Page 1: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

FAC‐003 Transmission Vegetation Management

NC NOVEMBRI CONSULTING, LLC

Page 2: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

Agenda

•About NERC and FERC•FAC‐003 Requirements and FERC Order 777•Transmission Vegetation Related Outages•Preparing for FAC‐003‐3•Development of the Transmission Vegetation Management Standard

•Enforcement Dates for Transmission Owners and Generator Owners

Page 3: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

About NERC

North American Electric Reliability Corporation: A not‐for‐profit entity whose mission is to ensure the reliability of the Bulk‐Power System in North America. •NERC develops and enforces Reliability Standards•Annually assesses seasonal and long‐term reliability•Monitors the Bulk‐Power System through system awareness

•Educates, trains, and certifies industry personnel 

Page 4: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

About NERC

Page 5: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

•Over 1900 Registered Entities Balancing AuthorityDistribution ProviderGenerator OwnerGenerator Operator Interchange Authority Load‐Serving Entity Planning Authority Purchasing‐Selling Entity

About NERC

Reliability Coordinator Reserve Sharing Group Resource Planner Transmission Owner Transmission Operator Transmission Planner Transmission Service Provider

Page 6: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

About NERC

•NERC Certification is required for three of the fifteen registration categories Balancing Authority Transmission Operator Reliability Coordinator

Page 7: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

About NERC

•There are 114 NERC Standards that contain over 1200 requirements and subrequirements

•Each NERC Standard contains the following: Purpose Applicability RequirementsMeasures Violation Risk Factors (VRFs) Violation Severity Levels (VSLs)

Page 8: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

About NERC

NERC Reliability Standards are developed using an ANSI‐accredited process that: •Ensures the process is open to all persons who are directly and materially affected by the reliability of the Bulk Power System

• Is transparent to the public•Demonstrates the consensus for each standard•Fairly balances the interests of all stakeholders•Provides for reasonable notice and opportunity for comment

Page 9: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

About NERC

Procedure for the Development of a Reliability Standard

Page 10: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

About NERC

Page 11: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

About NERC

NERC is subject to oversight by the Federal Energy Regulatory Commission and governmental authorities in Canada

Page 12: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

About FERC

The Federal Energy Regulatory Commission is an independent agency that regulates the interstate transmission of electricity, natural gas, and oil•Protects the reliability of the high voltage interstate transmission system through mandatory reliability standards

•Enforces FERC regulatory requirements through imposition of civil penalties and other means

•Approves NERC Board of Trustees adopted reliability standards

Page 13: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

About FERC

FERC can also revise NERC BOT adopted reliability standards or set expectations for requirements. FAC‐003‐2 examples – FERC Order 777:Modification to the Violation Risk Factor from Medium to High for Requirement 2ROW DefinitionRequirement 1Requirement 3Requirement 6Requirement 7

Page 14: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

The FAC‐003 Standard

ROW Definition: The corridor of land under a transmission line needed to operate the line. The width of the corridor is established by engineering or construction standards as documented in either construction documents, pre‐2007 vegetation maintenance records, or by the blowout standard in effect when the line was built. The ROW width in no case exceeds the Transmission Owner’s legal rights but may be less based on the aforementioned criteria.

Page 15: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

The FAC‐003 Standard

FERC Order: “…auditors will be able to request supporting information used to set the width of the right‐of‐way, including any of the available information listed in the right‐of‐way definition.”

Page 16: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

The FAC‐003 Standard

When are pre‐2007 vegetation maintenance records to be used for defining a ROW?Were there are no engineering or construction standards that reference the width of ROW to be maintained for vegetation; and Evidence exists in maintenance records for a width that was in fact maintained prior to the standard becoming mandatory

Page 17: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

The FAC‐003 Standard

Requirement 1: Each TO shall manage vegetation to prevent encroachments into the MVCD of its applicable lines which are either an element of an Interconnection Reliability Operating Limit, or an element of a Major WECC Transfer Path; operating within their Rating and all Rated Electrical Operating Conditions of the types shown below:Observed in real time, no sustained outage Fall‐in inside the ROW, sustained outage Blowing together of lines and vegetation inside the ROW, sustained outage Vegetation growth, sustained outage

Page 18: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

The FAC‐003 Standard

FERC Order: “…while clearances required at the time of maintenance may vary from one region or area to another, our proposed approval of FAC‐003‐2 is based on our understanding, which is drawn directly from NERC’s statements in its petition, that transmission operators [owners] will manage vegetation to distances beyond the MVCD to ensure no encroachment into the MVCD.”

Page 19: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

The FAC‐003 Standard

Requirement 3: Each TO shall have documented maintenance strategies or procedures or processes or specifications it uses to prevent the encroachment of vegetation into the MVCD of its applicable lines that accounts for the following: Movement of applicable line conductors under their Rating and all Rated Electrical Operating Conditions;  Inter‐relationships between vegetation growth rates, vegetation control methods, and inspection frequency. 

Page 20: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

The FAC‐003 Standard

FERC Order: “…documented maintenance strategies can take many forms. While accommodating flexibility, these documented strategies must have sufficient specification to provide a means to follow the transmission owner’s strategy through a paper trail or guidelines. Documented strategies cannot be so vague as to fail to provide any clear guidance for auditors…” 

Page 21: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

The FAC‐003 Standard

Requirement 4: Reporting of vegetation likely to cause a faultRequirement 5: Constraints from performing needed vegetation work Neither R4 or R5 were commented on in FERC Order 777

Page 22: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

The FAC‐003 Standard

Requirement 6: Each applicable TO and applicable GO shall perform a Vegetation Inspection of 100% of its applicable transmission lines at least once per calendar year and with no more than 18 calendar months between inspections on the same ROW

Page 23: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

The FAC‐003 Standard

FERC Order 777: “…the fall‐in of a danger tree from outside the defined right‐of‐way but within a transmission owner’s control would likely merit examination to determine whether the transmission owner is properly conducting the annual Vegetation Inspection as required by Requirement R6…”

Page 24: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

The FAC‐003 Standard

Requirement 7: Each applicable TO and applicable GO shall complete 100% of its annual vegetation work plan of applicable lines to ensure no vegetation encroachments occur within the MVCD

Page 25: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

The FAC‐003 Standard

FERC Order 777: “…the fall‐in of a danger tree from outside the defined right‐of‐way but within a transmission owner’s control would likely merit examination to determine whether the transmission owner is properly… …performing the annual work plan as required by Requirement R7”

Page 26: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

Transmission Vegetation Related Outages

Page 27: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

Fall‐in Outages –Outside ROW

17

24

1416

9

16

11

19

4

2007 2008 2009 2010 2011 2012 2013 2014 2015

Fall‐in Outages ‐Category 3Through 2nd Quarter 2015

Page 28: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

Grow‐in Outages

16

11

32

01

0 01

2007 2008 2009 2010 2011 2012 2013 2014 2015

Grow‐in Outages ‐Category 1Through 2nd Quarter 2015

Page 29: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

TVMP• Ensure each requirement of FAC‐003‐3 is thoroughly 

addressed in your program documentationMeasures• Ensure you have a clear understanding of the measures for 

each requirement and what supporting documentation and information is needed to comply with them

Evidence Retention• Ensure you meet the evidence retention periods for each 

requirement

Preparing for FAC‐003‐3

Page 30: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

Development of the Transmission Vegetation Management Standard

Page 31: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

•August 14, 2003 Northeast Blackout•Affected more than 50 million people and over 61,000 megawatts of electric load

•The US / Canada Joint Task Force indicated that the lack of adequate tree maintenance on various transmission rights‐of‐way was one of the primary causes of the Northeast Blackout Inadequate System Understanding Inadequate Situational Awareness Inadequate Reliability Coordinator Diagnosis Support

Why Develop a TVM Standard

Page 32: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

• In mid‐2004 the Transmission System Vegetation Management Standard Drafting Team was established and tasked with developing a Transmission Vegetation Management Program standard 

•As a result of that effort FAC‐003‐1 was approved and became mandatory and enforceable on July 18, 2007

Reaction to the NE Blackout

Page 33: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

Applicability –Transmission Owners•Adopted by the NERC Board of Trustees: November 2, 2011

•Filed with FERC: December, 21 2011•FERC NOPR: October 18, 2012•FERC Order 777 Issued: March 21, 2013•FERC Order Effective: May 28, 2013 •Mandatory and Enforceable: July 1, 2014• Inactive: November 25, 2013

FAC‐003‐2 Approval and Enforcement Dates

Page 34: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

Applicability –Transmission Owners•Adopted by the NERC Board of Trustees: May 9, 2012

•Filed with FERC: July 30, 2012•FERC NOPR: April 18, 2013•FERC Order 785 Issued: September 19, 2013•FERC Order Effective: November 25, 2013•Mandatory and Enforceable: July 1, 2014

FAC‐003‐3Approval and Enforcement Dates

Page 35: FAC 003 Transmission Vegetation Management€¦ · 2015-10-13  · The FAC‐003 Standard FERC Order: “…while clearances required at the time of maintenance may vary from one

Applicability –Generator Owners•Adopted by the NERC Board of Trustees: May 9, 2012

•Filed with FERC: July 30, 2012•FERC NOPR: April 18, 2013•FERC Order 785 Issued: September 19, 2013•FERC Order Effective: November 25, 2013•Requirement 3 becomes Mandatory and Enforceable: January 1, 2015

•Remaining Requirements become Mandatory and Enforceable: January 1, 2016

FAC‐003‐3 Approval and Enforcement Dates