facilities design sagd 2014
DESCRIPTION
Although planned capital expenditure in Alberta's oil sand industry is estimated upwards of $20 billion in 2014, the economics of SAGD operations are becoming increasingly strained in Western Canada with many projects going over schedule and budget due to increasing supplier costs and execution challenges. E&P companies are striving to meet high demands in terms of productivity, yet the economics of operating existing and commissioning new SAGD projects is being threatened due to rising costs. DESIGNING AND EXECUTING FACILITIES WITHIN BUDGET In light of what is currently happening in the industry, it has become imperative for the Alberta Oil Sands Industry to find a solution that can combat the rising costs of facilities design and process engineering. Facilities design is clearly a cost-critical part of SAGD, and right now, facilities and process engineering managers have the opportunity to drive down these costs by pulling together to exchange design best practices, construction plans and equipment selection case studies. To this end, the first Facilities Design SAGD 2014 congress is coming to Calgary on December 9-10. Presenters at the solutions-packed congress will examine best practices in key well site areas including equipment selection processes and optimal designs for oil/water separation, water treatment, steam generation and gathering facilities with the overall goal of finding and developing methods to reduce the costs and construction times of developing In Situ Oil Sands facilities.TRANSCRIPT
Well Site Facilities & Process Engineering Professionals
Canada’s First Congress Dedicated Purely To In Situ Facilities And Process Engineering Professionals
Optimizing The Costs And Construction Times Of Developing SAGD Oil Sands Facilities:
Examining The Latest Designs, Equipment Selection Processes And Well Site Technologies Being Used To Reduce The Costs Of Oil Separation, Water Treatment, Steam Generation And Processing Facilities
OPERATOR CASE STUDIES ON:
December 9 - 10 | Calgary | Canada
David Safari VP Facilities Laricina Energy
Expert Speakers Including:
M Follow Us: @UnconventOilGas
www.sagd-facilities-design-2014.com
Register By FridayOctober 24, 2014
*SAVE $200
EQUIPMENT SELECTION PROCESSES: Designing and delivering well site production facilities to budget - assessing equipment evaluation and selection processes being used to drive down the capital and maintenance cost of in situ facilities
OIL-WATER SEPARATION: Determining the most effective chemicals for use on emulsion and how they are affected by heat and pressure to identify opportunities for improving separation energy efficiency and costs
PAD VS CENTRALIZED: Comparing the project logistical and equipment costs of separating and processing gas and liquids on the well pad versus a central facility to determine which yields optimal project economics
WATER TREATMENT FACILITIES DESIGN: Analyzing the very latest evaporators, softeners and chemicals being successfully applied to reduce the costs of in situ oil sands production
STEAM GENERATOR FACILITIES & SOR REDUCTION: Quantifying the particle tolerance of OTSG’s and the impact on steam productivity of new boiler designs
PROJECT MANAGEMENT & DESIGN EXECUTION: Identifying key construction methods and project management strategies being used to execute facilities designs within time frame and budget
GATHERING FACILITIES: Examining how the sizing of gathering lines and erosion tolerance of pressurized storage tanks have been incorporated into design to reduce the costs and increase the run life of the facilities
Amogh Katyayan Engineering Manager CNRL
Manoj Somonathan Project Engineer & Management Total
Larry Ginther Operations Manager Cavalier Energy
Shally Xiao Production Engineer PetroChina
Ken James President & CEO Oak Point Energy
Shabir Premji CEO Groundstar Resources
Organized By:
Well Site Facilities & Process Engineering Professionals
Although planned capital expenditure in Alberta’s oil sand industry is estimated upwards of $20 billion in 2014, the economics of SAGD operations are becoming increasingly strained in Western Canada with many projects going over schedule and budget due to increasing supplier costs and execution challenges. E&P companies are striving to meet high demands in terms of productivity, yet the economics of existing and commissioning of new SAGD projects is being threatened due to rising costs.
DESIGNING AND EXECUTING FACILITIES WITHIN BUDGET
In light of what is currently happening in the industry, it has become imperative for the Alberta Oil Sands industry to find a solution that can combat the rising costs of facilities design and process engineering. Facilities design is clearly a cost-critical part of SAGD right now, facilities and process engineering managers have the opportunity to drive down these costs by pulling together to exchange design best practices, construction plans and equipment selection case studies.
To this end, the first Facilities Design SAGD 2014 congress is coming to Calgary on December 9-10 this year. Presenters at the solutions-packed congress will examine best practices in key well site areas including equipment selection processes and optimal designs for oil/water separation, water treatment, steam generation and gathering facilities, with the overall goal of finding and developing methods to reduce the costs and construction times of developing in situ oil sands facilities.
Expert industry professionals from leading E&P companies will be speaking on the key topics within facilities design to improve the run times and costs of SAGD. Facilities being covered include:
• Steam Generation Facilities
• Oil/Water Separation Facilities
• De-Oiling Facilities
• Water Treatment Facilities
• Gathering Facilities
• Pad Vs Centralized Facilities
As well as this, case studies will be delivered demonstrating project management and design execution strategies being used to ensure operations are carried out within budget and on schedule.
WHAT WILL THIS CONGRESS DELIVER TO DELEGATES?
THE ONLY CONGRESS FOR FACILITIES
ENGINEERS IN CANADA: For the first time
in history, a congress has been designed
specifically for the facilities and process
engineering functions in Western Canada.
This means every session has been created
to provide delegates with job relevant,
applicable insights and solutions to improve
design processes
COST FOCUSED: Due to the rapidly
increasing costs of in situ, and specifically
SAGD, oil sands production, the facilities’
teams that are managing to successfully
drive down operational costs are the teams
experiencing the greatest degree of success.
These teams are also the ones sharing their
insights at this congress
TURN AROUND TIME REDUCTION:
Time equals money and due to the fact
turnaround time is such a powerful cost
driver in oilfield facilities; presentations are
also geared towards providing solutions to
achieving this end goal
DESIGN, CONTRUCTION AND
MAINTENANCE: The program has been
designed to offer solutions at every stage of
oilfield facilities projects to ensure that overall
project time and costs can be reduced
CASE STUDY FOCUSED: Rather than
supplier led or academic presentations,
speakers will deliver practical case studies
to provide delegates with tried and tested
design methods and project execution plans
that can be transferred between companiesThe BMO Centre - Palomino Room20 Roundup WayCalgary, Alberta, CanadaT2G-2W1Phone: (403) 261-0531Website: http://venues.calgarystampede.com/venues/bmo-centre/
VENUE INFORMATION:
www.sagd-facilities-design-2014.com (1) 800 721 3915 [email protected]
Register By FridayOctober 24, 2014
*SAVE $200
OIL-WATER SEPARATION, WATER TREATMENT & STEAM GENERATION FACILITIESDay 1Tuesday December 9, 2014
8.30 Chair’s Opening Remarks
KEYNOTE: EQUIPMENT SELECTION PROCESS
8.40 Designing And Delivering Well Site Production Facilities To Budget: Assessing Equipment Evaluation And Selection Processes Being Used To Drive Down The Capital And Maintenance Cost Of In Situ Facilities
•BudgetCriteria:Assessinghowtheequipmentwasevaluatedandselectedtomeetthegivenbudgetwithoutcompromisingproduction
•ResourceCompetencies:Analyzingstrategiesusedtoassessthereliabilityoftheequipmentselectedtoreducefuturemaintenancecostsofthefacilities
•Performance:Understandinghowthekeyequipmentperformancecriteriaweremeasuredandbalancedwithcoststoensurefacilitiesmetproductionrequirements
•FailureRates:Examininghowfailureratesarebeingaccuratelymeasuredduringevaluationtoensureselectionsaremadeonthebasisofminimaloperationaldowntime
•Reservoir:Examininghowprocessandfacilitiesengineersareusingreservoircharacteristicstoselectthemosteffectiveandcostefficientequipmentforproduction
David Safari, VP Facilities, Laricina Energy
9.10 Question & Answer Session
COST REDUCTION: SAGD CASE STUDY
9.20 Assessing Major Step Changes Being Taken To Cut Costs In Key Areas Of Well Site Facilities And Ensure In Situ Projects Remain Economic In Alberta
•Sizing:examininginnovativewaysfacilitiesengineersarereducingthesizeofSAGDinfrastructurewhilstmaintainingproductionlevelsandreducingthecostsoffacilities
•FailureRates:discoveringoptimummaintenanceprocessesbeingusedinSAGDtoreducetheriskoffacilitiesfailure
•DiluentCosts:examininghowoperatorsarereducingthecostsofdiluenttooptimizetheeconomicsofoiltreatment
•LabourCosts:hearinghowtheoperatorssecured,trainedandmaintainedthelaborneededtosuccessfullyexecutetheproject
•Compliance:identifyingkeyregulatorychallengesassociatedwithtechnologydesignandhowtominimizetheimpactthesehaveonfacilitiescost
Shally Xiao, Production Engineer, PetroChina
9.50 Question & Answer Session
BALANCING CAPEX & OPEX: CONSTRUCTION & OPERATION
10.00 Examining Key Operational Facilities Design Inputs And Anticipating The Encounters Faced During The Planning And Construction Phases To Identify Opportunities To Balance CAPEX And OPEX
•Utilizingoperationsandprojectmanagementpersonnelworkingtogethertoensurethefacilitiescanbeoperatedefficientlyandcosteffectivelytoavoidadditionalcapitalexpenditure,whichcansignificantlyreducethefacilitiesoperatingbudget
•Comprehensivelyexaminingsolutionstothechallengesbeingfacedbyoperationswhencommissioning,startingupandoperating,includinggettingtherightequipmentinplacetoensureoperationcanhandleprocesschallengeswithoutgoingovertheoperatingbudget
•ExaminingtheselectionandsizingofequipmentforbothprocesstreatingandwatertreatmenttomaximizeproductionthroughtheeverchangingSteamoilratiosseenthroughthelifecycleofSAGDwell,whileensuringthatregulatorytargetsmaybeachieved
•Evaluatingtheideaofhavingoperationsstaffplayaroleinfacilityconstructiontodiscoveranybenefitsofoperationsworkingintandemwithmaintenancepersonnelonsitethroughconstruction
Larry Ginther, Operations Manager, Cavalier Energy
10.30 Question & Answer Session
10.40 Morning Refreshments In The Exhibition Area
WELL PAD VS CENTRALIZED FACILITIES
11.10 Comparing The Logistical And Equipment Project Costs Of Separating And Processing Gas And Liquids On The Well Pad Versus A Central Facility To Determine Which Is More Economical
•Comparingthelifecyclecostsofmultiplewellpadstothoseofacentralprocessingfacilitytoidentifywhichisthemostcostefficientlongterm
•ComparingtheliftandpressurerequirementsofapadversusaCPFtocalculateoverallprojecteconomicsandinformthedecisiononwhichdesigntouse
•Hearinghowoperatorsareusingproductionpredictionstocalculatewhethertheextraupfrontcapitalcostsofacentralizedfacilityoutweighthelowershorttermcostsofpadfacilities
•DeciphertheextenttowhichpadcostscanbedrivendownthroughstandardizationtodeterminewhetherthiswouldmakepadsmorecosteffectivethanCPF
11.40 Question & Answer Session
11.50 Lunch In The Exhibition Showcase Area
WATER TREATMENT FACILITIES DESIGNANALYZING CHEMICALS AND TECHNOLOGIES USED IN
OIL WATER SEPARATION AND EVALUATING THEIR EFFECT ON PRODUCTIVITY
EVAPORATOR FOCUS
12.50 Examining Methods Being Used To Minimize Failure Rates To Improve The Reliability And Maintenance Costs Of Evaporators
Evaluatingthecostsandperformanceofdifferenttypesofevaporatorstohelpselectwhichismosteffectiveforeachoperation:•SeededSlurryHighpHPlate&FrameHorizontalAssessingthe
plotspaceandlayoutofeachevaporatortypetoassesshoweachwillfitoperationallyintothedesign
•Understandinghowoperatorsarecalculatingdowntimewhenevaluatingevaporators
•Lookingatboththeoperationalandthechemicalrisksofevaporatorsandidentifyingkeymethodsinfailingpreventiontoensurewateristreatedtoahighenoughqualitytoensurelongevityoftheboiler
Ken James, Co-President & Co-CEO, Oak Point Energy
1.20 Question & Answer Session
LIME SOFTENERS VS EVAPORATORS: LATEST RESULTS
1.30 Comparing The Capital Costs, Energy Efficiency, Reliability And Maintenance Costs Of Lime Softeners Versus Evaporators To Determine Which Is Most Effective in Removing Hardness From Water
•Comparingcasestudiestoshowwhichmethodhasproventorecoverthemostuseablewaterforsteamgeneration
•Identifyingwhentoadjustchemicalsinlimesoftenerstoensureoptimalsilicaremoval
•Learningwhatcomponentsshouldbefedintothelimesoftenertohelpmaintainandkeepthebedhealthytopre-emptfailuresandreducemaintenancecosts
•Identifyingkeyindicatorsthatshowwhenanadjustmentinchemicalsisrequired,andoptimaladjustmentmethods,togenerateimprovedwaterquality
•Addressingtheprosandconsofbothtypesofwatertreatmentfromaneconomicalstandpointtodeterminewhichonehasmoreeconomicalvalueandpositiveimpactonextractionrate
Caroline Mussbacher, Water Treatment Specialist, Laricina Energy
2.00 Question & Answer Session
2.10 Networking Lunch In The Exhibition Showcase Area
ALTERNATIVE CHEMICAL & MECHANICAL TREATMENTS
2.40 Learning About The Latest Alternative Chemical And mechanical Methods For Treating Water To Uncover More Innovative, Cost Effective And Reliable Treatment Options
Chemical
•Polymers:delvingintothedifferenttypesofpolymerstodiscoverwhicharethemostefficientintermsofensuringthelightnessofthewaterandfoulingprevention
Mechanical
•Combiningmechanicalandchemicaltreatments:analyzingtheeconomicalvalueofusingmultistagepumpstotreatthewateralongsideusingthewatertreatmentchemicals
•ElectroStaticGrids:evaluatingtheinfluenceofelectrostaticgridsonwaterqualitycomparedtolimesoftenersandevaporatorstodeterminewhichhasthemostimpactonwaterquality
3.10 Question & Answer Session
STEAM GENERATION FACILITIES: SOR REDUCTIONQUANTIFYING THE PARTICLE TOLERANCE OF OTSG’S AND THE IMPACT ON STEAM PRODUCTIVITY OF NEW
BOILER DESIGNS
WATER QUALITY TOLERANCE: PANEL
3.20 Learning The Maximum Levels Of TDS That Can Be Handled By OTSGs To Identify Opportunities For Reducing Water Treatment Costs
•AssessingwhichwaterspecsarebeingusedinOTSGsindifferentregionsofAthabascaandlearningtheextenttowhichwatertreatmentcostsarebeingreducedbychangingspecs
•Understandinghowtomonitorandpredictwhenthewaterisgoingtocausefoulingtoreducerepaircosts
•Analyzingdifferentboilerdesigntechniquesforreducingsteamtooilratiotoshowwhichisthemostefficientinoptimizingsteamusage
Larry Ginther, Operations Manager, Cavalier Energy
3.50 Question & Answer Session
OIL-WATER SEPARATION AND DE-OILINGUSING CASE STUDIES TO IDENTIFY THE MOST
COST EFFECTIVE CHEMICALS, PROCESSES AND TECHNOLOGIES FOR SEPARATION AND DE-OILING TO ENSURE OPTIMAL QUALITY WATER FOR STEAM
GENERATION WITHOUT OVERSPENDING
OIL-WATER SEPARATION
3.20 Determining The Most Effective Chemicals For Separating Emulsion And How They Are Affected By Heat And Pressure To Identify Opportunities For Improving Separation Energy Efficiency And Costs
•Identifyingwhichchemicalsareprovingmostcostandperformanceeffectiveinbreakingupemulsionstoaidselection:ReverseEmulsifier
•DemulsifierExamininghowthesechemicalsareimpactedbytemperatureandpressuretoidentifywhichvariablesmustbecontrolledduringtheseparationprocess
•Comparinginstrumentsformeasuringtheinterfacebetweenoilandwaterinsidetheseparatortodeterminethemostreliablemethod
3.50 Question & Answer Session
DE-OILING
4.00 Examining The Latest Advancements In De-Oiling Technology That Have Been Shown To Enable Increased Water Recovery During Treatment
Examiningcurrenttechnologiesbeingusedforde-oilingtodiscovernewwaystoincreaseefficiencyofseparation:•OilremovalsFilters•Identifyingnewmechanicalwaysoftreatingtheresidualoilin
thewatertobetterprepareitforsteamgenerationNitin Bhat, Process Lead, Senior Process Engineer, Laricina Energy
4.30 Question & Answer Session
5.30 Chair’s Closing Remarks
5.40 - 6.40 Networking Drinks Reception In Exhibition Showcase Area
www.sagd-facilities-design-2014.com (1) 800 721 3915 [email protected]
8.30 Chair’s Opening Remarks
PROJECT MANAGEMENT & DESIGN EXECUTION
8.40 Identifying Key Construction Methods And Project Management Strategies Being Used To Execute Facilities Designs Within Time Frame And Budget
•Comprehensivelyexamininghowlongtermcostswereminimizedbyinvestingextrainitialcostsandtimeintoleadershipvisionandexecutionplanningtolessenhumanerror
•Investigatinghowfacilitiesmanagershaveworkedwithsupplierstoreduceleadtimesofequipmentdelivery,materialsdeliveryandoverallprojectturnaroundtime
•Analyzingprojectexecutionrisksandmitigationstrategiesusedtoreducefacilitiesfailureandoperationalcosts
•Understandinghowequipmentfromvalvestospecializedcompressorswasattainedatoptimalcoststoensuretheprojectwasdeliveredinbudget
Mark Brown, Director, US Oil Sands
9.10 Question & Answer Session
EPC RELATIONS & PROJECT EXECUTION
9.20 Identifying Ways To Develop Trust Between The E&P And The EPC During The Bidding, Proposal And Execution Phases To Reduce The Risk Of Projects Running Over Budget And Schedule
•ImpactonExecution:Measuringtheextenttowhichthetrustbetweentheengineeringproviderandtheproducerimpactsoverallprojectexecutiontocreateafoundationonwhichtodevelopremedies
•Bidding&Proposal:Understandinghowtransparencyandopenbudgetknowledgecanbeappliedtoresolvetherequired/feasiblemanhoursdebatebetweentheEPCandtheE&PcompanyduringbiddingandproposalstageExecution:
•Examiningmethodsforensuringknowledgeoftheexecutionprocessisconsistentbetweenthetechnicalteamandengineeringcompany,toavoid“missedpromises”andminimizetheriskofrunningoverscheduleKickOffMeetings:
•Assessinghowtooptimise“kickoff”meetingsandhowtheycanpreventprojectsfromfallingbehindscheduleatlaterstagesintheprojecttomitigateextraexpenditure
Amogh Katyayan, Engineering Manager, CNRL
9.50 Question & Answer Session
FEASIBILITY STUDIES
10.00 An Analysis Of The Design Plan To Decipher Ways In Which You Can Achieve Maximum Usage And Longevity Of The Plant
•Evaluationofthedesignplanstructuretorecognizethecost,howmuchyouaregoingtosaveandhowlongitwillpayyouback
•Investigatingwaysofmeasuringtheoilproductiontohelpkeepontrackofproductionratestoenhancethelifeoftheplant
•Reviewingcasestudieswithdataonpastprojectstodecipherthepositivesandhowtousewhattheyhadincommoninconjunctionwithfutureprojectdesign
10.30 Question & Answer Session
FIT FOR PURPOSE CONSTRUCTION
10.40 Examining Planning And Construction Processes Being Used To Build Fit For Purpose Facilities: Identifying Opportunities To Eliminate Costs Incurred By Oversizing
•Understandinghowtheconstructionprocessimpactstheoperabilityandcostsofthefacilitytoreduceunnecessaryexpenditure
•Assessingallaspectsofsafetyinregardstothebuildingoffitforpurposefacilitiesandevaluatingitseffectonthereliabilityoftheplant
•Comprehensivelyexaminingteambuildingbestpracticesaroundexecutionfocusedareassuchasconstructionandassessingimpactontheeconomicsandqualityofthefacilities
David Safari, VP Facilities, Laricina Energy
11.10 Question & Answer Session
11.20 Morning Refreshments In Exhibition Showcase Area
LABOR AVAILABILITY: PANEL
11.50 Learning How To Develop Long Term Plans With The Local Government, Unions, Contractors And Colleges To Secure The Qualified Workforce Needed For In Situ Development
•Hearinghowanoperatorsshareda10yeardevelopmentplan,includinghumanresourcerequirements,withlocalunionsandgovernmenttohelpfulfilllongtermlaborrequirements
•Examininghowtheoperatorcoordinatedandmaintainedrelationshipswithmultiplecontractorstoensureshorttermlaborrequirementsweremet
•Understandingwhatcanbedoneindesignphasetominimizelaborrequirementsandtheimpactsthishasonthetimeandcostsoffacilitiesconstruction
•ComparingtheuseofCanadianworkerscomparedtooverseasworkerstoassesswhetherfurtheropeningtheskilledlaborpoolcouldhelpimprovetheworkforceinAlberta
Manoj Somanathan, Project Engineering & Management, TOTAL
Anthony Ladipo, Pipeline Construction Engineer, Shell
12.20 Question & Answer Session
MODULARIZATION
12.30 Determining The Overall Impact On Cost Per Pair And Cost Per Barrel Economics Of Modularizing And Standardizing Facilities: Case Study Comparison
•Exploringtheuseoffabricationshopsasawayofreducingtheamountworkonsiteandoverallfacilitiescosts
•Hearingtheextenttowhichcostsweresavedwhenaproducerstartedtostandardizemodulesacrosswellsites
•Examininghowusingmodulescancutdownleadtimeonmaterialsourcingtohelpkeepprojectsonscheduleandwithinbudget
1.00 Question & Answer Session
1.10 Lunch In The Exhibition Showcase Area
CRUDE TREATMENT & GATHERING FACILITIESEXAMINING METHODS OF UTILIZING DILUENT USE AND GATHERING FACILITIES DESIGN TO OPTIMIZE
PRODUCTION AND IMPROVE LONGEVITY OF THE PLANT
DILUENT SUPPLY & COSTS
2.10 Deciphering Ways Of Securing Sufficient Levels Of Diluent And Reducing The Costs Of Supply To Optimize In Situ Production Economics
•Examiningtheeffectofdiluentontheemulsionstabilitytodiscovernewwaysofutilizingthediluentduringseparationandoptimizingproduction
•Acomprehensivelookatalternativestrategies/technologiestoreducediluentuseduringseparationwhilstmaintainingandimprovingproductionvalue
•Analyzingtheoperationalcostofdiluentandcomparingitseffectonoilwaterseparationtodeterminethemostcosteffectivemethodofusingthediluent
Shabir Premji, CEO, Groundstar Resources
2.40 Question & Answer Session
GATHERING FACILITIES
2.50 Examining How The Sizing Of Gathering Lines And Erosion Tolerance Of Pressurized Storage Tanks Have Been Incorporated Into Design To Reduce The Costs And Increase The Run Life Of The Facilities
•AssessinginnovativepipelinedesignsbeingusedtofacilitatetheflowratepressureneededtotransporttheoilforproductionAnalyzingtheprodsandconsofstandardizinggatheringlinedesignstocutdownonconstructioncosts
•Hearinghowimplementingpressurizedstoragetankshelpedreducefacilitiescostsbyreducingtheneedforpumpstations
Anthony Ladipo, Pipeline Construction Engineer, Shell
3.20 Question & Answer Session
3.30 Afternoon Refreshments In Exhibition Showcase Area
BOILER DESIGNS
4.00 Identifying Which Steam Generator Designs Are Being Used By Operators To Reduce SOR And Reduce Overall In Situ Facilities Costs
•InvestigatingtheidealsteamqualitythatcanbeappliedtotheOTSGtoproducemaximumqualitysteamwhilereducetheriskoffouling
•Assessingthebenefitsofhigherrisksandcostsversuslowersteamqualitytodeterminewhichboileristhemostcosteffectiveintermsofsteamtooilratio
•Examiningnewboilerdesignstoidentifyopportunitiesforfurtherreducingfoulingandthecostofrepairs
•ComparingtheeffectivenessandcostsofdrumboilersandOTSGstoidentifywhichyieldsoptimalSOR
4.30 Question & Answer SessionPRODUCED WATER COOLERS: MAINTENANCE
REVEALING NEW METHODS OF CLEANING PRODUCED WATER COOLERS TO MINIMIZE MAINTENANCE COSTS
WITHOUT AFFECTING WATER QUALITY
WATER COOLERS
4.40 Identifying Optimal Cleaning Frequencies And Processes For Produced Water Coolers To Enable The Optimization Of Run Times And Maintenance Costs
•Hearinghowoperatorshavebeenexecutingacleaningwhilerunningprogrammeandtheextenttowhichthishasreduceddowntimerelatedcosts
•Exploringbettercosteffectivemethodsofmechanicallycleaningthewatercoolerwhilstmaintainingorimprovingproducedwaterquality
•Learninginnovativewaytoincreasetheeffectivenessofchemicalcleaningtoimprovemaintenanceofthewatercooler
5.10 Question & Answer Session
5.20 Chair’s Closing Remarks & End Of Congress
Day 2Wednesday December 10, 2014
OPTIMIZING FACILITIES EXECUTION, MODULARIZATION, PROCESSING FACILITIES & SKILLED LABOR
Excellent content and a great learning experience.
ConocoPhillips Canada
I liked the content - very current for oil sands management. Sunshine Oil Sands Ltd
www.sagd-facilities-design-2014.com (1) 800 721 3915 [email protected]
Sponsorship OpportunitiesThe Facilities Design SAGD 2014 congress offers a unique platform for oil sands producers and industry suppliers to discuss solutions to the current bottlenecks being faced with equipment selection processes and optimal designs for oil/water separation, water treatment, steam generation and gathering facilities, with the overall goal of finding and developing methods to reduce the costs and construction times of in situ oil sands facilities.
SAGD E&P Companies, Including:
• Laricina Energy
• Cavalier Energy
• Osum Oil Sands
• PetroChina
• CNRL
• Total
• Groundstar Resources
• Oak Point Energy
• Process Engineers
• Facilities Engineers
• Project Engineers
• Surface Facilities
• Operations Engineers
• Production Engineers
• Mechanical Engineer
• Chemical Engineers
• Asset Integrity
• Maintenance
• Design Phase
• Electrical Engineers
• Civil Engineers
Meet Senior Decision Makers From:
COOs, VPs, Directors, Managers, Team Leads & Chiefs Of:
Achieving Your Business And Marketing Objectives At The Congress
DEMONSTRATE THOUGHT LEADERSHIP:
If you are able to provide solutions to topics covered on our agenda you may be interested in a perfectly-timed speaking opportunity, enabling you to present your value proposition to your target audience. Why not give your company a
competitive edge in the market?
RAISE BRAND AWARENESS AND INCREASE YOUR PROFILE:
To further cement your position in the market and to raise your brand awareness, we can provide you with high visibility before, during and after the congress. This
will maximize your exposure among clients and prospects.
MEET AND NETWORK WITH DECISION MAKERS:
Facilities Design SAGD 2014 is this year’s dedicated congress for in situ oil sands facilities decision makers. This intimate forum will make networking easy by allowing you to meet relevant job titles in one place at one time. ‘Meaningful’ relationships are easier to convert into contracts!
Do You Provide A New Technology Or Solution In One Of These Areas?If so, then contact us to discuss how you can showcase it to our attendees.
To secure your booth or discuss tailor-made sponsorship packages, please contact:
John Duggan
+ (1) 800 721 3915
www.sagd-facilities-design-2014.com (1) 800 721 3915 [email protected]
Address For Invoice Purposes
Zip/Postal Code
Country
Payment must be received in full prior to the event.
*Option 1. CREDIT CARD Please charge my * VISA * AMERICAN EXPRESS * MASTERCARD
Expiry date
Security Code / CVV (required)
Signature of card holder
Amount $ CAD
Card number
Name on card
I would like to register the delegate(s) below for the 2 day congressFacilities Design SAGD 2014
PYesDetails PLEASE USE CAPITALS - PHOTOCOPY FOR MULTIPLE DELEGATES
Delegate Rates GUESTS ARE RESPONSIBLE FOR THEIR OWN TRAVEL AND ACCOMMODATION ARRANGEMENTS
Payment PLEASE TICK APPROPRIATE BOXES AND COMPLETE DETAILS
How To Finalize Your Registration
*Option 2. INVOICE An invoice containing payment instructions will be sent electronically upon receipt of the completed registration form.
Delegate 1
* Mr * Dr * Miss * Ms * Mrs * Other:
Name
Position
Organization
Telephone
Delegate 2
* Mr * Dr * Miss * Ms * Mrs * Other:
Name
Position
Organization
Telephone
All prices quoted above are inclusive of GST
Now that your details are completed please send your registration form to
our Customer Service Team using one of the following options:
Option 1. Email: [email protected]
Option 2. Fax: (1) 800 714 1359
Enquiries And More Information
Should you have any enquiries or if you would like to request more
information please contact our friendly Customer Service Team on
(1) 800 721 3915 or visit the conference website at
www.sagd-facilities-design-2014.com
Super Early Booking Discount Early Booking Discount Standard Rate
Book And Pay By Friday October 3 Book And Pay By Friday October 24 From October 25
2 Day Congress Pass * $1499 CAD SAVE $400 * $1699 CAD SAVE $200 * $1899 CAD
Add Audio & Video Materials * $399 CAD
*SAVE UP TO 20%WITH GROUP DISCOUNTSCall for rates: (1) 800 721 3915
Terms & Conditions
The conference is being organized by Canadian Business Conferences, a division of London Business Conferences Ltd, a limited liability company formed under English company law and registered in the UK no. 5090859.Cancellations received 30 days prior to the event taking place will be eligible for a refund less $150 administration fee, after which point no refund will be given. Cancellations must be made in writing, if you are unable to attend you may nominate a colleague to take your place at no additional cost.Receipt of this booking form, inclusive or exclusive of payment constitutes formal agreement to attend and acceptance of the terms and conditions stated.All outstanding fees must be paid within our standard payment period of 7 days. Any outstanding invoices will remain valid should cancellation of attendance be received outside of the aforementioned cancellation period.* If you are claiming the early booking discount this may not be used in conjunction with other discounts
advertised elsewhere. All discount codes and offers must be claimed at the time of registration.Canadian Business Conferences reserves the right to alter or cancel the speakers or program.We would like to keep you informed of other Canadian Business Conferences products and services. This will be carried out in accordance with the Data Protection Act. Please write to the Head of Marketing, Canadian Business Conferences at the address below if you specifically do not want to receive this information.Canadian Business Conferences. Bankers Hall. West Tower, 888. 3rd Street SW. 10th Floor. Calgary. AB. T2P 5C5Canadian Business Conferences will not accept liability for any individual transport delays and in such circumstances the normal cancellation restrictions apply.Canadian Business Conferences is a Division of London Business Conferences Limited.Registered in England No. 5090859 EIN. no: 98-0514924
www.sagd-facilities-design-2014.com (1) 800 721 3915 [email protected]