3 Retail Market Subcommittee No Voting Items this Month  RMGRR111 - Process Updates for the Request of Historical Usage Data via Smart Meter Texas Web Portal Describes new process for third parties to obtain 15-min historical usage via the SMT Establishes that 15-min historical usage data is not provided by TDUs in current LOA process for historical usage Pending design decisions by AMIT  RMGRR113 - Updates to Standard Historical Usage Request Clarifies that an applicant at a new residence may authorize the TDU to release 12-mos of historical usage, despite not having lived in the premise during the past 12 mos. Being withdrawn by submitter due to PUCT Staff opposition

TRANSCRIPT

Page 1: Feb 7, 2013 Technical Advisory Committee RMS Update Rob Bevill

Feb 7, 2013Technical Advisory Committee

RMS Update

Rob Bevill

Page 2: Feb 7, 2013 Technical Advisory Committee RMS Update Rob Bevill

2

Retail Market Subcommittee --- 2013 Leadership

RMS• chair: Rob Bevill - Green Mountain Energy Co. • vice-chair: Kathy Scott - CenterPoint Energy

TX SET WG• chair: Diana Rehfeldt - TNMP • vice-chair: Monica Jones - Reliant Energy

TDT WG• chair: Isabelle Durham – CenterPoint Energy• vice-chair: Gricelda Calzada – AEP

MarkeTrak TF• co-chair: Monica Jones - Reliant Energy• co-chair: Carolyn Reed - CenterPoint Energy

Sharyland Transition TF• co-chair: B.J. Flowers - TXU Energy • co-chair: Kathy Scott - CenterPoint Energy• co-chair: Bridget Headrick - Sharyland

Page 3: Feb 7, 2013 Technical Advisory Committee RMS Update Rob Bevill

3

Retail Market Subcommittee

No Voting Items this Month

RMGRR111 - Process Updates for the Request of Historical Usage Data via Smart Meter Texas Web Portal • Describes new process for third parties to obtain 15-min historical usage via the

SMT• Establishes that 15-min historical usage data is not provided by TDUs in current

LOA process for historical usage• Pending design decisions by AMIT

RMGRR113 - Updates to Standard Historical Usage Request • Clarifies that an applicant at a new residence may authorize the TDU to release

12-mos of historical usage, despite not having lived in the premise during the past 12 mos.

• Being withdrawn by submitter due to PUCT Staff opposition

Page 4: Feb 7, 2013 Technical Advisory Committee RMS Update Rob Bevill

4

Retail Market Subcommittee

Advanced MeteringAMS deployment 95% complete: 6.3 million meters installed AMIT Steering Committee to be sunset in MarchProject 34610 (AMS Implementation) to be closed in MarchProject 41171 opened as repository for AMIT documentationProject 41172 opened to monitor completion of SMT Portal

• Projects Working Group will manage remaining SMT software releases

Advanced Metering Working Group to be created under RMS• Operational monitoring of SMT and AMS data

Home Area Network to be managed by Joint TDSPs• HAN Support Model being piloted w/ volunteer REP

Page 5: Feb 7, 2013 Technical Advisory Committee RMS Update Rob Bevill

5

Retail Market Subcommittee

Sharyland Transition to Competition

Sharyland Transition Task Force (STTF)

• Define procedures to transition Sharyland's Stanton, Colorado City, Brady, and Celeste divisions into ERCOT on May 1, 2014

• Customers that do not select a competitive REP will be allocated to default service REPs

• ~41,000 ESI IDs and ~18,000 customers

• Default REPs must complete EDI testing with ERCOT in either June 2013 or Oct 2013 flight test

Page 6: Feb 7, 2013 Technical Advisory Committee RMS Update Rob Bevill

6

Retail Market Subcommittee

Sharyland Transition to Competition

STTF Scope Statement – Approved by RMS

In accordance with the Final Order in PUCT Docket No. 39592, Sharyland Transition Task Force (STTF) has been assembled to discuss, develop, and document processes that allow for seamless transition of the former NOIE Customers (inclusive of Brady, Celeste, Colorado City, and Stanton territories) into the competitive ERCOT Market. This entails transitioning Customers from Sharyland’s integrated utility to the Competitive Retailer of choice or Default REP and the loading or creation of the premise-based information within ERCOT systems to allow customer choice and settlement to work according to market rules and/or ERCOT Protocols.

Page 7: Feb 7, 2013 Technical Advisory Committee RMS Update Rob Bevill

7

Retail Market Subcommittee

ERCOT 22-hour System Outage on 12/3/12

Retail Market - Lessons Learned

Market Conference Call – trigger • Propose change to Retail SLA

Market Notices• Trigger & Content• Propose changes to COPS Communications Guide

Manual Workarounds to get Customers Power On• Trigger for switching to manual processes• Propose changes to Retail Market Guide

Page 8: Feb 7, 2013 Technical Advisory Committee RMS Update Rob Bevill

8

Retail Market Subcommittee

Questions?