federal agency update - a public real estate symposium

44
Federal Agency Update - A Public Real Estate Symposium Las Vegas, Nevada January 26, 2010 Procedures Guide for Right of Way Cost Estimation and Cost Management

Upload: emele

Post on 04-Feb-2016

29 views

Category:

Documents


0 download

DESCRIPTION

Federal Agency Update - A Public Real Estate Symposium. Procedures Guide for Right of Way Cost Estimation and Cost Management. Las Vegas, Nevada January 26, 2010. NCHRP 8- 49 (2). - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Federal Agency Update - A Public Real Estate Symposium

Federal Agency Update - A Public Real Estate Symposium

Las Vegas, NevadaJanuary 26, 2010

Procedures Guide for Right of Way Cost Estimation and Cost Management

Page 2: Federal Agency Update - A Public Real Estate Symposium

NCHRP 8- 49 (2)

Stuart Anderson Texas A&M Keith Molenaar Univ. Colorado Cliff Schexnayder Del E. Webb School of Const., Arizona State U.

Page 3: Federal Agency Update - A Public Real Estate Symposium

Outline• Background

• Methodology

• Data Collection & Results

• Issues

• Procedure Guide

• Discussion

Page 4: Federal Agency Update - A Public Real Estate Symposium

BackgroundState highway agencies problems with

project cost escalation.

Phase I of NCHRP Project 8-49 Focused on cost escalation relative

to general project cost estimating Product - Guidance, Report 574,

focuses on estimating strategies, methods, & tools

Page 5: Federal Agency Update - A Public Real Estate Symposium

NCHRP Report 574Guidance for

Cost Estimation and Management for Highway Projects During Planning,

Programming, andPreconstruction

http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_574.pdf

Page 6: Federal Agency Update - A Public Real Estate Symposium

Targeted – Right of Way Cost estimation and Cost estimation management

Phase II of NCHRP 8-49

Page 7: Federal Agency Update - A Public Real Estate Symposium

NCHRP Report 625

Procedures Guide forRight-of-Way Cost Estimation

and Cost Management

http://onlinepubs.trb.org/onlinepubs/nchrp/

nchrp_rpt_625-2.pdf

Page 8: Federal Agency Update - A Public Real Estate Symposium

NCHRP Report 625Procedures Guide for

Right-of-Way Cost Estimationand Cost Management

This ROW Guidebook includes content from the accompanying project Research Report 132 and the Estimating Guide 574

Page 9: Federal Agency Update - A Public Real Estate Symposium

NCHRP Web-Only Document 132

Right of Way Methods and Tools to Control Project Cost Escalation

http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_w132.pdf

Page 10: Federal Agency Update - A Public Real Estate Symposium

Research Objective

Develop inclusive right-of-way cost estimation and cost estimation management procedures based on literature and current practice, that integrates with the cost estimate steps documented in NCHRP Report 574

Page 11: Federal Agency Update - A Public Real Estate Symposium

FrameworkPhase I Implications Project development phases General project cost estimation

& estimate management steps Cost estimating & cost

management flowcharts Tool appendix approach

Page 12: Federal Agency Update - A Public Real Estate Symposium

FrameworkImpact of Phase I on Phase II Focus on creating a ROW Cost

Estimating & Cost Management Procedures Guide – a “how to”

Create more detailed processes for cost estimating & cost management for ROW to support procedure guide

Page 13: Federal Agency Update - A Public Real Estate Symposium

FrameworkImpact of Phase I on Phase II

Use some Phase I tools but created additional tools focused on ROW using same format and structure as in the

NCHRP Report 574

Page 14: Federal Agency Update - A Public Real Estate Symposium

Data Collection

1. Literature review

2. On-site interviews Interview Protocol

Six areas of interest that focused on different aspects of the cost estimation & estimate management process

Page 15: Federal Agency Update - A Public Real Estate Symposium

Data Collection Interview Process Who? SHAs and other organizations that

acquire ROW Central Office and Region/District

perspectives How? Ask questions relative to project

development phase

Page 16: Federal Agency Update - A Public Real Estate Symposium

Data CollectionDocuments collected

– ROW manuals

– Unique tools used in practice (i.e. cost estimating systems, estimate documents, spreadsheets)

Early flowchart feedback

Page 17: Federal Agency Update - A Public Real Estate Symposium

Data Analysis

Review of Practices Critical issues to ROW cost

estimation Successful practices and

tools

Page 18: Federal Agency Update - A Public Real Estate Symposium

Data AnalysisFlowchart techniqueData subdivided into four categories: Inputs (primary and secondary)

Process steps

Outputs

Decisions and loops(cycles within the process)

Page 19: Federal Agency Update - A Public Real Estate Symposium

LimitationsSmall sample size

Differences between agencies: Large verses small

Organizational make-up ― centralized verses decentralized

Project development phases

Terminology and acronyms

Page 20: Federal Agency Update - A Public Real Estate Symposium

ResultsProblem Areas• Damages • Condemnations• Appreciation & market conditions• Risk analysis & contingency• Early scope definition• Estimating tools• Estimator experience & knowledge

Page 21: Federal Agency Update - A Public Real Estate Symposium

Right of Way Issues Current practices lack structure and

organization.

Communication between ROW personnel and project development team needs to improve.

The ROW estimation is highly dependent on scope definition.

Page 22: Federal Agency Update - A Public Real Estate Symposium

Right of Way Issues ROW planning estimates typically

not prepared by ROW staff.

SHAs do not utilize risk analysis and the application of contingency to all estimates.

Cost estimation management and cost control are underutilized.

Page 23: Federal Agency Update - A Public Real Estate Symposium

PROGRAMMING

ROW Project Development:· Define Project Scope:

Identify ROW area and/or rough parcels needed (impacted)

· Document ROW Required on rough conceptual plan or aerial photo (schematic)

Determine Baseline ROW Estimate Basis· Review ROW required as documented per

project type and scope· Request clarification of uncertain ROW

requirements· Document requirements in project estimate

file

Approve & Communicate Baseline ROW Cost Estimate· Obtain management approval· Authorize communication internally and

externally

Determine Baseline ROW Risk & Set Contingency· Identify risks· Assess and analyze risks· Assign contingency· Document risk analysis and basis for

contingency· Compile baseline ROW cost estimate (base

plus contingency)

Review Baseline ROW Cost Estimate· Determine level of review· Review estimate basis & assumptions· Verify completeness and Cost Data· Review Contingency amount based on

identified risks

Baseline ROW Cost Estimate

To PreliminaryDesign

ScopeDevelopment

ROW Requirements

Input from Environmental,

Utilities, Railroad

Prepare Baseline ROW Base Estimate· Review estimate basis· Document observations from field visit · Calculate potential area of land by land type· Develop cost basis for each ROW element· Convert cost basis to estimate for each

element· Document estimate assumptions including

uncertain items· Summarize all estimate elements for total

ROW base cost

Real Estate Appreciation

Rate

Land Market Values

Field Visit by Estimator (Improvements,

Damages, Existing Conditions, etc.)

Condemnation RateHistorical

Data

- Removal of Improvements- Relocation Assistance- Support Costs

Future Development (Community

Planning)

Represents the dynamic nature of the milestone dependant on the practices

of the State highway agency.

*

Priority Program≤ 10 years

*

FromPlanning

Modifications

Update Estimate Basis(Scope/

Location)

Prepare Base Estimate

Perform Risk Analysis

(Set Contingency)

Review Total Cost Estimate

Historical Data Input from 3rd Parties

Input from Disciplines

Market Conditions

Baseline Estimate

TrafficRoadwayStructures

ROWEnvironmentalConstruction

Utilities

Project Scoping5-25% Design

Project Complexity

Obtain Appropriate Approvals

Communicate Approval

Macro Environment

Project Estimate

P

RE

LIM

IN

AR

Y D

ES

IG

N

Authorize Project

*

PR

OG

RA

MM

IN

G

Database

Document

Step

Input

Milestone

Pha

se

Legend

Decision

COST ESTIMATING AND COST ESTIMATING MANAGEMENT

To Final Design

ROWResearchResults

ProceduresGuide

Page 24: Federal Agency Update - A Public Real Estate Symposium

Organization of GuideChp 1 IntroductionChp 2 Integrated Estimating ProcessChp 3 Agency Process OverviewChp 4 Conceptual ROW EstimatingChp 5 Baseline ROW EstimatingChp 6 Update ROW EstimatingChp 7 ROW Cost ManagementChp 8 ConclusionsAppendix - Tools

Page 25: Federal Agency Update - A Public Real Estate Symposium

Organization of GuideTools Appendix – provides detailed information on each of the tools discussed in the Procedures Guide.

Tool description is consistent with that used in NCHRP Report 574.

Page 26: Federal Agency Update - A Public Real Estate Symposium

Agency Level

ProcessFlowchart

Transportation Need

Conceptual ROWestimate

Update ROWestimate

Baseline ROWestimate

ROW CostManagement

Page 27: Federal Agency Update - A Public Real Estate Symposium

ROW Estimating Elements

• Land only

• Land and structures

• Other property improvements

• Damages

• Utility relocations

Page 28: Federal Agency Update - A Public Real Estate Symposium

ROW Estimating Elements

• Relocation assistance program• Administrative settlements• Settlements or trials• Support Costs• Appreciation (market forces)

depreciation is possible but as much of a problem

Page 29: Federal Agency Update - A Public Real Estate Symposium

Key ROW Estimating Inputs

Requirements Values for land and structures Historical data Inflation/appreciation rates Condemnation rates Future highest and best use

Page 30: Federal Agency Update - A Public Real Estate Symposium

Baseline ROW Cost Estimate

Baseline ROW Estimate Basis

PrepareBaseline ROW Base Estimate

Baseline ROW Risk/Contingency

Review Baseline ROW Estimate

Approval Baseline ROW Estimate

Page 31: Federal Agency Update - A Public Real Estate Symposium

PRELIMINARY DESIGN

ROW Project Development:· Refine ROW Scope per

preliminary plans and refined overall Project Scope

· Develop preliminary ROW plan

Approve & Communicate Updated ROW Cost Estimate· Review Impacts of changes· Obtain management approval· Authorize communication internally and

externally

Review Updated ROW Cost Estimate· Review estimate changes (basis and

assumptions)· Verify completeness and cost data for

changes· Review effect of changes on contingency

amount

Updated ROW Cost Estimate

To FinalDesign

ROW Requirements (Preliminary ROW

Plans)

Revised ROW Required

(Revised Plans)

Estimate on Budget?

YES

NO

Update ROW Estimate Basis· Review current ROW plans and

compare to previous requirements· Identify changes· Update ROW Estimate file

Update ROW Risks & Contingency· Review risks· Update risks as necessary· Update contingency value· Document update to risk and contingency

Input from Environmental,

Utilities, Railroad

Update ROW Base Estimate· Review updated estimate basis to understand

changes· Document observations of field visit to

confirm modifications· Review changes to existing estimate

assumptions/limitations· Calculate total area of land for each parcel· Revise cost basis to update estimate for each

element· Convert cost basis to update estimate for

each element· Update estimate documentations include

uncertain items· Summarize all estimate elements for updated

total ROW cost

Real Estate Appreciation

Rate

Land Market Values

Field Visit by Estimator (Improvements,

Damages, Existing Conditions, etc.)

Condemnation Rate

Historical Data

- Removal of Improvements- Relocation Assistance- Support Costs

Future Development (Community

Planning)

*

STIP≤ 4 years

Represents the dynamic nature of the milestone dependant on the practices

of the State highway agency.

*

FromProgramming

Potential Design/ROW Trade offs

CostEstimation

ManagementLoop

Modifications

Update ROW Cost Estimate

Update ROW Estimate Basis

Update ROW Base Estimate

Update ROW Risks/contingency

Review Updated ROW Estimate

Approve Updated ROW Estimate

Estimate in Budget NOYes

Page 32: Federal Agency Update - A Public Real Estate Symposium

ROW Cost

Final Design Phase

Management

Page 33: Federal Agency Update - A Public Real Estate Symposium

“How to” ChapterEstimation/Cost ManagementIntroductionFlowchart

Project complexity Phase inputs Process step description Tools (tied to tool appendix) Tips for success Outputs

Page 34: Federal Agency Update - A Public Real Estate Symposium

ToolsGeneric methods include:• B1 Budget Control• C1 Communication• E2 Estimate Review - External• E3 Estimate Review - Internal• I2 Identification of Risk• R3 Risk Analysis

Page 35: Federal Agency Update - A Public Real Estate Symposium

Risk AnalysisAnalysis of Risk and UncertaintyAnalysis of uncertainty involves

quantifying identified risks. Risk analysis is used to prioritize identified risks for mitigation, monitoring, and control purposes. Risk analysis can be extremely helpful for understanding project uncertainty and setting appropriate contingencies.

Page 36: Federal Agency Update - A Public Real Estate Symposium

Risk Analysis

What Is It?

In the context of cost estimation, this tool quantifies project risk and uncertainty to provide a better understanding of contingency and the ultimate project cost.

Page 37: Federal Agency Update - A Public Real Estate Symposium

Risk AnalysisWhy?

Highway project delivery, particularly the estimation of right-of-way cost, is a complex task heavy with uncertainty.

What Does It Do?

This tool quantifies the effect of potential risks in terms of their consequences to cost and schedule.

Page 38: Federal Agency Update - A Public Real Estate Symposium

Risk AnalysisWhen?

Risk analysis can be used throughout the project development process.

Examples

Caltrans has documented a qualitative risk analysis procedure: Project Risk Management Handbook: Threats and Opportunities, May 2007

Page 39: Federal Agency Update - A Public Real Estate Symposium

Risk AnalysisTips

Conduct the risk analysis early in the project development process.

Resources

Project Risk Management Handbook: Threats and Opportunities, Caltrans,

www.dot.ca.gov/hq/projmgmt/guidance_prmhb.htm

Page 40: Federal Agency Update - A Public Real Estate Symposium

Structured Approach

Collaborative Atmosphere

Key Principles

– Create an environment for success

– Create procedures for establishing a Baseline ROW Cost Estimate

Guide Conclusions

Page 41: Federal Agency Update - A Public Real Estate Symposium

Key Principles–Create processes to identify risk

and for setting contingency–Require ROW reviews–Create ROW cost control

mechanisms–Support good communication

practices

Guide Conclusions

Page 42: Federal Agency Update - A Public Real Estate Symposium

Stick to the process ―a process that:

Considers risk – identify and mitigate

Requires reviews and approvals Involves updating the estimate

when new or more detailed information is available.

Magic Bullets

Page 43: Federal Agency Update - A Public Real Estate Symposium

Communicate estimate consistency and accuracy to the project team and management

Page 44: Federal Agency Update - A Public Real Estate Symposium

Questions - Discussion!