field sampling plan - records collections · field personnel to perform the planne field workd a....
TRANSCRIPT
-
Sraperfnamdl Records Coiteir
EPA Contract No. 68-W9-0036
EPA Work Assignment No. 04-1LA4
EPA Project Officer: Nancy Barmakian
EPA Remedial Project Manager: Roger Duwart
FIELD SAMPLING PLAN
for Remedial Investigation/Feasibility Study
Activities
Holton Circle Site
Londonderry, New Hampshire
OCTOBER 1990
Prepared by:
METCALF & EDDY, INC.
M&E Project Manager: Nicholas D'Agostino
kVHE
Metcalf&Eddy
-
FIELD SAMPLING PLAN
TABLE OF CONTENTS
Section
LIST OF FIGURES
LIST OF TABLES
1.0 INTRODUCTION
2.0 PROJECT DESCRIPTION
2.1 SITE LOCATION AND DESCRIPTION
2.2 SITE BACKGROUND
2.3 SAMPLING SCHEDULE
3.0 SAMPLING OBJECTIVES
4.0 SAMPLING LOCATION AND FREQUENCY
4.1 SAMPLING LOCATIONS
4.2 SAMPLING FREQUENCY
4.2.1 Unconsolidated Materials Sampling
4.2.2 Test Pit Sampling
4.2.3 Groundwater Sampling
4.2.4 Surface Water and Sediment Sampling
5.0 RECONNAISSANCE
5.1 WETLANDS RECONNAISSANCE
5.2 GEOLOGICAL RECONNAISSANCE
6.0 SURFACE GEOPHYSICAL SURVEY
6.1 TOWN GARAGE
6.2 DELINEATION OF FRACTURE ZONES
7.0 PIEZOMETER, UNCONSOLIDATED MATERIALS BORINGS AND
MONITORING WELL INSTALLATION
7.1 INTRODUCTION
7.2 PIEZOMETERS
7.3 UNCONSOLIDATED MATERIAL BORINGS
-
TABLE OF CONTENTS (Continued)
Section Page
7.4 TEST PITS 7-4
7.5 OVERBURDEN MONITORING WELLS INSTALLATION 7-4
7.6 BEDROCK MONITORING WELL INSTALLATION 7-7
7.7 MONITORING WELL DEVELOPMENT 7-10
7.8 SOIL CLEANUP 7-11
7.9 SURVEYING 7-11
8.0 SAMPLING PROCEDURES 8-1
8.1 UNCONSOLIDATED MATERIALS SAMPLING METHODS 8-1
8.1.1 Surface Unconsolidated Materials Sampling 8-1
8.1.2 Sediment Sampling 8-2
8.1.3 Borehole Unconsolidated Materials Sampling 8-3
8.1.4 Test Pit Sampling 8-5
8.2 WATER SAMPLING METHODS 8-7
8.2.1 Groundwater Monitoring Well Sampling 8-7
8.2.2 Waterloo Multilevel Well Sampling 8-12
8.2.3 Surface Water Sampling 8-15
8.3 QUALITY CONTROL SAMPLES 8-17
8.3.1 Trip Blanks 8-17
8.3.2 Equipment Blanks 8-17
8.3.3 Field Duplicates 8-18
9.0 HYDROGEOLOGIC INVESTIGATIONS 9-1
9.1 SLUG TESTS 9-1
9.2 SURFACE WATER MEASUREMENTS 9-1
10.0 DECONTAMINATION PROCEDURES 10-1
10.1 EQUIPMENT 10-1
10.1.1 Non-Sampling Field Equipment 10-1
10.1.2 Sampling Equipment 10-2
10.1.3 Ice Chests and Shipping Containers 10-6
10.1.4 Vehicles 10-6
i i
-
TABLE OF CONTENTS (Continued)
Section Page
10.2 QUALITY CONTROL PROCEDURES 10-7
10.3 DOCUMENTATION 10-8
11.0 SAMPLE HANDLING FOR ANALYSIS 11-1
11.1 SAMPLE PRESERVATION 11-1
11.2 SAMPLE CUSTODY 11-1
11.2.1 Chain of Custody 11-4
11.2.2 Sample Packaging and Shipping 11-12
11.3 DOCUMENTATION 11-14
11.3.1 Sample Designation/Identification 11-16
11.3.2 Corrections to Documentation 11-16
11.3.3 Photographs 11-17
11.3.4 Records 11-17
12.0 DISPOSAL OF STUDY-DERIVED WASTES 12-1
12.1 SOLID WASTE 12-1
12.1.1 Soil Cuttings 12-1
12.1.2 Personnel Protection Equipment 12-1
12.2 LIQUID WASTE 12-1
12.2.1 Decontamination Water 12-1
12.2.2 Well Development Purge Water 12-2
13.0 FIELD TEST EQUIPMENT 13-1
13.1 CALIBRATION 13-1
13.1.1 Photoionization Detector 13-1
13.1.2 pH Meter 13-4
13.1.3 Conductivity Meter 13-5
13.2 PREVENTIVE MAINTENANCE 13-8
13.2.1 Instrument Calibration and Maintenance 13-8
13.2.2 Instrument Maintenance Logbooks 13-8
14.0 REFERENCES 14-1
APPENDICES
A-1 APPENDIX A: METCALF & EDDY SOP SECTION 6.0, SUBSURFACE
INVESTIGATIONS
i i i
-
LIST OF FIGURES
Figure Page
2-1 Location Map 2-2
Construction
2-2 Site Map 2-3
2-3 Field Investigation Schedule - Phase I I 2-5
4-1 Proposed Sampling Locations 4-2
6-1 Proposed Locations of Magnetomer, EM & GPR Surveys 6-2
6-2 Proposed Locations of Seismic Refraction and VLF
Surveys 6-6
7- 1 Geologic Log 7-3
7-2 Schematic Diagram of Peizometer/Monitoring Well 7-5
7-3 Monitoring Well Completion Log 7-8
7- 4 Topographic Base Map 7-12
8- 1 Test Pit Log Forms 8-6
8-2 Well Sampling Worksheet 8-11
11-1 EPA CLP Sample Label 11-6
11-2 Sample Tag and Custody Seal 11-8
11-3 Chain of Custody Form 11-9
11-4 RAS Traffic Report 11-10
11-5 SAS Packing List 11-11
11-6 Example Federal Express A i r b i l l 11-13
11-7 Field Logbook I n i t i a l Field Information 11-20
11-8 Field Logbook Groundwater Monitoring Well Sampling
Data 11-21
11-9 Field Logbook Surface Water Sampling Data 11-22
11-10 Field Logbook Soil/Sediment Sampling Data 11-23
iv
-
LIST OF TABLES
Table Page
4-1 Proposed Monitoring Well Information 4-3
4-2 Summary of Soil Sampling Activities 4-5
4-3 Summary of Sampling Activities 4-6
10- 1 Typical Materials Required for Equipment
Decontamination 10-3
11- 1 Sampling Parameter, Containers and Preservation 11-2
11-2 Field/Sampling Team Documentation Objectives to
Ensure Valid Data Collection 11-15
13-1 Preventive Maintenance Requirements of Field
Equipment 13-7
v
-
1.0 INTRODUCTION
This Field Sampling Plan (FSP) is the part of the Sampling and Analysis Plan
(SAP) that provides guidance for f i e l d work. I t defines the sampling and data
acquisition protocols to be used in the Phase I I Field Investigations at the
Holton Circle Site, Londonderry, New Hampshire. The FSP shall be used by
f i e l d personnel to perform the planned f i e l d work. A copy of the FSP w i l l be
made available to each member of the f i e l d team. Collection of environmental
samples and other data from the five sites of concern and subsequent analysis
are necessary to determine the nature and extent of any contamination at the
Holton Circle Site.
The purpose of this plan is to assure that the acquisition and analysis of
samples is performed in the highest quality manner and that the results w i l l
be defensible in a court of law. For this reason, f i e l d testing and sampling
shall be performed according to accepted and approved protocols defined by
this document. Any deviation from this plan must receive the approval of the
EPA project manager.
1-1
-
2.0 PROJECT DESCRIPTION
2.1 SITE LOCATION AND DESCRIPTION
Holton Circle is a residential development of approximately 25 homes located
north of Pillsbury Road in Londonderry, New Hampshire (see Figures 2-1 and
2-2). Isabella Drive, a new 22-lot subdivision, has been extended from the
northwestern corner of Holton Circle as shown in Figure 2-2. .Both Holton
Circle and Isabella Drive are situated on a topographic high, bounded on the
north, the east and the west by wetlands.
2.2 SITE BACKGROUND
Eight Holton Circle residential wells and the town garage bedrock well located
nearby have been determined to be contaminated with several volatile organic
compounds. Previous investigations have included f i l e reviews, interviews,
fracture trace analyses, water and soil sampling, and geophysical surveys. No
contamination source has been found to date, although several sources of
possible contamination have been identified. The Londonderry town garage is
located off of West Range Road, southwest of the wetlands. The town garage is
currently used for vehicle maintenance and road salt storage. I t was
previously used by the military during the 1940's and more recently as a
temporary municipal solid waste transfer station for a period of at least
six months after closure of the Auburn Road Landfill. Beyond the wetlands to
the east is a natural gas pipeline, the Londonderry high school, f i r e station
and town offices. Paul Hick's Auto Repair Shop and residential homes are
located south of the Holton Circle area along Pillsbury Road.
There is some indication that the town garage area may be a source of
contamination due the previous history of this area as a military dump
(CT Male). Maintenance for the radio becon tower, located west of the town
garage may have resulted in contamination due to the use of wash rocks for
cleaning equipment.
2-1
-
FIGURE 2-1. LOCATION MAP, HOLTON CIRCLE, LONDONDERRY, NEW HAMPSHIRE
LOCATION MAP, HOLTON CIRCLE, LONDONDERRY, NEW HAMPSHIRE
2-2
-
WETLANDS 52-15 52-17
52-13
52-11 (15)
(17) ( 1 9 ) / 52-19
.(21)
(10) J '(14) 52-21
^3L 52-7
52-9 (11),
(7)
/(6) .52-6
52-10 '52-14 (16'
'52-1
,(23)
52-23 ^ (25)
(18) ' 52-16 /(27) 52-25
A. AL
52-5 (5)
14-21
14-19 I(30)1
1 4 " 1 8
(28) AL
14-23 \P2LJ£ UJ .14-25
14-26 VS5 , fl O I
ALSO 38 HOLTON CIRCLE
SOURCE: ADAPTED FROM TOWN OF LONDONDERRY, NH PROPERTY TAX MAP
SCALE IN FEET
FIGURE 2-2. SITE MAP, HOLTON CIRCLE, LONDONDERRY, NEW HAMPSHIRE
M E T C A L F
-
2.3 SAMPLING SCHEDULE
The Phase I sampling of the water supply wells for the individual Holton
Circle residents and the two town garage wells were conducted the f i r s t week
in March 1990 by the New Hampshire Department of Environmental
Services (NHDES). Samples collected during the last in April 1990 were s p l i t
between Metcalf & Eddy (M&E) and the NHDES and submitted for comparative
analyses. The last sampling episode was conducted in June 1990 by the NHDES.
A work schedule for the Phase I I site characterization is shown in Figure 2-3.
2-4
-
DESCRIPTION JULY
HOLTON CIRCLE RI/FS Field Investigation - Phase II
U.S. EPA ARCS 09-11-90
1990 AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER
Sampling Location Survey
Wetlands Reconnaissance
Surface Geophysics
Well Installation
Borings
Well Development
Test Pits
Downhole Geophysical Logging
Solinst Installation
Residential Well Sampling
Environmental Sampling Water
Environmental Sampling Soil (Borings & Surface Soil)
Slug Testing
Final Sampling Location Survey
FIGURE 2-3. Field Investigation Schedule-Phase II
-
3.0 SAMPLING OBJECTIVES
The objectives for the Remedial Investigation/Feasibility Study (RI/FS) work
assignment are to investigate the extent of groundwater contamination at the
Holton Circle site and attempt to identify a source of the contamination.
The f i e l d work has been divided into two phases. Phase I was the sampling of
the existing residential wells to ascertain the present degree of
contamination in preparation for installing groundwater monitoring wells in
the Holton Circle area during the remedial investigation phase of the
project. This sampling was completed in April 1990.
The i n i t i a l site characterization (Phase I I f i e l d investigation) is intended
to provide sufficient information to establish subsurface conditions, to
characterize the hydrogeologic setting of the site, and to allow for the
preliminary identification of potentially feasible remedial alternatives. The
study w i l l focus on the area surrounding the town garage, west of the Holton
Circle residences. To accomplish this objective the following f i e l d
a ctivities w i l l be conducted:
• Wetlands Reconnaissance
• Surface Geophysical Surveys
Monitoring Well Installation
• Downhole Geophysical Logging
• Environmental Sampling
• Hydrogeologic Investigations
• Site Survey/Mapping
3-1
-
4.0 SAMPLING LOCATION AND FREQUENCY
4.1 SAMPLING LOCATIONS
Fourteen (14) monitoring well locations have been tentatively chosen. Seven
(7) of these are overburden wells and seven (7) are bedrock wells. Three (3)
of the bedrock wells w i l l be multi-level wells using the Solinst Waterloo
Multilevel System. Proposed groundwater monitoring wells and surface water
monitoring points are shown in Figure 4-1 and proposed monitoring well details
are provided in Table 4-1. The fi n a l determination of monitoring well
locations w i l l be made on the basis of the surface geophysical surveys and the
water quality of existing residential wells. The locations of the proposed
bedrock monitoring wells w i l l be selected on the basis of the two fracture
trace analysis reports and the suspected contaminant migration directions.
Monitoring well pairs w i l l be installed in the su r f i c i a l and bedrock aquifers
near the radio tower, downgradient of the town garage and in the wetland
area. The locations of a l l proposed monitoring wells are shown in Figure 4-1.
Three wells located between Holton Circle and the Town Garage w i l l be screened
in preferential fracture zones using Solinst Waterloo Multilevel Systems.
Borehole geophysical logging w i l l be conducted by the USGS in these three
bedrock boreholes to determine the presence and location of transmissive
bedrock fracture zones.
The direction of groundwater flow in the surficial and bedrock aquifers w i l l
be determined by measuring water level elevations. Piezometers w i l l be
installed in four locations surrounding the town garage to aid in this
determination. Slug tests w i l l be conducted in the overburden wells to
determine the hydraulic conductivity of the surfi c i a l aquifer.
Surface water elevations in the wetland area w i l l be measured to compare with
groundwater elevation measurements in the surfi c i a l and bedrock aquifers.
This comparison w i l l determine i f groundwater in the v i c i n i t y of Holton Circle
is discharging into the wetlands. Seasonal measurements of groundwater and
4-1
-
_ • LEGEND Note: Ovatoufden Monitoring Wei Location Wll be star Oata; Bed * ^ S K K ^ S ^ s ! ̂ ' ^ Soil Boring/Test Pit Area © Monitoring Well Pair Location
• Piezometer Location • Surficial/Shallow Soil Sampling Location SCALE IN FEET
FIGURE 4-1. PROPOSED SAMPLING LOCATIONS, HOLTON CIRCLE SITE, LONDONDERRY, NH
-
TABLE 4-1. PROPOSED MONITORING WELL INFORMATION
Well Projected Siting
Number Formation Depth ( f t ) Rationale
MW-1S, 2S Overburden 35 Monitor groundwater quality in the
s u r f i c i a l aquifer in the western
part of the town garage in the
Radio Beacon area.
MW-1D, 2D Bedrock 185 Monitor groundwater quality in the
bedrock aquifer on the western part
of the town garage in Radio Beacon
area.
MW-3S, 4S, 5S Overburden 35 Monitor groundwater quality in
s u r f i c i a l aquifer in the eastern
part of the town garage in the
Military Dump area.
MW-3D, 4D , 5D Bedrock 185 Monitor groundwater quality in the
bedrock aquifer in the eastern part
of the town garage, in the Military
Dump area. MW-4D to have downhole
geophysical logging and Solinst
Waterloo multi-level well system
installed.
MW-6S, 7S Overburden 35 Monitor groundwater quality between
the town garage and Holton Circle.
MW-6D*, 7D* Bedrock 185,385 Monitor groundwater quality in the
bedrock aquifer between town garage
and Holton Circle. MW-6D and 7D to
have multi-level wells using the
Solinst Waterloo System.
* These wells w i l l be installed as multi-level wells.
surface water elevation may indicate a migration potential that exists during
periods of low water levels.
4.2 SAMPLING FREQUENCY
I t is estimated that up toa total of 684 bottles w i l l be used for sampling
and analyses which include t r i p blanks, matrix spikes and duplicates, and
4-3
-
equipment blanks. Samples w i l l be analyzed for CLP volatiles, CLP metals, and
CLP semivolatiles, as well as other parameters listed in Tables 4-2 and 4-3.
Complete l i s t s of the CLP parameters are presented in the QAPP.
4.2.1 Unconsolidated Materials Sampling
Samples of unconsolidated materials w i l l be collected during the overburden
monitoring well installations. Samples w i l l be collected at the surface and
at five foot intervals to the top of bedrock (anticipated to be a maximum
depth of 30-35 feet). Mine borings w i l l be dr i l l e d in f i l l areas as
identified by the geophysical surveys to identify residual concentrations of
chemicals in the overburden soils. Continuous s p l i t spoon samples w i l l be
obtained. Soil boring depths are anticipated to range from 15 to 20 feet.
The borings w i l l be dr i l l e d according to specifications in M&E SOP Section 6.0
as included in Appendix A.
A maximum of three unconsolidated material samples w i l l be selected for
laboratory analysis from each borehole and four samples from each borehole to
be developed into an overburden well. Samples for chemical analysis w i l l be
selected on the basis of results of screening with a PID. Samples w i l l most
l ikely be collected at the top of the water table and near the top of the
bedrock.
Sampling of unconsolidated f i l l materials w i l l follow the soil sampling
protocol described in Section 8.1. Samples w i l l be analyzed according to the
parameters and methods shown in Table 4-2.
4.2.2 Test Pit Sampling
Test p i t samples w i l l be collected at a frequency of two samples per test p i t
for each test p i t dug in the area of each of the ten anomalies detected in the
Holton Circle area. Test p i t sampling protocol is described in Section 8.1.
Test p i t samples w i l l be selected based on the results of screening with a PID
and w i l l be analyzed according to the parameters and methods shown in
Table 4-2. Contingency exists for the collection of an additional 10 samples
4-4
-
' TAiJUftl -2p!luMMl!IP (
Analytical Boring Sediment Test Pit Trip Equipment Total Parameter Method*1} v 3 n 0Samples^'^' Sampl es > Samples^1 3' Blanks Blanks Duplicates Soil Water
TCL Volatile Organics (VOCs) CLP RAS 59 8 10 14 8 8 85 22
TCL Metals CLP RAS 59 8 10 8 8 85 8
TCL Semivolatile CLP RAS Organics (sVOCs) 59 10 85 8
Total Petroleum Hydrocarbons CLP SAS 59 8 10 85
TCL CLP RAS Pesticides/PCBs 8
TCL - Target Compound List
(1) EPA-CLP METHODS FOR RAS
Organics: USEPA Contract Laboratory Program, Statement of Work for Organics Analysis, Multi-Media/Multi-
Concentration, February 1988.
Inorganics: USEPA Contract Laboratory Program, Statement of Work for Inorganics Analysis, Multi-Media/Multi-
Concentration, July 1988.
EPA-CLP METHODS FOR SAS
See SAS Request in Appendices
(2) Up to 4 samples for each of the seven overburden monitoring wells and up to 3 samples for each of nine borings (with an
additional 1 sample collected at a depth of 6 to 24 inches for the four borings included in area 5) w i l l be obtained.
Professional judgment w i l l be used in selecting the samples to be submitted for analysis. Samples w i l l be selected
based upon the concentration of volatile organics as measured with the PID. In the absence of volatile organics, the
samples w i l l be selected based on color and visual observation of discoloration (staining) of the s o i l . I f deemed
appropriate from the screening, two of the samples to be submitted for each well/boring w i l l be collected from the
bedrock and from the area just above the water table.
(3) Sediment samples to be taken at depths of 6 inches and 2 feet at wetlands areas between the town garage and Holton
Circle.
(4) Test p i t samples w i l l be collected at a frequency of 2 samples per test with one test p i t in the area of each of the ten
anomalies. Contingency exists for the collection of an additional 10 samples based upon f i e l d screening. Ten samples
w i l l be selected for analysis.
(5) Samples must contain greater than 30% solids for the sample data to be considered usable.
-
TABLE 4-3. SifiMART OF HATCH SAH-LIMG ACTIVITIES AT HOLTOM CIRCLE. LOMDOHDEBRI. NEW HAMPSHIRE
T o t a l per A n a l y t i c a l Groundwater Su r face Water T r i p Equipment
(3) Sample a ( 3 ) Blanks Blanks D u p l i c a t e s Sampling Round
f t t hod (1) Samples (2)
LABORATORY ANALYSES:
TCL V o l a t i l e O rgan i cs (VOCs) CLP RAS
20 36
TCL M s t a l s , U h f l l t e r e dF i l t e r e d
CLP RAS 20 20
2 0
3 2
3 2
28 24
TCL S e m i v o l a t i l e CLP RAS 20 28
Organ ics (aVOCs)
B i c a r b o n a t e 2320-8 20 21
Ch lo r i de 325 .3 20 2 28
N i t r a t e / N i t r i t e 353.3 20 2 28
S u l f a t e 3 7 5 . 1 20 2 28
Or thophosphate 3 65.1 20 2 28
FIELD ANALYSES:
Temperature E170.1 20 2 21
PH E150.1 20 2 21
C o n d u c t i v i t y E1 20.1 20 21
TCL T a r g e t Compound L i s t
0 ) H 0 D U S EF^ n L i c 3 r p
0 A R C o n S t r a c t L a b o r a t o r y Program, S ta tement o f Work f o r O r gan i c s A n a l y s i s . M u l t i - M e d i a / H u l t i
i n o r g a n i c s : S ^ ' t S ^ r i ' J ! ^ - . S ta tement o f Work f o r I n o r g a n i c s A n a l y s i s . M u l t i - M e d i a / M u l t i -
C o n c e n t r a t i o n , J u l y 1988.
Methods " " " c h e m i c a l A n a l y s i s o f Water and Wastes, EPA 6 0 0 / 1 - 7 9 - 0 2 0 , March 1983.
2^20 B METHODS
Standard Methods f o r t h e Exam ina t i on o f Water and Wastewater , 17 th E d i t i o n , 1989.
(2) Groundwater Samples - Three samples each t o be o b t a i n e d f rom bedrock v e i l s MW-1D, 6D and 7D. S i n g l e samples t o be o b t a i n e d f rom MW-1 D, 2D, 3D, 5D. S ing le samples t o be o b t a i n e d f rom ove rbu rden w e l l s MW-1S t h r o u g h 7S.
(3) A t o t a l o f two samp l i ng rounds a r e p roposed . Tne second round i s p roposed f o r June 1991.
4-6
-
based on the f i e l d screening. Ten test p i t samples w i l l be selected for
analysis.
4.2.3 Groundwater Sampling
Groundwater samples w i l l be collected from each of the monitoring wells
installed in the Holton Circle area. I t is anticipated that two water samples
w i l l be collected from each of the 3 multi-level wells, although as many as
five may be taken from each. Groundwater sampling protocol is described in
Section 8.2.1. Groundwater samples w i l l be analyzed according to the
parameters and methods listed in Table 4-3.
4.2.4 Surface Water and Sediment Sampling
Two surface water and eight sediment samples (4 locations at depths of
6 inches and 2 feet) w i l l be collected and analyzed according to the
parameters and methods listed in Tables 4-2 and 4-3.
The two surface water samples and two of the sediment samples w i l l be taken at
the surface water elevation monitoring points (shown in Figure 4-1) as well as
two additional locations selected during the wetlands reconnaissance.
Protocols for the sediment and surface water sampling methods are discussed in
Sections 8.1.2 and 8.2.2 respectively.
4-7
-
5.0 RECONNAISSANCE
5.1 WETLANDS RECONNAISSANCE
The wetlands area in the vicinity of the Holton Circle subdivision w i l l be
investigated as a potential i l l e g a l disposal area. This investigation w i l l
include the examination of available aerial photographs including those taken
in conjunction with topographic maps drawn for this study. The wetlands
reconnaissance w i l l also include a thorough walk-through of the wetland
area. Signs of dumping, stressed vegetation, stained soils and disturbed
areas w i l l a l l be noted. Two sediment sampling locations w i l l be selected
based upon the best judgement of probable contamination.
5.2 GEOLOGICAL RECONNAISSANCE
Bedrock outcrops in the site vicinity w i l l be examined and described by an M&E
geologist. One outcrop is known to exist in the Holton Circle subdivision;
any others discovered during the process of staking surface geophysical
surveys or during the wetlands reconnaissance w i l l also be examined. A l l
available geological literature and maps of the site v i c i n i t y w i l l be
reviewed.
A fresh surface of the bedrock w i l l be observed and the lithology described.
The strike and dip of any geologic structures such as joi n t surfaces bedding
planes, cleavage planes and schistosity w i l l be measured and recorded in a
f i e l d notebook. All observations w i l l be reported in the Rl report
appendices.
5-1
-
6.0 SURFACE GEOPHYSICAL SURVEYS
6.1 TOWN GARAGE
Surface geophysical surveys w i l l be conducted in the vi c i n i t y of the Town
Garage in order to determine the existence of buried drums and a possible
chloride plume suspected to be migrating away from the Town Garage in a
northeast direction. Metcalf 4 Eddy w i l l subcontract this work to Weston
Geophysical.
A combination of three surface geophysical methods w i l l be used to investigate
the Town Garage area. Magnetometer surveys w i l l be conducted to locate buried
drums. Ground penetrating radar (GPR) and electromagnetic (EM) methods w i l l
be used to verify magnetometer data. EM w i l l also be used to detect the
suspected chloride.
Surface geophysical surveys w i l l be conducted in the five areas which are
delineated in Figure 6-1. The areas were designated primarily based on
information from CT Male Associates (1986) which included a sketch map from a
site v i s i t conducted in September, 1986. Each area is described below as well
as:
Area 1 - Former Salt Pile Location
According to the CT. Male report, Area 1 is the approximate former location
of the Town Garage salt pile and has also had f i l l material added, evidenced
by an embankment along the eastern, northern and northwestern edges of the
Town Garage compound.
Area 2 - Military Dump Area
According to the CT. Male report, Area 2 is reportedly a former military dump
site located at the northern corner of the Town Garage property.
6-1
-
Areas 1 and 2: Magnetometer and GPR Area 4: GPR and EM 400 n 400
Area 3: Magnetometer and EM Area 5: EM Only t f i S S ^ S I j ^ ^ ^ , ̂
FIGURE 6-1. PROPOSED LOCATIONS OF MAGNETOMETER, EM AND GPR SURVEYS
HOLTON CIRCLE SITE, LONDONDERRY, NH
-
A magnetometer survey w i l l be conducted in Areas 1 & 2 to determine the
existence of buried drums in the f i l l material. Magnetometer data w i l l be
verified by conducting a GPR survey which w i l l investigate any magnetic
anomalies detected EM was not selected as an appropriate geophysical method in
Areas 1 & 2 because of expected elevated levels of chlorides.
Area 3 - Former Pond Area
According to the C.T. Male report, a small depression in the woods south of
the highway garage has reportedly been f i l l e d with stones. The depression is
intermittantly f i l l e d with water. According to aerial photos of aerial photos
the area.
The former pond area w i l l be investigated using a magnetometer survey backed
up with an EM survey.
Area 4 - Former Radio Beacon Area
The site of the former radio beacon is located just inside the entrance to the
Town Garage compound. The radio beacon area contains a concrete block
building and 2 three-sided steel antennas approximately 50 feet high. This
area w i l l be investigated for buried drums using EM techniques and a GPR
survey.
Area 5 - Dead Tree Area
A line of dead trees oriented north-northeast from the Town Garage w i l l be
investigated using EM techniques. I t is suspected that a chloride plume may
have migrated in that direction.
6.2 DELINEATION OF FRACTURE ZONES
Surface geophysical surveys w i l l be conducted in the v i c i n i t y of the Holton
Circle site in an attempt to further verify the presence of suspected fracture
zones previously identified. Metcalf & Eddy w i l l subcontract this work to
6-3
-
Weston Geophysical. Figure 6-2 shows the proposed survey lines for
delineating fracture zones.
VeryOlow frequency (VLF) geophysical data w i l l be used to identify anomalous
zones of increased conductivity in the v i c i n i t y of the Holton Circle site.
Lineations in the anomaly pattern oriented along the strike of suspected
fracture zones w i l l provide evidence for the existence of the fractures.
VLF receivers use 15 to 25 kHz signals from military VLF radio transmitters.
The total depth of penetration of VLF methods is on the order of 150 to 180
feet, which is considerably deeper than that achieved with conventional
electromagnetic methods.
Locations of proposed seismic and VLF survey lines are shownin Figure 6-2.
All seismic and VLF lines w i l l be run perpendicular to the strike of the
primary orientation of foliation in bedrock in the areas which is
approximately N50°E. This average declination was obtained by examining
fracture trace analysis reports (BCI Geonetics, 1986; NUS, 1986; EPIC, 1989)
and by measuring the bedrock outcrop at the end of Isabella Drive.
Seismic and VLF lines 1-4 w i l l be approximately 650 feet long; lines 5 and 6
w i l l be approximately 400 feet. The total footage is approximately
3,400 feet. The spacing of lines 1-5 w i l l be 400 feet; the spacing between
lines 5 and 6 w i l l be 200 feet. I f seismic and VLF profiling reveal anomalous
features indicating bedrock valleys or fracture zones, additional shorter
lines may be run between the original lines.
Seismic refraction methods w i l l be used to predict the depth to the water
table, determine overburden thickness, identify bedrock topographic features
( i . e. top of bedrock), and verify the existence and orientation of any
significant bedrock fracture zones.
I t is expected that seismic refraction surveys w i l l verify anomalous zones
detected by the VLF survey and locate low areas in the top of bedrock surface
where dense non-aqueous phase liquids (DNAPL) may be concentrated.
6-4
-
HOLTON SITE, LONDONDERRY, NH
-
Seismic refraction methods are based on the velocity distribution of
a r t i f i c i a l l y generated seismic waves traveling in the subsurface. Seismic
waves are refracted at interfaces between geologic layers or across
significant fracture zones.
Seismic refraction lines w i l l be run along existing and proposed VLF survey
lines. Total linear footage of proposed seismic refraction survey lines is
approximately 16,000 feet.
6-6
-
7.0 PIEZOMETER, UNCONSOLIDATED MATERIALS BORINGS, TEST PITS, AND MONITORING
WELL INSTALLATION
7.1 INTRODUCTION
This section describes the protocols that w i l l be followed by f i e l d personnel
during the d r i l l i n g of soil borings and the installation of piezometers and
monitoring wells at Holton Circle. Prior to any d r i l l i n g , each proposed site
w i l l be checked for underground u t i l i t i e s by M&E personnel. Public/private
u t i l i t y company representatives w i l l be contacted where appropriate.
An experienced geologist w i l l be present at each operating d r i l l r i g for the
logging of samples, monitoring of d r i l l i n g operations, recording of s o i l and
groundwater data, monitoring and recording the well installation procedures of
that r i g , and preparing the boring logs and well diagrams. Each geologist
w i l l be responsible for only one operating r i g . Each geologist w i l l have, on
site, sufficient tools and professional equipment in operable condition to
e fficiently perform his duties.
7.2 PIEZOMETERS
The town garage is located on a topographic high and recharge to the
overburden and bedrock aquifers most likely occurs at this location. Four
piezometers w i l l be installed at the Town Garage to determine the direction of
groundwater flow in the s u r f i c i a l aquifer. This information is necessary for
siting the overburden monitoring wells. Proposed piezometer locations are
shown in Figure 4-1.
The water table at the Town Garage is approximately 3-4 feet deep.
Piezometers w i l l be constructed of 2-inch ID Schedule 40 PVC and w i l l be
installed according to specifications for the installation of monitoring wells
provided in the M&E SOP Section 6.0 which is included in Appendix A.
Piezometers w i l l be installed using 10-foot screens with the top set at the
water table. Piezometer depths are anticipated to be 20-feet each. A
schematic diagram of the piezometer construction is shown in Figure 7-2.
7-1
-
7.3 UNCONSOLIDATED MATERIALS BORINGS
All borings w i l l be advanced to bedrock with a truck-mounted d r i l l r i g using
4 1/4 inch hollow stem augers. Samples w i l l be retrieved with a 2-inch
outside diameter (OD) 2-foot long s p l i t spoon sampler. Standard penetration
tests w i l l be conducted using ASTM 1586. The s p l i t spoon sampler w i l l be
driven 24 inches by a 140 pound weight with a 30-inch free f a l l . Samples w i l l
be obtained every five feet and a head space analysis performed on each of the
samples. I f any contamination is detected, the Remedial Project Manager (RPM)
w i l l be contacted. I f necessary, continuous sampling w i l l be performed u n t i l
signs of contamination are no longer evident. Analytical sampling of soils in
the overburden wells is discussed in Sections 4 and 8.1.
A Metcalf & Eddy geologist w i l l describe the soils using the procedure
described in ASTM D2488-84, Standard Practice for Description and
Identification of Soils (Visual-Manual Procedure). All pertinent information
observed during d r i l l i n g operations w i l l be noted in the f i e l d notebook. The
following information w i l l be noted on the geologic log (Figure 7-1).
D r i lling method, type of d r i l l i n g r i g , d r i l l e r ' s name
• Diameter of the borehole
• Sample type, depth interval sampler is driven, percent recovery
• Number of blow counts required to drive each 6-inch interval of the
s p l i t spoon sampler
• Time at which the sampler is brought to the surface
• Air monitoring instrument readings
• Start and completion times for each boring
• Depth at which water is f i r s t encountered
• Lithology (USCS) and stratigraphic descriptions, including
percentages of particle sizes
7-2
-
FIGURE 7-1. GEOLOGIC LOG
Metcalf S Eddv. Inc, GEOLOGIC LOG
ENSDCERS
PROJECT SHEET BORING NO.
SITE LOCATION: JOB NO. 1 OF
LOCATION: 6H0UND ELEV. TOTAL DEPTH
DRILL CONTRACTOR: ENG/SEO: BEGUN
DRILL RIG: DRILLER: FINISHED:
HOLE SIZE: HEATHER: GROUND MATER (DEPTH/ELEV.):
/
DRILLING METHOD: DRILLING FLUID/SOURCE: TOP OF ROCK (DEPTH/ELEV.):
SAMPLE STRATIGRAPHIC 61 DESCRIPTION DESCRIPTION
to
IB
SAMPLE TYPES NOTES: B0RIN6 NO. SS-SPLIT SPOON. ST-SHELBY TUBE
R-ROCK CORE. O-OTHER
7-3
-
• Munsell color and code
• Other soil characteristics (solvent odor, discoloration, etc.)
7.4 TEST PITS
Test pits w i l l be excavated in the military dump area and other areas where
buried metal objects (drums) may be located as determined from the geophysical
investigation. Test pits w i l l be excavated in accordance with M&E SOP
Section 6.0 which is included in Appendix A. The four potential areas for
test pits are shown in Figure 4-1. Two samples each w i l l be collected from
approximately ten test pits to be dug in these areas. Contingency exists for
the collection of an additional ten samples based on the f i e l d screening. A
total of ten test p i t samples w i l l be submitted for analysis.
7.5 OVERBURDEN MONITORING WELL INSTALLATION
Monitoring wells w i l l be located as per Section 4.1 of this Field Sampling
Plan. Installation procedures are documented in Section 6.0 of the M&E SOP
which is included in Appendix A. Monitoring well construction details are
shown in Figure 7-2. A minimum auger diameter of 4-1/4 inches ID w i l l be used
to permit proper installation of the casing. The auger fli g h t s w i l l maintain
the integrity of the borehole during installation and ensure that the sand
pack is equally distributed in the annular space. The pore size of the sand
pack w i l l be greater than the screen slot size. The overburden monitoring
wells w i l l be installed to bedrock, approximately 30-35 feet below ground
surface. In order to effectively seal the monitoring wells from surface
runoff, a minimum five-foot seal w i l l be placed above the sand pack. This
seal w i l l consist of a minimum 2-foot thick bentonite pellet seal overlain by
a minimum 3-foot bentonite-cement grout mixture.
According to f i e l d screening results, the overburden monitoring wells w i l l be
screened in the most contaminated or permeable zone. In screening results
indicate no contamination, the wells w i l l be screened just above the bedrock
surface.
7-4
-
FIGURE 7-2. SCHEMATIC DIAGRAM OF PIEZOMETER/MONITORING WELL CONSTRUCTION
C E M E N T F I L L E O
S T E E L G U A R O POST (ONE O F T H R E E )
H O L E DIAMETER
• INCHES
TOP O F S U R F A C E CASING
TOP OF RISER CASING
GROUNO S U R F A C E
DIA: 4" OR L A R G E R TYPE: S T E E L LOCKING
P R O T E C T O R PIPE
S U R F A C E CASING
BOTTOM OF S U R F A C E CASING
B A C K F I L L T Y P E : PORTLAND CEMENT
OIA: 2 INCH RISER CASING TYPE: SCHEDULE *0 PVC
TOP OF S E A L
ANNULAR SEAL TYPE: BENTONITE
P E L L E T S
BOTTOM OF SEAL
TOP OF SCREEN
F I L T E R MATERIAL T Y P E : C L E A N OTTAWA
SANO ( IF N E C E S S A R Y )
S C R E E N DIA: 2 INCH T Y P E : S C H E D U L E 40 OPENING WIDTH: 0.020 INCH OR LESS
BOTTOM OF S C R E E N
BOTTOM OF HOLE
7-5
-
After the borehole has been advanced to the target depth, procedures and
protocols for well installation are as follows:
• Verify the bottom borehole depth by measuring with a weighted
fiberglass tape through the auger f l i g h t s .
• Monitoring well casing w i l l consist of new, 2-inch diameter,
Schedule 40 polyvinyl chloride (PVC). The casing w i l l be
flush-threaded riser, screen and end cap; individual screen lengths
w i l l not exceed 10 feet. PVC screens w i l l be installed in
monitoring wells. The machined screen slots w i l l be sized to retain
at least 90 percent of the sand pack. A l l casing w i l l be steam
cleaned the same day i t is installed.
• PVC casing w i l l be suspended inside the augers and clean
well-rounded s i l i c a sand added slowly as the auger f l i g h t s are
removed. Estimates of the volume of sand needed to raise the sand
pack to 2 feet above the top of the screen and frequent tape checks
w i l l be made to avoid bridging and assure proper sand placement.
• Bentonite pellets w i l l be added slowly after the sand pack has been
emplaced. The bentonite pellet seal w i l l form a barrier to keep the
bentonite/cement grout from penetrating the sand pack. The pellet
seal w i l l be manually checked with a weighted tape to assure that a
minimum two-feet exists. I f the bentonite pellet seal is above the
existing water table, clean potable water w i l l be added to allow
proper hydration. The pellet seal w i l l be allowed to hydrate for at
least eight hours.
• The bentonite/cement grout w i l l be installed according to Section 6.0 of the M&E SOP (as included in Appendix A) and w i l l consist of Portland Type I or I I cement mixed with clean potable water and 2-5% by weight powdered bentonite. The grout mixture w i l l be tremied into the hole and be allowed to set for a minimum of 24 hours before development to effectively seal the well. The sides of the grout seal w i l l be nearly vertical at the surface to prevent frost heaving.
Wells w i l l be vented with a 1/4-inch hole d r i l l e d in the above
ground casing.
• A locking protective casing w i l l be installed over the well
immediately after well installation according to Section 6.0 of the
M&E SOP (as included in Appendix A).
• I f the well location is such that vehicular t r a f f i c is a potential
hazard then guard posts w i l l be installed.
• The individual well caps w i l l be marked.
7-6
-
A well construction log w i l l be completed for each monitoring well
installed (Figure 7-3).
7.6 BEDROCK MONITORING WELL INSTALLATION
A total of seven monitoring wells w i l l be installed a minimum of 150 feet into
bedrock. Depending on the overburden thickness, the wells w i l l be
approximately 185 feet which corresponds to the depth of the shallowest
contaminated Holton Circle residential well. MW-6, however, w i l l be d r i l l e d
350 feet into bedrock. Four bedrock monitoring wells (at the Town Garage)
w i l l be single.open hole wells. The three remaining wells, two in the wetland
area and one at the Town Garage w i l l be multilevel wells screened in
transmissive fracture zones determined by borehole geophysical logging
techniques. The multilevel wells w i l l be sited in fracture zones determined
from the surface geophysical surveys and w i l l be located between Holton Circle
and the two suspected source areas.
The four monitoring wells at the Town Garage w i l l be installed by the
following procedure:
An 8-inch borehole w i l l be advanced 5 feet into unfractured bedrock
using a downhole hammer and air rotary d r i l l i n g techniques
• A 6-inch diameter casing w i l l be lowered to the bottom of the
borehole
The 6-inch casing is withdrawn 1 to 2 feet while a Portland
cement/bentonite grout is tremied into the bottom 10 feet of the
borehole
The casing is then lowered into the grout at the bottom of the
borehole and allowed to set for a minimum of 24 hours
The wells w i l l be advanced further using NX rock coring through the
grout into the bedrock. I t is estimated that 10 to 20 feet of
bedrock w i l l be cored at each well
Bedrock w i l l be drilled using a downhole hammer and air rotary
d r i l l i n g techniques to create a 4-inch borehole to minimum of 150
feet into bedrock except for MW-6 which w i l l be d r i l l e d to a depth
of 350 feet into bedrock
7-7
-
FIGURE 7-3. MONITORING HELL COMPLETION LOG
GROUNDWATER INSTALLATION PROJECT
D R I L L I N G CONTRACTOR. COORDINATES:
BEGUN: SUPERVISOR: WELL SITE WATER LEVEL DEPTH ELEV F INISHED D R I L L E R .
DEPTH IN ELEV. IN REFERENCE POINT & ELEVATION:
-TOP OF SURFACE CASING:
-TOP OF RISER CASING: /—GROUNOSURFACE
G E N E R A L I Z E D DIA. :
GEOLOGIC LOG • S U R F A C E CASING TYPE
• BOTTOM OF SURFACE CASING
' B A C K F I L L : TYPE:
OIA. • RISER CASING: TYPE
• TOP OF SEAL
• A N N U L A R S E A L : TYPE:
BOTTOM OF SEAL
- TOP OF SCREEN
- F I L T E R M A T E R I A L : TYPE:
- SCREEN: D IA . : TYPE:
OPENING WIDTH: TYPE:
• BOTTOM OF SCREEN
• BOTTOM OF SUMP M E T H O D D R I L L E D :
- BOTTOM OF HOLE
M E T H O D DEVELOPED : HOLE DIAMETER
TIME DEVELOPED :
MRS Menoir&Eddv
7-8
-
• The monitoring wells w i l l then be completed as open-rock holes
Monitoring wells MW-4, MW-6 and MW-7 w i l l be installed as multiple screened
wells.
These boreholes w i l l be geophysically logged and a maximum of five fracture
zones within the borehole w i l l be isolated using a Waterloo multi-level
groundwater monitoring system manufactured by Solinst Canada, Ltd. The system
uses a casing string made up of water activated packers, stainless steel port
modules, various casing lengths, a base plug and a surface manifold. The
system to be installed in the three Holton Circle multi-level wells w i l l
contain dedicated pumps for sampling and pressure tranducers for monitoring
water levels. The Waterloo system w i l l be installed by a Solinst senior
technician. M&E w i l l provide a geologist to observe and assist with the
installation.
The Solinst technician's judgement w i l l be the f i n a l determinant for the
detailed installation protocol. The procedure for installation is as follows:
• Determine levels which are to be sampled
• Layout equipment, tubing, wiring, etc. for the f u l l well depth
Thread each piece of casing and lower into the hole, generally in 10
foot segments
• Add water to the central casing as necessary to counter act buoyancy
• Activate packers - they must s i t for 48 hours before sampling
• A permanently installed manifold is installed at the top of the well
D rilling fluids and muds generated during the installation of bedrock
monitoring wells w i l l be screened using headspace analysis with the Photovac
Microtip. Materials w i l l be drummed i f contamination is detected above 10 ppm
using the f i e l d screening and disposed of at the direction of NHDES. For
pricing purposes, i t is assumed that no drums w i l l be generated. Fluids and
muds w i l l be disposed of by i n f i l t r a t i o n into shallow trenches at a location
selected by EPA and the NHDES.
7-9
-
7.7 MONITORING WELL DEVELOPMENT
Monitoring well development w i l l be performed after the grout seal has set for
a minimum of 48 hours. Well development w i l l be continuously supervised by •
the site geologist or engineer. Development protocols are as follows:
Measure the static water level and total well depth.
Surge the well with a surge block and/or bailer followed by removal
of well water with a bailer or pump. Wells should not be pumped
dry.
• Well development should continue u n t i l a minimum of 3 to 5 well
volumes have been removed and u n t i l temperature, pH, and
conductivity measurements have stabilized to within 10/5.
Well development samples w i l l be retrieved every 15 minutes to
monitor turbidity and percent of fines over time.
Slowly recharging wells w i l l be developed as follows:
• I f possible, water w i l l be removed from the well at a rate equal to
or less than the recharge rate of the aquifer by use of a
peristaltic pump, bailer or a bladder pump.
• I f the above technique is not possible, the well w i l l be surged and
pumped using a closed bottom bailer in an effort to dislodge fine
materials from the screen and sand pack.
• I f the slowly recharging well does not recover to ninety percent of
i t s static water level within six to eight hours, one well volume
w i l l be removed.
• I f the slowly recharging well recovers in less than six hours, a
minimum of two well volumes w i l l be removed.
Well development water w i l l be contained. Refer to Section 12
regarding waste storage and disposal.
• Physical characteristics such as color, odor, turbidity, the
presence of separate phases, odors, etc. w i l l be noted throughout
well development operations.
Also noted in the f i e l d notebook w i l l be duration of different
development methods (time spent bailing, pumping) and estimated
quantities of water removed.
7-10
-
7.8 SOIL CLEANUP
All d r i l l cuttings w i l l be screened with an Photovac Microtip using headspace
analysis to characterize the soil cuttings. Refer to Section 12 for methods
of storage, testing, and disposal of soil cuttings.
7.9 SURVEYING
All newly installed piezometers, test pits, monitoring wells, surface water
monitoring stations, and sampling locations w i l l be surveyed by M&E personnel
after completion of the Phase I I fiel d investigations. A notch w i l l be made
in the top of the PVC to establish each piezometer and monitoring well
measuring point. The measuring point for each well w i l l be marked and
described in the Rl report appendices. Surveying w i l l have vertical and
horizontal accuracies of 0.01 and 0.1 feet respectively. Survey points w i l l
be tied to the United States Geological Survey (USGS) vertical datum and to
the New Hampshire State Coordinate System. A l l bench marks w i l l be clearly
identified on the base map and a l l surveyed locations w i l l be noted on
appropriate site maps. A written description of each sampling locations
coordinates w i l l be included in the Rl appendices.
A topographic base map of the site w i l l be prepared with a contour interval of
2 feet and a New Hampshire State Plane planimetric grid coordinate system.
The map, at a scale of 1 inch = 400 feet, w i l l include the Londonderry town
garage, Londonderry High School/Fire Department and other features in the
v i cinity of the Holton Circle subdivision. The area which w i l l be included in
the topographic base map is shown in Figure 7-4.
7-11
-
FIGURE 7-4. TOPOGRAPHIC BASE MAP
-
8.0 SAMPLING PROCEDURES
The following sections outline the equipment and sampling procedures that
shall be used for the collection of surface water, sediment, unconsolidated
materials, and groundwater at Holton Circle, Londonderry, New Hampshire.
Decontamination procedures for the sampling equipment are outlined in
Section 10.0, and disposal of any study-derived waste is outlined in
Section 12.0.
8.1 UNCONSOLIDATED MATERIALS SAMPLING METHODS
For field equipment calibration, see Section 13.1.
8.1.1 Surface Unconsolidated Materials Sampling
Equipment
• Stainless steel trowel
• Stainless steel t i l e spade or hand auger
• Sample containers
Sampling Procedure
1. Record the physical characteristics of the unconsolidated materials
such as color, odor, and texture.
2. Make a sketch of the sampling location.
3. Photograph the sampling location and conditions.
4. Excavate the test site to a depth of 0 to 6 inches using a
decontaminated stainless steel t i l e spade or hand auger.
5. while wearing a new pair of PVC gloves, collect a representative
unconsolidated material sample using the hand trowel.
6. For samples being collected for volatile organics analysis, minimize
any disturbance or mixing of the unconsolidated material. Invert a
40 ml VOA vial or 125 ml bottle and insert i t directly into the
sample unconsolidated material. Twist the vial or bottle into the
8-1
-
soil and f i l l the container as completely as possible to minimize
the air space. After volatile organics have been collected, the
remaining samples may be mixed or composited. F i l l the containers
at least 3/4 f u l l for a l l other analyses.
7. Immediately label, refrigerate/ice, and log the sample into the
f i e l d logbook.
8. Complete the chain of custody form to accompany sample shipment.
Documentation
In addition to the observations noted in Section 11.3, the following
information shall be documented and reported in the f i e l d logbook when
sampling surface soils:
• Description of the sample
• Approximate depth of the sample collection
• Information on whether the sample is a grab or composite sample
• Method of composting
• Whether the sample was sent to be analyzed or not, and why
A general outline of a typical data entry page of the f i e l d logbook is given
in Figure 11-6.
8.1.2 Sed iment Sampling
Equipment
• Stainless steel trowel, scoop, or hand core sampler with stainless
steel liner tubes
• Stainless steel spoons
• Sample containers
• Stainless steel bowls
8-2
-
Sampling Procedures
Samples shall be collected beginning with the area suspected of least
contamination (or the most upstream location) and proceeding to the areas of
most contamination (or the most downstream location). I f surface waters are
to be collected, collect them f i r s t . Then, collect sediment samples according
to the following procedures:
1. Record the physical characteristics of the sediment such as color,
odor, and texture.
2. Make a sketch of the sampling locations.
3. Photograph the sampling locations and conditions.
4. Wearing a new pair of PVC gloves, collect equal portions of sediment
with a trowel or scoop at a minimum of three points in the sampling
v i c i n i t y and transfer the samples into a stainless steel bowl.
5. For samples being collected for volatile organics analysis, minimize
any disturbance or mixing of the s o i l . Invert a 40 ml VOA vi a l or
125 ml bottle and insert i t directly into the sample s o i l . Twist
the v i a l or bottle into the soil and f i l l the container as
completely as possible to minimize the air space.
After volatile organics have been collected, the remaining samples
may be mixed or composited. F i l l the containers at least 3/4 f u l l
for a l l other analysis.
6. Immediately label, refrigerate/ice, and log the samples into the
bound f i e l d logbook.
7. Complete the sample chain of custody form.
Documentation
(See Section 8.1.1)
8.1.3 Borehole Unconsolidated Materials Sampling
Equipment
• Split spoon sampler (supplied by d r i l l i n g contractor)
• Stainless steel spoon or spatula
8-3
-
Stainless steel bowl
Sample containers
Sampling Procedures
1. Record the physical characteristics of the unconsolidated material
such as color, odor, and texture.
2. Make a sketch of the sampling locations.
3. Photograph the sampling locations and conditions.
4. A 2-inch nominal diameter s p l i t spoon equipped with sand catchers
(as needed) to minimize loss of sample w i l l be used.
5. In accordance with ASTM D 1586 Standard Penetration Test, drive the
s p l i t spoon sampler eighteen (18) inches into the ground at the test
site using a 140-pound hammer falling t h i r t y (30) inches. Record
the blowcount required to drive the s p l i t spoon sampler.
6. Withdraw the s p l i t spoon from the borehole.
7. Scan the s p l i t spoon sample for volatile organics with a
photoionization detector (PID).
8. Samples being collected for volatile organic analysis (VOA) shall be
sampled f i r s t in order to minimize any volatile loss from the
sample. Invert a 125 ml bottle and insert i t directly into the
unconsolidated material sample in a position where VOAs were
detected. Twist the vial or bottle into the so i l and f i l l the
container as completely as possible to minimize the air space.
After the volatile organic samples have been secured, remove a
portion of the soil collected from the split-spoon sampler (near
where the VOA sample was collected) and place in a zip-loc plastic
bag. Then mix or composite the remainder of the s o i l sample
collected. F i l l the appropriate sample containers at least 3/4 f u l l
with s o i l for a l l remaining analyses.
9. Immediately label, refrigerate/ice, and log the sample into a bound
f i e l d logbook.
10. Complete the sample chain of custody form to accompany sample
shipment.
11. Following the collection of soil samples from each borehole, screen
the corresponding samples placed in the plastic bags with a PID or
an organic vapor analyzer (OVA). Each screened sample w i l l remain
in a plastic bag for 20-30 minutes and the bag w i l l be shaken
8-4
-
i n i t i a l l y to release volatiles from the s o i l . The concentration
w i l l be measured by penetrating the bag with the probe of the PID.
The samples collected from the depths exhibiting the highest
v olatile organic compound concentrations shall be chosen for
laboratory analysis. In the absence of the detection volatile
organics, samples collected for testing w i l l be based on color and
visual observation of discoloration (staining) of the unconsolidated
material. A maximum of three soil samples shall be submitted from
each borehole (with an additional one sample collected at a depth of
6 to 24 inches for the four borings included in Area 4). A maximum
of four s o i l samples shall be submitted for each borehole developed
into an overburden well.
Documentation
(See Section 8.1.1)
8.1.4 Test Pit Sampling
Equipment
• Backhoe
• Hand Trowel
Sample Containers
Sampling Procedure
1. Record the weather conditions and other on-site particulars.
2. Record the physical characteristics of the test p i t and sediment
such as color, odor, and texture.
3. Make a sketch of the test p i t boundaries and sampling locations in
relation to site landmarks. Use a test p i t log form (see
Figure 7-9) to record the sketch of the test p i t dimensions and
describe the materials encountered.
4. Photograph the sampling locations and conditions.
5. Excavate the test site with the backhole to a depth of approximately
10-15 feet or u n t i l groundwater is encountered.
6. Measure and record the dimensions of the test p i t .
7. Monitor the soil/sediment sample contained in the backhoe with an
HNu photoionization detector or an organic vapor analyzer. Collect
a representative sample from the backhoe bucket using a hand
trowel. Never enter the test p i t to collect samples.
8-5
-
FIGURE 8-1. TEST PIT LOG FORMS
Job No.. Test Pit No.
Project . Logged by
Date •
Metcalf & Eddy, Inc.
TEST PIT LOG
i — i — r i — i — r 1 ' I GROUND 10 15 ELEV
10
15
Notes: .
8-6
-
8. I f samples are being collected for volatile organics analysis,
minimize any disturbance or mixing of the s o i l . Wearing a new pair
of PVC gloves, invert a 40 ml VOA via l and insert i t directly into
the sample s o i l . Twist the sample into the soil and f i l l the
container as completely as possible to minimize the air space.
After volatile organics have been collected, the remaining samples
may be mixed or composited. F i l l the containers at least 3/4 f u l l
for a l l other analyses.
9. Immediately label and tag (as required); refrigerate/ice; and log
the samples into the bound f i e l d logbook and complete the sample
chain of custody form.
10. Decontaminate the trowel and backhoe bucket between test pits or
between discreet contamination layers from which samples are to be
collected for analysis.
Documentation
(See Section 8.1.1)
8.2 WATER SAMPLING METHODS
8.2.1 Single Level Groundwater Monitoring Well Sampling
Equipment
• Stainless steel measurement tape weighted and used to measure the
water level
• Bladder, Fultz, centrifugal, or positive displacement hand pump to
purge the well.
TEFLON® or stainless steel bailers for sample collection (Clear
teflon bailers should be used for floating product estimations.)
TEFL0N®-coated stainless steel cable to be used as leader line for
bailers ( I t must be decontaminated between uses.)
• Sample containers
• Required sample preservatives ( i f sample containers do not already
contain preservatives)
• Disposable polystyrene cups for collection of f i e l d monitoring
aliquots
• pH meter
8-7
-
• Thermometer, non-mercury type
• Conductivity meter
Standard pH buffer solutions of pH 4.0, 7.0, and 10.0 units
• Single-use KC1 conductivity calibration standard solutions
• F iltration apparatus, 0.45 micron
• Photoionization detector and/or organic vapor analyzer
Note: For calibration of f i e l d instruments see Section 7.2.
Sampling Procedure
Samples shall be collected beginning with the well located in the area
suspected of least contamination (up gradient) and proceeding to the areas of
most contamination. Other factors, such as well recovery time, may also
influence the order of sample collection. The following procedure shall be
used:
1. Unlock the protective casing on the well.
2. Sample the air in the well head for organic vapors using a
photoionization detector or organic vapor analyzer, and record the
measurements.
3. Decontaminate the measuring tape as described in Section 10.1.2.
Using the measuring tape, measure and record the well's static
groundwater level and the depth to the bottom of the well. Record
the measurement from the water surface to the top of the well casing
to the nearest 0.01 foot.
4. From the well diameter and the measured depth of the standing water,
calculate (or use a well volume table to determine) the volume of
the standing water in the well. Note and record the volume.
5. (Optional) I f a floating layer is suspected to be present on top of
the well water, gently lower a decontaminated, clear teflon bailer
to below the water surface and withdraw. Using the photoionization
detector or organic vapor analyzer, measure the headspace of the
sample in the bailer and record the reading. Examine the surface of
the water in the bailer for the presence of floating materials. I f
possible, measure and record the thickness of this layer.
8-8
-
6. Wearing a new pair of PVC gloves, begin purging the well with a
purging pump or bailer. The actual number of well volumes to be
removed during a purging may vary depending on the site
characteristics, well design, and the chemicals or parameters for
which analysis shall be performed. At a minimum, three well volumes
should be purged from each well unless the well is pumped to
dryness. The purged volumes are estimated by discharging the purge
water into a container of known volume. During the purging of each
well volume, measure and record the water's temperature,
conductivity, and pH several times as i t is removed from the well at
the end of each well volume. Discontinue purging when three well
volumes have been removed provided the pH and conductivity readings
have stabilized. I f the measurements have not stabilized ( i . e . , any
given pH or conductivity reading demonstrates more than a 10 percent
difference from the previous reading), further purging may be
necessary. A minimum of three readings is required.
In wells.that recover slowly, wells w i l l be sampled after purging as
soon as there is enough water in the well bore to obtain a sample.
I f the well goes to dryness during the purging process, several
options are available. The options are based on the time required
for the water-level recovery, the type of analysis to be performed,
and the type of purging and sampling equipment being used. The
option to be used for each investigation should be approved on a
site-specific basis prior to sampling. The options may include the
following:
For water-level recoveries of 0.5 to 1 hour, purge three well
volumes. Sampling shall be performed within three hours of the
f i n a l purge.
For water-level recoveries of up to eight hours, the well may
be purged early in the day. Sampling may be performed after
the well level has recovered to within 80 percent of the
original static water level measured.
• I f water-level recoveries exceed 24 hours, the well may be
purged once on one day and the samples may be collected within
24 hours on the following day.
The discharged water collected from each well purge is disposed of
as described in Chapter 12.
7. Using a decontaminated bailer, withdraw two f u l l bailers of
groundwater from the well. Dispose of these f i r s t two bailers of
sample along with the discharged well purge water as described in
the Health & Safety Plan. (Personnel handling the bailer must wear
new PVC gloves.)
8. Using the same bailer and leader line, collect groundwater samples
from the well. Record the time at the beginning and end of the
bailing. (During sample collection, the leader line and bailer
8-9
-
should not touch the ground or any objects except for the well
casing.)
9. Immediately, wearing new PVC gloves, transfer the groundwater sample
directly from the bailer to the appropriate sample containers.
A l l sample containers should be f i l l e d to the shoulder,
approximately 3/4's f u l l , except for those samples requiring
volatile organic analyses. Samples collected for volatile organics
analysis w i l l be collected f i r s t . For the collection of volatile
organic samples in VOA vials, be sure that there are no air bubbles
in the vial after i t has been capped; ensure this by turning the
v i a l upside down and tapping i t l i g h t l y .
Samples collected for dissolved metals analysis must be f i e l d
f i l t e r e d on-site at the time of sample collection. F i l t r a t i o n shall
be performed using a laboratory cleaned and dedicated 0.45 micron
f i l t e r . Particularly turbid samples may be prefiltered through a
glass fiber f i l t e r prior to the 0.45 micron f i l t e r to speed the
f i l t r a t i o n process. Samples of unfiltered groundwater w i l l also be
collected for metals analysis.
10. Collect a f i n a l sample aliquot in a disposable container and
immediately measure and record the pH, temperature, and conductivity
of that sample.
11. Immediately label, preserve i f necessary, refrigerate/ice, and log
the samples into a bound f i e l d logbook.
12. Complete the chain of custody form to accompany sample shipment.
13. Remeasure and record the standing water level in the well after
sampling.
14. Replace the protective cap on the well and lock.
Documentation
In addition to the sampling observations listed in Section 11.3, the following
observations should be documented and reported in the f i e l d logbook when
sampling monitoring wells: well purging data (see Figure 8-1), sample
characteristics, and a note as to whether the well was secured upon ar r i v a l .
A general outline of a typical data entry page of the f i e l d logbook for actual
sample collection is given in Figure 11-4.
8-10
-
FIGURE 8-2. WELL SAMPLING WORKSHEET
WELL SAMPLING WORKSHEET
Job No. Samplers Job Name
Well ID Date Sampled .Time: Start .End
. inches + 12 = . _(d)ft. Well secured upon arrival? Y/N Casing Diameter ft. Standing water (gal.) = —Depth of well from T.O.C. _
x well volumes Depth of water from T.O.C. ft.
= gallons to purge Feet of standing water .0>) ft-PIP Readings (ppm)
Standing Breathing Water = rc [(d? + 4] 00 V l u m e° -3.14IC i t )
2 +4 ] . f t ) x 7.48 gal/ft gals Well
End. Purge: Time Start. Purging method
Conductivity Temperature, (C) pH
1 well volume = . gal.
2 well volume = . gal.
3 well volume = gal.
Final volume = gal.
Bailer 1D# Sample Collection: Time Start -End
Sample Characteristics (Circle all applicable)
none sulfide fishy musty petroleum Describe odor:
colorless black brown orange red Describe color:
Describe appearance: turbid silty sand clay floaters sheen
clear multlphased foaming slimy algae
Organic Layer? Length? Samples preserved?
Comments . —
8-11
-
8.2.2 Waterloo Multilevel Well Sampling
Because the multilevel well is novel to M&E no perfected procedure exists for
sampling. However, the following may be considered a guideline. I t w i l l be
necessary to become familiar with the sampling procedure through demonstration
from a Solonist Technician.
Equipment
• Readout box to take measurements from pressure transducers
• Pump control box to operate pumps for purging and sampling
• A nitrogen tanks with regulator that w i l l reduce the pressure to
less than 300 psi
• Sample containers
pH meter
• Thermometer, non-mercury type
• Conductivity meter
Standard pH buffer solutions of pH 4.0, 7.0, and 10.0 units
Single-use KC1 conductivity calibration standard solutions
• F i ltration apparatus, 0.45 micron
Photoionization detector and/or organic vapor analyzer
Sampling Procedure
Samples shall be collected beginning with the well located in the area
suspected of least contamination (up gradient) and proceeding to the areas of
most contamination. Other factors, such as well recovery time, may also
influence the order of sample collection. The following procedure shall be
used:
1. Unlock the protective casing on the well.
8-12
-
2. Sample the air in the well head for organic vapors using a
photoionization detector or organic vapor analyzer, and record the
measurements.
3. Connect the readout box to the pressure transducers via the
alligator clips. I t is important to make sure that the proper
connections are made.
4. Connect the pump control box to the manifold taking care to connect
each tube to the proper pump controller.
5. Connect the nitrogen supply to the manifold. The pressure should be
regulated below 300 psi.
6. Wearing a new pair of PVC gloves, begin purging the well by
activating the required port pump. The actual number of well
volumes to be removed during a purging may vary depending on the
site characteristics, well design, and the chemicals or parameters
for which analysis shall be performed. At a minimum, three well
volumes should be purged from each well unless the well is pumped to
dryness. The purged volumes are estimated by discharging the purge
water into a container of known volume. During the purging of each
well volume, measure and record the water's temperature,
conductivity, and pH several times as i t is removed from the well at
the end of each well volume. Discontinue purging when three well
volumes have been removed provided the pH and conductivity readings
have stabilized. I f the measurements have not stabilized ( i . e . , any
given pH or conductivity reading demonstrates more than a 10 percent
difference from the previous reading), further purging may be
necessary. A minimum of three readings is required.
I f the well goes to dryness during the purging process, several
options are available. The options are based on the time required
for the water-level recovery, the type of analysis to be performed,
and the type of purging and sampling equipment being used. The
option to be used for each investigation should be approved on a
site-specific basis prior to sampling. The options may include the
following:
For water-level recoveries of 0.5 to 1 hour, purge three well
volumes. Sampling shall be performed within three hours of the
f i n a l purge.
• For water-level recoveries of up to eight hours, the well may
be purged early in the day. Sampling may be performed after
the well level has recovered to within 80 percent of the
original static water level measured.
• I f water-level recoveries exceed 24 hours, the well may be
purged once on one day and the samples may be collected within
24 hours on the following day.
8-13
-
The discharged water collected from each well purge is disposed of
as described in Chapter 12.
7. F i l l the sample containers from the portal tube indicated for each
sampling level. Extra care must be taken to avoid contaminating the
ends of the portal tubes. Record the time at the beginning and end
of the sampling.
A l l sample containers should be f i l l e d to the shoulder,
approximately 3/4's f u l l , except for those samples requiring
v olatile organic analysis. Samples collected for volatile organics
analysis must be collected f i r s t . For the collection of volatile
organic samples in VOA vials, be sure that there are no air bubbles
in the v i a l after i t has been capped; ensure this by turning the
v i a l upside down and tapping i t l i g h t l y .
Samples collected for dissolved metals analysis must be f i e l d
f i l t e r e d . Filtration shall be performed using a laboratory cleaned
and dedicated 0.45 micron f i l t e r . Particularly turbid samples may
be prefiltered through a glass fiber f i l t e r prior to the 0.45 micron
f i l t e r to speed the f i l t r a t i o n process.
8. Collect a f i n a l sample aliquot in a disposable container and
immediately measure and record the pH, temperature, and conductivity
of that sample.
9. Immediately label, preserve i f necessary, refrigerate/ice, and log
the samples into a bound f i e l d logbook.
10. Complete the chain of custody form to accompany sample shipment.
11. Remeasure and rerecord readings from each of the pressure
transducers.
12. Disconnect the nitrogen, the readout box and the control box.
13. Replace the protective cap on the well and lock.
Documentation
In addition to the sampling observations listed in Section 11.3, the following
observations should be documented and reported in the f i e l d logbook when
sampling monitoring wells: well purging data (see Figure 9-1), sample
characteristics, and a note as to whether the well was secured upon ar r i v a l .
A general outline of a typical data entry page of the f i e l d logbook for actual
sample collection is given in Figure 11-4.
8-14
-
8.2.3 Surface Water Sampling
Equipment
• Sample containers
• Required sample preservatives ( i f sample containers do not contain
preservatives)
• Disposable polystyrene cups for collection of f i e l d monitoring
aliquot
• pH meter
• Conductivity meter
• Thermometer
Standard pH buffer solutions of pH 4.0, 7.0 and 10.0
• Single-use KC1 conductivity calibration standard solutions
• F i l t r a t i o n apparatus, 0.45 micron
Note: For calibration of field instruments, see Section 7.2.
Sampling Procedure
To prevent cross-contamination of samples, sample collection shall start at
locations suspected of least contamination and proceed to locations of most
contamination. I f sediments are to be collected, collect surface water
f i r s t . Collect samples according to the following procedures:
1. Estimate the depth of water. ( I f a pole is to be used, wait to
perform this task u n t i l after actual sampling to avoid water
turbulence.)
2. Record the weather conditions and other on-site particulars.
3. Record the physical characteristics of the water body such as odor,
color, temperature, pH, conductivity, presence of any dead
vegetation and surface sheens, etc.
4. Make a sketch of the surface water boundaries and sampling
locations.
8-15
-
5. Photograph the sampling locations and conditions.
6. Collect a sample by immersing the sample container in the water. Do
not collect samples at the surface; instead, the sample container
should be inverted, lowered to the approximate sampling depth, and
held at about a 45-degree angle. I f the surface water is a flowing
stream, river, or brook, hold the sample container at about a
45-degree angle with the mouth of the bottle facing upstream.
Samples collected for volatile organic analysis must contain no air
bubbles in the VOA vial after i t has been capped; ensure this by
turning the vi a l upside down and tapping i t l i g h t l y . F i l l a l l other
sample containers to the shoulder.
7. Collect a f i n a l sample aliquot in a disposable container and
immediately measure and record the pH, temperature, and conductivity
of that sample.
8. Immediately label, preserve i f necessary, refrigerate/ice, and log
the samples into a bound f i e l d logbook.
9. Complete the chain of custody form to accompany sample shipment.
10. I f possible, calculate an estimate of the surface water flow ( i f
any) from a measurement of the linear cross-section flow velocity
(using a bobber and a stop watch) and an estimate of the flow
volume's cross-sectional area.
Documentation
In addition to the sampling observations listed in Section 11.3, the following
observations should be documented in the f i e l d logbook when sampling surface
water:
Time of sample collected
Description of water body, color, odor, appearance
Depth of water
Depth of sample collection for each specimen collected
Description of sampling location (e.g., l e f t bank, eddy, middle,
etc.)
8-16
-
A general outline of a typical data entry page of the f i e l d logbook is given
in Figure 11-5.
8.3 QUALITY CONTROL SAMPLES
During each sampling episode, a number of quality control (QC) samples must be
collected and submitted for laboratory analysis. The number and frequency of
the QC sample collection is outlined in Section 10.0 of the Quality Assurance
Project Plan (QAPP) specific to this investigation.
A l i s t of the types of QC samples that shall be collected along with a brief
description of each sample type is outlined in the following sections.
8.3.1 Trip Blanks
Trip blanks are collected for chemical analysis of volatile organics. The
analytical results serve as a baseline measurement of volatile organic
contamination that samples may be exposed to during transport and laboratory
storage prior to analysis.
Trip blanks are comprised of deionized water which is placed in sample
containers transported to the sample collection site, handled along with the
samples, and returned to the laboratory along with samples of water and/or
s oil collected for volatile organic analysis. The t r i p blank containers are
not to be opened in the f i e l d .
Typically, one t r i p blank is included in each shipping container for volatile
organics analysis, is stored in the laboratory with the samples, and is
analyzed by the laboratory (for volatile organics only).
8.3.2 Equipment Blanks
Equipment blanks are collected for each piece of sampling equipment used in
the collection of samples when devices other than the sample bottle i t s e l f is
required. The analysis of these blanks serves to verify the cleanliness of
the sampling equipment.
8-17
-
Equipment blanks are comprised of deionized water which is placed in sample
containers transported to the sample collection site, opened, poured into the
sampling device following equipment decontamination procedures (or pumped
through i t as in the case of sampling pumps), transferred back to the sample
bottle, and returned to the laboratory for analysis. The equipment blanks are
analyzed for the same parameters as the associated samples.
One equipment blank shall be collected per each day of sample collection or at
a frequency of ten percent of the samples collected for each media sampled,
whichever is greater. Every other equipment blank shall be submitted for
laboratory analysis.
8.3.3 Field Duplicates
Field duplicates are defined as two samples collected independently of each
other at a sampling location during a single episode of sampling. Analysis of
these duplicates provides s t a t i s t i c a l information relating to sample
v ariability and serves as a check on the precision of any sample collection
method as i t pertains to the sampled area.
Ten percent of a l l samples w i l l be collected in duplicate and submitted for
laboratory analysis. Field duplicates shall be labeled in such a manner so
that persons performing laboratory analysis are not able to distinguish
duplicates from other collected samples.
8-18
-
9.0 HYDROGEOLOGIC INVESTIGATIONS
Hydrogeologic investigations include testing and characterization of the
hydraulic properties of the aquifers at the site.
9.1 SLUG TESTS
Slug tests w i l l be conducted on a l l overburden wells to determine hydraulic
conductivity in the surfi c i a l aquifer. These w i l l be performed after sampling
is completed to avoid any possibility of sample contamination by slug test
equipment. Slug test equipment w i l l be decontaminated between wells.
The following protocol w i l l be used:
• The static water level w i l l be measured
A slug of known volume w i l l be instantaneously introduced into each
well
• The recovery of the water level in each well w i l l be measured and
recorded with time using an insitu data logger and pressure
transducer, u n t i l the water level reaches the previous static level
• The slug w i l l be instantaneously removed and the recovery of the
well recorded as above
Though not l i k e l y , i f the water table is below the top of the screen
then only slug removal w i l l be performed
The slug tests w i l l be duplicated i f necessary
The data w i l l then be plotted on semi-logarithmic paper and analyzed using
both the Hvorslev (1951) method and the Bouwer and Rice (1976) method and
comparing the results.
9.2 SURFACE HATER MEASUREMENT
Three surface water monitoring stations w i l l be installed in the wetland areas
in the vici n i t y of Holton Circle (Figure 4-1). These stations w i l l be used to
monitor changes in surface water elevations so that the groundwater recharge
potential and the groundwater/surface water relationship can be evaluated.
9-1
-
10.0 DECONTAMINATION PROCEDURES
Decontamination is the process of removing contaminants that have accumulated
on excavation equipment and sampling apparatus. Proper decontamination is
essential in minimizing the transfer of harmful materials into clean areas, in
the prevention of cross-contamination between samples due to the use of
improperly decontaminated field/sampling equipment, and in protecting workers
from hazardous substances.
10.1 EQUIPMENT
All equipment involved in site investigation activities shall be
decontaminated prior to leaving the site. The general outline for such
decontamination procedures is included in the following sections.
10.1.1 Non-Sampling Field Equipment
Non-sampling f i e l d equipment is any equipment that may potentially contact a
sample area. A l l equipment and power tools used as non-sampling equipment
( i . e . , d r i l l i n g equipment, well casings and screens, backhoes, dredges,
augers, etc.) shall be decontaminated before and following usage, as well as
prior to removal from the site. Large and heavy d r i l l i n g equipment shall be
steam cleaned. Light or small equipment such as hand tools shall be rinsed
with tap water, scrubbed with a water/mild soap solution, and rinsed again
with tap water, or shall be steam cleaned. Al l equipment decontamination
shall be performed at a decontamination station specified in the site specific
Health and Safety Plan.
A ll d r i l l i n g and other non-sampling equipment shall be handled to prevent
cross-contamination in the f i e l d by the use of sawhorses and plastic ground
cloths. No equipment shall be placed directly on the ground.
10-1
-
10.1.2 Sampling Equipment
Prior to f i e l d use, the c