facilities williams report overview inglewood unified school district january 16, 2015

10
Facilities Williams Report Overview Inglewood Unified School District January 16, 2015

Upload: hilda-beasley

Post on 16-Dec-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Facilities Williams Report Overview Inglewood Unified School District January 16, 2015

Facilities Williams Report Overview

Inglewood Unified School DistrictJanuary 16, 2015

Page 2: Facilities Williams Report Overview Inglewood Unified School District January 16, 2015

Maintenance/Facilities Dept.• Department Staff

– Joe Dominguez, Deputy Superintendent 1yr 5mth

– Robert Tiger, Director of MOT 6 months

– Cindi Collecchi, Document Specialist 36yrs 8mths

– Anthony Boyd, Warehouse Supervisor 12 years

Page 3: Facilities Williams Report Overview Inglewood Unified School District January 16, 2015

9 Williams Visit - School Sites

• Inglewood High School

• Morningside High School

• Monroe Middle School

• Parent Elementary

• Centinela Elementary

• Warren Lane Elementary

• Hudnall Elementary

• Crozier Middle School

• Woodworth Elementary

Page 4: Facilities Williams Report Overview Inglewood Unified School District January 16, 2015

Inglewood High School• Extreme Deficiencies Findings: 23

• Corrected Extreme Deficiencies: 20

• Pending Extreme Deficiencies: 3– Room/Area near B1: Breezeway under const. Monday 1/19

– Room/Area Grounds: (Spring/Summer) exterior paint /plaster /finish/breezeways

– Room/Area D2 AVID Room: lighting covers – special order 1/28

– Room/Area School Wide: damaged grounds/fields/asphalt/drainage

– Room/Area M202: floor tile missing – Tuesday 1/20

Page 5: Facilities Williams Report Overview Inglewood Unified School District January 16, 2015

Morningside High School

• Extreme Deficiencies Findings: 10

• Corrected Extreme Deficiencies: 8

• Pending Extreme Deficiencies: 2– Room/Area Classroom T6: floor sagging (portable)

Spring/Summer

– Room/Area I3: exit door blocked by security gate

Page 6: Facilities Williams Report Overview Inglewood Unified School District January 16, 2015

Monroe Middle School

• Extreme Deficiencies Findings: 5

• Corrected Extreme Deficiencies: 3

• Pending Extreme Deficiencies: 2– Room/Area Kitchen/MPR: Stage/Storage Area (2) – 1/27

• Open wall severe damage, several studs damaged missing, floor damaged/cracked, ceiling tiles damaged/stained/missing, plaster/paint damaged

– Room/Area Classroom A3: cracks, deterioration, eroded soil

Page 7: Facilities Williams Report Overview Inglewood Unified School District January 16, 2015

Plan of Action• Restrooms Deep Cleaned

• Locker rooms Deep Cleaned– Painting/Floor polishing/wax being scheduled

• Restrooms Painted

• Exterminating Company Monthly/On Call

• Custodians assigned to designated restrooms

• Roof repair/replacement quotes in process

• Custodian training best practices being scheduled in partnership with ASCIP

Page 8: Facilities Williams Report Overview Inglewood Unified School District January 16, 2015

Moving Forward• Hiring of additional Maintenance Workers

• LAWA - $44m

• Surplus sale of Park Property - $600k

• Rotation of Contractors Pool - Area of Expertise

• Supervisory Positions Pending

• Measure GG – Reinvest to “FIX” our schools

Page 9: Facilities Williams Report Overview Inglewood Unified School District January 16, 2015

Equity and Modernization Issues

• Improve security, access points and perimeter of school by installing/replacing fencing, develop better site drainage ading retaining walls.

• Improve parking and instructional facilities by relocating the Maintenance - Grounds, Operations, Transporation Department.

• Remove/replace pipes on roofs.• Modernize and improve size and functionality of multipurpose

room.

Page 10: Facilities Williams Report Overview Inglewood Unified School District January 16, 2015

Thank You

Any Questions???