ffc forms, implementation plans, reviewer performance ... · 12/12/11 1 peer review guidance update...

36
12/12/11 1 Peer Review Guidance Update FFC Forms, Implementation Plans, Reviewer Performance, Impact of QCM on Peer Review and Other Guidance December 12, 2011 Peer Review Program Presenters AICPA Peer Review Program Staff Sue Lieberum, Senior Technical Manager Rachelle Drummond, Technical Manager 2

Upload: buianh

Post on 12-Apr-2018

226 views

Category:

Documents


3 download

TRANSCRIPT

12/12/11

1

Peer Review Guidance Update FFC Forms, Implementation Plans, Reviewer Performance, Impact of QCM on Peer Review and Other GuidanceDecember 12, 2011

Peer Review Program

Presenters

AICPA Peer Review Program Staff

• Sue Lieberum, Senior Technical Manager

• Rachelle Drummond, Technical Manager

2

12/12/11

2

Peer Review Program

Objectives

The webinar will inform participants of the recent changes to peer review guidance (approved at August and October 2011 PRB meetings) as well as provide you with an opportunity to learn about and weigh in on the guidance that is being developed.

Understand the peer review requirements for completion of FFC Forms, the impact revised guidance for implementation plans, reviewer performance, and QCM will have on peer reviews and understand the basis for developing guidance.

3

Peer Review Program

Topics to be Covered

Finding for Further Consideration (FFC) Forms

Implementation Plans

Reviewer Qualifications, Responsibilities and Performance

Peer Review Focus Areas

On the Horizon

Peer Review Hotline

Upcoming Peer Review Events

4

12/12/11

3

Finding for Further Consideration (FFC) Forms

Revisions effective January 1, 2012

Peer Review Program

FFC Forms

Used on both System Reviews and Engagement Reviews

Firm Responses – comprehensive, genuine, feasible

Previously requested:• Whether the firm agrees with the finding and will

implement the reviewer’s recommendation

• A description of the firm’s plan, including timing, to address the finding

6

12/12/11

4

Peer Review Program

FFC Forms

FFC Form revised for firm’s responses to include:• How the firm intends to implement the reviewer’s

recommendation

- Or alternative plan if the firm does not agree with the recommendation

• The person(s) responsible for implementation

• The timing of the implementation

• Additional procedures to ensure the finding is not repeated in the future, if applicable.

Example: The engagement partner for all ERISA engagements will take 8 hours of ERISA CPE and the Quality Control (QC) partner will be responsible for ensuring the CPE is obtained by December 31, 2011. The QC partner will also monitor CPE for all A&A personnel to ensure compliance with firm policies and procedures.

7

Peer Review Program 8

12/12/11

5

Peer Review Program

Questions

9

Implementation Plans

Revisions effective January 1, 2012

12/12/11

6

Peer Review Program

Implementation Plans

Finding vs. Deficiency

IPs should not be used:• To correct a finding communicated on an FFC form that should

be a deficiency in the report.

• To make up for poorly constructed recommendations and responses on the FFC form.

• As a 4th level of reporting

If it is determined that a severe IP is necessary to correct the finding, RABs should ensure the conclusion of finding vs. deficiency was accurate.

11

Peer Review Program

Implementation Plans

If finding does not rise to level of deficiency• RAB considers whether firm’s response is comprehensive,

genuine, and feasible.

Repeat Finding• If the firm’s previous response was the same and it did not work

to correct the finding, it should not be deemed as comprehensive, genuine, and feasible.

• Interpretation 83-2

• Supplemental Guidance (Section 3300)

Overarching Principle – if the firm’s response properly addresses the issue, the RAB generally should allow the firm to proceed without additional intervention.

12

12/12/11

7

Peer Review Program

IPs Allowable for a System Review

Finding Allowable plan(s) to be performed as soon as reasonably possible

Engagements not performed or reported on in accordance with professional standards in all material respects Initial finding on must select industry Repeat findings for any industry

Require the firm to hire an outside party acceptable to the RAB to perform preissuance or postissuance reviews of certain types or portions of engagements focusing on the areas identified in the finding Require the firm to hire an outside party acceptable to the RAB to review the firm’s internal monitoring or inspection report

Repeat findings Require members of the firm to take specified types of and amounts of CPE Require firm to submit monitoring or inspection report to the RAB

Failure to possess applicable firm license(s)

Submit proof of valid firm license(s)

13

Peer Review Program

IPs Allowable for an Engagement Review

Finding Allowable plan(s) to be performed as soon as reasonably possible

Repeat findings Require members of the firm to take specified types of and amounts of CPE Require firm to submit monitoring or inspection report to the RAB

Failure to possess applicable firm license(s)

Submit proof of valid firm license(s)

14

12/12/11

8

Peer Review Program

Implementation Plans – Other Actions

Guidance in exhibits 4-2 and 5-2 must be followed• Even in instances where the same finding is included on more

than two reviews

- Consider more rigorous implementation plan

- Example: require 24 hours of CPE or change the nature of the required courses.

- Example: require both CPE and submission of monitoring report to the RAB

Actions Not Allowed• Team captain revisit

• Monitoring performed by an outside party

• Accelerated review

Compliance monitored during oversight

15

Peer Review Program

Questions

16

12/12/11

9

Reviewer Qualifications, Responsibilities and Performance

Effective January 1, 2012

Peer Review Program

Topics to be Covered

Overview of Required Reviewer Performance

Meeting and Maintaining Reviewer Qualifications

Responsibility to Perform Timely and Professional

Pattern of Poor Performance

Reviewer Feedback

Other Communications

Serious Weakness

Reviewer Performs Reviews for Multiple AEs

18

12/12/11

10

Peer Review Program

Topics to be Covered

Egregious Performance

Allegation or Investigation

Limitations or Restrictions

Oversight at the Reviewer’s Expense

Reviewer Monitoring Report

Board Hearing Panels

Rules of Procedure for Reviewers

19

Peer Review Program

Overview of Required Reviewer Performance

• Qualifications

• Responsibilities

• Failure to meet and maintain qualifications and responsibilities

20

12/12/11

11

Peer Review Program

Qualifications

Meeting and Maintaining Reviewer Qualifications

- Meet

- Maintain

- Monitor

21

Peer Review Program

Procedure When Reviewer is Ineligible

Confirmation

Notification

Restriction

Appeal

Release

Multiple Times

22

12/12/11

12

Peer Review Program

Committee Considerations

Scheduled but not commenced

Commenced but fieldwork is not complete

Commenced and fieldwork is complete

Submitted to Committee

Accepted but acceptance letter not issued

Accepted and acceptance letter sent

23

Peer Review Program

Peer Reviewer Decision Model

AE

det

erm

ines

sta

tus

of

op

en r

evie

ws

Review scheduled

Reschedule

Oversight

Review commenced

Reschedule

Oversight

New review

Other

Fieldwork completed

Oversight

Other

Review accepted

If within retention period consider oversight

If outside retention period notify affected firms

24

12/12/11

13

Peer Review Program

Questions

25

Peer Review Program

CASE #1

When a reviewer fails to meet one of the qualifications to be a reviewer and receives notification through an Ineligibility Letter, the reviewer can:

a. Continue to perform reviews previously scheduled

b. Continue to schedule reviews

c. Tell the firm they should be granted an extension

d. None of the above

The answer is d.

26

12/12/11

14

Peer Review Program

Timely and Professional Manner

Open Review

Responsiveness to Requests

Resume Verification

27

Peer Review Program

Procedure for Suspending When Not Timely

First Letter Contact Reviewer Suspension

28

12/12/11

15

Peer Review Program

Suspension Procedure for Not Submitting Resume Documentation

Initial Request

Warning Letter

Contact Reviewer Suspension

Request National 

Suspension

29

Peer Review Program

Reviewer Appeal Process

Reviewer May Appeal to the Board

Committee forms panel

3-member minimum Appoint chair Schedule &

conduct meetingCommunicate

decision

Create opportunity to present sides

30

12/12/11

16

Peer Review Program

Committee Considerations

Reviewer is not timely and professional

Reviewer fails to submit appropriate documentation to support resume codes

31

Peer Review Program

Questions

32

12/12/11

17

Peer Review Program

CASE #2

When a reviewer is suspended for not submitting workpapers timely, the reviewer can still perform reviews he/she was previously approved to perform.

a. True

b. False

The answer is a.

33

Peer Review Program

Feedback

Pattern or Poor Performance• Reviewer feedback

- Weaknesses in the reviewer’s performance

- Remedial and educational

- Not punitive

- Used to monitor future performance

- Shared by all administering entities

- Pattern could lead to board action

34

12/12/11

18

Peer Review Program

Feedback• Comes from PRC

• Must be signed by member of PRC

• Maintained in reviewer’s file

Other Communications• Can come from technical

reviewer

• E-mail, memo

• Not maintained in reviewer’s file

Feedback vs. Other Communications

35

Peer Review Program

Serious Weakness in Performance

Performance deficiencies occur when• Serious weaknesses in a reviewer’s performance on

a particular review, or

• A pattern of weaknesses substantiated by multiple feedback forms and/or suspensions.

Performance Monitoring Letter

Performance Deficiency Letter

36

12/12/11

19

Peer Review Program

Procedure for Multiple AE’s

Feedback

AE 1 Issues Monitoring

Letter

Reviewer Performs

Reviews in Multiple AE’s

Performance Does Not Improve

Discussion & Agreement 

Between AE’s

AE 2 Issues Performance 

Letter

37

Peer Review Program

Performance Deficiencies

Bypassing the Performance Monitoring Letter

38

12/12/11

20

Peer Review Program

Reviewer Appeal Process

Reviewer May Appeal to the Board

Committee forms panel

3-member minimum Appoint chair Schedule &

conduct meetingCommunicate

decision

Create opportunity to present sides

39

Peer Review Program

Committee Considerations

Performance deficiency letter has been issued within the last 30 days and has not been signed by the reviewer

Performance deficiency letter has been signed by the reviewer

40

12/12/11

21

Peer Review Program

Peer Reviewer Decision Model

AE

det

erm

ines

sta

tus

of

op

en r

evie

ws

Review scheduled

Reschedule

Oversight

Review commenced

Reschedule

Oversight

New review

Other

Fieldwork completed Oversight

Review accepted

If within retention period consider oversight

If outside retention period notify affected firms

41

Peer Review Program

National Restriction

FeedbackAE 1 Issues Monitoring

Letter

Reviewer Performs

Reviews in Multiple AE’s

Performance Does Not Improve

Discussion & Agreement

Between AE’s

AE 2 Issues Performance

Letter

Performance Does Not Improve

Removal Letter Board Consideration

42

12/12/11

22

Peer Review Program

Egregious Performance

• Evidence, facts and circumstances must be weighed

• If deemed egregious, board may take action against reviewer

• Feedback, monitoring and deficiency letters not required

43

Peer Review Program

Committee Considerations

Scheduled but not commenced

Commenced but fieldwork is not complete

Commenced and fieldwork is complete

Submitted to Committee

Accepted but acceptance letter not issued

Accepted and acceptance letter sent

44

12/12/11

23

Peer Review Program

Peer Reviewer Decision Model

AE

det

erm

ines

sta

tus

of

op

en r

evie

ws

Review scheduled

Reschedule

Oversight

Review commenced

Reschedule

Oversight

New review

Other

Fieldwork completed Oversight

Review accepted

If within retention period consider oversight

If outside retention period notify affected firms

45

Peer Review Program

Allegation/Investigation

Obligation of reviewer and reviewing firms to notify the relevant administering entity of allegation or investigation from• Regulatory, monitoring, enforcement bodies or others

• Related to the conduct of accounting, audit or attestation engagements performed by the reviewer

Does not automatically make reviewer ineligible to perform reviews• Administering entity may consider oversight

46

12/12/11

24

Peer Review Program

Limitations/Restrictions

Obligation of reviewer and reviewing firms to notify the relevant administering entity of limitation or restriction from• Regulatory, monitoring, enforcement bodies or others

• Related to the reviewer or reviewing firm’s ability to practice

Individual may not serve as a reviewer• Begins on the date he/she receives notification

• Must withdraw immediately from peer review

• Remains in effect until limitation/restriction is removed by regulatory body

One or more of a firm’s office• Board will consider specific circumstances

47

Peer Review Program

Questions

48

12/12/11

25

Peer Review Program

CASE #3

When a technical reviewer provides remedial guidance to the reviewer in an email, this is considered:

a. Reviewer Feedback

b. Other communication which should be maintained in the reviewers file

c. Other communication which should not be maintained

The answer is c.

49

Peer Review Program

CASE #4

Santa Klass has received a performance monitoring letter from AE #1. Santa’s next review is performed on a review that AE #2 administers. The committee of AE #2 has performed oversight on this review. The oversight report indicates continual performance problems as outline in the performance monitoring letter. AE #2 should issue another performance monitoring letter.

a. True

b. False

The answer is b. 50

12/12/11

26

Peer Review Program

CASE #5

Due to poor performance, a restriction is placed on a reviewer. The restriction provides that the reviewer have only one review open at a time. The reviewer disagrees with the restriction and appeals to the committee. While waiting for the appeal to take place, the restriction should be lifted until the appeal process has been completed.

a. True

b. False

The answer is b.

51

Peer Review Program

Oversight at Reviewer’s Expense

Same AE

2 Oversights in 2

Calendar Years

Oversight at Reviewer’s

Expense

Reviewer Refuses to

Pay

Fee Dispute?

If no, submit to board

52

12/12/11

27

Peer Review Program

Reviewer Monitoring Report

The AE that initially requested the reviewer be added to the reviewer monitoring report

The reviewer’s name, firm, and member number

The date of deficiency letter(s) or suspension letter(s)

The AE that issued the letter(s)

Deficiency type

Reviewer status

Restriction

Whether the action was ratified by the board

The date that the restriction was removed, if applicable

53

Peer Review Program

SHARE

54

12/12/11

28

Peer Review Program

Board Hearing Panel

Hearings are ordinarily held for

• Appeals for ineligibility

• National ratification of a corrective action

• Appeals of a committee decision

• Reviewers not cooperating (for example, not signing the performance deficiency letter)

• Request for removal from the list of qualified reviewers

Panel decisions may be appealed

55

Peer Review Program

Rules of Procedures for Reviewers

Similar to Rules of Procedures for Firms

Provides Guidance to Reviewers and AE’s

Hearing Panels

Ad Hoc Committees

Review Panels

AICPA.org

56

12/12/11

29

Peer Review Program

Three Important Points to Remember

Transparency

Fair Procedures

Follow the Guidance

57

Peer Review Program

Questions

58

12/12/11

30

Peer Review Focus Areas

Peer Review Program

Topics to be Covered

Impact of Quality Control Materials (QCM) on Peer Reviews

Noncompliance with SSARS No. 19

Other Resume Code Clarification

Mentor Program

60

12/12/11

31

Peer Review Program

Impact of Quality Control Materials (QCM) on Peer Reviews

QCM – New Guidance Effective January 1, 2012

QCM are a Significant Peer Review Consideration

Peer Review Standards Interpretations 42-2 and 42-3

New Checklist Questions

• Summary Review Memorandum

• Quality Control Policies and Procedures (QCPP) Checklist

• Guidelines for Review of QCPP Checklist

61

Peer Review Program

Noncompliance with SSARS No. 19

Preliminary findings – Decrease in Pass reports in Engagement Reviews

Increase in Pass with Deficiency and Fail reports in Engagement Reviews due to noncompliance with SSARS No. 19

Multiple Instances of Non-Compliance with SSARS No. 19

62

12/12/11

32

Peer Review Program

Other Resume Code Clarification

The “Other” reviewer resume code is defined as:• Supervising one or more accounting or auditing

engagements or carrying out the quality control functions for a firm when the peer reviewer is neither a partner nor a professional employee of the firm.

Performing post issuance reviews for other firms does not qualify

63

Peer Review Program

Mentor Program

Team captain candidates may forego the second day of the restructured “How To” course with significant participation as a team member in a System Review.

Significant Participation – obtained when an approved and qualified team captain “Mentor” oversees the candidate perform virtually all team captain responsibilities.

Available May 2012

Become a Mentor Now - apply through Peer Review Home Page

64

12/12/11

33

On the Horizon

Peer Review Program

Topics to be Covered

Matter for Further Consideration Form (MFC Form)

System Review Scope and Must Selects

Recall Guidance

Conference Agenda

66

12/12/11

34

Peer Review Hotline

Peer Review Program

Peer Review Hotline

Technical Staff(919) 402-4502, option 3

[email protected]

Administration and Operations Staff(919) 402-4502, option 2

[email protected]

68

12/12/11

35

Peer Review Program

Questions

69

Peer Review Program

Upcoming AICPA Events

Peer Review Board Meetings

• January 20, 2012

• May 8, 2012

• August 8, 2012

• October 2012 – date TBD

Peer Review Conference

• August 5-7, 2012

• Indianapolis, Indiana at the JW Marriott

70

12/12/11

36

Thank you for participating!