f305 intermediate corporate finance indiana university class 5

8
F305 Intermediate Corporate Finance Indiana University Class 5

Upload: christian-cannon

Post on 31-Dec-2015

213 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: F305 Intermediate Corporate Finance Indiana University Class 5

F305Intermediate Corporate Finance

Indiana University

Class 5

Page 2: F305 Intermediate Corporate Finance Indiana University Class 5

Project Analysis – Managerial Options

While planning is essential, things rarely work out as planned! So, what if:

We miss sales projections Timing is not what was expected A project is wildly successful Effect on other products is unexpected The economy has changed The discount rate changes Cost estimates are incorrect

The Case of Daimler-Chrysler

Page 3: F305 Intermediate Corporate Finance Indiana University Class 5

What Are Management’s Options?

The company can postpone (Timing Option)

Scale back or abandon Build in flexibility Expand or duplicate Strategic options

Test marketSmall scale tests

Page 4: F305 Intermediate Corporate Finance Indiana University Class 5

The Timing Option Most attractive when:

Uncertainty is large Immediate project cash flows are small

The Abandonment Option Treated as an Option in investments

Provides partial insurance against failure Similar to a Put option, with the exercise price equal

to the value of the project’s assets if they were sold or shifted to a more valuable use

So, provides a means to assign an abandonment value to the cash flow and arrive at a value including abandonment

Page 5: F305 Intermediate Corporate Finance Indiana University Class 5

Built-in Flexibility

Is a project convertible to alternative uses? Inputs Outputs Expansion

Each alternative is assigned a probability to arrive at an overall NPV for the flexible project

Option to expand a project not built in to the original plan

Page 6: F305 Intermediate Corporate Finance Indiana University Class 5

What if?

Scenario Analysis – allows the analyst to change multiple variables at once. If many conditions change, what is the effect on the project analysis

Sensitivity Analysis – how sensitive is the analysis to single factor fluctuation?

Break Even Analysis The trade off between fixed costs and variable costs Accounting break-even

Page 7: F305 Intermediate Corporate Finance Indiana University Class 5

Break Even Analysis Consider the following two cost structures

FC(A) + VC(A) * Q where FC = 40,000 and variable costs are $0.30

FC(B) + VC(B) * Q where FC = 60,000 and variable costs are $0.15

At what point are we indifferent to the cost structure? If Cost structure A had Q = 20,000, how many

additional units would have to be sold under cost structure B to make the two cost structures comparable?

Page 8: F305 Intermediate Corporate Finance Indiana University Class 5

Break Even Analysis

Consider the following variables P = price per unit v = variable cost per unit Q = number of units sold FC = fixed costs D = depreciation T = tax rate

Then

B/E Q = (FC + D) / (P – v) Q = (40,000+4,000) / ($3.00 - $.30)