fdep springs initiative fy2018 final evaluations · springs - citrus county awt upgrades to the...
TRANSCRIPT
FDEP Springs Initiative FY2018 Final Evaluations
Table of Contents
Northern Region Springs Projects - Recommended
P134 - Springs - Citrus County AWT Upgrades to the Brentwood WWTF........................................ 1
P136 - Springs - Citrus Co. Brentwood to Meadowcrest Recl. Water Sys. Interconnection.............. 2
P137 - Springs - Citrus County Northwest Quadrant Sewer Extension............................................. 3
P138 - Springs-City of Brooksville Mtn. Prk Subd. Septic Tanks Abandonment to Cntrl Sewer Sys. 4
P139 - Springs - City of Brooksville Hernando Oaks Golf Course Reclaimed Water........................ 5
P140 - Springs - City of Crystal River Indian Waters Septic-to-Sewer Phase II................................ 6
P142 - Springs - City of Williston Northwood Estates Septic-to-Sewer............................................. 7
P143 - Springs - City of Williston WWTP AWT Upgrade................................................................... 8
P144 - Springs - Marion County Rainbow Springs Central Sewer Feasibility Study......................... 9
Northern Region Springs Projects - Not Recommended
P135 - Springs - Citrus Co. Chassahowitzka to Sugarmill Woods Wastewater Interconnection....... 10
P141 - City of Dunnellon Wastewater Collection SCADA System..................................................... 11
Tampa Bay Region Springs Projects - Recommended
N635 - Restoration-Pasco County Crews Lake Natural Systems Construction Phase..................... 12
P146 - Springs - Pasco Co. Septic Tank Abatement Feasibility Study in the Weeki Wachee Springshed. 13
Risk Level:
Project No. P134
Citrus County
Springs - Citrus County AWT Upgrades to the Brentwood WWTF
Type 2 Multi-Year Contract: No
FY2018
Description
Construction upgrades to the existing Brentwood WWTF to advanced wastewater treatment
standards.
Description:
The contractual Measurable Benefit will be the installation of necessary components for a fully
operational municipal sanitary sewer system that will meet advanced wastewater treatment
standards.
Measurable Benefit:
Total Project Cost: $1,508,000 (Construction only);
Citrus County: $754,000;
District: $0;
FDEP: $754,000.
Costs:
Evaluation
Application Quality: Application included most of the required information identified in the CFI Guidelines.
District PM had to work with the Cooperator to obtain required information.
Medium
The benefit of the project is the reduction of pollutant loads to Kings Bay/Crystal River
springshed, a SWIM priority water body, by an estimated 13,698 lbs/Yr TN. There will
be no monitoring or performance testing requirements.
Project Benefit: High
The $3.67 per pound of total Nitrogen removed is below the average cost of $224/lb of
previously funded stormwater projects.
Cost Effectiveness: High
Past Performance: Based on an assessment of the schedule and budget for the 3 ongoing projects.High
Complementary Efforts: The cooperator has a mandatory sewer connection ordinances, and enforces it.High
Project is not expected to begin until after March 1, 2018.Project Readiness: Low
Strategic Goals
Strategic Goals: High Strategic Initiative - Alternative Water Supplies: Increase development of
alternative sources of water to ensure groundwater and surface water sustainability.
Strategic Initiative - Water Quality Maintenance and Improvement: Develop
and implement programs, projects and regulations to maintain and improve water
quality.
Northern Region Priority: Improve northern coastal spring systems.
Overall Ranking and Recommendation
This project will result in water quality improvements to the Kings Bay/Crystal River springshed,
a SWIM Priority water body. Recommend forwarding project to FDEP for funding consideration
subject to Legislative Appropriation.
Recommended.
Funding
TotalFutureFunding Source Prior FY2018
$0$754,000$0 $754,000Citrus County
$0$754,000$0 $754,000FDEP
Total $0 $1,508,000 $0 $1,508,000
1
Risk Level:
Project No. P136
Citrus County
Springs - Citrus County Brentwood to Meadowcrest Reclaimed Water System
Interconnection
Type 2 Multi-Year Contract: No
FY2018
Description
Construction of a reclaimed waterline to interconnect the Brentwood WWTF to the Meadowcrest
WWTF to increase reclaimed water availability for reuse or recharge.
Description:
The contractual Measureable Benefit will be the construction of approximately 29,000 feet of
reclaimed water line to interconnect the upgraded Brentwood WWTF to the Meadowcrest
WWTF.
Measurable Benefit:
Total Project Cost: $5,260,000 (Construction only)
Citrus County: $2,630,000
District: $0.00
FDEP: $2,630,000
Costs:
Evaluation
Application Quality: Application included most of the required information identified in the CFI Guidelines.
District PM had to work with the Cooperator to obtain remaining information.
Medium
The benefit of this project is the reduction of pollutant loads to the Kings Bay/Crystal
River watershed, a SWIM priority water body, by an estimated 18,797 lbs/yr TN and
the supply of 0.50 MGD of reclaimed water. There will be no monitoring or performance
testing requirements.
Project Benefit: High
$10.52 per gallon per day of capital cost, which is below the $10 to $15 per gallon
average for alternative supplies. The $9.33 per pound of total Nitrogen removed is
below the average cost of $224/lb of previously funded stormwater projects.
Cost Effectiveness: High
Past Performance: Based on an assessment of the schedule and budget for the 3 ongoing project.High
Complementary Efforts: The cooperator has a mandatory sewer connection ordinance, and enforces it.High
Project is ready to begin on or before December 1, 2017.Project Readiness: High
Strategic Goals
Strategic Goals: High Strategic Initiative - Reclaimed Water: Maximize beneficial use of reclaimed
water to offset potable water supplies and restore water levels and natural systems .
Strategic Initiative - Water Quality Maintenance and Improvement: Develop
and implement programs, projects and regulations to maintain and improve water
quality.
Northern Region Priority: Improve northern coastal spring systems.
Northern Region Priority: Ensure long-term sustainable water supply.
Overall Ranking and Recommendation
This project will result in water quality and water quantity improvements to the Kings
Bay/Crystal River springshed, a SWIM Priority water body. Recommend forwarding project to
FDEP for funding consideration subject to Legislative Appropriation .
Recommended.
Funding
TotalFutureFunding Source Prior FY2018
$0$2,630,000$0 $2,630,000FDEP
$0$2,630,000$0 $2,630,000Citrus County
Total $0 $5,260,000 $0 $5,260,000
2
Risk Level:
Project No. P137
Citrus County
Springs - Citrus County Northwest Quadrant Sewer Extension
Type 2 Multi-Year Contract: No
FY2018
Description
Construction of a sewer main expansion located within the Northwest quadrant of Citrus County
primarily serviced by septic systems.This sewer main extension will route up to 2.00 MGD of
wastewater flows at build out to the Meadowcrest WWTF to produce additional high-quality
reclaimed water flows that will in turn be sent to the Duke Energy Crystal River Power Complex.
Description:
The contractual Measurable Benefit will be the construction of approximately 10,300 feet of
sewer main for the purpose of extending the County’s wastewater collection system to the
Northwest quadrant of the County.
Measurable Benefit:
Total Project Cost: $6,000,000 (Construction only)
Citrus County: $3,000,000
District: $0
FDEP: $3,000,000
Costs:
Evaluation
Application Quality: The application included most of the required information identified in the guidleines.
District PM had to work with the cooperator to obtain the remaining required
information.
Medium
The benefit of the project is the reduction of pollutant loads to the Kings Bay/Crystal
River springshed, a SWIM priority water body, by an estimated 87,791 lbs/ yr TN and
the supply of 2.0 MGD of reclaimed water. There will be no monitoring or performance
testing requirements.
Project Benefit: High
The $2.27 per pound of total Nitrogen removed is below the average cost of $224/lb of
previously funded stormwater projects and the $0.62 per gallon of capital cost is below
the $10 to $15 per gallon average for alternative supplies.
Cost Effectiveness: High
Past Performance: Based upon an assessment of the schedule and budget for 3 ongoing projectsHigh
Complementary Efforts: The cooperator has a mandatory sewer connection ordinance and enforces it.High
Project is ready to begin on or before March 1, 2018.Project Readiness: Medium
Strategic Goals
Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop
and implement programs, projects and regulations to maintain and improve water
quality.
Northern Region Priority: Improve northern coastal spring systems.
Overall Ranking and Recommendation
This project will result in water quality and water quantity improvements to the Kings
Bay/Crystal River springshed. a SWIM priority water body. Recommend forwarding project to
FDEP for funding consideration subject to Legislative Appropriation .
Recommended.
Funding
TotalFutureFunding Source Prior FY2018
$0$3,000,000$0 $3,000,000FDEP
$0$3,000,000$0 $3,000,000Citrus County
Total $0 $6,000,000 $0 $6,000,000
3
Risk Level:
Project No. P138
City of Brooksville
Springs - City of Brooksville Mountain Park Subdivision Septic Tanks Abandonment to
Central Sewer System
Type 2 Multi-Year Contract: No
FY2018
Description
Design, permitting and construction to connect existing residential septic tank users in the
Weeki Wachee Springshed to the City of Brooksville wastewater collection system .
Description:
The contractual Measurable Benefit will be the installation of approximately 8,000 linear feet of
sewer line and any necessary components for a fully operational municipal sewer system that
will allow for the connection of up to 64 residences.
Measurable Benefit:
Total project cost: $1,475,000 (Design, permitting and construction)
City of Brooksville: $33,696 (Water hook-up and connection fees)
District: $0
FDEP: $1,441,304
Costs:
Evaluation
Application Quality: Application included the required information identified in the CFI Guidelines.High
The benefit from this water quality project is the reduction of pollutant loads to the
Weeki Wachee Springshed, which is a SWIM Priority water body, by an estimated
1000 lb/yr TN. There will be no monitoring or performance testing requirements.
Project Benefit: High
The $49.17 per pound of total Nitrogen removed is below the average cost of $224/lb of
previously funded stormwater projects.
Cost Effectiveness: High
Past Performance: Based on the cooperator having no ongoing projects with the District they are ranked
high.
High
Complementary Efforts: The City of Brooksville Code of Ordinances Sec. 86-103-- Connection with Sewer
States that, since sewer rates are based on water consumption, connection to the
City's water system shall be required at the same time as connection to the sewer
system is required under this subsection if the City's water system is also available.
High
Project is ready to begin on or before March 1, 2018.Project Readiness: Medium
Strategic Goals
Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop
and implement programs, projects and regulations to maintain and improve water
quality.
Northern Region Priority: Improve northern coastal spring systems.
Overall Ranking and Recommendation
This project will result in water quality improvements to the Weeki Wachee springshed , a SWIM
Priority water body. Recommend forwarding project to FDEP for funding consideration subject to
Legislative Appropriation.
Recommended.
Funding
TotalFutureFunding Source Prior FY2018
$0$33,696$0 $33,696City of Brooksville
$0$1,441,304$0 $1,441,304FDEP
Total $0 $1,475,000 $0 $1,475,000
4
Risk Level:
Project No. P139
City of Brooksville
Springs - City of Brooksville Hernando Oaks Golf Course Reclaimed Water Project
Type 2 Multi-Year Contract: No
FY2018
Description
Design, permitting and construction of reclaimed water transmission mains and other necessary
appertenances to supply Reclaimed Water to Hernando Oaks Golf Course .
Description:
The contractual Measurable Benefit will be the installation of approximately 7,500 feet of
reclaimed water transmission mains, other necessary appurtenances and supply 0.225 MGD of
reclaimed water in the Weeki Wachee Springshed.
Measurable Benefit:
Total Project Cost: $490,000 (Design, permitting and construction)
City of Brooksville: $0
District: $0
FDEP: $490,000
Costs:
Evaluation
Application Quality: Application included the required information identified in the Springs guidelines.High
The benefit from this project is the supply of 0.225 MGD of reclaimed water for
irrigation use within the Weeki Wachee Springshed, a SWIM Priority waterbody. There
will be no monitoring or performance testing requirements.
Project Benefit: High
$2.88 per gallon of capital cost, which is below the $10 to $15 per gallon average for
alternative supplies.
Cost Effectiveness: High
Past Performance: Based on the cooperator having no ongoing projects with the District they are ranked
high.
High
Complementary Efforts: Brooksville reclaimed water system includes metering and incentive based reuse rate
structures for high volume water users and has pro-active reclaimed water expansion
policies which maximize utilization, water resource benefits, and environmental
benefits.
High
Project is ready to begin on or before March 1, 2018. (Pending City's execution of
Customer Supply Agreement with golf course)
Project Readiness: Medium
Strategic Goals
Strategic Goals: High Strategic Initiative - Reclaimed Water: Maximize beneficial use of reclaimed
water to offset potable water supplies and restore water levels and natural systems .
Northern Region Priority: Improve northern coastal spring systems.
Northern Region Priority: Ensure long-term sustainable water supply.
Overall Ranking and Recommendation
This project will result in water quantity improvements to the Weeki Wachee Springshed , a
SWIM priority water body. Recommend forwarding to FDEP for funding consideration provided
cooperator submits executed reuse agreement by April 30, 2017 and subject to Legislative
Appropriation.
Recommended.
Funding
TotalFutureFunding Source Prior FY2018
$0$490,000$0 $490,000FDEP
$0$1$0 $1City of Brooksville
Total $0 $490,001 $0 $490,001
5
Risk Level:
Project No. P140
Crystal River
Springs - City of Crystal River Indian Waters Septic-to-Sewer Phase II
Type 2 Multi-Year Contract: No
FY2018
Description
Design, permitting, and construction of municipal sewer system including connection fees, plant
demolition and tank abandonment, and necessary components. This project will allow for the
connection of private package wastewater package plant(s) and provide City central sewer to
areas currently served by septic systems within the Crystal River springshed.
Description:
The contractual Measurable Benefit will be the installation of approximately 25,000 feet of sewer
line and any necessary components for a fully operational municipal sanitary sewer system that
will allow for the connection of a private package plant and parcels currently on septic system
that will be connected to the City's sewer system.
Measurable Benefit:
Total project cost: $4,000,000 (Design, permitting, construction)
City of Crystal River: $400,000
District: $0
FDEP: $3,600,000
Costs:
Evaluation
Application Quality: Application included most of the required information identified in the CFI guidelines.
District PM had to work with cooperator to obtain remaining required information.
Medium
The benefit of this water quality project is the reduction of pollutant loads to Crystal
River, a SWIM Priority water body, by an estimated 3,803 lbs/yr TN. There will be no
monitoring or performance testing requirements.
Project Benefit: High
The $35 per pound of total Nitrogen removed is below the average cost of $224/lb of
previously funded stormwater projects.
Cost Effectiveness: High
Past Performance: Based on the cooperator having no ongoing projects with the District they are ranked
high.
High
Complementary Efforts: The City has a mandatory connection ordinance in place to ensure homes are
connected to the sewer system.
High
Project is ready to begin on or before March 1, 2018.Project Readiness: Medium
Strategic Goals
Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop
and implement programs, projects and regulations to maintain and improve water
quality.
Northern Region Priority: Improve northern coastal spring systems.
Overall Ranking and Recommendation
This project will result in water quality improvements to the Crystal River/Kings Bay, a SWIM
priority water body. Recommend forwarding to FDEP for funding consideration subject to
Legislative Appropriation.
Recommended.
Funding
TotalFutureFunding Source Prior FY2018
$0$3,600,000$0 $3,600,000FDEP
$0$400,000$0 $400,000Crystal River
Total $0 $4,000,000 $0 $4,000,000
6
Risk Level:
Project No. P142
Williston
Springs - City of Williston Northwood Estates Septic-to-Sewer
Type 2 Multi-Year Contract: No
FY2018
Description
Design, permitting, and construction of a municipal sanitary sewer system for Northwood
Estates. This includes the sewer pipe to connect septic system users to the City's central
sewer system and all necessary components. This project will provide the infrastructure to allow
for the connection of approximately 35 septic tanks and allow for additional infrastructure
installation and septic removal in the future.
Description:
The contractual Measurable Benefit will be the installation of approximately 4,300 feet of sewer
line and any necessary components for a fully operational municipal sanitary sewer system that
will allow for the connection of approximately 35 residences.
Measurable Benefit:
Total project cost: $1,794,000 (Design, permitting, construction)
City of Williston: $21,000
District: $0
FDEP: $1,773,000
Costs:
Evaluation
Application Quality: Application included most of the required information identified in the CFI guidelines.
District PM had to work with cooperator to obtain remaining required information.
Medium
The benefit of this water quality project is the reduction of pollutant loads to Rainbow
Springs, a SWIM Priority water body, by an estimated 761 lbs/yr TN. There will be no
monitoring or performance testing requirements.
Project Benefit: High
The $79 per pound of total Nitrogen removed is below the average cost of $224/lb of
previously funded stormwater projects.
Cost Effectiveness: High
Past Performance: Based on the cooperator having no ongoing projects with the District they are ranked
high.
High
Complementary Efforts: Northwood Estates residents support the effort and the City Council passed and
adopted a formal resolution also in support of this project.
Medium
Project is ready to begin on or before December 1, 2017.Project Readiness: High
Strategic Goals
Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop
and implement programs, projects and regulations to maintain and improve water
quality.
Northern Region Priority: Improve northern coastal spring systems.
Overall Ranking and Recommendation
This project will result in water quality improvements to Rainbow Springs, a SWIM Priority water
body. Recommend forwarding to FDEP for funding consideration subject to Legislative
Appropriation.
Recommended.
Funding
TotalFutureFunding Source Prior FY2018
$0$21,000$0 $21,000Williston
$0$1,773,000$0 $1,773,000FDEP
Total $0 $1,794,000 $0 $1,794,000
7
Risk Level:
Project No. P143
Williston
Springs - City of Williston WWTP AWT Upgrade
Type 2 Multi-Year Contract: No
FY2018
Description
Design, permitting, and construction to upgrade the City's existing wastewater treatment plant
(WWTP) to advanced wastewater treatment standards.
Description:
The contractual Measurable Benefit will be the installation of necessary components to allow for
a fully operational municipal sanitary sewer system to meet advanced wastewater treatment
standards
Measurable Benefit:
Total project cost: $3,021,000 (Design, permitting, construction)
City of Williston: $0
District: $0
FDEP: $3,021,000
Costs:
Evaluation
Application Quality: Application included most of the required information identified in the CFI guidelines.
District PM had to work with cooperator to obtain remaining required information.
Medium
The benefit of this water quality project is the reduction of pollutant loads to Rainbow
Springs, a SWIM Priority water body, by an estimated 3,082 lbs/yr TN. There will be
no monitoring or performance testing requirements.
Project Benefit: High
The $33 per pound of total Nitrogen removed is below the average cost of $224/lb of
previously funded stormwater projects.
Cost Effectiveness: High
Past Performance: Based on the cooperator having no ongoing projects with the District they are ranked
high.
High
Complementary Efforts: City Council is adopting a formal resolution in support of this project.Medium
Project is ready to begin on or before December 1, 2017.Project Readiness: High
Strategic Goals
Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop
and implement programs, projects and regulations to maintain and improve water
quality.
Northern Region Priority: Improve northern coastal spring systems.
Overall Ranking and Recommendation
This project will result in water quality improvements to Rainbow Springs, a SWIM Priority water
body. Recommend forwarding to FDEP for funding consideration subject to Legislative
Appropriation.
Recommended.
Funding
TotalFutureFunding Source Prior FY2018
$0$1$0 $1Williston
$0$3,021,000$0 $3,021,000FDEP
Total $0 $3,021,001 $0 $3,021,001
8
Risk Level:
Project No. P144
Marion County
Springs - Marion County Rainbow Springs Central Sewer Feasibility Study
Type 2 Multi-Year Contract: No
FY2018
Description
This project is for a feasibility study to investigate and determine the most feasible options to
reduce septic tanks and achieve central wastewater collection and treatment for properties in the
Rainbow Springs/River Springshed.
Description:
The contractual Measurable Benefit will be a feasibility study that identifies potential projects
and associated costs to convert from OSTDS to a central sewer system within a springs
protection zone in the Rainbow Springs/River Springshed, a Class I Outstanding Florida Water
System, first magnitude spring system, and SWIM priority waterbody.
Measurable Benefit:
Total project cost: $150,000 (Feasibility study)
Marion County cost: $20,000
District cost: $0
FDEP cost: $130,000
Costs:
Evaluation
Application Quality: Application included all of the required information identified in the CFI guidelines.High
The benefit of this water quality project will be the identification of projects for
implementation of reducing OSTDS in the Rainbow River Springshed, a SWIM priority
water body. If a central sewer program is fully implemented, approximately 250,000
lbs/yr of total nitrogen could be eliminated from the springshed.
Project Benefit: High
Study costs are comparable to similar projects such as N771 (Hernando County
Advanced Wastewater Treatment Master Plan Feasibility Study).
Cost Effectiveness: High
Past Performance: Based on an assessment of the schedule and budget for the two ongoing projects.High
Complementary Efforts: Marion County has a Spring Protection Resolution and comprehensive environmental
program. The County also has several ordinances that restrict irrigation, fertilizer use,
and OSTDS installation.
High
Project is ready to begin on or before March 1, 2018.Project Readiness: Medium
Strategic Goals
Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop
and implement programs, projects and regulations to maintain and improve water
quality.
Northern Region Priority: Improve northern coastal spring systems.
Overall Ranking and Recommendation
This project is a study to take septic tanks offline, which would improve springshed water quality
for Rainbow Springs and River, a SWIM priority waterbody and Outstanding Florida Water
System. Recommend forwarding to FDEP for funding consideration subject to Legislative
Appropriation.
Recommended.
Funding
TotalFutureFunding Source Prior FY2018
$0$20,000$0 $20,000Marion County
$0$130,000$0 $130,000FDEP
Total $0 $150,000 $0 $150,000
9
Risk Level:
Project No. P135
Citrus County
Springs - Citrus County Chassahowitzka to Sugarmill Woods Wastewater
Interconnection
Type 2 Multi-Year Contract: No
FY2018
Description
Design, permitting and construction of a force main on County Road 480 to allow diversion of
wastewater currently treated at the Meadowcrest Wastewater Treatment Plant to the Sugarmill
Woods Wastewater Treatment Plant. Allows decrease in pumping costs due to decrease in
distance and operational flexibility between the two plants.
Description:
The contractual Measurable Benefit will be the installation of approximately 16,645 linear feet of
sewer line and any necessary components for a fully operational municipal sanitary sewer
system that will result in optimizing flow to Sugarmill Woods Wastewater Treatment Plant .
Measurable Benefit:
Total project cost: $1,000,000 (Design, permitting and construction)
Citrus County: $500,000
District: $0
FDEP: $500,000
Costs:
Evaluation
Application Quality: Application included most of the required information identified in the CFI guidelines.
District PM had to work with cooperator to obtain remaining required information.
Medium
Low or no resource benefit expected.Project Benefit: Low
Project is not cost effective, due to no Resource Benefit to compare it to.Cost Effectiveness: Low
Past Performance: Based on an assessment of schedule and budget of 3 ongoing projects.High
Complementary Efforts: The cooperator has a mandatory sewer connection ordinance and enforces it.High
Project is ready to begin on or before October 1, 2017.Project Readiness: High
Strategic Goals
Strategic Goals: Low Strategic Initiative: None
Region Priority: None
Overall Ranking and Recommendation
This project will not result in water quality improvements to the Chassahowitzka Springshed, a
SWIM priority water body. Do not recommend forwarding to FDEP for funding consideration
subject to Legislative Appropriation.
Not recommended.
Funding
TotalFutureFunding Source Prior FY2018
$0$500,000$0 $500,000Citrus County
$0$500,000$0 $500,000FDEP
Total $0 $1,000,000 $0 $1,000,000
10
Risk Level:
Project No. P141
Dunnellon
City of Dunnellon Wastewater Collection SCADA System
Type 2 Multi-Year Contract: No
FY2018
Description
Install supervisory control and data acquisition(SCADA) system at three wastewater treatment
plants and 34 wastewater lift stations to allow continuous electronic monitoring of sanitary flows
to minimize overflows.
Description:
The Contractual Measurable benefit will be installation of a complete SCADA system for the
Dunnellon wastewater collection and treatment system.
Measurable Benefit:
Total Project Cost: $530,000, design, permitting & construction
City of Dunnellon: $ 53,000
District: $0
FDEP: $477,000
Costs:
Evaluation
Application Quality: Application included most of the required information identified in the CFI Guidelines.
District PM/CM had to work with cooperator to obtain remianing information.
Medium
Low or no resource benefit expected.Project Benefit: Low
Project is not cost effective, due to no Resource Benefit to compare to.Cost Effectiveness: Low
Past Performance: Based on an assessment of one FY2016 project.Medium
Complementary Efforts: The City has extended sewer services to replace septic tank systems in a number of
low areas. Lift stations constructed as part of that septic tank elimination effort would
be improved with the completion of the proposed SCADA project .
Low
Project is not expected to begin until after March 1st of the fiscal year the funding is
being requested.
Project Readiness: Low
Strategic Goals
Strategic Goals: Low
Overall Ranking and Recommendation
This project will not result in measurable water quality improvements. Do not recommend
forwarding to FDEP for funding consideration subject to Legislative Appropriation
Not recommended.
Funding
TotalFutureFunding Source Prior FY2018
$0$477,000$0 $477,000FDEP
$0$53,000$0 $53,000City of Dunnellon
Total $0 $530,000 $0 $530,000
11
Risk Level:
Project No. N635
Pasco County
Restoration-Pasco County Crews Lake Natural Systems Construction Phase
Type 2 Multi-Year Contract: No
FY2018
Description
Construction of infrastructure to provide reclaimed water to restore approximately 200 acres of
wetlands in and adjacent to Crews Lake. The FY18 funds are requested to complete
construction. The FY16 funds were budgeted to complete third party preview, final design and
permitting services. The FY15 funds were budgeted for 30% design, environmental monitoring,
and permitting services. This project has a conceptual construction estimate greater than $5
million dollars and the District is requiring a third party review of 30% design plans to confirm
construction costs and resource benefits. A feasibility study was completed by Pasco County in
2011.
Description:
The contractual Measurable Benefit will be the enhancement and restoration of approximately
200 acres of freshwater wetlands.
Measurable Benefit:
Total project cost $8,497,770 (environmental monitoring, design and permitting, third party
review, and construction).
Pasco County $2,124,443
District $2,124,442 with $365,885 budgeted in previous years, $1,758,557 requested for FY2018.
FDEP $4,248,885
Costs:
Evaluation
Application Quality: Application included all the required information identified in the CFI GuidelinesHigh
The benefit of this project is the reduction of pollutant loads to the Upper Floridan
Aquifer by an estimated 53,272 lbs/year TN and will create and enhance an area of
freshwater wetlands using reclaimed water.
Project Benefit: High
$2.36 per gallon of capital cost, which is below the $10 to $15 per gallon average for
alternative supplies. The $77.54 per pound of total Nitrogen removed is below the
average cost $224/lb and the $42,489 per acre restored is below the average cost of
$53,326.
Cost Effectiveness: High
Past Performance: Based on an assessment of the schedule and budget for the 12 ongoing project.High
Complementary Efforts: The County has an active environmentally sensitive land purchase program and
maintains nature parks and open spaces within the park system. The County operates
Adopt-a-Pond and Adopt-a-Road programs. Additionally, Pasco County has an active
stormwater utility that collects fees.
High
Project is ready to begin on or before December 1, 2017.Project Readiness: High
Strategic Goals
Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop
and implement programs, projects and regulations to maintain and improve water
quality.
Strategic Initiative - Conservation and Restoration: Identify critical
environmentally sensitive ecosystems and implement plans for protection or
restoration.
Northern Region Priority: Improve northern coastal spring systems.
Overall Ranking and Recommendation
This project will result in water quality and natural systems improvements to the combined
Aripeka/Weeki Wachee BMAP area. Recommend forwarding to FDEP for funding consideration
subject to Legislative Appropriation.
Recommended.
Funding
TotalFutureFunding Source Prior FY2018
$0$1,758,558$365,885 $2,124,443Pasco County
$0$1,758,557$365,885 $2,124,442District
$0$4,248,885$0 $4,248,885FDEP
Total $731,770 $7,766,000 $0 $8,497,770
12
Risk Level:
Project No. P146
Pasco County
Springs - Pasco County Septic Tank Abatement Feasibility Study in the Weeki Wachee
Springshed
Type 2 Multi-Year Contract: No
FY2018
Description
Feasibility study on the sewer system expansions necessary to take 3,000 residential septic
tanks offline in the Weeki Wachee Springshed.
Description:
The contractual Measurable Benefit will include the completion of a feasibility study that
identifies projects to convert from septic systems to a central sewer system within the Weeki
Wachee Springshed.
Measurable Benefit:
Total project cost: $500,000 (Feasibility study)
Pasco County: $250,000
District: $0
FDEP: $250,000 requested in FY18, and $59,550,000 anticipated to be requested in future
years. The conceptual construction cost estimate is $119,100,000.
Costs:
Evaluation
Application Quality: Application included most of the required information identified in the CFI guidelines.
District staff had to work with cooperator to obtain remaining required information .
Medium
The benefit of this water quality project will be the identification of projects for
implementation of reducing septic systems in the Weeki Wachee River springshed , a
SWIM priority water body, and Aripeka Springshed. If a central sewer program is fully
implemented, approximately 47,000 lbs/yr of total nitrogen could be eliminated from
the springshed.
Project Benefit: High
Study costs are high when compared to similar projects such as N771 (Hernando
County Advanced Wastewater Treatment Master Plan Feasibility Study).
Cost Effectiveness: Low
Past Performance: Based on an assessment of schedule and budget for 12 ongoing projects.High
Complementary Efforts: Pasco County currently has a reclaimed water system includes metering and incentive
based reuse rate structure for high volume water users and has pro-active reclaimed
water expansion policies which maximize utilization, water resource benefits and
environmental benefits.
High
Project is ready to begin on or before December 1, 2017.Project Readiness: High
Strategic Goals
Strategic Goals: High Strategic Initiative - Water Quality Maintenance and Improvement: Develop
and implement programs, projects and regulations to maintain and improve water
quality.
Northern Region Priority: Improve northern coastal spring systems.
Overall Ranking and Recommendation
This project is a study to take septic tanks offline, which would improve springshed water quality
for the Weeki Wachee River, a SWIM priority waterbody and Outstanding Florida Water
System, and the Aripeka springshed. Recommend forwarding to FDEP for funding consideration
subject to Legislative Appropriation.
Recommended.
Funding
TotalFutureFunding Source Prior FY2018
$0$250,000$0 $250,000Pasco County
$0$250,000$0 $250,000FDEP
Total $0 $500,000 $0 $500,000
13
The Southwest Florida Water Management District (District) does not discriminate on the basis of disability. This nondiscrimination policy involves every aspect of the District's functions, including access to and participation in the District's programs and activities. Anyone requiring reasonable accommodation as provided for in the Americans with Disabilities Act should contact the District's Human Resources Director, 2379 Broad Street, Brooksville, Florida 34604-6899; 1-352-796-7211 or 1-800-423-1476 (Florida only), extension 4702; TDD (Florida only) 1-800-231-6103; or email to [email protected]