feasibility study for the formation of a renewable energy

18
TRIBAL GOVERNMENT TRIBAL GOVERNMENT Feasibility Study for the Formation of a Renewable Energy Tribal Utility Viejas Tribal Government DOE EERE Tribal Energy Program Review Meeting November 19, 2003

Upload: others

Post on 09-Feb-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

Feasibility Study for the Formation of a Renewable Energy Tribal Utility

Viejas Tribal Government

DOE EERE Tribal Energy Program Review Meeting

November 19, 2003

- 2

PresentersPresenters

Jamal Kanj, P.E.Director of Public WorksViejas Tribal Government5000 Willows RoadAlpine, CA 91901(619) [email protected]

Sam ScuphamRenewable Energy SpecialistBlack & Veatch11401 Lamar AvenueOverland Park, KS 66211(913) [email protected]

TRIBAL GOVERNM ENTTRIBAL GOVERNM ENTTRIBAL GOVERNM ENTTRIBAL GOVERNM ENT

- 3

Project ObjectiveProject Objective

Investigate the feasibility of forming a renewable energy based tribal utility for the Viejas Tribe.

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

- 4

OverviewOverview

ProjectProject LocationLocation

30 miles east of San Diego

1600 acres

Business enterprises:

Gaming

Outlet Center

Government Structure

General Council

Tribal Council

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

- 5

Project ParticipantsProject Participants

Viejas Tribal Government

Black & Veatch Corporation

Legal Opinion

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

- 6

Tribal Concerns/Project DriversTribal Concerns/Project Drivers

The Tribe Has Several Concerns Regarding Energy Supply

Electric Rates (Price and Stability)

Electricity Reliability

Energy Independence

Local Control

Environmental Impacts

Viejas and Black & Veatch Have Cooperated on Energy Investigations Since 2001

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

- 7

Past work: Energy Assessment Study (2001)Past work: Energy Assessment Study (2001)

Objective: Evaluate options in face of “dynamic” California energy market

Demand projections

Alternative electrical supply through power purchase agreements

Wholesale and self-generation power generation options

Risk analysis and management plan

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

- 8

0

5

10

15

20

25

30

35

July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June

All-i

n E

ffect

ive

Rate

(cen

ts/k

Wh)

Large Accounts >100 kWSmaller Accounts 5-100 kW Average of Large Accounts

Average of Smaller Accounts

2000 2001

Electricity Price History

- 9

Past Work: Utility Formation Study (2002) Past Work: Utility Formation Study (2002)

Objective: Evaluate providing electricity to residents and tribal businesses

Distribution system valuation

Distribution system operations and maintenance

Customer service operations

Energy supply price forecasting

Economic/financial evaluations

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

- 10

Conclusions of Previous WorkConclusions of Previous Work

Largest costs and risks involved with forming a utility are associated with:

Procurement of electricity from the volatile California energy market

Transmission of purchased power to the reservation

Local renewable energy resources could address these issues

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

- 11

Project TasksProject Tasks

Renewable Energy Resources and Technology Assessment

Wind

Biogas

Biodiesel

Solar

Detailed Reservation Load Profile

Assessment of Energy Storage and Load Management Opportunities

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

- 12

Project Tasks (cont.)Project Tasks (cont.)

Electrical Interconnection Analyses

Distribution System Audit

Legal Analysis

Generation Mix Optimization Study – POWRPRO™

Environmental Analysis

Tribal Benefit Assessment

Economic Assessment

Business Plan Development

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

- 13

Project ScheduleProject Schedule

14 months total, including 12 months of wind data collection

Tasks prior to data collection complete:Renewble energy assessment (non-wind)Load profileEnergy storage, load managementDistribution system auditLegal analysisBenefit assessment

Tasks after data collection complete:Wind energy assessmentElectrical interconnectGeneration mix studyEnvironmental reviewEconomic assessmentBusiness plan

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

- 14

Project StatusProject Status

Area surrounding Viejas Reservation severely damaged by wildfires

Kick-off meeting postponed until mid-December

Wind monitoring towers purchased, ready to be installed

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

- 15

ExpectationsExpectations

Complete load demand of reservation and businesses may be met with renewables

Some wind energy development possible, may be economic if energy exported to SDG&E

Other renewables may be less cost effective, but still economically viable

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

- 16

Areas of Wind ResourceAreas of Wind ResourceAreas of Wind Resource

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

- 17

Sample Wind Analysis OutputsSample Wind Analysis OutputsPhotomontageWeibull Curve

Classification Depiction Wind Rose

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT

- 18

ConclusionConclusion

Project ready to start before end of 2003

Expected to be complete early 2005

Questions?

TRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENTTRIBAL GOVERNMENT