feasibility study for the development of a regional …€¦ · the study and results outlined in...

120
FINAL REPORT FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY Summary Report BLACK & VEATCH PROJECT NO. 184920 PREPARED FOR Central Iowa Regional Drinking Water Commission 21 JULY 2015 ® ® ©Black & Veatch Holding Company 2013. All rights reserved.

Upload: others

Post on 22-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

 

FINAL REPORT  

FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

Summary Report 

BLACK & VEATCH PROJECT NO. 184920 

PREPARED FOR 

Central Iowa Regional Drinking Water Commission 

21 JULY 2015 

 

®

®

©Black & Veatch Holding Company 2013. A

ll rights reserved. 

Page 2: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Table of Contents  i

Table of Contents 

1 ExecutiveSummary.........................................................................................................1

1.1 Purpose......................................................................................................................................1

1.2 SpecialNotice..........................................................................................................................1

1.3 Scope...........................................................................................................................................2

1.4 StakeholderInputandSWOTAnalysis........................................................................2

1.4.1 StakeholderInput........................................................................................................2

1.4.2 SWOTAnalysis..............................................................................................................3

1.5 ValuationEstimate................................................................................................................4

1.5.1 AssetInventory............................................................................................................5

1.5.2 EstimatedRangeofValue.........................................................................................6

1.6 FinancialAnalysis..................................................................................................................7

1.6.1 NetValueAnalysis.......................................................................................................7

1.6.2 DevelopmentofFiveYearFinancialProjection..............................................9

1.6.3 AnalysisofEffectiveRate......................................................................................10

1.6.4 FutureConsiderations............................................................................................11

1.7 Governance...........................................................................................................................12

1.7.1 PotentialInitiatingPrinciples..............................................................................12

1.7.2 KeyGovernanceIssues...........................................................................................12

1.7.3 GovernanceAlternatives.......................................................................................13

1.8 Conclusion.............................................................................................................................14

2 Introduction....................................................................................................................16

2.1 Participants...........................................................................................................................16

2.2 ScopeofWork......................................................................................................................17

3 StakeholderInputandSWOTAnalysis..................................................................18

3.1 StakeholderInput...............................................................................................................18

3.1.1 Input...............................................................................................................................18

3.1.2 GeneralTakeaways..................................................................................................19

3.2 SWOTAnalysis....................................................................................................................20

3.2.1 InputIntoFeasibilityStudy..................................................................................23

4 ValuationEstimate........................................................................................................25

4.1 DevelopmentofAssetInventory.................................................................................25

4.1.1 AssetInventory.........................................................................................................26

4.1.2 AssetInspection........................................................................................................31

4.1.3 AssetReview...............................................................................................................31

4.2 EstimationofOriginalCostLessDepreciation(OCLD)......................................32

Page 3: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Table of Contents  ii

4.2.1 OriginalCost...............................................................................................................33

4.2.2 AccumulatedDepreciation...................................................................................33

4.2.3 OCLDResults..............................................................................................................34

4.3 EstimationofReplacementCostLessDepreciation(RCLD)............................36

4.3.1 ReplacementCost.....................................................................................................37

4.3.2 AccumulatedDepreciation...................................................................................37

4.3.3 RCLDResults..............................................................................................................38

4.4 CombinedEstimateofValuation.................................................................................40

4.5 EstimateofPurchasedCapacityValue......................................................................41

4.6 OtherContributedDMWWAssets...............................................................................43

4.6.1 JointEastSideProject.............................................................................................43

4.6.2 PolkCityFeederMain.............................................................................................43

4.6.3 AnkenyContributiontoSWTPFeederMain.................................................43

4.6.4 WDMWW98thStreetElevatedStorageTank................................................44

4.6.5 L.P.MoonStorageandBoosterStation...........................................................44

4.7 ValuationConclusion........................................................................................................44

5 FinancialAnalysis..........................................................................................................45

5.1 NetValueAnalysis.............................................................................................................45

5.1.1 SummaryofEstimatedValueandNetValueperMGD.............................45

5.1.2 AlignmentofNetValuebyEntity.......................................................................48

5.1.3 SummaryofNetValueAnalysis..........................................................................50

5.2 DevelopmentofFiveYearFinancialProjection....................................................51

5.2.1 OperationandMaintenanceExpense...............................................................52

5.2.2 AnnualRenewalandReplacement....................................................................53

5.2.3 MajorCapitalImprovementCosts.....................................................................53

5.2.4 RepaymentofOutstandingPurchaseCapacityDebt.................................54

5.2.5 AdjustmenttoDesMoinesWaterWorks’NetValue.................................54

5.2.6 MajorCapitalImprovementFinancing............................................................54

5.2.7 ProjectionofAnnualRevenueRequirementsandEffectiveRate ..........................................................................................................................................55

5.2.8 Financingalternatives............................................................................................58

5.2.9 EffectiveRatesensitivity.......................................................................................59

5.3 AnalysisofEffectiveRate................................................................................................60

5.3.1 FutureConsiderations............................................................................................61

5.3.2 CommunitiesThatOptOut...................................................................................63

5.4 FinancialAnalysisConclusion.......................................................................................63

6 Governance......................................................................................................................64

6.1 PotentialInitiatingPrinciples.......................................................................................64

Page 4: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Table of Contents  iii

6.2 KeyGovernanceIssues....................................................................................................65

6.2.1 VotingRights..............................................................................................................65

6.2.2 BoardMakeup............................................................................................................66

6.3 GovernanceAlternatives.................................................................................................68

6.3.1 TraditionalMunicipalGovernance....................................................................68

6.3.2 ModificationofCurrentGovernanceArrangement....................................70

6.3.3 PublicPrivatePartnership....................................................................................71

7 NextSteps.........................................................................................................................73

7.1.1 ShortTerm..................................................................................................................73

7.1.2 LongTerm...................................................................................................................74

AppendixA..................................................................................................................................A

AppendixB..................................................................................................................................B

AppendixC...................................................................................................................................C

 

Page 5: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Table of Contents  iv

LIST OF TABLES  Table1‐1SummaryofTotalCapacityandFirmCapacity......................................................5

Table1‐2SummaryofEstimatedValuation.................................................................................6

Table1‐3SummaryofNetValueperMGDbyEntity...............................................................7

Table1‐4SummaryofAlignmentofNetValueperMGDbyEntity....................................8

Table1‐5BreakdownofTotalMidRangeValue........................................................................9

Table1‐6EstimateofProjectedRevenueRequirements........................................................9

Table1‐7‐EstimatedEffectiveRate.............................................................................................10

Table1‐8‐EffectiveRateComparison.........................................................................................10

Table1‐9FutureExpansionExample...........................................................................................11

Table2‐1FullServiceandWholesaleCustomersofDMWW..............................................16

Table4‐1TotalSourceandSupplyAssetsforRegionalUtility..........................................29

Table4‐2DistributionSystemStorageandPumpStationAssets.....................................30

Table4‐3DesMoinesWaterWorksTransmissionMainAssets.......................................31

Table4‐4TreatmentAssetStrengthsandWeaknessesReview........................................32

Table4‐5EstimatedOCLDValueofDMWWAssets................................................................35

Table4‐6EstimatedOCLDValueforWDMWWAssets.........................................................36

Table4‐7EstimatedOCLDValueforUrbandaleWW,Altoona,andAnkeny................36

Table4‐8RCLDResultsforDMWW.............................................................................................39

Table4‐9RCLDResultsforWDMWW.........................................................................................40

Table4‐10RCLDResultsforUrbandaleWaterWorks,Ankeny,andAltoona............40

Table4‐11CombinedEstimateofValuation............................................................................41

Table4‐12SummaryofCurrentPurchasedCapacityAmountsandOriginalContribution.....................................................................................................................42

Table4‐13EstimatedRangeofPurchasedCapacityValueforWholesaleCustomers.........................................................................................................................43

Table5‐1SummaryofTotalCapacity,Value,andNetValuebyEntity(MidRangeValue)....................................................................................................................46

Table5‐2PurchasedCapacityMidRangeValuebyCustomer..........................................47

Table5‐3AlignmentofNetValueperTotalCapacitybyEntity........................................49

Table5‐4SummaryofAlignmentofNetValueandTotalCapacity................................50

Table5‐5SummaryofNetValueorEquity...............................................................................51

Table5‐6ProposedOperation&MaintenanceExpense......................................................52

Table5‐7ProjectedRenewalandReplacement......................................................................53

Table5‐8MajorCapitalImprovementProgram.....................................................................54

Table5‐9EstimatedCapitalFinancingPlan..............................................................................55

Table5‐10SummaryofRevenueRequirementsandUnitCostDevelopment...........56

Table5‐11ProjectedBilledWaterUsage...................................................................................57

Page 6: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Table of Contents  v

Table5‐12AlternativeRevenueRequirementsandUnitCostDevelopment.............59

Table5‐13RateSensitivityComparison....................................................................................60

Table5‐14EffectiveRateComparison........................................................................................61

Table5‐15FutureExpansionExample........................................................................................62

Table6‐1HypotheticalWeightedVoteBasedon%ofNetValue....................................66

 

LIST OF FIGURES  Figure1SWOTAnalysisMatrix.......................................................................................................21

Page 7: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  1

1 Executive Summary 

1.1 PURPOSE Black&VeatchCorporation(Black&Veatch)anditssubconsultantHRGreen,Inc.(HRGreen)wereretainedbytheCentralIowaRegionalDrinkingWaterCommission(CIRDWC)toassessthefeasibilityofformingaregionalwaterproductionutility(RegionalProductionUtility)fortheGreaterDesMoines,Iowaregion.Thefeasibilitystudy(Study)outlinedinthisreport(Report)includesthefollowingspecificelements:

ReceiptofinputfromCIRDWCmemberswithrespecttothecurrentmethodofregionalwatersupply,aswellasinputrelatedtothemeritsanddrawbacksofformingaRegionalProductionUtility.

ConductofaStrengths,Weaknesses,Opportunities,andThreatsanalysistocomparethebenefitsanddrawbacksofprovidingregionalwaterserviceunderthecurrentmethod,versusprovidingwaterserviceviaaRegionalProductionUtility.

Estimationoffairmarketvalueofassetsthatwouldcomprisetheregionalwaterproductionentity.

AnalysisofthefinancialimpactoncustomersofmovingtoaRegionalProductionUtility.

AnalysisofelementsrelatedtogovernanceoftheRegionalProductionUtilityandassessmentofpotentialgovernancealternatives.

TheStudyandresultsoutlinedinthisReportdidnotincludealegalassessmentofthefeasibilityofformingaregionalwaterproductionentity.TheStudyprovidesabasefeasibilityassessmentthatincludesanestimateofthefinancialimpactoncustomerscomparedtotheircurrentwholesaleservicearrangementswithDesMoinesWaterWorks(DMWW).Fromthisbasefeasibilityassessment,CIRDWCmemberscanthendeterminewhetheritisintheirinteresttofurtherpursueaRegionalProductionUtility.IfaRegionalProductionUtilityispursuedbyCIRDWCmembersbeyondthisStudy,itisanticipatedthatadditionalfinancial,legal,andengineeringanalysiswouldbenecessary.

1.2 SPECIAL NOTICE Inconductingthisstudy,Black&Veatchrevieweddocuments,records,agreements,capitalimprovementprograms,andfinancialinformationforCIRDWCmembersasdeemednecessary.WhileBlack&Veatchconsiderssuchdocuments,records,andprojectionstobereliable,theaccuracyofthesedocumentshasnotbeenverified.

TherecommendationssetforthinthisReportbelowinclude“forward‐lookingstatements”.Informulatingtheseprojectionsand/orrecommendations,Black&Veatchhasmadecertainassumptionswithrespecttoconditions,events,andcircumstanceswhichmayormaynotoccurinthefuture.Themethodologyusedinperformingtheanalysesfollowsgenerallyacceptedpracticesforsuchprojections.Suchassumptionsandmethodologiesarereasonableandappropriateforthepurposeforwhichtheyareused.WhileBlack&Veatchbelievestheassumptionsarereasonableandtheprojectionmethodologyvalid,actualresultsmaydiffermateriallyfromthoseprojectedasinfluencedbytheconditions,events,andcircumstanceswhichactuallyoccur.Suchfactorsmay

Page 8: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  2

include(1)theabilityofCIRDWCmemberstoexecutetheirfinancialandcapitalimprovementprogramsasscheduledandwithinbudget,(2)regionalclimateandweatherconditionsaffectingwateruse,and(3)adverselegislative,regulatoryorlegaldecisions(includingenvironmentallawsandregulations)affectingtheirabilitytomanagetheirsystemstomeetwaterqualityrequirements,orotherregulatoryrequirements.

1.3 SCOPE TheStudywasconductedpertheScopeofWorkoutlinedintheConsultingServicesAgreementbetweenBlack&VeatchandCIRDWCdatedJune27,2014.ThegeneralelementsoftheScopeofWorksareasfollows:

Collectandreviewdatarelatedtofinancial,operational,andassetinformationtogainanunderstandingofthecurrentmethodologyusedtoprovidedrinkingwaterservicetotheGreaterDesMoinesregion.

ConductstakeholderinputsessionswithCIRDWCmemberstogainanunderstandingoftheircurrentoperations,aswellastoreceivetheirinputwithrespecttotheStudyandtheformationofapotentialregionalwaterproductionentity.

ConductSWOTanalysiswithCIRDWCmemberstounderstandthebenefitsanddrawbacksofformingaRegionalProductionUtilityversusthecurrentwholesaleservicearrangement.

PerformestimateoffairmarketvalueofassetsthatwouldcomprisetheRegionalProductionUtilityusingtheCostApproachmethodologyofvaluation.

PerformafinancialanalysistodeterminethepotentialimpactonwholesalecustomerratesunderaRegionalProductionUtility.

Evaluatethreepotentialgovernancealternatives,includingissuesofpotentialboardcomposition,votingrights,andresponsibilities.

1.4 STAKEHOLDER INPUT AND SWOT ANALYSIS 

1.4.1 Stakeholder Input 

Black&VeatchinterviewedCIRDWCmembersoverseveraldaysinJuly2014.AquestionnairewaspreparedbyBlack&Veatchthatfocusedonquestionsandissuesrelatedto1)generalcharacteristicsofcommunityandwaterutility;2)localstrategywithrespecttoanticipatedgrowthandfuturewaterneeds;3)inputonbenefitsanddrawbacksofformingaRegionalProductionUtility;4)financialandrateissuesformember’swaterutility;and5)generalinputwithrespecttotheStudy.AppendixApresentsacopyofthequestionnaireprovidedtoCIRDWCmembers.

Keytakeawaysfromthestakeholderinputsessionsinclude:

ThemajorityofmembersthatcurrentlyreceivetheirwaterservicefromDMWWareexpectingsteadygrowthinpopulationoverthecomingyears.

TherearemultipleplanninginitiativesforgrowthandeconomicdevelopmentbeingconductedthroughouttheDesMoinesmetroarea.WhilecommunicationbetweenDMWWandregionalcommunitiesdoesoccurwithrespecttowaterissues,thereisnocoordinated,regionalplanningwithrespecttodevelopingfuturewatersupplytomeetprojecteddemands.

Page 9: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  3

CurrentwholesalecustomersareveryinterestedinhavingmorerepresentationinthefuturedevelopmentandprovisionofwaterserviceintheGreaterDesMoinesregion.

Generally,membersindicatedthatgovernancewithproportionaterepresentationwouldbeacceptableinanynewregionalwaterproductionentity.Therewereasmallnumberofparticipantsthatadvocatedforaonemember,onevoteapproachtogovernance.

CurrentwholesalecustomersexpressedfrustrationwithDMWW’scostofservicestudyandratesettingapproach,however,therewasnotanoverarchingviewthattheyarereceivingpoorvalue.Inseveralinstances,wholesalecustomersindicatedtheyarereceivinggoodvalueatthecurrentrate.

MembersindicatedthatdealingwithDMWWonoperationalissuesisveryeasyandprofessional. MembersindicatedthatthefinishedwaterqualitytheyreceivefromDMWWisgenerallyverygood.

Membersindicatedthatthereisaconcernabouthowfuturewatersupplyandadditionalcapacitywillbedevelopedunderthecurrentframework.

1.4.2 SWOT Analysis 

TheSWOTAnalysiswasconductedonSeptember12,2014attheDesMoinesBotanicalGarden.TheSWOTAnalysiswasledbyBlack&VeatchandconsistedofapproximatelytwomembersfromeachCIRDWCcommunity/utility.Amorningsessionfocusedonthestrengths,weaknesses,opportunities,andthreatsoftheexistingmethodforprovidingregionalwaterservice.ThecurrentmethodincludesthemajorityofsourceofsupplyandtreatmentprovidedbyDMWWwithwholesalepurchasedcapacityagreementsorfullserviceagreementswiththesurroundingcommunities.Theafternoonsessionfocusedonthestrengths,weaknesses,opportunities,andthreatsofprovidingwaterservicetotheGreaterDesMoinesregionfromnewRegionalProductionUtility.Uponcompletionoftheafternoonsession,Black&VeatchreviewedindividualgroupresultstoderiveaconsolidatedsummarythatwasreviewedbyCIRDWCmembers.ThefollowingTablespresentthecombinedresultsoftheSWOTAnalysis.AppendixBpresentsacopyofthepresentationmaterialsusedduringtheSWOTanalysis.

STRENGTHS 

Current 

DMWW Staff Responsible and Knowledgeable 

Reliability of finished water  Currently finished water quality is good  Redundancy  Multiple sources of supply 

Ability of customer communities to make 

independent decisions 

Opportunity to choose level of service  Knowledge of defined capacity limits for each 

community

Regional Production Utility

More equal representation with regards to 

governance, planning, and rates 

More political influence at regulatory level 

More political stability on governing board 

Potential long‐term cost efficiencies (direct and 

indirect) 

Regional planning  Provide relative savings – slow the rate of increase

Page 10: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  4

WEAKNESSES 

Current 

Autocratic governance of water supply and production 

No current Board representation of customer 

communities 

No accountability to customer communities for how 

resources are spent or decisions made 

Source water quality  Source water quantity  Competing priorities for responding to regional 

growth 

Availability of purchased capacity to meet growth

Regional Production Utility

Size of governing body  Source water quality and quantity are still issues  Change in workforce impacting level of service 

Cost versus investment – long term change over 

short term pain 

Buy‐in costs  Conflict between growth and reinvestment 

Right now we know who to blame 

 

OPPORTUNITIES 

Current 

Improve current processes 

Individual communities continue to make 

independent decisions 

More inclusive governance and geographic diversity 

of Board 

Ability to improve watershed management

Regional Production Utility

Ability to influence quality and quantity  Long term bonding capability 

Predictability on revenue and costs  Better control over resources  Consistent message communicated with customers 

Input into regional economic development

THREATS 

Current 

Competing interests for same source water 

Division/breakup of current customer configuration 

Availability of capacity to meet customer community 

needs 

Nonpoint source pollution impact on source water 

Climate issues

Regional Production Utility

Initial cost of buy‐in  Less than 100% participation from communities 

Perception of reduction in work force  Loss of local control  Failure to meet customer expectations 

Nonpoint source pollution impact on source water 

Climate issues

1.5 VALUATION ESTIMATE TheformationofaRegionalProductionUtilityseparatefromDMWWwouldlikelyincludeatransactionthattransfersassetsfromDMWWandseveralotherentitiestothenewRegionalProductionUtility.Therefore,anestimateofthevalueofthoseassetsisneededtounderstandthelevelofvaluebroughtbyparticipantstothenewRegionalProductionUtility.Black&VeatchperformedavaluationtoestimatethepotentialfairmarketvalueofassetsusingtheCostApproachmethodofvaluation.ThisconsistsofdeterminingtheOriginalCostLessDepreciation(OCLD)andReplacementCostLessDepreciation(RCLD)toderivearangeofvalue.TheCostApproachprovidesareasonablerangeoffairmarketvalueforpurposesofthisStudy.

Page 11: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  5

1.5.1 Asset Inventory 

Black&VeatchreliedoninformationprovidedbyCIRDWCmemberstounderstandwhatpotentialwaterserviceassetswouldbetransferredtotheRegionalProductionUtility.AfterreviewinginformationanddiscussingwithCIRDWCmembers,Black&Veatchgenerallyselectedassetsthat1)currentlyservemorethanoneutilityorcommunity;or2)havethefuturepotentialofservingorsupportingtheservicetomorethanoneutilityorcommunityintheregion.AmapshowingtheGreaterDesMoinesregionandsignificantwaterproductionassetsisincludedinAppendixC.Thefollowingprovidesabriefdescriptionoftheidentifiedassets:

CorenetworkassetsofDMWWincludingsourceofsupply,treatmentfacilities(Fleur,McMullen,andSaylorvillewatertreatmentplants(WTP)),aswellastheassociatedcorenetworktransmissionmains,pumpstations,andstoragetanks.

SourceofsupplyandtreatmentfacilitiesofWestDesMoinesWaterWorks(WDMWW),aswellasthe98thStreetelevatedstoragetank.

WellsandtreatmentplantsownedandoperatedbytheCityofAltoona.

AquiferStorageandRecovery(ASR)wellsownedandoperatedbytheCityofAnkeny.

RawwaterquarriesownedbytheUrbandaleWaterWorks.

Alongwiththeassetinventory,Black&Veatchreviewedinformationrelatedtotheseassetstounderstandtheircapabilitieswithrespecttomeetingpeakdaywaterdemands.Basedonareviewofinformationanddiscussionswithstaffthatoperatetheseassets,theestimatedtotalandfirmcapacitiesoftheseassetsispresentedinTable1‐1.

Table 1‐1  Summary of Total Capacity and Firm Capacity 

LINE 

NO.  PHYSICAL ASSET 

TOTAL 

CAPACITY/ 

DEMAND, 

MGD 

FIRM 

CAPACITY/ 

DEMAND, 

MGD 

  WTP and ASR Supply Facility Capacity

1  City of Altoona Treatment Plants  3.90 0.58

2  City of Ankeny ASR Wells  4.32 0.00

3  DMWW Treatment Plants and ASR Wells 116.00 86.70

4  WDMWW Treatment Plant  9.90 6.90

5  Total WTP and ASR Capacity(a)  134.12 118.6

(a) The value of 118.6 mgd is not a summation. Total firm capacity considers all production facilities in operation with one of the seven WTPs (McMullen WTP) limited to firm capacity and one 3.0 mgd ASR well out of service to account for equipment being offline for maintenance and/or repair.    

Theidentifiedassetsarecurrentlynotdesignedtoworkincoordination,andBlack&VeatchandHRGreendidnotundertakedetailedmodelingoranalysistoassesstheoverallperformanceofthesystemsasacombinedRegionalProductionUtility.Basedonareviewofavailableinformation,areasonable,highlevelestimateoftheregionalpeakdaydemandisapproximately115mgd.This

Page 12: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  6

reflectsthatregionaldemandsarealreadyclosetofirmcapacitylimitsandapproachingtotalcapacitylimits.Assumingsteadygrowthintheregion,itappearsreasonabletoassumethatexpansionofregionalproductionassetswillbenecessaryinthecomingyears.

1.5.2 Estimated Range of Value 

Table1‐2presentstheresultsoftheCostApproachmethodofvaluation.Ingeneral,Black&Veatchreliedonassetinformationandotherdataprovidedbytheentitiesthatwouldcontributesourceofsupply,treatment,andtransmissionassetstotheRegionalProductionUtility.Incertaininstances,Black&VeatchdevelopedReplacementCostestimatesforspecificassetsusingengineeringjudgment.Black&VeatchusedcosttrendindicesfromtheHandy‐WhitmanBulletinNo.180:CostTrendsofWaterUtilityConstruction(Handy‐WhitmanIndex)toderivetheReplacementCostorOriginalCostoftheassets.TheOriginalCostandReplacementCostvaluesareadjustedforaccumulateddepreciationtorecognizethatovertime,thevalueofanassetdecreasesduetofactorssuchaswearandtear,actionoftheelements,orotherfactors.AccumulateddepreciationwasdeterminedonastraightlinebasisusingservicelifeestimatesdevelopedbyBlack&Veatch,aswellastheknownageoftheasset.Theestimatedvaluationrangesfromapproximately$234millionto$413million,withamidrangevalueof$323million.

Table 1‐2  Summary of Estimated Valuation 

1.5.2.1 Estimated Value of Purchased Capacity and Other Contributions 

DMWWmaintainsWholesaleWaterServiceMasterAgreementswithapproximately12communitiesintheGreaterDesMoinesregion.TheseagreementsprovidedamechanismforwholesalecustomerstocontributefundstoDMWWinexchangeforacommitmentbyDMWWtosupplyaspecificamountofpeakdaywater,orcapacity.Basedonareviewoftheagreementsandotherinformation,Black&VeatchdeterminedthatfundscontributedbythesecustomerswereprimarilyusedtoconstructDMWW’sMcMullenWTP(includingrawwaterassets),SaylorvilleWTP(includingrawwaterassets),SaylorvilleWTPFeederMain,andtwoASRwells.Therangeofvaluefortheseassetsisapproximately$71,791,000to$95,177,300,withamidrangevalueof$83,484,200.

Additionally,itwasdeterminedthatarecentprojecttoenhancewatersupplytotheeasternportionoftheregionalsystemwascontributedbythreecommunities.Theestimatedvalueofthisprojectrangesfromapproximately$12,422,200to$13,455,600,withamidrangevalueof$12,939,000.

Replacement  

Original Cost Cost

Line Original  Replacement Accumulated Accumulated

No. Description Cost Cost Depreciation Depreciation OCLD RCLD

1 Des Moines Water Works $288,395,300 $692,556,400 $78,733,700 $327,320,800 $209,661,600 $365,235,600

2 West Des Moines Water Works $27,060,600 $61,177,000 $9,900,400 $27,349,700 $17,160,200 $33,827,300

3 City of Altoona $8,145,700 $23,050,800 $3,857,400 $13,600,700 $4,288,300 $9,450,100

4 City of Ankeny $2,279,800 $3,310,400 $468,600 $729,700 $1,811,200 $2,580,700

5 Urbandale Water Works $870,900 $1,680,000 $0 $0 $870,900 $1,680,000

6 Estimated Valuation $326,752,300 $781,774,600 $92,960,100 $369,000,900 $233,792,200 $412,773,700

7 Mid Range Estimate $323,283,100

Page 13: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  7

TherewerealsocontributionsidentifiedforassetssuchasthePolkCityfeedermainandWDMWW’s98thStreetElevatedStorageTankwhichwereincorporatedintotheStudy.

WithintheFinancialAnalysisportionofthisReport,thesevaluesaredeductedfromtheapplicableentity’soverallvalue,andappliedtotheindividualutilitiesorcommunitiesthatmadethecontribution.ThenetmidrangevalueapplicabletoDMWWisapproximately$196.5million.

1.6 FINANCIAL ANALYSIS Afinancialanalysiswasconductedto1)defineanapproachforhowregionalparticipantscouldformaRegionalProductionUtilityonanequalbasis;and2)determinetheestimatedeffectiverateper1,000gallonsthatwouldapplytoparticipantsforwaterservicefromtheRegionalProductionUtility.AsignificantassumptioninthefinancialanalysisisthatallcurrentpurchasedcapacitycustomersandDMWWwouldparticipateinthenewRegionalProductionUtility.

1.6.1 Net Value Analysis 

TheNetValueanalysisreflectsthevaluebroughttothetablebypotentialparticipantsintheRegionalProductionUtility.Thenetvalueperentityreflectstheirrespectivevalue,offsetbyoutstandingnetdebtservicethatisheldbyDMWW,primarilyrelatedtopurchasedcapacitycontributions.ThefollowingTablepresentsthenetvaluebyentitybasedonthemidrangeestimateofvaluedeterminedintheValuationEstimatesectionofthisReport.

Table 1‐3  Summary of Net Value per MGD by Entity 

AsisseeninColumns1and2ofTable1‐3above,theentitieshavevaryinglevelsofclaimsonthetotalcapacityoftheregionalsystem.ThepurchasedcapacitycustomershavetheiramountsthathavebeencontractuallyagreedtowithDMWW.Inadditiontopurchasedcapacityamounts,WDMWW,Altoona,andAnkenyretainthecapacityrelatedtotheirtreatmentandASRfacilitiesthatwouldbetransferredtotheRegionalProductionUtility.DMWWretainsthetotalcapacityoftheDMWWsystem,lessthepurchasedcapacityamountspreviouslymentioned(approximately116mgd–56.137mgd=59.86mgd).

(1) (2) (3) (4) (5) (6) (7) (8)

Estimated Estimated

% Estimated DMWW DMWW % Net

Line Total Total Mid Range Outstanding Debt Service Net Net Value

No. Description Capacity Capacity Value Debt Reserve Value Value per mgd

mgd =(3)+(4)+(5) =(6)/(1)

Contributing Entities

1 Des Moines Water Works 59.86 44.63% $196,459,400 ($5,996,800) $703,400 $191,166,000 65.17% $3,193,400

2 Polk Co. (SE and Unincorporated) 1.95 1.45% $3,895,200 ($679,800) $0 $3,215,400 1.10% $1,648,900

3 Berwick Water Association 0.25 0.19% $371,800 ($56,300) $45,100 $360,600 0.12% $1,442,400

4 Urbandale Water Works 15.30 11.41% $24,028,800 ($11,204,700) $1,609,000 $14,433,100 4.92% $943,300

5 West Des Moines Water Works 18.87 14.07% $36,457,400 ($4,541,500) $708,100 $32,624,000 11.12% $1,728,600

6 Ankeny 12.60 9.39% $15,339,900 ($9,983,100) $959,500 $6,316,300 2.15% $501,300

7 Clive 6.98 5.20% $11,967,400 $0 $0 $11,967,400 4.08% $1,714,500

8 Waukee 3.69 2.75% $6,287,100 ($805,100) $171,000 $5,653,000 1.93% $1,530,300

9 Warren Rural Water 3.25 2.42% $4,827,300 $0 $0 $4,827,300 1.65% $1,487,200

10 Xenia Rural Water 2.95 2.20% $4,385,700 $0 $0 $4,385,700 1.50% $1,487,200

11 Norwalk 1.97 1.47% $2,922,200 ($412,400) $146,500 $2,656,300 0.91% $1,351,800

12 Bondurant 1.20 0.89% $1,784,600 ($684,800) $77,800 $1,177,600 0.40% $981,300

13 Altoona 4.90 3.65% $12,337,600 $0 $0 $12,337,600 4.21% $2,517,900

14 Polk City 0.35 0.26% $2,218,700 $0 $0 $2,218,700 0.76% $6,339,100

15 Total 134.12 100.00% $323,283,100 ($34,364,500) $4,420,400 $293,339,000 100.00% $2,187,100

Page 14: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  8

ThenetvaluebyentityisreflectedinColumn6,alongwiththeassociatedpercentageoftotalnetvalueinColumn7.ThenetvaluepermgdoftotalcapacityisreflectedinColumn8andshowsthatindividualentitiesarecontributingadifferentnetvaluepermgdtotheRegionalProductionUtility.

AlignmentofnetvaluepermgdbyentityprovidesfortheformationoftheRegionalProductionUtilitywithparticipantsonanequalbasis.Toachievethisalignment,Black&Veatchusedatwo‐stepprocess.First,acashpaymenttoDMWWwasassumedtoreduceitsoverallnetvaluepermgdtoalevelclosertotheotherentities.Second,thecontributionbyentitythatwouldbringallparticipantsintoalignmentonanetvaluepermgdbasiswasdetermined.Table1‐4presentsthealignmentofnetvaluepermgdbyentity.

Table 1‐4  Summary of Alignment of Net Value per MGD by Entity 

Ascanbeseen,thecashpaymentof$100milliontoDMWWinLine1resultsinanadjustednetvaluepermgdofapproximately$1,522,900.Black&VeatchthenmadetheadjustmentsseeninColumn3toaligneachentitywithDMWWatanetvalueof$1,522,900permgdoftotalcapacity.PositivevaluesinColumn3reflectcontributionsthatwouldhavetobemadebyentitiestothenewRegionalProductionUtility,whilenegativevaluesreflectcontributionsthatwouldhavetobemadetotheentities.Asforregionalcommunitiesthatcurrentlydonothavepurchasedcapacityagreements,thenetvaluepermgdamountof$1,522,900,multipliedbyneededcapacity,couldprovidethebuyinvaluenecessaryforachievingmembership.

OneimpacttotheRegionalProductionUtilitywouldbethelikelyneedtoissuedebttoperformthecashpaymentstoDMWW.Thisincludesthepaymenttoretiredebtrelatedtothecorenetwork,andthe$100millioncashpaymentnotedabove.Table1‐5presentsasummaryofthetotalmidrangevalue,andresultingnetvaluefortheRegionalProductionUtility.

(1) (2) (3) (4) (5) (6)

Net Adjusted

Cash Payment Contributions Adjusted Restated Net

Line Net Des Moines (To)/From Net Total Value

No. Description Value Water Works Other Entities Value Capacity per mgd

(1)+(2)+(3) (4) / (5)

Contributing Entities

1 Des Moines Water Works $191,166,000 ($100,000,000) $91,166,000 59.86 $1,522,900

2 Polk Co. (SE and Unincorporated) $3,215,400 ($245,800) $2,969,600 1.95 $1,522,900

3 Berwick Water Association $360,600 $20,200 $380,800 0.25 $1,522,900

4 Urbandale Water Works $14,433,100 $8,867,400 $23,300,500 15.30 $1,522,900

5 West Des Moines Water Works $32,624,000 ($3,882,200) $28,741,800 18.87 $1,522,900

6 Ankeny $6,316,300 $12,872,400 $19,188,700 12.60 $1,522,900

7 Clive $11,967,400 ($1,337,400) $10,630,000 6.98 $1,522,900

8 Waukee $5,653,000 ($27,300) $5,625,700 3.69 $1,522,900

9 Warren Rural Water $4,827,300 $116,100 $4,943,400 3.25 $1,522,900

10 Xenia Rural Water $4,385,700 $105,500 $4,491,200 2.95 $1,522,900

11 Norwalk $2,656,300 $336,200 $2,992,500 1.97 $1,522,900

12 Bondurant $1,177,600 $649,900 $1,827,500 1.20 $1,522,900

13 Altoona $12,337,600 ($4,875,300) $7,462,300 4.90 $1,522,900

14 Polk City $2,218,700 ($1,685,700) $533,000 0.35 $1,522,900

15 Total $293,339,000 ($100,000,000) $10,914,000 $204,253,000 134.12 $1,522,900

Page 15: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  9

Table 1‐5  Breakdown of Total Mid Range Value 

1.6.2 Development of Five Year Financial Projection 

ThesecondpartofthefinancialanalysisistodevelopanestimatedfiveyearfinancialprojectioniftheRegionalProductionUtilityweretobeformed,aswellastheresultingeffectiverateonaper1,000gallonbasis.

1.6.2.1 Revenue Requirements 

Forpurposesofthefinancialanalysis,Black&Veatchdevelopedafiveyearprojectionofrevenuerequirementsthatinclude1)operationandmaintenance(O&M)expense;2)anydebtserviceonoutstandingbondissues;3)annualprovisionforrenewalandreplacementcapitalofthesystem;4)othercashfundedcapital.

AsummaryoftherevenuerequirementscanbeseeninthefollowingTable1‐6.AscanbeseenonLine5,areasonableprojectionoftherevenuerequirementsfortheRegionalProductionUtilitystartsatapproximately$44.9millionin2016,andincreasestoapproximately$49.9millionby2020.

Table 1‐6 Estimate of Projected Revenue Requirements 

1.6.2.2 Projected Billed Usage and Effective Rate 

Todeterminetheeffectiverateper1,000gallons,itisnecessarytoestimatetheprojectedbilledusagethattheRegionalProductionUtilitywouldusetorecoverrevenue.Black&VeatchutilizedhistoricalbilledusageprovidedbyDMWWforthemajorityofentities.AdditionalbilledusagerelatedtoWDMWWandAltoonacustomersthatareservedbythoseentitieswasalsoincludedtoderiveatotalestimateofregionalbilledusage.Forprojectionpurposes,Black&VeatchassumedthatDMWWbilledusagedoesnotgrowoverthefiveyears.Forallotherbilledusage,itisestimated

Line Breakdown

No. Description of Value

1 Total Value Estimate ‐ Mid Range $323,283,100

2 Cash Payment to DMWW ($100,000,000)

3 Net Cash Payment to DMWW for Debt ($29,944,100)

4 Contributions From Participants $22,967,700

5 Contributions To Participants ($12,053,700)

6 Total Net Value (Equity) $204,253,000

Line

No. Description 2016 2017 2018 2019 2020

1 Operation & Maintenance Expense $25,072,700 $25,824,800 $25,487,800 $26,252,400 $27,040,000

2 Debt Service $8,241,000 $8,241,000 $8,241,000 $8,241,000 $8,241,000

3 Cash Financed Major Capital $0 $0 $500,000 $0 $3,000,000

4 Capital Renewals & Replacements $11,616,000 $11,289,000 $11,164,000 $11,616,000 $11,616,000

5 Total Revenue Requirements $44,929,700 $45,354,800 $45,392,800 $46,109,400 $49,897,000

Page 16: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  10

thattheannualgrowthwillbe1.5percent.Thisresultsinaneffectivegrowthrateof1.0percentannually.ThefollowingTable1‐7presentstheprojectofbilledusageandannualrevenuerequirements.Theeffectiveratebyyearisshownonaper1,000gallonsbasis.

Table 1‐7 ‐ Estimated Effective Rate 

LINE NO.  DESCRIPTION  2016 2017 2018 2019  2020

1  Annual Revenue Requirements  $44,929,700 $45,354,800 $45,392,800 $46,109,400  $49,897,000

2  Projected Billed Usage (1,000 gal.)  17,857,100 18,010,100 18,165,300 18,322,900  18,482,900

3  Estimated Effective Rate ($/1,000 gal.) $2.52 $2.52 $2.50 $2.52  $2.70

1.6.3 Analysis of Effective Rate 

Forcomparisonpurposes,Black&VeatchlookedatthecurrentratepaidbyseveralpurchasedcapacitycustomerstoDMWWunderthecurrentwholesalearrangement.DMWWrecentlyapprovedapurchasedcapacityrateof$1.53per1,000gallons.Forcomparisontothefiveyearprojection,Black&Veatchassumesthatthiswillincreaseto$1.59per1,000gallons.InadditiontothepurchasedcapacityratepaidtoDMWW,entitiesmustalsopaydebtservicerelatedtotheirpurchasedcapacitycontributiontoDMWW.Black&Veatchderivedanestimateofthiscostper1,000gallonsbytakingtheannualprincipalandinterestforeachentityanddividingitbytheirrespectivebilledusage.TheestimatedeffectiverateforWDMWW,CityofAnkeny,UrbandaleWaterWorks,andtheCityofWaukeeispresentedinLine2ofTable1‐8.ThecompleteTablepresentsacomparisonoftheeffectiverateunderaRegionalProductionUtilitytotheestimatedeffectiverateunderthecurrentwholesalearrangement.

Table 1‐8 ‐ Effective Rate Comparison 

LINE NO.  DESCRIPTION 

CITY OF ANKENY

URBANDALE WATER WORKS

CITY OF WAUKEE 

WEST DES MOINES WATER WORKS

1 2016 Effective Rate – Regional Production Utility ($/1,000 gal.)  $2.52 $2.52 $2.52  $2.52

2  Current Effective Rate ($/1,000 gal.) $2.15 $2.27 $2.37  $2.00

3  % Difference (Regional to Current) $17.2% $11% 6.3%  26.0%

Ascanbeseen,theestimatedeffectiveratefortheRegionalProductionUtilitywouldlikelybehighercomparedtothecurrenteffectiveratefortheabovecommunities.Whiletheabovecomparisonprovidesanindicationofthecurrentcomparison,Black&VeatchrecommendsthateachentityundertakeitsownseparateanalysisaseachentityisfamiliarwiththecostsitmayhaveincurredtopurchasecapacityorcontributetoDMWWovertheyears.Ingeneraltheestimatedeffectiverateisnotcompletelyoutoflinewithcurrentratespaidbyregionalentities.

Page 17: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  11

1.6.4 Future Considerations 

WhilethecomparisonoftheeffectiverateunderaRegionalProductionUtilitycomparedtothecurrentwholesalearrangementprovidesvaluableinformationtoseehowcurrentcostsmightchange,itisalsoimportanttoconsiderthevalueofpotentialchangestomeetingfuturegrowthdemands.

Underthecurrentwholesalearrangement,autilitythatneedsadditionalcapacitymorethanlikelymustobtainitfromDMWW.Black&VeatchunderstandsthatDMWWwillidentifythecostofthenecessaryimprovementstoaddthecapacity,andthenpassthatcostsolelyalongtotheutilitythatrequiresthecapacity.ThisapproachbyDMWWisnotuncommonandisdonetoprotectexistingcustomersfrombeingoverlyburdenedwithcostsforadditionalcapacitythatmaynotbenefitthem.

OnepotentialoptioncouldbefortheRegionalProductionUtilitytoshareintheoverallcostsforexpandingthecapacityofthesystem.ThesharingofexpansioncostsunderthisoptionwouldbeconsistentwiththenetvalueapproachoutlinedinthisReportthatbringsparticipantsintotheRegionalProductionUtilityonanequalbasis(netvaluepermgd).

Table1‐9providesahypotheticalexampleforconsideration.Underthecurrentsituation,thefourutilitiesrequireanadditional5.0mgdofcapacityeach.Thehypotheticalprojectcostof$60millionwouldbesplitbetweentheutilitiesonanequalbasis.Theassociatedbondissueresultsinannualprincipalandinterestpaymentsof$867,000peryear,andthesepaymentsarepassedonbyDMWWtotheutilities.Thisresultsinvaryingcostper1,000gallonsbasedontheirrespectivebilledusageforrecoveringthecost.

Thealternativeoptionreflectsthesharingofsystemexpansioncostsof20.0mgdamongallregionalparticipants.Theunitcostunderthisoptionis$0.20per1,000gallons.ForUtilityNo.2,thiswouldresultinannualsavingsofapproximately$375,000(($0.35‐$0.20)X2,500,000).

Table 1‐9 Future Expansion Example 

LINE NO.  UTILITY 

CAPACITY NEEDED (MGD)

ANNUAL PRINCIPAL 

AND INTEREST (1)

BILLED USAGE 

(1,000 GAL.)COST PER 1,000 GAL. 

CURRENT SITUATION 

1  Utility No. 1  5.0 $867,000 1,200,000 $0.72 

2  Utility No. 2  5.0 $867,000 2,500,000 $0.35 

3  Utility No. 3  5.0 $867,000 1,400,000 $0.62 

4  Utility No. 4  5.0 $867,000 500,000 $1.73 

POTENTIAL OPTION – REGIONAL PRODUCTION UTILITY

5  Total Regional Utility  20.0 $3,470,000 17,557,917 $0.20 

Note: Hypothetical analysis for illustration purposes only. 

(1) Estimated based on hypothetical project cost of $60M, 30‐year bond using 4.0% annual interest rate. 

Page 18: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  12

Existingutilitiesand/orcommunitiesthatarecustomersofDMWW,andthatarenotanticipatinggrowthmaybalkattheoptionofaregionalwaterutilitysharingexpansioncostsamongallregionalentities.However,theseentitiesmustconsiderthepotentialofgrowthcommunitiespursuingtheirfuturewaterneedseitherindividually,orasagroupseparatefromDMWW.OvertimethelossofrevenuefromanycustomerthatleavesDMWWcouldresultinrateincreasestocustomersthatremain,asfixedcostsoftheDMWWsystemarespreadoverasmallerbilledusagebase.

1.7 GOVERNANCE ThecreationofanewRegionalProductionUtilitywouldbeasignificantchangefromthecurrentarrangementthathasseenDMWWasthekeyplayerinthedevelopmentofthecurrentregionalwatersystem.GovernanceoftheprovisionofwatertothesurroundingcommunitiesviathecorenetworkisprimarilyadministeredbytheDMWWBoardofDirectors.ThisBoardiscurrentlyresponsiblefortheestablishmentofratesandcharges,systemplanning,capitalfinancing,andothermiscellaneousresponsibilitiesthatmustbehandledonadaytodaybasis.

1.7.1 Potential Initiating Principles 

AsCIRDWCmembersconsiderwhethertoestablishaRegionalProductionUtility,thereareseveralitemsorprinciplesderivedfromthestakeholderinputandSWOTanalysisthatwereimportanttomembers.TheseitemswerenotedbyBlack&Veatchasbeingimportanttooneorseveralmembers,andcouldprovidethebasisforafoundingdocumentcreatingtheRegionalProductionUtility.Theyareprovidedhereforconsideration:

FutureSourceofSupply–Memberswouldneedtoagreenottoindependentlydeveloptheirownsourceofsupply,unlessapprovedbytheRegionalProductionUtility.

FuturePurchaseofFinishedWater–Memberswouldneedtoagreetopurchaseallfuture,finishedwaterfromtheRegionalProductionUtility.

WaterQuality–MemberswouldneedtoagreetosupportallapprovedinitiativesbytheRegionalProductionUtilityrelatedtosourceandfinishedwaterquality.

SystemPlanningandExpansion–Memberswouldneedtoagreetoparticipateinregionalwatersystemplanningtobenefittheentireregion.

OutstandingDebt–MemberswouldneedtoagreethatalldebtrelatedtotheirindividualsystemsorpreviousrelationshipwithDMWWremainseparatefromtheRegionalProductionUtility.

RatesandCharges‐Memberswouldneedtoagreetoestablishsufficientratesandchargesthatsupportandmaintaintheexistingcorenetwork,aswellasexpandthecorenetworktomeetfutureregionaldemand.

1.7.2 Key Governance Issues 

ThisStudyaddressesseveralkeyaspectofgovernancethatwillneedtobeaddressedbytheregionalentities.

BoardMakeup–DuringthestakeholderinputandSWOTanalysis,are‐occurringthemefromCIRDWCmemberswastheirdesiretohaveaseatatthetablewithrespecttogovernanceissues,includingestablishmentofratesandchargesandsystemplanning.ThiswillrequirealargeBoard

Page 19: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  13

thatwillneedtoaccommodatevaryingviewpointsongovernanceandregionalwaterissues.CIRDWCmembersdidstatethatthelargeWRABoardfunctionseffectively.

InBlack&Veatch’sexperience,aneffectiveBoardmakeupwouldincludememberswhoareappointedbythegoverningbodiesoftheirrespectivecommunities.TheappointmentofBoardmembersispreferabletoaBoardthatismadeupofelectedmembers.

AprofessionalstaffwouldlikelybenecessarytoassisttheBoardinthedaytodayoperationoftheRegionalProductionUtility.StaffwouldincludeaGeneralManagerorExecutive,FinancialOfficer,ChiefEngineer,HumanResourceManager,andLegalManager.

BasedonfeedbackfromCIRDWCmembersandBlack&Veatch’sexperience,importantcommitteeswouldlikelyinclude:

● ExecutiveCommittee

● Planning/TechnicalCommittee

● FinanceCommittee

VotingRights–DuringthestakeholderinputphaseoftheStudy,amajorityofmembersagreedthatitwouldbereasonabletoassignagreaterweightintermsofvotingandgovernancetolarger(intermsofpopulation,usage,orotherwater‐relatedfactors)communities.WiththeNetValueanalysisaligningmembersonanequalbasisintermsofnetvaluepermgd,itcouldbepossibletoapportionvotesinseveralwaysasagreedtoatthefoundingoftheRegionalProductionUtility.Examplesincludeusingthetotalnetvaluecontributedbymembersorpopulation.

GrowthofRegionalSystem–Growingtheregionalwatersysteminanefficientmannertothebenefitofallmemberswillbeanimportantconsiderationformembers.Thisincludesissuessuchasratesandcharges,financingofexpansionimprovements,andserviceissues.Intermsoffinancinggrowth,memberswillneedtodecideonwhethertoadoptan“allin”approachwhereallmembershelpwithexpandingthecoresystemtothebenefitoftheregion,orwhethertofinanceexpansionprojectsthatarerecoveredonlyfromentitiesthatrequiretheexpansion.

1.7.3 Governance Alternatives 

DuringthestakeholderinputphaseoftheStudy,manyoftheCIRDWCmembersstatedthatthecurrentgovernancestructureoftheDesMoinesMetropolitanWastewaterReclamationAuthority(WRA)waseffective.MostoftheCIRDWCmembersparticipateasmembersoftheWRABoardthatoverseestheoperationoftheregionalwastewatersystem.Black&VeatchevaluatedseveralgovernancealternativesthatcouldbeconsideredbyCIRDWCmembers.Thesealternativesarediscussedbelow:

TraditionalAuthority–ThisalternativeismostcommoninBlack&Veatch’sexperienceandisalsosimilartothefamiliarWRAmodel.Inthisalternative,theBoardhasresponsibilityforthecorefunctionsoftheutility,includingfinancial,operational,planning,andregulatoryfunctions.Membersaretypicallyappointedbygoverningbodiesofthecommunitiesthatareservedbytheutility.Aprofessionalstaffmanagesthedaytodayoperationoftheutility.

ModificationofCurrentGovernanceArrangement–OnealternativetomovingfullytoaRegionalProductionUtilitycouldbeamodificationofthecurrentregionalwaterservicearrangement.Currently,managementofregionalwaterproductionandtransmission,financeandrates,and

Page 20: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  14

otherimportantfunctionsareoverseenbytheDMWWBoardofDirectors.Modificationstothisarrangementcouldbemadetoallowregionalentitiesmoreinputintotheoverallgovernanceoftheregionalwatersystem.

PublicPrivatePartnership–ThisalternativegovernanceoptioncouldtaketheformofaleasearrangementbetweenDMWWandaprivateorinvestor‐ownedutility.Theadvantagesofthisalternativegovernanceoptioncouldinclude1)retainownershipofassets;2)leasepaymentstoDMWWandpurchasedcapacitycustomers;3)potentialoperationalcostsavings;and4)mitigationofpoliticaldifferencebetweenregionalentities.Thepotentialdrawbackstothisgovernancealternativeare1)lossofcontrolinregionalwatersupplydecisions;2)potentialhigherratesduetorequiredhigherreturnoninvestment;and3)minimalinputintoregionalplanning.

1.8 CONCLUSION Black&VeatchwasretainedbyCIRDWCtostudyseveralimportantaspectswithrespecttopotentiallyformingaRegionalWaterProductionUtilityfortheGreaterDesMoinesregion.InitialtasksfocusedonreceivinginputfromCIRDWCmembersandincludedstakeholderinputandaSWOTanalysis.Anestimatedvaluationandfiveyearprojectionofpotentialrevenuerequirementswasderivedtodevelopaneffectivewaterrateper1,000gallonsformemberstocomparewiththeircurrentrate.GovernanceparameterswereanalyzedtounderstandissuesthatmemberswillhavetoagreetobeforeformingtheRegionalProductionUtility.

FromBlack&Veatch’sperspective,thisfirststepatevaluatingthepotentialforformingaRegionalProductionUtilityhasprovidedvaluableinformationforCIRDWCmembers.Thisinformationincludes:

ConsolidatedCIRDWCmemberinputintothepositiveandnegativeaspectsofformingaRegionalProductionUtilityversusthecurrentregionalarrangement.

Anestimatedvaluationofregionalproductionassets.

ANetValueanalysisthatestablishesmemberscomingintotheRegionalProductionUtilityonanequalbasis.

AnestimatedeffectivewatertreatmentandtransmissionrateforCIRDWCmemberstocomparetotheirexistingrates,aswellasfuturefinancialconsiderationsforbothgrowthandnon‐growthentities.

Considerationofgovernancecriteriasuchasboardresponsibilities,potentialcommittees,andpotentialweightedvotingoptions.Additionallyconsideredgovernancealternativestothecurrentregionalmethodforsupplyingwatertotheregion.

FromBlack&Veatch’sperspective,noneoftheinformationderivedduringthisStudyappearstobea“dealbreaker.”However,werealizethatCIRDWCmemberswillneedtodigesttheinformationandconsiderthebestpathforwardfortheircommunities.IfCIRDWCmembersdeterminethattheresultsofthisStudyarefavorableformovingforward,Black&Veatchwouldrecommendthefollowing:

Page 21: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Executive Summary  15

AdditionalevaluationanddiscussionofissuesraisedinthisStudybysub‐committeesoftheCIRDWCBoard.Thiscouldincludesub‐committeesfocusedonStudyelementssuchasfinancial,technical,andgovernanceissuesshouldCIRDWCmembersdecidetocontinuemovingforward.

Futurestepscouldincludeadditionalfinancialandlegalduediligencetoprovideamoredetailedfeasibilityassessment;draftingofmemorandumofunderstandingthatoutlineskeyprinciplesofaRegionalProductionUtility;andpublicinput.

Page 22: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Introduction  16

2 Introduction 

2.1 PARTICIPANTS DesMoinesWaterWorks(DMWW)provideswatertoapproximatelytwenty‐twosuburbancommunitiesandwaterdistrictsintheGreaterDesMoinesregion.Table1‐1isalistofthesecommunitiesandthecurrenttypeofserviceand/oragreementeachcommunityhaswithDMWW.EachofthecommunitiesshowninTable2‐1hastheopportunitytoparticipateinthenewRegionalProductionUtility.ThelastcolumninthetableindicatescommunitiesthathaveexpressedpotentialinterestinjoiningaRegionalProductionUtilityviaparticipationinthisStudyforCIRDWC.

Table 2‐1 Full Service and Wholesale Customers of DMWW 

COMMUNITY 

TOTAL  

SERVICE  

AGREEMENT WHOLESALE

PURCHASED 

CAPACITY 

REGIONAL 

UTILITY  

PARTICIPANT(a) 

Alleman 

Altoona 

Ankeny 

Berwick 

Bondurant 

Clive 

Cumming 

Greenfield Plaza 

Johnston 

Norwalk 

Pleasant Hill 

Polk City 

Polk County Benefited Water District 

Polk County RWD 1 (b) 

Runnells 

Unincorporated Warren County 

Urbandale 

Warren Rural Water 

Waukee 

West Des Moines 

Windsor Heights 

Xenia (b)  (a) Des Moines Water Works is a CIRDWC member and participant in this Study. 

Page 23: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Introduction  17

(b) Polk County RWD has reached an agreement to sell its purchased capacity to Xenia. As of the date of this report, the transaction has not been approved by the DMWW Board of Trustees. 

Forcommunitiesthathaveatotalserviceagreement,DMWWprovidesservicessuchasdistributionsystemoperation,maintenanceandreplacementofmainsandcustomerservice.ItisassumedthatDMWWwouldcontinuetoprovidetheseservicestothesecommunitiesifaRegionalProductionUtilitywasformed.Wholesalecustomersaresuppliedwaterthroughoneormoremastermeters.WholesalecustomershadtheoptioninthepasttopurchasecapacityinDMWW’ssystem.Thisupfrontinvestmentininfrastructureessentially“buysdown”thecommunity’srateforwholesalewaterbyeliminatingthereturnoninvestedcapitalcomponentoftheDMWWwholesalerate.Table2‐1indicateswhichwholesalecustomerscurrentlyhavepurchasedcapacityfromDMWW.IfaRegionalProductionUtilityisformed,thisStudyassumesthatthesepurchasedcapacitycontractswillbeeliminatedandwaterwillbeprovidedbythenewRegionalProductionUtility.ForcommunitiesthatdidnotparticipateinthisStudysponsoredbyCIRDWC,thisStudyassumestheywillcontinuetoreceivetheirwaterfromDMWWviathenewRegionalProductionUtility.

2.2 SCOPE OF WORK TheStudywasconductedpertheScopeofWorkoutlinedintheConsultingServicesAgreementbetweenBlack&VeatchandCIRDWCdatedJune27,2014.ThegeneralelementsoftheScopeofWorksareasfollows:

Collectandreviewdatarelatedtofinancial,operational,andassetinformationtogainanunderstandingofthecurrentmethodologyusedtoprovidedrinkingwaterservicetotheGreaterDesMoinesregion.

ConductstakeholderinputsessionswithCIRDWCmemberstogainanunderstandingoftheircurrentoperations,aswellastoreceivetheirinputwithrespecttotheStudyandtheformationofapotentialregionalwaterproductionentity.

ConductSWOTanalysiswithCIRDWCmemberstounderstandthebenefitsanddrawbacksofformingaRegionalProductionUtilityversusthecurrentwholesaleservicearrangement.

PerformestimateoffairmarketvalueofassetsthatwouldcomprisetheRegionalProductionUtilityusingtheCostApproachmethodologyofvaluation.

PerformafinancialanalysistodeterminethepotentialimpactonwholesalecustomerratesunderaRegionalProductionUtility.

Evaluatethreepotentialgovernancealternatives,includingissuesofpotentialboardcomposition,votingrights,andresponsibilities.

AttendCIRDWCmeetingstobriefCIRDWCmembersonprogressoftheStudy.

Page 24: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Stakeholder Input and SWOT Analysis  18

3 Stakeholder Input and SWOT Analysis 

3.1 STAKEHOLDER INPUT InJulyof2014,Black&VeatchmetwithCIRDWCmemberstobetterunderstandissuessurroundingthepotentialdevelopmentofaRegionalProductionUtility,andtoallowmemberstheopportunitytoprovideinputintothedevelopmentoftheStudy.TheinputfromCIRDWCmemberswasalsovaluableforpreparingandconductingtheStrengths,Weaknesses,Opportunities,andThreats(SWOT)Analysisthatwillbediscussedsubsequently.Thefollowingprovidesalistofthecommunitiesand/ororganizationsthatBlack&Veatchmetwithtoreceivestakeholderinput:

WestDesMoinesWaterWorksandCityofWestDesMoines DesMoinesWaterWorksandCityofDesMoines PolkCounty CityofJohnston CityofWaukee CityofPleasantHill XeniaRuralWater UrbandaleWaterWorksandCityofUrbandale CityofNorwalk WarrenCountyRuralWater CityofBondurant CityofAltoona CityofAnkeny CityofPolkCity CityofWindsorHeights CityofClive

3.1.1 Input 

PriortomeetingwithCIRDWCmemberstoreceivetheirinput,Black&Veatchpreparedaquestionnairetoallowmemberstoconsidercertainissues,aswellastoprovidebasicinformationontheirrespectivecommunitiesand/orutilities.ThequestionnaireisprovidedforreferenceinAppendixA.Keyelementsofthequestionnaireincludedunderstandingthecharacteristicsofeachcommunityorutility.Thesecharacteristicsincludeditemssuchas1)currentandgeneralconfigurationofindividualentity’swatersystem;2)numberoftypesofwaterutilitycustomers;3)annualandpeakwaterusage;4)numberofemployees;and5)annualbudget.ThisinformationwasimportantasitallowedBlack&VeatchtounderstandthescopeandsizeofmembersthatrequirewaterserviceintheGreaterDesMoinesregion.

Thenextcomponentofthequestionnairewasrelatedtounderstandingeachentity’sstrategy,particularlyrelatedtoprovidingwaterservice.Itemsinthissectionofthequestionnairefocusedonunderstandingwhetherthecommunityinquestionhadastrategicplan;estimatedgrowthtounderstandpotentialfuturewaterneeds;plansformeetingfuturewaterneeds;andgeneralinputrelatedtothecurrentquantityandqualityofthewatersuppliedtocustomers.

TheRegionalizationsectionofthequestionnaireprimarilyfocusedonreceivinginputaboutthebenefitsanddrawbacksofapotentialRegionalProductionUtility.Thus,memberswereaskedto

Page 25: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Stakeholder Input and SWOT Analysis  19

providetheiropinionastowhatwouldbethreebenefitstoformingaRegionalProductionUtility;andconversely,whatwouldbethreefearsordrawbackstoformingaRegionalProductionUtility.Additionally,memberswereaskedtoprovidetheir“bestcase”scenarioforprovidingwaterservicetotheregion.

ThenextsectionofthequestionnairefocusedongovernanceofthepotentialRegionalProductionUtility.Memberswereaskedtoprovideinputonseveralgovernanceparametersincluding1)generalstructureofgoverningBoard;2)levelofdaytodayinputoftheentityinthepotentialgoverningBoard;3)numberofmembers,professionalbackground,andgeographicalrepresentation;4)keyfocusareasandresponsibilitiesofpotentialBoard;and5)frequencyofpotentialBoard’smeetings.

Thequestionnairealsoincludedasectiononwatersupplytounderstandeachmember’sconcernsandinputrelativetothecurrentmethodofsupplyingwater.Questionsinthissectionfocusedonthestabilityofthecurrentwatersupply;themember’sabilitytocontributetotheregionalwatersupply;theprosandconsofthecurrentwatersupplysituation;thepotentialbenefitswithrespecttosupplyfromformingaRegionalProductionUtility.

TherewasalsoasectiononFinancialandRateissuesforeachmembertoprovideinput.ThepurposeofthissectionwastounderstandthecurrentratesthatmemberspaytoDMWWforwaterservice,aswellasunderstandingtheratesthateachmemberchargesitsowncustomersforoverallwaterservice.Additionally,memberswereaskedtheiropinionofthevalueofwaterserviceprovidedbyDMWW,aswellastheiropinionontransferringtheirwaterproductionassets,ifany,toanewproductionentity.

AsectionrelatedtoPublic/StakeholderinputwasincludedinthequestionnairetoreceivefeedbackrelatedtowhateachmemberwouldhavetodointermsofpublicoutreachshouldaRegionalProductionUtilitybepursued.Thisincludedunderstandingtheprocessforeducatingcitizens,andwhatstepswouldberequiredforamembertoreceivethenecessarypermissiontojoinanewRegionalProductionUtility.Aquestionwasalsoaskedtogaugewhethermembersarealreadyparticipatinginotherregionalinitiatives.

Finally,memberswereprovidedaperiodoftheinterviewtoprovidetheirowninputifnotalreadycoveredaspartofthequestions.Thisallowedmemberstoeitherre‐emphasizeimportantelementsoftheStudy,oraddnewitemstodiscusswithBlack&VeatchrelativetotheStudy.

3.1.2 General Takeaways 

Basedonthefeedbackreceivedfrommembersaspartofthestakeholderinput,thefollowingaregeneraltakeawaysderivedbyBlack&Veatchfromtheinterviews.Itshouldbenotedthatthetakeawaysbelowdonotnecessarilyreflectaunanimousopinionofallmembers,butaregeneraltakeawaysthatarederivedfromfeedbackfromseveralmembersduringourinterviews.

ThemajorityofmembersthatcurrentlyreceivetheirwaterservicefromDMWWareexpectingsteadygrowthinpopulationoverthecomingyears.

TherearemultipleplanninginitiativesforgrowthandeconomicdevelopmentbeingconductedthroughouttheDesMoinesmetroarea.WhilecommunicationbetweenDMWWandregional

Page 26: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Stakeholder Input and SWOT Analysis  20

communitiesdoesoccurwithrespecttowaterissues,thereisnocoordinated,regionalplanningwithrespecttodevelopingfuturewatersupplytomeetprojecteddemands.

CurrentwholesalecustomersareveryinterestedinhavingmoreofasayinthefuturedevelopmentandprovisionofwaterserviceinthegreaterDesMoinesregion.

Generally,membersindicatedthatgovernancewithproportionaterepresentationwouldbeacceptableinanynewregionalwaterproductionentity.Therewereasmallnumberofparticipantsthatadvocatedforaonemember,onevoteapproachtogovernance.

CurrentwholesalecustomersexpressedfrustrationwithDMWW’scostofservicestudyandratesettingapproach;however,therewasnotanoverarchingviewthattheyarereceivingpoorvalue.Inseveralinstances,wholesalecustomersindicatedtheyarereceivinggoodvalueatthecurrentrate.

MembersindicatedthatdealingwithDMWWonoperationalissuesisveryeasyandprofessional.

MembersindicatedthatthefinishedwaterqualitytheyreceivefromDMWWisgenerallyverygood.

Membersindicatedthatthereisaconcernabouthowfuturewatersupplyandadditionalcapacitywillbedevelopedunderthecurrentframework.

TheinputfromCIRDWCmembersalsoprovidedissuestobefurtherassessedduringaStrengths,Weaknesses,Opportunities,andThreats(SWOT)analysistobeconductedaspartoftheStudy.Basedonthestakeholderinput,severalimportantquestionswereidentifiedbyBlack&Veatch:

WouldagovernancemodelthatissimilartothatusedtoprovidewastewaterservicetothegreaterDesMoinesareabeappropriateorapplicableforapotentialregionalwaterproductionentity?

Wouldthelevelofrepresentationchangeovertimedependingonchangestowaterusage,numberofcustomers,etc.?

Howcanthecurrentcostofserviceandrateprocessbeimproved?

WhatisthebeststructureforaddressingfuturewaterqualityandquantityissuesforthegreaterDesMoinesregion?

3.2 SWOT ANALYSIS AspartoftheStudy,SWOTanalysiswasperformedwiththeCIRDWCmembers.TheSWOTanalysiswasconductedonSeptember12,2014attheDesMoinesBotanicalGarden.CIRDWCmemberswerenotifiedoftheSWOTworkshopinadvanceandtherewasattendancefromamajorityofCIRDWCmembersparticipatingintheStudy.AsummaryofthepresentationmaterialsisincludedinAppendixB.

ASWOTanalysisisastructuredplanningmethodusedtoevaluatethestrengths,weaknesses,opportunities,andthreatsinvolvedinaprojectorinabusinessventure,inthisinstanceapotentialbusinessventurerelatedtoaregionalwaterproductionentity.ASWOTexerciseprovidesthestructuretoallowallparticipantstovoicetheirthoughts,opinionsandconcernsrelatedtopotentialbusinessventure.Italsoinvolvesidentifyingtheinternalandexternalfactorsthatarefavorableandunfavorabletoachievetheobjectiveofthebusinessventure.

Page 27: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Stakeholder Input and SWOT Analysis  21

Figure1providesavisualdepictionforassessingapotentialbusinessventure.ThefollowingaregeneraldefinitionsrelatedtotheSWOTcomponents:

Strengthsareinternalcharacteristicsorissuesthatgivetheprojectorbusinessventureadvantageoverothers

Weaknessesareinternalcharacteristicsorissuesthatplacetheprojectorbusinessventureatadisadvantage

Opportunitiesareexternalcharacteristicsorissuesthatgivetheprojectorbusinessventureadvantageoverothers

Threatsareexternalcharacteristicsorissuesthatplacetheprojectorbusinessventureatadisadvantage

Figure 1 SWOT Analysis Matrix 

CIRDWCmembersweredividedintofourseparategroupsofapproximatelyeighttoninemembers.Ingeneral,Black&VeatchrequestednomorethantwoparticipantsfromeachCIRDWCmembertoprovideforabalancedandcandiddiscussion.Thefourseparategroupswerealsogenerallymixedtoprovidebalancedgroupsthatreflectthevariousentitiesthatcomprisethecurrentarrangementforprovidingregionalwater,i.e.,DMWW,wholesalecustomers,andtotalservicecustomers.Black&VeatchandHRGreenservedasfacilitatorsforthefourgroups,andanoverallfacilitatorfromBlack&Veatchmovedfromgrouptogrouptoresolveanyquestionsandkeepthegroupsonschedule.

Themorningportionofthedaylongsessionfocusedongeneratingthestrengths,weaknesses,opportunities,andthreatsofprovidingwaterunderthecurrentsituation.Thegroupsfocusedongeneratingfiveideasand/orconceptsforeachSWOTmatrixoption.Theafternoonsessionfocusedongeneratingthestrengths,weaknesses,opportunities,andthreatsofprovidingwaterunderapotentialRegionalProductionUtility.Aswiththemorningsession,thegroupswereaskedto

Strengths Weaknesses

Opportunities Threats

Helpful Harmful

Internal

External

Page 28: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Stakeholder Input and SWOT Analysis  22

generateapproximatelyfiveideaand/orconceptsforeachSWOTmatrixoptionunderthisscenario.

BasedontheideasandconceptsgeneratedforeachSWOTmatrixoption,andforeachscenario,Black&Veatchcompiledtheresultsandassessedcommonthemesthatarosefromthesmallgroupsessions,comparingthethemesbetweenbothscenarios(currentscenariowherewaterisprovidedbyDMWWtowholesaleandretailcustomersvs.waterprovidedbyanewRegionalProductionUtility).Thesecommonthemeswerepresentedtotheentiregroupattheendofthedayforreview,clarification,anddiscussion.Asummaryofthethemesbyscenarioispresentedbelow:

STRENGTHS 

Current 

Staff Responsible and Knowledgeable  Reliability of finished water  Currently finished water quality is good  Redundancy  Multiple sources of supply 

Ability of customer communities to make 

independent decisions 

Opportunity to choose level of service  Knowledge of defined capacity limits for each 

community

Regional Production Utility

More equal representation with regards to 

governance, planning, and rates 

More political influence at regulatory level 

More political stability on governing board 

Potential long‐term cost efficiencies (direct and 

indirect) 

Regional planning  Provide relative savings – slow the rate of increase

ThecurrentstrengthsreflectthatDMWWstaffareknowledgeableandprovidereliableandqualityservice.ThecurrentsituationalsoallowsforwholesalecustomerstomakeindependentdecisionsunderthedefinedcapacitylimitsthattheyhaveestablishedwithDMWW.ThestrengthsrelatedtoapotentialRegionalProductionUtilityreflectgreaterrepresentationfromaregionalperspectiveforgovernance,planning,andrateissues.Additionalstrengthsincludegreaterpoliticalstabilitywithrespecttogovernance,andgreaterpoliticalinfluencewithrespecttoregulatoryandpoliticalissuesthatmayimpactregionalwaterissues.

WEAKNESSES 

Current 

Autocratic governance of water supply and production 

No current Board representation of customer 

communities 

No accountability to customer communities for how 

resources are spent or decisions made 

Source water quality  Source water quantity  Competing priorities for responding to regional 

growth 

Availability of purchased capacity to meet growth

Regional Production Utility

Size of governing body  Source water quality and quantity are still issues  Change in workforce impacting level of service 

Cost versus investment – long term change over 

short term pain 

Buy‐in costs  Conflict between growth and reinvestment 

Right now we know who to blame 

 

Page 29: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Stakeholder Input and SWOT Analysis  23

Forthecurrentsituation,weaknesseswereidentifiedaslackofregionalrepresentationwithrespecttogovernanceandplanningissues.Additionalweaknessesincludepollutantsimpactingthesourcewater,lessthanrobustsourcewaterquantityduringpeakdemandperiods,anduncertaintywithrespecttomeetingfuturedemandswithaninabilitytopurchasemorecapacityfromDMWW.TheweaknessesrelatedtoaRegionalProductionUtilitycouldincludeamorediversegoverningbodythatmaypresentchallengeswithbuildingconsensus.Additionally,theremaybeupfrontcostsrelatedtothetransactionthatcouldmakeserviceviaaRegionalProductionUtilitycostprohibitive.

OPPORTUNITIES 

Current 

Improve current processes 

Individual communities continue to make 

independent decisions 

More inclusive governance and geographic diversity 

of Board 

Ability to improve watershed management

Regional Production Utility

Ability to influence quality and quantity  Long term bonding capability 

Predictability on revenue and costs  Better control over resources  Consistent message communicated with customers 

Input into regional economic development

Underthecurrentsituation,membersindicatedthatthereareopportunitiesforimprovingcurrentprocesses,e.g.,ratemethodology.However,theopportunitieswouldbepursuedviamultiplegoverningBoardsactingindependently.ForthepotentialRegionalProductionUtility,membersviewedopportunitiesasbeingamorecoordinatedapproachtocontrollingwaterproductioncostsandassociatedrates.Theyalsoviewedamorecoordinatedapproachtoaddressorinfluencewaterquantityandqualityissuesfacingtheregion.

THREATS 

Current 

Competing interests for same source water 

Division/breakup of current customer configuration 

Availability of capacity to meet customer community 

needs 

Nonpoint source pollution impact on source water 

Climate issues

Regional Production Utility

Initial cost of buy‐in  Less than 100% participation from communities 

Perception of reduction in work force  Loss of local control  Failure to meet customer expectations 

Nonpoint source pollution impact on source water 

Climate issues

ThemainthreatsfacingthegreaterDesMoinesregionunderthecurrentsituationconsistsofevengreatercompetitionforaccesstotheregion’ssourcewater.Thisisinadditiontononpointsourcepollutionandclimateissuesthattheregionisfacingthatlimittheavailabilityandqualityofsourcewater.FromaRegionalProductionUtilityperspective,thenonpointsourcepollutionandclimateissuesremain,however,otherthreatsconsistofthebreakupofthecurrentcustomerconfigurationwhichcouldimpacttherevenuesandexpensesofvariousmembersinanegativemanner.

3.2.1 Input Into Feasibility Study 

TheSWOTanalysisprovidedmemberstheabilitytovoicetheirconcernsandopinionsastomovingfromthecurrentmethodofprovidingwaterproductionservicetoonewherewaterserviceispotentiallygovernedandperformedviaaRegionalProductionUtility.Forpurposesofthisstudy,Black&Veatchwasalsoaskedtoperformafinancialanalysistoderiveanestimateoftheuniform

Page 30: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Stakeholder Input and SWOT Analysis  24

ratethatwouldbeapplicabletoallCIRDWCmembersshouldapotentialRegionalProductionUtilitybeformed.Black&VeatchwasalsoaskedtoevaluatethreeseparategovernancealternativesthatcouldbeusedbythepotentialRegionalProductionUtility.Inperformingthesetasks,Black&VeatchusedtheSWOTanalysisasabasisforunderstandingwhetherouranalysis1)sustainedstrengthsormitigatedcurrentweaknessesidentifiedbythemembers,and2)enhancedordidnotpreventthemembersfromtakingadvantageofregionalopportunitiesormitigatingexternalthreats.

Additionally,thesummaryoftheSWOTanalysisispresentedinthisreportasareferencepointforthemembersastheycontinuetheirdiscussionsaroundaRegionalProductionUtility.WhilethisStudyprovidesanimportantfirststepindeterminingthemeritsofaRegionalProductionUtility,additionalworkanddiscussionbetweenthememberswillhavetobeperformedshouldthemembersdecidetocontinuedownthepathtowardaRegionalProductionUtility.TheissuesraisedduringthisSWOTanalysisprovideabasisforfuturediscussionsand/ordocuments.

Page 31: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  25

4 Valuation Estimate WhenassessingthefeasibilityofcreatingaRegionalProductionUtility,considerationmustbegiventotheestimatedvalueofwaterproductionandtransmissionassetsthatwouldcomprisethenewentity.Astherearemultipleutilitiesthatwouldpotentiallycontributeassetstothenewentity,thescopeofworkforthisengagementwascraftedtoprovideCIRDWCwithanestimatedvaluebasedontheCostApproachmethodologyofutilityvaluation.TheCostApproachprovidesanindicationofassetvaluebasedon1)theoriginalcostofinvestmentmadebycurrentownerstoconstructthecurrentsystem,and2)thereplacementcostthatapotentialbuyerwouldhavetoinvesttoconstructanessentiallysimilarwaterproductionsystem.Inbothinstances,Black&Veatchfactorsinestimateddepreciationtorecognizethatovertime,assetsdecreaseinvaluebasedonfactorssuchaswearandtear,actionoftheelements,andobsolescence.InBlack&Veatch’sexperience,areasonableestimateoffairmarketvaluebetweenawillingbuyerandsellerwouldfallsomewherebetweentherangeoforiginalcostlessdepreciation(OCLD)andreplacementcostlessdepreciation(RCLD).OthervaluationapproachessuchastheIncomeApproachandMarketApproachwerenotfactoredintothevaluationestimateduetocostconstraintsofthestudy.InBlack&Veatch’sexperience,theIncomeApproachandMarketApproachwouldgenerallyhelptobetterrefinetheoverallvaluewithintheOCLDandRCLDrange.Anappraisaloflandisalsonotincludedinthevaluationestimate.

Thefollowingsectionsoutlinetheapproachtoderivethevaluationestimate.Thegeneralapproachwasto1)definethepotentialassetstobetransferredfromcurrentutilitiestothenewRegionalProductionUtility;2)determineOCLD;and3)determineRCLD.ThisapproachprovidesCIRDWCwithanestimatedrangeofvalueforregionalwaterproductionassets,alsoprovidesvaluableinputforconductingthefinancialanalysisdescribedlaterinthisReport.

4.1 DEVELOPMENT OF ASSET INVENTORY Black&VeatchworkedwithCIRDWCmemberstoidentifywatersystemassetsthatwouldtransfertoaregionalwaterproductionutility.Assetswouldincludeallsourcesofsupply,watertreatmentplants(WTP),transmissionmains,pumpingfacilities,andstoragetanksforsupplyingfinishedwatertotheindividualentities.

Oneofthegoalsofregionalizationistohaveaconsolidatedapproachfordevelopingrawwatersourcesandprovidingtreatedwater.Productionfacilitiesforallmemberswouldbeincludedintheregionalentityandwerethereforeincludedaspotentialassets.Productionfacilitiesweredeterminedtoincludetreatmentfacilitiesandaquiferstorageandrecovery(ASR)wells.ASRwellswereincludedduetothebasisthattheyfunctiontoprovidefinishedwaterintothesystemandoffsetdemandfromothertreatmentfacilitiesduringpeakdemandperiods.

Generally,transmissionmainsandstorageassetsweredeemedtobeeligibleforinclusionintotheregionalutilityifthatassetserved(orhadtheabilitytoserve)morethanoneentity.DMWWhaspreviouslyidentifiedaCoreNetworkoftransmissionmains,storagetanks,andpumpingfacilitieswhichitusestosupplyfinishedwaterthroughouttheGreaterDesMoinesregion.TheseCoreNetworkfacilitieswereidentifiedasassetsthatwouldbetransferredtotheRegionalProductionUtility.However,individualcommunitydistributionsystemsthatprovidemoredirectservicetocustomers,includingpumpstations,distributionmains,andstoragetanks,werenotincludedaspotentialassets.

Page 32: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  26

4.1.1 Asset Inventory 

AssetsgenerallyincludedinthevaluationareshownonthemapinAppendixCandsummarizedinTables4‐1through4‐3below.ThesephysicalassetsweredeterminedbasedonpreliminarydiscussionswithCIRDWCmembers.IndividualrawwatersourcesarenotidentifiedintheTables,butthesesourceswouldbeincludedaspotentialassetsandareincludedaspartofeachrespectivetreatmentfacility.Thefollowingsectionsprovideabriefoverviewoftheassets.

4.1.1.1 City of Altoona 

TheCityofAltoona(Altoona)haspurchasedcapacityfromDMWWbutdoesnotcurrentlyutilizetheinterconnection.Instead,AltoonameetsallitsdemandsusingthreeWTPs,eachwithsimilarsourceandtreatmentcomponents.FourdeepJordanaquiferwellssupplythewatertotheWTPs.Treatmentconsistsofaeration,pressurefiltration,ionexchangesoftening,andchlorination.WTPNo.1isfedfromWellNo.1andWellNo.2;WTPNo.2andWTPNo.3areeachsuppliedfromasinglewell.Theionexchangeprocessremovescalciumandmagnesiumionstoprovidesofteningbutdoesnotremovetotaldissolvedsolids(TDS)andsulfates.TDSandsulfatesdonothaveanyprimarydrinkingwaterlimits,butdohavesecondarylimitsassociatedwithtasteandodors(aesthetics).

Altoona’sWTPsarenotcurrentlylocatedadjacenttoanyCoreNetworkpiping.However,basedonthe2013WaterSystemMasterPlanconductedbyBlack&Veatch,theWTPsarenearcapacityandarethereforenotlikelytohaveasignificantamountofadditionalcapacitytosupplywateroutsideAltoona’sdistributionsystem.However,itisrecognizedthatduringpeakdemandperiodsfortheregion,theseWTPssupplyasignificantamountofwaterthatotherwisewouldlikelyhavetobesuppliedbyDMWW.

ThetotaltreatmentproductioncapacitiesofAltoona’sthreeWTPsareshowninTable4‐1below.

4.1.1.2 City of Ankeny 

TheCityofAnkeny(Ankeny)haspurchasescapacityfromDMWWandusesthistomeetthemajorityofitsdemands.AnkenyalsohastwodeepJordanaquiferwellsthatareusedasASRwellstomeetseasonalpeakdemands.ThetwoASRwellsareincludedasapotentialassettotheregionalutility.NeitherwellislocatedadjacenttotheCoreNetworkpipingandthesupplyfromthesewellswouldmostlikelybeusedexclusivelyintheAnkenydistributionsystem.However,itisrecognizedthatduringpeakdemandperiodsfortheregion,theseASRssupplyasignificantamountofwaterthatotherwisewouldlikelyhavetobesuppliedbyDMWW.

ThetotalproductioncapacityoftheASRwellsisshowninTable4‐1below.

4.1.1.3 Des Moines Water Works 

4.1.1.3.1 Source of Supply and Treatment Assets 

DesMoinesWaterWorks(DMWW)ownsandoperatesthreeWTPfacilitiesandtwoASRwellstosupplywaterthroughouttheGreaterDesMoinesregion.

ThethreeWTPfacilitiesconsistoftheFleurWTP,L.D.McMullenWTP(McMullenWTP),andtheSaylorvilleWTP.Sourceofsupplyforallthreefacilitiesconsistsofdirectsurfacewaterandgroundwaterunderthedirectinfluenceofsurfacewater.TheFleurandMcMullenWTPsutilize

Page 33: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  27

lime/sodaashsofteningwithconventionalfiltrationanddisinfectionfortreatment.TheSaylorvilleWTPutilizesultra‐filtration(UF)membranefiltersandreverseosmosis(RO)membranesoftening.

TheFleurWTPutilizestworiverintakesalongtheRaccoonRiverandDesMoinesRiver,witheachintakecapableofsupplyingupto100mgdinrawwatertotheWTP.TheFleurWTPalsoutilizesariverbankstyleinfiltrationgalleryalongtheRaccoonRiverwhichpullswaterfromtheriverandprovidesriverbankfiltrationtolimitturbidityandothersuspendedsolids,whilesimultaneouslyprovidingsomedenitrification.Thecapacityoftheinfiltrationgalleryvariesfromapproximately10mgdto20mgddependingontheriverlevel.Rawwaterfromthetworiversourcestypicallypassesthroughpresedimentationforturbidityandtotalorganiccarbon(TOC)removal.DMWWcanalsobypasspresedimentationandsendflowdirectlytothesofteningbasins.ThetotalcapacityoftheFleurWTPisapproximately75mgd,whichislimitedbythefiltrationcapacity.Firmcapacityisapproximately70mgd,whichislimitedbyfiltrationandsofteningcapacity.

TheMcMullenWTPcurrentlyusesradialandhorizontalalluvialwellsandtwosurfacewatersources(CrystalLakeandMaffittReservoir).Allrawwateristreatedthroughsolids‐contactsofteningbasinsandfiltration.TotaltreatmentcapacityoftheMcMullenWTPis25mgdandfirmcapacityis12.5mgdwithoneofthetwosofteningbasinsoutofservice.

TheSaylorvilleWTPusestworadialcollectorwellstosupplyrawwatertotheWTP.Thesmallerofthetwowellsisratedforapproximately5mgd.TotaltreatmentcapacityoftheSaylorvilleWTPis10mgd.ThetreatmentefficiencyoftheUFandROmembranesisapproximately83percent,whichresultsinafirmcapacityofapproximately4.2mgd,whichislimitedbythesourcewatercapacity.

DMWWpurchasedapproximately3.235billiongallonsofstoragecapacityintheSaylorvilleReservoirfromtheArmyCorpsofEngineersintheearly1980’s.ThisstoragevolumeservesasabackupwatersupplyduringperiodsofdroughtandcanbereleasedfromthereservoirandcollectedbytheDesMoinesRiverintakedownstreamoftheSaylorvilleReservoir.

ThetotalproductioncapacityofDMWW’streatmentfacilitiesareshowninTable4‐1below.Thesecapacitiesarebasedonsourcewaterandtreatmentcomponents.DMWWisintheprocessofmakingimprovementstoincreasesourcewatercapacityattheMcMullensite,whichisanticipatedtoincreaseproductiontothetotaldesigncapacityof25mgdduringlowriverlevels.Inaddition,theUFmembranesattheSaylorvilleWTPfacilityareneartheendoftheirusefullifeandDMWWisintheprocessofreplacingthesemembranes.Oncereplaced,thenewUFmembranesareanticipatedtorestoretheoperatingcapacityoftheSaylorvilleWTPbacktoitsdesigncapacity.

DMWWoperatestwoASRwellsduringthehighsummerseasonaldemandperiod.TheASRwellsarelocatedattheMcMullenWTPsiteandtheL.P.Moonstorageandpumpstationsite.

4.1.1.3.2 Transmission Mains, Pumping, and Storage Assets 

DMWWalsooperatestheCoreNetworktotransportanddeliverwateracrossthemetroarea.Theseincludetwogroundstoragereservoirs,threestandpipes,twoelevatedstoragetanks,fivepumpstationfacilities,andapproximately134milesoftransmissionmainsranginginsizefrom12‐inchto60‐inchindiameter.ThesefacilitiesareshowninTables4‐2and4‐3below.Thestorageandpumpingfacilitieswereincludedaspotentialassetsbasedontheiroperationalfunctionalityofservingmultipleentities.

Page 34: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  28

TheDMWWCoreNetworktransmissionandpumpingassetsconsideredfortheregionalutilitycurrentlyoperatewithfivepressurezonesasdescribedbelow.Thesepressurezonesonlyincludethosethatwouldservetheregionalutility;additionalpressurezonesexisttoserveindividualentities.Thenumberingconventionusedbelowisonlyforthecontextofthisstudy.1. PressureZone1:SupplybyFleurandMcMullenWTPsandservedbyAllenHazenTowerand

PumpStation,Nollen,Tenny,andWilchinskiStandpipes.ThesystemnormallyfloatsoffthewaterlevelintheTennyandWilchinskiStandpipes.Thesystemhydraulicgradeline(HGL)normallyoperatesabovetheleveloftheAllenHazenTowerandNollenStandpipe.

2. PressureZone2:SupplybySaylorvilleWTPandPolkCountyPumpStation.ThePolkCountyGroundStoragefacilityisfilledbyPressureZone1andre‐pumpedtoserveAnkeny(throughPressureZone2)andruralPolkCounty(separatepressurezone).

3. PressureZone3:SupplybyNollenStandpipethroughPressureZone1.NollenPumpStationre‐pumpstoserveportionsoftheDMWWandBondurantsystems.

4. PressureZone4:SupplythroughPressureZone1andre‐pumpedthroughEastsidePumpStationintoSharedEastsideTower.ServesPleasantHill,Altoona,andPolkCountyRWDsystems.

5. PressureZone5:SupplythroughPressureZone1andLPMoonASR.LPMoonGroundStorageandPumpStationutilizestwosetsofpumpstoservei)WDMWW’s98thStreetTowerthatservestheWDMWW,Clive,andWaukeesystems,andii)UrbandaleandXeniasystems.

FromdiscussionswithDMWW,dischargepressuresfromtheFleurWTPregularlyexceed100poundspersquareinch(psi)andcanapproach120psibasedonthedemandlocationandpointsofentryintotheCoreNetworkpiping.DMWWrecentlyinstalledacontrolvalveontheinfluenttotheWilchinskiStandpipeinordertothrottleflowintothestoragetankanddivertwaterfromtheFleurWTPtothenorthandwesternportionsoftheCoreNetworksystem.

4.1.1.4 Urbandale Water Works 

TheCityofUrbandalehaspurchasedabandonedquarrypitslocatedalongtheDesMoinesRiverthatcouldbedevelopedintoarawwatersource.Theestimatedcurrentcapacityofthequarrypitsisapproximately725milliongallons.UrbandalealsoobtainedawithdrawalratepermitfromtheIowaDepartmentofNaturalResourcestoallowwithdrawalupto30mgddirectlyfromtheDesMoinesRiver.Atthetimeofthisreport,themaximumfeasiblewithdrawallimitfromthequarrypit/DesMoinesRiversourceisnotknown,butisassumedthatthewithdrawalpermitcanbeusedtorechargethequarryasneeded.

4.1.1.5 West Des Moines Water Works 

WestDesMoinesWaterWorks(WDMWW)ownsandoperatesoneWTPfacility,theA.C.WardWTP.GroundwaterwellsfortheWTPconsistofthreedeepJordanaquiferwellsand18totalshallowalluvialwells.Thewellfieldtotalcapacityisapproximately9.9mgdandislimitedtoafirmcapacityofapproximately6.9mgdwithtwoofthethreeJordanwellsinoperation.ThelimesofteningprocesscannotremoveTDSandsulfatesthatarenaturallyoccurringintheJordanaquifer,whichcanresultintasteandodorissueswiththefinishedwater.

Page 35: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  29

TheWTPconsistsofaeration,lime/sodaashsoftening,filtration,anddisinfection.ThetotaltreatmentcapacityoftheA.C.WardWTPis12mgdandthefirmtreatmentcapacityis9mgdwithoneofthesolids‐contactsofteningbasinsoutofservice.TheWTPiscurrentlylimitedbyrawwatersourcecapacity.TheproductioncapacityofWDMWW’streatmentfacilitiesareshowninTable4‐1below.WDMWW’ssystem‐widedemandinWDMWW’sserviceareacanexceedthecapacityoftheA.C.WardWTP,withtheremainingwatersuppliedbyDMWW.

TheA.C.WardWTPisnotlocatedalonganyCoreNetworkpiping.ItisassumedforthepurposesofthisstudythatallwaterproducedbytheA.C.WardWTPwillremaininWDMWW’sdistributionsystemandnotsuppliedbackintotheCoreNetwork.

WDMWWownsanelevatedstoragetankalong98thStreetthatcurrentlyservestheWDMWW,Clive,andWaukeesystems;allthreeentitiesprovidedinitialcapitalandongoingmaintenancecostsforthestoragetank.The98thStreetESTisfedbytheLPMoonpumpstationandisoperatedbyDMWW.

Table 4‐1 Total Source and Supply Assets for Regional Utility 

PHYSICAL ASSET 

TOTAL CAPACITY/

DEMAND, MGD 

FIRM CAPACITY/ 

DEMAND, MGD 

WTP and ASR Supply Facility Capacity 

Altoona ‐ WTP No. 1  1.30 0.58 

Altoona ‐ WTP No. 2  1.30 0.00 

Altoona ‐ WTP No. 3  1.30 0.00 

Ankeny ‐ ASR No. 1  1.44 0.00 

Ankeny ‐ ASR No. 2  2.88 0.00 

DMWW ‐ Fleur WTP  75.00 70.00 

DMWW ‐ LP Moon ASR  3.00 0.00 

DMWW – L.D. McMullen WTP  25.00 12.50 

DMWW ‐ McMullen ASR  3.00 0.00 

DMWW ‐ Saylorville WTP  10.00 4.20 

WDMWW – A.C. Ward WTP  9.90 6.90 

Total WTP and ASR Capacity(a)  134.12 118.60 

2012 Maximum Day Finished Water Demands(b)

Altoona  3.90 

Ankeny  4.30 

DMWW  96.60 

WDMWW  9.90 

Total 2012 Maximum Day Finished Water Demand 114.70 

2012 Remaining Capacity  19.42 3.90 

Page 36: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  30

(a) The value of 118.6 mgd is not a summation. Total estimated firm capacity considers all production facilities in operation with one of the seven WTPs (McMullen WTP) limited to firm capacity and one 3.0 mgd ASR well out of service to account for equipment being offline for maintenance and/or repair. (b) DMWW recorded a peak day usage of 96.6 mgd during the summer months of 2012. For the purposes of this report, it was assumed that the other production facilities in the metro operated by Altoona, Ankeny, and West Des Moines were operating near full capacity.  

Table 4‐2 Distribution System Storage and Pump Station Assets 

PHYSICAL ASSET 

TOTAL CAPACITY, MG/MGD 

DMWW ‐ Allen Hazen Tower and Pump Station 2.0 MG – EST

18.5 MGD – PS  

DMWW ‐ Eastside Tower and Pump Station 2.0 MG – EST

11.5 MGD – PS 

DMWW ‐ LP Moon Ground Storage and Pump Station 6.0 MG – GST

21.5 MGD – PS 

DMWW ‐ Nollen Standpipe and Pump Station 4.0 MG – SP

20.0 MGD – PS 

DMWW ‐ Polk County Ground Storage and Pump Station 

5.0 MG – GST

10.0 MGD – PS 

DMWW ‐ Tenny Standpipe  4.0 MG – SP

DMWW ‐ Wilchinski Standpipe  2.4 MG – SP

WDMWW – 98th Street Tower  2.5 MG ‐ EST

TOTAL GROUND STORAGE  17.0 MG

TOTAL ELEVATED STORAGE  10.9 MG

TOTAL PUMP STATION  81.5 MGD

(a) EST = Elevated Storage Tank:  Allen Hazen tower effectively operates below the hydraulic grade line of the Pressure Zone 1 and therefore its capacity is considered to be ground storage capacity under normal operating conditions. (b) SP = Standpipe: Tenny and Wilchinski standpipes effectively operate as elevated storage and are therefore considered to be included in the total elevated storage capacity calculation.  However, due to their standpipe configuration their total effective capacity is significantly lower than the total capacity identified.  (c) PS = Pump Station 

Page 37: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  31

Table 4‐3 Des Moines Water Works Transmission Main Assets 

PHYSICAL ASSET 

TOTAL  

LENGTH, FT 

12‐INCH  40 

14‐INCH  20,220 

16‐INCH  104,960 

18‐INCH  300 

20‐INCH  81,260 

24‐INCH  206,950 

30‐INCH  120,180 

36‐INCH  122,210 

42‐INCH  15,160 

48‐INCH  34,280 

60‐INCH  890 

TOTAL  706,450 

4.1.2 Asset Inspection 

Black&VeatchandHRGreenconductedinspectionsofalltheproposedassetstoidentifytherelativeconditionofthefacilitiesincomparisontotheirrespectiveage.InspectionswereconductedinOctoberandNovemberof2014withtheassistanceoftheowner’sstaff.Inspectionsweremadeoftreatment/productionfacilitiesforAltoona,DMWW,andWDMWWandDMWW’sstorageandpumpstationsassignedtotheCoreNetwork.

4.1.3 Asset Review 

Areviewoftheassetswasgenerallybasedontherelativeage,condition,andtypeofmaterialfortreatment,supply,storage,andpumpingfacilities.Ingeneral,theconditionofallfacilitiesappearedtobecommensuratewiththeageofthefacility.Theageandmaterialsofconstructionwereusedtoassignanticipatedlifeexpectancy,whichfactorsintothecostdepreciationasdiscussedbelow.

Itshouldbenotedthatforthepurposesofthisstudy,noinspection,review,orhydraulicmodelingwasprovidedforthewatertransmissionmainsassociatedwithDMWW’sCoreNetworkpiping.Additionalhydraulicmodelingisrecommendedtodetermineifadditionalimprovementsarerequired.DMWWnotedthathighdistributionsystempressuresattheFleurWTPsometimescurrentlylimitthepumpingrateduringhighdemandperiodsinordertopreventwatermainbreaksonolderwatermainsduetohighpressures.

Asummaryofthestrengthsandweaknessesfortheindividualtreatment/supplyfacilitiesareincludedinTable4‐4.

   

Page 38: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  32

Table 4‐4 Treatment Asset Strengths and Weaknesses Review 

FACILITY  STRENGTHS WEAKNESSES

Altoona WTPs 

Reliableandconsistentsource Distributedfacilitiesresultinbetterhydraulicperformanceofthedistributionsystem

Softenedwater

SinglewellperWTPfacility ResidualTDSandsulfatescanresultintasteandodorissues

Ankeny ASRs 

Consistentsourceoffinishedwatertoseasonallyoffsethighfinishedwaterdemandperiods

ASRrechargeiscontingentuponadequatefinishedwaterquality

Onlyavailableseasonally

DMWW Fleur WTP 

Threesourcesofsupply(infiltrationgalleryandtworiversources)

Limesofteningprocess Multipleandflexibletreatmentsystems

Ageandcondition Limitedhypochloriteandferricchemicalstorage

Nofilter‐to‐waste Waterqualityconcernsw/DBPs

Limitedmechanicalnitrateremovalcapabilities

Locatedinfloodplain

DMWW McMullen WTP and ASR 

Limesofteningprocess ASRlocatedon‐site Treatmentcapacityexpandable

Currentlylimitedbysourcewaterquantity

Nomechanicalnitrateremovalcapabilities

DMWW Saylorville WTP 

UF/ROtreatmentprovidesconsistentfinishedwaterquality

Treatmentcapacityexpandable Fullcapacitymechanicalnitrateremoval

Currentlylimitedbysourcewaterquantity

Treatmentcapacityimpactedbyrawwatertemperatureandhardness

Unprovenadequacyofpretreatmentforsuccessfullong‐termUFmembranelife

WDMWW A.C. Ward WTP 

Reliableandconsistentsource Limesofteningprocess

Currentlylimitedbysourcewaterquantity

ResidualTDSandsulfatescanresultintasteandodorissues

4.2 ESTIMATION OF ORIGINAL COST LESS DEPRECIATION (OCLD) Asnotedabove,theassetinventorywasderivedtounderstandtheassetsthatwouldbetransferredtoanewRegionalProductionUtility.Black&VeatchrequestedinformationfromCIRDWCmembersrelatedtotheseassets,includinginformationsuchastheoriginalcostinvestedtoconstructtheassets,ifavailable.Informationwasalsorequestedwithrespecttocurrentunitcostsforitemssuch

Page 39: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  33

asmains,meters,andotherassets.Thisdatawasusedtoderiveanestimateoftheoriginalcostforvariousassettypes.AdditionalexplanationofthedevelopmentofOCLDforassetscontributedbyindividualutilitiesisprovidedinthefollowingsections.

4.2.1 Original Cost 

TheassetinventoryaboveprovidesageneraloverviewofthemajorassetsrecognizedbyBlack&VeatchasbeingnecessaryforanewRegionalProductionUtility.Generally,theseassetsincludedsourceofsupply,treatment,pumpstations,storage,transmissionmains(includingappurtenances),andwholesalemeters.

Formajorfacilitytypeassets,e.g.,wells,intakes,treatmentplants,pumpstations,etc.,Black&Veatchprimarilyusedoriginalcostinformationprovidedbytheutilitiesasabasisfortheoriginalcostestimatefortheirrespectiveassets.Forassetsinstalledmorerecently,thecostandscaleoftheassetwasreviewedforreasonableness,andingeneralBlack&VeatchutilizedthesevaluesasitsestimatefororiginalcostofmajorabovegroundfacilitiesforDMWWandWDMWW.ForAltoonaandAnkeny’sassets,theoriginalcostwasdeterminedbyestimatingthecurrentreplacementcostvalueoftheassets,andthentrendingthevaluesbacktotheirdateofinstallationusingHandy‐WhitmanBulletinNo.180:CostTrendsofWaterUtilityConstruction(Handy‐WhitmanIndex).ThetrendfactorforAnkeny’sASRwellsandAltoona’streatmentplantsisthetrendindexvaluefortheyearofinstallation,dividedbythetrendindexvalueforthecurrentyearforeachassettype.

FortransmissionmainsthatprimarilyareownedbyDMWW,availabledataconsistedofGeographicInformationSystem(GIS)datarelatedtocorenetworkmainsprovidedbyDMWW.Originalcostdatawasnotassociatedwiththisdata,therefore,Black&Veatchhadtoestimatetheoriginalcostoftransmissionmains.Todothis,anestimateofreplacementcostperfootofmainwasprovidedbyDMWWandmultipliedbythelengthofeachmainsegmenttoderivetheestimatedreplacementcostpersegmentofmainprovidedintheGIS.TheoriginalcostforeachsegmentwasthendeterminedbytrendingbackthereplacementcosttotheyearofinstallationnotedintheGISusingtrendindicesfromtheHandy‐WhitmanIndex.Thetrendfactorfortransmissionmainsisthetrendindexvaluefortheyearofinstallation,dividedbythetrendindexvalueforthecurrentyearforeachassettype.Asimilarapproachwasalsousedtoderivetheoriginalcostforwholesalemeters.

FortherawwaterquarriesownedbyUrbandaleWaterWorks,Black&VeatchprimarilyreliedonthevaluepaidbyUrbandaleWaterWorksforthequarriesandadjacentparcelsbasedoninvoicesprovidedbyUrbandaleWaterWorks.

4.2.2 Accumulated Depreciation 

AccumulatedDepreciationprovidesanestimateofthedecreaseinvalueduetofactorssuchaswearandtear,actionoftheelements,andobsolescence.ForthisStudy,Black&Veatchutilizedthestraightlinemethodfordeterminingaccumulateddepreciationforassets.

Therearetwokeyelementsneededfordeterminingstraightlinedepreciation.Thefirstistheageoftheasset.Thisdatapointwasgenerallyderivedfromassetdataprovidedbytheutilities.Theotherdatapointneededistheestimatedservicelifeforeachasset.Black&VeatchandHRGreendevelopedgeneral,estimatedservicelivesforvariousassetclasses.Thefollowingprovidesanoverviewofestimatedservicelivesformajorassets:

Page 40: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  34

Structures&Improvements–75years Wells&Springs–50years ElectricPumpingEquipment–25years LargeTreatmentPlantEquipment–30years ElevatedSteelTanks–75years ConcreteStorageReservoirs–75years Pre‐stressedConcreteTransmissionMains–100years PolyvinylChloride(PVC)TransmissionMains–50years DuctileIronTransmissionMains–75years CommunicationEquipmentandSCADA–20years LaboratoryEquipment–10years WholesaleMeters–20years

ThesegeneralservicelifeestimateswerethenreviewedforindividualassetsbasedonthesitevisitsconductedbyBlack&Veatch.IfbasedonthesitevisitBlack&Veatchdeterminedthatanalternateservicelifewasapplicable,theservicelifewasadjustedhigherorlowertoreflectourjudgmentoftheservicelifeofanindividualasset.Theaccumulateddepreciationfactortobeappliedtotheoriginalcostwasdeterminedbycomparingtheageoftheassettoitsestimatedservicelife.Theaccumulateddepreciationfactor,multipliedbytheassetoriginalcostprovidedtheestimatedaccumulateddepreciationforeachasset.

4.2.3 OCLD Results 

ThefollowingTablespresenttheresultsoftheOCLDforassetsthatpotentiallycouldbeconveyedtoanewRegionalProductionUtility.

4.2.3.1 DMWW OCLD Results 

AscanbeseenonTable4‐5,theOCLDforDMWWassetsisapproximately$210.3million.ThistotalestimatedOCLDisbrokenoutbymajorassetclass,includingsourceofsupply,treatment,boostersandstorage,transmissionmains,andmiscellaneousassets.IncludedinthemiscellaneousOCLDvalueisanestimateofgoingconcern.Goingconcerngenerallyrecognizesthatabuyerofassetswouldalsopurchasethebusinessprocesses,vendorrelationships,andotherbusiness‐relateditemsthatallowthesellertoefficientlyconductbusinessonadaytodaybasis.ForDMWW,Black&Veatchutilizedahighlevelestimateofgoingconcernofapproximately$6.2millionderivedfromDMWW’s2013operatingincome.TheMiscellaneouslineitemalsoincludesconstructionworkinprogress(CWIP)estimatetorecognizevalueincorenetworkassetsthatarealreadyunderconstructionandlikelytobeinserviceatthedateofanytransaction.

Page 41: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  35

Table 4‐5 Estimated OCLD Value of DMWW Assets 

4.2.3.2 WDMWW OCLD Results 

AspresentedinTable4‐6,theestimatedOCLDvalueforWDMWWassetsisapproximately$17.1million.ThisincludesOCLDvalueprimarilyforwells,treatmentplant,andthe98thStreetstoragereservoirasnotedaboveintheassetinventorysection.SimilartoDMWW,highlevelestimateofgoingconcernisprovidedforWDMWWinLine6ofapproximately$979,000andisbasedonWDMWW’s2013NetOperatingIncome.

Original Cost

Line Original  Accumulated

No. Description Cost Depreciation OCLD

Source of Supply

1   Des Moine River Intake $9,165,000 $4,409,100 $4,755,900

2   Fleur Infiltration Gallery $1,296,300 $937,800 $358,500

3   Maffitt Raw Water $10,307,600 $1,955,800 $8,351,800

4   Maffitt Reservoir $1,172,300 $679,800 $492,500

5   Saylorville Lake Storage $3,033,500 $0 $3,033,500

6   Saylorville WTP Raw Water $8,616,600 $448,300 $8,168,300

Treatment

7   Fleur WTP $51,413,900 $25,290,000 $26,123,900

8   Fleur Nitrate Facility $4,185,500 $2,417,600 $1,767,900

9   Fleur Laboratory $534,900 $446,500 $88,400

10   McMullen WTP $29,975,700 $9,402,100 $20,573,600

11   Saylorville WTP $27,405,900 $3,561,700 $23,844,200

Boosters and Storage

12   Hazen Storage $1,655,000 $1,001,200 $653,800

13   East Side Tower $4,597,200 $198,900 $4,398,300

14   LP Moon Booster and Storage $8,838,200 $2,825,200 $6,013,000

15   Polk Co. Storage $2,177,200 $945,600 $1,231,600

16   Polk Co. Booster $1,751,700 $1,189,000 $562,700

17   Standpipes $2,731,400 $1,536,800 $1,194,600

18   ASR Wells $6,558,400 $900,400 $5,658,000

Transmission Mains

19   Mains $88,559,700 $17,826,300 $70,733,400

20   SWTP Feeder Main ‐ Purch. Cap. $5,411,600 $216,500 $5,195,100

21   Wholesale Meters $210,000 $84,000 $126,000

Miscellaneous

22   General Office $3,750,200 $999,000 $2,751,200

23   Other $1,677,500 $1,462,100 $215,400

24   Miscellaneous $13,370,000 $0 $13,370,000

25 Total DMWW Assets $288,395,300 $78,733,700 $209,661,600

Page 42: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  36

Table 4‐6 Estimated OCLD Value for WDMWW Assets 

4.2.3.3 Other OCLD Results 

Table4‐7providestheestimatedOCLDvalueforassetscontributedbyAltoona,Ankeny,andUrbandaleWaterWorks.TheseassetsareconsolidatedonthesameTableastheirnumberofassetitemsislimitedcomparedtoDMWWandWDMWW.Noestimateofgoingconcernwasdeterminedfortheseassets.

Table 4‐7 Estimated OCLD Value for Urbandale WW, Altoona, and Ankeny 

4.3 ESTIMATION OF REPLACEMENT COST LESS DEPRECIATION (RCLD) Thereplacementcostlessdepreciation(RCLD)providesanindicationoftheupperrangeofvaluerelatedtotheassetsthatwouldcomprisethepotentialRegionalProductionUtility.Replacementcostreflectsanestimateofwhatapotentialbuyerwouldhavetopaytoconstructtheregionalproductionassetsatpresentvalue.AswiththeOCLDanalysis,accumulateddepreciationisderivedandsubtractedfromthereplacementcosttoreflectthatvaluediminishesovertimeduetofactorssuchaswearandtear,actionoftheelements,andobsolescence.ThedeterminationoftheRCLD

Original Cost

Line Original  Accumulated

No. Description Cost Depreciation OCLD

Source of Supply

1   Wells and Equipment $4,543,400 $1,582,200 $2,961,200

Treatment

2   Plant Structures and Buildings $9,730,700 $3,385,700 $6,345,000

3   Treatment Equipment $7,987,200 $4,389,400 $3,597,800

Mains

4   Raw and Finished Water $604,200 $157,600 $446,600

Storage

5   98th Street Tower $3,216,100 $385,500 $2,830,600

6   Miscellaneous $979,000 $0 $979,000

7 Total WDMWW Assets $27,060,600 $9,900,400 $17,160,200

Original Cost

Line Original  Accumulated

No. Description Cost Depreciation OCLD

Urbrandale

1   Raw Water Quarries $870,900 $0 $870,900

Ankeny

2   ASR Wells $2,279,800 $468,600 $1,811,200

Altoona

3   Wells and Treatment Facilities $8,145,700 $3,857,400 $4,288,300

4 Total Other  $11,296,400 $4,326,000 $6,970,400

Page 43: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  37

valuefortheassetsthatwouldcomprisetheRegionalProductionUtilityisdiscussedinthefollowingsections.

4.3.1 Replacement Cost 

ForthisStudy,ReplacementCostreflectstheestimatedpresentdayvaluethatapotentialbuyerwouldhavetoinvesttoconstructaregionalproductionsystemsimilartothatconstructedbyDMWW,WDMWW,Altoona,Ankeny,andUrbandaleWaterWorks.Thereplacementcostisgenerallydesignedtoreflectwhatitwouldtakeapotentialbuyertoconstructassetsofsimilarscaleandtechnology.

Aswiththeoriginalcostdeterminationabove,Black&Veatchreliedondataprovidedbytheutilitiesthatincludedtheoriginalcostoftheassetandtheyearofinstallation.ForDMWWandWDMWW,thisincludedassetschedulesthatincludedoriginalcost,yearofinstallation,andadescriptionoftheassetforabovegroundassetssuchaswells,treatmentplants,storagetanks,pumpstations,andothersimilarabovegroundassets.TheoriginalcostfortheseassetswastrendedtotheirrespectivereplacementcostvalueusingtheHandy‐WhitmanIndex.Thetrendindexforthecurrentyear(2014),dividedbythetrendindexfortheyearofinstallationbyassettypeprovidedthetrendfactor.Thetrendfactor,multipliedbytheoriginalcostprovidedthereplacementcostestimate.Black&VeatchandHRGreenalsoevaluatedtheresultingreplacementcostestimateforreasonablenessusingourknowledgeofsimilarconstructionprojects.Ifthereplacementcostderivedviatrendingwasviewedtobetoohighortoolow,Black&Veatchadjustedthereplacementcosttoreflectareasonablereplacementcostvaluebasedonourknowledgeandexperience.

ThereplacementcostforthecorenetworktransmissionmainsownedbyDMWWwasderivedinthesamemannerasnotedaboveinthedescriptionofthedevelopmentoforiginalcost.Theestimatedreplacementcostperfootofmainwasmultipliedbytheapplicabletransmissionmainsegmentlengthtoderivethereplacementcostestimate.

FortheASR,treatmentplant,andsourceofsupplyquarriesownedbyAnkeny,Altoona,andUrbandaleWaterWorks,respectively,Black&Veatchderivedestimatedreplacementcostestimatesusingengineeringjudgmentandexperience.Theseestimateswerecomparedtoknownprojectsofsimilarscopeandsizetoassessforreasonableness.

4.3.2 Accumulated Depreciation 

AswiththeOCLDanalysis,accumulateddepreciationwasderivedtoreflectthatovertime,thereplacementcostvaluewoulddiminishduetofactorssuchaswearandtear,actionoftheelements,andobsolescence.Black&Veatchusedthesamegeneralservicelifevalues,whichareshownasfollows,astheoriginalcostanalysis.

Structures&Improvements–75years Wells&Springs–50years ElectricPumpingEquipment–25years LargeTreatmentPlantEquipment–30years ElevatedSteelTanks–75years ConcreteStorageReservoirs–75years

Page 44: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  38

Pre‐stressedConcreteTransmissionMains–100years PolyvinylChloride(PVC)TransmissionMains–50years DuctileIronTransmissionMains–75years CommunicationEquipmentandSCADA–20years LaboratoryEquipment–10years WholesaleMeters–20years

Similartothedeterminationofaccumulateddepreciationfortheoriginalcostanalysis,ifBlack&Veatchfeltthatbasedonsitevisits,amorereflectiveservicelifeshouldbeused,thentheservicelifewasadjustedtobemorereflectiveoftheobservedcondition.

Straightlinedepreciationwasusedtodeterminetheaccumulateddepreciationusingthefollowingformula:

AccumulatedDepreciation=((Age/ServiceLife)xReplacementCost)

Iftheageoftheassetwasgreaterthantheservicelife,theaccumulateddepreciationwassetequaltothereplacementcost.TheaccumulateddepreciationwasthensubtractedfromthereplacementcosttoderivetheestimatedReplacementCostLessDepreciationorRCLD.

4.3.3 RCLD Results 

ThefollowingTablespresenttheresultsoftheOCLDforassetsthatpotentiallycouldbeconveyedtoanewRegionalProductionUtility.

4.3.3.1 DMWW RCLD Results 

Table4‐8presentsasummaryoftheestimatedRCLDresultsforthecorenetworkassetsofDMWW.Ascanbeseen,theRCLDvalueforDMWWassetsisapproximately$365million.Thisincludesassetsrelatedtothesourceofsupplyintakes,collectorwells,treatmentplants,transmissionmains,pumpstations,andstoragefacilitiesofDMWW.AswiththeOCLDanalysis,italsoincludesahighlevelmiscellaneousvalueestimateforgoingconcernandaprovisionforCWIP.

4.3.3.2 WDMWW RCLD Results 

Table4‐9presentsasummaryoftheestimatedRCLDresultsforWDMWW.Thisincludeswells,theA.C.WardWTP,98thStreetelevatedstoragetank,andmiscellaneousrawandfinishedwatermains.AswiththeOCLDanalysis,ahighlevelestimateforgoingconcernisincludedintheRCLDvalueforWDMWW.

4.3.3.3 Other RCLD Results 

Table4‐10presentstheestimatedRCLDforthewaterassetscurrentlyownedbyUrbandaleWaterWorks,Ankeny,andAltoona.

Page 45: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  39

Table 4‐8  RCLD Results for DMWW 

Line Replacement Accumulated

No. Description Cost Depreciation RCLD

Source of Supply

1   Des Moine River Intake $26,442,500 $12,929,400 $13,513,100

2   Fleur Infiltration Gallery $16,715,000 $14,795,500 $1,919,500

3   Maffitt Raw Water $16,569,800 $3,377,000 $13,192,800

4   Maffitt Reservoir $15,864,400 $11,211,700 $4,652,700

5   Saylorville Lake Storage $7,257,300 $0 $7,257,300

6   Saylorville WTP Raw Water $9,754,800 $505,300 $9,249,500

Treatment

7   Fleur WTP $208,435,800 $147,560,200 $60,875,600

8   Fleur Nitrate Facility $9,167,600 $5,356,900 $3,810,700

9   Fleur Laboratory $923,700 $830,500 $93,200

10   McMullen WTP $51,015,200 $15,924,900 $35,090,300

11   Saylorville WTP $30,448,200 $3,967,400 $26,480,800

Boosters and Storage

12   Hazen Storage $7,020,100 $6,682,500 $337,600

13   East Side Tower $4,826,000 $209,200 $4,616,800

14   LP Moon Booster and Storage $11,326,300 $3,623,700 $7,702,600

15   Polk Co. Storage $3,827,100 $1,661,900 $2,165,200

16   Polk Co. Booster $3,775,800 $2,764,000 $1,011,800

17   Standpipes $15,414,600 $10,858,800 $4,555,800

18   ASR Wells $5,500,000 $777,300 $4,722,700

Transmission Mains

19   Mains $216,318,000 $78,141,100 $138,176,900

20   SWTP Feeder Main ‐ Purch. Cap. $6,709,600 $268,400 $6,441,200

21   Wholesale Meters $322,700 $129,100 $193,600

Miscellaneous

22   General Office $7,337,900 $2,038,500 $5,299,400

23   Other $4,214,000 $3,707,500 $506,500

24   Miscellaneous $13,370,000 $0 $13,370,000

25 Total DMWW Assets $692,556,400 $327,320,800 $365,235,600

Page 46: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  40

Table 4‐9  RCLD Results for WDMWW 

Table 4‐10  RCLD Results for Urbandale Water Works, Ankeny, and Altoona 

4.4 COMBINED ESTIMATE OF VALUATION ThecombinedestimateofvaluationreflectsthecombinedvalueofassetscontributedbytheutilitiesofDMWW,WDMWW,Altoona,Ankeny,andUrbandaleWaterWorks.ThecombinedestimateofvaluereflectstherangeofvaluethatprovidesareasonablebasisforestablishingthefairmarketvalueofwaterutilityassetsthatcouldbetransferredtoanewRegionalProductionUtility.AsisseeninTable4‐11,thecombinedestimatedrangeofvaluationisapproximately$234millionto$413million.ThelowrangevaluerepresentsthesumofOCLDvaluesforTables4‐5through4‐7,whilethehighrangevaluerepresentsthesumofRCLDvaluesforTables4‐8through4‐10.Themidrangerepresentsthemedianbetweenthelowandhighrange.

Repl. Cost

Line Replacement Accumulated

No. Description Cost Depreciation RCLD

Source of Supply

1   Wells and Equipment $8,957,900 $3,291,900 $5,666,000

Treatment

2   Plant Structures and Buildings $30,636,700 $15,343,700 $15,293,000

3   Treatment Equipment $13,388,500 $7,648,300 $5,740,200

Mains

4   Raw and Finished Water $1,414,900 $370,500 $1,044,400

Storage

5   98th Street Tower $5,800,000 $695,300 $5,104,700

6   Miscellaneous $979,000 $0 $979,000

7 Total WDMWW Assets $61,177,000 $27,349,700 $33,827,300

Line Replacement Accumulated

No. Description Cost Depreciation RCLD

Urbrandale

1   Raw Water Quarries $1,680,000 $0 $1,680,000

Ankeny

2   ASR Wells $3,310,400 $729,700 $2,580,700

Altoona

3   Wells and Treatment Facilities $23,050,800 $13,600,700 $9,450,100

4 Total Other  $28,041,200 $14,330,400 $13,710,800

Page 47: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  41

Table 4‐11  Combined Estimate of Valuation 

4.5 ESTIMATE OF PURCHASED CAPACITY VALUE Beginninginapproximately1996,DMWWbeganenteringintowholesalewatercontractswithsurroundingcommunitiesthatwereexperiencingcustomergrowth,andasaresult,neededadditionalwaterfromDMWW.ThesewholesalewatercontractsarecommonlyreferredtoasWholesaleWaterServiceMasterAgreementsorPurchasedCapacityAgreements.Inapproximately2006,DMWWenteredintoanewWholesaleWaterServiceMasterAgreement(2006Agreement)withtheoriginal1996communitiesandseveralothercommunitiesthatwerealsoseekingaccesstoadditionalwaterfromDMWW.The2006agreementsupersededthe1996agreements.

Ingeneral,thecommunitiesseekingwaterfromDMWWcontributedanupfrontamountofcapitaltohelpDMWWbuildthenecessarytreatmentfacilitiesthatwouldprovideadditionalwatertothegreaterDesMoinesregion.The2006purchasedcapacityamountwas$1.90pergallonperdayofcapacity.CommunitiescouldelecttoeitherpayDMWWupfrontfortheirpurchasedcapacity,ortheycouldelecttohaveDMWWissuerevenuebondsfortheprojects,andthecommunitywouldpaytheirapplicableshareoftheprincipalandinterestdueeachyear.

DMWWprovidedBlack&Veatchwithasummaryoftheoriginalcontributedamountsbyentityandtheirassociatedcurrentpurchasedcapacityamounts.AsisseeninTable4‐12,theamountcontributedbythecommunitiestotalsapproximately$79million.Sincethe2006AgreementindicatesthatthepurchasedcapacityamountsweretobeusedtoconstructtreatmentandASRfacilities,Black&VeatchcomparedtheoriginalcontributionamountinTable4‐12totheoriginalcostamountsinTable4‐5.ThefacilitiesrelatedtoMaffittRawWater,SaylorvilleWTPRawWater,McMullenWaterTreatmentPlant,SaylorvilleWaterTreatmentPlant,SaylorvilleWTPFeederMain,andASRWellsreflectanoriginalcostofapproximately$88,275,800,whichcomparescloselytotheoriginalcontributionamount.AsitappearsthattheseDMWWassetswereprimarilyconstructedusingpurchasedcapacitycontributions,Black&VeatchutilizedtheOCLDandRCLDamountsfortheseassetstoderiveanestimateofthepurchasedcapacityvaluefortherespectiveentitiesthatenteredintotheWholesaleWaterServiceMasterAgreementwithDMWW.Table4‐13presentstheestimatedrangeofpurchasedcapacityvalueforthecommunitiesand/orutilitiesthatpurchasedcapacityfromDMWW.ThisrangerepresentsBlack&Veatch’sestimateofthepurchasedcapacityvaluecontributedbythewholesalecustomersofDMWW.ThispurchasedcapacityvalueisnotinadditiontotheestimatedvalueofDMWWassets.ThepurchasedcapacityvaluereflectstheportionoftheDMWWvalueestimatethatwascontributedbythewholesalecustomers,andisusedintheNetValuedeterminationdiscussedinsubsequentsectionsofthisReport.

Total

Line Value

No. Description Estimate

1 Low Range (OCLD) $233,792,200

2 Mid Range $323,283,100

3 High Range (RCLD) $412,773,700

Page 48: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  42

Table 4‐12  Summary of Current Purchased Capacity Amounts and Original Contribution 

Community/Utility 

Current 

Purchased 

Capacity 

(mgd) 

Original Capital 

Contribution 

   

Polk Co. (SE and Unincorporated)  1.950  $1,937,500 

Berwick Water Association 0.250  $310,000 

Urbandale Water Works  15.300  $22,584,000 

West Des Moines Water Works  8.973  $11,564,100 

Ankeny  8.280  $12,365,000 

Clive  6.980  $11,400,000 

Waukee  3.694  $4,105,000 

Warren Rural Water  3.246  $3,343,000 

Xenia Rural Water  2.949  $3,623,400 

Norwalk1  1.965  $2,353,800 

Bondurant2  1.200  $2,940,000 

Altoona  1.000  $1,900,000 

Polk City  0.350  $665,000 

   

Total  56.137 $79,090,800

                                                             

 

 

 

1 Includes original purchased capacity contribution from the City of Cumming, which was subsequently purchased by Norwalk. 2 Includes original purchased capacity contribution from the City of Pleasant Hill, which was subsequently purchased by the City of Bondurant. 

Page 49: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  43

Table 4‐13  Estimated Range of Purchased Capacity Value for Wholesale Customers 

4.6 OTHER CONTRIBUTED DMWW ASSETS 

4.6.1 Joint East Side Project 

DuringthecourseofthisStudy,Black&VeatchwasalsoabletodeterminethattheJointEastSideprojectwascontributedbyseveralwholesalecustomersandafullservicecustomerofDMWW.TheJointEastSideprojectgenerallyconsistsofapumpstation,transmissionmain,andanelevated2.0mgdstoragetank.TheprojectwasdesignedtoprimarilyservethecustomersofAltoona,PleasantHill,andPolkCounty.FrominformationprovidedbyDMWW,itisestimatedthattheprojectcostisapproximately$13million.TheassetsarerelativelynewandBlack&VeatchdevelopedanestimatedOCLDandRCLDvalueof$12,422,000and$13,456,000,respectively.

InformationprovidedbyDMWWreflectsthattheprojectwassplitbetweenthethreecommunitiesasfollows:

PleasantHill–61.54% Altoona–30.77% PolkCounty–7.69%

ThisestimatedvalueisassignedtothesecommunitiesintheNetValuedeterminationinsubsequentsectionsofthisReport.

4.6.2 Polk City Feeder Main 

DMWWindicatedthatafeedermainrunsnorthalongthewestsideofAnkenytosupplywatertoPolkCity.PolkCitycontributedapproximately$1,579,520tocompletethisprojectwhichisownedbyDMWW.Theestimatedvalueforthiscontributionis$1,516,339(OCLD)to$1,880,056(RCLD),withamidrangevalueof$1,698,197.

4.6.3 Ankeny Contribution to SWTP Feeder Main 

DMWWindicatedthatAnkenycontributedapproximately$772,350towardtheconstructionofthenorthfeedermainrelatedtotheSWTP.Theestimatedvalueforthiscontributionis$741,456(OCLD)to$919,305(RCLD),withamidrangevalueof$830,381.

Replacement  

Original Cost Cost

Line Original  Replacement Accumulated Accumulated

No. Description Cost Cost Depreciation Depreciation OCLD RCLD

1   Maffitt Raw Water $10,307,600 $16,569,800 $1,955,800 $3,377,000 $8,351,800 $13,192,800

2   Saylorville WTP Raw Water $8,616,600 $9,754,800 $448,300 $505,300 $8,168,300 $9,249,500

3   McMullen WTP $29,975,700 $51,015,200 $9,402,100 $15,924,900 $20,573,600 $35,090,300

4   Saylorville WTP $27,405,900 $30,448,200 $3,561,700 $3,967,400 $23,844,200 $26,480,800

5   ASR Wells $6,558,400 $5,500,000 $900,400 $777,300 $5,658,000 $4,722,700

6   SWTP Feeder Main $5,411,600 $6,709,600 $216,500 $268,400 $5,195,100 $6,441,200

7 Purchased Capacity Estimate $88,275,800 $119,997,600 $16,484,800 $24,820,300 $71,791,000 $95,177,300

8 Mid Range Estimate $83,484,200

Page 50: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Valuation Estimate  44

4.6.4 WDMWW 98th Street Elevated Storage Tank  

InformationprovidedbyWDMWWindicatesthatits98thStreetElevatedStorageTankincludesanagreementwithCliveandWaukee.ThesetwoentitiescontributedtotheconstructionofthisassetwhichisownedbyWDMWW.Thefollowingpresentsthepercentagesplitoftheassetbetweenthecommunities:

WDMWW–40% Clive–40% Waukee–20%

ThisestimatedvalueisassignedtothesecommunitiesintheNetValuedeterminationinsubsequentsectionsofthisReport.

4.6.5 L.P. Moon Storage and Booster Station 

DMWWindicatedthattheconstructionoftheL.P.MoonStorageandBoosterstationwascompletedwithcontributionsfromseveralentities.DMWWstaffreviewedtheagreementsrelatedtothisproject,andindicatedthatmoreworkwouldneedtobedonetoreadilydeterminetheamountofcontributionfromseveraldifferententities.ForpurposesofthisStudy,anydeterminedcontributionforthisassetwouldbeassignedtotheappropriateentityforpurposesofdeterminingtheirrespectiveNetValuethatisdiscussedinthefollowingsectionsofthisReport.

4.7 VALUATION CONCLUSION ThepurposeoftheestimatedvaluationistoderiveanestimatedrangeofvaluethatCIRDWCmemberscanuseasabasisforcontemplatingthemeritsofformingaRegionalProductionUtility.TheformationofaRegionalProductionUtilitywillrequireatransferofassets.Therefore,understandingtheestimatedvaluetoutilitiesthatcontributewaterproductionassetsisnecessarytounderstandthepotentialupfrontcostsofanytransaction.

Itshouldbenotedthatthevaluationestimatedoesnotincludeanappraisedvalueoflandownedbyanycontributingutility.TheestimatedvalueisbasedoninformationavailabletoBlack&VeatchandreflectsBlack&Veatch’sopinionofareasonableestimatebasedontheCostApproachmethodologyofvaluationonly.TheuseoftheIncomeApproachandMarketApproachwerebeyondthescopeofthisStudy,butcouldhelprefineorestablishavalueestimatethatismateriallydifferentthantherangeoutlinedherein.

TheestimatedvaluationprovidesabasisforconductingtheFinancialAnalysisdiscussedsubsequentlyinthisReport.ForpurposesoftheFinancialAnalysis,Black&Veatchhaschosentoselectthemidrangeofthetotalvaluationestimate,orapproximately$323,283,100.

Page 51: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  45

5 Financial Analysis ThenextstepintheStudywastoassessthefinancialimpactonCIRDWCmembersshouldaRegionalProductionUtilitybeformed.Ingeneral,Black&VeatchutilizedathreestepprocesstoderivethepotentialimpactonCIRDWCmemberscomparedtothecurrentprocessthatutilizestheWholesaleWaterServiceMasterAgreements.

Step1:DeterminetheNetValueorEquitythatwouldbecontributedbymemberstothepotentialRegionalProductionUtility.

Step2:Determinetheestimatedrevenuerequirements(includingtransactionpayments)thatthepotentialRegionalProductionUtilitywouldneedduringthefirstfiveyearsofoperation.

Step3:DetermineaneffectiveuniformratethatwouldapplytomembersofthepotentialRegionalProductionUtilityandcomparetothecurrentwholesalerate.

Thefinancialanalysisincorporatesthefindingsofthevaluationestimateintoafiveyearfinancialprojection,allowingpotentialparticipantstoevaluatethefinancialimpactofregionalizationofjoiningtheRegionalProductionUtility.Thefinancialprojectionincludesdevelopingtherevenuerequirementsforthenewentity.Thesecosts,appliedtotheestimatedbilledusage,deriveanestimatedeffectiveunitcostper1,000gal.

5.1 NET VALUE ANALYSIS TheNetValueAnalysisprovidesonepathforwardfortransitioningfromthecurrentmethodofprovidingwatertoapotentialRegionalProductionUtility.ThemainobjectiveoftheNetValueanalysisistobringpotentialparticipantsintotheRegionalProductionUtilityonanequalbasis.ThisincludesdeterminingtheNetValue,orequity,contributionofparticipantsonapermgdofcapacitybasis,andperforminganynecessaryadjustmentstoalignparticipantswiththesamenetvaluepermgdofcapacity.AkeyassumptionforthisanalysisisthatDMWW,andallentitiesthathaveaPurchasedCapacityAgreementwithDMWW,willjointheRegionalProductionUtility.

ForpurposesofthisNetValueAnalysis,Black&usedthemidrangevalueestimate,orapproximately$323,283,100.

5.1.1 Summary of Estimated Value and Net Value per MGD 

ThefirstpartoftheNetValueanalysisistodeterminethenetvaluepermgdofeachentity.NetvalueisreflectedonapermgdbasisasDMWWandthesurroundingutilitieshaveprimarilydesignedthecorenetworktoserveatotalcapacitythatincludestheneedsofDMWWandutilitiesthathavea2006AgreementforpurchasedcapacitywithDMWW.ThefollowingTablepresentsasummaryofthecurrentnetvaluebyentity.

5.1.1.1 Total Capacity 

TheTotalCapacitypresentedinTable5‐1,Column1andColumn2includesthefollowing:

TotalcapacityoftheDMWWsystemof116mgd,including56.137mgdofpurchasedcapacityrelatedtothe2006Agreements.ThenettotalcapacityapplicabletoDMWWis59.86mgd.

Additionaltotalcapacitycontributedbyutilitieswithproductionassets.ThisincludesWDMWW(9.9mgd);Altoona(3.9mgd);andAnkeny(4.32mgd).

Page 52: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  46

Table 5‐1  Summary of Total Capacity, Value, and Net Value by Entity (Mid Range Value) 

(1)

(2)

(3)

(4)

(5)

(6)

(7)

(8)

Estimated

Estimated

%Estimated

DMWW

DMWW

%Net

Line

Total

Total

Mid Range

Outstanding

Debt Service

Net

Net

Value

No.

Description

Capacity

Capacity

Value

Debt

Reserve

Value

Value

per mgd

mgd

=(3)+(4)+(5)

=(6)/(1)

Contributing Entities

1Des Moines Water Works

59.86

44.63%

$196,459,400

($5,996,800)

$703,400

$191,166,000

65.17%

$3,193,400

2Polk Co. (SE and Unincorporated)

1.95

1.45%

$3,895,200

($679,800)

$0$3,215,400

1.10%

$1,648,900

3Berw

ick Water Association

0.25

0.19%

$371,800

($56,300)

$45,100

$360,600

0.12%

$1,442,400

4Urbandale W

ater Works

15.30

11.41%

$24,028,800

($11,204,700)

$1,609,000

$14,433,100

4.92%

$943,300

5West Des Moines Water Works

18.87

14.07%

$36,457,400

($4,541,500)

$708,100

$32,624,000

11.12%

$1,728,600

6Ankeny

12.60

9.39%

$15,339,900

($9,983,100)

$959,500

$6,316,300

2.15%

$501,300

7Clive

6.98

5.20%

$11,967,400

$0$0

$11,967,400

4.08%

$1,714,500

8Waukee

3.69

2.75%

$6,287,100

($805,100)

$171,000

$5,653,000

1.93%

$1,530,300

9Warren Rural W

ater

3.25

2.42%

$4,827,300

$0$0

$4,827,300

1.65%

$1,487,200

10Xenia Rural W

ater

2.95

2.20%

$4,385,700

$0$0

$4,385,700

1.50%

$1,487,200

11Norw

alk

1.97

1.47%

$2,922,200

($412,400)

$146,500

$2,656,300

0.91%

$1,351,800

12Bondurant

1.20

0.89%

$1,784,600

($684,800)

$77,800

$1,177,600

0.40%

$981,300

13Altoona

4.90

3.65%

$12,337,600

$0$0

$12,337,600

4.21%

$2,517,900

14Polk City

0.35

0.26%

$2,218,700

$0$0

$2,218,700

0.76%

$6,339,100

15Total

134.12

100.00%

$323,283,100

($34,364,500)

$4,420,400

$293,339,000

100.00%

$2,187,100

Page 53: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  47

5.1.1.2 Estimated Total Value by Entity 

Table5‐1,Column3presentsthemidrangevaluebyentityandincludesthefollowing:

Purchasedcapacityvalueforentitiesthathavea2006AgreementforpurchasedcapacitywithDMWW.TheestimatedvaluefortheseentitiesisreflectedinTable5‐2.Themidrangepurchasedcapacityvalueof$83,484,200isdistributedtothepurchasedcapacitycustomersonthebasisoftheirpurchasedcapacityamounts.

Table 5‐2  Purchased Capacity Mid Range Value by Customer 

ValueofcontributedassetsfromentitiesotherthanDMWW.ThisincludessupplyandtreatmentassetsfromWDMWW,Altoona,UrbandaleWaterWorks,andAnkeny.Forexample,thetotalvalueforWDMWWshowninColumn3ofTable5‐1reflectsitspurchasedcapacityvalue,pluscontributedmidrangevalueofassets($36,457,400=$13,344,200+$23,113,200).

OthersignificantcontributionssuchasthePolkCityfeedermainandJointEastSideprojectforCityofPleasantHill(includedinDMWWasfullservicecustomer),PolkCo.,andAltoona.Oncedetermined,thecontributionbyentitiesrelatedtotheL.P.Moonstorageandpumpingstationwouldalsobeincluded.

5.1.1.3 Net Outstanding Debt 

Table5‐1,Columns4and5primarilypresentstheestimatedoutstandingdebtheldbyDMWWrelatedtocorenetwork,offsetbyapplicabledebtservicereserveamounts.ThisoutstandingdebtisprimarilydebtthatwasissuedbyDMWWonbehalfofpurchasedcapacitycustomers.WithanytransferofassetsfromDMWWtoanewRegionalProductionUtility,theoutstandingdebtheldbyDMWWwouldneedtobeaddressed.ForpurposesofthisStudyandReport,Black&Veatchhasassumedthatatthetimeofanytransaction,DMWWwouldbecompensatedbythenewRegional

%

Line Purchased Purchased Estimated

No. Purchased Capacity Holder Capacity Capacity Value

mgd

1 Polk Co. (SE and Unincorporated) 1.950 3.47% $2,899,900

2 Berwick Water Association 0.250 0.45% $371,800

3 Urbandale Water Works 15.300 27.25% $22,753,400

4 West Des Moines Water Works 8.973 15.98% $13,344,200

5 Ankeny 8.280 14.75% $12,313,600

6 Clive 6.980 12.43% $10,380,300

7 Waukee 3.694 6.58% $5,493,500

8 Warren Rural Water 3.246 5.78% $4,827,300

9 Xenia Rural Water 2.949 5.25% $4,385,700

10 Norwalk 1.965 3.50% $2,922,200

11 Bondurant 1.200 2.14% $1,784,600

12 Altoona 1.000 1.78% $1,487,100

13 Polk City 0.350 0.62% $520,500

14 Total 56.137 100.00% $83,484,200

Page 54: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  48

ProductionUtilitytoretiretheoutstandingdebt,lessoutstandingdebtservicereserveamounts.Additionallegalandfinancialanalysisshouldbeundertakenbeforeanypotentialtransactiontodeterminewhetherthisisfeasibleornot.

Black&VeatchwasalsoabletodeterminethatAnkenyhassomeoutstandingdebtrelatedtoitsASRwells.Thisamountisapproximately$1,545,000andisincludedinTable5‐1,Column4,Line6.

Black&Veatchalsorecognizesthatsomeentitiesmayhaveoutstandingdebtrelatedtotheir2006Agreements.Forpurposesofthisstudy,Black&Veatchassumesthatthoseentitieswouldcontinuetopaytheprincipalandinterestpaymentsrelatedtothatdebtafteranypotentialtransaction.

5.1.1.4 Estimated Net Value by Entity 

Table5‐1,Column6presentsthenetvaluebyentity.ItisderivedbysubtractingthenetoutstandingdebtheldbyDMWWfromthetotalvaluerelatedtothecorenetwork.ThepercentageofnetvaluebyentityispresentedinTable5‐11,Column7.

Table5‐1,Column8presentsthenetvaluepermgdofcapacitybyentity.ItisderivedbydividingColumn6byColumn1.Ascanbeseen,thenetvaluepermgdbyentityisnotuniform.DMWWwiththecontributionofamajorityofassetsreflectsthehighestnetvaluepermgd,whileAnkenyreflectsthelowestnetvaluepermgd.ThelowernetvaluepermgdvalueforAnkenyisprimarilyrelatedtothefactthatitscontributionforthe2006AgreementwasprimarilyfinancedthroughdebtissuedbyDMWW.ThereisalsosomeoutstandingdebtrelatedtoAnkeny’sASRwellsofapproximately$1,545,000thatwouldlikelyneedtoberetiredatthetimeofthetransaction.

5.1.2 Alignment of Net Value by Entity 

Asindicatedabove,theentitiescontributedvaryinglevelsofnetvalueonapermgdbasis.TobringeachentityintothepotentialRegionalProductionUtilityonanequalbasis,Black&Veatchperformedatwo‐stepprocesstoalignthenetvalueofeachentityonapermgdbasis.ThefirststepincludesbuyingdownthenetvalueofDMWWtoalevelmoreconsistentwiththeotherentities.Thisresultsinanew,lowernetvaluepermgdforDMWW.Thesecondstepincludesaligningthenetvalueofallotherstothenew,lowernetvalueofDMWW.Table5‐3presentsthealignmentofcustomersonanetvaluepertotalcapacitybasis.Table5‐3,Column1restatestheNetValuebyentityasreflectedonTable5‐1.

5.1.2.1 Cash Payment to DMWW 

ThecashpaymenttoDMWWisthefirststepinaligningthenetvaluepertotalcapacityoftheentitiesandisshowninTable5‐3,Column2.Black&Veatchusedanestimatedcashpaymentof$100million.ItisassumedfortheStudyandthisReportthatthecashpaymentwouldbefundedfromdebtissuedbytheRegionalProductionUtility.Theprincipalandinterestrelatedtothispaymentwouldbeincludedintheannualrevenuerequirementsofthenewentityandpayableaspartofitsuniformratewhichisdiscussedlaterinthisreport.

ThecashpaymenttoDMWWresultsinanewnetvalueofapproximately$91,166,000.WhendividedbythetotalcapacityapplicabletoDMWWtheresultis$1,522,900permgdoftotalcapacity.

Page 55: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  49

Table 5‐3  Alignment of Net Value per Total Capacity by Entity 

(1)

(2)

(3)

(4)

(5)

(6)

Net

Adjusted

Cash Payment

Contributions

Adjusted

Restated

Net

Line

Net

Des Moines

(To)/From

Net

Total

Value

No.

Description

Value

Water Works

Other Entities

Value

Capacity

per mgd

(1)+(2)+(3)

(4) / (5)

Contributing Entities

1Des Moines Water Works

$191,166,000

($100,000,000)

$91,166,000

59.86

$1,522,900

2Polk Co. (SE and Unincorporated)

$3,215,400

($245,800)

$2,969,600

1.95

$1,522,900

3Berw

ick Water Association

$360,600

$20,200

$380,800

0.25

$1,522,900

4Urbandale W

ater Works

$14,433,100

$8,867,400

$23,300,500

15.30

$1,522,900

5West Des Moines Water Works

$32,624,000

($3,882,200)

$28,741,800

18.87

$1,522,900

6Ankeny

$6,316,300

$12,872,400

$19,188,700

12.60

$1,522,900

7Clive

$11,967,400

($1,337,400)

$10,630,000

6.98

$1,522,900

8Waukee

$5,653,000

($27,300)

$5,625,700

3.69

$1,522,900

9Warren Rural W

ater

$4,827,300

$116,100

$4,943,400

3.25

$1,522,900

10Xenia Rural W

ater

$4,385,700

$105,500

$4,491,200

2.95

$1,522,900

11Norw

alk

$2,656,300

$336,200

$2,992,500

1.97

$1,522,900

12Bondurant

$1,177,600

$649,900

$1,827,500

1.20

$1,522,900

13Altoona

$12,337,600

($4,875,300)

$7,462,300

4.90

$1,522,900

14Polk City

$2,218,700

($1,685,700)

$533,000

0.35

$1,522,900

15Total

$293,339,000

($100,000,000)

$10,914,000

$204,253,000

134.12

$1,522,900

Page 56: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  50

5.1.2.2 Alignment of Net Value per MGD of Other Entities 

Oncethenewnetvaluepertotalcapacityof$1,522,900forDMWWwasestablished,Black&Veatchderivedtheestimatedcontributionthatwouldbemadeby,ormadetotheotherentitiestoachievealignmentwithDMWW.ThiscontributionisreflectedinTable5‐3,Column3.Negativevaluesreflectcashpaymentstoentitiestoaligntheirnetvaluepertotalcapacityat$1,522,900permgd.PositivevaluesreflectcashpaymentsfromtherespectiveentitiestothenewRegionalProductionUtilitytoaligntheirnetvaluepertotalcapacityat$1,522,900permgd.Table5‐3,Column4reflectsthenewadjustednetvaluepermgdbyentitypostcontribution.Table5‐3,Column5restatesthetotalcapacitybyentity.TheColumn4adjustednetvalueisdividedbythistotalcapacitytoreflecttheadjustednetvaluepermgdinColumn6.Ascanbeseen,thecashpaymenttoDMWW,combinedwithcontributionsbothtoandfromtheentities,alignsallparticipantsonthesamebasis.

5.1.3 Summary of Net Value Analysis 

TheNetValueanalysisalignseachofthepotentialmembersoftheRegionalProductionUtilityonanequalbasis.Thisalignmentiskeyforseveralreasons.Firstitestablisheseachcommunityonanequalbasisintermsoftheirrespectivecontribution,ornetvalue,tothenewRegionalProductionUtility.Thisalignmenthelpsexplaintopolicymakersandthepublicthatthecommunitiesarecomingintotheendeavoronanequalbasis.Second,thealignmentpavesthewayforjustificationofuniformrates,whichwasadesirefrommanyCIRDWCmembersduringtheStakeholderInputphaseoftheStudy.AsisseeninTable5‐4,thealignmentachievesequalfootingforparticipantsbothintermsofnetvalueandtheirrespectivepercentageoftotalcapacity.

Table 5‐4  Summary of Alignment of Net Value and Total Capacity 

TheNetValueanalysisresultsincashpaymenttoDMWW.ThecashpaymentsarerelatedtotheretirementofoutstandingdebtheldbyDMWW,andalsoacashpaymenttolowerDMWW’snet

Adjusted % Adjusted

Line Net Net Total % Total

No. Description Value Value Capacity Capacity

Contributing Entities

1 Des Moines Water Works $91,166,000 44.63% 59.86 44.63%

2 Polk Co. (SE and Unincorporated) $2,969,600 1.45% 1.95 1.45%

3 Berwick Water Association $380,800 0.19% 0.25 0.19%

4 Urbandale Water Works $23,300,500 11.41% 15.30 11.41%

5 West Des Moines Water Works $28,741,800 14.07% 18.87 14.07%

6 Ankeny $19,188,700 9.39% 12.60 9.40%

7 Clive $10,630,000 5.20% 6.98 5.20%

8 Waukee $5,625,700 2.75% 3.69 2.75%

9 Warren Rural Water $4,943,400 2.42% 3.25 2.42%

10 Xenia Rural Water $4,491,200 2.20% 2.95 2.20%

11 Norwalk $2,992,500 1.47% 1.97 1.47%

12 Bondurant $1,827,500 0.89% 1.20 0.90%

13 Altoona $7,462,300 3.65% 4.90 3.65%

14 Polk City $533,000 0.26% 0.35 0.26%

15 Total $204,253,000 100.00% 134.12 100.00%

Page 57: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  51

valuetoalevelclosertotheotherentities.ForpurposesofthisStudy,thecashpaymentswouldbemadebythenewRegionalProductionUtilitymostlikelythroughtheissuanceofdebtthatwouldthenbepaidbackbyallmembers.Table5‐5presentsasummaryofthemidrangevalueandderivationofthenetvalue,orequityofthepotentialRegionalProductionUtility.

Table 5‐5  Summary of Net Value or Equity 

AsTable5‐5shows,thenetvalueequatestoapproximately$204millionandconsistsofthetotalvalue,offsetbycashpaymentstoDMWWandnetcontributionsfromotherentities.Thenetvalueisapproximately63percentofthetotalmidrangevalue.TheamountsforthecashpaymentstoDMWWtoreduceDMWW’snetvalueanddefeaseDMWWdebtwillbeincludedinthefollowingsections.

5.1.3.1 Potential Buy In Amount for Non‐Members 

ThereareseveralcommunitiesthatreceivetheircompletewaterservicefromDMWW.ForpurposesofthisStudy,theircapacityisincludedintheDMWWlineitem.ThereisalsotheCityofJohnston,whichisawholesalecustomerofDMWWthatdidnotenterintoaPurchasedCapacityAgreement.Thus,thequestionwasposedtoBlack&Veatch:“whatwouldJohnstonhavetocontributetogainparticipationinthenewRegionalProductionUtility?”TheNetValueanalysisprovidesabasisforacceptingnewmemberstotheRegionalProductionUtility.

FortheCityofJohnston,itscurrentpeakdaywaterneedmultipliedbythenetvaluepermgdseenaboveinTable5‐3couldprovidecontributionnecessary.Black&VeatchutilizedanestimatedpeakdaydemandfortheCityofJohnstonof7.0mgd.Thispeakdaydemand,multipliedby$1,522,900equals$10,660,300,andcouldserveasonecontributionbasisforacceptingnewparticipants.

Additionally,shouldtheCIRDWCmembersdeterminetopursuetheRegionalProductionUtility,asimilarmethodcouldbeusedforfullservicecustomersservedbyDMWW.ConsiderationwillneedtobegiventothedistributionoftotalcapacitycomparedtoDMWW.Asmentionedpreviously,thedemandfortheCityofJohnstonandfullservicecustomersofDMWWisincludedinthetotalDMWWcapacityof59.86mgd.

5.2 DEVELOPMENT OF FIVE YEAR FINANCIAL PROJECTION Forpurposesofthefinancialanalysis,Black&Veatchdevelopedafiveyearprojectionofrevenuerequirementsthatinclude:(1)operationandmaintenance(O&M)expense,(2)annualrenewalandreplacementcosts,(3)debtserviceand/orcashfinancingofmajorcapitalimprovements,(4)debt

Line Breakdown

No. Description of Value

1 Total Value Estimate ‐ Mid Range $323,283,100

2 Cash Payment to DMWW ($100,000,000)

3 Net Cash Payment to DMWW for Debt ($29,944,100)

4 Contributions From Participants $22,967,700

5 Contributions To Participants ($12,053,700)

6 Total Net Value (Equity) $204,253,000

Page 58: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  52

serviceand/orcashfinancingoftherepaymentofoutstandingdebtcurrentlyheldbyDMWWrelatedtoPurchasedCapacityAgreementsortheconstructionofthecorenetwork,and(5)debtserviceand/orcashfinancingofthepaymenttoDMWWtoachievealignmentbetweensystemcapacityandnetvalue.

5.2.1 Operation and Maintenance Expense 

TheoperatingbudgetsforDMWW,WDMWW,andAltoonawereutilizedtodevelopaprojectedoperatingbudgetfortheassetstobecontributedbytheseentitiestotheRegionalProductionUtility.Theelementsofoperationandmaintenanceexpenseincludetheannualexpenseassociatedwithsourceofsupply,treatment,pumpstation,storage,andtransmissionmainsassociatedwiththecontributedassetsaswellasadministrativecostsassociatedwiththenewRegionalProductionUtility.

AsummaryofproposedoperationandmaintenanceexpenseispresentedinTable5‐6.TheprojectedoperationandmaintenanceexpensereflectsDMWW2015proposedbudgetforWaterProductionwhichincludeslaborandnon‐laborexpensesassociatedwiththemaintenance,energyandchemicalsforthethreeWTPs,storageandpumping,laboratory,facilityandvehiclemaintenance,communicationsystem,andHVAC.TheexpensesassociatedwithDesMoinesRemoteStoragehasbeenexcludedsinceO&MforthesefacilitieswillremainwithDMWW.Inaddition,anallowancehasbeenmadeforO&MassociatedwithDMWW’scorenetworktransmissionsystem.

ProjectedoperationandmaintenanceexpenseforWDMWWreflectsitsdraft2015budgetamountsforWaterTreatmentPlantexcludingthecostsassociatedwithpurchasedwater,aswellasagrantforanaeratorretrofit.The2015budgetfortheCityofAnkeny’stwoASRwellsisbasedonapercentageofDMWW’sbudgetforL.P.MoonPumpingandMaintenance.TheCityofAltoona’s2015proposedbudgetforWaterOperationswasthebasisforprojectedoperationexpenseassociatedwiththeCity’streatmentplantsandwells.

Table 5‐6  Proposed Operation & Maintenance Expense 

Line Budget

No. Description 2015 2016 2017 2018 2019 2020

Des Moines Water Works

1 Production $15,122,500 $15,576,200 $16,043,500 $16,524,800 $17,020,500 $17,531,100

2 Core Network Distribution System 1,536,000 1,582,100 1,629,600 1,678,500 1,728,900 1,780,800

West Des Moines Water Works

3 Production 2,647,164 2,726,600 2,808,400 2,892,700 2,979,500 3,068,900

City of Ankeny

4 ASR Wells 127,207 131,000 134,900 138,900 143,100 147,400

City of Altoona

5 Production 852,392 878,000 904,300 931,400 959,300 988,100

New Authority

6 Administration 4,178,800 4,304,100 4,433,300 4,566,300 4,703,300

7 Estimated Savings (1,111,800) (1,145,200) (1,179,600)

8 Total $20,285,263 $25,072,700 $25,824,800 $25,487,800 $26,252,400 $27,040,000

Page 59: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  53

InadditiontotheO&Midentifiedaboveassociatedwiththecontributedassets,administrativecostsassociatedwiththenewRegionalProductionUtilityneedtobeconsidered.Thesecostsincludepersonnel,materials,andsuppliesassociatedwithhumanresources,finance,informationtechnology,engineering,andmanagementofthenewentity.BasedonpreviousefficiencystudiesperformedbyBlack&Veatch,areasonableestimateofadministrativeexpensesassociatedwiththenewentityisapproximately20percentofthetotalofallotherexpenses.ThisamountisshownonLine6ofTable5‐6.

ItisanticipatedthatthenewRegionalProductionUtilitywilleventuallyexperiencesavingsassociatedwithareductionintheduplicationofservicesandtheconsolidatedpurchasingofmaterialsandsupplies.EstimatedsavingsareprojectedtoimpactO&MassociatedwithchemicalandenergycostsassociatedwithDMWW’sandWDMWW’swatertreatmentplants.AdditionalsavingscouldberealizedbycoordinatingO&Mactivitiesrelatedtofacilitymaintenance,vehiclemaintenance,communicationsystem,andHVACO&MbetweenDMWW,WDMWW,andAltoona.Thesesavingsareestimatedtobeginin2018andareshownonLine7ofTable5‐6.

O&Mexpenseprojectionsfortheyears2016through2020arebasedonbudgeted2015expenseamountsadjustedtoincludeanallowanceforinflation,estimatedat3percentannually.AsshowninTable5‐6,O&Mexpenseisprojectedtoincreasefrom$25,072,700in2016to$27,040,000by2020.

5.2.2 Annual Renewal and Replacement 

Annualrenewalandreplacementexpendituresincludethosecostswhichtendtoberoutinelyincurredeachyearfornormalreplacements,extensions,andminorimprovements.Projectedrenewalandreplacementcostswereestimatedusingthereplacementcostandaverageservicelifefromthevaluationanalysisabove,aswellaslookingatthehistoricalcapitalspendforDMWW.ProjectedrenewalandreplacementcostsaredeterminedaspresentedinTable5‐7.

Table 5‐7  Projected Renewal and Replacement 

5.2.3 Major Capital Improvement Costs 

ProjectedexpendituresformajorcapitalimprovementsconsistofprojectsassociatedwiththecontributedassetsprovidedbyDMWW,WDMWW,andAltoona.BasedonDMWW’scapitalbudget,improvementsduringthe2016‐2020studyperiodconsistsofprojectsassociatedwithFacilityMaintenance,RawWaterMaffitt,theFleurDriveTreatmentPlant,andtheMcMullenTreatmentPlant.

Line

No. Description 2016 2017 2018 2019 2020

1 Des Moines Water Works $9,700,000 $9,700,000 $9,700,000 $9,700,000 $9,700,000

2 West Des Moines Water Works 1,390,000 1,063,000 938,000 1,390,000 1,390,000

3 City of Ankeny 66,000 66,000 66,000 66,000 66,000

4 City of Altoona 460,000 460,000 460,000 460,000 460,000

5 Total $11,616,000 $11,289,000 $11,164,000 $11,616,000 $11,616,000

Page 60: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  54

AnticipatedprojectsforWDMWW’sproductionassetsconsistofrepaintinggroundstoragetanksNo.1andNo.2,andreplacementofthelimeslakerattheA.C.WardWTP.Tomeetfuturewaterdemandsbeyondtheyear2020,projectsrelatedtoAltoona’sproductionassetsincludeconstructionofanewwellatWaterTreatmentPlantNo.1toreplaceWellNo.2,andreplacementofmajorequipmentcomponentsatWaterTreatmentPlantNo.1.Thefive‐yearmajorcapitalimprovementprogramcostsareestimatedtototal$15,615,400andareshowninTable5‐8.

Table 5‐8  Major Capital Improvement Program 

5.2.4 Repayment of Outstanding Purchase Capacity Debt 

AsmentionedintheNetValueAnalysissection,Black&Veatchhasassumedthatatthetimeofanytransaction,DMWWwouldbecompensatedbythenewRegionalProductionUtilitytoretireoutstandingdebtissuedbyDMWWonbehalfofpurchasedcapacitycustomers.Thisamount,asshowninTable5‐1,Column4totals$34,364,000.ItisassumedthatthedebtservicereserveseeninTable5‐1,Column5willoffsettheoutstandingdebtservice.Thisresultsinanetoutstandingdebtpaymentof$29,944,000.

5.2.5 Adjustment to Des Moines Water Works’ Net Value 

AsdiscussedintheNetValueAnalysissectionofthisReport,inordertobringeachentityintothepotentialRegionalProductionUtilityonanequalbasis,atwo‐stepprocesswasusedtoalignthenetvalueofeachentityonapermgdbasis.ThefirststepwastobuydownthenetvalueofDMWWtoalevelmoreconsistentwithotherentitiesusingacashpaymentof$100,000,000.Thesecondstep,whichinvolvesanestimatedcontributionthatwouldbemadeby,ormadetotheotherentities,wouldalignthenetvalueofallotherstothenew,lowernetvalueofDMWW.Thisvalue,asshowninColumn3ofTable5‐3is$10,914,000.Thenetcashpaymentof$89,086,000consistsofthecashpaymenttoDMWW,offsetbythecontributionstoandfromtheentities.

5.2.6 Major Capital Improvement Financing 

Table5‐9presentsthecapitalimprovementfinancingplanwhichsummarizestheprojectedsourceandapplicationoffundsoverthefive‐yearstudyperiod.Thisplananticipatesthatproposedcapitalimprovementswillbefinancedfromacombinationofbondproceedsandannualoperatingrevenue;however,otheralternativescanbeconsideredandarediscussedlaterinthissection.

Line

No. Description 2016 2017 2018 2019 2020

1 Des Moines Water Works $6,198,700 $5,639,300 $0 $0 $0

2 West Des Moines Water Works 0 327,000 452,000 0 0

3 City of Altoona 0 0 0 0 2,998,400

4 Total 6,198,700$     $5,966,300 $452,000 $0 $2,998,400

Page 61: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  55

Table 5‐9  Estimated Capital Financing Plan 

Line1indicatesthattheRegionalProductionUtilitywillbegin2016withnounencumberedcashorinvestmentsavailabletofundcapitalcost.Anoptionwouldbetousesomeorallofthecontributionsfromotherentitiestoinitiallyfundtheconstructionfund,however,thatoptionisnotpresentedinthisReport.Arevenuebondissueintheamountof$142,500,000in2016isprojectedandshownonLine2ofTable5‐9.Theproceedsofthisissuancewillfundallcapitalrelatedcostsin2016and2017.Theamountsandyearsofeachloanaredevelopedconsideringcapitalprogramneedsandothersourcesofcapitalimprovementfinancing.

Cashfinancingofcapitalimprovementsfromannualrevenuesisexpectedtototal$3,500,000forthestudyperiodasindicatedonLine3ofTable5‐9.Interestincomeonthecapitalfunds,whichisshownonLine4,reflectsanassumed1.0percentannualinterestrate.Line5showsthetotalofallfundsavailabletofinancethecapitalimprovementprogram.

Theapplicationoffundsshowthat$15,615,400majorcapitalimprovementsexpendituresareprojectedovertheplanningperiodasshownonLine6.Line7showsthenetrepaymentofoutstandingdebtcurrentlyheldbyDMWWrelatedtothecorenetworkandpurchasedcapacity.ThenetcashpaymenttoDMWWtoachievealignmentbetweenthesystemcapacityandnetvalueispresentedonLine8.Line9ofTable5‐9showsthedebtissuancecostsassociatedwiththeprojectedbondissuance.Thiscostisestimatedtobe2.0percentofthetotalissuanceamount.Line10reflectstheestimateddebtservicereserverequirementwhichisequaltoannualprincipalandinterest.Theissuancecostanddebtservicereserveamountsareassumedtobefundedfromthebondproceeds.

Line11showsthetotalofallfundapplications.TheendofyearbalanceisshownonLine12,andreflectsLine11subtractedfromLine5.

5.2.7 Projection of Annual Revenue Requirements and Effective Rate 

Table5‐10showstheprojectedfinancialobligationsforthenewRegionalProductionUtilityfortheperiod2016through2020.ThistablesummarizesO&Mexpense,debtservicerequirementson

Line

No. Description 2016 2017 2018 2019 2020

Construction Funds Available

1 Beginning Balance ‐$                         6,242,500$       338,900$           392,800$           396,700$          

2 Revenue Bond Proceeds 142,500,000 0 0 0 0

3 Transfer from Operating Fund (Cash Financing) 0 0 500,000 0 3,000,000

4 Interest Income 62,200 62,700 5,900 3,900 19,100

5 Total Funds Available 142,562,200$   6,305,200$       844,800$           396,700$           3,415,800$      

Construction Funds Used

6 Major Capital Improvements 6,198,700$       5,966,300$       452,000$           ‐$                         2,998,400$      

7 Repayment of Outstanding DMWW Debt 29,944,000 0 0 0 0

8 Net Cash Payment to DMWW 89,086,000 0 0 0 0

9 Revenue Bond Issuance Expense 2,850,000 0 0 0 0

10 Revenue Bond Debt Service Reserve Requirement 8,241,000 0 0 0 0

11 Total Funds Utilized 136,319,700$   5,966,300$       452,000$           ‐$                         2,998,400$      

12 Ending Balance 6,242,500$       338,900$           392,800$           396,700$           417,400$          

Page 62: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  56

proposedbonds,thetransferofoperatingfundsformajorcapitalimprovementfinancing,andcapitalrenewalandreplacementcosts.

O&Mexpense,previouslyprojectedinTable5‐6,isshownonLine1.EstimateddebtservicerequirementsonrevenuebondsprojectedtobeissuedtohelpfinancemajorcapitalprogramexpendituresandothercapitalrequirementsareshownonLines2and3.Revenuebondsindicatedtobeissuedduringthestudyperiodareassumedtobe30year,4.0percentfixedinterestbondswithequalannualpaymentsofprincipalandinterest.Line4reflectstheprojectedtransferoffundsfromoperationstoassistinmajorcapitalfinancing.CapitaloutlayforrenewalsandreplacementsisshownonLine5ofTable5‐10.Line6indicatesthetotalrevenuerequirementsforthefiveyearperiod.

Table 5‐10  Summary of Revenue Requirements and Unit Cost Development 

Todeterminetheeffectiveunitcostper1,000gallonsofbilledwaterconsumption,usagefromeachofthe14contributingentitieswasprojectedbasedonhistoricalbilledusageprovidedbyDMWW.AsummaryofhistoricalandprojectedwaterusageispresentedinTable5‐11.Projectedquantitiesarebasedon(1)recognitionofhistoricalusagequantitiesandtrends,(2)totalwaterconsumptionbythecontributingentities,and(3)projectedgrowthratesinthecustomerbase.

Line

No. Description 2016 2017 2018 2019 2020

1 Operating Expense $25,072,700 $25,824,800 $25,487,800 $26,252,400 $27,040,000

Debt Service

2 Projected Future Bonds 8,241,000 8,241,000 8,241,000 8,241,000 8,241,000

3 Total Debt Service on Bonds 8,241,000 8,241,000 8,241,000 8,241,000 8,241,000

4 Cash Financing of Major Capital 0 0 500,000 0 3,000,000

5 Renewals & Replacement 11,616,000 11,289,000 11,164,000 11,616,000 11,616,000

6 Total Revenue Requirements $44,929,700 $45,354,800 $45,392,800 $46,109,400 $49,897,000

7 Projected Usage ‐ 1,000 gal. 17,857,100 18,010,100 18,165,300 18,322,900 18,482,900

8 Unit Cost ‐ $/1,000 gal. $2.52 $2.52 $2.50 $2.52 $2.70

Page 63: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  57

Table 5‐11  Projected Billed Water Usage 

(1)

(2)

(3)

(4)

(5)

(6)

(7)

(8)

(9)

(10)

(11)

Line

2‐year

Projection

No.

Description

2013

2014

Average

Base

2016

2017

2018

2019

2020

1,000 gal.

1,000 gal.

1,000 gal.

1,000 gal.

1,000 gal.

1,000 gal.

1,000 gal.

1,000 gal.

1,000 gal.

Contributing Entities

1Des Moines Water Works

7,931,336

7,387,434

7,659,385

7,659,385

7,659,385

7,659,385

7,659,385

7,659,385

7,659,385

2Polk Co. (SE and Unincorporated)

693,540

640,478

667,009

667,009

687,169

697,477

707,939

718,558

729,336

3Berw

ick Water Association

29,449

32,930

31,189

31,189

32,132

32,614

33,103

33,599

34,103

4Urbandale W

ater Works

1,668,940

1,415,742

1,542,341

1,542,341

1,588,958

1,612,793

1,636,985

1,661,539

1,686,462

5West Des Moines Water Works

899,201

739,937

819,569

2,469,969

      

2,544,624

2,582,793

2,621,535

2,660,858

2,700,771

6Ankeny

1,716,937

1,531,156

1,624,046

1,624,046

1,673,133

1,698,230

1,723,703

1,749,559

1,775,802

7Clive

659,958

584,555

622,256

622,256

641,064

650,680

660,440

670,346

680,402

8Waukee

437,206

395,094

416,150

416,150

428,728

435,159

441,686

448,312

455,036

9Warren Rural W

ater

670,806

557,656

614,231

614,231

632,796

642,288

651,922

661,701

671,627

10Xenia Rural W

ater

513,240

612,208

562,724

562,724

579,732

588,428

597,255

606,214

615,307

11Norw

alk

254,975

239,462

247,219

247,219

254,691

258,512

262,389

266,325

270,320

12Bondurant

118,588

148,747

133,667

133,667

137,707

139,773

141,869

143,997

146,157

13Altoona

150

                  

22                     

86876,000

          

902,477

916,014

929,754

943,701

957,856

14Polk City

99,447

84,015

91,731

91,731

94,504

95,921

97,360

98,820

100,303

15Total

15,693,772

14,369,436

15,031,603

17,557,917

17,857,100

18,010,066

18,165,326

18,322,915

18,482,868

Page 64: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  58

BasedonhistoricaldataprovidedbyDMWW,itwasdeterminedthatusagein2013and2014reflectstypicalweatherconditionsandwaterusage,therefore,theaverageof2013and2014wasusedasthebasisforprojectedwaterusage.ThehistoricalwaterconsumptionforWestDesMoinesWaterWorksandtheCityofAltoonadoesnotreflectwaterproducedbythewatertreatmentplantscurrentlyownedandoperatedbythoseentities.UndertheRegionalProductionUtility,theseplantswouldbeincludedintheassetspurchased.Therefore,thewaterprovidedbytheseplantstoservetheCitiesofWestDesMoinesandAltoonaisincludedintheprojectionbaseforthenewRegionalProductionUtility,andisshowninColumn6ofTable5‐11.Projectedusagethrough2020reflects0.0percentgrowthfortheDesMoinesWaterWorksserviceareaand1.5percentgrowthforallotherentities.Thisreflectsconservativeestimatesbasedonhistoricalgrowthandassumedfuturegrowthasprovidedbyeachentity.Salesvolumesforthisperiodareprojectedtoincreaseatanaveragerateofabout1.0percentannually.

Line8ofTable5‐10showstheprojectedunitcostforwaterpurchasedfromthenewentityper1,000gallonsbasedontherevenuerequirementsonLine6dividedbytheprojectedbilledusageshownonLine7.

5.2.8 Financing alternatives 

Theunitcostsdeterminedintheprevioussectionarebasedonfinancingallcapitalrelatedcostsin2016and2017withtheissuanceofarevenuebond.Asanalternative,ifthenewRegionalProductionUtilitycouldreachagreementonarepaymentscheduledirectlywithDMWW,thenasmallerrevenuebondcouldbeissuedfortheremainingcapitalcostsandthenewRegionalProductionUtilitywouldpaylessinbondissuancecostsanddebtservicereserve.Table5‐12reflectstheproposedrevenuerequirementsandunitcostforthisscenario.ProposeddebtserviceonLine2reflectsarevenuebondissueintheamountof$51,000,000whichwouldbeusedtofundtherepaymentofoutstandingDMWWdebtandmajorcapitalprojectsin2016and2017.Line4showstheestimatedannualpaymentsthenewRegionalProductionUtilitywouldmakedirectlytoDMWWaspaymenttoachievealignmentbetweenthesystemcapitalandnetvalue.Thesepaymentsarebasedona40‐yeartermand5percentinterest.Line9indicatesthatthisfinancingoptionwouldhaveafavorableimpactontheproposedunitcostswhencomparedtodebtfinancingallinitialcapitalcosts.

Page 65: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  59

Table 5‐12  Alternative Revenue Requirements and Unit Cost Development 

5.2.9 Effective Rate sensitivity 

Inanefforttodeterminehowmuchtheunitcostswillfluctuateasaresultofchangesinassumptions,aratesensitivityanalysiswasperformedcomparingtheinitialbaserun(Table5‐10)against3alternatives.TheresultsaresummarizedinTable5‐13.Line1ofTable5‐13reflectsthesameunitcostsshowninTable5‐10.

Thefirstvariabletobeconsideredwastheestimatedfairmarketvalueforthecontributedassets.TheinitialbaserunshowninTables5and6isbasedonthemid‐rangevalueofassets;however,therevenuerequirementswerealsodeterminedusingthelow‐rangevalueofassets.TheresultingunitcostsarepresentedinLine4ofTable5‐13andreflectadecreaseofapproximately4percent.

Thesecondvariableconsideredwastheestimatedrenewalandreplacementcosts.Theestimatedrenewalandreplacementcostsreflectahighlevel,conservativeestimate.However,additionalplanningandengineeringcouldresultinalower,actualamount.Therefore,theestimatedrenewalandreplacementcostswerereducedby15percent.Lines2and5inTable5‐13reflectthereducedunitcostsforthemid‐rangeandlow‐rangevaluation,respectively.

Line

No. Description 2016 2017 2018 2019 2020

1 Operating Expense $25,072,700 $25,824,800 $25,487,800 $26,252,400 $27,040,000

Debt Service

2 Projected Future Bonds 2,660,000 2,660,000 2,660,000 2,660,000 2,660,000

3 Total Debt Service on Bonds 2,660,000 2,660,000 2,660,000 2,660,000 2,660,000

4 Net Cash Payment to DMWW 5,192,000 5,192,000 5,192,000 5,192,000 5,192,000

5 Cash Financing of Major Capital 0 0 500,000 0 3,000,000

6 Renewals & Replacement 11,616,000 11,289,000 11,164,000 11,616,000 11,616,000

7 Total Revenue Requirements $44,540,700 $44,965,800 $45,003,800 $45,720,400 $49,508,000

8 Projected Usage ‐ Mgal 17,857,100 18,010,100 18,165,300 18,322,900 18,482,900

9 Unit Cost ‐ $/Mgal $2.49 $2.50 $2.48 $2.50 $2.68

Page 66: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  60

Table 5‐13  Rate Sensitivity Comparison 

Thethirdvariableconsideredforthesensitivityanalysiswasthegrowthrateofprojectedbilledwaterusage.Thegrowthassumptionsusedintheinitialbaserunreflectaconservativeoverallannualgrowthrateof1.0percent.TheunitcostsshowninLines3and4ofTable5‐13reflectaslightlyhigherannualgrowthrateof1.5percent.Theunitcostsdecreasebyapproximately1.5percent.

5.3 ANALYSIS OF EFFECTIVE RATE InanefforttoprovideacomparisonbetweentheeffectiveratespresentedinthisReportandDMWW’sexistingwholesalerates,itisusefultotakeintoconsiderationtheeffectiveratethatcontributingentitiesarecurrentlypayingforpurchasedwater.ThecurrenteffectiveratetakesintoconsiderationthepurchasedcapacityratechargedbyDMWW,aswellastheoutstandingdebtservicerelatedtoPurchasedCapacityAgreements.

DMWWissueddebtforeachofthefourentitiesshownonLines1through4ofTable5‐14forpurchasedcapacity,andeachentityreimbursesDMWWfortheannualprincipalandinterestpayment.Theannualprincipalandinterestpaymentduein2016foreachcommunityisshowninColumn4.Theunitcostper1,000gallonsfordebtserviceisdeterminedbydividingtheannualprincipalandinterestpaymentinColumn4bytheprojectedbilledusagefor2016,showninColumn3.TheresultingunitcostfordebtservicerelatedtopurchasecapacityisshowninColumn5.

DMWW’spurchasecapacityratewillincreasefrom$1.46per1,000gallonsto$1.53per1,000gallonseffectiveApril1,2015;anincreaseof4.8percent.Forcomparisonpurposes,itisassumedthattheratewillincreaseanother4.0percentin2016to$1.59per1,000gallonsasshowninColumn7ofTable5‐14.TheeffectiverateforthefourentitiesidentifiedinTable5‐14isdeterminedbyaddingtheunitcostfordebtservice(Column5)andtheestimated2016purchasedcapacityrate(Column7)andisshowninColumn8.ThecalculatedcurrenteffectiveratefromTable5‐14isgenerallylowerthanthepotentialeffectiveratefortheRegionalProductionUtilityshowninTable5‐10.Whenthelowrangeportionofthevaluationestimateisusedinthefinancialanalysis,

Line

No. Description 2016 2017 2018 2019 2020

$/1,000 gal. $/1,000 gal. $/1,000 gal. $/1,000 gal. $/1,000 gal.

Mid‐Range Valuation

1 Conservative Base Run $2.52 $2.52 $2.50 $2.52 $2.70

2 Reduction in R&R $2.42 $2.42 $2.41 $2.42 $2.61

3 Higher Usage Projection $2.49 $2.48 $2.44 $2.44 $2.61

Low‐Range Valuation

4 Conservative Base Run $2.40 $2.41 $2.39 $2.41 $2.59

5 Reduction in R&R $2.31 $2.31 $2.30 $2.31 $2.50

6 Higher Usage Projection $2.38 $2.37 $2.33 $2.34 $2.50

Page 67: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  61

theresultingeffectiverate(Table5‐13,Line4)ismorecomparabletothederived,currenteffectiverateinTable5‐14.

Table 5‐14  Effective Rate Comparison 

Whiletheabovecomparisonprovidesanindicationofthecurrentcomparison,Black&Veatchrecommendsthateachentityundertakeitsownseparateanalysis,aseachentityisfamiliarwiththecostsitmayhaveincurredtopurchasecapacityorcontributetoDMWWovertheyears.Ingeneral,theestimatedeffectiverateisnotcompletelyoutoflinewithcurrenteffectiveratespaidbyregionalutilities.

ItisalsoimportanttonotethattheeffectiverateunderthepotentialRegionalProductionUtilityofapproximately$2.52per1,000gal.islessthanDMWW’scurrent“WithStorage”rateforwholesalecustomers.The“WithStorage”rateincludesthefullyloaded,wholesaleratethatrecoversO&M,depreciation,andreturnoninvestmentfromwholesalecustomers.

5.3.1 Future Considerations 

WhilethecomparisonoftheeffectiverateunderaRegionalProductionUtilitycomparedtothecurrentwholesalearrangementprovidesvaluableinformationtoseehowcurrentcostsmightchange,itisalsoimportanttoconsiderthevalueofpotentialchangestomeetingfuturegrowthdemands.

Underthecurrentwholesalearrangement,autilitythatneedsadditionalcapacitymorethanlikelymustobtainitfromDMWW.Black&VeatchunderstandsthatDMWWwillidentifythecostofthenecessaryimprovementstoaddtothecapacity,andthenpassthatcostsolelyalongtotheutilitythatrequiresthecapacity.ThisapproachbyDMWWisnotuncommonandisdonetoprotectexistingcustomersbeingoverlyburdenedoncostsforadditionalcapacitythatmaynotbenefitthem.

(1) (2) (3) (4) (5) (6) (7) (8)

Estimated

2016 2015 2016 Estimated

Line 2016 Annual P&I per Purch Cap Purch Cap 2016 Effective

No. Description Usage P&I 1,000 gal. Rate (a) Rate Rate

1,000 gal. (4) / (3) (6) x 104% (5) + (7)

1 City of Ankeny 1,673,133 $939,828 $0.56 $1.53 $1.59 $2.15

2 City of Urbandale 1,588,958 $1,072,853 $0.68 $1.53 $1.59 $2.27

3 City of Waukee 428,728 $333,566 $0.78 $1.53 $1.59 $2.37

4 West Des Moines Water Works 739,937 $301,794 $0.41 $1.53 $1.59 $2.00

Des Moines Water Works ‐ Wholesale (a)

5 Purchased Capacity $1.53

6 With Storage $3.33

7 Off Peak $1.72

(a) Effective April 1, 2015.

Page 68: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  62

OnepotentialoptioncouldbefortheRegionalProductionUtilitytoshareintheoverallcostsforexpandingthecapacityofthesystem.ThesharingofexpansioncostsunderthisoptionwouldbeconsistentwiththenetvalueapproachoutlinedinthisReportthatbringsparticipantsintotheRegionalProductionUtilityonanequalbasis(netvaluepermgd).

Table5‐15providesahypotheticalexampleforconsideration.Inthisexample,itisassumedthatanadditional20mgdofcapacityisrequiredtoserve4customers.Thehypotheticalprojectcostofthisadditionalcapacityis$60,000,000andwillbefinancedwitha30yearrevenuebondwith4percentinterest.Theannualprincipalandinterestpaymentwillbe$3,470,000.Underthecurrentorganizationalstructure,thefourcommunitiesallocatetheannualprincipalandinterestpaymentbasedontheallocationofthenewcapacity.Eachcommunity’scostofdebtper1,000gallonsisbasedontheirshareoftheannualdebtserviceallocatedtotheirannualusage,whichresultsinunitcostsrangingfrom$0.35per1,000gallonsto$1.73,asshowninTable5‐15.

Thealternativeoptionreflectsthesharingofsystemexpansioncostsof20.0mgdamongallregionalparticipants.AsshownonLine5,theunitcostofdebtper1,000gallonsisbasedontheannualdebtserviceallocatedtothetotalregionalbilledwaterusageandresultsin$0.20per1,000gallons.Theannualsavingsthateachofthefourcommunitieswouldrealizeundertheregionalentityscenariorangesfrom$379,000to$785,000.

Table 5‐15 Future Expansion Example 

Existingutilitiesand/orcommunitiesthatarecustomersofDMWW,andthatarenotanticipatinggrowthmaybalkattheoptionofaregionalwaterutilitysharingexpansioncostsamongallregionalentities.However,theseentitiesmustconsiderthepotentialofgrowthcommunitiespursuingtheirfuturewaterneedseitherindividually,orasagroupseparatefromDMWW.Overtime,thelossofrevenuefromanycustomerthatleavesDMWWcouldresultinincreasestocustomersthatremainasfixedcostsoftheDMWWsystemarespreadoverasmallerbilkedusagebase.

LINE NO.  UTILITY 

CAPACITY NEEDED (MGD)

ANNUAL PRINCIPAL 

AND INTEREST (1)

BILLED USAGE 

(1,000 GAL.)COST PER 1,000 GAL. 

CURRENT SITUATION 

1  Utility No. 1  5.0 $867,000 1,200,000 $0.72 

2  Utility No. 2  5.0 $867,000 2,500,000 $0.35 

3  Utility No. 3  5.0 $867,000 1,400,000 $0.62 

4  Utility No. 4  5.0 $867,000 500,000 $1.73 

POTENTIAL OPTION – REGIONAL PRODUCTION UTILITY

5  Total Regional Utility  20.0 $3,470,000 17,557,917 $0.20 

 

Page 69: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Financial Analysis  63

5.3.2 Communities That Opt Out 

AnotherquestionisrelatedtotheimpactofthisStudyshouldoneormoreentitiesdecidenottojointheRegionalProductionUtility.With14differententitiesincludedintheNetValueanalysisabove,analyzingthemultiplescenariosthatcouldmaterializeisbeyondthescopeofthisStudy.Therearehowever,severalitemstoconsider.

First,iftheentitythatoptsoutcontinuestoreceiveitswaterfromtheRegionalProductionUtility,theimpacttotheeffectiverateinTable5‐10wouldlikelybenegligible.ThisisbecausetheprojectedcostsoftheRegionalProductionUtilitywouldbespreadoverthebilledusagewhichwouldincludetheentitythatoptsout.

Second,iftheentitythatoptsoutdecidestopurchaseorproducewaterseparatefromtheRegionalProductionUtility,thenthepotentialimpacttotheeffectiverateinTable5‐10wouldbenegative.Thisisparticularlythecaseiftheentityisalargeruserofwater.ThebilledusagedeductedfromthetotalregionalbilledusagewouldresultinahighereffectiveratefortheRegionalProductionUtility.

Finally,ifoneormoreentitiesdecidetooptout,thenthepercentageofadjustednetvalue(seeTable5‐4)wouldchange.EachoftheentitiesthatjointheRegionalProductionUtilitywouldreceivealargershareofnetvalue,orequityintheorganization.

5.4 FINANCIAL ANALYSIS CONCLUSION ForpurposesofthisStudy,Black&VeatchdeterminedanestimatedrangeofvaluefortheassetsthatcouldbetransferredtoanewRegionalProductionUtility.ShouldCIRDWCmembersdecidetomoveforwardwithformingtheRegionalProductionUtility,therangeofvalueestimateprovidesabasisforconsiderationandnegotiation.

TheNetValueanalysisalsoprovidesamethodforbringingregionalparticipantsintotheRegionalProductionUtilityonanequalbasis.Itisachievedbyassessingthenetvaluethateachentitybringstothetable,andthenadjustingeachentitytothesamenetvaluepermgdofcapacityusingcontributionsandacashpaymenttoDMWW.Becauseeachparticipantcomesintotheendeavoronanequalbasis,auniformrateispossible,alongwiththesharingofbothongoingmaintenancecostsandexpansionofthesystem.

Black&VeatchalsodevelopedaprojectionofrevenuerequirementsforthefirstfiveyearsoftheRegionalProductionUtility.Thisresultedinanestimatedeffectiverateof$2.52per1,000gallons.ThiseffectiverateappearstobehigherthanthecurrenteffectiveratesforWDMWW,UrbandaleWaterWorks,Ankeny,andWaukeebyabout6.0percentto26.0percent.However,thishighercostprovidesentitieswithparticipationinthegovernanceoftheRegionalProductionUtility.Itshouldalsobeevaluatedinthecontextofhoweachentitywillfinancefutureimprovementsforadditionalwatersupply.

Page 70: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Governance  64

6 Governance 

6.1 POTENTIAL INITIATING PRINCIPLES DuringthefirstphaseofthisStudy,CIRDWCmembersprovidedfeedbacktoBlack&VeatchwithrespecttotheirreasonsforpotentiallycreatingaRegionalProductionUtility,aswellaspotentialconcernsthatmightarisefromcreatingandjoiningaRegionalProductionUtility.BasedonfeedbackfromthestakeholderinputandSWOTAnalysismentionedabove,thefollowingsectionsoutlinepotentialinitiatingprinciplesthatparticipantscouldincludeinafoundingdocumentfortheRegionalProductionUtility.ThepurposeoftheseprincipleswouldbetoprovideanorganizationalframeworkforoversightoftheRegionalProductionUtilityandallowfortheregionalgrowthandexpansionofthewatersystem.

FutureSourceofSupply–Memberswouldneedtoagreetoberestrictedfromindependentlydevelopingtheirownsourceofsupply,unlessapprovedbytheRegionalProductionUtility.Thisprinciplebalancestheregionalneedforwatertosupportgrowingcommunitieswithaconcernthatcommunitiesactingindependentlyonsourceofsupplyissuescouldcreateaninefficientregionalsystemforwaterdelivery.Forexample,ifacurrentwholesalecustomerofDMWWdevelopsitsownsourceofsupplyandleavesDMWWasacustomer,thecurrentDMWWcorenetworkcouldoperateinanunder‐utilizedmanner.Thiswouldleavefixedcostsforthecorenetworktobelargelybornbycustomersthatdonotutilizeasignificantportionofthecorenetwork.

FuturePurchaseofFinishedWater–Memberswouldneedtoagreetopurchaseallfuture,finishedwaterfromtheRegionalProductionUtility.ThisprinciplebalancestheneedtodevelopaRegionalProductionUtilitythatisdedicatedtoservingtheregion,withthepotentialnegativeimpactthatcouldariseifmembersoftheRegionalProductionUtilitydeveloptheirownsourceofsupplies,orenterintoseparateagreementsforwaterfromotherentities.Anadvantageofhavingtotalcommitmentfromallmembersisthatexistingandfuturecostsofthecorenetworkwouldbecoveredbyagrowingbasedofbilledusageand/orcustomers.

WaterQuality–MemberswouldneedtoagreetosupporttheapprovedinitiativesoftheRegionalProductionUtilityrelatedtosourceandfinishedwaterquality.DuringthestakeholderinputandSWOTAnalysis,CIRDWCmembersindicatedthatsourcewaterandfinishedwaterqualitywasimportanttothem.ThisprinciplestatesthatparticipantsintheRegionalProductionUtilitywouldcommittoapprovedinitiativesdesignedtoimprovebothsourceandfinishedwaterquality.

SystemPlanningandExpansion–Memberswouldneedtoagreetoparticipateinregionalwatersystemplanningtobenefittheentireregion.Thisprinciplepromotestheefficientplanningofthecorenetworksystem.Thisprinciplewouldbalancethedesireofgrowingcommunitiestodevelopasystemthatmeetsfuturedemand,withthedesireofnon‐growthcommunitiestoconductresponsibleplanningthatexpandstheregionalwatersystemefficiently.

OutstandingDebt–MemberswouldneedtoagreethatalldebtrelatedtotheirindividualsystemsorpreviousrelationshipwithDMWWremainseparatefromtheRegionalProductionUtility.ThisprincipleprotectstheRegionalProductionUtilityfromanynegativefinancialimpactsofdebtrelatedtothepotentialmembers.ThisdoesnotincludetheoutstandingdebtcurrentlyheldbyDMWWforthecorenetworkand/orpurchasedcapacityfinancedforwholesalecustomers.As

Page 71: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Governance  65

describedintheFinancialAnalysissectionofthisReport,thatdebtcouldbepaidoffbytheRegionalProductionUtility,orretiredinanotheracceptablemanner.Futurelegalandfinancialadvicewouldneedtobeundertakentodeterminethebestmannerforaddressingthatdebt.

RatesandCharges‐Memberswouldneedtoagreetoestablishsufficientratesandchargesthatsupportandmaintaintheexistingcorenetwork,aswellasexpandthecorenetworktomeetfutureregionaldemand.Thisprinciplewouldrequirethatfutureratesandchargeswillprovidecapitalforoperatingandmaintainingthecurrentcorenetworksystem,aswellasexpandingtheregionalsystemtomeetfuturedemand.

6.2 KEY GOVERNANCE ISSUES 

6.2.1 Voting Rights 

AnunderlyingpurposeforthisStudywasthedesireofregionalcommunitiestohaveavoiceintheplanningandprovisionofwatertotheregion.Thisincludesplanningtoaddresssourceofsupplyissuesandfuturedemands,aswellastheestablishmentofratesandcharges.DuringthestakeholderinputportionoftheStudy,CIRDWCmemberswereaskedtheiropinionwithrespecttohowtheyviewedgovernanceandvotingrights.MostoftheCIRDWCmembersrespondedthataweightingofvotingrightstoreflecttherelativesizeofregionalcommunitiesappearedappropriate.

TheNetValueanalysisportionoftheStudyprovidesamechanismwhereeachoftheparticipantswouldbeabletoparticipateintheRegionalProductionUtilityonthesamebasisintermsofthenetvaluepermgdofcapacityneededfromtheRegionalProductionUtility.BybringingthesamenetvaluepermgdtotheRegionalProductionUtility,Black&Veatchbelievesthisprovidesparticipantswiththeabilitytoestablishvotingrightsinseveraldifferentways.

Thefirstexamplethatcouldbeacceptableweightsaparticipant’svoteonthebasisofthenetvaluecontributedtotheRegionalProductionUtility.ThenetvaluereflectstheresultsofTable5‐4above,wherethenetvaluecontributedbyparticipantsequalstheirpercentageofthesystemtotalcapacity.ThefollowingTablereflectsahypotheticalexampleofaweightedvotebasedonthenetvaluecontributedbyparticipants.Ascanbeseen,anissuebroughtbeforetheRegionalProductionUtilityforconsiderationwouldbevotedonbyonememberforeachparticipant.EachvotewouldbeweightedbasedonthepercentageofnetvaluecontributedbyeachparticipanttotheRegionalProductionUtility.Inthishypotheticalexample,“yes”votesforfourparticipantscomparedto“no”votesfor10participants,resultsinoverallapprovalofthehypotheticalmeasure.

Page 72: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Governance  66

Table 6‐1  Hypothetical Weighted Vote Based on % of Net Value 

6.2.1.1 Other Voting Rights Options 

TheuseofnetvaluepermgdisoneoptionforestablishingvotingrightsformembersoftheRegionalProductionUtility.Anotheroptionwouldbetoweightthevoteusingthepopulationnumbersforeachparticipant.ThiswouldbesimilartothemethodologyusedbyWRA,whichassignsanadditionalrepresentativetomembersforeachpopulationincrementof25,000persons.WithrespecttotheRegionalProductionUtility,theuseofpopulationincrementscouldbeused,ordeterminingthetotalpopulationofparticipantsandusingtheresultingweightedpercentagecouldbeanotheralternative.

6.2.2 Board Makeup 

DuringthestakeholderinputandSWOTanalysis,are‐occurringthemefromCIRDWCmemberswastheirdesiretohaverepresentationwithrespecttogovernanceissues,includingestablishmentofratesandchargesandsystemplanning.ThiswillrequirealargeBoardthatwillneedtoaccommodatevaryingviewpointsongovernanceandregionalwaterissues.CIRDWCmembersdidstatethatthelargeWRABoardfunctionseffectively.

Aneffectiveboardmakeupwouldincludememberswhoareappointedbythegoverningbodiesoftheirrespectivecommunities.Theappointmentofboardmembersispreferabletoaboardthatismadeupofdirectlyelectedmembers.BasedonourdiscussionswithotherregionalwaterentitiesacrosstheU.S.,boardmembersthataredirectlyelectedtotheirpositionprovidesanadditionallayerofwaterpoliticsthatcaninterferewithaneffectivedecision‐makingprocess.Thiscanalsoresultinthepoliticizationofregionalwaterissuesandabreakdownofcooperationbetweencommunities.Thealternativeofgoverningthroughappointedmembersretainsaccountabilityofgoverningmemberstotheirrespectivecommunities,whileallowingappointedmemberstoworkonregionalwaterissuesinalesspoliticalenvironment.

Line (1) (2) (3) (4) (5) (6)

No. Description % Net Value Factor YES NO YES NO

=(1)x(2)x(3) =(1)x(2)x(4)

1 Des Moines Water Works 44.63% 100 1 44.63 0

2 Polk Co. (SE and Unincorporated) 1.45% 100 1 1.45 0

3 Berwick Water Association 0.19% 100 1 0 0.19

4 Urbandale Water Works 11.41% 100 1 0 11.41

5 West Des Moines Water Works 14.07% 100 1 0 14.07

6 Ankeny 9.40% 100 1 9.4 0

7 Clive 5.20% 100 1 5.2 0

8 Waukee 2.75% 100 1 0 2.75

9 Warren Rural Water 2.42% 100 1 0 2.42

10 Xenia Rural Water 2.20% 100 1 0 2.2

11 Norwalk 1.47% 100 1 0 1.47

12 Bondurant 0.90% 100 1 0 0.9

13 Altoona 3.65% 100 1 0 3.65

14 Polk City 0.26% 100 1 0 0.26

15 Total 100.00% 4 10 60.68 39.32

Page 73: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Governance  67

AprofessionalstaffwouldlikelybenecessarytoassisttheBoardinthedaytodayoperationoftheRegionalProductionUtility.StaffwouldincludeaGeneralManagerorExecutive,FinancialOfficer,ChiefEngineer,HumanResourceManager,andLegalManager.BasedonfeedbackfromCIRDWCmembersandBlack&Veatch’sexperience,importantcommitteeswouldlikelyinclude:

ExecutiveCommittee–ThiswouldbeimportantforalargeboardcontemplatedfortheDesMoinesregion.TheExecutiveCommitteeprovidesguidanceandfeedbacktotheprofessionalstaffasnecessaryandmayconsistofapproximatelythreemembers.Typically,theExecutiveCommitteewouldincludeaChair,ViceChair,andSecretary.TheExecutiveCommitteewouldbenominatedandappointedbytheboardatthebeginningofeachyear.

Planning/TechnicalCommittee–Thiswouldbeanimportantcommitteethatplansforthefutureexpansionoftheregionalwatersystem,aswellasplanningfortraditionalprojectssuchascapitalmaintenanceandwaterqualityenhancement.

FinanceCommittee–ThiswouldbeimportantformanagingtheoverallfinancesoftheRegionalProductionUtility,aswellastheestablishmentofratesandcharges.

6.2.2.1 Staff 

DuringthestakeholderinputportionoftheStudy,severalCIRDWCmembersnotedthatWRAcontractsoutoperationofthewastewatersystemtotheCityofDesMoines.Black&VeatchrealizesthatcontractingoutallorsomeoftheoperationsoftheRegionalProductionUtilitytoanotherentitycouldbeanoption.Nevertheless,itisalsolikelythattheRegionalProductionUtilitywouldwanttohaveaprofessionalstafftohandlemanagementandpolicyissuesrelatedtotheutility.Ingeneral,theprofessionalstaffwouldtypicallyconsistofthefollowingpositions:

ChiefExecutiveorGeneralManager–TheChiefExecutiveorGeneralManagerwouldberesponsiblefortheoveralloperationandmanagementoftheRegionalProductionUtility.Thisincludesresponsibilitiessuchasoversightofoperationstoensurewaterisproducedinsufficientquantitiesandofaqualitynecessaryfortheregion;planningtoensuretheabilityoftheRegionalProductionUtilitytomeetfuturedemand;financialmanagement;anddevelopmentandimplementationofBoardpoliciesandprocedures.TheChiefExecutiveorGeneralManagerwouldalsoretaintheauthoritytosignandexecutelegaldocumentsonbehalfoftheRegionalProductionUtility.

ChiefEngineer–TheChiefEngineerwouldoverseetheplanningandconstructionofanyimprovementsandwouldleadthedevelopmentofregionalplanningtoensurethewatersystemmeetstheneedsoftheregionandutilityparticipants.TheChiefEngineerwouldworkwiththeBoardTechnicalCommitteetoderiveanoverallplanforexpandingtheregionalwatersystemtomeetfuturedemand,aswellasperformingtheappropriateassetmanagementtoensuretheexistingsystemisingoodworkingorder.

ChiefFinancialOfficer–TheChiefFinancialOfficerwouldoverseeallfinancialaffairsoftheorganization.Thispositionwouldleadthedevelopmentoftheannualbudgetandauditprocesses,aswellasthedevelopmentofannualratesandchargestobeassessedbytheRegionalProductionUtility.TheChiefFinancialOfficerwouldworkcloselywiththeBoardFinanceCommitteetodevelopappropriatepoliciesandproceduresformaintainingappropriatefinancialcontrolswithrespecttothevariousfundsmaintainedbytheRegionalProductionUtility.

Page 74: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Governance  68

HumanResourcesManager–AHumanResourcesmanagerwouldberequirediftheRegionalProductionUtilityinheritsorhiresemployeesthatrunthedaytodayoperationsoftheutility.Thismanagerwouldoverseehiringpractices,training,disciplineissues,andotherpersonnel‐relatedissues.TheHumanResourcesmanagerwouldworkwiththeChiefFinancialOfficeronemployeebenefitissuessuchasannualpay,benefits,andretirementplanningissues.IftheRegionalProductionUtilitywerehireacontractoperator,theHumanResourcesManagermightnotberequired.Alternatively,itisfeasibletooutsourceHumanResourcefunctions.

Legal–ALegalmanagerorGeneralCounselwouldprovidetheBoardandstaffwithlegaldirectiononutilityissues.Additionally,thismanagercouldoverseeriskmanagementissues

6.3 GOVERNANCE ALTERNATIVES 

6.3.1 Traditional Municipal Governance 

ThefirstalternativeevaluatedbyBlack&Veatchconsistsofatraditionalmunicipalutilitygovernancemodelonaregionalbasis.DuringthestakeholderinputphaseofthisStudy,CIRDWCmembersgenerallyindicatedthattheDesMoinesMetropolitanWastewaterReclamationAuthority(WRA)wassuccessfulmodelforregionalgovernance.Black&VeatchreviewedtheAmendedandRestatedAgreementfortheDesMoinesMetropolitanWastewaterReclamationAuthoritythatoriginatedin2004.TheAgreementincludesprovisionsthatoutlineissuessuchas1)votingrights;2)organizationandpowersoftheboard;3)acquisitionandtransferofwastewaterassets;4)constructionoffutureimprovements;5)operationandmaintenanceofthewastewatersystem;and5)financialissuessuchasbudgeting,audits,andissuanceofbonds.Ingeneral,theAgreementprovidesagoodexampleofcomponentsthatwouldneedtobeaddressedshouldCIRDWCmembersdeterminetomoveforwardwithcreatingaRegionalProductionUtility.

Thereareseveralother,similarexamplesthathavebeencreatedacrosstheU.S.,albeitwithvariationsinthenumberofmembers,howtheyareelectedorappointed,orothergovernancematters.Thetraditionalmunicipalgovernancemodelconsistsofboardmembersthatareelectedorappointedbythecommunitiestheyrepresent,andthatexercisetheirauthorityunderstatestatutestoprovideapublicneed.Inthiscase,theprovisionofdrinkingwateronaregionalbasistothecommunitiesthatcomprisetheGreaterDesMoinesregion.ItshouldbenotedthatthisStudydoesnotincludealegalanalysisofformingaregionalwaterutility,oralegalanalysisastotheappropriateresponsibilitiesofaregionalwaterutility.ThatanalysiswillneedtobeundertakenbyCIRDWConaseparatebasisfromthisStudy.

ThereareseveralexamplesofcommunitiesacrosstheU.S.thathavecometogethertoaddresswaterneedsonaregionalbasis.Thefollowingprovidesabriefdescriptionofseveralutilitiesthatusetraditionalmunicipalgovernance:

CentralArizonaProject–TheCentralArizonaProject(CAP)isamulti‐countymunicipalcorporationgovernedbymembersrepresentingMaricopa,Pima,andPinalcounties.TheCAPprovidesapproximately1.5millionacre‐feetofwaterperyeartocentralArizona.TheCAPconsistsofasecure,open‐airwatercanalthatoriginatesatLakeHavasuandstretchesapproximately336milestotheCityofTucson.Therawwaterissuppliedformunicipal,agricultural,andtribaluse.ThemissionoftheCAPistobethestewardofcentralArizona'sColoradoRiverwaterentitlementandacollaborativeleaderinArizona'swatercommunity.

Page 75: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Governance  69

Governanceisconductedbya15‐memberBoardofDirectorsthatarepopularlyelectedfromMaricopa,Pima,andPinalcounties.Boardmembersservestaggeredsixyearterms.ThenumberofBoardmembersisgenerallybasedonthepopulationsofthecountiesrepresented.Thereare10membersfromMaricopaCounty;fourfromPimaCounty;andonefromPinalCounty.KeypowersincludetheresponsibilityformanagingthebusinessofCAP,executingallnecessarycontractsandinstrumentsfortheCAP,employingthestaffthatmanageandoperateCAP,receivingandinvestingmoniesforCAP,andestablishingrevenuebondingprogram.EstablishedBoardcommitteesconsistofanExecutiveCommittee,CentralArizonaGroundwaterReplenishmentDistrictCommittee,FinanceandAuditCommittee,andPublicPolicyCommittee.

TheBoardmanagesthedaytodayoperationsofCAPwithaGeneralManagerassociatedstafftotalingapproximately400employees.

TampaBayWater–TampaBayWater(TBW)isaregionalwatersupplyentitythatprovideswholesaledrinkingwatertotheFloridacommunitiesofHillsboroughCounty,PascoCounty,PinellasCounty,NewPortRichey,St.PetersburgandTampa.Thepopulationofthisregionisapproximately2.3million.ThemissionofTBWistoreliablyprovideclean,safewatertotheTampaBayregionnowandforfuturegenerations.Tomeettheneedsoftheregion,TBWderivesrawwaterfromgroundwater,surfacewater,andseawatersources.Themajorityofsupplyissuppliedfromwellfields,butissupplementedfromwatertreatedatsurfacewateranddesalinationtreatmentplants.ThehistoryofTBWdatesbacktothemid‐1990swhenthecommunitiesoftheregiondecidedtoformTBWtocooperateregionallyonwatersupplyandplanningissues.

GovernanceisconductedbyaninememberBoardofDirectorsconsistingofelectedpersonsappointedbytheirrespectivecommunities.TherearetwomembersrepresentingHillsboroughCounty;twomembersrepresentingPinellasCounty;twomembersrepresentingPascoCounty;onememberrepresentingtheCityofTampa;onememberrepresentingtheCityofSt.Petersburg;andonememberrepresentingtheCityofNewPortRichey.EachBoardmemberhasonevoteandapprovalofactionsbeforetheBoardrequiressixvotesoutofnine.

TBWhasanInterlocalagreementthatoutlinesthedutiesandresponsibilitiesofTBWandtheBoard.Ofsignificantnoteistheemphasisonwatermasterplanning,andexclusivityprovisionsrecognizingTBWastheprimarysupplierofregionaldrinkingwater.Therearecurrently125fulltimeemployeeswithaGeneralManagerthatoverseesthedaytodayoperationsonbehalfoftheBoard.

Thetwoorganizationsabovewerecreatedtoaddresswatersupplyissuesorotherregionalissuesthatareuniquetotheirownrespectiveregions.IntheinstanceoftheCAP,theregionalentitywasformedtomanagetheoperationofafederallyconstructedprojecttoensuresufficientwatersupplytoregionalstakeholders.TBWwasformedtocoordinatethemanagementofwatersupplyandtreatmentservicetoseveralregionalstakeholders.Bothhavedevelopedtheiruniquegovernancestructures,butcommonalitiesincludeboardsthatdeveloppoliciesandprovideoversighttoensuremanagementofwaterissuesonaregionalbasis.InBlack&Veatch’sopinion,asimilargovernancestructurecouldbecreatedtoaddressregionalwatersupply,treatment,andtransmissionissuesfortheGreaterDesMoinesregion.

Page 76: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Governance  70

6.3.2 Modification of Current Governance Arrangement 

Underthecurrentarrangement,DMWWcontrolstheproductionandtransmissionofdrinkingwatertotheGreaterDesMoinesregion.ThisincludesconductingtheplanningandsettingratesandchargestofundcapitalinvestmentandO&M.Onepotentialalternativewouldbetograntregionalcommunitiesgreaterinputintofutureregionalplanningandratesettingdecisions.Onemechanismforachievingthiswouldbetore‐negotiateexistingpurchasedcapacityagreementstoaddprovisionsrelatedtogovernanceoftheregionalutility.Thefollowingprovidesseveralaspectsthatcouldbeaddressedinare‐negotiatedpurchasedcapacityagreement.

FinancialPlanningandRateConsiderations–AconsistentthemefromCIRDWCmembersthatreceiveservicefromDMWWwasthattheratesettingprocesswasdifficulttounderstand.TherewasdiscussionaboutthedifficultyofunderstandingDMWW’srateprocess,aswellastheplanningandnotificationprocessforestablishingratesfromyeartoyear.Thiscouldbeoneareathatpurchasedcapacitycustomersre‐negotiateaspartoftheirexistingWholesaleServiceMasterAgreement.Potentialitemstoincludewouldhavetobenegotiated,however,negotiationpointscouldinclude:

● EstablishingafinancialplanningandratesettingcommitteethatconsistsofbothfullservicecustomersofDMWWandcustomerswithpurchasedcapacityagreements.Whilethecommitteewouldnothavefinalsayinthedeterminationofrates,itcouldserveasavenueforcustomerstoprovideinputtoDMWW,understandhowcostsareallocated,andratesdetermined.

● CostofServiceDetermination–Thecurrentcostofserviceandrateprocessisconductedinhouse.ApotentialsolutiontoderivemoreconfidencefromDMWWcustomerswouldbetojointlyhireaconsultingfirmtoperformacostofservicestudytoderivetheallocationofcoststoDMWWcustomers.

● RateProcess–Thiscouldincludeamoredetaileddescriptionthatcouldbeincludedinagreementsthatoutlinesthecostofserviceandrateprocess.Therateprocesscouldincludeadescriptionofcoststhatwouldbeincludedinpurchasedcapacityrates,etc.Therecouldbeadetailedexampleofthecostallocationprocessincludedintheagreementsforfutureunderstanding.Thegoalwouldbetoestablishanupfrontunderstandingofhowcostofserviceandratesareestablished.

WaterSystemPlanning–CommunicationonwatersystemplanningappearstoprimarilyoccurbetweenDMWWandindividualcommunities.OnewaytoexpandthistoamoreregionalbasiswouldbetocreateatechnicalorplanningadvisorycommitteetoassistDMWWwithunderstandingwaterneedsonbothanindividualcommunityandregionalbasis.Thiscommitteecouldalsofocusontrackingandmeetingregularlytodiscusspeakdayandpeakhourdemands,aswellasstrategiestomeetfuturedemands.Additionaltopicscouldincludesourcewaterqualityandfinishedwaterqualitytorepresenttheseissuesfromamoreregionalbasis.

Other–Theitemsabovearejustsomeexamplesofissuesthatcouldbere‐negotiatedbetweenDMWWanditsWholesaleMasterServiceAgreementcustomers.Otherimportantitemscouldadditionallybeadded,however,theyshouldgenerallyreflectissuesthatfurthergreaterregionalcooperation.

Page 77: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Governance  71

Intermsofgovernance,themodificationofthecurrentgovernancearrangementwillstillleavetheDMWWBoardofDirectorswithafinalsayinmattersimportanttoregionalcommunitiesandutilities.ThesuccessofthisalternativewouldbedependentontheabilityofDMWWandtheregionalcommunitiestoworktogethercollaborativelytobuildtrustandfurtherregionalcooperation.

6.3.3 Public Private Partnership 

PublicPrivatePartnerships(PPPs)withinthewaterindustryrepresentcooperationbetweenmunicipalandprivateentitiesintheareaofpublicwatersupply.Ingeneral,theuseofPPPsformajorU.S.watersystemshasbeenlimited,however,thereareseveralexampleswheremajormunicipalitiesutilizeprivateentitiesinsomeformtoassistwithprovidingwaterorwastewaterservicetocustomers.Severalexamplesinclude:

CityofBuffalo,NewYork–BuffaloWaterutilizesVeoliaWaterNorthAmericatooperateandmaintainitswatersupplyanddistributionsystem.BuffaloWaterretainsratesettingresponsibilityandoverallownershipofthewaterassets.

Indianapolis,IN–Intheearly2000s,theCityofIndianapolisutilizedPPPsinseveralinstancestoassistwiththeprovisionofwaterandwastewaterservice.Inapproximately2001,theDepartmentofWaterworkscontractedwithVeoliaWaterNorthAmericatooperateandmaintainthewatersystemassets,includingsupply,treatment,transmission,anddistributionassets.TheBoardofWaterworksmaintainedownershipoftheassets,aswellasresponsibilityfordevelopmentofpoliciesandstrategicdirectionoftheutility.TheCityofIndianapoliscontractedwithUnitedWatertooperateandmaintainthewastewatersystem.Thisincludedtheliftstations,collectionsystem,andtreatmentplantsownedbytheCity.Aswiththewatersystem,theCitymaintainedownershipofthewastewaterassets.In2011,boththewaterandwastewaterassetswerepurchasedbyCitizensEnergyGroup,alocalenergyutility.CitizensEnergyGroupnolongerusesVeoliatooperateandmaintainthewatersystem,butdoesutilizeUnitedWatertooperateandmaintainthewastewatersystem.

ThereareseveralotherexampleswherePPPsareutilizedbymunicipalitiesforwaterandwastewaterservicetocustomers.Ingeneral,PPPscanbeusedtofocusonareaswheremunicipalitiesmaylackexperienceortoachievecostsavingsinwaterorwastewaterservice.WithrespecttoregionalwaterservicefortheGreaterDesMoinesregion,CIRDWCmembersdidnotindicatethattheyviewedaPPPasapotentialsolution.However,Black&VeatchhasincludedthisalternativeinthisStudyasmeansofconsideringalternativegovernanceoptions.

ThereareseveralpotentialoptionsforaPPP.Thefollowingisprovidedasareasonableexample;however,theremaybeothermorepreferablePPParrangementsthatwouldhavetobeinvestigatedifCIRDWCbelievesthistobeapotentialalternative.

LongTermLease–Underalongtermleasearrangement,thecurrentownerofthecorenetworkwouldlikelyreceiveanupfrontpayment.Inexchange,theprivateentitywouldmanage,operate,andmaintainthesystemunderaleaseagreement.Theleaseagreementwouldhavetobenegotiatedtoreflectkeyprovisionsdesiredbyregionalparticipants,includingitemssuchaswaterqualityexpectations,ratesandcharges,sharingofcostsavings,andotherimportantitems.Theprivateentitywouldprovidekeygovernancerolesfortheutilityduringthetermofthelease.

Page 78: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Governance  72

Thisincludessettingpoliciesandprocedures,establishingratesandcharges,andotherpolicy‐relateditems.Itistypicalwithinotherstatesforastateregulatorybodytooverseeratesandchargesforinvestor‐ownedutilities.Considerationofhowratesandchargeswouldbeimplementedwouldbeakeycomponentoftheleaseagreement.ConsiderationwouldalsoneedtobegiventowhatroletheIowaUtilitiesBoardwouldplay,ifany.

ThepotentialbenefitsofthisarrangementincludepotentialO&Mcostsavings.Thesecostsavingscouldbesharedbetweentheprivateentityandtheratepayers.Othernon‐costbenefitscouldincludegovernanceanddecision‐makingfromanunbiasedperspective.Intheory,aprivateentitywouldmakeregionalwaterdecisionswithlessconcernforindividualcommunityneeds.Capitalinvestment,bothforupkeepoftheexistingsystemandexpansiontomeetfuturedemand,wouldbemadetoderiveanefficientregionalsystem.Finally,aleasearrangementhasanexpirationdate,albeitlongerterm,forendingtheleaseshouldcustomersbeunhappy.

Thepotentialdrawbacksofthisarrangementareevidentinthatregionalcommunitieswouldhavelimitedsayinthegovernanceoftheregionalprovisionofwater.ThedesireforhavingasayinthegovernanceofaRegionalProductionUtilitywasakeyreasonforCIRDWCimplementingthisStudy.Additionally,implementationofcapitalprojectsistypicallymoreexpensiveforprivateorinvestor‐ownedutilities.Municipalutilitieshavetheabilitytoissuetax‐exemptdebtandcanissuerevenuebondsatcompetitiveinterestrates.Privateorinvestor‐ownedentitiesgenerallycannotissuetax‐exemptdebtandrequireahigherrateofreturnoninvestmentfortheirownersorshareholders.

OtherModifications–Asindicatedabove,thereareotherPPPalternativesthatCIRDWCcouldexplore.Asakeydrawbacktothelongtermsystemleasewasthelackofgovernanceforregionalcommunities,amodificationtotheleasearrangementwouldbetoallowsomeformofgovernancebyregionalcommunities.Thiscouldincludeprovidingoversightonkeyitemssuchasratesandcharges,systemplanning,waterquality,andotheritems.Thisgovernancemodificationandtheinteractionwiththeprivateorinvestor‐ownedentitywouldhavetobecarefullyconsideredanddocumentedtoensuresuccessbothfortheregionalcommunitiesandfortheprivateorinvestor‐ownedentity.

Page 79: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Next Steps  73

7 Next Steps ThecompletionofthisStudyisCIRDWC’sfirststeptowardevaluatingwhethertoformaRegionalProductionUtility.ThisStudyhasprovidedvaluableinformation,includinganestimateofvalueofassetsthatcouldbetransferred,aprojectedfiveyearscheduleofrevenuerequirements,andanestimatedeffectiverateforcomparingtothecurrentcostofwaterfromDMWW.Additionally,CIRDWCmembersevaluatedthestrengths,weaknesses,opportunities,andthreatsofthecurrentmethodforprovidingwater,versustheregionalalternative.ThenextstepsmustcontinuetodriveCIRDWCmembersclosertoultimatelydeterminingwhethertoformtheRegionalProductionUtility.Thefollowingsectionsincludebothshortandlongertermtaskstocontinuemovingtowardafinaldetermination.

7.1.1 Short Term 

WithrespecttothisStudy,thereareseveralissuesthatshouldbeconsideredfurtherbyCIRDWCmembers.Thisfurtherconsiderationcanbecompletedintheshortterm,whichisapproximately4to6monthsafterthecompletionofthisStudy.Onemethodforconsideringissueswouldbetoformsub‐committeestomoreefficientlyreviewelementsofthisStudyandfutureissuestoberesolved.Thegoalofeachsub‐committeewouldbetoconsiderelementsofthisStudy,assesswhetheranydealbreakersexist;assesswhethertherearebetteroptionsforcreatingaRegionalProductionUtility;anddevelopconclusionsandrecommendationsthatcanbepresentedtothefullCIRDWCboard.ThefollowingaresomeitemsthatCIRDWCmembersmaywanttoconsiderfurther:

Financial–ThefinancialreviewwouldconsistofreviewingtheestimatedvaluationforthisStudy,aswellastheNetValueanalysisandderivationoftheeffectivefortheRegionalProductionUtility.AhigherorlowervaluationestimateimpactsthecashpaymenttoDMWWaswellascontributionstoandfromindividualentities.Questionstoconsiderinclude:Doesthevaluationestimateappearreasonable?Ifnot,whatisabetterestimate?DoestheNetValueanalysisappeareffectiveforbringingregionalparticipantsintotheutilityonanequalbasis?HowshouldoutstandingdebtheldbyDMWWbehandled?CanthecashpaymenttoDMWWbereduced?Istheresultingeffectiverateanon‐startercomparedtotheexistingrate?

Theanswerstothesequestionscanvary,however,bydiscussingtheseissuesamongCIRDWCmembers,greaterclarityandacommonunderstandingacrossCIRDWCcandevelop.

Technical–ThetechnicalreviewwouldconsistoffocusingonthetechnicalaspectsoftheRegionalProductionUtility.Questionstobeconsideredcouldinclude:ShouldanyotherregionalassetsbeincludedintheStudy?ShouldanyoftheregionalassetsincludedintheStudybeexcluded?Howwouldoperationsbeperformed?HowwouldtheRegionalProductionUtilitybemanaged?

Governance–Thegovernancereviewcouldfocusonquestionssuchas:Shouldboardmembersbeelectedorappointed?Whatcommitteesshouldbeestablished?Howwouldvotingrightsbeweighted?Whatwouldbegeneraldutiesandresponsibilitiesofboard?Howwouldnewmembersjoin?

Theaboveprovidejustsomeexamplesofareasthatsub‐committeescouldconsider.Oncetheseissueshavebeenaddressedinsub‐committee,aconsolidatedsetofconclusionsandfindingscanbedevelopedbythefullCIRDWCboard.Atthispoint,conclusionsandfindingscanbediscussedwith

Page 80: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Next Steps  74

politicalandutilitygoverningbodiestoobtainadditionalinputandfeedback.CIRDWCcanthendeterminewhethertocontinuemovingforwardintheprocess.

7.1.2 Long Term 

ForpurposesofthisReport,longtermreflectsanadditionalperiodbeyondthe4to6monthshorttermperiodmentionedabove.ThiscouldlastanadditionalsixmonthsorlongerbeyondtheshorttermperiodandisonlynecessaryifCIRDWCdeterminestocontinuemovingforward.

7.1.2.1 Additional Due Diligence 

Atthispoint,itisenvisionedthatfurtherduediligencewouldbeneeded,includinglegalandfinancialanalysisofhowtheRegionalProductionUtilitywouldbeformed,transferofassets,establishingfinancialstatements,staffandmanagementplanning,andotherimportantmatters.Technicalduediligencecouldalsobedonetofocusinondevelopinginitialplansformaintainingthecorenetworkandproceedingwiththeinitialexpansion,includingpotentialprojectsandtiming.

Additionally,CIRDWCmaywanttobegindraftingamemorandumofunderstandingthatwouldformthebasisofaregionalagreement.Importantcomponentswouldlikelyincludeinitiatingprinciples,boardmakeupandresponsibilities,sharingofcosts,andotherareasimportanttopotentialparticipants.Thisadditionalduediligence,plusadraftmemorandumofunderstandingcanthenbepresentedtothefullCIRDWCboardforconsideration.

7.1.2.2 Public Input 

Shouldtheboarddeterminetomoveforward,itwouldlikelythenbeappropriatetobeginpublichearings.ThepublichearingscouldbeheldineachcommunitytopresentthemeritsofaRegionalProductionUtilitycomparedtothecurrentarrangement.Thiswillallowthepublictoconsidertheimpactofdeal,andprovideinputtotheultimatedecision‐makers.

Page 81: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Appendix A  A

Appendix A 

Page 82: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CENTRAL IOWA REGIONAL DRINKING WATER COMMISSION 

BLACK & VEATCH | Central Iowa Regional Drinking Water Commission  1

Central Iowa Regional Drinking Water Commission 

QUESTIONNAIRE FOR FEASIBILITY OF REGIONAL WATER PRODUCTION ENTITY 

1. Entity Characteristics 

a. NameofEntitytobeInterviewed

b. InterviewParticipantsw/Titles

c. CurrentandGeneralSystemConfiguration/Service

Sourceofsupply Treatment Transmission Distributionsystem CustomerCare

d. NumberofAccounts/Customers

Types–Residential/Commercial/Industrial

e. Whatcurrentsystemassetsdoyouownorhaveownershipin?

Whatvaluewouldyouplaceonyourassets? Howdidyoudeterminethatvalue?

f. AverageAnnualWaterUsage

g. PeakUsage

Howdoyoumeasure? Howdoyoumeetrequirements?

h. NumberofEmployees

Management Operations Administrative/Support

i. EstimatedAnnualBudget

Operating Capital

2. Entity Strategy 

a. Doyouhaveastrategicplan?

b. Doyoucoordinatewithlocalchamber/economicdevelopment/Council/Commission?

c. Whatisyouranticipatedsystemgrowth?,i.e.,annualpercentagegrowthrateofnewcustomers.

Page 83: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CENTRAL IOWA REGIONAL DRINKING WATER COMMISSION 

BLACK & VEATCH | Central Iowa Regional Drinking Water Commission  2

d. Inyouropinion,doesthecurrentregionalwatersituationhinderorpromoteeconomicdevelopmentintheregion?

e. Donewcustomerspayanup‐frontcapitalchargeforjoiningthesystem?

f. Doyouhaveadequatesupplyforanticipatedgrowth?

g. Howdoyouplanonaddressingincreasedwaterdemand?

h. Howwouldyouclassifythequantityandqualityofyourwater?

3. Regionalization 

a. Whatarethreeitemsthatyourentityseeswouldbebeneficialfromapotentialregionalproductionauthority?

b. Whatarethreeitemsthatyoufearfromapotentialregionalproductionauthority?

c. Whatwouldbethe“best”scenariofortheregion?

d. Doyouhaveconcernsabouttheimpactofaregionalwaterproductionentityonyourcurrentstaff?

4. Governance 

a. Whatisyourgeneralconceptofwhatthegovernancestructureofanewregionalwaterproductionentityshouldbe?

b. Howimportantisitforyourentitytohavearoleintheday‐to‐daygovernanceofanewregionalwaterproductionentity?

c. WithrespecttoanewBoardthatoverseesapotentialregionalproductionentity,whatisyouropinionoftheidealcomposition?

NumberofMembers GeographicalRepresentation ProfessionalBackground

d. Inyouropinion,whatshouldbethekeyfocusorresponsibilitiesoftheBoard?

e.g.,Planning,Finance,Budget,Operations,Policy

e. Inyouropinion,howfrequentlyshouldtheBoardofapotentialregionalproductionentitymeet?,e.g.,monthly,bimonthly,quarterly

5. Water Supply 

a. Inyouropinion,howstableistheregionalwatersupply?

b. Doesyourentityhaveasignificantsourceofsupplythatcouldcontributetothepotentialregionalproductionentity?

c. Doesyourentityforeseesignificantpopulationand/oreconomicgrowthinthecomingyears?

d. Whereisyourcurrentsupplyderivedfrom?

e. Doyouhaveacontractforwatersupply?ifso,whoisthecontractwith?

Page 84: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CENTRAL IOWA REGIONAL DRINKING WATER COMMISSION 

BLACK & VEATCH | Central Iowa Regional Drinking Water Commission  3

f. Whataretheprosandconsofthecurrentwatersupplysituation?

g. Howcanapotentialregionalproductionauthorityalleviateorimprovethecurrentsituation?

6. Financial and Rate Stability 

a. Whatistheratethatyourentitypayscurrentlyforwater?

b. Whoestablishestheratepaidbyyourentity?

c. Inyouropinion,doesthecurrentrateprovideyourcommunitywithgoodvalue?

d. Inyouropinion,howshouldnewproductionandwatersupplyprojectsbefunded?

e. Whatisyouropinionwithrespecttotransferringcommunitywaterproductionassetstoanewregionalwaterproductionentity?

7. Public / Stakeholder Input 

a. Howawareareyourcitizens/customersofcurrentwatersituation?

Dotheyknowwhatyoursourceofsupplyis?

Dotheyunderstandyourcoststructure?

b. Inyouropinion,whatwouldbethegeneralreactionofyourcommunity’scitizenstotheformationofanewregionalwaterproductionentity?,e.g.,positive,negative,indifferent?

c. Inyouropinion,whatarekey,publicengagementcomponentsthatwouldbenecessaryleadingtotheformationofaregionalproductionauthority?

d. Whatisthegeneralpoliticalprocessthatyourcommunitywouldberequiredtoundertaketoapprovetheformationofaregionalproductionentity?

e. Isyourcommunityconservation‐minded?

f. Doyoushareanyserviceswithyourneighboringcommunities?

Police/Fire/Parks/School/Library/PublicWorks

8. Open Discussion / Topics  

Page 85: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Appendix B  B

Appendix B 

Page 86: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

12 September 2014

CEN

TRAL IOWA REG

IONAL DRINKING W

ATER 

COMMISSION

SWOT ANALYSIS FO

R THE FEASIBILITY 

OF A REG

IONAL WATER PRODUCTION 

ENTITY

Page 87: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

AGEN

DA

Definition

Process

Expected Outcomes

2

Page 88: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

WHAT IS A 

SWOT ANALYSIS

3

Page 89: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

DEFINITION OF SWOT

•A SWOT an

alysis is a structured planning method used to 

evaluate the strengths, weaknesses, opportunities, and 

threats involved in

 a project or in a business venture

•The feasibility of creating a regional water production entity 

is the project or business venture

•To

days’ exercise will provide the structure to allow all 

participants to voice their thoughts, opinions and concerns

•Th

e analysis involves identifying the internal and 

external factors that are favorable and unfavorable to 

achieve the objective of the business venture or project

•The objective is to provide sustainable water supply to m

eet 

the strategic needs of the Greater Des M

oines area

DEFINE SW

OT

16 September 2014

4

Black & Veatch

Page 90: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

DEFINITION OF SWOT

SWOT MATR

IX

16 September 2014

5

Black & Veatch

Strengths

Weaknesses

Opportunities

Threats

Helpful

Harmful

Internal External

Page 91: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

DEFINITION OF SWOT

•Strengths

•Internalcharacteristics or issues that give the project 

or business venture advantage

over others

•Weaknesses

•Internalcharacteristics or issues that place the project 

or business venture at a disad

vantage

•Opportunities

•Externalcharacteristics or issues that give the project 

or business venture advantage

over others

•Th

reats

•Externalcharacteristics or issues that place the project 

or business venture at a disad

vantage

SWOT MATR

IX

16 September 2014

6

Black & Veatch

Page 92: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

DEFINITION OF SWOT

Keepanopenmindandpositiveattitude

•Destructive 

•Dominating

•Rushing

•Withdrawing

•Discounting

•Digressing

•Blocking

•Constructive 

•Cooperative

•Clarifying

•Inspiring

•Harmonizing

•Risk Taking

•Process Checking

BEH

AVIORS

Black & Veatch

7

16 September 2014

Page 93: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

WORKSH

OP

PROCESS

8

Page 94: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

WORKSHOP PROCESS

•Schedule

•Team

s

•Procedure 

ELEM

ENTS

16 September 2014

9

Black & Veatch

Page 95: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

WORKSHOP PROCESS

•9:00 –4:00

•2 Breaks

•Networking

•Phone calls / emails / 

texting / facebook

•Please return promptly

•Lunch hour

•3:00 –Summary

•Combine sm

all group 

analysis

•Prioritize

SCHED

ULE

Black & Veatch

10

16 September 2014

Agenda

9:00 am – 4:00 pm 

  9:00 –  Presentation of Feed

back from one‐on‐one interviews 

9:30 –  SW

OT Analysis Briefing 

Process 

Expected

 Outcomes 

10:00 –  Break 

10:30 –  SWOT – Analysis of continuation of curren

t situation 

 10:50

 –  

strengths 

 11:10

 –  

weaknesses 

 11:30

 –  

opportunities 

 11:50

 –  

threats 

12:00 – Lunch 

1:00 – SWOT – Analysis of Regional Production Entity 

 1:00 –  

strengths 

 1:20 –  

weaknesses 

 1:40 –  

opportunities 

 2:00 –  

threats 

2:30 – Break 

3:00 – summary – findings of the tw

o analyses are combined

 and outcomes are 

prioritized 

3:30 – 3:45 – W

orkshop concludes 

Page 96: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

WORKSHOP PROCESS

•SW

OT Analysis

•2 small‐group sessions

•Morning –Curren

t Situation

•Afternoon –Regional Entity

•Each session budgeted 1 hour 20 m

inutes for activity

•Aim

 for approximately 20 m

inutes per m

atrix 

componen

t

•5 –10 ideas, concepts, issues characteristics for each 

element of the SWOT matrix for each option

•Summary

•Full group activity ‐Participation and input from all 

members

•Combine and analyze the findings of the tw

o sessions

SCHED

ULE

16 September 2014

11

Black & Veatch

Page 97: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

WORKSHOP PROCESS

•4 Team

s Designated

•Diversified

 Groups

•Optimal group size is 8 –9 participan

ts

•Ground Rules

•Everyone turn off your cell phones

•We begin/end on tim

e

•Inform

ation shared

 in the room stays in

 the room

•Activities

•Determine critical issues

•Write responses for each of the 4 four boxes

•Be prepared

 to discuss with the larger group

TEAMS

16 September 2014

12

Black & Veatch

12

Page 98: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

WORKSHOP PROCESS

•Questions as thought starters: 

•Internal Stren

gths: W

hat skills, services and resources 

distinguish us?

•Internal W

eaknesses: W

hat do our customers think we 

could do better?  W

here could we be more efficient?

•External Opportunities: W

hat influen

ces, partnerships 

and resources could be tapped

 to help us move forw

ard?

•External Threats: W

hat forces, trends, technology 

changes, governmen

tal policy, and social patterns could 

limit our ability to m

eet our goals? 

PROCED

URES

16 September 2014

13

Black & Veatch

Page 99: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

EXPEC

TED 

OUTC

OMES

14

Page 100: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

EXPECTED OUTCOMES

•Expected Outcomes for Current Situation vs. 

Regional Production Entity

•Identify common themes which create a platform

 to 

move forw

ard

•Identify common themes which create significan

t barriers or incentives to m

ove forw

ard

COMBINED

 GROUP

16 September 2014

15

Black & Veatch

Page 101: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

EXPECTED OUTCOMES

•What critical action items need to be addressed in

 order to m

ove forw

ard?

•What hap

pens if we do nothing to address these 

issues?  Is this acceptable?

•If chan

ge can

 be achieved, w

hat are the positive 

outcomes that result?

GOING FORWARD

16 September 2014

16

Black & Veatch

Page 102: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

QUESTIONS?

Page 103: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

www.bv.com

Page 104: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

12 September 2014

CEN

TRAL IOWA REG

IONAL DRINKING W

ATER 

COMMISSION

INTERVIEW FEEDBACK

FEASIBILITY OF A REG

IONAL WATER 

PRODUCTION ENTITY

Page 105: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

•Weeks of July 14than

d July 21stone‐on‐one 

interviews were conducted with participating 

entities

•Interviews lasted 1 –2 hours

•Form

al questions

•Open

 tim

e for discussion

•Data Collected

•Hard data on community specifics

•Opinions and concerns about curren

t situation and 

impact of regional entity

•Purpose

•Provide inform

ation for the SW

OT Analysis

ACTIVITIES

12 September 2014

Page 106: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

•Altoona

•Ankeny

•Bondurant

•Clive

•Cumming

•Des Moines

•Johnston

•Norw

alk

•Pleasan

t Hill

•Polk City

•Polk County

•Urban

dale

•Warren County

•Wau

kee

•West Des 

Moines

•Windsor 

Heights

•Xenia

PARTICIPANTS

12 September 2014

Black & Veatch

3

Page 107: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

•Governan

ce

•Tran

sparency

•Cap

acity

GEN

ERAL TH

EMES

12 September 2014

4

Black & Veatch

Page 108: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

•Th

emes

•Proportionate rep

resentation

•Future “say in water issues”

•Issues to consider during SW

OT

•Is Des M

oines W

astewater governance m

odel 

appropriate?

•Size and rep

resentation

•Would level of representation change over time? If so, 

how?

GOVER

NANCE

12 September 2014

5

Black & Veatch

Page 109: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

TRANSPAREN

CY

12 September 2014

6

Black & Veatch

•Th

emes

•Cost of Service and Rate Study

•Developmen

t of volume charge

•Capacity Buy in

•Capacity Projects vs. Internal DMWW Projects

•Operations

•Issues to consider during SW

OT

•How can

 the curren

t cost of service and rate process 

be im

proved?

Page 110: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CAPACITY

12 September 2014

7

Black & Veatch

•Th

emes

•Adeq

uate capacity for future needs

•Sustainable Growth

•Quality

•Finished

 vs. Source 

•Issues to consider during SW

OT

•What is the best structure for addressing future 

quantity and quality needs?

Page 111: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

SWOT TEAMS

Team

ATeam

 BTeam

CTeam

 D

Facilitator: M

ike Borchers

Facilitator: Anna White

Facilitator: Heath

Picken

Facilitator: Peggy Howe

Jeff W

alters 

Tim Hoskins 

E.J. Giovannetti 

Dan

 Lovett

Karen

 Novak‐Sw

alwell 

Dale Acheson

DianaWilson

Tom Hadden

Mark Lindem

an 

SkipCronkling

Karen

 Oppelt

Shane Kinsey 

Graham

 Gillette 

Mike Schultze

John M

cCune 

Mark Wandro

Casey

Harvey

Pat Collison 

Rachel Swisher 

John Gibson

Merrill Heemstra 

Randy Beavers 

GaryBen

jamin

Ken

 Plager 

Betty Glover

Jason Van

Essen

Len M

urray 

Bill Stowe

Bart Weller 

Amy Kahler

Jaki Livingston

Madeline Sturm

Jim M

cKen

na 

Jean

 Lare 

Scott Cirksen

Page 112: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

www.bv.com

Page 113: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

12 September 2014

CEN

TRAL IOWA REG

IONAL DRINKING W

ATER 

COMMISSION

SWOT SU

MMARY

Page 114: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CURRENT VS. REGIONAL PRODUCTION ENTITY

Regional Production Entity

•More equal rep

resentation with 

regards to governance, planning, and 

rates

•More political influen

ce at regulatory 

level

•More political stability on governing 

board

•Potential long‐term

 cost efficiencies 

(direct and indirect)

•Regional planning

•Provide relative savings –slow the 

rate of increase

Current

•Staff Responsible and Knowledgeable

•Reliability of finished

 water

•Curren

tly finished

 water quality is 

good

•Red

undancy

•Multiple sources of supply

•Ability of customer communities to 

make indep

enden

t decisions

•Opportunity to choose level of service

•Knowledge of defined

 capacity lim

its 

for each community 

STREN

GTH

S

2

12 September 2014

Page 115: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CURRENT VS. REGIONAL PRODUCTION ENTITY

Regional Production Entity

•Size of governing body

•Source water quality and 

quantity are still issues

•Change in

 workforce im

pacting 

level of service

•Cost versus investmen

t –long 

term

 change over short term 

pain

•Buy‐in costs

•Conflict between growth and 

reinvestmen

t

•Right now we know who to 

blame

Current

•Autocratic governance of water 

supply and production

•No curren

t Board rep

resentation 

of customer communities

•No accountability to customer 

communities for how resources 

are spen

t or decisions made

•Source water quality

•Source water quantity

•Competing priorities for 

responding to regional growth

•Availability of purchased

 capacity to m

eet growth

WEA

KNESSES

3

12 September 2014

Page 116: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CURRENT VS. REGIONAL PRODUCTION ENTITY

Regional Production Entity

•Ability to influen

ce quality and 

quantity

•Long term

 bonding capability

•Predictability on reven

ue and 

costs

•Better control over resources

•Consisten

t message 

communicated

 with customers

•Input into regional economic 

developmen

t

Current

•Im

prove curren

t processes

•Individual communities continue 

to m

ake indep

enden

t decisions

•More inclusive governance and 

geographic diversity of Board

•Ability to im

prove watershed

 managem

ent

OPPORTU

NITIES

4

12 September 2014

Page 117: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CURRENT VS. REGIONAL PRODUCTION ENTITY

Regional Production Entity

•Initial cost of buy‐in

•Less than

 100% participation 

from communities

•Perception of reduction in

 work 

force

•Loss of local control

•Failure to m

eet customer 

expectations

•Nonpoint source pollution 

impact on source water

•Clim

ate issues

Current

•Competing interests for same 

source water

•Division/breakup of curren

t customer configuration

•Availability of capacity to m

eet 

customer community needs

•Nonpoint source pollution 

impact on source water

•Clim

ate issues

THREA

TS

5

12 September 2014

Page 118: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

www.bv.com

Page 119: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

CIRDWC | FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY 

 BLACK & VEATCH | Appendix C  C

Appendix C 

Page 120: FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL …€¦ · The Study and results outlined in this Report did not include a legal assessment of the feasibility of forming a regional

Strat

ford W

ater T

reatm

ent P

lant

43 M

iles t

o the

Nor

th

Urba

ndale

Roc

k Qua

rries

Raco

on R

iver In

take

and P

ump S

tation

Infiltr

ation

Gall

ery,

Rech

arge P

onds

,an

d Low

-Lift P

ond

Rech

arge P

ump S

tation

Urba

ndale

WTP

Site P

rope

rty

DM R

IVER

INTA

KE

GROU

ND ST

ORAG

EAN

D PO

LK C

OPU

MPIN

G ST

ATIO

N

TENN

YST

ANDP

IPEDM

RIVE

R PU

MPIN

G ST

ATIO

N HAZE

NTO

WER A

NDPU

MP ST

ATIO

NNO

LLEN

STAN

DPIPE

AND

PUMP

ING

STAT

ION

WEST

SIDE S

TORA

GE LP

MOON

TANK

, PUM

PST

ATIO

N, AN

D ASR

98TH

STRE

ETWE

ST D

ES M

OINE

SST

ORAG

E TAN

K

SHAR

EDEA

STSID

ETA

NK

SE 6

AVE

(5420

) SE P

OLK

PUMP

ING

STAT

ION

WILC

HINS

KIST

ANDP

IPE

WDMW

W A.

C. W

ardMu

nicipa

l WTP

,an

d Well

Field

(Sha

llow

Alluv

ialan

d Dee

p Jor

dan)

Polk

City

WTP a

ndSh

allow

Well

s

ASR

#1An

keny

ASR

#2An

keny

WTP #

1Al

toona

and

Deep

Well

WTP #

2Al

toona

and

Deep

Well

WTP #

3Al

toona

and

Deep

Well

DMWW

-Fle

ur W

TP

DMWW

- McM

ullen

WTP,

ASR,

Coll

ector

Wells

, and

Surfa

ceWa

ter Su

pply

(Maff

ittan

d Crys

tal La

kes)

DMWW

- Say

lorvil

leWT

P and

Colle

ctor W

ells

Xenia

Rur

al Wa

terDi

strict

Woo

dward

Water

Trea

tmen

t Pan

t

Sourc

es: E

sri, H

ERE,

DeLo

rme,

TomT

om, In

terma

p, inc

remen

t P C

orp., G

EBCO

, USG

S, FA

O, N

PS, N

RCAN

, Geo

Base

, IGN,

Kada

ster N

L,Or

dnan

ce Su

rvey,

Esri J

apan

, MET

I, Esri

Chin

a (Ho

ng Ko

ng), s

wissto

po, M

apmy

India,

© O

penS

treetM

ap co

ntribu

tors,

and t

he G

IS Us

erCo

mmun

ity

HRG PLOT: 2:09:40 PM 1/27/2015 BY: mliska FILE: \\HRGDMNAS\Data\40140043\GIS\MXD\CIRDWC_JointEntityCoreNetwork_Preliminary_11x17.mxd

NOVE

MBER

2014

PREL

IMIN

ARY

1 inc

h = 13

,000 f

eet

06,5

0013

,000

3,250

Feet

JOIN

T ENT

ITYCO

RE N

ETWO

RK

®

Lege

nd+

Eleva

ted Ta

nk#

ASR

[ ÚPu

mp St

ation

U TSta

ndPip

e3 Q

Treatm

ent P

lant

DMWW

Cor

e Wate

r Pipe

12"

14"

16"

18"

20"

24"

30"

36"

42"

48"

60"

Urba

ndale

Purch

ased

Prop

erty