fieldbus foundation – india marketing committee fieldbus ... · pdf filedavid brown...
TRANSCRIPT
1© 2009 Fieldbus Foundation
2009 FFIEUC-Mumbai Conference
AuthorDavid BrownBechtel Corporation CAT Engineering Specialist
AuthorDavid BrownBechtel Corporation CAT Engineering Specialist
Fieldbus Foundation – India Marketing Committee
Fieldbus FoundationEnd Users Council Conference-2009
On Site Support of the Reliance JERP Project
2
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic –
Segment Design
Assigning Devices to Segments
Physical Layer
Segment Pre-Commissioning
Team Cooperation
Lessons Learned
3
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Segment Design Based on Loop Severity
Implementation of Fieldbus into the project was based on FF AG181 rev 2.0 guideline for valve Criticality from the beginning of the project. During the design some units relaxed the use of criticality 1 & 2 on new loops. After installation started loops that were changed or added used the loop severity approach.
The Segment Design Risk Assessment is an operability review process performed prior to FOUNDATION™ fieldbus (FF) Segment design.
The purpose of the design review is to evaluate the impact of FF associated failures to determine segment design(s) that minimize process risks.
4
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Segment Design Based on Loop Severity
A process severity ranking is determined for control loops leading to segment design recommendations made in relation to risk ranking and good engineering design practices.
The design intent for control loops with higher risk is to minimize the number and type of devices on a segment, reducing the process risk, to facilitate ease of isolating control loops with high process severity ranking during troubleshooting and maintenance, and increasing reliability.
The analysis may also identify control loops that should not be FOUNDATION™ fieldbus due to loop control criteria.
5
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Assigning Devices to Segments
The FF AG181 guideline was used to start with and based on this and experiences from the design team the segments are laid out based on the following guidelines.
Spur lengths set to 90 meters with a maximum of 120 meters
Total segment less than 1900 meters
The Interim Junction Boxes located to minimize the number of Home Run Trunk cables from the field to the PIB’s
The Barrier Junction Boxes located to meet the spur length
Critical devices on the same segment within the wiring limits
For some segments used two barrier JB’s to maintain the loop integrity
This required detailed drawings that showed device locations
6
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Physical Layer
Physical Layer Connectivity Equipment Used on the Reliance Project
With the size of the plant being a logistic issue along with the different environmental areas the Hybrid Segment, High Powered Trunk, concept was utilized.
Allows for Intrinsic Safety circuits to be located in the field
Uses standard FF Barriers for Intrinsic Safety function
Utilizes standard FF power supplies for up to three FF barrier interfaces per segment.
Allows for longer segment distances
7
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Hybrid High Power Segment
8
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Hybrid High Power Segment
9© 2009 Fieldbus Foundation
2009 FFIEUC-Mumbai Conference
Fieldbus Foundation – India Marketing Committee
Fieldbus FoundationEnd Users Council Conference-2009
Pre-Commissioning and Validation of FF Segments Improves Start-Up
10
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Project Issues
With FOUNDATION™ Fieldbus systems getting larger, more devices and segments, some of the common project issues become scheduling nightmares.
– Segment check-out such as the right device in the right place.
– Segment validation of the physical hardware and signals.– At present it can take up to 15-20 minutes per device to
commission on each segment using the standard DCS.
11
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Solution
New schemes are being developed to shorten the Commissioning and Validation process.One such scheme is being used on a couple of Mega projects.
12
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Solution
The scheme uses the following equipment along with data from the INtools data base.The use of devices such as the 375 Field Communicator used as the LAS and read/write of the following information.
– TAG Name– Device Address– Checking on DD and software revisions
14
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Solution
FBT- 6 FOUNDATION™ Fieldbus physical layer tester
15
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – SolutionScopemeter for checking signal quality and measure resistance and capacitance on the segment
16
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Solution
FOUNDATION™ Fieldbus power supply for powering the portion of the segment being tested Line to 24 vdc power supplyCoupler block for connecting up the devices to the segment being tested
18
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Solution
Basic Segment Testing LayoutTrunk
Spurs Spurs
19
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Solution
Field Junction Box with CouplerField Junction Box with Coupler
20
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Solution
Five pair Trunk cable in instrument cabinet
Single pair for testing
21
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Solution
Interim Junction BoxInterim Junction Box
22
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Solution
Field Barrier Junction Box
Barrier Isolation
Trunk Input Terminals
23
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Solution
Field Barrier Junction BoxField Barrier Junction Box
Field Device Spurs
Field Device Spurs
BarriersBarriers
24
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Data Collection
Data collection Process:With a Fluke Scopemeter or a DVM check for shorts
Signal to signalSignal to shield
Power up the segment with test FF supplyConnect the 375 and power up and select Foundation Fieldbus operation
Allow 375 to be LASCheck Livelist for devices and address
Once Livelist is established connect the FBT - 6 and validate segment physical operation and store data.
25
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Data Collection
After the FBT – 6 data has been stored use the 375 to complete the data review and update.If the address for the devices are located in the parking area you will need to change each device to the listed address in INtools and then check the TAG along with the revisions.After all the data has been checked and recorded along with the devices updated you have completed the Validation and Pre-Commission.
30
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Team Cooperation
The worlds largest FF project has presented several challenges.
During construction with the wiring and installation
Start-up with finding compatibility issues with different devices
Issues during normal operation requiring upgrades
Through all of the challenges Team work has been the prime reason for the plant being were it is today. Everyone from Reliance, EPC’s such as Bechtel and others along with the Vendors like Invensys have worked together to identify the root cause and fix the Issues.
31
2009 FFIEUC-Mumbai Conference
© 2009 Fieldbus Foundation
Fieldbus Foundation Topic – Lessons Learned
Lessons Learned from the project:Training is the key to success during
construction and start-up
Communications between all parties is a must to meet the schedules and find resolutions to issues
Device interoperability must be known before installation of devices. Any new device that does not have a minimum of one year run time needs very detailed testing before accepting.