feasibility assessment: proposed b.c. lng facilities and renewable power

42
1 Proposed British Columbia LNG Facilities and Renewable Power Feasibility Assessment May 13, 2014 Steve Davis & Associates Ltd.

Upload: clean-energy-canada

Post on 02-Jul-2015

1.252 views

Category:

Engineering


5 download

DESCRIPTION

Navius Research Inc. and Steve Davis & Associates produced a conceptual design for powering the LNG terminal on the North Coast that would maximize renewables at its production facility and do so reliably, affordably and on schedule—using established commercial technologies. Further, doing so reduces that plant’s carbon pollution by 45 percent, its air emissions - nitrogen oxides - by 70 percent and increases local permanent jobs by 40 percent. The cost for all these benefits? A 1 percent increase in projected sales price of the LNG.

TRANSCRIPT

Page 1: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

1

Proposed British Columbia

LNG Facilities and

Renewable Power

Feasibility Assessment

May 13, 2014

Steve Davis & Associates Ltd.

Page 2: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

OUTLINEI. Basic parameters for powering the Liquefied

Natural Gas (LNG) facility

A. Sizing, assumptions and objectives

B. Scenarios: D-Drive, Ancillary Renewables-Grid and

Maximum Renewables

II. Maximum Renewables Scenario

A. Description of Power Facilities

B. Schedule

C. Reliability

• Power availability, by fuel, as wind generation changes

III. Summary of Scenario Comparisons

IV. APPENDIX: Reference Slides

2

Page 3: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

I. Basic Powering Parameters• Single LNG Facility

‒Producing 22 MTPA (Million Tonnes per Annum)

• 1,000 MW power requirement (at full build out)

‒Compression = 800 MW

‒Ancillary = 200 MW

‒Built in two phases; 500 MW each

• Power Scenarios Considerations

Designs proposed by LNG proponents

Designs by recent and proposed LNG – e.g. No shared facilities

Government and BC Hydro goals & constraints– e.g. No increase to other BC Hydro ratepayers

3

Page 4: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Design Objectives1. Maximize renewable generation

2. Meet LNG industry requirements on:

Reliability and

Schedule – meet terminal start-up date

3. Reduce Greenhouse Gas (GHG) emissions

4. Reduce local emissions (i.e. NOx)

5. Provide Legacy of power infrastructure

6. Avoid BC Hydro twinning transmission lines

7. Create permanent local jobs

8. Minimal increase in cost of LNG produced4

Page 5: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

3 Scenarios

1. Direct Drive (D-Drive)

– Single cycle gas turbines (SCGT) directly drive

Compression and power Ancillaries

2. Ancillary Renewables - Grid– Highly efficient SCGT direct drive for Compression

– Ancillary powered by Grid connected to wind

3. Maximum Renewables (Max RE)

– Combined cycle gas turbine (CCGT), Reciprocating

Engines (Recips), Boil-off-gas (BoG) turbines and

wind power produce electricity to drive Compression

– Ancillary powered by Grid connected to wind

5

Page 6: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Power #s for 3 Scenarios

6

Page 7: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

D-Drive vs Max Renewables

7

Page 8: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Ancillary RE-Grid vs Max

Renewables

8

Page 9: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

II. Max. Renewables Scenario

• 1,000 MW power requirement for E-LNG

Built in two phases of 500 MW each

Compression = 800 MW. Ancillary = 200 MW

• Ancillary load is driven by the grid connected

to local wind project

• Compression uses electrical motors that can

be fully driven by gas power

Phase 1 is CCGT; Phase 2 adds Recips.

Wind output is used to reduce generation from

gas engines and power ancillary9

Page 10: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Facilities Map

10

Wind FarmReciprocating

Gas Engines

LNG

Facility

Ancillary

CCGT

Grid

LNG Facility

Compression

Boil Off Gas

Gas Turbine

Maximum RE

Page 11: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Facility Sizes*:

11

Wind FarmReciprocating

Gas Engines

LNG

Facility

Ancillary

CCGT

Grid

LNG Facility

Compression

Boil Off Gas

Gas Turbine

MW

783

MW

400

MW

40

MW

360

MW

200

MW

200

MW

800

MW

* At Full Build-Out

Page 12: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Energy:

12

Wind FarmReciprocating

Gas Engines

LNG

Facility

Ancillary

CCGT

Grid

LNG Facility

Compression

Boil Off Gas

Gas Turbine

TWh/y

ear

2.2 1.6 0.3 3.0

1.7

1.8

7.0

Result = 44% Renewables

Page 13: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Power Cost:

13

Wind FarmReciprocating

Gas Engines

LNG

Facility

Ancillary

CCGT

Grid

LNG Facility

Compression

Boil Off Gas

Gas Turbine

$ per

MWh

$144 $86 $72

$62

$95

$108

Page 14: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Two

Gas

Turbines

@ 120 MW

each

One

Steam

Turbine

@ 120 MW

14 2-on-1 CCGT Totaling 360 MW

Page 15: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Reciprocating Gas Engines

15

Twenty 18 MW engines + One 40 MW Steam Turbine = 400 MW

Photo of 20 engines at 231 MW wind-chaser project near Denver

Page 16: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

RECIPROCATING ENGINES

Excellent Wind Chasers

• Very fast start and high ramp rates

• Modular (e.g. 20 engines at 18 MW each),

yields efficient part-load operation:

– Individual units can be turned off and on,

rather than turned down.

• Combined-cycle increases efficiency

• High reliability, especially w. multiple units

• NOx can be lower than gas turbines

16

Page 17: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Power Availability

17

0

200

400

600

800

1,000

1,200

0 10 20 30 40 50 60 70 80 90 100

MW

Ava

iab

le

% of hours each year

Power Available by Source - Maximum Renewables, Full build-out

CCGT

Wind

Grid

Combined Cycle

Recips.

BoG Turbine

Page 18: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

B. Schedule

Maximum Renewables Scenario

• Planned Schedule and Phasing

• Upsetting Events - Delay in:

CCGT or Reciprocating Engines

Transmission

Wind Energy

Other LNG facility

18STEVE DAVIS & ASSOCIATES LTD.

STEVE DAVIS & ASSOCIATES LTD.

Page 19: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Current Experience

• There are many examples of CCGTs,

SCGTs and Reciprocating Engines

Lead time ~ 5 years*

• B.C. has four operating wind farms:

Lead time ~ 5 - 6 years*

• Transmission

Capacity upgrades to Prince Rupert or Kitimat

are straightforward and already underway

Transmission lines from wind farms

19* Source: BC Hydro 2013 Resource Options Update Report

Page 20: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Power Schedule and Phasing

20

0

500

1000

1500

2000

2500

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

MW

In

sta

lled

CCGT

BoG Turbine

Grid, phase 1

Grid, phase 2

Combined Cycle Recips.Wind 1

Wind phase 1

Wind 2

Compression Load, Phase 2

Total Load, Phase 2

Total Load, Phase 1

Compression Load, Phase 1

Phase 1 on-line in 2019

Phase 2 on-line in 2022

Page 21: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Upset Event:

CCGT or Recips. are Late

• Are generation plants more likely than

D-Drive to be delayed?

Generation plants have more flexible siting.

Air permitting should be quicker in a

chosen location than in a required location.

Separate target to oppose, but supports

lower environmental impacts.

• Plants are dedicated to individual facility

21

Page 22: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Upset Event:

Transmission Upgrades Late

• Twinned line to coast is not needed

• Wind farm or interconnection late?

Run on grid plus thermal generation

22

Page 23: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Upset Event:

Other LNG Facility is Late

• Has no bearing on power supply

• No generation and transmission is

contingent on multiple facilities

23

Page 24: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

C. RELIABILITY

Max Renewables Scenario

• Statistics at steady state operation

Current use: familiarity and reliability

Availability and efficiency

Redundancy

• Responses to upsetting events

Wind variation

Transmission outage

24STEVE DAVIS & ASSOCIATES LTD.

STEVE DAVIS & ASSOCIATES LTD.

Page 25: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Current Use• Unfamiliar?

Snohvit E-LNG plant: Operating since 2007

Freeport E-LNG plant: Under-construction

Woodfibre LNG application to NEB involves E-LNG

CCGT are common technology

Global capacity of large recips.: 55GW+ in 2013*

• Unreliable? Initial Snohvit problems explained and overcome

‒ Joint owner, GDF Suez, proposes E-LNG design on next project

Shell/Siemens report*: higher efficiency, lower costs

ABB report*: faster delivery, lower downtime

25STEVE DAVIS & ASSOCIATES LTD.

STEVE DAVIS & ASSOCIATES LTD. * See Appendix G for Reference Sources

Page 26: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Availability and Efficiency

• CCGT (phase 2)

Full output for over 75% of time

Never less than 60% output

94% avg. utilization: high efficiency

• Combined cycle reciprocating engines

Modular: reliable and no penalty for part load

operation

26STEVE DAVIS & ASSOCIATES LTD.

STEVE DAVIS & ASSOCIATES LTD.

Page 27: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Redundancy

• Different levels of redundancy are

possible

• All scenarios considered have same

amount of redundancy:

allows apples-to-apples comparison

27STEVE DAVIS & ASSOCIATES LTD.

STEVE DAVIS & ASSOCIATES LTD.

Page 28: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Upset Event:

Key Points- Wind Variation• When no wind:

CCGT and reciprocating engines at 100%

• When full wind:

CCGT at 60% output, recips. are idled

• When wind ramps up or down

Use reciprocating engines to follow wind

Small scale battery storage (e.g. GE’s

Brilliant Platform) creates smooth power to

follow with 30 minute foresight

28STEVE DAVIS & ASSOCIATES LTD.

STEVE DAVIS & ASSOCIATES LTD.

Page 29: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Partial Wind to No Wind

29

0

200

400

600

800

1,000

1,200

0 10 20 30 40 50 60 70 80 90 100

MW

ava

iala

ble

% of hours each year

Power Available by Source - Maximum Renewables, Phase 2

CCGT

Wind

Grid

Combined Cycle

Recips.

BoG Turbine

Full Wind No Wind

Recips: 90 MW to 400 MW in 30 seconds

Wind: At worst, would drop in 15-30 minutes

Page 30: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Full Wind to No Wind

30

0

200

400

600

800

1,000

1,200

0 10 20 30 40 50 60 70 80 90 100

MW

ava

iala

ble

% of hours each year

Power Available by Source - Maximum Renewables, Phase 2

CCGT

Wind

Grid

Combined Cycle

Recips.

BoG Turbine

Full Wind No Wind

CCGT: 216 MW to 360 MW in 2 minutes (75 MW/min)

Recips: 0 MW to 400 MW in 2-5 minutes (hot start)

Page 31: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Upset Event:

Transmission Failure

• Only ancillary load is powered from grid

• Frequent short duration (e.g. lightning

strikes) outages won’t affect liquefaction

• Transmission from wind farms is new: build

with insulation

31STEVE DAVIS & ASSOCIATES LTD.

STEVE DAVIS & ASSOCIATES LTD.

Page 32: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

III.a Summary: Max RE vs D-Drive

• Increase Renewables from 0% to 44%

Increase wind from 0 MW to 783 MW, and

Reduce thermal generation by replacing SCGTs with

wind-chasing Reciprocating Engines and BoG Turbines.

• Maintain LNG Reliability & Schedule requirements

• Increase local permanent jobs by 43%

• Build $2.9 billion wind power legacy

• Power & Reduce GHG intensity by 46%

Reduce NOx by 68%

• Increase Power Cost by 19%

• Increase LNG Sales Price by 1.1%32

Page 33: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

III.b Summary: Max RE vs Ancillary Grid

• Increase Renewables from 20% to 44%

Increase wind from 630 MW to 783 MW, and

Reduce thermal generation by replacing half the SCGTs with

wind-chasing Recip. Engines and BoG Turbines.

• Maintain LNG Reliability & Schedule requirements

• Increase local permanent jobs by 2%

• Increase wind power/transmission investment 26%

Reduce GHG intensity by 24%

Reduce NOx by 38%

• Increase Power Cost by 15%

• Increase LNG Sales Price by 0.9%33

Page 34: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

IV. APPENDIX

A. Facilities Map: Direct Drive Scenario

B. Facilities Map: Ancillary RE – Grid Scenario

C. Capex for Maximum Renewables Scenario

D. Comparison Table: 3 Scenarios

E. Summary Comparison Table: D-Drive vs.

Ancillary RE – Grid

F. Key Assumptions in Financial Model

G. Reference Sources

34

Page 35: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Appendix A Facilities Map:

Ancillary Renewables - Grid

35

Wind Farm

LNG

Facility

Ancillary

SCGT

Grid

LNG Facility

Compression

Page 36: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Appendix B

Facilities Map: Direct Drive

36

LNG

Facility

Ancillary

SCGT

LNG Facility

Compression

Boil Off Gas

Gas Turbine

Page 37: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Appendix C Capex:

37

Wind FarmReciprocating

Gas Engines

LNG

Facility

Ancillary

CCGT

Grid

LNG Facility

Compression

Boil Off Gas

Gas Turbine

Maximum Renewables

2.70

$ BILLION

0.45 0.03 0.41

0.198

Page 38: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Summary Table38 Appendix D

Page 39: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

D-Drive vs Ancillary RE - Grid

39

Appendix E

Page 40: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Modeling Assumptions

40

Appendix F

Page 41: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Reference Sources for statements on slide 9

• Global capacity of large scale recips 55 GW

– Wartsila Power Plants References see:

www.wartsila.com/en/power-plants/references

• Shell/Siemens report:

– All electric driven Refrigeration Compressors in LNG Plants offer

advantages.

– By Fritz Kleiner, Siemens AG and Steve Kauffman, Shell

Development Ppy. Ltd., presented at GasTech2005

• ABB report:

– All electric LNG plants; Better, safer, more reliable – and

profitable.

– By Havard Devold, Tom Nestli & John Hurter ©2006 ABB

Process Automation Oil and Gas 41

Appendix G

Page 42: Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power

Navius Research Inc.

[email protected]

604.683.1452

Steve Davis & Associates Consulting Ltd.

[email protected]

604-926-8352

42