Fermilab Master Plan

Fermilab Master Plan

Overview Presentation

Mission Support Organization

Planning Winter Workshop

Feb 20, 2013

Page 2: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Fermilab Master Plan

Integrating the new vision for

the Intensity Frontier facilities

and other Science with a sound strategy for

infrastructure and support facility development

Page 3: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Fermilab Master Plan

In order to help define and best use all laboratory resources to most effectively and efficiently meet Fermilab’s Plan for Discovery, the laboratory is developing a Fermilab Campus Master Plan (FCMP) for the next 20 years. The document will guide the development of modern, productive, and efficient laboratory facilities that will enable the laboratory to fulfill its mission of advancing humankind’s understanding of matter and energy by providing facilities for particle physicists from across the country and around the globe. The FCMP will build on the laboratory’s rich scientific and aesthetic heritage to develop capable, flexible, energy efficient facilities appropriate for 21st century science.

Executive summary

Page 4: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Fermilab Master Plan

Plan Objectives

The Fermilab Campus Master Plan is a focused plan for the next 10 years, while providing a brief outlook into a 20 year time horizon of the laboratory. The building priorities for the first 10 years are:Modernization : Replacement of inadequate and antiquated

fabrication, assembly and machining facilities dating back to the beginning of the laboratory. Development of office, technical, lab and meeting spaces that are flexible, provide efficient us of space and energy, and meet the needs of current and future engineers, scientists and other users.Consolidation: Replacement of the current scattered, obsolete and

inefficient network of support buildings with modern consolidated buildings that meet the needs of the next era of science.

Page 5: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Fermilab Master Plan

Centralization: Development of a vision for a vibrant and interconnected central campus region anchored by Wilson Hall. New consolidated buildings will be planned in proximity to Wilson Hall and other major central region buildings. Re-imagined vehicular, pedestrian and bicycle pathways will be designed to connect these buildings.Aesthetic Enhancement: Development of principles that will guide the next era of the planning and design of the Fermilab Campus and buildings. Also addressed will be guidance regarding landscaped design, signage and way finding. Sustainability: Development of building designs and site features that meet DOE guiding principles for sustainability.

Plan Objectives

Page 6: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Fermilab Master Plan

A second feature of the plan will be the documentation of the Fermilab Campus and its facilities and systems as they related to the current, near-term and long term scientific program. The study will also briefly address known facility needs beyond the next 10 years, provide a baseline for the yearly update of the master planning documents.

Executive Summary

Page 7: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Fermilab Master Plan

The Fermilab Campus Master Plan (FCMP) project consists of the creation of a site-wide master plan to guide the development of the physical facility. The FCMP will propose new buildings, site elements, and utility systems for the Fermilab campus over a time period fro the present to the 2020’s and beyond, with a sharper focus on the next 10 years. The purpose of the FCMP is to facilitate the efficient and effective fulfillment of the laboratory’s scientific mission.

Brief Description of the Project

Page 8: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Fermilab Master Plan

The Plan will create a forward looking framework for designing in detail support facilities and removing existing, obsolete facilities. The plan will integrate with (but not include the design of) currently understood concepts for planned experimental facilities to be developed during the time period. Additionally, the plan will document know utility system deficiencies and propose solutions that will integrate the new and existing experimental facilities, as well as existing and proposed support facilities.

Brief Description of the Project

Page 9: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Fermilab Master Plan

The outcome and benefits of the FCMP will be the creation of document that will assist Fermilab Management, the Department of Energy, and other stakeholders in delineating the scope and design concepts for building construction, site layout and utility system improvements. It will reside alongside the Plan for Discovery, and the plans for the major experiment construction initiatives as a tool to define budget and funding plans for the defined time horizon.

Plan Outcomes and Benefits

Page 10: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Fermilab Master Plan

Project 1/Industrial Facilities Consolidation

The Fermilab Technical Division is experiencing a severe lack of high quality, premium industrial space,

In addition, it has been a longstanding necessity for the laboratory to consolidate antiquated machine shop facilities into modern advanced manufacturing environments.

This proposed Industrial facility will replace a network of over many scattered and obsolete and inadequate buildings, dating to the beginning era of the laboratory

Many of these buildings were existing single family residences converted for lab use. Others are pre-engineered pole buildings.

In order to continue to maintain our competitive edge in, and to gain momentum in, the current and future highly competitive technology driven world, we must have the facility described as we move forward.

Page 11: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Fermilab Master Plan

Project 2/ Integrated Engineering Research Building

The purpose of the Integrated Engineering Research Center is to consolidate PPD, AD assembly space, lab space, meeting space, and office space into a new building in proximity to Wilson Hall.

The design and location of the building will promote integration of the diverse engineering disciplines

Office space in the building will accommodate engineers and technicians that support the HEP research program at Fermilab.

Meeting space will be designed to encourage interdisciplinary communication among engineers and scientists.

Lab space will be used for detector R&D, prototyping, and to operate test stands before and during experiment operations.

Assembly space will be used to build and test detector systems, and will be used for systems integration prior to installation in an experimental hall.

Page 12: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Fermilab Master Plan

Project 3/ Wilson Hall 2.0

Upgrade of the existing 40 plus year old building.

Secure its place as the hub of Fermilab for the next era of science.

Perform a sustainable building conversion; windows, mechanical and plumbing systems.

Plan for more flexible, easily adaptable and changeable office construction system.

Meet ADA requirements throughout.

Page 13: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Fermilab Master Plan

Project 4 / Central Campus

Gaol of developing a vibrant and interconnected central campus region anchored by Wilson Hall. Study location of other projects with relation to their proximity Wilson hall as part of an integrated planStudy parking structures or other means to bring parking closer to buildingsStudy vehicular circulation in the region with a view towards re-imagined vehicular, pedestrian and bicycle ways will be designed to connect areas in the central region

Page 14: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013
Page 15: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Central Campuses

Page 16: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Site Organization

WH Wilson Hall Centrally located on the Fermi Site

Supporting facilities clustered together orbiting around Wilson Hall

Industrial Center

LabA-F

TD

Lab 8

PPD

Page 17: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Site Organization

WH

Industrial Center

LabA-F

TD

Lab 8

PPD

Study the “Central Campus Zone” and its spatial/work relationships with the supporting facilities on site

Study outdated facilities on the site periphery and their work relationships with Wilson Hall

.5 miles 1.0 miles 1.5 miles 2.0 miles

Page 18: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

WH

Industrial Center

LabA-F

TD

Lab 8

PPD

.5 miles 1.0 miles 1.5 miles 2.0 miles

Page 19: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

WH

Industrial Center

LabA-F

TD

Lab 8

PPD

Consolidate the footprints

to maximize the efficiency at each operation

.5 miles 1.0 miles 1.5 miles 2.0 miles

Page 20: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

WH

Industrial Center

LabA-F

TD

Lab 8

PPD

Consolidate the footprints

to maximize the efficiency at each operation

.5 miles 1.0 miles 1.5 miles 2.0 miles

Page 21: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

WH

Industrial Center

Next study appropriate central campus locations for these spaces and functions.

.5 miles 1.0 miles 1.5 miles 2.0 miles

Page 22: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

WH

Industrial Center

.5 miles 1.0 miles

• With these functions centralized we can create a strong central campus and increased sense of community

• Additional we can improve the working proximity between all and while promoting pedestrian traffic between the buildings

Page 23: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

WH

Industrial Center

.5 miles

Developing a Central Area

Page 24: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Developing a Central Campus

How do we centralize and bring the campus

together?

Page 25: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

.5 miles.25 miles

.33 miles

Page 26: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

First we can zero in on the general parameters of “Central Campus”

.5 miles.33 miles

.25 miles

Page 27: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Wilson Hall North Strategy

.5 miles.25 miles

.33 miles

Page 28: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Industrial Area Strategy

.5 miles.25 miles

.33 miles

Page 29: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Beyond the Berm Strategy

.5 miles.25 miles

.33 miles

Page 30: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Westward

.5 miles.25 miles

.33 miles

Page 31: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

.5 miles.25 miles

.33 miles

East West Strategy

Page 32: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

Study work and building relationships in order to develop of strategy that ties the main core together.

Analyze advantages and disadvantages to each location

.5 miles.33 miles

.25 miles

Page 33: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013

.5 miles.25 miles

.33 miles

Page 34: Fermilab Master Plan Overview Presentation Mission Support Organization Planning Winter Workshop Feb 20, 2013