f5 progress test question 1
TRANSCRIPT
-
8/17/2019 F5 Progress Test Question 1
1/3
ACCA
Paper F5
Performance Management
Online Progress Test 1
Question Paper
-
8/17/2019 F5 Progress Test Question 1
2/3
ALL questions are compulsory and MUST be attempted
1 Uni-craft is a toy manufacturer producing more than 30 product lines for disabledchildren. The products are specialised and in high demand all over Europe. Recently they
are facing stronger competition due to increased flux of products from the Chinese market.Uni-craft is considering introducing an ABC system in an effort to build a fair cost structure
and a more competitive price for its products. Details of its three products from the latestbudget working papers are set out below:
Product: Barugan Jen-10 Fonic
Annual production (units) 1,000,000 2,000,000 500,000
Selling price per unit $4.75 $3.70 $5.00Direct material/unit $1.00 $0.50 $0.75
Direct Labour/unit $2.50 $1.50 $1.75
Batch size (units) 1,000 500 250
Machine hrs per unit 2 3 4Set ups per batch 4 4 6
Purchase orders per batch 2 3 1
Three cost pools have been identified. Their costs for the year are as follows:$
Machine running costs: 1,400,000
Set up costs: 1,500,000Purchase order costs: 600,000
Currently, Uni-craft operates an absorption costing system where all overheads are
absorbed based on machine hours.
Required(a) Calculate the total cost per unit for each product using:
(i) the current absorption costing method; (5 marks)
(ii) an activity based costing method based on the cost driversidentified above.
(9 marks)
(b) Comment on how a switch to an ABC approach will help Uni-craft,
discussing areas of pricing, costing and product competitiveness.
(6 marks)
(Total: 20 Marks)
-
8/17/2019 F5 Progress Test Question 1
3/3
Formulae Sheet
Learning curve
baxY
Where: y = cumulative average time to produce X units
a = the time taken for the first unit of output
x = the cumulative number of units produced
b = the index of learning (log LR/log 2)
LR = the learning rate as a decimal
Regression analysis
bxay
22 xxn
yxxynb
n
xb
n
ya
2222 yynxxn
yxxynr
Demand curve
bQaP
quantityinchange
priceinchangeb
0Qwhenpricea
MR = a – 2bQ