field sampling plan - records collections · field personnel to perform the planne field workd a....

141
Sraperfnamdl Records Coiteir EPA Contract No. 68-W9-0036 EPA Work Assignment No. 04-1LA4 EPA Project Officer: Nancy Barmakian EPA Remedial Project Manager: Roger Duwart FIELD SAMPLING PLAN for Remedial Investigation/Feasibility Study Activities Holton Circle Site Londonderry, New Hampshire OCTOBER 1990 Prepared by: METCALF & EDDY, INC. M&E Project Manager: Nicholas D'Agostino kVHE Metcalf&Eddy

Upload: others

Post on 08-Oct-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

  • Sraperfnamdl Records Coiteir

    EPA Contract No. 68-W9-0036

    EPA Work Assignment No. 04-1LA4

    EPA Project Officer: Nancy Barmakian

    EPA Remedial Project Manager: Roger Duwart

    FIELD SAMPLING PLAN

    for Remedial Investigation/Feasibility Study

    Activities

    Holton Circle Site

    Londonderry, New Hampshire

    OCTOBER 1990

    Prepared by:

    METCALF & EDDY, INC.

    M&E Project Manager: Nicholas D'Agostino

    kVHE

    Metcalf&Eddy

  • FIELD SAMPLING PLAN

    TABLE OF CONTENTS

    Section

    LIST OF FIGURES

    LIST OF TABLES

    1.0 INTRODUCTION

    2.0 PROJECT DESCRIPTION

    2.1 SITE LOCATION AND DESCRIPTION

    2.2 SITE BACKGROUND

    2.3 SAMPLING SCHEDULE

    3.0 SAMPLING OBJECTIVES

    4.0 SAMPLING LOCATION AND FREQUENCY

    4.1 SAMPLING LOCATIONS

    4.2 SAMPLING FREQUENCY

    4.2.1 Unconsolidated Materials Sampling

    4.2.2 Test Pit Sampling

    4.2.3 Groundwater Sampling

    4.2.4 Surface Water and Sediment Sampling

    5.0 RECONNAISSANCE

    5.1 WETLANDS RECONNAISSANCE

    5.2 GEOLOGICAL RECONNAISSANCE

    6.0 SURFACE GEOPHYSICAL SURVEY

    6.1 TOWN GARAGE

    6.2 DELINEATION OF FRACTURE ZONES

    7.0 PIEZOMETER, UNCONSOLIDATED MATERIALS BORINGS AND

    MONITORING WELL INSTALLATION

    7.1 INTRODUCTION

    7.2 PIEZOMETERS

    7.3 UNCONSOLIDATED MATERIAL BORINGS

  • TABLE OF CONTENTS (Continued)

    Section Page

    7.4 TEST PITS 7-4

    7.5 OVERBURDEN MONITORING WELLS INSTALLATION 7-4

    7.6 BEDROCK MONITORING WELL INSTALLATION 7-7

    7.7 MONITORING WELL DEVELOPMENT 7-10

    7.8 SOIL CLEANUP 7-11

    7.9 SURVEYING 7-11

    8.0 SAMPLING PROCEDURES 8-1

    8.1 UNCONSOLIDATED MATERIALS SAMPLING METHODS 8-1

    8.1.1 Surface Unconsolidated Materials Sampling 8-1

    8.1.2 Sediment Sampling 8-2

    8.1.3 Borehole Unconsolidated Materials Sampling 8-3

    8.1.4 Test Pit Sampling 8-5

    8.2 WATER SAMPLING METHODS 8-7

    8.2.1 Groundwater Monitoring Well Sampling 8-7

    8.2.2 Waterloo Multilevel Well Sampling 8-12

    8.2.3 Surface Water Sampling 8-15

    8.3 QUALITY CONTROL SAMPLES 8-17

    8.3.1 Trip Blanks 8-17

    8.3.2 Equipment Blanks 8-17

    8.3.3 Field Duplicates 8-18

    9.0 HYDROGEOLOGIC INVESTIGATIONS 9-1

    9.1 SLUG TESTS 9-1

    9.2 SURFACE WATER MEASUREMENTS 9-1

    10.0 DECONTAMINATION PROCEDURES 10-1

    10.1 EQUIPMENT 10-1

    10.1.1 Non-Sampling Field Equipment 10-1

    10.1.2 Sampling Equipment 10-2

    10.1.3 Ice Chests and Shipping Containers 10-6

    10.1.4 Vehicles 10-6

    i i

  • TABLE OF CONTENTS (Continued)

    Section Page

    10.2 QUALITY CONTROL PROCEDURES 10-7

    10.3 DOCUMENTATION 10-8

    11.0 SAMPLE HANDLING FOR ANALYSIS 11-1

    11.1 SAMPLE PRESERVATION 11-1

    11.2 SAMPLE CUSTODY 11-1

    11.2.1 Chain of Custody 11-4

    11.2.2 Sample Packaging and Shipping 11-12

    11.3 DOCUMENTATION 11-14

    11.3.1 Sample Designation/Identification 11-16

    11.3.2 Corrections to Documentation 11-16

    11.3.3 Photographs 11-17

    11.3.4 Records 11-17

    12.0 DISPOSAL OF STUDY-DERIVED WASTES 12-1

    12.1 SOLID WASTE 12-1

    12.1.1 Soil Cuttings 12-1

    12.1.2 Personnel Protection Equipment 12-1

    12.2 LIQUID WASTE 12-1

    12.2.1 Decontamination Water 12-1

    12.2.2 Well Development Purge Water 12-2

    13.0 FIELD TEST EQUIPMENT 13-1

    13.1 CALIBRATION 13-1

    13.1.1 Photoionization Detector 13-1

    13.1.2 pH Meter 13-4

    13.1.3 Conductivity Meter 13-5

    13.2 PREVENTIVE MAINTENANCE 13-8

    13.2.1 Instrument Calibration and Maintenance 13-8

    13.2.2 Instrument Maintenance Logbooks 13-8

    14.0 REFERENCES 14-1

    APPENDICES

    A-1 APPENDIX A: METCALF & EDDY SOP SECTION 6.0, SUBSURFACE

    INVESTIGATIONS

    i i i

  • LIST OF FIGURES

    Figure Page

    2-1 Location Map 2-2

    Construction

    2-2 Site Map 2-3

    2-3 Field Investigation Schedule - Phase I I 2-5

    4-1 Proposed Sampling Locations 4-2

    6-1 Proposed Locations of Magnetomer, EM & GPR Surveys 6-2

    6-2 Proposed Locations of Seismic Refraction and VLF

    Surveys 6-6

    7- 1 Geologic Log 7-3

    7-2 Schematic Diagram of Peizometer/Monitoring Well 7-5

    7-3 Monitoring Well Completion Log 7-8

    7- 4 Topographic Base Map 7-12

    8- 1 Test Pit Log Forms 8-6

    8-2 Well Sampling Worksheet 8-11

    11-1 EPA CLP Sample Label 11-6

    11-2 Sample Tag and Custody Seal 11-8

    11-3 Chain of Custody Form 11-9

    11-4 RAS Traffic Report 11-10

    11-5 SAS Packing List 11-11

    11-6 Example Federal Express A i r b i l l 11-13

    11-7 Field Logbook I n i t i a l Field Information 11-20

    11-8 Field Logbook Groundwater Monitoring Well Sampling

    Data 11-21

    11-9 Field Logbook Surface Water Sampling Data 11-22

    11-10 Field Logbook Soil/Sediment Sampling Data 11-23

    iv

  • LIST OF TABLES

    Table Page

    4-1 Proposed Monitoring Well Information 4-3

    4-2 Summary of Soil Sampling Activities 4-5

    4-3 Summary of Sampling Activities 4-6

    10- 1 Typical Materials Required for Equipment

    Decontamination 10-3

    11- 1 Sampling Parameter, Containers and Preservation 11-2

    11-2 Field/Sampling Team Documentation Objectives to

    Ensure Valid Data Collection 11-15

    13-1 Preventive Maintenance Requirements of Field

    Equipment 13-7

    v

  • 1.0 INTRODUCTION

    This Field Sampling Plan (FSP) is the part of the Sampling and Analysis Plan

    (SAP) that provides guidance for f i e l d work. I t defines the sampling and data

    acquisition protocols to be used in the Phase I I Field Investigations at the

    Holton Circle Site, Londonderry, New Hampshire. The FSP shall be used by

    f i e l d personnel to perform the planned f i e l d work. A copy of the FSP w i l l be

    made available to each member of the f i e l d team. Collection of environmental

    samples and other data from the five sites of concern and subsequent analysis

    are necessary to determine the nature and extent of any contamination at the

    Holton Circle Site.

    The purpose of this plan is to assure that the acquisition and analysis of

    samples is performed in the highest quality manner and that the results w i l l

    be defensible in a court of law. For this reason, f i e l d testing and sampling

    shall be performed according to accepted and approved protocols defined by

    this document. Any deviation from this plan must receive the approval of the

    EPA project manager.

    1-1

  • 2.0 PROJECT DESCRIPTION

    2.1 SITE LOCATION AND DESCRIPTION

    Holton Circle is a residential development of approximately 25 homes located

    north of Pillsbury Road in Londonderry, New Hampshire (see Figures 2-1 and

    2-2). Isabella Drive, a new 22-lot subdivision, has been extended from the

    northwestern corner of Holton Circle as shown in Figure 2-2. .Both Holton

    Circle and Isabella Drive are situated on a topographic high, bounded on the

    north, the east and the west by wetlands.

    2.2 SITE BACKGROUND

    Eight Holton Circle residential wells and the town garage bedrock well located

    nearby have been determined to be contaminated with several volatile organic

    compounds. Previous investigations have included f i l e reviews, interviews,

    fracture trace analyses, water and soil sampling, and geophysical surveys. No

    contamination source has been found to date, although several sources of

    possible contamination have been identified. The Londonderry town garage is

    located off of West Range Road, southwest of the wetlands. The town garage is

    currently used for vehicle maintenance and road salt storage. I t was

    previously used by the military during the 1940's and more recently as a

    temporary municipal solid waste transfer station for a period of at least

    six months after closure of the Auburn Road Landfill. Beyond the wetlands to

    the east is a natural gas pipeline, the Londonderry high school, f i r e station

    and town offices. Paul Hick's Auto Repair Shop and residential homes are

    located south of the Holton Circle area along Pillsbury Road.

    There is some indication that the town garage area may be a source of

    contamination due the previous history of this area as a military dump

    (CT Male). Maintenance for the radio becon tower, located west of the town

    garage may have resulted in contamination due to the use of wash rocks for

    cleaning equipment.

    2-1

  • FIGURE 2-1. LOCATION MAP, HOLTON CIRCLE, LONDONDERRY, NEW HAMPSHIRE

    LOCATION MAP, HOLTON CIRCLE, LONDONDERRY, NEW HAMPSHIRE

    2-2

  • WETLANDS 52-15 52-17

    52-13

    52-11 (15)

    (17) ( 1 9 ) / 52-19

    .(21)

    (10) J '(14) 52-21

    ^3L 52-7

    52-9 (11),

    (7)

    /(6) .52-6

    52-10 '52-14 (16'

    '52-1

    ,(23)

    52-23 ^ (25)

    (18) ' 52-16 /(27) 52-25

    A. AL

    52-5 (5)

    14-21

    14-19 I(30)1

    1 4 " 1 8

    (28) AL

    14-23 \P2LJ£ UJ .14-25

    14-26 VS5 , fl O I

    ALSO 38 HOLTON CIRCLE

    SOURCE: ADAPTED FROM TOWN OF LONDONDERRY, NH PROPERTY TAX MAP

    SCALE IN FEET

    FIGURE 2-2. SITE MAP, HOLTON CIRCLE, LONDONDERRY, NEW HAMPSHIRE

    M E T C A L F

  • 2.3 SAMPLING SCHEDULE

    The Phase I sampling of the water supply wells for the individual Holton

    Circle residents and the two town garage wells were conducted the f i r s t week

    in March 1990 by the New Hampshire Department of Environmental

    Services (NHDES). Samples collected during the last in April 1990 were s p l i t

    between Metcalf & Eddy (M&E) and the NHDES and submitted for comparative

    analyses. The last sampling episode was conducted in June 1990 by the NHDES.

    A work schedule for the Phase I I site characterization is shown in Figure 2-3.

    2-4

  • DESCRIPTION JULY

    HOLTON CIRCLE RI/FS Field Investigation - Phase II

    U.S. EPA ARCS 09-11-90

    1990 AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER

    Sampling Location Survey

    Wetlands Reconnaissance

    Surface Geophysics

    Well Installation

    Borings

    Well Development

    Test Pits

    Downhole Geophysical Logging

    Solinst Installation

    Residential Well Sampling

    Environmental Sampling Water

    Environmental Sampling Soil (Borings & Surface Soil)

    Slug Testing

    Final Sampling Location Survey

    FIGURE 2-3. Field Investigation Schedule-Phase II

  • 3.0 SAMPLING OBJECTIVES

    The objectives for the Remedial Investigation/Feasibility Study (RI/FS) work

    assignment are to investigate the extent of groundwater contamination at the

    Holton Circle site and attempt to identify a source of the contamination.

    The f i e l d work has been divided into two phases. Phase I was the sampling of

    the existing residential wells to ascertain the present degree of

    contamination in preparation for installing groundwater monitoring wells in

    the Holton Circle area during the remedial investigation phase of the

    project. This sampling was completed in April 1990.

    The i n i t i a l site characterization (Phase I I f i e l d investigation) is intended

    to provide sufficient information to establish subsurface conditions, to

    characterize the hydrogeologic setting of the site, and to allow for the

    preliminary identification of potentially feasible remedial alternatives. The

    study w i l l focus on the area surrounding the town garage, west of the Holton

    Circle residences. To accomplish this objective the following f i e l d

    a ctivities w i l l be conducted:

    • Wetlands Reconnaissance

    • Surface Geophysical Surveys

    Monitoring Well Installation

    • Downhole Geophysical Logging

    • Environmental Sampling

    • Hydrogeologic Investigations

    • Site Survey/Mapping

    3-1

  • 4.0 SAMPLING LOCATION AND FREQUENCY

    4.1 SAMPLING LOCATIONS

    Fourteen (14) monitoring well locations have been tentatively chosen. Seven

    (7) of these are overburden wells and seven (7) are bedrock wells. Three (3)

    of the bedrock wells w i l l be multi-level wells using the Solinst Waterloo

    Multilevel System. Proposed groundwater monitoring wells and surface water

    monitoring points are shown in Figure 4-1 and proposed monitoring well details

    are provided in Table 4-1. The fi n a l determination of monitoring well

    locations w i l l be made on the basis of the surface geophysical surveys and the

    water quality of existing residential wells. The locations of the proposed

    bedrock monitoring wells w i l l be selected on the basis of the two fracture

    trace analysis reports and the suspected contaminant migration directions.

    Monitoring well pairs w i l l be installed in the su r f i c i a l and bedrock aquifers

    near the radio tower, downgradient of the town garage and in the wetland

    area. The locations of a l l proposed monitoring wells are shown in Figure 4-1.

    Three wells located between Holton Circle and the Town Garage w i l l be screened

    in preferential fracture zones using Solinst Waterloo Multilevel Systems.

    Borehole geophysical logging w i l l be conducted by the USGS in these three

    bedrock boreholes to determine the presence and location of transmissive

    bedrock fracture zones.

    The direction of groundwater flow in the surficial and bedrock aquifers w i l l

    be determined by measuring water level elevations. Piezometers w i l l be

    installed in four locations surrounding the town garage to aid in this

    determination. Slug tests w i l l be conducted in the overburden wells to

    determine the hydraulic conductivity of the surfi c i a l aquifer.

    Surface water elevations in the wetland area w i l l be measured to compare with

    groundwater elevation measurements in the surfi c i a l and bedrock aquifers.

    This comparison w i l l determine i f groundwater in the v i c i n i t y of Holton Circle

    is discharging into the wetlands. Seasonal measurements of groundwater and

    4-1

  • _ • LEGEND Note: Ovatoufden Monitoring Wei Location Wll be star Oata; Bed * ^ S K K ^ S ^ s ! ̂ ' ^ Soil Boring/Test Pit Area © Monitoring Well Pair Location

    • Piezometer Location • Surficial/Shallow Soil Sampling Location SCALE IN FEET

    FIGURE 4-1. PROPOSED SAMPLING LOCATIONS, HOLTON CIRCLE SITE, LONDONDERRY, NH

  • TABLE 4-1. PROPOSED MONITORING WELL INFORMATION

    Well Projected Siting

    Number Formation Depth ( f t ) Rationale

    MW-1S, 2S Overburden 35 Monitor groundwater quality in the

    s u r f i c i a l aquifer in the western

    part of the town garage in the

    Radio Beacon area.

    MW-1D, 2D Bedrock 185 Monitor groundwater quality in the

    bedrock aquifer on the western part

    of the town garage in Radio Beacon

    area.

    MW-3S, 4S, 5S Overburden 35 Monitor groundwater quality in

    s u r f i c i a l aquifer in the eastern

    part of the town garage in the

    Military Dump area.

    MW-3D, 4D , 5D Bedrock 185 Monitor groundwater quality in the

    bedrock aquifer in the eastern part

    of the town garage, in the Military

    Dump area. MW-4D to have downhole

    geophysical logging and Solinst

    Waterloo multi-level well system

    installed.

    MW-6S, 7S Overburden 35 Monitor groundwater quality between

    the town garage and Holton Circle.

    MW-6D*, 7D* Bedrock 185,385 Monitor groundwater quality in the

    bedrock aquifer between town garage

    and Holton Circle. MW-6D and 7D to

    have multi-level wells using the

    Solinst Waterloo System.

    * These wells w i l l be installed as multi-level wells.

    surface water elevation may indicate a migration potential that exists during

    periods of low water levels.

    4.2 SAMPLING FREQUENCY

    I t is estimated that up toa total of 684 bottles w i l l be used for sampling

    and analyses which include t r i p blanks, matrix spikes and duplicates, and

    4-3

  • equipment blanks. Samples w i l l be analyzed for CLP volatiles, CLP metals, and

    CLP semivolatiles, as well as other parameters listed in Tables 4-2 and 4-3.

    Complete l i s t s of the CLP parameters are presented in the QAPP.

    4.2.1 Unconsolidated Materials Sampling

    Samples of unconsolidated materials w i l l be collected during the overburden

    monitoring well installations. Samples w i l l be collected at the surface and

    at five foot intervals to the top of bedrock (anticipated to be a maximum

    depth of 30-35 feet). Mine borings w i l l be dr i l l e d in f i l l areas as

    identified by the geophysical surveys to identify residual concentrations of

    chemicals in the overburden soils. Continuous s p l i t spoon samples w i l l be

    obtained. Soil boring depths are anticipated to range from 15 to 20 feet.

    The borings w i l l be dr i l l e d according to specifications in M&E SOP Section 6.0

    as included in Appendix A.

    A maximum of three unconsolidated material samples w i l l be selected for

    laboratory analysis from each borehole and four samples from each borehole to

    be developed into an overburden well. Samples for chemical analysis w i l l be

    selected on the basis of results of screening with a PID. Samples w i l l most

    l ikely be collected at the top of the water table and near the top of the

    bedrock.

    Sampling of unconsolidated f i l l materials w i l l follow the soil sampling

    protocol described in Section 8.1. Samples w i l l be analyzed according to the

    parameters and methods shown in Table 4-2.

    4.2.2 Test Pit Sampling

    Test p i t samples w i l l be collected at a frequency of two samples per test p i t

    for each test p i t dug in the area of each of the ten anomalies detected in the

    Holton Circle area. Test p i t sampling protocol is described in Section 8.1.

    Test p i t samples w i l l be selected based on the results of screening with a PID

    and w i l l be analyzed according to the parameters and methods shown in

    Table 4-2. Contingency exists for the collection of an additional 10 samples

    4-4

  • ' TAiJUftl -2p!luMMl!IP (

    Analytical Boring Sediment Test Pit Trip Equipment Total Parameter Method*1} v 3 n 0Samples^'^' Sampl es > Samples^1 3' Blanks Blanks Duplicates Soil Water

    TCL Volatile Organics (VOCs) CLP RAS 59 8 10 14 8 8 85 22

    TCL Metals CLP RAS 59 8 10 8 8 85 8

    TCL Semivolatile CLP RAS Organics (sVOCs) 59 10 85 8

    Total Petroleum Hydrocarbons CLP SAS 59 8 10 85

    TCL CLP RAS Pesticides/PCBs 8

    TCL - Target Compound List

    (1) EPA-CLP METHODS FOR RAS

    Organics: USEPA Contract Laboratory Program, Statement of Work for Organics Analysis, Multi-Media/Multi-

    Concentration, February 1988.

    Inorganics: USEPA Contract Laboratory Program, Statement of Work for Inorganics Analysis, Multi-Media/Multi-

    Concentration, July 1988.

    EPA-CLP METHODS FOR SAS

    See SAS Request in Appendices

    (2) Up to 4 samples for each of the seven overburden monitoring wells and up to 3 samples for each of nine borings (with an

    additional 1 sample collected at a depth of 6 to 24 inches for the four borings included in area 5) w i l l be obtained.

    Professional judgment w i l l be used in selecting the samples to be submitted for analysis. Samples w i l l be selected

    based upon the concentration of volatile organics as measured with the PID. In the absence of volatile organics, the

    samples w i l l be selected based on color and visual observation of discoloration (staining) of the s o i l . I f deemed

    appropriate from the screening, two of the samples to be submitted for each well/boring w i l l be collected from the

    bedrock and from the area just above the water table.

    (3) Sediment samples to be taken at depths of 6 inches and 2 feet at wetlands areas between the town garage and Holton

    Circle.

    (4) Test p i t samples w i l l be collected at a frequency of 2 samples per test with one test p i t in the area of each of the ten

    anomalies. Contingency exists for the collection of an additional 10 samples based upon f i e l d screening. Ten samples

    w i l l be selected for analysis.

    (5) Samples must contain greater than 30% solids for the sample data to be considered usable.

  • TABLE 4-3. SifiMART OF HATCH SAH-LIMG ACTIVITIES AT HOLTOM CIRCLE. LOMDOHDEBRI. NEW HAMPSHIRE

    T o t a l per A n a l y t i c a l Groundwater Su r face Water T r i p Equipment

    (3) Sample a ( 3 ) Blanks Blanks D u p l i c a t e s Sampling Round

    f t t hod (1) Samples (2)

    LABORATORY ANALYSES:

    TCL V o l a t i l e O rgan i cs (VOCs) CLP RAS

    20 36

    TCL M s t a l s , U h f l l t e r e dF i l t e r e d

    CLP RAS 20 20

    2 0

    3 2

    3 2

    28 24

    TCL S e m i v o l a t i l e CLP RAS 20 28

    Organ ics (aVOCs)

    B i c a r b o n a t e 2320-8 20 21

    Ch lo r i de 325 .3 20 2 28

    N i t r a t e / N i t r i t e 353.3 20 2 28

    S u l f a t e 3 7 5 . 1 20 2 28

    Or thophosphate 3 65.1 20 2 28

    FIELD ANALYSES:

    Temperature E170.1 20 2 21

    PH E150.1 20 2 21

    C o n d u c t i v i t y E1 20.1 20 21

    TCL T a r g e t Compound L i s t

    0 ) H 0 D U S EF^ n L i c 3 r p

    0 A R C o n S t r a c t L a b o r a t o r y Program, S ta tement o f Work f o r O r gan i c s A n a l y s i s . M u l t i - M e d i a / H u l t i

    i n o r g a n i c s : S ^ ' t S ^ r i ' J ! ^ - . S ta tement o f Work f o r I n o r g a n i c s A n a l y s i s . M u l t i - M e d i a / M u l t i -

    C o n c e n t r a t i o n , J u l y 1988.

    Methods " " " c h e m i c a l A n a l y s i s o f Water and Wastes, EPA 6 0 0 / 1 - 7 9 - 0 2 0 , March 1983.

    2^20 B METHODS

    Standard Methods f o r t h e Exam ina t i on o f Water and Wastewater , 17 th E d i t i o n , 1989.

    (2) Groundwater Samples - Three samples each t o be o b t a i n e d f rom bedrock v e i l s MW-1D, 6D and 7D. S i n g l e samples t o be o b t a i n e d f rom MW-1 D, 2D, 3D, 5D. S ing le samples t o be o b t a i n e d f rom ove rbu rden w e l l s MW-1S t h r o u g h 7S.

    (3) A t o t a l o f two samp l i ng rounds a r e p roposed . Tne second round i s p roposed f o r June 1991.

    4-6

  • based on the f i e l d screening. Ten test p i t samples w i l l be selected for

    analysis.

    4.2.3 Groundwater Sampling

    Groundwater samples w i l l be collected from each of the monitoring wells

    installed in the Holton Circle area. I t is anticipated that two water samples

    w i l l be collected from each of the 3 multi-level wells, although as many as

    five may be taken from each. Groundwater sampling protocol is described in

    Section 8.2.1. Groundwater samples w i l l be analyzed according to the

    parameters and methods listed in Table 4-3.

    4.2.4 Surface Water and Sediment Sampling

    Two surface water and eight sediment samples (4 locations at depths of

    6 inches and 2 feet) w i l l be collected and analyzed according to the

    parameters and methods listed in Tables 4-2 and 4-3.

    The two surface water samples and two of the sediment samples w i l l be taken at

    the surface water elevation monitoring points (shown in Figure 4-1) as well as

    two additional locations selected during the wetlands reconnaissance.

    Protocols for the sediment and surface water sampling methods are discussed in

    Sections 8.1.2 and 8.2.2 respectively.

    4-7

  • 5.0 RECONNAISSANCE

    5.1 WETLANDS RECONNAISSANCE

    The wetlands area in the vicinity of the Holton Circle subdivision w i l l be

    investigated as a potential i l l e g a l disposal area. This investigation w i l l

    include the examination of available aerial photographs including those taken

    in conjunction with topographic maps drawn for this study. The wetlands

    reconnaissance w i l l also include a thorough walk-through of the wetland

    area. Signs of dumping, stressed vegetation, stained soils and disturbed

    areas w i l l a l l be noted. Two sediment sampling locations w i l l be selected

    based upon the best judgement of probable contamination.

    5.2 GEOLOGICAL RECONNAISSANCE

    Bedrock outcrops in the site vicinity w i l l be examined and described by an M&E

    geologist. One outcrop is known to exist in the Holton Circle subdivision;

    any others discovered during the process of staking surface geophysical

    surveys or during the wetlands reconnaissance w i l l also be examined. A l l

    available geological literature and maps of the site v i c i n i t y w i l l be

    reviewed.

    A fresh surface of the bedrock w i l l be observed and the lithology described.

    The strike and dip of any geologic structures such as joi n t surfaces bedding

    planes, cleavage planes and schistosity w i l l be measured and recorded in a

    f i e l d notebook. All observations w i l l be reported in the Rl report

    appendices.

    5-1

  • 6.0 SURFACE GEOPHYSICAL SURVEYS

    6.1 TOWN GARAGE

    Surface geophysical surveys w i l l be conducted in the vi c i n i t y of the Town

    Garage in order to determine the existence of buried drums and a possible

    chloride plume suspected to be migrating away from the Town Garage in a

    northeast direction. Metcalf 4 Eddy w i l l subcontract this work to Weston

    Geophysical.

    A combination of three surface geophysical methods w i l l be used to investigate

    the Town Garage area. Magnetometer surveys w i l l be conducted to locate buried

    drums. Ground penetrating radar (GPR) and electromagnetic (EM) methods w i l l

    be used to verify magnetometer data. EM w i l l also be used to detect the

    suspected chloride.

    Surface geophysical surveys w i l l be conducted in the five areas which are

    delineated in Figure 6-1. The areas were designated primarily based on

    information from CT Male Associates (1986) which included a sketch map from a

    site v i s i t conducted in September, 1986. Each area is described below as well

    as:

    Area 1 - Former Salt Pile Location

    According to the CT. Male report, Area 1 is the approximate former location

    of the Town Garage salt pile and has also had f i l l material added, evidenced

    by an embankment along the eastern, northern and northwestern edges of the

    Town Garage compound.

    Area 2 - Military Dump Area

    According to the CT. Male report, Area 2 is reportedly a former military dump

    site located at the northern corner of the Town Garage property.

    6-1

  • Areas 1 and 2: Magnetometer and GPR Area 4: GPR and EM 400 n 400

    Area 3: Magnetometer and EM Area 5: EM Only t f i S S ^ S I j ^ ^ ^ , ̂

    FIGURE 6-1. PROPOSED LOCATIONS OF MAGNETOMETER, EM AND GPR SURVEYS

    HOLTON CIRCLE SITE, LONDONDERRY, NH

  • A magnetometer survey w i l l be conducted in Areas 1 & 2 to determine the

    existence of buried drums in the f i l l material. Magnetometer data w i l l be

    verified by conducting a GPR survey which w i l l investigate any magnetic

    anomalies detected EM was not selected as an appropriate geophysical method in

    Areas 1 & 2 because of expected elevated levels of chlorides.

    Area 3 - Former Pond Area

    According to the C.T. Male report, a small depression in the woods south of

    the highway garage has reportedly been f i l l e d with stones. The depression is

    intermittantly f i l l e d with water. According to aerial photos of aerial photos

    the area.

    The former pond area w i l l be investigated using a magnetometer survey backed

    up with an EM survey.

    Area 4 - Former Radio Beacon Area

    The site of the former radio beacon is located just inside the entrance to the

    Town Garage compound. The radio beacon area contains a concrete block

    building and 2 three-sided steel antennas approximately 50 feet high. This

    area w i l l be investigated for buried drums using EM techniques and a GPR

    survey.

    Area 5 - Dead Tree Area

    A line of dead trees oriented north-northeast from the Town Garage w i l l be

    investigated using EM techniques. I t is suspected that a chloride plume may

    have migrated in that direction.

    6.2 DELINEATION OF FRACTURE ZONES

    Surface geophysical surveys w i l l be conducted in the v i c i n i t y of the Holton

    Circle site in an attempt to further verify the presence of suspected fracture

    zones previously identified. Metcalf & Eddy w i l l subcontract this work to

    6-3

  • Weston Geophysical. Figure 6-2 shows the proposed survey lines for

    delineating fracture zones.

    VeryOlow frequency (VLF) geophysical data w i l l be used to identify anomalous

    zones of increased conductivity in the v i c i n i t y of the Holton Circle site.

    Lineations in the anomaly pattern oriented along the strike of suspected

    fracture zones w i l l provide evidence for the existence of the fractures.

    VLF receivers use 15 to 25 kHz signals from military VLF radio transmitters.

    The total depth of penetration of VLF methods is on the order of 150 to 180

    feet, which is considerably deeper than that achieved with conventional

    electromagnetic methods.

    Locations of proposed seismic and VLF survey lines are shownin Figure 6-2.

    All seismic and VLF lines w i l l be run perpendicular to the strike of the

    primary orientation of foliation in bedrock in the areas which is

    approximately N50°E. This average declination was obtained by examining

    fracture trace analysis reports (BCI Geonetics, 1986; NUS, 1986; EPIC, 1989)

    and by measuring the bedrock outcrop at the end of Isabella Drive.

    Seismic and VLF lines 1-4 w i l l be approximately 650 feet long; lines 5 and 6

    w i l l be approximately 400 feet. The total footage is approximately

    3,400 feet. The spacing of lines 1-5 w i l l be 400 feet; the spacing between

    lines 5 and 6 w i l l be 200 feet. I f seismic and VLF profiling reveal anomalous

    features indicating bedrock valleys or fracture zones, additional shorter

    lines may be run between the original lines.

    Seismic refraction methods w i l l be used to predict the depth to the water

    table, determine overburden thickness, identify bedrock topographic features

    ( i . e. top of bedrock), and verify the existence and orientation of any

    significant bedrock fracture zones.

    I t is expected that seismic refraction surveys w i l l verify anomalous zones

    detected by the VLF survey and locate low areas in the top of bedrock surface

    where dense non-aqueous phase liquids (DNAPL) may be concentrated.

    6-4

  • HOLTON SITE, LONDONDERRY, NH

  • Seismic refraction methods are based on the velocity distribution of

    a r t i f i c i a l l y generated seismic waves traveling in the subsurface. Seismic

    waves are refracted at interfaces between geologic layers or across

    significant fracture zones.

    Seismic refraction lines w i l l be run along existing and proposed VLF survey

    lines. Total linear footage of proposed seismic refraction survey lines is

    approximately 16,000 feet.

    6-6

  • 7.0 PIEZOMETER, UNCONSOLIDATED MATERIALS BORINGS, TEST PITS, AND MONITORING

    WELL INSTALLATION

    7.1 INTRODUCTION

    This section describes the protocols that w i l l be followed by f i e l d personnel

    during the d r i l l i n g of soil borings and the installation of piezometers and

    monitoring wells at Holton Circle. Prior to any d r i l l i n g , each proposed site

    w i l l be checked for underground u t i l i t i e s by M&E personnel. Public/private

    u t i l i t y company representatives w i l l be contacted where appropriate.

    An experienced geologist w i l l be present at each operating d r i l l r i g for the

    logging of samples, monitoring of d r i l l i n g operations, recording of s o i l and

    groundwater data, monitoring and recording the well installation procedures of

    that r i g , and preparing the boring logs and well diagrams. Each geologist

    w i l l be responsible for only one operating r i g . Each geologist w i l l have, on

    site, sufficient tools and professional equipment in operable condition to

    e fficiently perform his duties.

    7.2 PIEZOMETERS

    The town garage is located on a topographic high and recharge to the

    overburden and bedrock aquifers most likely occurs at this location. Four

    piezometers w i l l be installed at the Town Garage to determine the direction of

    groundwater flow in the s u r f i c i a l aquifer. This information is necessary for

    siting the overburden monitoring wells. Proposed piezometer locations are

    shown in Figure 4-1.

    The water table at the Town Garage is approximately 3-4 feet deep.

    Piezometers w i l l be constructed of 2-inch ID Schedule 40 PVC and w i l l be

    installed according to specifications for the installation of monitoring wells

    provided in the M&E SOP Section 6.0 which is included in Appendix A.

    Piezometers w i l l be installed using 10-foot screens with the top set at the

    water table. Piezometer depths are anticipated to be 20-feet each. A

    schematic diagram of the piezometer construction is shown in Figure 7-2.

    7-1

  • 7.3 UNCONSOLIDATED MATERIALS BORINGS

    All borings w i l l be advanced to bedrock with a truck-mounted d r i l l r i g using

    4 1/4 inch hollow stem augers. Samples w i l l be retrieved with a 2-inch

    outside diameter (OD) 2-foot long s p l i t spoon sampler. Standard penetration

    tests w i l l be conducted using ASTM 1586. The s p l i t spoon sampler w i l l be

    driven 24 inches by a 140 pound weight with a 30-inch free f a l l . Samples w i l l

    be obtained every five feet and a head space analysis performed on each of the

    samples. I f any contamination is detected, the Remedial Project Manager (RPM)

    w i l l be contacted. I f necessary, continuous sampling w i l l be performed u n t i l

    signs of contamination are no longer evident. Analytical sampling of soils in

    the overburden wells is discussed in Sections 4 and 8.1.

    A Metcalf & Eddy geologist w i l l describe the soils using the procedure

    described in ASTM D2488-84, Standard Practice for Description and

    Identification of Soils (Visual-Manual Procedure). All pertinent information

    observed during d r i l l i n g operations w i l l be noted in the f i e l d notebook. The

    following information w i l l be noted on the geologic log (Figure 7-1).

    D r i lling method, type of d r i l l i n g r i g , d r i l l e r ' s name

    • Diameter of the borehole

    • Sample type, depth interval sampler is driven, percent recovery

    • Number of blow counts required to drive each 6-inch interval of the

    s p l i t spoon sampler

    • Time at which the sampler is brought to the surface

    • Air monitoring instrument readings

    • Start and completion times for each boring

    • Depth at which water is f i r s t encountered

    • Lithology (USCS) and stratigraphic descriptions, including

    percentages of particle sizes

    7-2

  • FIGURE 7-1. GEOLOGIC LOG

    Metcalf S Eddv. Inc, GEOLOGIC LOG

    ENSDCERS

    PROJECT SHEET BORING NO.

    SITE LOCATION: JOB NO. 1 OF

    LOCATION: 6H0UND ELEV. TOTAL DEPTH

    DRILL CONTRACTOR: ENG/SEO: BEGUN

    DRILL RIG: DRILLER: FINISHED:

    HOLE SIZE: HEATHER: GROUND MATER (DEPTH/ELEV.):

    /

    DRILLING METHOD: DRILLING FLUID/SOURCE: TOP OF ROCK (DEPTH/ELEV.):

    SAMPLE STRATIGRAPHIC 61 DESCRIPTION DESCRIPTION

    to

    IB

    SAMPLE TYPES NOTES: B0RIN6 NO. SS-SPLIT SPOON. ST-SHELBY TUBE

    R-ROCK CORE. O-OTHER

    7-3

  • • Munsell color and code

    • Other soil characteristics (solvent odor, discoloration, etc.)

    7.4 TEST PITS

    Test pits w i l l be excavated in the military dump area and other areas where

    buried metal objects (drums) may be located as determined from the geophysical

    investigation. Test pits w i l l be excavated in accordance with M&E SOP

    Section 6.0 which is included in Appendix A. The four potential areas for

    test pits are shown in Figure 4-1. Two samples each w i l l be collected from

    approximately ten test pits to be dug in these areas. Contingency exists for

    the collection of an additional ten samples based on the f i e l d screening. A

    total of ten test p i t samples w i l l be submitted for analysis.

    7.5 OVERBURDEN MONITORING WELL INSTALLATION

    Monitoring wells w i l l be located as per Section 4.1 of this Field Sampling

    Plan. Installation procedures are documented in Section 6.0 of the M&E SOP

    which is included in Appendix A. Monitoring well construction details are

    shown in Figure 7-2. A minimum auger diameter of 4-1/4 inches ID w i l l be used

    to permit proper installation of the casing. The auger fli g h t s w i l l maintain

    the integrity of the borehole during installation and ensure that the sand

    pack is equally distributed in the annular space. The pore size of the sand

    pack w i l l be greater than the screen slot size. The overburden monitoring

    wells w i l l be installed to bedrock, approximately 30-35 feet below ground

    surface. In order to effectively seal the monitoring wells from surface

    runoff, a minimum five-foot seal w i l l be placed above the sand pack. This

    seal w i l l consist of a minimum 2-foot thick bentonite pellet seal overlain by

    a minimum 3-foot bentonite-cement grout mixture.

    According to f i e l d screening results, the overburden monitoring wells w i l l be

    screened in the most contaminated or permeable zone. In screening results

    indicate no contamination, the wells w i l l be screened just above the bedrock

    surface.

    7-4

  • FIGURE 7-2. SCHEMATIC DIAGRAM OF PIEZOMETER/MONITORING WELL CONSTRUCTION

    C E M E N T F I L L E O

    S T E E L G U A R O POST (ONE O F T H R E E )

    H O L E DIAMETER

    • INCHES

    TOP O F S U R F A C E CASING

    TOP OF RISER CASING

    GROUNO S U R F A C E

    DIA: 4" OR L A R G E R TYPE: S T E E L LOCKING

    P R O T E C T O R PIPE

    S U R F A C E CASING

    BOTTOM OF S U R F A C E CASING

    B A C K F I L L T Y P E : PORTLAND CEMENT

    OIA: 2 INCH RISER CASING TYPE: SCHEDULE *0 PVC

    TOP OF S E A L

    ANNULAR SEAL TYPE: BENTONITE

    P E L L E T S

    BOTTOM OF SEAL

    TOP OF SCREEN

    F I L T E R MATERIAL T Y P E : C L E A N OTTAWA

    SANO ( IF N E C E S S A R Y )

    S C R E E N DIA: 2 INCH T Y P E : S C H E D U L E 40 OPENING WIDTH: 0.020 INCH OR LESS

    BOTTOM OF S C R E E N

    BOTTOM OF HOLE

    7-5

  • After the borehole has been advanced to the target depth, procedures and

    protocols for well installation are as follows:

    • Verify the bottom borehole depth by measuring with a weighted

    fiberglass tape through the auger f l i g h t s .

    • Monitoring well casing w i l l consist of new, 2-inch diameter,

    Schedule 40 polyvinyl chloride (PVC). The casing w i l l be

    flush-threaded riser, screen and end cap; individual screen lengths

    w i l l not exceed 10 feet. PVC screens w i l l be installed in

    monitoring wells. The machined screen slots w i l l be sized to retain

    at least 90 percent of the sand pack. A l l casing w i l l be steam

    cleaned the same day i t is installed.

    • PVC casing w i l l be suspended inside the augers and clean

    well-rounded s i l i c a sand added slowly as the auger f l i g h t s are

    removed. Estimates of the volume of sand needed to raise the sand

    pack to 2 feet above the top of the screen and frequent tape checks

    w i l l be made to avoid bridging and assure proper sand placement.

    • Bentonite pellets w i l l be added slowly after the sand pack has been

    emplaced. The bentonite pellet seal w i l l form a barrier to keep the

    bentonite/cement grout from penetrating the sand pack. The pellet

    seal w i l l be manually checked with a weighted tape to assure that a

    minimum two-feet exists. I f the bentonite pellet seal is above the

    existing water table, clean potable water w i l l be added to allow

    proper hydration. The pellet seal w i l l be allowed to hydrate for at

    least eight hours.

    • The bentonite/cement grout w i l l be installed according to Section 6.0 of the M&E SOP (as included in Appendix A) and w i l l consist of Portland Type I or I I cement mixed with clean potable water and 2-5% by weight powdered bentonite. The grout mixture w i l l be tremied into the hole and be allowed to set for a minimum of 24 hours before development to effectively seal the well. The sides of the grout seal w i l l be nearly vertical at the surface to prevent frost heaving.

    Wells w i l l be vented with a 1/4-inch hole d r i l l e d in the above

    ground casing.

    • A locking protective casing w i l l be installed over the well

    immediately after well installation according to Section 6.0 of the

    M&E SOP (as included in Appendix A).

    • I f the well location is such that vehicular t r a f f i c is a potential

    hazard then guard posts w i l l be installed.

    • The individual well caps w i l l be marked.

    7-6

  • A well construction log w i l l be completed for each monitoring well

    installed (Figure 7-3).

    7.6 BEDROCK MONITORING WELL INSTALLATION

    A total of seven monitoring wells w i l l be installed a minimum of 150 feet into

    bedrock. Depending on the overburden thickness, the wells w i l l be

    approximately 185 feet which corresponds to the depth of the shallowest

    contaminated Holton Circle residential well. MW-6, however, w i l l be d r i l l e d

    350 feet into bedrock. Four bedrock monitoring wells (at the Town Garage)

    w i l l be single.open hole wells. The three remaining wells, two in the wetland

    area and one at the Town Garage w i l l be multilevel wells screened in

    transmissive fracture zones determined by borehole geophysical logging

    techniques. The multilevel wells w i l l be sited in fracture zones determined

    from the surface geophysical surveys and w i l l be located between Holton Circle

    and the two suspected source areas.

    The four monitoring wells at the Town Garage w i l l be installed by the

    following procedure:

    An 8-inch borehole w i l l be advanced 5 feet into unfractured bedrock

    using a downhole hammer and air rotary d r i l l i n g techniques

    • A 6-inch diameter casing w i l l be lowered to the bottom of the

    borehole

    The 6-inch casing is withdrawn 1 to 2 feet while a Portland

    cement/bentonite grout is tremied into the bottom 10 feet of the

    borehole

    The casing is then lowered into the grout at the bottom of the

    borehole and allowed to set for a minimum of 24 hours

    The wells w i l l be advanced further using NX rock coring through the

    grout into the bedrock. I t is estimated that 10 to 20 feet of

    bedrock w i l l be cored at each well

    Bedrock w i l l be drilled using a downhole hammer and air rotary

    d r i l l i n g techniques to create a 4-inch borehole to minimum of 150

    feet into bedrock except for MW-6 which w i l l be d r i l l e d to a depth

    of 350 feet into bedrock

    7-7

  • FIGURE 7-3. MONITORING HELL COMPLETION LOG

    GROUNDWATER INSTALLATION PROJECT

    D R I L L I N G CONTRACTOR. COORDINATES:

    BEGUN: SUPERVISOR: WELL SITE WATER LEVEL DEPTH ELEV F INISHED D R I L L E R .

    DEPTH IN ELEV. IN REFERENCE POINT & ELEVATION:

    -TOP OF SURFACE CASING:

    -TOP OF RISER CASING: /—GROUNOSURFACE

    G E N E R A L I Z E D DIA. :

    GEOLOGIC LOG • S U R F A C E CASING TYPE

    • BOTTOM OF SURFACE CASING

    ' B A C K F I L L : TYPE:

    OIA. • RISER CASING: TYPE

    • TOP OF SEAL

    • A N N U L A R S E A L : TYPE:

    BOTTOM OF SEAL

    - TOP OF SCREEN

    - F I L T E R M A T E R I A L : TYPE:

    - SCREEN: D IA . : TYPE:

    OPENING WIDTH: TYPE:

    • BOTTOM OF SCREEN

    • BOTTOM OF SUMP M E T H O D D R I L L E D :

    - BOTTOM OF HOLE

    M E T H O D DEVELOPED : HOLE DIAMETER

    TIME DEVELOPED :

    MRS Menoir&Eddv

    7-8

  • • The monitoring wells w i l l then be completed as open-rock holes

    Monitoring wells MW-4, MW-6 and MW-7 w i l l be installed as multiple screened

    wells.

    These boreholes w i l l be geophysically logged and a maximum of five fracture

    zones within the borehole w i l l be isolated using a Waterloo multi-level

    groundwater monitoring system manufactured by Solinst Canada, Ltd. The system

    uses a casing string made up of water activated packers, stainless steel port

    modules, various casing lengths, a base plug and a surface manifold. The

    system to be installed in the three Holton Circle multi-level wells w i l l

    contain dedicated pumps for sampling and pressure tranducers for monitoring

    water levels. The Waterloo system w i l l be installed by a Solinst senior

    technician. M&E w i l l provide a geologist to observe and assist with the

    installation.

    The Solinst technician's judgement w i l l be the f i n a l determinant for the

    detailed installation protocol. The procedure for installation is as follows:

    • Determine levels which are to be sampled

    • Layout equipment, tubing, wiring, etc. for the f u l l well depth

    Thread each piece of casing and lower into the hole, generally in 10

    foot segments

    • Add water to the central casing as necessary to counter act buoyancy

    • Activate packers - they must s i t for 48 hours before sampling

    • A permanently installed manifold is installed at the top of the well

    D rilling fluids and muds generated during the installation of bedrock

    monitoring wells w i l l be screened using headspace analysis with the Photovac

    Microtip. Materials w i l l be drummed i f contamination is detected above 10 ppm

    using the f i e l d screening and disposed of at the direction of NHDES. For

    pricing purposes, i t is assumed that no drums w i l l be generated. Fluids and

    muds w i l l be disposed of by i n f i l t r a t i o n into shallow trenches at a location

    selected by EPA and the NHDES.

    7-9

  • 7.7 MONITORING WELL DEVELOPMENT

    Monitoring well development w i l l be performed after the grout seal has set for

    a minimum of 48 hours. Well development w i l l be continuously supervised by •

    the site geologist or engineer. Development protocols are as follows:

    Measure the static water level and total well depth.

    Surge the well with a surge block and/or bailer followed by removal

    of well water with a bailer or pump. Wells should not be pumped

    dry.

    • Well development should continue u n t i l a minimum of 3 to 5 well

    volumes have been removed and u n t i l temperature, pH, and

    conductivity measurements have stabilized to within 10/5.

    Well development samples w i l l be retrieved every 15 minutes to

    monitor turbidity and percent of fines over time.

    Slowly recharging wells w i l l be developed as follows:

    • I f possible, water w i l l be removed from the well at a rate equal to

    or less than the recharge rate of the aquifer by use of a

    peristaltic pump, bailer or a bladder pump.

    • I f the above technique is not possible, the well w i l l be surged and

    pumped using a closed bottom bailer in an effort to dislodge fine

    materials from the screen and sand pack.

    • I f the slowly recharging well does not recover to ninety percent of

    i t s static water level within six to eight hours, one well volume

    w i l l be removed.

    • I f the slowly recharging well recovers in less than six hours, a

    minimum of two well volumes w i l l be removed.

    Well development water w i l l be contained. Refer to Section 12

    regarding waste storage and disposal.

    • Physical characteristics such as color, odor, turbidity, the

    presence of separate phases, odors, etc. w i l l be noted throughout

    well development operations.

    Also noted in the f i e l d notebook w i l l be duration of different

    development methods (time spent bailing, pumping) and estimated

    quantities of water removed.

    7-10

  • 7.8 SOIL CLEANUP

    All d r i l l cuttings w i l l be screened with an Photovac Microtip using headspace

    analysis to characterize the soil cuttings. Refer to Section 12 for methods

    of storage, testing, and disposal of soil cuttings.

    7.9 SURVEYING

    All newly installed piezometers, test pits, monitoring wells, surface water

    monitoring stations, and sampling locations w i l l be surveyed by M&E personnel

    after completion of the Phase I I fiel d investigations. A notch w i l l be made

    in the top of the PVC to establish each piezometer and monitoring well

    measuring point. The measuring point for each well w i l l be marked and

    described in the Rl report appendices. Surveying w i l l have vertical and

    horizontal accuracies of 0.01 and 0.1 feet respectively. Survey points w i l l

    be tied to the United States Geological Survey (USGS) vertical datum and to

    the New Hampshire State Coordinate System. A l l bench marks w i l l be clearly

    identified on the base map and a l l surveyed locations w i l l be noted on

    appropriate site maps. A written description of each sampling locations

    coordinates w i l l be included in the Rl appendices.

    A topographic base map of the site w i l l be prepared with a contour interval of

    2 feet and a New Hampshire State Plane planimetric grid coordinate system.

    The map, at a scale of 1 inch = 400 feet, w i l l include the Londonderry town

    garage, Londonderry High School/Fire Department and other features in the

    v i cinity of the Holton Circle subdivision. The area which w i l l be included in

    the topographic base map is shown in Figure 7-4.

    7-11

  • FIGURE 7-4. TOPOGRAPHIC BASE MAP

  • 8.0 SAMPLING PROCEDURES

    The following sections outline the equipment and sampling procedures that

    shall be used for the collection of surface water, sediment, unconsolidated

    materials, and groundwater at Holton Circle, Londonderry, New Hampshire.

    Decontamination procedures for the sampling equipment are outlined in

    Section 10.0, and disposal of any study-derived waste is outlined in

    Section 12.0.

    8.1 UNCONSOLIDATED MATERIALS SAMPLING METHODS

    For field equipment calibration, see Section 13.1.

    8.1.1 Surface Unconsolidated Materials Sampling

    Equipment

    • Stainless steel trowel

    • Stainless steel t i l e spade or hand auger

    • Sample containers

    Sampling Procedure

    1. Record the physical characteristics of the unconsolidated materials

    such as color, odor, and texture.

    2. Make a sketch of the sampling location.

    3. Photograph the sampling location and conditions.

    4. Excavate the test site to a depth of 0 to 6 inches using a

    decontaminated stainless steel t i l e spade or hand auger.

    5. while wearing a new pair of PVC gloves, collect a representative

    unconsolidated material sample using the hand trowel.

    6. For samples being collected for volatile organics analysis, minimize

    any disturbance or mixing of the unconsolidated material. Invert a

    40 ml VOA vial or 125 ml bottle and insert i t directly into the

    sample unconsolidated material. Twist the vial or bottle into the

    8-1

  • soil and f i l l the container as completely as possible to minimize

    the air space. After volatile organics have been collected, the

    remaining samples may be mixed or composited. F i l l the containers

    at least 3/4 f u l l for a l l other analyses.

    7. Immediately label, refrigerate/ice, and log the sample into the

    f i e l d logbook.

    8. Complete the chain of custody form to accompany sample shipment.

    Documentation

    In addition to the observations noted in Section 11.3, the following

    information shall be documented and reported in the f i e l d logbook when

    sampling surface soils:

    • Description of the sample

    • Approximate depth of the sample collection

    • Information on whether the sample is a grab or composite sample

    • Method of composting

    • Whether the sample was sent to be analyzed or not, and why

    A general outline of a typical data entry page of the f i e l d logbook is given

    in Figure 11-6.

    8.1.2 Sed iment Sampling

    Equipment

    • Stainless steel trowel, scoop, or hand core sampler with stainless

    steel liner tubes

    • Stainless steel spoons

    • Sample containers

    • Stainless steel bowls

    8-2

  • Sampling Procedures

    Samples shall be collected beginning with the area suspected of least

    contamination (or the most upstream location) and proceeding to the areas of

    most contamination (or the most downstream location). I f surface waters are

    to be collected, collect them f i r s t . Then, collect sediment samples according

    to the following procedures:

    1. Record the physical characteristics of the sediment such as color,

    odor, and texture.

    2. Make a sketch of the sampling locations.

    3. Photograph the sampling locations and conditions.

    4. Wearing a new pair of PVC gloves, collect equal portions of sediment

    with a trowel or scoop at a minimum of three points in the sampling

    v i c i n i t y and transfer the samples into a stainless steel bowl.

    5. For samples being collected for volatile organics analysis, minimize

    any disturbance or mixing of the s o i l . Invert a 40 ml VOA vi a l or

    125 ml bottle and insert i t directly into the sample s o i l . Twist

    the v i a l or bottle into the soil and f i l l the container as

    completely as possible to minimize the air space.

    After volatile organics have been collected, the remaining samples

    may be mixed or composited. F i l l the containers at least 3/4 f u l l

    for a l l other analysis.

    6. Immediately label, refrigerate/ice, and log the samples into the

    bound f i e l d logbook.

    7. Complete the sample chain of custody form.

    Documentation

    (See Section 8.1.1)

    8.1.3 Borehole Unconsolidated Materials Sampling

    Equipment

    • Split spoon sampler (supplied by d r i l l i n g contractor)

    • Stainless steel spoon or spatula

    8-3

  • Stainless steel bowl

    Sample containers

    Sampling Procedures

    1. Record the physical characteristics of the unconsolidated material

    such as color, odor, and texture.

    2. Make a sketch of the sampling locations.

    3. Photograph the sampling locations and conditions.

    4. A 2-inch nominal diameter s p l i t spoon equipped with sand catchers

    (as needed) to minimize loss of sample w i l l be used.

    5. In accordance with ASTM D 1586 Standard Penetration Test, drive the

    s p l i t spoon sampler eighteen (18) inches into the ground at the test

    site using a 140-pound hammer falling t h i r t y (30) inches. Record

    the blowcount required to drive the s p l i t spoon sampler.

    6. Withdraw the s p l i t spoon from the borehole.

    7. Scan the s p l i t spoon sample for volatile organics with a

    photoionization detector (PID).

    8. Samples being collected for volatile organic analysis (VOA) shall be

    sampled f i r s t in order to minimize any volatile loss from the

    sample. Invert a 125 ml bottle and insert i t directly into the

    unconsolidated material sample in a position where VOAs were

    detected. Twist the vial or bottle into the so i l and f i l l the

    container as completely as possible to minimize the air space.

    After the volatile organic samples have been secured, remove a

    portion of the soil collected from the split-spoon sampler (near

    where the VOA sample was collected) and place in a zip-loc plastic

    bag. Then mix or composite the remainder of the s o i l sample

    collected. F i l l the appropriate sample containers at least 3/4 f u l l

    with s o i l for a l l remaining analyses.

    9. Immediately label, refrigerate/ice, and log the sample into a bound

    f i e l d logbook.

    10. Complete the sample chain of custody form to accompany sample

    shipment.

    11. Following the collection of soil samples from each borehole, screen

    the corresponding samples placed in the plastic bags with a PID or

    an organic vapor analyzer (OVA). Each screened sample w i l l remain

    in a plastic bag for 20-30 minutes and the bag w i l l be shaken

    8-4

  • i n i t i a l l y to release volatiles from the s o i l . The concentration

    w i l l be measured by penetrating the bag with the probe of the PID.

    The samples collected from the depths exhibiting the highest

    v olatile organic compound concentrations shall be chosen for

    laboratory analysis. In the absence of the detection volatile

    organics, samples collected for testing w i l l be based on color and

    visual observation of discoloration (staining) of the unconsolidated

    material. A maximum of three soil samples shall be submitted from

    each borehole (with an additional one sample collected at a depth of

    6 to 24 inches for the four borings included in Area 4). A maximum

    of four s o i l samples shall be submitted for each borehole developed

    into an overburden well.

    Documentation

    (See Section 8.1.1)

    8.1.4 Test Pit Sampling

    Equipment

    • Backhoe

    • Hand Trowel

    Sample Containers

    Sampling Procedure

    1. Record the weather conditions and other on-site particulars.

    2. Record the physical characteristics of the test p i t and sediment

    such as color, odor, and texture.

    3. Make a sketch of the test p i t boundaries and sampling locations in

    relation to site landmarks. Use a test p i t log form (see

    Figure 7-9) to record the sketch of the test p i t dimensions and

    describe the materials encountered.

    4. Photograph the sampling locations and conditions.

    5. Excavate the test site with the backhole to a depth of approximately

    10-15 feet or u n t i l groundwater is encountered.

    6. Measure and record the dimensions of the test p i t .

    7. Monitor the soil/sediment sample contained in the backhoe with an

    HNu photoionization detector or an organic vapor analyzer. Collect

    a representative sample from the backhoe bucket using a hand

    trowel. Never enter the test p i t to collect samples.

    8-5

  • FIGURE 8-1. TEST PIT LOG FORMS

    Job No.. Test Pit No.

    Project . Logged by

    Date •

    Metcalf & Eddy, Inc.

    TEST PIT LOG

    i — i — r i — i — r 1 ' I GROUND 10 15 ELEV

    10

    15

    Notes: .

    8-6

  • 8. I f samples are being collected for volatile organics analysis,

    minimize any disturbance or mixing of the s o i l . Wearing a new pair

    of PVC gloves, invert a 40 ml VOA via l and insert i t directly into

    the sample s o i l . Twist the sample into the soil and f i l l the

    container as completely as possible to minimize the air space.

    After volatile organics have been collected, the remaining samples

    may be mixed or composited. F i l l the containers at least 3/4 f u l l

    for a l l other analyses.

    9. Immediately label and tag (as required); refrigerate/ice; and log

    the samples into the bound f i e l d logbook and complete the sample

    chain of custody form.

    10. Decontaminate the trowel and backhoe bucket between test pits or

    between discreet contamination layers from which samples are to be

    collected for analysis.

    Documentation

    (See Section 8.1.1)

    8.2 WATER SAMPLING METHODS

    8.2.1 Single Level Groundwater Monitoring Well Sampling

    Equipment

    • Stainless steel measurement tape weighted and used to measure the

    water level

    • Bladder, Fultz, centrifugal, or positive displacement hand pump to

    purge the well.

    TEFLON® or stainless steel bailers for sample collection (Clear

    teflon bailers should be used for floating product estimations.)

    TEFL0N®-coated stainless steel cable to be used as leader line for

    bailers ( I t must be decontaminated between uses.)

    • Sample containers

    • Required sample preservatives ( i f sample containers do not already

    contain preservatives)

    • Disposable polystyrene cups for collection of f i e l d monitoring

    aliquots

    • pH meter

    8-7

  • • Thermometer, non-mercury type

    • Conductivity meter

    Standard pH buffer solutions of pH 4.0, 7.0, and 10.0 units

    • Single-use KC1 conductivity calibration standard solutions

    • F iltration apparatus, 0.45 micron

    • Photoionization detector and/or organic vapor analyzer

    Note: For calibration of f i e l d instruments see Section 7.2.

    Sampling Procedure

    Samples shall be collected beginning with the well located in the area

    suspected of least contamination (up gradient) and proceeding to the areas of

    most contamination. Other factors, such as well recovery time, may also

    influence the order of sample collection. The following procedure shall be

    used:

    1. Unlock the protective casing on the well.

    2. Sample the air in the well head for organic vapors using a

    photoionization detector or organic vapor analyzer, and record the

    measurements.

    3. Decontaminate the measuring tape as described in Section 10.1.2.

    Using the measuring tape, measure and record the well's static

    groundwater level and the depth to the bottom of the well. Record

    the measurement from the water surface to the top of the well casing

    to the nearest 0.01 foot.

    4. From the well diameter and the measured depth of the standing water,

    calculate (or use a well volume table to determine) the volume of

    the standing water in the well. Note and record the volume.

    5. (Optional) I f a floating layer is suspected to be present on top of

    the well water, gently lower a decontaminated, clear teflon bailer

    to below the water surface and withdraw. Using the photoionization

    detector or organic vapor analyzer, measure the headspace of the

    sample in the bailer and record the reading. Examine the surface of

    the water in the bailer for the presence of floating materials. I f

    possible, measure and record the thickness of this layer.

    8-8

  • 6. Wearing a new pair of PVC gloves, begin purging the well with a

    purging pump or bailer. The actual number of well volumes to be

    removed during a purging may vary depending on the site

    characteristics, well design, and the chemicals or parameters for

    which analysis shall be performed. At a minimum, three well volumes

    should be purged from each well unless the well is pumped to

    dryness. The purged volumes are estimated by discharging the purge

    water into a container of known volume. During the purging of each

    well volume, measure and record the water's temperature,

    conductivity, and pH several times as i t is removed from the well at

    the end of each well volume. Discontinue purging when three well

    volumes have been removed provided the pH and conductivity readings

    have stabilized. I f the measurements have not stabilized ( i . e . , any

    given pH or conductivity reading demonstrates more than a 10 percent

    difference from the previous reading), further purging may be

    necessary. A minimum of three readings is required.

    In wells.that recover slowly, wells w i l l be sampled after purging as

    soon as there is enough water in the well bore to obtain a sample.

    I f the well goes to dryness during the purging process, several

    options are available. The options are based on the time required

    for the water-level recovery, the type of analysis to be performed,

    and the type of purging and sampling equipment being used. The

    option to be used for each investigation should be approved on a

    site-specific basis prior to sampling. The options may include the

    following:

    For water-level recoveries of 0.5 to 1 hour, purge three well

    volumes. Sampling shall be performed within three hours of the

    f i n a l purge.

    For water-level recoveries of up to eight hours, the well may

    be purged early in the day. Sampling may be performed after

    the well level has recovered to within 80 percent of the

    original static water level measured.

    • I f water-level recoveries exceed 24 hours, the well may be

    purged once on one day and the samples may be collected within

    24 hours on the following day.

    The discharged water collected from each well purge is disposed of

    as described in Chapter 12.

    7. Using a decontaminated bailer, withdraw two f u l l bailers of

    groundwater from the well. Dispose of these f i r s t two bailers of

    sample along with the discharged well purge water as described in

    the Health & Safety Plan. (Personnel handling the bailer must wear

    new PVC gloves.)

    8. Using the same bailer and leader line, collect groundwater samples

    from the well. Record the time at the beginning and end of the

    bailing. (During sample collection, the leader line and bailer

    8-9

  • should not touch the ground or any objects except for the well

    casing.)

    9. Immediately, wearing new PVC gloves, transfer the groundwater sample

    directly from the bailer to the appropriate sample containers.

    A l l sample containers should be f i l l e d to the shoulder,

    approximately 3/4's f u l l , except for those samples requiring

    volatile organic analyses. Samples collected for volatile organics

    analysis w i l l be collected f i r s t . For the collection of volatile

    organic samples in VOA vials, be sure that there are no air bubbles

    in the vial after i t has been capped; ensure this by turning the

    v i a l upside down and tapping i t l i g h t l y .

    Samples collected for dissolved metals analysis must be f i e l d

    f i l t e r e d on-site at the time of sample collection. F i l t r a t i o n shall

    be performed using a laboratory cleaned and dedicated 0.45 micron

    f i l t e r . Particularly turbid samples may be prefiltered through a

    glass fiber f i l t e r prior to the 0.45 micron f i l t e r to speed the

    f i l t r a t i o n process. Samples of unfiltered groundwater w i l l also be

    collected for metals analysis.

    10. Collect a f i n a l sample aliquot in a disposable container and

    immediately measure and record the pH, temperature, and conductivity

    of that sample.

    11. Immediately label, preserve i f necessary, refrigerate/ice, and log

    the samples into a bound f i e l d logbook.

    12. Complete the chain of custody form to accompany sample shipment.

    13. Remeasure and record the standing water level in the well after

    sampling.

    14. Replace the protective cap on the well and lock.

    Documentation

    In addition to the sampling observations listed in Section 11.3, the following

    observations should be documented and reported in the f i e l d logbook when

    sampling monitoring wells: well purging data (see Figure 8-1), sample

    characteristics, and a note as to whether the well was secured upon ar r i v a l .

    A general outline of a typical data entry page of the f i e l d logbook for actual

    sample collection is given in Figure 11-4.

    8-10

  • FIGURE 8-2. WELL SAMPLING WORKSHEET

    WELL SAMPLING WORKSHEET

    Job No. Samplers Job Name

    Well ID Date Sampled .Time: Start .End

    . inches + 12 = . _(d)ft. Well secured upon arrival? Y/N Casing Diameter ft. Standing water (gal.) = —Depth of well from T.O.C. _

    x well volumes Depth of water from T.O.C. ft.

    = gallons to purge Feet of standing water .0>) ft-PIP Readings (ppm)

    Standing Breathing Water = rc [(d? + 4] 00 V l u m e° -3.14IC i t )

    2 +4 ] . f t ) x 7.48 gal/ft gals Well

    End. Purge: Time Start. Purging method

    Conductivity Temperature, (C) pH

    1 well volume = . gal.

    2 well volume = . gal.

    3 well volume = gal.

    Final volume = gal.

    Bailer 1D# Sample Collection: Time Start -End

    Sample Characteristics (Circle all applicable)

    none sulfide fishy musty petroleum Describe odor:

    colorless black brown orange red Describe color:

    Describe appearance: turbid silty sand clay floaters sheen

    clear multlphased foaming slimy algae

    Organic Layer? Length? Samples preserved?

    Comments . —

    8-11

  • 8.2.2 Waterloo Multilevel Well Sampling

    Because the multilevel well is novel to M&E no perfected procedure exists for

    sampling. However, the following may be considered a guideline. I t w i l l be

    necessary to become familiar with the sampling procedure through demonstration

    from a Solonist Technician.

    Equipment

    • Readout box to take measurements from pressure transducers

    • Pump control box to operate pumps for purging and sampling

    • A nitrogen tanks with regulator that w i l l reduce the pressure to

    less than 300 psi

    • Sample containers

    pH meter

    • Thermometer, non-mercury type

    • Conductivity meter

    Standard pH buffer solutions of pH 4.0, 7.0, and 10.0 units

    Single-use KC1 conductivity calibration standard solutions

    • F i ltration apparatus, 0.45 micron

    Photoionization detector and/or organic vapor analyzer

    Sampling Procedure

    Samples shall be collected beginning with the well located in the area

    suspected of least contamination (up gradient) and proceeding to the areas of

    most contamination. Other factors, such as well recovery time, may also

    influence the order of sample collection. The following procedure shall be

    used:

    1. Unlock the protective casing on the well.

    8-12

  • 2. Sample the air in the well head for organic vapors using a

    photoionization detector or organic vapor analyzer, and record the

    measurements.

    3. Connect the readout box to the pressure transducers via the

    alligator clips. I t is important to make sure that the proper

    connections are made.

    4. Connect the pump control box to the manifold taking care to connect

    each tube to the proper pump controller.

    5. Connect the nitrogen supply to the manifold. The pressure should be

    regulated below 300 psi.

    6. Wearing a new pair of PVC gloves, begin purging the well by

    activating the required port pump. The actual number of well

    volumes to be removed during a purging may vary depending on the

    site characteristics, well design, and the chemicals or parameters

    for which analysis shall be performed. At a minimum, three well

    volumes should be purged from each well unless the well is pumped to

    dryness. The purged volumes are estimated by discharging the purge

    water into a container of known volume. During the purging of each

    well volume, measure and record the water's temperature,

    conductivity, and pH several times as i t is removed from the well at

    the end of each well volume. Discontinue purging when three well

    volumes have been removed provided the pH and conductivity readings

    have stabilized. I f the measurements have not stabilized ( i . e . , any

    given pH or conductivity reading demonstrates more than a 10 percent

    difference from the previous reading), further purging may be

    necessary. A minimum of three readings is required.

    I f the well goes to dryness during the purging process, several

    options are available. The options are based on the time required

    for the water-level recovery, the type of analysis to be performed,

    and the type of purging and sampling equipment being used. The

    option to be used for each investigation should be approved on a

    site-specific basis prior to sampling. The options may include the

    following:

    For water-level recoveries of 0.5 to 1 hour, purge three well

    volumes. Sampling shall be performed within three hours of the

    f i n a l purge.

    • For water-level recoveries of up to eight hours, the well may

    be purged early in the day. Sampling may be performed after

    the well level has recovered to within 80 percent of the

    original static water level measured.

    • I f water-level recoveries exceed 24 hours, the well may be

    purged once on one day and the samples may be collected within

    24 hours on the following day.

    8-13

  • The discharged water collected from each well purge is disposed of

    as described in Chapter 12.

    7. F i l l the sample containers from the portal tube indicated for each

    sampling level. Extra care must be taken to avoid contaminating the

    ends of the portal tubes. Record the time at the beginning and end

    of the sampling.

    A l l sample containers should be f i l l e d to the shoulder,

    approximately 3/4's f u l l , except for those samples requiring

    v olatile organic analysis. Samples collected for volatile organics

    analysis must be collected f i r s t . For the collection of volatile

    organic samples in VOA vials, be sure that there are no air bubbles

    in the v i a l after i t has been capped; ensure this by turning the

    v i a l upside down and tapping i t l i g h t l y .

    Samples collected for dissolved metals analysis must be f i e l d

    f i l t e r e d . Filtration shall be performed using a laboratory cleaned

    and dedicated 0.45 micron f i l t e r . Particularly turbid samples may

    be prefiltered through a glass fiber f i l t e r prior to the 0.45 micron

    f i l t e r to speed the f i l t r a t i o n process.

    8. Collect a f i n a l sample aliquot in a disposable container and

    immediately measure and record the pH, temperature, and conductivity

    of that sample.

    9. Immediately label, preserve i f necessary, refrigerate/ice, and log

    the samples into a bound f i e l d logbook.

    10. Complete the chain of custody form to accompany sample shipment.

    11. Remeasure and rerecord readings from each of the pressure

    transducers.

    12. Disconnect the nitrogen, the readout box and the control box.

    13. Replace the protective cap on the well and lock.

    Documentation

    In addition to the sampling observations listed in Section 11.3, the following

    observations should be documented and reported in the f i e l d logbook when

    sampling monitoring wells: well purging data (see Figure 9-1), sample

    characteristics, and a note as to whether the well was secured upon ar r i v a l .

    A general outline of a typical data entry page of the f i e l d logbook for actual

    sample collection is given in Figure 11-4.

    8-14

  • 8.2.3 Surface Water Sampling

    Equipment

    • Sample containers

    • Required sample preservatives ( i f sample containers do not contain

    preservatives)

    • Disposable polystyrene cups for collection of f i e l d monitoring

    aliquot

    • pH meter

    • Conductivity meter

    • Thermometer

    Standard pH buffer solutions of pH 4.0, 7.0 and 10.0

    • Single-use KC1 conductivity calibration standard solutions

    • F i l t r a t i o n apparatus, 0.45 micron

    Note: For calibration of field instruments, see Section 7.2.

    Sampling Procedure

    To prevent cross-contamination of samples, sample collection shall start at

    locations suspected of least contamination and proceed to locations of most

    contamination. I f sediments are to be collected, collect surface water

    f i r s t . Collect samples according to the following procedures:

    1. Estimate the depth of water. ( I f a pole is to be used, wait to

    perform this task u n t i l after actual sampling to avoid water

    turbulence.)

    2. Record the weather conditions and other on-site particulars.

    3. Record the physical characteristics of the water body such as odor,

    color, temperature, pH, conductivity, presence of any dead

    vegetation and surface sheens, etc.

    4. Make a sketch of the surface water boundaries and sampling

    locations.

    8-15

  • 5. Photograph the sampling locations and conditions.

    6. Collect a sample by immersing the sample container in the water. Do

    not collect samples at the surface; instead, the sample container

    should be inverted, lowered to the approximate sampling depth, and

    held at about a 45-degree angle. I f the surface water is a flowing

    stream, river, or brook, hold the sample container at about a

    45-degree angle with the mouth of the bottle facing upstream.

    Samples collected for volatile organic analysis must contain no air

    bubbles in the VOA vial after i t has been capped; ensure this by

    turning the vi a l upside down and tapping i t l i g h t l y . F i l l a l l other

    sample containers to the shoulder.

    7. Collect a f i n a l sample aliquot in a disposable container and

    immediately measure and record the pH, temperature, and conductivity

    of that sample.

    8. Immediately label, preserve i f necessary, refrigerate/ice, and log

    the samples into a bound f i e l d logbook.

    9. Complete the chain of custody form to accompany sample shipment.

    10. I f possible, calculate an estimate of the surface water flow ( i f

    any) from a measurement of the linear cross-section flow velocity

    (using a bobber and a stop watch) and an estimate of the flow

    volume's cross-sectional area.

    Documentation

    In addition to the sampling observations listed in Section 11.3, the following

    observations should be documented in the f i e l d logbook when sampling surface

    water:

    Time of sample collected

    Description of water body, color, odor, appearance

    Depth of water

    Depth of sample collection for each specimen collected

    Description of sampling location (e.g., l e f t bank, eddy, middle,

    etc.)

    8-16

  • A general outline of a typical data entry page of the f i e l d logbook is given

    in Figure 11-5.

    8.3 QUALITY CONTROL SAMPLES

    During each sampling episode, a number of quality control (QC) samples must be

    collected and submitted for laboratory analysis. The number and frequency of

    the QC sample collection is outlined in Section 10.0 of the Quality Assurance

    Project Plan (QAPP) specific to this investigation.

    A l i s t of the types of QC samples that shall be collected along with a brief

    description of each sample type is outlined in the following sections.

    8.3.1 Trip Blanks

    Trip blanks are collected for chemical analysis of volatile organics. The

    analytical results serve as a baseline measurement of volatile organic

    contamination that samples may be exposed to during transport and laboratory

    storage prior to analysis.

    Trip blanks are comprised of deionized water which is placed in sample

    containers transported to the sample collection site, handled along with the

    samples, and returned to the laboratory along with samples of water and/or

    s oil collected for volatile organic analysis. The t r i p blank containers are

    not to be opened in the f i e l d .

    Typically, one t r i p blank is included in each shipping container for volatile

    organics analysis, is stored in the laboratory with the samples, and is

    analyzed by the laboratory (for volatile organics only).

    8.3.2 Equipment Blanks

    Equipment blanks are collected for each piece of sampling equipment used in

    the collection of samples when devices other than the sample bottle i t s e l f is

    required. The analysis of these blanks serves to verify the cleanliness of

    the sampling equipment.

    8-17

  • Equipment blanks are comprised of deionized water which is placed in sample

    containers transported to the sample collection site, opened, poured into the

    sampling device following equipment decontamination procedures (or pumped

    through i t as in the case of sampling pumps), transferred back to the sample

    bottle, and returned to the laboratory for analysis. The equipment blanks are

    analyzed for the same parameters as the associated samples.

    One equipment blank shall be collected per each day of sample collection or at

    a frequency of ten percent of the samples collected for each media sampled,

    whichever is greater. Every other equipment blank shall be submitted for

    laboratory analysis.

    8.3.3 Field Duplicates

    Field duplicates are defined as two samples collected independently of each

    other at a sampling location during a single episode of sampling. Analysis of

    these duplicates provides s t a t i s t i c a l information relating to sample

    v ariability and serves as a check on the precision of any sample collection

    method as i t pertains to the sampled area.

    Ten percent of a l l samples w i l l be collected in duplicate and submitted for

    laboratory analysis. Field duplicates shall be labeled in such a manner so

    that persons performing laboratory analysis are not able to distinguish

    duplicates from other collected samples.

    8-18

  • 9.0 HYDROGEOLOGIC INVESTIGATIONS

    Hydrogeologic investigations include testing and characterization of the

    hydraulic properties of the aquifers at the site.

    9.1 SLUG TESTS

    Slug tests w i l l be conducted on a l l overburden wells to determine hydraulic

    conductivity in the surfi c i a l aquifer. These w i l l be performed after sampling

    is completed to avoid any possibility of sample contamination by slug test

    equipment. Slug test equipment w i l l be decontaminated between wells.

    The following protocol w i l l be used:

    • The static water level w i l l be measured

    A slug of known volume w i l l be instantaneously introduced into each

    well

    • The recovery of the water level in each well w i l l be measured and

    recorded with time using an insitu data logger and pressure

    transducer, u n t i l the water level reaches the previous static level

    • The slug w i l l be instantaneously removed and the recovery of the

    well recorded as above

    Though not l i k e l y , i f the water table is below the top of the screen

    then only slug removal w i l l be performed

    The slug tests w i l l be duplicated i f necessary

    The data w i l l then be plotted on semi-logarithmic paper and analyzed using

    both the Hvorslev (1951) method and the Bouwer and Rice (1976) method and

    comparing the results.

    9.2 SURFACE HATER MEASUREMENT

    Three surface water monitoring stations w i l l be installed in the wetland areas

    in the vici n i t y of Holton Circle (Figure 4-1). These stations w i l l be used to

    monitor changes in surface water elevations so that the groundwater recharge

    potential and the groundwater/surface water relationship can be evaluated.

    9-1

  • 10.0 DECONTAMINATION PROCEDURES

    Decontamination is the process of removing contaminants that have accumulated

    on excavation equipment and sampling apparatus. Proper decontamination is

    essential in minimizing the transfer of harmful materials into clean areas, in

    the prevention of cross-contamination between samples due to the use of

    improperly decontaminated field/sampling equipment, and in protecting workers

    from hazardous substances.

    10.1 EQUIPMENT

    All equipment involved in site investigation activities shall be

    decontaminated prior to leaving the site. The general outline for such

    decontamination procedures is included in the following sections.

    10.1.1 Non-Sampling Field Equipment

    Non-sampling f i e l d equipment is any equipment that may potentially contact a

    sample area. A l l equipment and power tools used as non-sampling equipment

    ( i . e . , d r i l l i n g equipment, well casings and screens, backhoes, dredges,

    augers, etc.) shall be decontaminated before and following usage, as well as

    prior to removal from the site. Large and heavy d r i l l i n g equipment shall be

    steam cleaned. Light or small equipment such as hand tools shall be rinsed

    with tap water, scrubbed with a water/mild soap solution, and rinsed again

    with tap water, or shall be steam cleaned. Al l equipment decontamination

    shall be performed at a decontamination station specified in the site specific

    Health and Safety Plan.

    A ll d r i l l i n g and other non-sampling equipment shall be handled to prevent

    cross-contamination in the f i e l d by the use of sawhorses and plastic ground

    cloths. No equipment shall be placed directly on the ground.

    10-1

  • 10.1.2 Sampling Equipment

    Prior to f i e l d use, the c