feasibility report may 2014 - cavendish school, eastbourne · 1 executive summary / introduction 4...
TRANSCRIPT
CAVENDISH PRIMARY SCHOOLFEASIBILITY REPORTMAY 2014
ECE Architecture
Unit 1 WestCoate House3 Coate StreetLondon E2 9AG
Telephone London +44 207 729 5505 [email protected]
www.ecearchitecture.com
Revisions
Revision Notes Issue Date By Checked ByA Draft Issue 01.05.2014 SM
B Feasibility Issue 08.05.14 SM NE
CONTENT
1 Executive Summary / Introduction 04
2 Client Brief 07
3 Site 09
4 Site Analysis 17
5 Opportunities for colocation and joint use of space 22
6 Accommodation Schedule & Baseline Design 25
7 Layout Options 29
8 School Precedent 45
9 Sport England 48
10 Archeology & Planning Information 53
11 Utility Information 55
12 Programme 59
13 Risk Register 62
14 Structural Engineer’s Report 64
15 Quantity Surveyor’s Report 83
16 Next Steps 85
3ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
1 EXECUTIVE SUMMARY /INTRODUCTION
4 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
EXECUTIVE SUMMARY1. This current document is a feasibility report.
2. The client brief summarises the need for a new primary school in Eastbourne and the requirements of ESCC and the existing Cavendish secondary school for an ‘all-through school design solution’.
3. The existing Cavendish Secondary School has been documented through photographs, OS maps, and existing building plans.
4. The site topography, surfaces, vehicle and pedestrian movements, and site orientation have been analysed.
5. The secondary school plans have been analysed for opportunities for colocation and joint / shared use of spaces between the secondary and primary phases.
6. The EFA Baseline design and BB99 were reviewed as a starting point for the building proposals.
7. We have considered three alternative locations on the Cavendish site for the new primary school, each of which will have a different impact on cost, buildability, disruption during the building process, impact on the wider transport network, impact on local parking, impact on secondary school facilities, perceived impact on road safety, and impact on the provision of local recreational facilities.
8. As a result of a simple appraisal exercise, option 2 emerges as the Preferred Option. This option allows for a building in the south east of the site, access off Eldon Road and opportunities for connections to the existing secondary school.
9. A case study of St Matthew’s Academy for Business and Enterprise has been included as an example of a new all-through school.
10. The potential loss of recreational facilities has initiated consultation with Sport England which will continue through the later stages as this will have a central role to play in gaining planning approval for the proposed development. Mitigation measures for sport are likely to be needed.
11. The site is within a Archaeological Notification Area and there has been some initial conversation with County Council planners.
12. Utilities information has been collected for the site to show the gas, local water and power networks within the area.
13. The programme shows the building being complete by September 2016.
14. The risk register identifies the key issues and level of risk to the project.
15. HOP have explained the site geology and all existing services on the site in their feasibility report.
16. Sweet have carried out a high level cost plan, a summary of the three options are -
• Option #1 = £10-10.4m
• Option #2 = £10.3 - 10.7m
• Option #3 = £11.4 - 11.8m
These costs exceed current budget and that economies will need to be sought during the preconstruction period
17. There are a range of further investigations and further steps that need to be undertaken in the next stage.
5ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
BACKGROUNDThis Feasibility Report has been commissioned by East Sussex County Council following the births in Eastbourne have risen significantly, from 862 in 2001/2 to 1175 in 2010/11. Predicted shortfall shows the need for a 2FE at Year R plus a further 1FE at Year 3 in 2013/2014. The estimated Year R shortfall rise to around 5FE by 2016/17 and there are currently predicted to be shortfalls at Year R until the early part of the next decade which increases the pressure and need for a new primary school.
CLIENT BRIEFAs referred to in the Client Instruction and Project Brief document (CAD00004) East Sussex County Council (ESCC) have considered these issues and concluded that the existing Cavendish School at Eldon Road should be explored as site for a new two form entry (2FE) Primary School as Phase 1 of an ongoing programme to provide these much needed school places. (Please see section 2 of this report for more detailed information).
The target is to investigate the possibility of adding a 420 place, 2FE Primary School on the site with a date of opening of 1st September 2016, the start of the school year. There will be a need to find accommodation for the first year of pupils in September 2015 with the existing school site. The school would have to be ready for occupation prior to this in the summer holidays so that preparations can be made for the official opening.
The new school is to comply with current design standards and should therefore meet all the requirements set out in the Education Funding Agency (EFA) Baseline Areas which are based on area figures set out in Building Bulletin 99
(BB99) but with a reduction in GIA area of 10%.
PURPOSE OF REPORTThe methodology and objectives of this study are:
• A site survey and analysis of the proposed site and surroundings focusing on: access to the site for both vehicles and pedestrians; topography; orientation, neighbour proximity and site security
• A review of the EFA requirements in terms of what can be achieved spatially on the site, looking at building area, play areas, pitches, parking and cycle parking requirements.
• Development of 3 options for a new 2FE school which explores the different location of the building on the site
• Programme for the works to achieve proposed completion date
• Conclusions and recommendations moving forward to the design phase.
STANDARDS AND REGULATIONSThis document has been prepared using the following guidelines:
• BB99 (2nd Edition) Building Framework for Primary Schools
• BB94 Inclusive School Design
• BB91 Access for Disabled People to Schools BB85 School Grounds : A Guide to Good Practice
• Disability Discrimination Act 2005
• The Building Regulations
6 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
2 CLIENT BRIEF
7ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
The preparation of a feasibility study to investigate the viability of the Cavendish Secondary School site in Eastbourne to accommodate the following:
• provision of new 2 storey 2 form entry primary school
• sufficient car parking for staff and disabled staff / visitors
• location for a sixth form centre within school site (jointly run with Ratton School)
• adequate playground and playing field space
• regenerate use of the sports centre building
• a design solution for an all-through school (2-19 years) to make the best use of the current secondary school building and integrate any facilities which can be shared between secondary and primary school for efficient and effective use of space
Address the following criteria:
• Design to BB99 – 10% / EFA Baseline Guidance
• Negotiate planning restrictions around site
• Project delivered by September 2016 (for new build), temporary accommodation set up by September 2015.
• Project budget £7-8 million
Considerations for the Primary school building include:
• Good quality educational environment
• Nursery provision for 2-5 year olds (2x38 groups) = 76 in total
• safety of children’s pedestrian movements around site are guarded from vehicle movements
• good circulation and connectivity taking into account the wide age range of pupils
• good access for the primary phase that does not put pressure on current access to secondary school
• canteen facilities for the primary phase are adequate and consideration given to a shared solution
• adequate facilities for sports are provided for the primary phase and appropriate facilities for secondary and community use to gain Sport England approval
• access is maximised to the relevant areas particularly for the new primary provision
• Free flow space between nursery, reception and Year 1 classes (EYFS) as well as direct access from classroom to an outdoor space
• 1 WC and 1 WHB per 10, 2-5 years children
• Nappy change area with sluice and laundry facilities
• Shared kitchen for use by adults and children
8 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
3 SITE
9ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
SITE LOCATION
4
Aerial View - Cavendish
site Eastbourne centre
Aerial View - Cavendish site boundary
secondary school adjoining housing
adjoining housing adjoining housing
10 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
SITE PHOTOGRAPHS
Site Photos - Cavendish existing Secondary school entrance
Site Photos - Cavendish main Secondary school building car park access road
Site Photos - Cavendish neighbouring church site boundary Eldon Road vehicle site entrance
9
Site Photos - Cavendish view to South Downs site entrance off Cobbold Avenue Site Photos - Cavendish
sports Hall Cobbold Avenue neighbouring properties
Site Photos - Newhaven sports hall site boundary existing tennis courts
11ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
SITE PHOTOGRAPHS
Site Photos - Cavendish hockey ground / pitch netball courts main Secondary school
Site Photos - Cavendish sports hall in sports centre Site Photos - Cavendish
1st floor entrance to Sports centre via dance studio
Site Photos - Cavendish bridge to Sports centre via dance studio
hockey ground / pitch
Site Photos - Cavendish sports centre / dance studio
main Secondary school sports hall teaching block
stairs / multiple levels
19
Site Photos - Caavendish access road through site stepped access to site
12 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
EXISTING SITE PLAN
N
site boundary
Cobbold Avenue
Secondary school building
Eldon Road
neighbouring church
13ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
EXISTING BUILDING PLANS
14 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
Ground Floor Plan of Secondary School
Ground Floor Plan - Cavendish
main secondary school entrance
Sports hall
teaching block
main assembly hall
First Floor Plan of Secondary School
First Floor Plan - Cavendish dance studio
Art block
main assembly hall
canteen
1.24A
ART
1.24
ART1.26
1.C05
1.S06
SCIENCE1.16
OFFICE1.15
SCIENCE1.14
PREP ROOM1.12
D&T(FOOD TECHNOLOGY)1.01
D&T(EXTILES)1.03
CLASSROOM1.05
CLASSROOM1.06
1.S03
VOID
1.S05
STORE1.03A
STORE
1.26ASTORE
1.26BKILN
STORE1.13
1.14A
SCIENCE1.11
SCIENCE1.08
PREP ROOM1.09
CLASSROOM1.07
OFFICE1.04
STORE1.01A
SCIENCE1.21
SCIENCE1.20
SCIENCE1.19
PREP ROOM1.18
STORE1.17
1.S07
1.S04OFFICE
1.10
1.S01
GREENHOUSE1.20A
1.S02
1.25GROUP ROOM
1.27STORE
OFFICE1.23
STORE1.22
WC(M/F)1.02
1.C01
1.C02 1.C03
1.C04A
A
CARETAKERS OFFICEB.12
BOILERB.10
STOREB.05A
KITCHENB.06
DINING HALLB.05
CLASSROOMB.04
CLASSROOMB.02
B.05BSTORE
B.01
MEDIASTUDIO
B.03STORE
STOREB.06A
STOREB.06B
STOREB.06C
STOREB.13A
STOREB.13
WC(M/F)B.12A
STOREB.11
WCB.07
B.09
STOREB.08
STORE
B.C02
B.S01
B.C01
B.C03
A
B.C04
FIRST FLOOR
BASEMENT FLOOR
STORE
108m²
2m²8m²
11m²29m²
12m²
89m²
16m² 43m² 45m² 45m²
80m²
72m² 19m² 83m² 22m²
65m²
3m²
8m²
74m² 15m² 60m²
6m²
6m²
16m²
5m²
8m²
11m²
2m²
17m²
86m²
24m²
81m²
9m²
60m²
70m²
95m²
12m²
15m²16m²
2m² 8m²
8m² 13m²
69m²
10m²
12m² 13m²
17m²
34m²
1m²
19m²
21m² 11m²
11m² 15m²
3m²
13m² 9m²
84m²
4m²
1m²
2m²
203m²51m²50m²
7m²
6m²
7m²
55m²
43m²
EAST SUSSEX COUNTY COUNCIL
4064 - The Cavendish School
76 Franklynn Road
t : 01444 453364
Haywards HeathWest Sussex RH16 4DJ
Chartered SurveyorsAsset Management
e : [email protected] : www.hamsonbs.co.uk
Health and Safety ConsultantsPlanning Supervisors
f : 01444 456144
The Kiln
PartnershipHAMSON
1602.63-4064-B0&01/A3 (NTS) DO NOT SCALE FROM THIS DRAWING
August 2011
Basement Floor Plan of Secondary School
B
GENERAL TEACHING0.01 0.02 0.03 0.04
OFFICE0.05
GENERAL TEACHING0.07
STORE0.06
D&T(GRAPHICS)0.12
WC(M/F)0.10
STORE0.09
WC(G)0.08
0.11WC(B)
D&T(MULTI-MATERIALS)0.13
0.C01
PREP0.14
0.15GENERAL TEACHING
D&T(ELECTRONICS)0.17
0.15AOFFICE
PLANT0.16
GENERAL TEACHING0.01
GARAGE
0.69 0.70
GENERAL TEACHING0.71
STORE0.72
ICT/MEDIA ROOM0.73
0.C130.S08
MUSIC0.68
DRAMASTUDIO
0.62
MUSIC0.67
OFFICE0.68A
MUSIC POD0.68B
MUSIC POD0.68C
CONTROL ROOM0.68D
MUSIC POD0.67A
MUSIC POD0.67B
MUSIC POD0.67C
MUSIC POD0.67D
MUSIC PRACTICE0.66
MUSIC PRACTISE0.64
TUCK SHOP0.63
0.61CAREERS LIBRARY
0.54
WC(G)0.53
0.53A
WC(B)0.51
0.51A
OFFICE0.49
OFFICE
0.52
OFFICE0.52A
STAFFWC(M/F)
0.48
0.600.590.580.57SPECIAL NEEDS
0.560.55
0.40GENERAL TEACHING
0.39STAFFROOM
0.38STAFFROOM
0.29
WC(M)0.28
WC(F)0.27
ICT ROOM0.01
0.01A 0.02
0.01B
CHANGING ROOM0.03
PE STORE0.04
THEATRE0.05
STORE
STORE
STORE
0.05A
STORE
GENERAL TEACHING0.11 0.12
OFFICE0.13
STORE0.13A
OFFICE0.14
OFFICE0.22
OFFICE0.23
OFFICE0.21
0.C04
GENERAL OFFICE0.24
GENERAL TEACHING0.06 0.07 0.08
LEARNING RESOURCES CENTRE0.10
ELEC0.10A
OFFICE0.16 OFFICE
0.17
OFFICE0.19
OFFICE0.20
STORE0.33
0.S03
OFFICE0.34
GYMNASIUM0.30
0.30A
STORE
0.S05
SHOWER(M/F)0.42
0.09
STORE
0.26A
EXTENDEDRECEPTION
SICK BAY0.26
WATERMAIN0.25
0.C01
0.C02
0.S01
0.C03
0.C07
0.C08
STORE0.65
STORE0.71A
0.C14
0.S07
OFFICE0.60A
STORE0.50
0.S04
0.C10
0.35COMPUTER ROOM
0.36
OFFICE0.37
WC(B/G)0.44
WC(B)0.45
0.47OFFICE
0.46
OFFICE
0.41
OFFICE
CHANGING(G)0.31
HALL0.15
0.15A
SOUND ROOM
0.S02
0.S06
D A0.C05
0.C09
0.C11
CACCESS VIA BRIDGEFROM GROUND LEVEL
0.04A
WC(M/F)
MAIN ENTRANCE
0.C06
STORESTORE
STORE0.18
WC(D)
STORE0.32
STORE0.30B
0.C12
WC(G)0.43
SHOWER(D)0.42A
51m²
11m²
48m² 48m² 51m²
59m²
11m²
58m²
5m²
4m²
18m²
63m²
102m²
17m²
67m²
7m²
7m²
105m²
24m²
27m²
10m²
6m²
24m²
29m²
23m²
12m²
16m²8m²
7m²
17m² 12m²
1m²
6m²
1m²
19m²11m²
2m²
47m² 48m²
19m²
45m²44m²
91m²
63m²25m²24m²37m²
115m²
11m ²
44m²44m²44m²39m²
10m²
18m²
5m²11m²
7m²3m²
1m²
31m²
13m²14m²
15m²
20m²
16m²
6m²
21m²44m²45m²
64m²
10m²
14m²
2m²
41m ²
30m²
17m²
9m²
53m²
6m²
2m²
6m²
44m²
62m² 70m² 53m²
14m²
311m²
22m²20m²
2m²
4m²
12m²
13m²10m²
4m²
43m²
7m²
60m² 59m²
75m²
11m²
6m²
1m²
3m²
37m²15m²
169m²
11m²
4m²
5m²
5m²
7m²
3m²
3m²
3m²
3m²
59m²8m²
4m²
48m²
11m²
12m²
10m²
90m²
69m²
10m²1m²
35m² 14m²
39m² 39m²
47m²
89m²
141m²
3m²
236m²
1m²
74m²
GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING SPECIAL NEEDS GENERAL TEACHING GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING
GENERAL TEACHINGGENERAL TEACHING
COMPUTER ROOM
GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING GENERAL TEACHING GENERAL TEACHING
basic teachinghalls
learning resourcesstaff and admin.storage
non-net area
toilets (and personal care)
GROUND FLOOR PLAN
circulation
plant
1.24A
ART
1.24
ART1.26
1.C05
1.S06
1.161.151.14PREP ROOM
1.12
HOME ECONOMICS1.01
HOME ECONOMICS1.03
GENERAL TEACHING1.05 1.06
1.S03
UPPER ASSEMBLY AREA of 61ASSEMBLY HALL
1.S05
STORE1.03A
STORE
1.26ASTORE
1.26BSTORE
STORE1.13
1.14A
1.11
SCIENCELAB1.08
PREP ROOM1.091.07
OFFICE1.04
STORE1.01A
1.21
1.20
1.19
PREP ROOM1.18
STORE1.17
1.S07
1.S04OFFICE1.10
1.S01
GREENHOUSE1.20A
1.S02
1.25OFFICE
1.27STORE
OFFICE1.23
STORE1.22
WC(M/F)1.02
1.C01
1.C02 1.C03
1.C04A
A
SITE MANAGEMENTB.12
PLANTB.10
STOREB.05A
KITCHENB.06
CANTEENB.05B.04
GENERAL TEACHINGB.02
B.05BSTORE
B.01STORAGE
B.03STORE
STOREB.06A
STOREB.06B
STOREB.06C
STOREB.13A
STOREB.13
WC(M/F)B.12A
STOREB.11
WCB.07
B.09STORE
B.08
KITCHENSTAFF
B.C02
B.S01
B.C01
B.C03
A
B.C04
FIRST FLOOR
BASEMENT FLOOR
STORE
108m²
2m²8m²
11m²29m²
12m²
89m²
16m² 43m² 45m² 45m²
80m²
72m² 19m² 83m² 22m²
65m²
3m²
8m²
74m² 15m² 60m²
6m²
6m²
16m²
5m²
8m²
11m²
2m²
17m²
86m²
24m²
81m²
9m²
60m²
70m²
95m²
12m²
15m²16m²
2m² 8m²
8m² 13m²
69m²
10m²
12m² 13m²
17m²
34m²
1m²
19m²
21m² 11m²
11m² 15m²
3m²
13m² 9m²
84m²
4m²
1m²
2m²
203m²51m²50m²
7m²
6m²
7m²
55m²
43m²
GENERAL TEACHING GENERAL TEACHINGSCIENCE
LABSCIENCE
LABSCIENCE
LABPREP ROOM
SCIENCELAB
SCIENCELAB
SCIENCELAB
GENERAL TEACHING
basic teachinghalls
learning resourcesstaff and admin.storage
non-net area
toilets (and personal care)
circulationplant
Below and overleaf is an analysis of the existing school plan and the current use of the secondary school spaces.
GROUND AND BASEMENT FLOOR PLAN / MAIN BUILDING
B
GENERAL TEACHING0.01 0.02 0.03 0.04
OFFICE0.05
GENERAL TEACHING0.07
STORE0.06
D&T(GRAPHICS)0.12
WC(M/F)0.10
STORE0.09
WC(G)0.08
0.11WC(B)
D&T(MULTI-MATERIALS)0.13
0.C01
PREP0.14
0.15GENERAL TEACHING
D&T(ELECTRONICS)0.17
0.15AOFFICE
PLANT0.16
GENERAL TEACHING0.01
GARAGE
0.69 0.70
GENERAL TEACHING0.71
STORE0.72
ICT/MEDIA ROOM0.73
0.C130.S08
MUSIC0.68
DRAMASTUDIO
0.62
MUSIC0.67
OFFICE0.68A
MUSIC POD0.68B
MUSIC POD0.68C
CONTROL ROOM0.68D
MUSIC POD0.67A
MUSIC POD0.67B
MUSIC POD0.67C
MUSIC POD0.67D
MUSIC PRACTICE0.66
MUSIC PRACTISE0.64
TUCK SHOP0.63
0.61CAREERS LIBRARY
0.54
WC(G)0.53
0.53A
WC(B)0.51
0.51A
OFFICE0.49
OFFICE
0.52
OFFICE0.52A
STAFFWC(M/F)
0.48
0.600.590.580.57SPECIAL NEEDS
0.560.55
0.40GENERAL TEACHING
0.39STAFFROOM
0.38STAFFROOM
0.29
WC(M)0.28
WC(F)0.27
ICT ROOM0.01
0.01A 0.02
0.01B
CHANGING ROOM0.03
PE STORE0.04
THEATRE0.05
STORE
STORE
STORE
0.05A
STORE
GENERAL TEACHING0.11 0.12
OFFICE0.13
STORE0.13A
OFFICE0.14
OFFICE0.22
OFFICE0.23
OFFICE0.21
0.C04
GENERAL OFFICE0.24
GENERAL TEACHING0.06 0.07 0.08
LEARNING RESOURCES CENTRE0.10
ELEC0.10A
OFFICE0.16 OFFICE
0.17
OFFICE0.19
OFFICE0.20
STORE0.33
0.S03
OFFICE0.34
GYMNASIUM0.30
0.30A
STORE
0.S05
SHOWER(M/F)0.42
0.09
STORE
0.26A
EXTENDEDRECEPTION
SICK BAY0.26
WATERMAIN0.25
0.C01
0.C02
0.S01
0.C03
0.C07
0.C08
STORE0.65
STORE0.71A
0.C14
0.S07
OFFICE0.60A
STORE0.50
0.S04
0.C10
0.35COMPUTER ROOM
0.36
OFFICE0.37
WC(B/G)0.44
WC(B)0.45
0.47OFFICE
0.46
OFFICE
0.41
OFFICE
CHANGING(G)0.31
HALL0.15
0.15A
SOUND ROOM
0.S02
0.S06
D A0.C05
0.C09
0.C11
CACCESS VIA BRIDGEFROM GROUND LEVEL
0.04A
WC(M/F)
MAIN ENTRANCE
0.C06
STORESTORE
STORE0.18
WC(D)
STORE0.32
STORE0.30B
0.C12
WC(G)0.43
SHOWER(D)0.42A
51m²
11m²
48m² 48m² 51m²
59m²
11m²
58m²
5m²
4m²
18m²
63m²
102m²
17m²
67m²
7m²
7m²
105m²
24m²
27m²
10m²
6m²
24m²
29m²
23m²
12m²
16m²8m²
7m²
17m² 12m²
1m²
6m²
1m²
19m²11m²
2m²
47m² 48m²
19m²
45m²44m²
91m²
63m²25m²24m²37m²
115m²
11m ²
44m²44m²44m²39m²
10m²
18m²
5m²11m²
7m²3m²
1m²
31m²
13m²14m²
15m²
20m²
16m²
6m²
21m²44m²45m²
64m²
10m²
14m²
2m²
41m ²
30m²
17m²
9m²
53m²
6m²
2m²
6m²
44m²
62m² 70m² 53m²
14m²
311m²
22m²20m²
2m²
4m²
12m²
13m²10m²
4m²
43m²
7m²
60m² 59m²
75m²
11m²
6m²
1m²
3m²
37m²15m²
169m²
11m²
4m²
5m²
5m²
7m²
3m²
3m²
3m²
3m²
59m²8m²
4m²
48m²
11m²
12m²
10m²
90m²
69m²
10m²1m²
35m² 14m²
39m² 39m²
47m²
89m²
141m²
3m²
236m²
1m²
74m²
GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING SPECIAL NEEDS GENERAL TEACHING GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING
GENERAL TEACHINGGENERAL TEACHING
COMPUTER ROOM
GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING GENERAL TEACHING GENERAL TEACHING
basic teachinghalls
learning resourcesstaff and admin.storage
non-net area
toilets (and personal care)
GROUND FLOOR PLAN
circulation
plant
15ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
1.24A
ART
1.24
ART1.26
1.C05
1.S06
1.161.151.14PREP ROOM
1.12
HOME ECONOMICS1.01
HOME ECONOMICS1.03
GENERAL TEACHING1.05 1.06
1.S03
UPPER ASSEMBLY AREA of 61ASSEMBLY HALL
1.S05
STORE1.03A
STORE
1.26ASTORE
1.26BSTORE
STORE1.13
1.14A
1.11
SCIENCELAB1.08
PREP ROOM1.091.07
OFFICE1.04
STORE1.01A
1.21
1.20
1.19
PREP ROOM1.18
STORE1.17
1.S07
1.S04OFFICE1.10
1.S01
GREENHOUSE1.20A
1.S02
1.25OFFICE
1.27STORE
OFFICE1.23
STORE1.22
WC(M/F)1.02
1.C01
1.C02 1.C03
1.C04A
A
SITE MANAGEMENTB.12
PLANTB.10
STOREB.05A
KITCHENB.06
CANTEENB.05B.04
GENERAL TEACHINGB.02
B.05BSTORE
B.01STORAGE
B.03STORE
STOREB.06A
STOREB.06B
STOREB.06C
STOREB.13A
STOREB.13
WC(M/F)B.12A
STOREB.11
WCB.07
B.09STORE
B.08
KITCHENSTAFF
B.C02
B.S01
B.C01
B.C03
A
B.C04
FIRST FLOOR
BASEMENT FLOOR
STORE
108m²
2m²8m²
11m²29m²
12m²
89m²
16m² 43m² 45m² 45m²
80m²
72m² 19m² 83m² 22m²
65m²
3m²
8m²
74m² 15m² 60m²
6m²
6m²
16m²
5m²
8m²
11m²
2m²
17m²
86m²
24m²
81m²
9m²
60m²
70m²
95m²
12m²
15m²16m²
2m² 8m²
8m² 13m²
69m²
10m²
12m² 13m²
17m²
34m²
1m²
19m²
21m² 11m²
11m² 15m²
3m²
13m² 9m²
84m²
4m²
1m²
2m²
203m²51m²50m²
7m²
6m²
7m²
55m²
43m²
GENERAL TEACHING GENERAL TEACHINGSCIENCE
LABSCIENCE
LABSCIENCE
LABPREP ROOM
SCIENCELAB
SCIENCELAB
SCIENCELAB
GENERAL TEACHING
basic teachinghalls
learning resourcesstaff and admin.storage
non-net area
toilets (and personal care)
circulationplant
FIRST FLOOR PLAN / MAIN BUILDING
SPORTS HALL0.01
CHANGING(M)0.12
CHANGING(F)0.13
0.C04
0.C03
0.S01
0.C01
0.C02
OFFICE0.07
OFFICE0.02
STAFF KITCHEN0.03
BOILER ROOM0.06
ELEC0.04
STORE0.05
WC(D)0.08
WC(F)0.09
WC(F)0.10
WC(M)0.11
STORE0.01A
STORE0.01B
CACCESS VIA BRIDGEFROM GROUND LEVEL
19m²
OFFICE0.07A
10m²
3m²
2m²
9m²
10m²
6m²
39m²
5m²
3m² 3m² 6m²
34m² 8m²
2m²
26m²
25m²
2m²
32m²
535m²
3m²
C
DANCE STUDIO1.01
GYMNASIUM1.02
STORE1.04
WC(D)1.03
STORE1.02A
1.S01
129m²
1m²
24m²
4m²
1m²
70m²
basic teachinghalls
learning resourcesstaff and admin.storage
non-net area
toilets (and personal care)circulation
plant
SPORTS HALL0.01
CHANGING(M)0.12
CHANGING(F)0.13
0.C04
0.C03
0.S01
0.C01
0.C02
OFFICE0.07
OFFICE0.02
STAFF KITCHEN0.03
BOILER ROOM0.06
ELEC0.04
STORE0.05
WC(D)0.08
WC(F)0.09
WC(F)0.10
WC(M)0.11
STORE0.01A
STORE0.01B
CACCESS VIA BRIDGEFROM GROUND LEVEL
19m²
OFFICE0.07A
10m²
3m²
2m²
9m²
10m²
6m²
39m²
5m²
3m² 3m² 6m²
34m² 8m²
2m²
26m²
25m²
2m²
32m²
535m²
3m²
C
DANCE STUDIO1.01
GYMNASIUM1.02
STORE1.04
WC(D)1.03
STORE1.02A
1.S01
129m²
1m²
24m²
4m²
1m²
70m²
basic teachinghalls
learning resourcesstaff and admin.storage
non-net area
toilets (and personal care)circulation
plant
SPORTS HALL GROUND FLOOR PLAN
DANCE STUDIO FIRST FLOOR PLAN
B
GENERAL TEACHING0.01 0.02 0.03 0.04
OFFICE0.05
GENERAL TEACHING0.07
STORE0.06
D&T(GRAPHICS)0.12
WC(M/F)0.10
STORE0.09
WC(G)0.08
0.11WC(B)
D&T(MULTI-MATERIALS)0.13
0.C01
PREP0.14
0.15GENERAL TEACHING
D&T(ELECTRONICS)0.17
0.15AOFFICE
PLANT0.16
GENERAL TEACHING0.01
GARAGE
0.69 0.70
GENERAL TEACHING0.71
STORE0.72
ICT/MEDIA ROOM0.73
0.C130.S08
MUSIC0.68
DRAMASTUDIO
0.62
MUSIC0.67
OFFICE0.68A
MUSIC POD0.68B
MUSIC POD0.68C
CONTROL ROOM0.68D
MUSIC POD0.67A
MUSIC POD0.67B
MUSIC POD0.67C
MUSIC POD0.67D
MUSIC PRACTICE0.66
MUSIC PRACTISE0.64
TUCK SHOP0.63
0.61CAREERS LIBRARY
0.54
WC(G)0.53
0.53A
WC(B)0.51
0.51A
OFFICE0.49
OFFICE
0.52
OFFICE0.52A
STAFFWC(M/F)
0.48
0.600.590.580.57SPECIAL NEEDS
0.560.55
0.40GENERAL TEACHING
0.39STAFFROOM
0.38STAFFROOM
0.29
WC(M)0.28
WC(F)0.27
ICT ROOM0.01
0.01A 0.02
0.01B
CHANGING ROOM0.03
PE STORE0.04
THEATRE0.05
STORE
STORE
STORE
0.05A
STORE
GENERAL TEACHING0.11 0.12
OFFICE0.13
STORE0.13A
OFFICE0.14
OFFICE0.22
OFFICE0.23
OFFICE0.21
0.C04
GENERAL OFFICE0.24
GENERAL TEACHING0.06 0.07 0.08
LEARNING RESOURCES CENTRE0.10
ELEC0.10A
OFFICE0.16 OFFICE
0.17
OFFICE0.19
OFFICE0.20
STORE0.33
0.S03
OFFICE0.34
GYMNASIUM0.30
0.30A
STORE
0.S05
SHOWER(M/F)0.42
0.09
STORE
0.26A
EXTENDEDRECEPTION
SICK BAY0.26
WATERMAIN0.25
0.C01
0.C02
0.S01
0.C03
0.C07
0.C08
STORE0.65
STORE0.71A
0.C14
0.S07
OFFICE0.60A
STORE0.50
0.S04
0.C10
0.35COMPUTER ROOM
0.36
OFFICE0.37
WC(B/G)0.44
WC(B)0.45
0.47OFFICE
0.46
OFFICE
0.41
OFFICE
CHANGING(G)0.31
HALL0.15
0.15A
SOUND ROOM
0.S02
0.S06
D A0.C05
0.C09
0.C11
CACCESS VIA BRIDGEFROM GROUND LEVEL
0.04A
WC(M/F)
MAIN ENTRANCE
0.C06
STORESTORE
STORE0.18
WC(D)
STORE0.32
STORE0.30B
0.C12
WC(G)0.43
SHOWER(D)0.42A
51m²
11m²
48m² 48m² 51m²
59m²
11m²
58m²
5m²
4m²
18m²
63m²
102m²
17m²
67m²
7m²
7m²
105m²
24m²
27m²
10m²
6m²
24m²
29m²
23m²
12m²
16m²8m²
7m²
17m² 12m²
1m²
6m²
1m²
19m²11m²
2m²
47m² 48m²
19m²
45m²44m²
91m²
63m²25m²24m²37m²
115m²
11m ²
44m²44m²44m²39m²
10m²
18m²
5m²11m²
7m²3m²
1m²
31m²
13m²14m²
15m²
20m²
16m²
6m²
21m²44m²45m²
64m²
10m²
14m²
2m²
41m ²
30m²
17m²
9m²
53m²
6m²
2m²
6m²
44m²
62m² 70m² 53m²
14m²
311m²
22m²20m²
2m²
4m²
12m²
13m²10m²
4m²
43m²
7m²
60m² 59m²
75m²
11m²
6m²
1m²
3m²
37m²15m²
169m²
11m²
4m²
5m²
5m²
7m²
3m²
3m²
3m²
3m²
59m²8m²
4m²
48m²
11m²
12m²
10m²
90m²
69m²
10m²1m²
35m² 14m²
39m² 39m²
47m²
89m²
141m²
3m²
236m²
1m²
74m²
GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING SPECIAL NEEDS GENERAL TEACHING GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING
GENERAL TEACHINGGENERAL TEACHING
COMPUTER ROOM
GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING GENERAL TEACHING GENERAL TEACHING
basic teachinghalls
learning resourcesstaff and admin.storage
non-net area
toilets (and personal care)
GROUND FLOOR PLAN
circulation
plant
16 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
4 SITE ANALYSIS
17ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
1
2
3
Secondary school building
highest level
lowest level
THREE DISTINCT LEVELS OF THE SITE
42.1m 41.9m
47.0m
55.9m
There is approximately a 14m fall from Cobbold Avenue to Eldon Road
18 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
SITE SURFACES AND PLAYING SURFACES
main secondary school building surrounding dwellings
N
19ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
VEHICLE AND PEDESTRIAN ROUTES
Eldon Road
surrounding dwellings
overflow carpark (owned by church) used when required for
special events by the school
limited parking spaces on site
problematic single lane entrance and
exit to site
Secondary entry & exit for service only
busy, congested road is only access point to secondary school
site boundary restricted gate to site, not in use
Secondary school main building
multiple steps across site - no level access to Sports Centre
and Humanities Teaching Block. No step free access to all areas
of site
Cobbold Avenue
multiple pedestrian access points along Eldon Road
N
20 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
SITE ORIENTATION AND SUN PATH DIAGRAM
Secondary school main building site boundary surrounding dwellings
N
AM
PM
21ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
5 OPPORTUNITIES FOR COLOCATION & JOINT USE OF SPACE
22 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
1.24A
ART
1.24
ART1.26
1.C05
1.S06
1.161.151.14PREP ROOM
1.12
HOME ECONOMICS1.01
HOME ECONOMICS1.03
GENERAL TEACHING1.05 1.06
1.S03
UPPER ASSEMBLY AREA of 61ASSEMBLY HALL
1.S05
STORE1.03A
STORE
1.26ASTORE
1.26BSTORE
STORE1.13
1.14A
1.11
SCIENCELAB1.08
PREP ROOM1.091.07
OFFICE1.04
STORE1.01A
1.21
1.20
1.19
PREP ROOM1.18
STORE1.17
1.S07
1.S04OFFICE1.10
1.S01
GREENHOUSE1.20A
1.S02
1.25OFFICE
1.27STORE
OFFICE1.23
STORE1.22
WC(M/F)1.02
1.C01
1.C02 1.C03
1.C04A
A
SITE MANAGEMENTB.12
PLANTB.10
STOREB.05A
KITCHENB.06
CANTEENB.05B.04
GENERAL TEACHINGB.02
B.05BSTORE
B.01STORAGE
B.03STORE
STOREB.06A
STOREB.06B
STOREB.06C
STOREB.13A
STOREB.13
WC(M/F)B.12A
STOREB.11
WCB.07
B.09STORE
B.08
KITCHENSTAFF
B.C02
B.S01
B.C01
B.C03
A
B.C04
FIRST FLOOR
BASEMENT FLOOR
STORE
108m²
2m²8m²
11m²29m²
12m²
89m²
16m² 43m² 45m² 45m²
80m²
72m² 19m² 83m² 22m²
65m²
3m²
8m²
74m² 15m² 60m²
6m²
6m²
16m²
5m²
8m²
11m²
2m²
17m²
86m²
24m²
81m²
9m²
60m²
70m²
95m²
12m²
15m²16m²
2m² 8m²
8m² 13m²
69m²
10m²
12m² 13m²
17m²
34m²
1m²
19m²
21m² 11m²
11m² 15m²
3m²
13m² 9m²
84m²
4m²
1m²
2m²
203m²51m²50m²
7m²
6m²
7m²
55m²
43m²
GENERAL TEACHING GENERAL TEACHINGSCIENCE
LABSCIENCE
LABSCIENCE
LABPREP ROOM
SCIENCELAB
SCIENCELAB
SCIENCELAB
GENERAL TEACHING
shared facilitiescirculationentrances
B
GENERAL TEACHING0.01 0.02 0.03 0.04
OFFICE0.05
GENERAL TEACHING0.07
STORE0.06
D&T(GRAPHICS)0.12
WC(M/F)0.10
STORE0.09
WC(G)0.08
0.11WC(B)
D&T(MULTI-MATERIALS)0.13
0.C01
PREP0.14
0.15GENERAL TEACHING
D&T(ELECTRONICS)0.17
0.15AOFFICE
PLANT0.16
GENERAL TEACHING0.01
GARAGE
0.69 0.70
GENERAL TEACHING0.71
STORE0.72
ICT/MEDIA ROOM0.73
0.C130.S08
MUSIC0.68
DRAMASTUDIO
0.62
MUSIC0.67
OFFICE0.68A
MUSIC POD0.68B
MUSIC POD0.68C
CONTROL ROOM0.68D
MUSIC POD0.67A
MUSIC POD0.67B
MUSIC POD0.67C
MUSIC POD0.67D
MUSIC PRACTICE0.66
MUSIC PRACTISE0.64
TUCK SHOP0.63
0.61CAREERS LIBRARY
0.54
WC(G)0.53
0.53A
WC(B)0.51
0.51A
OFFICE0.49
OFFICE
0.52
OFFICE0.52A
STAFFWC(M/F)
0.48
0.600.590.580.57SPECIAL NEEDS
0.560.55
0.40GENERAL TEACHING
0.39STAFFROOM
0.38STAFFROOM
0.29
WC(M)0.28
WC(F)0.27
ICT ROOM0.01
0.01A 0.02
0.01B
CHANGING ROOM0.03
PE STORE0.04
THEATRE0.05
STORE
STORE
STORE
0.05A
STORE
GENERAL TEACHING0.11 0.12
OFFICE0.13
STORE0.13A
OFFICE0.14
OFFICE0.22
OFFICE0.23
OFFICE0.21
0.C04
GENERAL OFFICE0.24
GENERAL TEACHING0.06 0.07 0.08
LEARNING RESOURCES CENTRE0.10
ELEC0.10A
OFFICE0.16 OFFICE
0.17
OFFICE0.19
OFFICE0.20
STORE0.33
0.S03
OFFICE0.34
GYMNASIUM0.30
0.30A
STORE
0.S05
SHOWER(M/F)0.42
0.09
STORE
0.26A
EXTENDEDRECEPTION
SICK BAY0.26
WATERMAIN0.25
0.C01
0.C02
0.S01
0.C03
0.C07
0.C08
STORE0.65
STORE0.71A
0.C14
0.S07
OFFICE0.60A
STORE0.50
0.S04
0.C10
0.35COMPUTER ROOM
0.36
OFFICE0.37
WC(B/G)0.44
WC(B)0.45
0.47OFFICE
0.46
OFFICE
0.41
OFFICE
CHANGING(G)0.31
HALL0.15
0.15A
SOUND ROOM
0.S02
0.S06
D A0.C05
0.C09
0.C11
CACCESS VIA BRIDGEFROM GROUND LEVEL
0.04A
WC(M/F)
MAIN ENTRANCE
0.C06
STORESTORE
STORE0.18
WC(D)
STORE0.32
STORE0.30B
0.C12
WC(G)0.43
SHOWER(D)0.42A
51m²
11m²
48m² 48m² 51m²
59m²
11m²
58m²
5m²
4m²
18m²
63m²
102m²
17m²
67m²
7m²
7m²
105m²
24m²
27m²
10m²
6m²
24m²
29m²
23m²
12m²
16m²8m²
7m²
17m² 12m²
1m²
6m²
1m²
19m²11m²
2m²
47m² 48m²
19m²
45m²44m²
91m²
63m²25m²24m²37m²
115m²
11m ²
44m²44m²44m²39m²
10m²
18m²
5m²11m²
7m²3m²
1m²
31m²
13m²14m²
15m²
20m²
16m²
6m²
21m²44m²45m²
64m²
10m²
14m²
2m²
41m ²
30m²
17m²
9m²
53m²
6m²
2m²
6m²
44m²
62m² 70m² 53m²
14m²
311m²
22m²20m²
2m²
4m²
12m²
13m²10m²
4m²
43m²
7m²
60m² 59m²
75m²
11m²
6m²
1m²
3m²
37m²15m²
169m²
11m²
4m²
5m²
5m²
7m²
3m²
3m²
3m²
3m²
59m²8m²
4m²
48m²
11m²
12m²
10m²
90m²
69m²
10m²1m²
35m² 14m²
39m² 39m²
47m²
89m²
141m²
3m²
236m²
1m²
74m²
GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING SPECIAL NEEDS GENERAL TEACHING GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING
GENERAL TEACHINGGENERAL TEACHING
COMPUTER ROOM
GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING GENERAL TEACHING GENERAL TEACHING
shared facilitiescirculation
GROUND FLOOR PLAN
shared facilities include:
dining arealearning resources centreassembly hallgymnasiumtheatredrama studiostaff roomstaff management officeplant spacekitchen
entrancesAn analysis of the spaces that can be shared between the primary and secondary
phases of the ‘All through School’ have been highlighted below and on the next
page.
This is detailed alongside Option 2 later in the report.
Shared facilities might include -
• dinning area / canteen
• gymnasium
• Learning Resource Centre
• Assembly hall
• theatre
• studio
• staff management office
• plant space
• kitchen
GROUND AND BASEMENT FLOOR PLAN
B
GENERAL TEACHING0.01 0.02 0.03 0.04
OFFICE0.05
GENERAL TEACHING0.07
STORE0.06
D&T(GRAPHICS)0.12
WC(M/F)0.10
STORE0.09
WC(G)0.08
0.11WC(B)
D&T(MULTI-MATERIALS)0.13
0.C01
PREP0.14
0.15GENERAL TEACHING
D&T(ELECTRONICS)0.17
0.15AOFFICE
PLANT0.16
GENERAL TEACHING0.01
GARAGE
0.69 0.70
GENERAL TEACHING0.71
STORE0.72
ICT/MEDIA ROOM0.73
0.C130.S08
MUSIC0.68
DRAMASTUDIO
0.62
MUSIC0.67
OFFICE0.68A
MUSIC POD0.68B
MUSIC POD0.68C
CONTROL ROOM0.68D
MUSIC POD0.67A
MUSIC POD0.67B
MUSIC POD0.67C
MUSIC POD0.67D
MUSIC PRACTICE0.66
MUSIC PRACTISE0.64
TUCK SHOP0.63
0.61CAREERS LIBRARY
0.54
WC(G)0.53
0.53A
WC(B)0.51
0.51A
OFFICE0.49
OFFICE
0.52
OFFICE0.52A
STAFFWC(M/F)
0.48
0.600.590.580.57SPECIAL NEEDS
0.560.55
0.40GENERAL TEACHING
0.39STAFFROOM
0.38STAFFROOM
0.29
WC(M)0.28
WC(F)0.27
ICT ROOM0.01
0.01A 0.02
0.01B
CHANGING ROOM0.03
PE STORE0.04
THEATRE0.05
STORE
STORE
STORE
0.05A
STORE
GENERAL TEACHING0.11 0.12
OFFICE0.13
STORE0.13A
OFFICE0.14
OFFICE0.22
OFFICE0.23
OFFICE0.21
0.C04
GENERAL OFFICE0.24
GENERAL TEACHING0.06 0.07 0.08
LEARNING RESOURCES CENTRE0.10
ELEC0.10A
OFFICE0.16 OFFICE
0.17
OFFICE0.19
OFFICE0.20
STORE0.33
0.S03
OFFICE0.34
GYMNASIUM0.30
0.30A
STORE
0.S05
SHOWER(M/F)0.42
0.09
STORE
0.26A
EXTENDEDRECEPTION
SICK BAY0.26
WATERMAIN0.25
0.C01
0.C02
0.S01
0.C03
0.C07
0.C08
STORE0.65
STORE0.71A
0.C14
0.S07
OFFICE0.60A
STORE0.50
0.S04
0.C10
0.35COMPUTER ROOM
0.36
OFFICE0.37
WC(B/G)0.44
WC(B)0.45
0.47OFFICE
0.46
OFFICE
0.41
OFFICE
CHANGING(G)0.31
HALL0.15
0.15A
SOUND ROOM
0.S02
0.S06
D A0.C05
0.C09
0.C11
CACCESS VIA BRIDGEFROM GROUND LEVEL
0.04A
WC(M/F)
MAIN ENTRANCE
0.C06
STORESTORE
STORE0.18
WC(D)
STORE0.32
STORE0.30B
0.C12
WC(G)0.43
SHOWER(D)0.42A
51m²
11m²
48m² 48m² 51m²
59m²
11m²
58m²
5m²
4m²
18m²
63m²
102m²
17m²
67m²
7m²
7m²
105m²
24m²
27m²
10m²
6m²
24m²
29m²
23m²
12m²
16m²8m²
7m²
17m² 12m²
1m²
6m²
1m²
19m²11m²
2m²
47m² 48m²
19m²
45m²44m²
91m²
63m²25m²24m²37m²
115m²
11m ²
44m²44m²44m²39m²
10m²
18m²
5m²11m²
7m²3m²
1m²
31m²
13m²14m²
15m²
20m²
16m²
6m²
21m²44m²45m²
64m²
10m²
14m²
2m²
41m ²
30m²
17m²
9m²
53m²
6m²
2m²
6m²
44m²
62m² 70m² 53m²
14m²
311m²
22m²20m²
2m²
4m²
12m²
13m²10m²
4m²
43m²
7m²
60m² 59m²
75m²
11m²
6m²
1m²
3m²
37m²15m²
169m²
11m²
4m²
5m²
5m²
7m²
3m²
3m²
3m²
3m²
59m²8m²
4m²
48m²
11m²
12m²
10m²
90m²
69m²
10m²1m²
35m² 14m²
39m² 39m²
47m²
89m²
141m²
3m²
236m²
1m²
74m²
GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING SPECIAL NEEDS GENERAL TEACHING GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING
GENERAL TEACHINGGENERAL TEACHING
COMPUTER ROOM
GENERAL TEACHING GENERAL TEACHING
GENERAL TEACHING GENERAL TEACHING GENERAL TEACHING
shared facilitiescirculation
GROUND FLOOR PLAN
shared facilities include:
dining arealearning resources centreassembly hallgymnasiumtheatredrama studiostaff roomstaff management officeplant spacekitchen
entrances
staff room staff room
Assembly hall gymnasium
theatre
LRC
drama studio
storesdining area / canteen site
management office
plant
kitchen
23ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
1.24A
ART
1.24
ART1.26
1.C05
1.S06
1.161.151.14PREP ROOM
1.12
HOME ECONOMICS1.01
HOME ECONOMICS1.03
GENERAL TEACHING1.05 1.06
1.S03
UPPER ASSEMBLY AREA of 61ASSEMBLY HALL
1.S05
STORE1.03A
STORE
1.26ASTORE
1.26BSTORE
STORE1.13
1.14A
1.11
SCIENCELAB1.08
PREP ROOM1.091.07
OFFICE1.04
STORE1.01A
1.21
1.20
1.19
PREP ROOM1.18
STORE1.17
1.S07
1.S04OFFICE1.10
1.S01
GREENHOUSE1.20A
1.S02
1.25OFFICE
1.27STORE
OFFICE1.23
STORE1.22
WC(M/F)1.02
1.C01
1.C02 1.C03
1.C04A
A
SITE MANAGEMENTB.12
PLANTB.10
STOREB.05A
KITCHENB.06
CANTEENB.05B.04
GENERAL TEACHINGB.02
B.05BSTORE
B.01STORAGE
B.03STORE
STOREB.06A
STOREB.06B
STOREB.06C
STOREB.13A
STOREB.13
WC(M/F)B.12A
STOREB.11
WCB.07
B.09STORE
B.08
KITCHENSTAFF
B.C02
B.S01
B.C01
B.C03
A
B.C04
FIRST FLOOR
BASEMENT FLOOR
STORE
108m²
2m²8m²
11m²29m²
12m²
89m²
16m² 43m² 45m² 45m²
80m²
72m² 19m² 83m² 22m²
65m²
3m²
8m²
74m² 15m² 60m²
6m²
6m²
16m²
5m²
8m²
11m²
2m²
17m²
86m²
24m²
81m²
9m²
60m²
70m²
95m²
12m²
15m²16m²
2m² 8m²
8m² 13m²
69m²
10m²
12m² 13m²
17m²
34m²
1m²
19m²
21m² 11m²
11m² 15m²
3m²
13m² 9m²
84m²
4m²
1m²
2m²
203m²51m²50m²
7m²
6m²
7m²
55m²
43m²
GENERAL TEACHING GENERAL TEACHINGSCIENCE
LABSCIENCE
LABSCIENCE
LABPREP ROOM
SCIENCELAB
SCIENCELAB
SCIENCELAB
GENERAL TEACHING
shared facilitiescirculationentrances
SPORTS HALL0.01
CHANGING(M)0.12
CHANGING(F)0.13
0.C04
0.C03
0.S01
0.C01
0.C02
OFFICE0.07
OFFICE0.02
STAFF KITCHEN0.03
BOILER ROOM0.06
ELEC0.04
STORE0.05
WC(D)0.08
WC(F)0.09
WC(F)0.10
WC(M)0.11
STORE0.01A
STORE0.01B
CACCESS VIA BRIDGEFROM GROUND LEVEL
19m²
OFFICE0.07A
10m²
3m²
2m²
9m²
10m²
6m²
39m²
5m²
3m² 3m² 6m²
34m² 8m²
2m²
26m²
25m²
2m²
32m²
535m²
3m²
C
DANCE STUDIO1.01
GYMNASIUM1.02
STORE1.04
WC(D)1.03
STORE1.02A
1.S01
129m²
1m²
24m²
4m²
1m²
70m²
shared facilitiescirculation
entrances
FIRST FLOOR PLAN
SPORTS HALL0.01
CHANGING(M)0.12
CHANGING(F)0.13
0.C04
0.C03
0.S01
0.C01
0.C02
OFFICE0.07
OFFICE0.02
STAFF KITCHEN0.03
BOILER ROOM0.06
ELEC0.04
STORE0.05
WC(D)0.08
WC(F)0.09
WC(F)0.10
WC(M)0.11
STORE0.01A
STORE0.01B
CACCESS VIA BRIDGEFROM GROUND LEVEL
19m²
OFFICE0.07A
10m²
3m²
2m²
9m²
10m²
6m²
39m²
5m²
3m² 3m² 6m²
34m² 8m²
2m²
26m²
25m²
2m²
32m²
535m²
3m²
C
DANCE STUDIO1.01
GYMNASIUM1.02
STORE1.04
WC(D)1.03
STORE1.02A
1.S01
129m²
1m²
24m²
4m²
1m²
70m²
shared facilitiescirculation
entrances
SPORTS HALL GROUND FLOOR PLAN
DANCE STUDIO FIRST FLOOR PLAN
dance studio
assembly hall
24 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
6 ACCOMMODATION SCHEDULE & BASELINE DESIGN
25ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
TARGET AREA SCHEDULE FOR NEW PRIMARY SCHOOL
26 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
Cav
endi
sh P
rimar
y Sc
hool
Sche
dule
of A
ccom
mod
atio
n60
65/K
01V
ersi
on:
1 - 2
8/02
/14
pupi
l pla
ces
420
pupi
lsnu
mbe
r of c
lass
es
14cl
asse
sFo
rms
of E
ntry
(FE)
and
type
2F
Epr
imar
y
Gro
up s
ize
BB
.99
area
m2
BB
.99
- 10%
are
a m
2N
o. o
f roo
ms
PRO
POSE
DEF
A B
asel
ine
basi
c te
achi
ngZO
NE
Pre
cept
ion
clas
s30
6356
211
212
4K
S1
clas
sbas
e (In
fant
s)30
6356
422
424
8K
S2
clas
sbas
e (J
unio
rs)
3063
568
448
440
Sha
red
teac
hing
are
a (fo
od/s
cien
ce/D
&T/
ICT)
/ S
peci
alis
t Pra
ctic
al15
38.5
352
7069
Sum
mar
y88
279
485
488
1H
alls
ZON
E Q
mai
n ha
ll (u
sed
for d
inin
g an
d as
sem
bly)
(Spo
rt E
ngla
nd -
18m
x10x
6.1m
)42
022
620
3.4
120
3.4
180
stud
io55
Sum
mar
y22
620
3.4
203.
423
5Le
arni
ng R
esou
rces
ZON
E T
Libr
ary
420
3126
126
24sm
all g
roup
room
(SE
Nco
) / S
EN
reso
urce
68.
67.
52
1513
smal
l gro
up ro
om (2
No.
)6
8.6
7.5
430
27LR
C li
brar
y10
Sum
mar
y78
70.2
7174
TOTA
L TE
AC
HIN
G A
REA
11
8610
6711
28.4
1190
staf
f and
adm
in.
ZON
E S
head
’s o
ffice
/mee
ting
room
20
181
1816
staf
f roo
m40
361
3648
staf
f wor
k ro
om20
181
18ge
nera
l offi
ce
2522
.51
22.5
13si
ck b
ay (a
djac
ent)
54.
51
4.5
4en
tranc
e / c
ircul
atio
n / r
ecep
tion
/ wai
ting
1210
.81
10.8
inte
rvie
w /
soci
al s
ervi
ces
(adj
acen
t)8
7.2
17.
27
copi
er/re
prog
raph
ics
65.
41
5.4
8S
EN
ther
apy/
Med
ical
Insp
ectio
n (M
I) ro
om13
11.7
111
.712
Sen
ior M
anag
emen
t9
Sum
mar
y11
410
2.6
134.
111
7st
orag
eZO
NE
Rcl
ass
stor
age
(rece
ptio
n)
32.
72
5.4
6.24
clas
s st
orag
e (in
fant
and
juni
or)
32.
712
32.4
4.8
teac
hing
sto
rage
10.
914
12.6
Dra
ma
65.
41
5.4
Food
/Sci
ence
/ DT
65.
41
5.4
6P
E s
tore
(adj
acen
t to
perfo
rman
ce h
all)
22.6
14.5
114
.518
PE
sto
re (e
xter
nal)
65.
41
5.4
4no
n-te
achi
ng s
tora
gece
ntra
l sto
ck
87.
21
7.2
6cl
oakr
oom
s/lu
nch
box
stor
age/
lock
ers
(rece
ptio
n)3
2.7
010
.8cl
oakr
oom
s/lu
nch
box
stor
age/
lock
ers
(infa
nts)
25.9
2cl
oakr
oom
s/lu
nch
box
stor
age/
lock
ers
(juni
ors)
32.7
3se
curit
y st
orag
e4
3.6
13.
6di
ning
cha
ir/ta
ble
stor
e/ s
erve
ry20
181
1816
stag
ing
stor
e8
7.2
17.
2co
mm
unity
sto
re4
3.6
13.
6ca
reta
kers
/ m
aint
enan
ce s
tore
65.
41
5.4
5cl
eane
r’s s
tore
(2N
o.)
21.
81
1.8
3A
pp s
tore
1.5
Sum
mar
y15
013
512
7.9
139.
99
TOTA
L SC
HO
OL
NET
AR
EA15
5213
96.8
1390
.414
46.9
9
nurs
ery
Nur
sery
cla
ss30
6356
.762
ZON
E N
Nur
sery
2-3
yr's
2.5
1230
130
3-5
yr's
2.3
2659
.81
59.8
Kitc
hen/
staf
f15
115
7N
urse
ry s
tora
ge (n
urse
ry)
101
103.
12N
ures
ery
grou
p10
Ass
iste
d ch
angi
ng9
Nur
eser
y cl
ockr
oom
6.16
TOTA
L N
UR
SEY
NET
AR
EA11
4.8
97.2
8
non-
net a
rea
ZON
E K
kitc
hen
(full-
serv
ice
inc.
Sto
res)
78
421
4265
serv
ery
(see
cha
ir st
ore)
00
toile
ts (a
nd p
erso
nal c
are)
ZON
E M
nurs
ery
toile
ts (3
WC
S +
3 W
HB
's)
129.
52
199.
6re
cept
ion
toile
ts (3
WC
S +
3 W
HB
's)
129.
52
199.
6in
fant
s to
ilets
(3W
CS
+ 3
WH
B's
)9
othe
r pup
il to
ilets
(1:2
0 =
210-
60 =
150
= 1
50/2
0 =
8WC
S &
8W
HB
's)
100
901
9031
.58
Acc
essi
ble
visi
tor t
oile
ts3.
53
26
4H
ygie
ne fa
cilit
ies
87.
51
7.5
staf
f toi
lets
(3 N
o.) (
1 P
ER
25
Sta
ff &
1 fo
r eve
ry 2
5 ab
ove)
3.5
31
34
Dis
. WC
5
circ
ulat
ion
(incl
udin
g lo
bbie
s) (1
.9m
wid
e or
1.2
m m
in.)
312.
8428
1.56
128
1.56
348.
04pl
ant (
incl
. ser
ver)
and
vent
s (1
0No.
)41
.71
37.5
41
37.5
443
parti
tions
69.5
262
.57
162
.57
72.3
5Li
ft (1
.8m
x 1
.8m
)6.
48S
tair
121
.08
Sta
ir 2
7S
tair
(roof
)10
TOTA
L N
ON
-NE
T A
RE
A56
8.16
645.
73
TOTA
L G
RO
SS A
REA
2230
2007
2073
.36
2190
.00
Exte
rnal
Are
asne
t are
aS
ports
pitc
hes
8400
184
00so
ft pl
ay (i
nfor
mal
& s
ocia
l)18
501
1850
gam
es c
ourts
(har
d su
rface
d) (2
2mx3
3m)
1440
114
40ha
rd p
lay
(info
rmal
& s
ocia
l)10
301
1030
habi
tat
620
162
0flo
at21
001
2100
TOTA
L N
ET
SIT
E A
RE
A15
440
1389
615
440
non-
net a
rea
Ext
erna
l Non
-net
are
asFo
otpr
int o
f bui
ldin
gde
liver
y ac
cess
refu
se a
reas
bicy
cle
stor
age
entra
nce
path
s, ro
ads
etc.
C
ar p
arki
ng
TOTA
L G
RO
SS S
ITE
AR
EAFr
om17
320
To19
300
ECE DEVELOPMENT PROPOSALDevelopment of the site options and primary school general arrangement plan is based on the EFA baseline design. This was the starting point and the layout developed according to the options on the site. The blocks of colour, as shown on drawings in section 6 of the report indicate the zones of the plan below.
The plan will be further developed as the contractor is involved and a modular construction route is considered and investigated further.
27ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
Classroom BlockHall BlockAdmin / Ancillary Block
Education Funding AgencyEFA Baseline School Designs Dwg. No.:
Scale:
Overall GIFA
Ground:First: Second:Total:
TARGET: 2190m2
6,00
06,
000
6,00
0
8,900 10,150
Lift
Infants(62.0 m2)
Infants(62.0 m2)
Infants(62.0 m2)
Nursery(62.0 m2)
Reception(62.0 m2)
Reception(62.0 m2)
NurseryGroup(10.0 m2)
StaffWork
(7.0 m2)ReceptionWC
Coats
SeniorMAN(9.0 m2)
Head / Mtg(16.0 m2)
Server(4.0 m2)
CentralStock(6.0 m2)
Interview(7.0 m2)
Small Group(9.0 m2)
GeneralOffice(13.0 m2)
SEN / MI(12.0 m2)
AssistedChanging
(9.0 m2)
MaintEquip(5.0 m2)
StoreStore
LRC-Library(10.0 m2)
NurseryWC
Infants WC
Coats
StoreStore
Coats
Infants WC
StoreStore
Coats
Coats Coats Coats
StaffVisitWC
(4.0 m2)
Sick Bay(4.0 m2)
Infants(62.0 m2)
Library(24.0 m2)Main Hall
(180.0 m2)
Ext St(4.0 m2)
PupilWC
PupilWC
Kitchen(65.0 m2)
PE Store(18.0 m2)
ChairStore
(16.0 m2)
Plant(29.0 m2)
Repro-graphics
(8.0 m2)
WaitingArea
Clnr(1.5 m2)
App St(1.5 m2)
Store PupilWC
(5.0 m2)
2.01.0011:200 at A3Primary Type 2 420 + 26N 3-11
Standard Classroom Option
GROUND FLOOR PLAN
N1248m2
932m2
10m2
2190m2
EFA BASELINE DESIGN
28 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
Education Funding AgencyEFA Baseline School Designs Dwg. No.:
Scale:
Overall GIFA
Ground:First: Second:Total:
TARGET: 2190m2
6,00
06,
000
6,00
0
8,900 10,150
Lift
Infants(62.0 m2)
Infants(62.0 m2)
Infants(62.0 m2)
Nursery(62.0 m2)
Reception(62.0 m2)
Reception(62.0 m2)
NurseryGroup(10.0 m2)
StaffWork
(7.0 m2)ReceptionWC
Coats
SeniorMAN(9.0 m2)
Head / Mtg(16.0 m2)
Server(4.0 m2)
CentralStock(6.0 m2)
Interview(7.0 m2)
Small Group(9.0 m2)
GeneralOffice(13.0 m2)
SEN / MI(12.0 m2)
AssistedChanging
(9.0 m2)
MaintEquip(5.0 m2)
StoreStore
LRC-Library(10.0 m2)
NurseryWC
Infants WC
Coats
StoreStore
Coats
Infants WC
StoreStore
Coats
Coats Coats Coats
StaffVisitWC
(4.0 m2)
Sick Bay(4.0 m2)
Infants(62.0 m2)
Library(24.0 m2)Main Hall
(180.0 m2)
Ext St(4.0 m2)
PupilWC
PupilWC
Kitchen(65.0 m2)
PE Store(18.0 m2)
ChairStore
(16.0 m2)
Plant(29.0 m2)
Repro-graphics
(8.0 m2)
WaitingArea
Clnr(1.5 m2)
App St(1.5 m2)
Store PupilWC
(5.0 m2)
2.01.0011:200 at A3Primary Type 2 420 + 26N 3-11
Standard Classroom Option
GROUND FLOOR PLAN
N1248m2
932m2
10m2
2190m2
Education Funding AgencyEFA Baseline School Designs Dwg. No.:
Scale:
Overall GIFA
Ground:First: Second:Total:
TARGET: 2190m2
8,900 10,150
6,00
06,
000
6,00
0
Lift
Store
SmallGroup(9.0 m2)
Small Group(9.0 m2)
SEN Resource(13.0 m2)
Vent Vent Vent Vent Vent
VentVent Vent Vent
Store
Specialist Store(6.0 m2)
Juniors(55.0 m2)
Juniors(55.0 m2)
Juniors(55.0 m2)
Juniors(55.0 m2)
Juniors(55.0 m2)
Juniors(55.0 m2)
Juniors(55.0 m2)
Juniors(55.0 m2)
Coats
Specialist Practical(69.0 m2)
PupilToiletsAcc
WC(4.0 m2)
PupilToilets
Clnr(1.5 m2)
StoreVent
App St(1.5 m2)
Coats
Store
Store
Store
WC
Studio(55.0 m2)
Store Coats
Store
Staff(48.0 m2)
5 6
13
4321
14
15
16171819202122
LockersCoats
LockersLockers
2.01.0021:200 at A3Primary Type 2 420 + 26N 3-11
Standard Classroom Option
FIRST FLOOR PLAN
N1248m2
932m2
10m2
2190m2
Education Funding AgencyEFA Baseline School Designs Dwg. No.:
Scale:
Overall GIFA
Ground:First: Second:Total:
TARGET:2190m2
Stair access torooftop plant
8,900 10,150
6,00
06,
000
6,00
0
RLRL RL RL RLRL
7
8
9
10
111213141516
18
19
20
17
Air handling units on roof connected to vent shafts
Air handling units on roof connected to vent shafts
v v v v v v
vvvvvv
v v v v v
vvv vv vv v
Pitched roofover
RL
RL
RL
2.01.0031:200 at A3Primary Type 2 420 + 26N 3-11
Standard Classroom Option
SECOND FLOOR PLAN
N1248m2
932m2
10m2
2190m2
SECOND / ROOF PLAN
7 LAYOUT OPTIONS
29ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION 1
pitch
netball courts
school car parking / access
playing surface
school parking
playing surface
existing sports hall
existing teaching block
SITE LAYOUT
• New 2 storey primary school on existing secondary
school tennis courts
• New access off Cobbold Avenue
• Refurbish / upgrade existing sports hall
• New 6th Form Centre in reconfigured part of existing
school
• Loss of external playing surfaces
2 storey primary school
30 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION 1
shared playing area
area lost to community sports use
shared playing area
IMPACT ON EXTERNAL AREAS
31ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION 1
Eldon Road
new school + hard / soft play areas
Bird’s eye view
Cobbold Avenue
3D MODEL VIEW
32 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION 1
Bird’s eye view From Eldon Road
From West From Cobbold Avenue
3D MODEL VIEWS
33ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION 2 SITE LAYOUT
• New 2 storey primary school on existing secondary
school pitches off Eldon Road
• Existing access of Eldon Road doubled up for primary
school use
• Refurbish / upgrade existing sports hall
• New 6th Form Centre in reconfigured part of existing
school
• Loss of external playing surfaces
pitch
netball courts
Secondary school car parking / access
school parking / access
playing surface
existing sports hall
existing teaching block
games court
2 storey primary school
34 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION 2 OPPORTUNITIES FOR JOINT USE OF SPACES
1
75
9
28
Shelter
2
The Cavendish School
7a
COBBOLD AVENUE
4
5
Victoria
El Sub Sta
LB
2a
51
12
2
Netball Courts(hard surface)
Shelter
33
14
14
2
TCB
16
13
15663
5
Tennis Court(Hard surface)
168
164
28
34
77
ED & W
ard Bdy
26
1
1
Baptist Church
COBBOLD AVENUE
146
49
CR
ELDON ROAD
5-Aside pitch(Grass surface)
8
Tennis Court(Hard surface)
11 A-Side Pitch / 4 cross court (5-Aside) Pitches
(Grass surface)
9 A-Side Pitch / 3 Cross court (5-Aside)pitches
(Grass surface)
5-Aside pitch(Hard surface)
1
75
9
28
Shelter
ELDON ROAD
2
The Cavendish School
7a
COBBOLD AVENUE
4
5
Victoria
El Sub Sta
LB
2a
38
12
2
Netball Courts(hard surface)
Shelter
33
14
14
9b
2
16
13
63
5
13
Tennis Court(Hard surface)
9a
26
168
164
34
77
26
1
Baptist Church
COBBOLD AVENUE
El Sub Sta
1 ELDON ROAD
5-Aside pitch(Grass surface)
GLEN
DALE AVEN
UE
8
Tennis Court(Hard surface)
11 A-Side Pitch / 4 cross court (5-Aside) Pitches
(Grass surface)
9 A-Side Pitch / 3 Cross court (5-Aside)pitches
(Grass surface)
5-Aside pitch(Hard surface)
33
1
75
9
Shelter
144
ELDON ROAD
2
The Cavendish School
7a
COBBOLD AVENUE
BEVERIN
GTO
N C
LOSE
32
4
5
Victoria
El Sub Sta
LB
2a
51
12
2
Netball Courts(hard surface)
Shelter
33
14
14
2
TCB
16
156
34
63
5
35
Tennis Court(Hard surface)
142
26
164
ED a
nd W
ard
Bdy
34
77
ED & W
ard Bdy26
1
1
Baptist Church
COBBOLD AVENUE
1
146
49
CR
ELDON ROAD
WILLIN
GD
ON
RO
AD
5-Aside pitch(Grass surface)
8
Tennis Court(Hard surface)
11 A-Side Pitch / 4 cross court (5-Aside) Pitches
(Grass surface)
9 A-Side Pitch / 3 Cross court (5-Aside)pitches
(Grass surface)
5-Aside pitch(Hard surface)
Basement Plan
Ground Plan
First Floor Plan
typical shared use space in all through school
typical shared use space in all through school
typical shared use space in all through school
35ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION 2
shared playing area
shared playing area
area lost to community sports use
IMPACT ON EXTERNAL AREAS
36 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION 2
new school + hard / soft play areas
Eldon Road Cobbold Avenue
3D Model View
Bird’s eye view
37ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION 2 3D Model Views
Bird’s eye viewFrom Eldon Road
From West
38 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION 3SITE LAYOUT• Demolish temporary construction part of existing
sports hall retaining 2 storey segment
• Reconfigure retained 2 storey segment for primary
school use.
• Develop new 2 storey primary school accommodation
• New 6th Form Centre in reconfigured part of existing
school
• Rebuild new sports centre on adjoining site, possibly
for community use
• New access point off Cobbold Avenue shared by
primary school and sports centre
• New car parking spaces shared between new primary
school and sports centre
pitch
netball courts
Secondary school car parking / access
new primary school
playing surface
existing teaching block games court
new sports centre
39ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION 3
shared playing area
shared playing area
area lost to community sports use
IMPACT ON EXTERNAL AREAS
40 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION 33D MODEL VIEW
new school + hard / soft play areas
Eldon Road
new sports facility Cobbold Avenue
41ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION 33D MODEL VIEWS
Bird’s eye viewFrom Eldon Road
From West From Cobbold Avenue
42 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION 1
New site access on Cobbold Avenue is distant from existing Eldon Road access
and may reduce impact on wider transport network
Reduced impact on secondary school
This option, with its loss of playing surfaces is likely to attract negative attention
from Sport England
OPTION 2
Shared site access point may increase local traffic issues in Eldon Road with
similar impact to #1 on the wider transport network
Construction process may have greater impact on operation of secondary school
Collocated schools have stronger sense of education pathway from junior to
senior levels
This option, with its loss of playing surfaces is likely to attract negative attention
from Sport England
OPTION 3
New site access on Cobbold Avenue is distant from existing Eldon Road access
and may reduce impact on wider transport network
This option, with its provision of an enlarged sports centre (possibly for
community use), may provide mitigation to Sport England for loss of existing
playing surfaces.
Reduced impact on secondary school
This option contemplates the development of a larger, modern sports centre
which will increase the total development costs.
Option reuses part of the existing sports hall floorspace and so may reduce the
development costs of the primary school itself.
COMMENTARY ON OPTIONS
43ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
OPTION APPRAISAL CRTIERIA OPTION 1 OPTION 2 OPTION 3
Likelihood of receiving planning approval 5 7 5
Objection from neighbours 3 8 4
impact on highways infrastructure 5 8 5
level of section 106 cost 3 3 3
ability to creative an effective all-through school 2 8 6
ability to satisfy sport England 4 5 7
ability to meet September 2016 opening 10 10 10
improvement to sports facilities (Revenue / amenities) 3 3 8
level of running cost savings generated by new scheme 3 3 6
Added value to existing school 3 8 7
TOTAL 41 63 61
OPTION SCORING MATRIX
We have compared the three options using a simple scoring matrix. The resultant
total scores indicate the provisionally Option 2 scored marginally better than
Option 3 and considerably better than Option 1.
At feasibility stage we consider Option 2 to be the Preferred Option.
44 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
8 SCHOOL PRECEDENT
45ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
St Matthew Academy for Business and Enterprise www.architectureplb.com Page 1 of 2
St Matthew Academy for Business andEnterprise, BlackheathCompletion Date 2008Contract Value £23mClient DfES / Roman Catholic Diocese ofSouthwark
Commissioned under the DfES AcademiesProgramme Framework Agreement, the StMatthew Academy for Business and Enterpriseis a new build all-age City Academy, catering for1320 pupils from the age of 4 to 16 along with a13-place nursery. The project was shortlisted foran RIBA Award in 2010 and Highly Commendedin the BCSE Inspiring Design Awards 2009.
The new school was built on existing playingfields between the predecessor schoolbuildings. The site is within the BlackheathConservation Area, bounded by residentialdevelopment including some Listed buildings. Aconsidered approach to materials and massingallowed a contemporary building to be created,reflecting the Business and Enterprisespecialism, whilst responding to the sensitivecontext. Energy conservation was also a stronginfluence on the building form and massing,with top-lit atria and courtyards maximisingnatural light and ventilation. Photovoltaic panelsand a green roof add to the project’s sustainablecredentials.
The Academy caters for both secondary andprimary pupils. The design providesopportunities for sharing facilities whilemaintaining distinct areas appropriate to the
needs of children of different age groups. Thedining facilities, library and assembly hall areshared by all pupils, and a shared staff roomencourages dialogue and collaboration betweenprimary and secondary staff.
Key Stage 1 and 2 class bases are located to thewest at ground and lower ground floor, takingadvantage of a step in site levels to allowprimary class bases to open out to their ownexternal play areas. This location allowed aseparate entrance to be created, providing aroute for primary pupils and parents directly intothe play areas at the beginning and end of theday.
The innovative design responds to theeducational aspects of the brief providing forproject-based and personalised learning with amix of open and enclosed spaces. Enclosed,more traditional classrooms are gathered aroundthe open plan breakout areas providing a highdegree of flexibility and openness, facilitatinggroup working and creating an environment thatreflects the modern workplace. In the specialistareas these breakout areas are double height,top-lit spaces, providing a focus for eachspecialist department.
01
0302
01 External courtyard02 Diagram of open spaces03 Double height ICT atrium
EXAMPLE OF AN ALL THROUGH SCHOOL9700sqm GIA
Total Area : 9700sqm GIAProcurement Type : Design and Build (DfES Academies Framework)Local Authority : London Borough of Lewisham
Key to the school’s Christian ethos is thedevelopment of a strong school community. Ahigh degree of transparency and visualconnection between the various elements ofthe Academy reinforce this sense of communityas well as responding to the brief for acontemporary and businesslike, modernlearning environment.
The assembly hall is designed as a focal spacefor the school community; clad in warm timberwith natural light flooding in during the day andartificial light shining out at night, it provides acelebratory space at the heart of the school.
01 Longitudinal section02 Assembly Hall03 First floor plan04 Key Stage 2 play area05 External canopy
St Matthew Academy for Business and Enterprise www.architectureplb.com Page 2 of 2
01
02 03
04
05
Key1 General Teaching 2 Assembly mezzanine3 Drama / Dance4 Media Suite5 Music6 Art
Total Area : 9700sqm GIAProcurement Type : Design and Build (DfES Academies Framework)Local Authority : London Borough of Lewisham
Key to the school’s Christian ethos is thedevelopment of a strong school community. Ahigh degree of transparency and visualconnection between the various elements ofthe Academy reinforce this sense of communityas well as responding to the brief for acontemporary and businesslike, modernlearning environment.
The assembly hall is designed as a focal spacefor the school community; clad in warm timberwith natural light flooding in during the day andartificial light shining out at night, it provides acelebratory space at the heart of the school.
01 Longitudinal section02 Assembly Hall03 First floor plan04 Key Stage 2 play area05 External canopy
St Matthew Academy for Business and Enterprise www.architectureplb.com Page 2 of 2
01
02 03
04
05
Key1 General Teaching 2 Assembly mezzanine3 Drama / Dance4 Media Suite5 Music6 Art
St Matthew Academy for Business and Enterprise www.architectureplb.com Page 1 of 2
St Matthew Academy for Business andEnterprise, BlackheathCompletion Date 2008Contract Value £23mClient DfES / Roman Catholic Diocese ofSouthwark
Commissioned under the DfES AcademiesProgramme Framework Agreement, the StMatthew Academy for Business and Enterpriseis a new build all-age City Academy, catering for1320 pupils from the age of 4 to 16 along with a13-place nursery. The project was shortlisted foran RIBA Award in 2010 and Highly Commendedin the BCSE Inspiring Design Awards 2009.
The new school was built on existing playingfields between the predecessor schoolbuildings. The site is within the BlackheathConservation Area, bounded by residentialdevelopment including some Listed buildings. Aconsidered approach to materials and massingallowed a contemporary building to be created,reflecting the Business and Enterprisespecialism, whilst responding to the sensitivecontext. Energy conservation was also a stronginfluence on the building form and massing,with top-lit atria and courtyards maximisingnatural light and ventilation. Photovoltaic panelsand a green roof add to the project’s sustainablecredentials.
The Academy caters for both secondary andprimary pupils. The design providesopportunities for sharing facilities whilemaintaining distinct areas appropriate to the
needs of children of different age groups. Thedining facilities, library and assembly hall areshared by all pupils, and a shared staff roomencourages dialogue and collaboration betweenprimary and secondary staff.
Key Stage 1 and 2 class bases are located to thewest at ground and lower ground floor, takingadvantage of a step in site levels to allowprimary class bases to open out to their ownexternal play areas. This location allowed aseparate entrance to be created, providing aroute for primary pupils and parents directly intothe play areas at the beginning and end of theday.
The innovative design responds to theeducational aspects of the brief providing forproject-based and personalised learning with amix of open and enclosed spaces. Enclosed,more traditional classrooms are gathered aroundthe open plan breakout areas providing a highdegree of flexibility and openness, facilitatinggroup working and creating an environment thatreflects the modern workplace. In the specialistareas these breakout areas are double height,top-lit spaces, providing a focus for eachspecialist department.
01
0302
01 External courtyard02 Diagram of open spaces03 Double height ICT atrium Open space diagram
46 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
Total Area : 9700sqm GIAProcurement Type : Design and Build (DfES Academies Framework)Local Authority : London Borough of Lewisham
Key to the school’s Christian ethos is thedevelopment of a strong school community. Ahigh degree of transparency and visualconnection between the various elements ofthe Academy reinforce this sense of communityas well as responding to the brief for acontemporary and businesslike, modernlearning environment.
The assembly hall is designed as a focal spacefor the school community; clad in warm timberwith natural light flooding in during the day andartificial light shining out at night, it provides acelebratory space at the heart of the school.
01 Longitudinal section02 Assembly Hall03 First floor plan04 Key Stage 2 play area05 External canopy
St Matthew Academy for Business and Enterprise www.architectureplb.com Page 2 of 2
01
02 03
04
05
Key1 General Teaching 2 Assembly mezzanine3 Drama / Dance4 Media Suite5 Music6 Art
17/4/2014 The school day - St Matthew Academy
http://www.stmatthewacademy.co.uk/17/the-school-day 1/2
Search:
IN THIS SECTION
THE SCHOOL DAY
THE HOUSE SYSTEM
HOW WE RUN ENTERPRISE
MEDIA CENTRE
STUDENT VOICE
STUDENT CARE
OUTDOOR EDUCATION
THE SCHOOL DAY
Primary
TimesReception
Key stage 1Key stage 2
8.50-9.20 Period 1 Period 1
9.20-10.00 Period 2 Period 2
10-00-10.30 Form time Form time
10.30-10.50 Break Break
10.50-11.30 Period 3 Period 3
11.30-12.10 Period 4 Period 4
12.10-12.50 Lunch Period 5
12.50-13.30 Period 5 Lunch
13.30-14.10 Period 6 Period 6
14.10-14.50 Period 7 Period 7
14.50-15.20 Period 8 Period 8
Secondary
Times Key stage 3 Key stage 4
8.40-10.00 Period 1 Period 1
10.00-10.30 Form time Form time
10-30-10.50 Break Break
10.50-12.10 Period 2 Period 2
12.10-12.50 Lunch Period 3
12.50-13.30 Period 3
13.30-14.10 Lunch
14.10-15.30 Period 4 Period 4
WELCOME ABOUT US PRIMARY SECONDARY SCHOOL LIFE INFORMATION NEWS & EVENTS FACILITIES HIRE
CONTACT
Total Area : 9700sqm GIAProcurement Type : Design and Build (DfES Academies Framework)Local Authority : London Borough of Lewisham
Key to the school’s Christian ethos is thedevelopment of a strong school community. Ahigh degree of transparency and visualconnection between the various elements ofthe Academy reinforce this sense of communityas well as responding to the brief for acontemporary and businesslike, modernlearning environment.
The assembly hall is designed as a focal spacefor the school community; clad in warm timberwith natural light flooding in during the day andartificial light shining out at night, it provides acelebratory space at the heart of the school.
01 Longitudinal section02 Assembly Hall03 First floor plan04 Key Stage 2 play area05 External canopy
St Matthew Academy for Business and Enterprise www.architectureplb.com Page 2 of 2
01
02 03
04
05
Key1 General Teaching 2 Assembly mezzanine3 Drama / Dance4 Media Suite5 Music6 Art
St Matthew Academy for Business and Enterprise www.architectureplb.com Page 1 of 2
St Matthew Academy for Business andEnterprise, BlackheathCompletion Date 2008Contract Value £23mClient DfES / Roman Catholic Diocese ofSouthwark
Commissioned under the DfES AcademiesProgramme Framework Agreement, the StMatthew Academy for Business and Enterpriseis a new build all-age City Academy, catering for1320 pupils from the age of 4 to 16 along with a13-place nursery. The project was shortlisted foran RIBA Award in 2010 and Highly Commendedin the BCSE Inspiring Design Awards 2009.
The new school was built on existing playingfields between the predecessor schoolbuildings. The site is within the BlackheathConservation Area, bounded by residentialdevelopment including some Listed buildings. Aconsidered approach to materials and massingallowed a contemporary building to be created,reflecting the Business and Enterprisespecialism, whilst responding to the sensitivecontext. Energy conservation was also a stronginfluence on the building form and massing,with top-lit atria and courtyards maximisingnatural light and ventilation. Photovoltaic panelsand a green roof add to the project’s sustainablecredentials.
The Academy caters for both secondary andprimary pupils. The design providesopportunities for sharing facilities whilemaintaining distinct areas appropriate to the
needs of children of different age groups. Thedining facilities, library and assembly hall areshared by all pupils, and a shared staff roomencourages dialogue and collaboration betweenprimary and secondary staff.
Key Stage 1 and 2 class bases are located to thewest at ground and lower ground floor, takingadvantage of a step in site levels to allowprimary class bases to open out to their ownexternal play areas. This location allowed aseparate entrance to be created, providing aroute for primary pupils and parents directly intothe play areas at the beginning and end of theday.
The innovative design responds to theeducational aspects of the brief providing forproject-based and personalised learning with amix of open and enclosed spaces. Enclosed,more traditional classrooms are gathered aroundthe open plan breakout areas providing a highdegree of flexibility and openness, facilitatinggroup working and creating an environment thatreflects the modern workplace. In the specialistareas these breakout areas are double height,top-lit spaces, providing a focus for eachspecialist department.
01
0302
01 External courtyard02 Diagram of open spaces03 Double height ICT atrium
St Matthew Academy for Business and Enterprise www.architectureplb.com Page 1 of 2
St Matthew Academy for Business andEnterprise, BlackheathCompletion Date 2008Contract Value £23mClient DfES / Roman Catholic Diocese ofSouthwark
Commissioned under the DfES AcademiesProgramme Framework Agreement, the StMatthew Academy for Business and Enterpriseis a new build all-age City Academy, catering for1320 pupils from the age of 4 to 16 along with a13-place nursery. The project was shortlisted foran RIBA Award in 2010 and Highly Commendedin the BCSE Inspiring Design Awards 2009.
The new school was built on existing playingfields between the predecessor schoolbuildings. The site is within the BlackheathConservation Area, bounded by residentialdevelopment including some Listed buildings. Aconsidered approach to materials and massingallowed a contemporary building to be created,reflecting the Business and Enterprisespecialism, whilst responding to the sensitivecontext. Energy conservation was also a stronginfluence on the building form and massing,with top-lit atria and courtyards maximisingnatural light and ventilation. Photovoltaic panelsand a green roof add to the project’s sustainablecredentials.
The Academy caters for both secondary andprimary pupils. The design providesopportunities for sharing facilities whilemaintaining distinct areas appropriate to the
needs of children of different age groups. Thedining facilities, library and assembly hall areshared by all pupils, and a shared staff roomencourages dialogue and collaboration betweenprimary and secondary staff.
Key Stage 1 and 2 class bases are located to thewest at ground and lower ground floor, takingadvantage of a step in site levels to allowprimary class bases to open out to their ownexternal play areas. This location allowed aseparate entrance to be created, providing aroute for primary pupils and parents directly intothe play areas at the beginning and end of theday.
The innovative design responds to theeducational aspects of the brief providing forproject-based and personalised learning with amix of open and enclosed spaces. Enclosed,more traditional classrooms are gathered aroundthe open plan breakout areas providing a highdegree of flexibility and openness, facilitatinggroup working and creating an environment thatreflects the modern workplace. In the specialistareas these breakout areas are double height,top-lit spaces, providing a focus for eachspecialist department.
01
0302
01 External courtyard02 Diagram of open spaces03 Double height ICT atrium
Total Area : 9700sqm GIAProcurement Type : Design and Build (DfES Academies Framework)Local Authority : London Borough of Lewisham
Key to the school’s Christian ethos is thedevelopment of a strong school community. Ahigh degree of transparency and visualconnection between the various elements ofthe Academy reinforce this sense of communityas well as responding to the brief for acontemporary and businesslike, modernlearning environment.
The assembly hall is designed as a focal spacefor the school community; clad in warm timberwith natural light flooding in during the day andartificial light shining out at night, it provides acelebratory space at the heart of the school.
01 Longitudinal section02 Assembly Hall03 First floor plan04 Key Stage 2 play area05 External canopy
St Matthew Academy for Business and Enterprise www.architectureplb.com Page 2 of 2
01
02 03
04
05
Key1 General Teaching 2 Assembly mezzanine3 Drama / Dance4 Media Suite5 Music6 Art
47ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
9 SPORT ENGLAND
48 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
The Sport England remit is to ‘protect playing fields, space for team sports and open spaces used for recreation use’.
Any proposal to develop the Cavendish site with a loss of playing surfaces will be at odds with the Sport England remit and a mitigation case is likely to need to be mounted if our project is to find success.
Initial considerations
Areas of the existing grounds are already currently used by the public for recreation. It is not possible to develop a new primary school on the site, even in 2 storey configuration, without loss of external recreation space.
The existing sports hall is used by the public (as well as the school) although it is understood that the public use is less than might be expected. On initial appraisal the existing sport hall accommodation is not up to expected standards.
The main hall part of the existing sports building is lightweight, ‘temporary’ construction and could therefore be considered to be time-limited.
Initial Consultation
Option 2 proposal has been sent to Sport England on the 17th April for their pre-application advice. Our plans show the existing layout of marked surfaces on the site and possible mitigation strategy.
The Sport England criteria for the Cavendish site has been reviewed in the table across.
Summary
Early engagement and satisfying Sport England is likely to be a key element in the success of the development.
Pre-application comments from consultation with Sport England will be considered and responded to as the project design stages evolve.
Current use of cavendish sports centre
2012 - 2103 - Total Visits = 33,524
2013 - 2014 - Total visits = 34,200
49ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
EXISTING SPORTS USE OF THE SITE
site boundary
Secondary school building
sports hall
50 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
games court + pitch BB99Cavendish School site boundary
2 storey school footprint EFAhard + soft play areas BB99
SITE AREA ANALYSIS
The minimum EFA guidelines for external space is quantified below alongside an analysis of the existing site areas to show it is essential for the secondary and the primary phase to share sports facilities.
Diagram showing new 2FE primary school footprint requirements.
51ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
1
75
9
28
Shelter
ELDON ROAD
2
The Cavendish School
7a
COBBOLD AVENUE
4
5
Victoria
El Sub Sta
LB
2a
51
38
12
2
Netball Courts(hard surface)
Shelter
33
14
14
2
TCB
16
13
156
63
5
Tennis Court(Hard surface)
9a
26
168
164
28
34
77
ED & W
ard Bdy
26
1
1
Baptist Church
COBBOLD AVENUE
El Sub Sta
1
146
49
CR
ELDON ROAD
5-Aside pitch(Grass surface)
GLEN
DALE AVEN
UE
8
Tennis Court(Hard surface)
11 A-Side Pitch / 4 cross court (5-Aside) Pitches
(Grass surface)
9 A-Side Pitch / 3 Cross court (5-Aside)pitches
(Grass surface)
5-Aside pitch(Hard surface)
PROPOSED SPORTS PITCH LAYOUT
2 X 5-aside
New primary school
New sports pitch
(shared)
New games court
(shared)
sports pitches relocated and reorganised
52 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
10 ARCHEOLOGY ANDPLANNING INFORMATION
53ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
East Sussex County Council - County Archaeologist
An archaeological contractor will need to be employed to undertake the desk based assessments and impact assessments – they will need to contact the Historic Environment Record for the relevant information .
Partially within Archaeological Notification Area for Ocklynge Hill, prehistoric and Saxon cemetery. Uncertain level of past impacts. Will require full HER search by archaeological contractor to produce Archaeological Desk Based assessment (including impact assessment). It would be likely that we would recommend evaluation trial trenching to understand further the site’s potential and to inform the design and planning decision.
CONSERVATION & TPO’s
The Cavendish School is not located within conservation areas, nor are they subject to any tree preservation orders.
Part of Cavendish School is located within an archaeological notification area which is shown on a map in the next page.
PLANNING CONSULTATION
An initial meeting with David Vickers, the ESCC Planner was held on the 26th March to discuss the possibility of Cavendish as a site for a new primary school. This was an early introduction to the schemes and we were advised to seek early advice from Sport England and Highways. This has since been done.
Both the highways officers and planners had some comment about previous contact with neighbours of Cobbold Ave in relation to the fence at Cavendish.
Currently we are working towards having a meeting with the planners on the 25th June where we will have a preferred option and some initial feedback from Sport England.
1
75
9
28
Shelter
ELDON ROAD
2
The Cavendish School
7a
COBBOLD AVENUE
4
5
Victoria
El Sub Sta
LB
2a
51
38
12
2
Netball Courts(hard surface)
Shelter
33
14
14
2
TCB
16
13
156
63
5
Tennis Court(Hard surface)
9a
26
168
164
28
34
77
ED & W
ard Bdy
26
1
1
Baptist Church
COBBOLD AVENUE
El Sub Sta
1
146
49
CR
ELDON ROAD
2 5-Aside pitches(Grass surface)
GLEN
DALE AVEN
UE
8
Tennis Court(Hard surface)
11 A-Side Pitch / 4 cross court (5-Aside) Pitches
(Grass surface)
9 A-Side Pitch / 3 Cross court (5-Aside)pitches
(Grass surface)
Ocklynge Hill (Site of Saxon cemetery)
Archeological Notification Area (ANA)
Archeological Sensitive Area
54 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
11 UTILITY INFORMATION
55ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
LOCAL GAS DISTRIBUTION NETWORK
site boundary main gas line
56 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
LOCAL WATER DISTRIBUTION
foul pipe surface water pipe manhole
57ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
LOCAL POWER NETWORK
LV Cable Substation
LV Cable into
secondary
school building
58 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
12 PROGRAMME
59ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
ID Task Name Duration
1 Cavendish school meeting 0 days
2 Feasibility study / option appraisal 5 wks
3 Client / stakeholder approval 2 wks
4 Sport England engagement 8 wks
5 Concept Design 4 wks
6 Client / stakeholder approval 2 wks
7 Developed Design / planning application 8 wks
8 Client / stakeholder approval 2 wks
9 Public consultation 3 wks
10 Planning approval period 13 wks
11 Technical design 20 wks
12 Building contractor pre-construction 28 wks
13 Construction / works to school 24 wks
14 Construction / independent 52 wks
15 Fit out 4 wks
16 Handover 0 days
17 MEETINGS 1 day?
18 Client meeting 1 0 days
19 Client meeting 2 0 days
20 Client meeting 3 0 days
1
2
3
4
5
6
7
8
9
10
11
12
13
14
29/07
28/04
04/08
13/10
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Septer 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter
2015 2016
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 1
Project: 6065_Cavendish masterprogrDate: Wed 07/05/14
60 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
PROGRAMME MILESTONES
Early May ‘14: ESCC Feasibility Sign Off
End June ’14: End of survey period
Early July ‘14: ESCC Sign Off Stage C Design
Early Oct ‘14: ESCC Sign Off Stage D Design
Early Nov ‘14: Public consultation
Mid Nov ‘14: Planning Application submission
Nov to March ‘15: Stage E / F1
Start April ‘15: Start on site
Start April ‘16: Completion
End April ’16: Fit Out
61ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
13 RISK REGISTER
62 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
Risk Register
Document Status LIVE Immediate (20+)Project name ESCC Cavendish Primary School High (13 to 19)Last update 02 / 04 / 2014 Medium (7 to 12)
Low (1 to 6)Risk Assessor Nick Evans ECE Closed out
Ref Risk Type Description of risks Description of impact:
Probability rating: 5 = Highly Likely, 4 = Likely, 3 = Fairly Likely, 2 = Unlikely, 1 =Very Unlikely
Impact rating: 5 = Disastrous, 4 = Severe, 3 = Large, 2 = Marginal, 1 = Negligible
Urgency (score out
of 25) Control method Risk Owner1.00 Team roles, Management
Structure, line of responsibilities and competencies
1.01 Delivery in line with Programme
Programme is not met resulting in delay to delivery of the project.
New primary school is not ready for the new term in Sept 2016.
Unlikely Severe
8
Keep master programme up to date in accordance with any developments and known issues which may affect progress.
Builder / ESCC / ECE
1.02 Key stakeholders (Cavendish Secondary School) not bought into the approved design
Secondary School could withhold support leading to problems with stakeholder agreement at key stages
Delay in completion of programme Unlikely Severe
8
ESCC to identify and engage with key stakeholders early in design process. Design team to assist by presenting proposals in workshop environment.
ESCC / ECE
2.00 Highways2.01 Highways Due to the nature of the site,
highways approval could be contentious.
Could delay planning approval process Fairly Likely Large9
Early transport assessments and engagement with highways officers at ESCC.
ESCC / GTA
3.00 Surveys ground condition, archaeology and contamination
3.01 Ground conditions Unforeseen conditions resulting in design alterations and cost on the project
Construction methods and design to mitigate conditions are expensive and time consuming in the construction limited period of 12 months.
Unlikely Severe8
Commission surveys early to establish what is within the ground before construction begins
Builder / ESCC / ECE / HOP
3.02 Archaeology Possible heritage assets uncovered and unforeseen findings could result in a delay to starting on site.
Construction would be on hold till discoveries are found and removed in a controlled environment. Delay to programme. Impact on site layout
Fairly Likely Large9
Commission archaeology survey early to establish what is within the ground before construction begins
Builder / ESCC / ECE
3.03 Asbestos (Main building) Unforeseen asbestos in existing secondary school building could delay start on site.
Asbestos will need to be removed by specialist contractor which may cause a delay to construction starting.
Fairly Likely Marginal6
Commission asbestos survey early to establish what is within the building before construction begins
Builder / ESCC / ECE
3.04 Incoming Services Unknown capacity of local sewer, gas, water and electrical networks.
Site will not be serviced with main water, gas and electricity. May have to source off site or generate on site. Could be expensive and time consuming.
Likely Severe
16
Commission capacity checks and radar surveys early to establish what local network capacities are and where incoming services are within site boundary.
Ramboll / ESCC / ECE / HOP
3.05 Cost of incoming services (both sites)
Costs will not be known until after completion of Stage C
Impact on project out turn cost Likely Large12
Appoint QS to monitor costs ESCC
3.06 Ecology Determining the possible location of any species of animal in and around the Cavendish site
Impact on programme, impact on project specification and impact on building layout.
Fairly Likely Marginal6
Commission survey early to establish extent of any habitations.
LLD / ESCC / ECE
4.00 Construction
4.01 Contractor Procurement Contractors procurement period is not met and Tender returns are delayed
Delay in completion of programme Unlikely Large
6
Ensure contractor's selected agree to programme dates and Tender returns come back at given time. All clarifications responded quickly.
Builder / ESCC / ECE
4.02 Contractors Programme Contractors programme including prefabrication not able to meet required opening dates.
Delayed by academic year Unlikely Large6
Careful selection procedures for preferred contractor.
ESCC
5.00 Approvals5.01 Planning Approval Delayed Planning Approval is not granted in
line with Programme datesDelayed to construction starting on site Unlikely Large
6
Engage early with planning authorities and establish collaborative lines of communication with the relevant officers. Consider lobbying of members / MP etc. at the appropriate point.
ECE / ESCC
5.01 Sport England Objections Building on playing fields results in a loss of community sporting facitilites which Sport England will object too.
Delay to plannning approval and to construction starting on site
Likely Large
12
Engage early with Sport England to establish collaborative lines of communication with the relevant officers. Develop a mitiigating strategy for improving the sporting environment.
ECE / ESCC
Page 1 of 1
Risk Register
Document Status LIVE Immediate (20+)Project name ESCC Cavendish Primary School High (13 to 19)Last update 07 / 05 / 2014 - V#2 Medium (7 to 12)
Low (1 to 6)Risk Assessor Nick Evans ECE Closed out
Ref Risk Type Description of risks Description of impact:
Probability rating: 5 = Highly Likely, 4 = Likely, 3 = Fairly Likely, 2 = Unlikely, 1 =Very Unlikely
Impact rating: 5 = Disastrous, 4 = Severe, 3 = Large, 2 = Marginal, 1 = Negligible
Urgency (score out
of 25) Control method Risk Owner1.00 Team roles, Management
Structure, line of responsibilities and competencies
1.01 Delivery in line with Programme
Programme is not met resulting in delay to delivery of the project.
New primary school is not ready for the new term in Sept 2016.
Unlikely Severe
8
Keep master programme up to date in accordance with any developments and known issues which may affect progress.
Builder / ESCC / ECE
1.02 Key stakeholders (Cavendish Secondary School) not bought into the approved design
Secondary School could withhold support leading to problems with stakeholder agreement at key stages
Delay in completion of programme Unlikely Severe
8
ESCC to identify and engage with key stakeholders early in design process. Design team to assist by presenting proposals in workshop environment.
ESCC / ECE
2.00 Highways2.01 Highways Due to the nature of the site,
highways approval could be contentious.
Could delay planning approval process Fairly Likely Large9
Early transport assessments and engagement with highways officers at ESCC.
ESCC / GTA
3.00 Surveys ground condition, archaeology and contamination
3.01 Ground conditions Unforeseen conditions resulting in design alterations and cost on the project
Construction methods and design to mitigate conditions are expensive and time consuming in the construction limited period of 12 months.
Unlikely Severe8
Commission surveys early to establish what is within the ground before construction begins
Builder / ESCC / ECE / HOP
3.02 Archaeology Possible heritage assets uncovered and unforeseen findings could result in a delay to starting on site.
Construction would be on hold till discoveries are found and removed in a controlled environment. Delay to programme. Impact on site layout
Fairly Likely Large9
Commission archaeology survey early to establish what is within the ground before construction begins
Builder / ESCC / ECE
3.03 Asbestos (Main building) Unforeseen asbestos in existing secondary school building could delay start on site.
Asbestos will need to be removed by specialist contractor which may cause a delay to construction starting.
Fairly Likely Marginal6
Commission asbestos survey early to establish what is within the building before construction begins
Builder / ESCC / ECE
3.04 Incoming Services Unknown capacity of local sewer, gas, water and electrical networks.
Site will not be serviced with main water, gas and electricity. May have to source off site or generate on site. Could be expensive and time consuming.
Likely Severe
16
Commission capacity checks and radar surveys early to establish what local network capacities are and where incoming services are within site boundary.
Ramboll / ESCC / ECE / HOP
3.05 Cost of incoming services (both sites)
Costs will not be known until after completion of Stage C
Impact on project out turn cost Likely Large12
Appoint QS to monitor costs ESCC
3.06 Ecology Determining the possible location of any species of animal in and around the Cavendish site
Impact on programme, impact on project specification and impact on building layout.
Fairly Likely Marginal6
Commission survey early to establish extent of any habitations.
LLD / ESCC / ECE
4.00 Construction
4.01 Contractor Procurement Contractors procurement period is not met and Tender returns are delayed
Delay in completion of programme Unlikely Large
6
Ensure contractor's selected agree to programme dates and Tender returns come back at given time. All clarifications responded quickly.
Builder / ESCC / ECE
4.02 Contractors Programme Contractors programme including prefabrication not able to meet required opening dates.
Delayed by academic year Unlikely Large6
Careful selection procedures for preferred contractor.
ESCC
5.00 Approvals5.01 Planning Approval Delayed Planning Approval is not granted in
line with Programme datesDelayed to construction starting on site Unlikely Large
6
Engage early with planning authorities and establish collaborative lines of communication with the relevant officers. Consider lobbying of members / MP etc. at the appropriate point.
ECE / ESCC
5.02 Sport England Objections Building on playing fields results in a loss of community sporting facitilites which Sport England will object too.
Delay to plannning approval and to construction starting on site
Likely Large
12
Engage early with Sport England to establish collaborative lines of communication with the relevant officers. Develop a mitiigating strategy for improving the sporting environment.
ECE / ESCC
5.03 Eastbourne Borough Council Objections
Objections from Borough Planners to the application could delay pllaning approval
Delay to plannning approval and to construction starting on site
Likely Large
12
Engage early with Eastbourne Borough Council to establish collaborative lines of communication with the relevant officers. Develop a mitiigating strategy for any objections
ECE / ESCC
Page 1 of 1
63ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
14 STRUCTURAL ENGINEER’S REPORT
64 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
HOP Consulting Limited t/a Hemsley Orrell Partnership
Registered Office: 73 Church Road, Hove, BN3 2BB Reg. no.
4402211 England
Directors: Jonathan W Orrell BSc (Hons), CEng, FICE, FCIOB, FIStructE, John F Spearman BSc (Hons), CEng, MICE, Alan Taylor BSc (Hons), CEng, MIStructE.
Adam Humphrey BEng (Hons), MEng, CEng, MIStructE Associates: David Jones MA, CEng, MIStructE, Lee Stewart BEng(Hons), CEng, MIStructE
Mark Naumann BEng (Hons), CEng, MICE Nigel Hosker BEng (Hons), CEng, MICE
Proposed New Primary School Cavendish School Eastbourne
Feasibility Study April 2014 Client: ECE Architecture Project: 14343/01 Prepared by Approved by Checked by M Baker Mark Naumann Mark Naumann
65ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
PROPOSED NEW PRIMARY SCHOOL CAVENDISH SCHOOL, EASTBOURNE
14343/01 – Feasibility Study 2 April 2014
CONTENTS 1.0 INTRODUCTION __________________________________________________ 3 2.0 SITE LOCATION __________________________________________________ 3 3.0 SITE GEOLOGY __________________________________________________ 4 4.0 SITECHECK REPORT _____________________________________________ 4 5.0 EXISTING SERVICES ______________________________________________ 4
UK Power Networks ________________________________________________ 4 Scotia Gas Networks _______________________________________________ 4 BT _____________________________________________________________ 5 Virgin Media ______________________________________________________ 5 Southern Water ___________________________________________________ 5
Appendix I – Architectural Proposals ______________________________________ 6 Appendix II – Service Enquiries __________________________________________ 7 Appendix III – Scotia Gas Networks Correspondence ________________________ 8
66 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
PROPOSED NEW PRIMARY SCHOOL CAVENDISH SCHOOL, EASTBOURNE
14343/01 – Feasibility Study 3 April 2014
1.0 INTRODUCTION
Hemsley Orrell Partnership has been instructed to conduct a feasibility report for the proposed new school development on the site of Cavendish School on Eldon Road in Eastbourne, based on information obtained from a Sitecheck Data report and Service plans provided by the relevant Statutory Authorities. It is proposed to construct a new 2 storey, 2 form entry primary school including car parking and playground space, on the grounds of Cavendish School. Currently there are 3 development options for the site, as shown in architectural information provided by ECE and included in Appendix I. Information for this report has been received from a number of external parties, HOP cannot be held responsible for the accuracy of this information. In light of any additional information becoming available, a change in proposed end use, improved practices or changes in legislation, amendment of reinterpretation of this report may be necessary after its original submission.
2.0 SITE LOCATION
The Cavendish School site is located within a residential area in Eastbourne on the North side of Eldon Road and to the West of the A2270 Willingdon Road.
Site Location Plan extract from Streetmap.com Cavendish School currently occupies the site with the school buildings, car parking and a mixture of hard surfaced play areas and sports pitches and soft landscaped playing fields. The main access to the school is from Eldon Road to the South.
Aerial Photo extract from Bing.com
67ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
PROPOSED NEW PRIMARY SCHOOL, CAVENDISH SCHOOL, EASTBOURNE
14343/01 – Feasibility Study 4 April 2014
3.0 SITE GEOLOGY
A review of the British Geological Survey maps of the area, indicate the Bedrock geology at the site to be predominantly Zag Chalk Formation. There are no Superficial Deposits recorded on site, although some head deposits are expected over chalk bedrock.
4.0 SITECHECK REPORT
A Sitecheck Data report has been obtained by HOP to inform the proposed development at the site. The report confirms the site is in Flood Zone 1.The report also shows that the site lies over both a Major Aquifer (highly permeable). However, EA online mapping shows that the site lies in a Source Protection Zone 1. The Sitecheck report shows that there is Very Low to No Hazard potential risk from Ground Stability Hazards on site, such as Collapsible Ground and Shrinking/Swelling Clay. The site is shown to be in an intermediate probability Radon area, as between 1 and 3% of homes are above the action level. The report indicates that no Radon protection measures are required on site, although this should be confirmed by further investigation. Currently, the Sitecheck report and mapping shows no potentially contaminative land uses on site. There are 3 Trade Directory entries within 250m of the site, all listed as ‘inactive’. Eastbourne District Council and East Sussex County Council have provided data regarding
landfill coverage and no areas of landfill are shown on the report mapping on or near to the site. The report shows there are no potentially contaminative past land uses on site, or historical tanks or landfill. Within 250m of the site there are shown to have been an electrical substation and a cemetery. Online Mapping shows the cemetery is still present, located adjacent to the school on the South side of Eldon Road. Once a development proposal has been finalised a Phase I Contaminated Land Desk Study, including the purchase of a full Envirocheck report and thorough site walkover, will inform the site as to whether there are any contamination risks present on site, which if present, should be followed by Phase II Site Investigation, remedial works and validation tests upon completion.
5.0 EXISTING SERVICES
Please note that this report should be read in conjunction with the attached original service plans, and that HOP cannot be held responsible if the plans from the Service Providers are incorrect. The service enquiries only show Statutory Service plant and therefore plant under private ownership of the school, or otherwise, will need to be located on site. The impact of development depends on the location of the new school and associated buildings; if they are over the gas, BT and electricity plant, these services may need diverting. We would also recommend a ground penetrating radar survey or similar to investigate private services that are not shown on service plans. Capacity of the existing service networks has not been considered at this stage due to the preliminary nature of the proposals to date.
UK Power Networks Provided UKPN plans show a spur from both a Low Voltage (LV) cable and a High Voltage (HV) cable under the pavement on Eldon Road connecting into the school. The cables run under the soft landscaping and footpaths to the East of the car parking area. A Substation is shown adjacent to the site’s Northern boundary, on Cobbold Avenue. HV and LV cables run under the footpath along the road from this location, with an LV spur running under the Eastern edge of the North-Western grass playing field, before connecting to the Northernmost building on site.
Scotia Gas Networks Scotia Gas plans show a 4” low pressure main and a 12” LHP main under Eldon Road. No connections are shown to the school buildings. Correspondence from Scotia Gas Networks, included in Appendix III, details conditions that will be placed on any construction work and development in the vicinity of the High Pressure gas main, including a building proximity zone of 14 metres. This may affect development option 2,
SITE
68 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
PROPOSED NEW PRIMARY SCHOOL, CAVENDISH SCHOOL, EASTBOURNE
14343/01 – Feasibility Study 5 April 2014
BT BT plans show underground cables running from a joint box on Eldon Road under the soft landscaping and car parking into the school building, with another joint box located on the school grounds shortly before the cables connect to the building.
The plans also show a spur coming from a joint box on the footpath on the far side of Cobbold Avenue, running under the road and along the Eastern edge of the North-Western grass playing field and connecting to the Northernmost building on site.
Virgin Media Virgin Media have confirmed that they have no plant located on or near the site.
Southern Water Plans provided by Southern Water show no underground drainage on site, only a 225mmdiameter foul sewer and a 37mm diameter storm sewer under Eldon Road, and a 225mm diameter foul sewer and 225mm diameter storm sewer under Cobbold Avenue.
Private drainage on site should be surveyed by CCTV inspection to ascertain its location,condition and capacity with regard to the proposed development.
Foul and Storm water capacity checks should be undertaken with Southern Water once development proposals are finalised, to inform any drainage scheme that will be designed.
69ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
PROPOSED NEW PRIMARY SCHOOL, CAVENDISH SCHOOL, EASTBOURNE
14343/01 – Feasibility Study 6 April 2014
APPENDIX I – ARCHITECTURAL PROPOSALS
70 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
33
OPTION 1 new 2FE primary school
37
OPTION 2
new 2FE primary school Saxon burial ground?
new 2FE primary school
41
OPTION 3
71ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
PROPOSED NEW PRIMARY SCHOOL, CAVENDISH SCHOOL, EASTBOURNE
14343/01 – Feasibility Study 7 April 2014
APPENDIX II – SERVICE ENQUIRIES
72 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
73ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
74 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
Plant Location95 Kilbirnie StreetGlasgowG5 8JD
Phone: 0141 418 4093Phone: 0845 070 3497Fax: 0141 429 6432Email: [email protected]
Max Baker, .Hemsley Orrell PartnershipHOP House41 Church RoadHove, BN3 2BE.
Our Ref:Your Ref:
Dear Customer,
SO/0025854
Date: 29/04/2014
Re: Enquiry at: Cavendish School, Eldon Road, Eastbourne BN21 1UE.
Thank you for your enquiry regarding the above location.
Please find enclosed an extract from our mains records in the location of the area covered by your proposals for your guidance. This plan only shows those pipes owned by SGN in its role as a Licensed Gas Transporter (GT). It should be noted that gas pipes owned by other GTs or privately owned may be present in this area and information regarding such pipes should be obtained from the owners. Where SGN knows this, they will be represented on the plans as a shaded area and/or a series of x’s.
The information shown on this plan is given without obligation, or warranty and the accuracy cannot be guaranteed. Service pipes, valve siphons, stub connections etc, are not shown but their presence should be anticipated. Your attention is drawn to the information and disclaimer on these plans. The information included on the plan is only valid for 28 days.
A colour copy of these plans and the gas safety advice booklet should be passed to the senior person on site in order to prevent damage to our plant and potential direct or consequential costs to your organisation.
There is High Pressure apparatus in the vicinity; accordingly a copy of your correspondence has been sent to our local engineer, who will be in contact shortly. It is essential that no work or crossings of this high pressure pipeline is carried out until a detailed consultation has taken place.
You will note the presence of our Low/Medium/Intermediate Pressure gas main in the proximity to your site. There should be mechanical excavations taking place above or within of the low pressure system, of the medium pressure system and of the intermediate pressure system. You should where required of mains .using hand dug trial holes
no 0.5m
confirm the position0.5m 3m
24 hour gas escape number 0800 111 999**Calls will be recorded and may be monitored
Southern Gas Networks plc is part of the Scotia Gas Networks GroupRegistered Office: St Lawrence House Station Approach HorleySurrey RH6 9HJRegistered in England & Wales No. 05167021http://www.sgn.co.uk
Yours faithfully,
Lesley Phillips
0141 418 4093
For safety reasons, safe digging practices, in accordance with HSE publication HSG47 “Avoiding Danger from Underground Services” must be used to verify and establish the actual position of mains, pipes, services and other apparatus on site before any mechanical plant is used. It is your responsibility to ensure that this information is provided to all persons (direct labour or contractors) working for you on or near gas plant. In addition please follow the advice given in our gas safety booklet (enclosed).
It must be stressed that both direct and consequential damage to gas plant can be dangerous both for your employees and the general public, repairs to any such damage will incur a charge. Your works should be carried out in such a manner that we are able to gain access to our apparatus throughout the duration of your operations.
If you require any further information please contact the number below.
24 hour gas escape number 0800 111 999**Calls will be recorded and may be monitored
Southern Gas Networks plc is part of the Scotia Gas Networks GroupRegistered Office: St Lawrence House Station Approach HorleySurrey RH6 9HJRegistered in England & Wales No. 05167021http://www.sgn.co.uk
75ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
E
E
E
E
R
E
R
E
E
E
R
E
R
Y E
E
EE
E
169
29
to
32
CR
21
to
24
13 t
o 16
Hanover C ourt
9 to
12
9447
18
1
33
2
31
1
2
130
63
116
49
100H
UR
ST R
OA
D
86
CW
1
20 10
1
17
90
Piece
1 to 6
Ockling
ED and
Ward B
dy7
23
LON
G A
CR
E C
LO
SE
50.0
m
102
35
114
1
79
WI L
LI NG
DO
N R
OA
D
49
128
5
1
EL D O N R O A D 93
CR47 .0 m
51 .5 m
4
142
51
107
R O D M I L L R O A D
144
144
1
2a
Su b St a
El
8
ED a
nd W
ard
Bdy
TC B2
146
63
53 .0 m
CW
LB
R O D M I L L D R I V E
34
ED & W
ard Bd
y
26
156
33
75
1
27
C O B B O L D A V E N U E 55 .9 m
534
BEV
ER
I NG
TO
N C
LO
SE
164
32
2
YI E L D I N G 'S C L O S E
77
25
28
168
21
1081
83
11 1385
60 .2 m
BEV
ER
I NG
TO
N C
LO
SE
14
180
C LO S E
R U TL A N D
22
CR
ED & W
ard Bd
y
26
H oc ke y G r ou n d
Te nn i s C o u rtTe nn i s C o u rt
Te nn i s C o u rt
El S u b St a
5
C O B B O L D A V E N U E
16 12149
826
38
13
28
42
1
WI N D M I L L C L O S E
107
5
1
CLO
SE
LUT
ON
14
52
25 7
42
MA
CM
I LLA
N D
RI V
E
17
20
Playing Field
Baptist Ch urch
Victoria
33
9b 9a
34
El S u b St a
7a
EL D O N R O A D
41 .1 m Sh el te r
42 .1 m
41 .9 mSh el te r
42 .5 m
1
2
The Cavendis h School
14
13
N et b al l C ou rt s
GLE
ND
AL
E AV
EN
UE
GR
ESH
AM
GLE
ND
AL
E A
VE
NU
E
CO
BB
OL
D A
VE
NU
E
179
TC B
177
175
a
DR
IVE
173
41 .7 m
LB
204
192
15 11 9 23
(s it e o f)38 .5 m
11
30
36 .1 m
16
236
49
56
25
61
68
252
37
256 65
72
41
264Vi c
arag
e
82
51
77
1
El S u b St a
CLO
SESt Elisabeth's C hurch 53
VI CT
OR
I A
Set t l eme nt
1 to 1 2
12 10
206
25
AVE
NU
E
8
32
42 .6 m
BA
LDW
I N
1 to 1
8
222 37
44
2
1
CourtW
ES
SE
X P
LA
CE
Cornwall
Li b rary
177 a
187
175
2a
GR ID M A IN 9
4' -0 " F .W
6' -0 " E .K
.
D.P
D.P
PIPE SY PHO N11 ' -0 " E .E . KC.3 0 "
-
-
-
-
-
-
B ef or e E x c av a tio nP 18 P r oc e dur e a ppl ies
B ef or e E x c av a tio nP 18 P r oc e dur e a ppl ies B ef or e E x c av a tio n
P 18 P r oc e dur e a ppl ies
B ef or e E x c av a tio nP 18 P r oc e dur e a ppl ies
-
-
B ef or e E x c av a tio nP 18 P r oc e dur e a ppl ies
-
-
DO C 0. 8
-
-
-
B ef or e E x c av a tio nP 18 P r oc e dur e a ppl ies
-
-
DO C 0. 6
DO C 0 .8
DO C 0 .8
Di a m e t e r & M a t e r ia lo f 4 " SI u n c o n f i r m e d .Da te d 2 1 / 0 2 / 1 4DR 4 1 4 3 7 2 5
8.1
9.2
0.9
2.1
1.2
1.4
1.9
1.5
1.8
1.8
1.5
1.8
3.8
1 .6
1.9
1.4
1.2
1.6
1.4
1.6
1.6
1.2
0.7
1 .4
0.7
6.1
1 .4
0.8
1.1
1 .4
1.3
1.2
1.3
1.2
1.6
7.6
1.6
1 .2
5.7
1 .1
0 .8
0.8
11.0
2.1
0.2
1 .0
2 .0
3.5
5 .0
1.4
4.2
11 .6
2.7
1 .5
3.0
5 .3
5.0
3.3
1 .2
3.5
0.8
1.9
2.2
0.7
3.3
0 .4
3.1
1 .2
8 .0
3.9
1.2
3.51 .3
1.3
1.4
1.1
6.5
1 .1
1.2
1.3
1.2
1.5
1.7
1.7
1.3
3 .5
2.0
3.3
1 .5
6.10 .4
1.5
1.5
1.3
1.2
1.3
1.3
1.4
1.3
2.4
1.4 1.2
1 .8
4.8
1 .1
1.1
13.7
12.9
7.7 4.6
2.7
2.5
10.1
5.2
2.5
1.4
1.4
6.8
7.2
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
55
5
5
5
NN
N
31 5 PE M / P
250
PE
(IN
12"
DI)
M/P
250
PE
(IN
12"
DI)
M/P
250 P
E M
/ P ( IN
12" D
I )
250 P
E M
/ P
250 P
E M
/ P ( IN
12" D
I )
25
0 P
E M
/ P
250 P
E M
/ P ( IN
12" D
I )
25
0 P
E M
/ P
250 P
E M
/ P ( IN
12" D
I )
$
!"$
$$
$!"
$
"!
$"!
""!!
$
$
!
!
!
$
$$
$
$
$
$
$
$
$$
$
$ $ $
$$
$
$ $ !"$
$ $
$
$ !!"" $
$
$$
$
"!
$
"
$
$
$
$
$
$
$
$
$
"!
$
$
$
"!"
!
!
"!
"!
"!
$
$
"!
$
$
$
$
$
"!
$
$
$
Q
B
Q
K
B
K
B
B
W
W
B
B
K
Q
Q
B B
B
Q
Q Q
Q Q
Q
Q B
Q Q
K
Q
B
B
B
Q
Q
Q
Q
Q
N N
N
N
4" DI
6" D
I
4" DI
4" SI
4" SI
4" DI 4" DI 1 8 0 PE ( I N 4 " SI )
4" DI 1 8 0 PE ( I N 4 " SI )
90 PE
2" PE
6" CI
63 PE
8" CI 63 PE
12" CI
4" SI
4" SI
90 P
E
9 0 PE
9 0 PE
6 3 PE
6 3 PE
4" SI
63 PE
90 PE
90 PE
3" PE
63 PE
6" D
I
6 " D I
63 PE
90 PE
4" D I
4" DI
90 PE
6 " C I
4" CI4" CI
4" CI4" SI
90
PE
( I
N 4
" C
I )
63
PE
( I N 4
" S
I )
6 3 PE ( I N 4 " CI )
1 2 5 PE ( I N 6 " C I)
6 " C I 6" CI
4" CI
6" CI
12
5 P
E ( I N
6" C
I)
6 " SI
3" S
T
8" CI
2" ST
8" CI
6" SI
4" CI
8" CI
8" C
I
6" SI
3 " SI
6 3 PE
6 3 PE
6" SI
4" CI
8" C I
6" SI
6" CI
6" SI
4" CI
125 PE
4" CI
1 2 5 PE
75
PE
( I N 4
" S
I ) 12
5 P
E ( I N
6" C
I)
4" CI
6 " CI
4" DI
1 8 0 PE ( I N 8" D I)
3" PE
6 3 PE ( I N 4 " SI )
4 " SI
1 8 0 PE ( I N 4 " SI )
4 " SI
4 " D
I
8" DI
1 8 0 PE
1 8 0 PE ( I N 4 " SI )
1 8 0 PE
1 8 0 PE ( I N
6" D
I)4
" SI
4" DI
6" D
I 3 " PE
90 PE
63 PE
180
PE
( IN
8"
DI)
1 8 0 PE
( I
N 8
" D
I)
4" DI
6 " DI
1 8 0 PE ( I N 6 " D I)
4 " D I 1 8 0 PE ( I N 4 " D I)
4 " SI
18
0 P
E ( I N
8" D
I)
4" D
I
4"
SI
4 " SI
4"
DI
18
0 P
E
( IN
8"
DI)
4 " SI
1 8 0 PE
( I
N 8
" D
I)
1 8 0 PE ( I N 4 " SI )
3" ST
6 3 PE
63
PE
8" C
I 6
3 P
E
2" PE
2" PE
2" C I
8" CI4" CI
2" PE
4" SI 8" CI
2" PE
2" PE
4" SI 8" CI
4" CI
4" DI
4" D I
2" PE
4" SI
63 P
E
4" SI
6" SI
4" S
I
4 " SI
4 " SI
4 " SI
4 " SI
4 " SI
4" CI
4" C I
4 " C I
6 3 PE ( I N 4 " CI )
9 0 PE
90
PE
( I N 4
" C
I )
9 0 PE ( I N 4 " CI )
4" SI
4" C I
4" SI
4" CI
8" SI
6 3 PE
8" CI
6 3 PE
6 3 PE
6" CI ( IN 0 )
6" SI
6" SI
90
PE
( I N 4
" C
I )
4 " C I
4" SI
4" S
I
4 " C I
4 " C I
6" CI
9 0 PE ( I N 4 " SI )
9 0 PE ( I N 4 " SI )
4" C
I
4" CI
4" CI
4 " C I
90
PE
( I N 4
" S
I )
4" C
I
4" C
I
4" C I
12
5 P
E ( I N
6" C
I)
4 " SI
90
PE
( I N 4
" S
I )
4 " C I
4 " C I
9 0 PE
4" C
I
4" CI
4 " SI
90
PE
( I N 4
" S
I )
90
PE
( I N 4
" S
I )
90
PE
( I
N 4
" S
I )
4 " C I
4 " SI
1 2 5 PE ( I N 6 " C I)
1 2 5 PE
90
PE
( I
N 4
" S
I )
4 " SI
12" ST H/P
12" ST H/P
12" ST H/P
12" ST H/P
12" ST H/P
12" ST H/P
12" ST H/P
90
PE
( I N 4
" C
I )
75
PE
( I N 4
" S
I )1
25
PE
( I N 6
" CI)
6 3 PE ( I N 4 " CI )
90
PE
( I
N 4
" C
I )
90
PE
( I N 4
" C
I )
12
5 P
E ( I N
6" C
I)
12
5 P
E
( IN
6"
CI)
12
5 P
E ( I N
6" C
I)
12
5 P
E
( IN
6"
CI)
4 " C I
90
PE
( I N 4
" S
I )
90
PE
( I N 4
" S
I )
90
PE
( I N 4
" S
I )
9 0 PE ( I N 4 " SI )
0.8
0.8
0 .8
0.8
0 .8
0 .8
0 .8
0.8
0 .6
0.8 0.6
0 .8
0 .8
0.8
0 .8
0.8
0.8
0.8
0.8
0.8
0.8
0.8
0 .8
0.8
0.8
0.8
0 .8
0.8
0.8
0.8
0.8
0 .8
0.8
0.8
0.8
0.8
0.8
0 .8
0.8
0.8
0 .8
0.8 0 .8
0.6
0.8
0 .8
0 .7
0 .7
0.7
0.7
0 .8
0.8
0.8
0.8
0.8
0.8
0.8
0.8
0.8
0.8
0.8
0.8
0.8
0.8
7'W. K
TQ5900SW TQ5900SE
TQ5900NW TQ5900NE
0 70 Meters
This plan shows the location of those pipes owned by Scotia Gas Networks (SGN) by virtue of being a licensed Gas Transporter(GT). Gas pipes owned by other GTs or third parties may also be present in this area but are not shown on this plan. Informationwith regard to such pipes should be obtained from the relevant owners. No warranties are given with regard to the accuracy of theinformation shown on this plan. Service pipes, valves, s iphons, sub-connections etc are not shown but their presence should beanticipated. You should be aware that a small percentage of our pipes/assets may be undergoing review and will temporarily behighlighted in yellow. If your proposed works are close to one of these pipes, you should contact the SGN Plant Protection Team on08450703497 for advice. No liability of any k ind whatsoever is accepted by SGN or its agents, servants or sub-contractors for anyerror or omission contained herein. Safe digging practices, in accordance with HS (G)47, must be used to verify and establish theactual position of mains, pipes, services and other apparatus on site before any mechanical plant is used. It is your responsibil ity toensure that plant location information is provided to all persons (whether direct labour or sub-contractors) working for you on ornear gas apparatus. Information included on this plan should not be referred to beyond a period of 28 days from the date of issue.
This plan is reproduced from or based on the OS map by Scotia Gas Networks plc, with the sanction of the controller of HM Stationery Office.Crown Copyright Reserved.
East Sussex County Area
INTRANET MAP VERSION 2.1LP MAINS
GRID REFERNCE:INTERNAL USE ONLY
USER ID:MP MAINSIP MAINSLHP MAINS
HISTORY DATALAsGTs SSSIs
Some examples of Plant items:Valve
Depth ofCover
Syphon DiameterChange
MaterialChange
DATE: 29/04/2014
SCALE 1:
E559454,N100379,TQ 59 00
lp54998
2115
WARNING! This area conta ins Gas Mains operating at High Pressure in excess of 7 bar. Before excavating in thearea contact the loca l network office.
76 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
77ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
Southern Water Southern House Capstone Road Chatham Kent ME5 7QA www.southernwater.co.ukSouthern Water Services Ltd Registered Office: Southern House Yeoman Road Worthing BN13 3NX Registered in England No. 2366670
Your Ref Our Ref Date Contact [email protected]
Fax 01634 844514DX:400450 Chatham 5
Attention:
Dear Sirs
Further to your recent enquiry regarding the provision of Southern Water apparatus record extracts for the above location.
Please be aware that there are areas within our region in which there are neither sewers nor water mains. Similarly, whilst the enclosed extract may indicate the approximate location of our apparatus in the area of interest, it should not be relied upon as showing that further infrastructure does not exist and may subsequently be found following site investigation. Therefore actual positions of the disclosed (and any undisclosed) infrastructure should be determined on site, because Southern Water does not accept any responsibility for inaccuracy or omission regarding the enclosed plan and accordingly it should not be considered to be a definitive document.
I confirm payment of the appropriate fee in the sum of £
The breakdown of costs is as follows: -
Provision of record extracts £
VAT @ 20.0% £
VAT Registration Number 813 0378 56
Should you require any additional information regarding this matter please contact this office at the address given at the foot of this letter.
Yours faithfully
Land Search Department
Hemsley Orrell PartnershipHOP House 41Church RoadHoveEast SussexBN3 2BE
MB/GAW/14343/1
172151
17 April 2014
Max Baker
Provision of Public Sewer Main Record Extracts – VAT ReceiptCavendish School, Eldon Road, Eastbourne, East Sussex, BN21 1UE
48.00
40.00
8.00
78 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
79ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
80 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
PROPOSED NEW PRIMARY SCHOOL, CAVENDISH SCHOOL, EASTBOURNE
14343/01 – Feasibility Study 8 April 2014
APPENDIX III – SCOTIA GAS NETWORKS CORRESPONDENCE
81ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
Max There is a high pressure pipeline in the vicinity of the proposed development which has Building Proximity Distance (BPD). The building proximity distance (zone 1) is 14 metres either side of the pipeline. This should not however be confused with the HSE consultation zones 2 & 3 which will be considerably greater. Zone 1 is a safety factor with reference to habitable buildings as recommended by IGE/TD/1. It is calculated from the diameter, material, wall thickness and pressure of the particular pipeline. Under Pipeline Safety Regulations 1996 this distance is declared to the HSE. Any intrusion within this safety zone should not be taken lightly and any intention to proceed should be accompanied by a risk assessment or provision of other supporting evidence especially in the event of any legal proceedings at a later date. I have attached a copy of our plans showing the pipelines in relation to this site. Pipelines laid in private land are protected by a Deed of grant, which prohibits certain activities within the easement strip like no addition to or removal of surface levels, no structures over or within the specified distance of the pipeline. Further details are available if you require them. A request to us for any copies could incur a small fee, payable in advance. Any vehicle crossings over the pipeline will require: calculations to prove that no additional stresses will be incurred; a design showing the roadway in relation to the pipeline; and method statements to be agreed with SGN before it goes ahead. Crossings need to be kept to a minimum. This pipeline is of prime importance to the gas supplies of this area. Should any work be contemplated it is essential that you comply with the restrictions detailed below and in the document SGN/SP/SSW22 in order to protect our plant and equipment and for the safety of your own operatives. 1) No mechanical excavation is allowed within 3 metres either side of pipeline. 2) No plant or storage of equipment shall be made within any easement strip. 3) If any metallic pipes or cables are being laid in proximity to gas pipelines then interference testing will be required, the cost of which to be borne by the promoter of the works. A minimum clearance of 600mm is required. 4) All precautions stated in publication SGN/SP/SSW22 (Safe Working in the Vicinity of High Pressure Gas Pipelines) shall be fully complied with in all respects. Acceptance of SSW22 shall be acknowledged by the responsible site person signing and returning the form Appendix A (back page) to the SGN representative contacted in (7). 5) No thrust boring shall take place within three metres of the pipeline. 6) All planting within the easement strip should comply with “Notes for Guidance on Tree Proximity”. 7) Before commencing work on site you must contact our Pipeline Maintenance Section on 0141 4184093 at least three days before work commences. A Southern Gas Networks representative will then contact you to arrange to visit site. Details of working near to high-pressure gas pipelines can then be discussed. 8) Pipeline sections that are planned and agreed by SGN to be permanently covered (i.e. by road surface) will require a coating survey. SGN will repair any indicated coating defects free of charge. The survey costs will be borne by the promoter of the works. Prior to any surface cover cathodic protection coupons and reference cells will require installation at no cost to SGN.
9) This pipeline is cathodically protected and as such has test cables located in surface boxes, were these to be lost through this work we would look to you for remedial action at no cost to SGN. 10) Intrusive construction methods will require an agreed method statement prior to work starting. 11) Please ensure these conditions, together with any relevant drawings are forwarded for use by the construction personnel of your works. 12) Any extended period of SGN site supervision may incur charges to you. These will be charged based on visiting times, materials and occurrences. You will be informed when these come into effect and be invoiced direct.
If you require anything further please let me know. Regards,
From: Tony Godwin/SDEP/SGN To: Simon Joyce/HOR/SGN@SGN Cc: Dave Cliffe/SDEP/SGN@SGN Date: 30/04/2014 14:52 Subject: TPES-SO-2085 Fw: HIDE REPORT SO/0025854 - Fw: Ratton Primary School/Cavendish School - Plant Enquiry
Hi Simon, you may want to look at this enquiry. Tony ----- Forwarded by Tony Godwin/SDEP/SGN on 30/04/2014 14:49 ----- From: Plant Location/SGN To: Tony Godwin/SDEP/SGN@SGN Date: 29/04/2014 10:55 Subject: HIDE REPORT SO/0025854 - Fw: Ratton Primary School/Cavendish School - Plant Enquiry Sent by: Lesley Phillips
82 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
15 QUANTITY SURVEYOR’S REPORT
83ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
East Sussex County Council
Primary Places - Inflation Forecast
New Cavendish Ratton
Primary Schools
1.1 Inflation - New Cavendish & Ratton Primary Schools for Completion by 1st Quater 2016
Commence RIBA Stage C (New Work Stage 2) 2Q 2014
Main Contract Commencement On Site 2Q 2015
1Q 2016
Current (Baseline)
2Q 2014
BCIS TPI 243.00 252.00 3.7% 258.00 6.2%
PUBSEC 186.00 194.00 4.3% 198.00 6.5%
Sweett Group 100.00 103.50 3.5% 105.25 5.3%
External QS Average 85.2 88.6 4.0% 90.50 6.2%
Combined Average 3.9% 6.0%
The above suggests forecast tender price inflation from current price levels (2Q 2014) to start on site (2Q 2015) of between 3.5 - 4.3%.
1.2 Averaged Project Inflation Factors
Recommended Project Inflation Factor 3.9%
Likley "worst case" Inflation Factor 7.0%
For the purposes of reporting it is suggested that the expected inflation factor to be used is 3.9% but that as a "forecast" this may rise to up
to 7% if inflationary pressures continue to increase.
The following information is specific to Cavendish and Ratton Primary Schools and comprises of forecast inflation factors to be used in conjunction with the
project Cost Plans and Programme.
Increases in construction activity, a renewed economic outlook and a general increase in new orders has led to inflationary tender prices from 3Q 2013. Thus
forecast tender prices are expected to continue to rise over forthcoming years.
Should the projects utilise "modular construction" then additional factors may be encountered due to the current presures within this sector of the industry.
Particularly relating to programes completing for the start of the school year (September) and early placing of orders with these specialsts is recommended to
limit any potential additional inflationary factors.
In assessing an inflation allowance a range of published indices have been consulted together with Sweett Group's internal assessments and that of other cost
management organisations.
Project Milestones
Start on Site Mid Point on Site
2Q 2015 4Q 2015
Completion of Construction works (as programme)
Job no 107902 - ESCC Page 1
Issue Date: 24/04/2014
Philip Woods
Associate Director
Sweett Group 60 Gray's Inn Rd London WC1X8AQ UNITED KINGDOM T +44 20 7061 9205 F +44 20 7430 0603 M +44 7810 551 128 E [email protected] www.sweettgroup.com
America • Europe • Middle East & Africa • India • Asia Pacific
Please don't print this e-mail unless you really need to.
The information contained in this e-mail is confidential and may be legally privileged. It is intended solely for use by [email protected] and others authorised to receive it. If you have received this e-mail in error, any disclosure, copying, distribution, or action taken in reliance, of the contents of this e-mail is strictly prohibited and may be unlawful. Whilst we take reasonable precautions to ensure that e-mails have been swept for viruses, we do not accept any liability as a result of the transmission or interception of this e-mail and advise you carry out your own virus checks. Sweett (UK) Limited (no. 6324201) Registered in England and Wales at 60 Gray’s Inn Road, London, WC1X 8AQ.
At this Feasibility stage, Sweett’s estimates of full project cost for the three options exceed the ESCC budget of £7 - £8M.
Attention will need to be paid to this forecast overspend on the following design development stages to identify more accurately the cost elements and how savings may be effected.
As the project plans are developed, the cost estimating will identify separately the capital expenditure for Early Years, primary and Sixth Form Centre provision. (Sixth Form Centre expenditure is to be met by Cavendish School).
Below is a summary by Philip Woods, Associate Director at Sweet.
84 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
16NEXT STEPS
85ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
NEXT STEPS
1. Commission high level highways report to outline key issues of proposed site.
2. As a follow up to Sport England engagement, survey local sports provision and analyse need for regeneration of the sports centre on Cavendish site.
3. Agree preferred option with stakeholders and develop design appropriately.
4. Develop cost plan taking due account of preliminary budget overrun at this stage
5. ESCC sign-off of Feasibility
KEY ISSUES INCLUDE -
• HIGHWAYS
• PLANNING
• ACOUSTICS
• GROUND CONDITIONS
• ECOLOGY / TREES
• SURVEYS
86 ESCC - CAVENDISH 2FE PRIMARY SCHOOL | FEASIBILITY REPORT | ECE ARCHITECTURE | MAY 2014
London Office Unit 1 West, Coate House, 3 Coate Street, London E2 9AG Tel +44 (0) 20 7729 5505Sussex Office Brooklyn Chambers, 11 Goring Road, Worthing Tel +44 (0) 1903 248777 [email protected] www.ecearchitecture.com