f.brinker, desy, july 17 st 2008 injection to doris and petra fitting the detector in the ip-region...
Post on 21-Dec-2015
217 views
TRANSCRIPT
F.Brinker, DESY, July 17st 2008
•Injection to Doris and Petra
•Fitting the detector in the IP-region
•Radiation issues
•Beam optic, Target cell
•Polarisation
•Work laying ahead
•Operational constrains
•Summary
Injection for DORIS III and PETRA III
Mode 1 (e+) :
DORIS needs new injection every 8 hours
PETRA runs in top up mode – one new bunch every
1-30 seconds, depending on current and lifetime
Mode 2 (e- or e+):
DORIS and PETRA are running in top-up mode
1 bunch to PETRA every 1-30 sec
1 bunch to DORIS every 30-60 sec
450 MeV Linac: Gun delivers electrons, which can be converted to positrons after half of the linac
PIA : accumulation of several linac pulses to increase the bunch current
DESY : 12.5 Hz / 7 GeV Synchrotron – a trigger generator allows the extraction at different energies to either Doris or Petra
Radiation issues:• No of particles lost in 30 days at a lifetime of 0.6 h and a maximum current of
140 mA: ~ 5 E14
• The dominant loss process is energy loss by bremsstrahlung – the particles would be lost mostly in the arc following the target and at the typical aperture limitations (Harwi, BW1, Septum)
• Particles lost in normal synchrotron radiation mode: between 3.3 E14 and 5.9 E14 per year (2003-2007)
• → Radiation dose per year would be doubled
• Radiation shielding is sufficient
• Radiation level at HASYLAB with open beam shutters too high ( from measurements when we had a small vacuum leak ) – but the level should be fine when the shutters are closed
• A significant part would be lost at the wiggler chambers → to protect the permanent magnet material the wiggler gaps should be open and some wigglers have to be moved away from the beam pipe (1-2 days)
doct3w doct3wBlast (symm.point / at 1.2 m) Emittance at 4.5 GeV 465 nm 438 nm Qx 7.17 7.17 Qz 4.77 5.23 βx 26 m 2.4 m 3.2 m βz 9.7 m 1.5 m 2.6 m Dx -1.3 m -0.5 m
Blast IP Additional quad at ± 7m
New optic with a reduced beam size at the IP :
from σx x σz = 3.7 x 0.7 mm2 to 1.1 x 0.3 mm2
Due to the asymmetry of the detector the target cell is not at the IP but at about 0.75 m
Optical functions at the insertion devices and injection are kept nearly unchanged
Target cell• To reach a high gas density the target cell conductivity
should be as small as possible• The conductivity is proportional to the cross section
divided by the inner surface of the tube• Making the target cell the most stringent aperture
limitation in the ring would probably cause background problems and could reduce the beam lifetime
• Present aperture limitations:– Wiggler BW1, βZ=6.7m, vertikal full aperture = 11mm– Absorber for Harwi, βX=15.5m, horizontal full aperture = 60mm
• Corresponding target cell dimensions: 28 x 7 mm2
• I would suggest an elliptical chamber of 30 x 8 mm2
• The conductance would be 75% of that of the present 15mm diameter circular pipe
Polarisation
• For the case that a beam polarisation could influence the cross sections M. Vogt and D. Barber calculated the expected polarisation at the energies of interest
• Of course the polarisation would be almost completely transversal!
At 2.3 GeV:
Rise time about 2.5 h and polarisation up to 90%
shown are results for 10 seeds with a typical orbit distortion
Moving the cavities
Present situation Changes for Olympus operation
•The 2 cavities would be moved to SL 26m
•The waveguide distribution would be changed such that 4 neighbouring cavities can still be connected to one RF-station – one waveguide passing Olympus
•Controls, interlocks etc. have to be changed accordingly
the costs would be about 10 k€
Magnet power supplies
• 1 additional power supply is needed for the extra pair of quadrupoles –a device from Hera-p could be used here
• Most of the P.S. have to be modified to allow the polarity switching:– 24 switches for 400 A : 60 k€– 10 switches for 800 A : 40 k€– Mechanics, cabling and controls : 70 k€ → 170 k€
Injection elements
• Also the kicker pulses have to reverted • Since the high voltage connections with well defined
inductance can’t simply be switched, new pulsers would be needed which can change the polarity of the current pulse
• There are two kickers at DORIS and one at DESY• The material costs per pulser including the HV power
supply are 29 k€
Vacuum elements
• Valves to separate the IP-region from the rest of the ring• Collimator insertions – have to be specified• Intersections to connect the ring vacuum with the
experiment vacuum system
Topic DORIS shutdown Necessary ?
Components to buy
Remove Argus No - Revise/rebuild rails and container No ? Install Blast No Electric power for detector No Low voltage distribution
(230V/50Hz ?) cables to power supply (reuse PS from Petra)
Water cooling of detector No Water pumps Cooling pipes
Air conditioning No Air conditioning design of collimator system Construction of vacuum parts No - Move cavities from IP to SL 26m Yes Pipes, cables Modification of vacuum system Yes 2 valves
collimator insertions Modification of magnet girder Yes - Installation of 2 Quadrupoles Yes cables Installation of PS polarity switches Yes Remotely controlled polarity
switches, cables, controller relocate cables and water pipes from IP Yes Pipes, cables Remove concrete blocks from IP-region Yes - modify workshop on the outside of DORIS Yes ? Shift detector in the ring Yes - Build up radiation shielding Yes ? Safety ( interlock, emergency stop, fire detector, gas detector )
Yes Detectors, cables, interfaces
Tasks for installing the detector :
Operational issues
• e+/e- operation of LINAC, PIA and DESY is possible – switching takes about 5 min. ( … on the long term DORIS and Petra should run with electrons only )
• For a fast change of the polarity of the DORIS magnets additional power supply switches have to be installed.
• The change of the particle type in DORIS should be possible within one hour. • Due to the lifetime reduction, energy changes and increased radiation a parallel
operation with Hasylab is not possible.• Due to the frequent changes of the particle type also a common operation with
Petra III is excluded ( at least for the normal Top-up mode at Petra! )• The particle optic in DORIS is matched to keep the optical functions nearly
unchanged at all wiggler positions – therefore it has not to be changed for the synchrotron radiation runs. The target cell can stay in the ring.
Summary
• The space for a detector like Blast is still available• Some modifications (and investments) are necessary – but no “show-stoppers” are
visible• An optic has been developed which should work for synchrotron radiation runs as
well as high energy runs• The most time consuming work can be done outside the Doris tunnel and needs no
shutdown time