FERDINAND T. DAY ELEMENTARY SCHOOL
GYM ADDITIONCommunity Meeting
01 Introductions02 Site Analysis / Existing Conditions03 Proposed Design04 Construction Impacts05 Next Steps06 Q & A
AGENDA
01 Introductions
Our Team
Site Analysis02
Existing Site Diagram
Proposed Site Diagram
Project Goals1. Provide larger gym than the
current physical activity space and a new stage which will serve the entire school and community events.
2. Provide permanent enclosed connection between school and playground.
3. Add more storage space for gym, stage and school.
4. Fit new gym addition design within the existing context.
03 Proposed Design
Building DiagramA. Existing School EntranceB. Gym Egress Stair/ After
Hours Entrance C. ADA Accessible/ after
Hours Entrance
Plan Notes Legend
D. Existing Garage Entrance
D
CB
AExisting parking garage
Existing school
123456R
Floor Plan: Level 1
EXISTING SCHOOL
A
EXISTING PARENT DROP-OFF TO REMAIN
B
Notes Legend
A. Egress StairB. Current Physical Activity
SpaceC. After hours stairD. Pedestrian entrance to
garageE. Existing ADA accessible
elevatorsF. DumpstersG. DeliveriesH. Gym above
CD
G
123456R
Floor Plan: Level 3
AFTER HOURS STAIR
EGRESS STAIR
EXISTING SCHOOL
123456R
Program Comparisons
1. Existing physical activity space: 3,200 gsf: 14’ high
2. New Gym Space: 4,500 gsf: 25’ high
3. Existing multi-purpose platform:180 gsf: 8’-6” high
4. New Stage: 665 gsf: 20’ high
Existing MaterialsA B C A. Brick
B. Metal PanelsC. Sun Shades
Notes Legend
Fiber Cement Panels:
East Elevation
B
A
C
D
GarageSchool
A. Sloped TPO roofB. Angled Fiber Cement Panels to match brickC. Columns clad in concreteD. Steel Frames
E
E. Flat Fiber Cement Panels to match school additionF. Storefront windows w/ sunshades
Notes Legend
F
South ElevationA. Sloped TPO roofB. Angled Fiber Cement Panels to match brickD. Steel Frames F. Storefront windows w/ sunshades
Notes Legend
BAD
School
FD
West Elevation A. Sloped TPO roofB. Angled Fiber Cement Panels to match brickC. Columns clad in concreteD. Steel Frames E. Flat Fiber Cement Panels to match school additionF. Storefront windows G. Mechanical Screen
Notes Legend
C
AB
Garage School
FG
D
E
North Elevation A. Sloped TPO roofB. Angled Fiber Cement Panels to match brickC. Columns clad in concreteD. Steel Frames E. Flat Fiber Cement Panels to match school additionF. Storefront windowsG. Mechanical ScreenH. Guardrail
Notes Legend
BAD
Garage
EGF
C
H
Playground
04 Construction Impacts
Impacts during construction
• The school and playground will remain open while school is in session.
Safety fences will be put in place for the duration of construction to keep
the students and staff safe and separate from construction activity.
• New alternatives for the parent drop-off / pick-up loop are being explored
together with ACPS and the city to determine the best options.
• New alternatives for the deliveries and dumpster access are being
explored together with ACPS and the city to determine the best options.
• General Contractor will work closely with school to coordinate activities to
support school operations.
Next Steps05
• Next Community Meeting – coming late winter/early spring 2020
• Design completed and submitted to City for Building Permit – February, 2020
• Construction begins – Summer, 2020
• Substantially complete – Winter/Spring, 2021
Next Steps
Questions?06