both walking scenes to be

shot from the same position.

Page 3: Filming Schedule & Editing Schedule   4 D Productions

Editing Schedule

Editing Schedule Date

Planning the days to edit. 27/12/09

Upload and Select final scenes

28/12/09 All group members begin

at 2pm at Malkit’s house. All scenes will be uploaded

onto computer. Import all scenes into

adobe premier pro 2.0. All scenes to be finalised by

4pm Put all scenes into a timeline 28/12/09

All scenes into a timeline to see the length of our footage.

Change order 29/12/09 Order of scenes need to be

altered in order to suit the song.

Putting all scenes into timeline and ordering into correct order should be completed by 5:30

Check all scenes are into groups of different scenes in the timeline. A group for street scenes, anchor scenes, Kingsway scenes and office scenes.

28/12/09 6pm all scenes will checked

into groupings and should be completed by 6:30pm.

Import song29/12/09

Editing will begin at 1pm at Malkit’s house.

The song will be imported to see if the length of our footage is too long, short or just right.

Page 4: Filming Schedule & Editing Schedule   4 D Productions

Check lip synchronisation 29/12/09 Ensure all lip sync of

scenes and lyrics match. This should be competed by 3pm leaving us to check all transitions and editing techniques that we can use.

View all editing techniques and transitions

29/12/09 From 3pm onwards, all

transitions and editing styles will be viewed. Any that that group decide on will be written down in a list to add the next day. All transitions should be viewed by 7pm,, including all video and audio effects

Insert all transitions 30/12/09 Group meet up at Malkit’s

at 11am All transitions and effects

chosen from the day before will be finalised as a group and inserted.

All other video and audio effects will be inserted.

Insert credits 02/01/10 Choose fonts and style. Add credits to the

beginning and end of song. View and get opinions on

colour, style, font and positioning of credits by all members of group

Finalise credits.Show Teacher and make alterations

07/01/10 Show our teacher our

video, get opinions and make any alterations.

We added Sepia tone to some scenes and added split screen after talking to our teacher because of the affect it would create to the beginning and end of our music video.

Upload final video to Facebook, YouTube and burn

12/01/10

Page 5: Filming Schedule & Editing Schedule   4 D Productions

onto a CD.