FACILITY LOCATION
![Page 2: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/2.jpg)
FACILITY LOCATION
Once a firm has decided to open a new facility OR relocate an existing facility, It must decide where that facility should be located.
![Page 3: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/3.jpg)
FACILITY LOCATION
Facility location problem involves the evaluation of various sites for a new facility.
There are several factors that influence the Facility Location Decision:
![Page 4: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/4.jpg)
Factors Related to Resources Labor availability, Labor cost, Labor Skills; Materials Availability, Material cost,
material quality; Equipment availability, Equipment Cost; Land availability, Land suitability, Land
cost; Energy availability, energy cost; Water availability, water quality, water cost.
![Page 5: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/5.jpg)
Factors Related to the Market
Proximity to the firm’s market, size of the market, potential needs of the market.
![Page 6: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/6.jpg)
Factors Related to the Infrastructure Availability of Financial Institutions,
Strength of Financial Institutions Government Stability, Government
taxes, Import and Export restrictions. Quality of life, Cultural issues, Environmental regulations,
Transportation availability, Transportation cost
And finally, Competitors’ size, strength and attitude in that region.
![Page 7: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/7.jpg)
FACILITY LOCATION There are many analytical techniques
that can be used in facility location decision.
Some of these are:1) Factor Rating2) Cost-Profit-Volume analysis3) Center of Gravity Method, and4) Transportation and Simulation
Models.
![Page 8: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/8.jpg)
Method of Factor Rating
In factor rating method, first we must identify the Most Important Factors in evaluating alternative sites for the new facility.
Then we should assign a weight between 0 and 100 to each of these factors.
![Page 9: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/9.jpg)
Method of Factor Rating
Each alternative location will then be rated based on these factor weights.
The most weighted alternative is selected as the best alternative.
![Page 10: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/10.jpg)
Example Samson Ltd. is considering three
alternative sites for its new facility. After evaluating the firm’s Needs, the
Managers have Narrowed the list of Important Selection Criteria down into three major Factors.
- Availability of skilled labor- Availability of Raw materials, and- Proximity to the firm’s markets.
![Page 11: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/11.jpg)
Example Weights reflecting the relative
importance of each factor have been assigned as follows:
![Page 12: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/12.jpg)
Example Based on these criteria, the
three Alternative sites were scored between 0 and 100 points:
![Page 13: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/13.jpg)
Example Now we will multiply each score by its
corresponding factor weight: Weighted scores are calculated as:
(Site Score)x(Factor Weight)
![Page 14: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/14.jpg)
Example
From these results, the largest total weight is for Site A. It appears to be the best location.
![Page 15: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/15.jpg)
Example
What happens if we change the factor weights. Lets use the following factor weights:
Skilled labor: 0.45; Raw Materials: 0.40; and Market: 0.15
Then the following results are obtained:
![Page 16: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/16.jpg)
Example
![Page 17: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/17.jpg)
Example
In this case, Site C appears to be the best choice with largest weight score.
Therefore, factor rating method is very sensitive to the weights assigned to each factor.
![Page 18: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/18.jpg)
Example
Since factor weights, selected factors, and assigned scores are all determined subjectively, the managers should be very careful in selecting these items and numbers.
![Page 19: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/19.jpg)
Cost-Profit-Volume Analysis
When the fixed and variable costs for each site differ, Cost-profit-volume analysis can be used to identify the location with the lowest cost.
![Page 20: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/20.jpg)
Example
Foster Paper Ltd. is considering three alternative sites for its new production facility.
The Annual Production Cost associated with each alternative is a linear function of the production volume. That is:
![Page 21: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/21.jpg)
Example
Total Production Cost = (Fixed Cost) + (variable unit cost) x (annual production volume)
Assume that The expected annual production volume is 250.000 units.
And further assume that: (x: production volume = 250.000)
![Page 22: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/22.jpg)
Example
For Site A: Prod. Cost = 10.000.000 + 250 xFor Site B: Prod. Cost = 25.000.000 + 150 xFor Site C: Prod. Cost = 60.000.000 + 50 x
Based on these information, Which site has the lowest cost?
![Page 23: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/23.jpg)
Example At a production volume of 250.000
units, site B has the lowest cost, because
For Site A: Prod. Cost = 10.000.000 + 250 (250.000) = 72.500.000
For Site B: Prod. Cost = 25.000.000 + 150 (250.000) = 62.500.000
For Site C: Prod. Cost = 60.000.000 + 50 (250.000) = 72.500.000
![Page 24: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/24.jpg)
Example
![Page 25: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/25.jpg)
Example This graphic shows that annual
production cost changes with different production volumes.
-If the expected annual production volume is below 150.000 units, then choose site A.
-If the expected annual production volume is between 150.000 and 350.000 units, then choose site B.
-If the expected annual production volume is over 350.000 units, then choose site C.
![Page 26: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/26.jpg)
Center of Gravity Method
The center of gravity method is used to find a location that Minimizes the Sum of Transportation Cost in between new facility and old facilities.
Transportation cost is assumed to be a linear function of the Number of Units Shipped AND the Traveling Distance.
![Page 27: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/27.jpg)
Center of Gravity Method
The location of the firm’s existing facilities are converted into x and y coordinates.
The following center of gravity equations are Then used for calculating the x and y coordinates for the new facility:
![Page 28: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/28.jpg)
Center of Gravity Method
![Page 29: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/29.jpg)
Center of Gravity Method Here, Cx : x coordinate for new location Cy : y coordinate for new location i: index for existing locations n: total number of existing locations xi: x coordinate of existing ith location ,
and yi: y coordinate of existing ith location.
![Page 30: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/30.jpg)
Example
Aldrich Manufacturing Company plans to build a Warehouse to serve its Distribution Centers in Columbus (Ohio), Frankfort (Kentucky), Nashville (Tennessee), and Richmond (Virginia).
![Page 31: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/31.jpg)
Example
![Page 32: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/32.jpg)
Example
The number of units to be shipped monthly from Harrisburg to the Distribution Centers are shown in the following table:
(Weighted Coordinates are calculated as: (Annual Shipping Volume) (x or y coordinate))
![Page 33: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/33.jpg)
Example
![Page 34: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/34.jpg)
Example Using the equations of center of
gravity: Cx = 2,040,000 / 10,000 = 204 (x
coordinate for new facility) Cy = 1,185,000 / 10,000 = 118.5
(y coordinate for new facility) The nearest city to (204, 118.5)
Charleston at West Virgina.
![Page 35: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/35.jpg)
Example
This method only considers the distances traveled. It does not consider the other factors such as the availability of roads on the selected location. Therefore, applying solely this method may not be applicable in every cases.
![Page 36: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/36.jpg)
Transportation Model
A special form of linear programming, that is Transportation Model, can be used to compare the total transportation cost associated with each alternative site.
![Page 37: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/37.jpg)
Transportation Model
The transportation model technique can be used to determine how many units should be shipped from each plant to each warehouse To Minimize Total Transportation Cost.
![Page 38: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/38.jpg)
Example
Straub Ltd. has three plants running at full capacity in Des Moines, Racine, and Gary.
These plants supply four Distribution warehouses in St. Paul, Milwaukee, Chicago, and Detroit.
![Page 39: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/39.jpg)
Example Straub plans to build a new plant. It has
narrowed down the choice of sites to two possibilities: Kalamazoo and Duluth.
We will now determine which site results in the lowest transportation Cost by using the unit transportation costs, warehouse demands, and plant capacities shown in the following:
![Page 40: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/40.jpg)
Example
![Page 41: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/41.jpg)
Example
![Page 42: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/42.jpg)
Example
We will approach this problem in the following manner:
We will first assume that the selected plant is the Kalamazoo plant, and calculate the total transportation cost.
![Page 43: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/43.jpg)
Example Later, we will assume the selected plant
is Duluth. Then we will compare the transportation costs for both plants.
Now, the first step is to find the Optimal number of units to ship between each plant-warehouse combination. This also gives the optimal transportation cost for the problem.
![Page 44: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/44.jpg)
Example We can use any of the
computerized LP tools for finding the optimum values for this problem.
Some of these include WINQSB, Lindo, OM Expert, and Excel.
We use WINQSB to solve this transportation model. The result is as follows:
![Page 45: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/45.jpg)
Example
![Page 46: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/46.jpg)
Example The total transportation cost will be
$10,225 if the new plant is built in Kalamazoo.
(This can be calculated simply by multiplying the shipment in each cell by its unit cost)
On the other hand, The optimal number of units to ship between each plant and Duluth Warehouse is found as follows:
![Page 47: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/47.jpg)
Example
![Page 48: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/48.jpg)
Example
The total transportation cost will be $13,825 if the new plant is built in Duluth.
Therefore, the Kalamazoo plant will incur the lowest transportation cost.
![Page 49: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/49.jpg)
Simulation Models
Firms often Consider many variables and Factors when they choose a facility location.
![Page 50: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/50.jpg)
Simulation Models
These variables are often difficult to estimate and they also change in time.
In these kinds of Dynamic Situations, Simulation may be the best modeling technique.
![Page 51: Factor Rating Method Unit 4](https://reader034.vdocuments.us/reader034/viewer/2022042613/54ffdcda4a7959b9108b4a47/html5/thumbnails/51.jpg)
Simulation Models
Simulation models allow managers to examine a range of Scenarios AND are well suited to open-ended problems.
However, the determination of the parameters in a simulation is also a challenging task.
Also, developing a simulation model may take considerable time and effort.