facilities institute july 9 - 12, 2012 houston, texas click to edit master title style

20
Click to edit Master title style www.NAEPnet.org

Upload: derrick-preston

Post on 18-Dec-2015

220 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Click to edit Master title style

www.NAEPnet.org

Page 2: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Understanding the Construction Manager at Risk

Project Delivery Method

Presented by

Steve Skabla, Vice President

Chief Estimator/Preconstruction Manager

Page 3: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Presentation Overview

• Overview of Various Project Delivery Methodso Traditional (Lump Sum) Bido Competitive Sealed Proposalso Design/Buildo Job Order Contractingo Construction Manager at Risk

• Explanation of Construction Manager at Risko Definitiono Characteristicso Pros/Cons o Project Exampleso Lessons Learned

• How to Evaluate Best Value

Page 4: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

What is a “Project Delivery Method”

The process of how a project will be planned, designed and built

OR

Procurement strategy for designing and constructing a facility

OR

Means of contractually communicating expectations and basis of reimbursement

OR

The process of managing how a project will be planned, designed and built

Page 5: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Price & Technical Qualifications

Price & Technical Qualifications

Overview of Delivery Methods

Owner

General Contractor

A/E

S u b c o n t r a c t o r s

TraditionalPrice only

Owner

Design/Builder

S u b c o n t r a c t o r s

Self-Perform

Select Design Construct

Owner

JOCContractor

A/E or Consultant

S u b c o n t r a c t o r s o rE m p l o y e e C r e w s

Select Design Construct

Traditional & CSP Design/Build Job Order Contract

Design Bid Construct

CSPPrice and Technical

Qualifications

Page 6: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Overview of Delivery Methods

Sub Sub Sub Sub

Owner

A/ECM

Sub

Construction Manager at Risk

Construct

DesignSelect

Fees, general conditions and qualifications

Page 7: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Construction Manager at Risk (CM at Risk)

• What to Expect from Your CMo Provide constructability reviewso Provide detailed cost estimates at Schematic Design, Design

Development and at Guaranteed Maximum Price (GMP)o Deliver GMP prior to completion of Construction Documentso Begin construction before design is 100% completeo Bring best subcontractors and best prices to the projecto Control costs/budgeto Take a business risko Provide financial guaranteeso Act in the Client’s best interest

Page 8: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Preconstruction (Not Just an Estimate & Schedule)

Solicitation & Pre-

QualificationProcess

Solicitation & Pre-

QualificationProcess

BudgetingBudgeting Bid Package DevelopmentBid Package Development

GMP Development

GMP Development

Value Engineering

Options

Value Engineering

Options

Purchasing Process

Purchasing Process

Over-the-Shoulder Design

Reviews

Over-the-Shoulder Design

Reviews

SchedulingSchedulingCoordination &

3D Collision Check

Coordination & 3D Collision

Check

ConstructabilityReview &

Improvement

ConstructabilityReview &

Improvement

Site Management

Planning

Site Management

Planning

Team Communication

Protocols

Team Communication

Protocols

Weekly & Monthly

Reporting Process

Weekly & Monthly

Reporting Process

Site LogisticsSite LogisticsFF&E

Coordination & Management

FF&E Coordination & Management

Meeting Management

Meeting Management

Life-Cycle Analysis

Life-Cycle Analysis

Job Hazard Analysis

Job Hazard Analysis

Severe Weather Preparedness

Severe Weather Preparedness

OCIP/CCIPPlan

OCIP/CCIPPlan

Testing & Commissioning

Process

Testing & Commissioning

Process

Occupancy Planning

Occupancy Planning

Quality Management

Process

Quality Management

Process

Planning for Service After Completion

Planning for Service After Completion

Page 9: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

PROS• Flexibility in selecting a builder • CM provides preconstruction

services and works in team concept with A/E & Owner

• Usually brought on early in design (program/SD)

• Constructability reviews at each stage of documents

• Opportunity to phase/fast track • Better opportunity to maximize

HUB/MBE subcontractor participation through bid package strategic initiatives

CONS• Price is not guaranteed at time

of selection• Owner must have more

involvement in the process• Difficult to evaluate actual cost

between CM at Risk candidates

CM at Risk

• Opportunity for bid strategies on inflationary materials

• Reduces the risk of proprietary specifications

• Change flexibility

Page 10: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Lowest Cost vs. Best Value

Best qualified firm will give you the most value for the 91%.

Page 11: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Best Suited

• Large new or renovation projects

• Schedule sensitive• Difficult to define• Subject to change

Least Suited

• Small or simple projects

Project Candidates for CM at Risk

Page 12: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Example: South Texas Research Facility

Page 13: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Texas A&M Univ., Veterinary Imaging & Cancer Treatment Center

Page 14: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

CM at Risk Lessons Learned

• The best performers at CM at Risk are the same best performers at CSP and hard bid.

• State procurement laws may vary the process.o Example: For Texas, 100% CDs and public subcontractor proposals

on each package are required prior to any real work.o It is more work, not less for the Architect and Contractor.

• Allow adequate time for review and approval of the Guaranteed Maximum Price (GMP).

• Allow adequate time for the subcontractor selection process by the CM and Owner approval

Page 15: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

CM at Risk Lessons Learned

• Agree on the subcontractor selection criteria and process early.

• The project design must be sufficiently advanced to have accurate general conditions proposals in the RFP.

• Clearly define what is to be included and excluded from “general conditions” in the RFP.

• Lump sum general conditions - not cost plus.o The most issues/problems.o 90% of contract administrator or Owner’s representative’s time

on 5% of cost.

Page 16: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

CM at Risk Lessons Learned

• Draft a total project schedule, not just a construction schedule.

• Give the CM the entire project budget. Tell the CM what parts it is responsible for.

• Add example schedule, decision milestones

Page 17: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Benefits of CM at Risk Delivery

Example: 1 Million GSF Public Hospital•4-year project duration•Items bought early•Potential cost savings

Page 18: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Pick the Right Delivery Method

• Before starting the selection process, determine which delivery method will provide “best value”

• Factors to consider (add more):o Project size and complexityo Time allocated for the construction o Competitiveness of the current/local construction marketo Desired flexibilityo Availability of contractors and subcontractors in the local market

• After deciding on key factors, evaluate the various delivery methods and formally adopt the method you deem “best value.”

Page 19: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Hand-out

Page 20: Facilities Institute July 9 - 12, 2012 Houston, Texas Click to edit Master title style

Facilities InstituteJuly 9 - 12, 2012Houston, Texas

Thank You

Steve Skabla

713.243.8301

[email protected]