f.24 - cornwall.gov.uk · series title value. 200 site clearance £8,355.26 300 fencing £50,296.70...
TRANSCRIPT
MEMORANDUM
- 1 - Memo Launceston Southern Link Road 150923.docx
To: Rebecca Jackson At: Cornwall Council
From: Ben Smith-Laing At: Parsons Brinckerhoff
Date: 23rd
September 2015 Ref: T5070-004 / 3513000GQ
Subject: LAUNCESTON SOUTHERN LINK ROAD
Introduction
There is a local desire to deliver a Southern Link Road (SLR) in Launceston to support higher growth levels and provide sustainable access to the proposed development cells south of the A30, while reducing pressure on the A30 and adjacent junctions.
Parsons Brinckerhoff are commissioned by Cornwall Council to develop alignment options for the proposed SLR. This note summarises the two likely alignments identified for the SLR based on topography, key points along the route and access requirements. Indicative cost estimates are also provided for these two routes in this note.
Key issues
The main constraints for the road route are:
Steep and challenging topography to south of Launceston;
Requirement to preserve potential development plots along route;
Consented development at western end of route on ‘Link Road’
Trees along Link Road;
Potential tie in points with existing highways
At this stage, the potential benefits of the SLR have not been examined through highways modelling.
Design Rationale
The route design has been carried out in consultation with Cornwall Council officers. There is a consented mixed-use development site at the western end of Link Road. It is understood that this has been designed to allow the new road to tie in to a roundabout within the site, and hence to the signal junction that forms the site access to the consented development site. This approach will also prevent the disruption of the avenue of trees on Link Road. This proposed signal junction lies shortly to the east of the Penygillam junction. The SLR would run from the above signal junction east to Landlake Road and then across to join the A388. It would also permit future access into any development sites to the west of Landlake Road, as it could potentially be extended into this area by a developer.
Geometry
Geometry of the SLR has been set out at 7.3m wide single carriageway with 2.0m verges and 1:2.5 earthwork slopes. Horizontal alignment complies with the Design Manual for Roads and Bridges for a design speed of 40mph. Tie in points to the existing highway network will be via roundabout junctions. These generally offer efficient operation, and are likely to show a ‘worst case’ in terms of land take.
Route Alignments
Two potential alignments have been drawn up (Route A and Route C). These are shown in Appendix A of this document. The reason for the two routes is to look at options that minimise the land take and extensive earthworks that will be required to deal with the challenging topography along the route.
- 2 -
The drawings of both routes indicate a large area of embankment spanning the Lowley Brook valley approximately 1/3 of the way along the route heading east to west. In terms of construction and environmental impact, this is unlikely to be a practical solution and this element has therefore been accounted for within the cost estimates as a concrete span bridge. For route A, the required span would be 235m and for route C, the required span would be 143m. These are large structures and form a significant portion of the costs.
Cost Estimates
Preliminary cost estimates have been produced for both route alignments. As set out earlier, both estimates exclude any works that may be required to the Landlake Road / Link Road junction.
The costs for the two routes are as follows:
Route A - £30.7m
Route C - £24.1m
It is likely that any future delivery of these schemes would be phased along with development. In order to help understand how this phased approach might happen, the above cost estimates have been broken down into smaller sections, as approximately indicated in the following diagram:
Figure 1: Cost Estimate Scheme Sections
These can be summarised as follows:
Route A
Section A Ch0 to Ch850 £2,141,882
Section B Ch850 - Ch1570 £3,022,354
Section C Ch1570 - 1750 (Structure) £21,023,090
Section D Ch1750 - Tavistock Road £2,032,827
Section E Ch0 – Link Road Development £2,463,457
Total Works Costs £30,683,610
Section A
Section B
Section C
Section D
Section E
- 3 -
Route C
Section A Ch0 to Ch850 £2,611,952
Section B Ch850 - Ch1570 £3,095,975
Section C Ch1570 - 1750 (Structure) £13,071,430
Section D Ch1750 - Tavistock Road £2,547,559
Section E Ch0 – Link Road Development £2,727,742
Total Works Costs £24,054,658
The full cost estimates are included as Appendix B of this document.
Conclusion
Two SLR alignments developed are feasible and likely to give very similar operational benefits. On this basis, it is considered that Route C would be more viable mainly due to its lower cost.
Filename: M:\Projects\TRANSPORTATION\3513000GR-HLV T5070-003 Launceston Bridge\Documents\Drawings\Working\31513000GQ-HLV-SK07.dwgPlot Date: 05.06.14
DRAWING NO: REVISION:
SCALE:
DRAWN BY:
CHECKED: APPROVED:
PROJECT MANAGER:
DRAWING TITLE:
PROJECT:
NOTES:
1. All dimensions are in metres unless otherwise stated.
2. Do not scale from this drawing.
This drawing is Copyright. It should not be relied on
or used in circumstances other than those for which it
was originally prepared and for which Cornwall Council
was originally commissioned. Cornwall Council accepts
no responsibility for this drawing to any party other than
the person(s) by whom it was commissioned.
REV DATE NATURE OF REVISION
REVISIONS
- FIRST ISSUE
SOLUTIONS
T5070-004
Launceston
General Arrangement
Route A
Version 3
Plan 1:2500 @ A1 ; Long Section NTS
BSL AHS
BSL 10/09/2015 BSL 10/09/2015
3513000GQ-HLV-007 -
10/09/2015
Crown copyright and database rights 2015 Ordnance Survey 100049047.
NOTES:
1. All dimensions are in metres unless otherwise stated.
2. Do not scale from this drawing.
LONG SECTION NOT TO SCALE
ROUNDABOUT LAYOUT IS
INDICATIVE ONLY AND
SHOWS A FOOTPRINT FOR
A 30m ICD ROUNDABOUT.
ROUNDABOUT LAYOUT IS
INDICATIVE ONLY AND
SHOWS A FOOTPRINT FOR
A 30m ICD ROUNDABOUT.
ROUNDABOUT LAYOUT IS
INDICATIVE ONLY AND
SHOWS A FOOTPRINT FOR
A 40m ICD ROUNDABOUT.
ROUNDABOUT LAYOUT IS
INDICATIVE ONLY AND
SHOWS A FOOTPRINT FOR
A 30m ICD ROUNDABOUT.
Additional land take required due to forward visibility
Filename: M:\Projects\TRANSPORTATION\3513000GR-HLV T5070-003 Launceston Bridge\Documents\Drawings\Working\31513000GQ-HLV-SK08.dwgPlot Date: 05.06.14
DRAWING NO: REVISION:
SCALE:
DRAWN BY:
CHECKED: APPROVED:
PROJECT MANAGER:
DRAWING TITLE:
PROJECT:
NOTES:
1. All dimensions are in metres unless otherwise stated.
2. Do not scale from this drawing.
This drawing is Copyright. It should not be relied on
or used in circumstances other than those for which it
was originally prepared and for which Cornwall Council
was originally commissioned. Cornwall Council accepts
no responsibility for this drawing to any party other than
the person(s) by whom it was commissioned.
REV DATE NATURE OF REVISION
REVISIONS
- FIRST ISSUE
SOLUTIONS
T5070-004
Launceston
General Arrangement
Route C
Version 3
Plan 1:2500 @ A1 ; Long Section NTS
BSL AHS
BSL 10/09/2015 BSL 10/09/2015
3513000GQ-HLV-008 -
10/09/2015
Crown copyright and database rights 2015 Ordnance Survey 100049047.
NOTES:
1. All dimensions are in metres unless otherwise stated.
2. Do not scale from this drawing.
LONG SECTION NOT TO SCALE
ROUNDABOUT LAYOUT IS
INDICATIVE ONLY AND
SHOWS A FOOTPRINT FOR
A 30m ICD ROUNDABOUT.
ROUNDABOUT LAYOUT IS
INDICATIVE ONLY AND
SHOWS A FOOTPRINT FOR
A 30m ICD ROUNDABOUT.
ROUNDABOUT LAYOUT IS
INDICATIVE ONLY AND
SHOWS A FOOTPRINT FOR
A 40m ICD ROUNDABOUT.
ROUNDABOUT LAYOUT IS
INDICATIVE ONLY AND
SHOWS A FOOTPRINT FOR
A 30m ICD ROUNDABOUT.
Additional land take required due to forward visibility
Series Title Value
200 Site Clearance £27,098.25
300 Fencing £123,744.23
400 Road Restraint Systems (Vehicle and Pedestrian) £2,917.60
500 Drainage £653,551.47
600 Earthworks £723,324.33
700 Pavements £1,368,785.34
1100 Kerbs, Footways & Paved Areas £78,794.36
1200 Traffic Signs & Road Markings £21,064.27
1300 Road Lighting £155,803.96
1700 Structural Concrete £6,350,000.00
3000 Landscaping and Ecology £19,470.48
Sub Total (£) £9,524,554.28
-Uplift to Spons rates for 6% contractor's overheads
and 4% contractor's profit 10.24% £975,314.36
£10,499,868.64
100 Preliminaries 15% £1,574,980.30
100 Traffic Management 20% £2,099,973.73
2700 Accomodation Works, Works for Statutory Undertakers 15% £1,574,980.30
Works Total (£) £15,749,802.96
- Optimism Bias Standard Civil Engineering) 44% £6,929,913.30
Total Works Costs £22,679,716.27
- Risk Allowance £394,587.50
- Design Fee 10% £2,267,971.63
- Client costs 5% £1,133,985.81
- Contract document preparation, procurement, etc. 3% £680,391.49
- Contract administration 5% £1,133,985.81
- Survey costs £125,000.00
- Supervision fees 10% £2,267,971.63
- Land cost (assumed value) £0.00
Grand Total (£) £30,683,610.14
Notes:
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Project Title: T5070-004 Launceston Link Road Option A
Drawing Reference: 3513000GQ-HLV-SK07
Date: Q3 2015 - 10/09/2015
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Cost Summary
Bill of Quantities: Feasibility Study
Project Number: 3513000GQ-HLV
Sub Total Works Cost (£)
Series Title Value
200 Site Clearance £3,448.82
300 Fencing £29,171.51
400 Road Restraint Systems (Vehicle and Pedestrian) £0.00
500 Drainage £114,896.94
600 Earthworks £216,022.45
700 Pavements £239,288.14
1100 Kerbs, Footways & Paved Areas £14,819.20
1200 Traffic Signs & Road Markings £4,742.27
1300 Road Lighting £31,654.56
1700 Structural Concrete £0.00
3000 Landscaping and Ecology £3,979.20
Sub Total (£) £658,023.09
-Uplift to Spons rates for 6% contractor's overheads
and 4% contractor's profit 10.24% £67,381.56
£725,404.65
100 Preliminaries 15% £108,810.70
100 Traffic Management 20% £145,080.93
2700 Accomodation Works, Works for Statutory Undertakers 15% £108,810.70
Works Total (£) £1,088,106.98
- Optimism Bias Standard Civil Engineering) 44% £478,767.07
Total Works Costs £1,566,874.05
- Risk Allowance £32,939.11
- Design Fee 10% £156,687.41
- Client costs 5% £78,343.70
- Contract document preparation, procurement, etc. 3% £47,006.22
- Contract administration 5% £78,343.70
- Survey costs £25,000.00
- Supervision fees 10% £156,687.41
- Land cost (assumed value) £0.00
Grand Total (£) £2,141,881.60
Notes:
Risk Allowance is apportioned between sections based on percentage of Total Works Cost
Project Title: T5070-004 Launceston Link Road Option A
Project Number: 3513000GQ-HLV
Bill of Quantities: Feasability Study Section A
Drawing Reference: 3513000GQ-HLV-SK07
Date: Q3 2015 - 10/09/2015
Cost Summary
Sub Total Works Cost (£)
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Series Title Value
200 Site Clearance £8,355.26
300 Fencing £50,296.70
400 Road Restraint Systems (Vehicle and Pedestrian) £0.00
500 Drainage £163,185.95
600 Earthworks £138,130.96
700 Pavements £490,301.50
1100 Kerbs, Footways & Paved Areas £30,059.40
1200 Traffic Signs & Road Markings £5,965.59
1300 Road Lighting £44,986.30
1700 Structural Concrete £0.00
3000 Landscaping and Ecology £4,908.00
Sub Total (£) £936,189.66
-Uplift to Spons rates for 6% contractor's overheads
and 4% contractor's profit 10.24% £95,865.82
£1,032,055.48
100 Preliminaries 15% £154,808.32
100 Traffic Management 20% £206,411.10
2700 Accomodation Works, Works for Statutory Undertakers 15% £154,808.32
Works Total (£) £1,548,083.22
- Optimism Bias Standard Civil Engineering) 44% £681,156.61
Total Works Costs £2,229,239.83
- Risk Allowance £32,465.14
- Design Fee 10% £222,923.98
- Client costs 5% £111,461.99
- Contract document preparation, procurement, etc. 3% £66,877.19
- Contract administration 5% £111,461.99
- Survey costs £25,000.00
- Supervision fees 10% £222,923.98
- Land cost (assumed value) £0.00
Grand Total (£) £3,022,354.11
Notes:
Risk Allowance is apportioned between sections based on percentage of Total Works Cost
Project Title: T5070-004 Launceston Link Road Option A
Project Number: 3513000GQ-HLV
Bill of Quantities: Feasability Study Section B
Drawing Reference: 3513000GQ-HLV-SK07
Date: Q3 2015 - 10/09/2015
Cost Summary
Sub Total Works Cost (£)
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Series Title Value
200 Site Clearance £5,083.05
300 Fencing £0.00
400 Road Restraint Systems (Vehicle and Pedestrian) £2,917.60
500 Drainage £55,664.23
600 Earthworks £30,201.80
700 Pavements £104,860.00
1100 Kerbs, Footways & Paved Areas £6,736.00
1200 Traffic Signs & Road Markings £1,329.38
1300 Road Lighting £0.00
1700 Structural Concrete £6,350,000.00
3000 Landscaping and Ecology £1,723.80
Sub Total (£) £6,558,515.86
-Uplift to Spons rates for 6% contractor's overheads
and 4% contractor's profit 10.24% £671,592.02
£7,230,107.88
100 Preliminaries 15% £1,084,516.18
100 Traffic Management 20% £1,446,021.58
2700 Accomodation Works, Works for Statutory Undertakers 15% £1,084,516.18
Works Total (£) £10,845,161.82
- Optimism Bias Standard Civil Engineering) 44% £4,771,871.20
Total Works Costs £15,617,033.02
- Risk Allowance £227,435.93
- Design Fee 10% £1,561,703.30
- Client costs 5% £780,851.65
- Contract document preparation, procurement, etc. 3% £468,510.99
- Contract administration 5% £780,851.65
- Survey costs £25,000.00
- Supervision fees 10% £1,561,703.30
- Land cost (assumed value) £0.00
Grand Total (£) £21,023,089.84
Notes:
Risk Allowance is apportioned between sections based on percentage of Total Works Cost
Project Title: T5070-004 Launceston Link Road Option A
Project Number: 3513000GQ-HLV
Bill of Quantities: Feasability Study Section C
Drawing Reference: 3513000GQ-HLV-SK07
Date: Q3 2015 - 10/09/2015
Cost Summary
Sub Total Works Cost (£)
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Series Title Value
200 Site Clearance £6,944.45
300 Fencing £14,504.60
400 Road Restraint Systems (Vehicle and Pedestrian) £0.00
500 Drainage £129,117.97
600 Earthworks £132,721.20
700 Pavements £277,313.00
1100 Kerbs, Footways & Paved Areas £10,104.00
1200 Traffic Signs & Road Markings £6,022.64
1300 Road Lighting £45,486.30
1700 Structural Concrete £0.00
3000 Landscaping and Ecology £4,908.00
Sub Total (£) £627,122.16
-Uplift to Spons rates for 6% contractor's overheads
and 4% contractor's profit 10.24% £64,217.31
£691,339.47
100 Preliminaries 15% £103,700.92
100 Traffic Management 20% £138,267.89
2700 Accomodation Works, Works for Statutory Undertakers 15% £103,700.92
Works Total (£) £1,037,009.20
- Optimism Bias Standard Civil Engineering) 44% £456,284.05
Total Works Costs £1,493,293.25
- Risk Allowance £21,747.31
- Design Fee 10% £149,329.33
- Client costs 5% £74,664.66
- Contract document preparation, procurement, etc. 3% £44,798.80
- Contract administration 5% £74,664.66
- Survey costs £25,000.00
- Supervision fees 10% £149,329.33
- Land cost (assumed value) £0.00
Grand Total (£) £2,032,827.33
Notes:
Project Title: T5070-004 Launceston Link Road Option A
Project Number: 3513000GQ-HLV
Bill of Quantities: Feasability Study Section D
Drawing Reference: 3513000GQ-HLV-SK07
Date: Q3 2015 - 10/09/2015
Risk Allowance is apportioned between sections based on percentage of Total Works Cost
Cost Summary
Sub Total Works Cost (£)
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Series Title Value
200 Site Clearance £3,266.68
300 Fencing £29,771.42
400 Road Restraint Systems (Vehicle and Pedestrian) £0.00
500 Drainage £190,686.38
600 Earthworks £206,247.92
700 Pavements £257,022.70
1100 Kerbs, Footways & Paved Areas £17,075.76
1200 Traffic Signs & Road Markings £3,004.39
1300 Road Lighting £33,676.80
1700 Structural Concrete £0.00
3000 Landscaping and Ecology £3,951.48
Sub Total (£) £744,703.53
-Uplift to Spons rates for 6% contractor's overheads
and 4% contractor's profit 10.24% £76,257.64
£820,961.17
100 Preliminaries 15% £123,144.17
100 Traffic Management 20% £164,192.23
2700 Accomodation Works, Works for Statutory Undertakers 15% £123,144.17
Works Total (£) £1,231,441.75
- Optimism Bias Standard Civil Engineering) 44% £541,834.37
Total Works Costs £1,773,276.12
- Risk Allowance £80,000.00
- Design Fee 10% £177,327.61
- Client costs 5% £88,663.81
- Contract document preparation, procurement, etc. 3% £53,198.28
- Contract administration 5% £88,663.81
- Survey costs £25,000.00
- Supervision fees 10% £177,327.61
- Land cost (assumed value) £0.00
Grand Total (£) £2,463,457.24
Notes:
Risk Allowance is apportioned average of Sections A-D
Project Title: T5070-004 Launceston Link Road Option A
Project Number: 3513000GQ-HLV
Bill of Quantities: Feasability Study Section E
Drawing Reference: 3513000GQ-HLV-SK07
Date: Q3 2015 - 10/09/2015
Cost Summary
Sub Total Works Cost (£)
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Series Title Value
200 Site Clearance £27,098.25
300 Fencing £125,054.23
400 Road Restraint Systems (Vehicle and Pedestrian) £2,917.60
500 Drainage £653,551.47
600 Earthworks £1,128,864.67
700 Pavements £1,368,785.34
1100 Kerbs, Footways & Paved Areas £78,794.36
1200 Traffic Signs & Road Markings £21,064.27
1300 Road Lighting £155,803.96
1700 Structural Concrete £3,850,000.00
3000 Landscaping and Ecology £19,470.48
Sub Total (£) £7,431,404.63
-Uplift to Spons rates for 6% contractor's overheads
and 4% contractor's profit 10.24% £760,975.83
£8,192,380.46
100 Preliminaries 15% £1,228,857.07
100 Traffic Management 20% £1,638,476.09
2700 Accomodation Works, Works for Statutory Undertakers 15% £1,228,857.07
Works Total (£) £12,288,570.69
- Optimism Bias Standard Civil Engineering) 44% £5,406,971.10
Total Works Costs £17,695,541.79
- Risk Allowance £394,587.50
- Design Fee 10% £1,769,554.18
- Client costs 5% £884,777.09
- Contract document preparation, procurement, etc. 3% £530,866.25
- Contract administration 5% £884,777.09
- Survey costs £125,000.00
- Supervision fees 10% £1,769,554.18
- Land cost (assumed value) £0.00
Grand Total (£) £24,054,658.08
Notes:
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Project Title: T5070-004 Launceston Link Road Option C
Drawing Reference: 3513000GQ-HLV-SK08
Date: Q3 2015 - 10/09/2015
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Cost Summary
Bill of Quantities: Feasibility Study
Project Number: 3513000GQ-HLV
Sub Total Works Cost (£)
Series Title Value
200 Site Clearance £3,448.82
300 Fencing £29,171.51
400 Road Restraint Systems (Vehicle and Pedestrian) £0.00
500 Drainage £114,896.94
600 Earthworks £360,555.45
700 Pavements £239,288.14
1100 Kerbs, Footways & Paved Areas £14,819.20
1200 Traffic Signs & Road Markings £4,742.27
1300 Road Lighting £31,654.56
1700 Structural Concrete £0.00
3000 Landscaping and Ecology £3,979.20
Sub Total (£) £802,556.09
-Uplift to Spons rates for 6% contractor's overheads
and 4% contractor's profit 10.24% £82,181.74
£884,737.83
100 Preliminaries 15% £132,710.67
100 Traffic Management 20% £176,947.57
2700 Accomodation Works, Works for Statutory Undertakers 15% £132,710.67
Works Total (£) £1,327,106.75
- Optimism Bias Standard Civil Engineering) 44% £583,926.97
Total Works Costs £1,911,033.72
- Risk Allowance £45,276.99
- Design Fee 10% £191,103.37
- Client costs 5% £95,551.69
- Contract document preparation, procurement, etc. 3% £57,331.01
- Contract administration 5% £95,551.69
- Survey costs £25,000.00
- Supervision fees 10% £191,103.37
- Land cost (assumed value) £0.00
Grand Total (£) £2,611,951.83
Notes:
Risk Allowance is apportioned between sections based on percentage of Total Works Cost
Project Title: T5070-004 Launceston Link Road Option C
Project Number: 3513000GQ-HLV
Bill of Quantities: Feasability Study Section A
Drawing Reference: 3513000GQ-HLV-SK08
Date: Q3 2015 - 10/09/2015
Cost Summary
Sub Total Works Cost (£)
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Series Title Value
200 Site Clearance £8,355.26
300 Fencing £50,296.70
400 Road Restraint Systems (Vehicle and Pedestrian) £0.00
500 Drainage £163,185.95
600 Earthworks £157,618.50
700 Pavements £490,301.50
1100 Kerbs, Footways & Paved Areas £30,059.40
1200 Traffic Signs & Road Markings £5,965.59
1300 Road Lighting £44,986.30
1700 Structural Concrete £0.00
3000 Landscaping and Ecology £4,908.00
Sub Total (£) £955,677.20
-Uplift to Spons rates for 6% contractor's overheads
and 4% contractor's profit 10.24% £97,861.34
£1,053,538.54
100 Preliminaries 15% £158,030.78
100 Traffic Management 20% £210,707.71
2700 Accomodation Works, Works for Statutory Undertakers 15% £158,030.78
Works Total (£) £1,580,307.81
- Optimism Bias Standard Civil Engineering) 44% £695,335.44
Total Works Costs £2,275,643.25
- Risk Allowance £44,369.50
- Design Fee 10% £227,564.33
- Client costs 5% £113,782.16
- Contract document preparation, procurement, etc. 3% £68,269.30
- Contract administration 5% £113,782.16
- Survey costs £25,000.00
- Supervision fees 10% £227,564.33
- Land cost (assumed value) £0.00
Grand Total (£) £3,095,975.02
Notes:
Risk Allowance is apportioned between sections based on percentage of Total Works Cost
Project Title: T5070-004 Launceston Link Road Option C
Project Number: 3513000GQ-HLV
Bill of Quantities: Feasability Study Section B
Drawing Reference: 3513000GQ-HLV-SK08
Date: Q3 2015 - 10/09/2015
Cost Summary
Sub Total Works Cost (£)
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Series Title Value
200 Site Clearance £5,083.05
300 Fencing £0.00
400 Road Restraint Systems (Vehicle and Pedestrian) £2,917.60
500 Drainage £55,664.23
600 Earthworks £31,691.50
700 Pavements £104,860.00
1100 Kerbs, Footways & Paved Areas £1,329.38
1200 Traffic Signs & Road Markings £6,736.00
1300 Road Lighting £0.00
1700 Structural Concrete £3,850,000.00
3000 Landscaping and Ecology £1,723.80
Sub Total (£) £4,060,005.56
-Uplift to Spons rates for 6% contractor's overheads
and 4% contractor's profit 10.24% £415,744.57
£4,475,750.12
100 Preliminaries 15% £671,362.52
100 Traffic Management 20% £895,150.02
2700 Accomodation Works, Works for Statutory Undertakers 15% £671,362.52
Works Total (£) £6,713,625.19
- Optimism Bias Standard Civil Engineering) 44% £2,953,995.08
Total Works Costs £9,667,620.27
- Risk Allowance £188,495.04
- Design Fee 10% £966,762.03
- Client costs 5% £483,381.01
- Contract document preparation, procurement, etc. 3% £290,028.61
- Contract administration 5% £483,381.01
- Survey costs £25,000.00
- Supervision fees 10% £966,762.03
- Land cost (assumed value) £0.00
Grand Total (£) £13,071,430.00
Notes:
Risk Allowance is apportioned between sections based on percentage of Total Works Cost
Project Title: T5070-004 Launceston Link Road Option C
Project Number: 3513000GQ-HLV
Bill of Quantities: Feasability Study Section C
Drawing Reference: 3513000GQ-HLV-SK08
Date: Q3 2015 - 10/09/2015
Cost Summary
Sub Total Works Cost (£)
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Series Title Value
200 Site Clearance £6,944.45
300 Fencing £15,814.60
400 Road Restraint Systems (Vehicle and Pedestrian) £0.00
500 Drainage £129,117.97
600 Earthworks £289,301.00
700 Pavements £277,313.00
1100 Kerbs, Footways & Paved Areas £10,104.00
1200 Traffic Signs & Road Markings £6,022.64
1300 Road Lighting £45,486.30
1700 Structural Concrete £0.00
3000 Landscaping and Ecology £4,908.00
Sub Total (£) £785,011.96
-Uplift to Spons rates for 6% contractor's overheads
and 4% contractor's profit 10.24% £80,385.22
£865,397.18
100 Preliminaries 15% £129,809.58
100 Traffic Management 20% £173,079.44
2700 Accomodation Works, Works for Statutory Undertakers 15% £129,809.58
Works Total (£) £1,298,095.77
- Optimism Bias Standard Civil Engineering) 44% £571,162.14
Total Works Costs £1,869,257.92
- Risk Allowance £36,445.97
- Design Fee 10% £186,925.79
- Client costs 5% £93,462.90
- Contract document preparation, procurement, etc. 3% £56,077.74
- Contract administration 5% £93,462.90
- Survey costs £25,000.00
- Supervision fees 10% £186,925.79
- Land cost (assumed value) £0.00
Grand Total (£) £2,547,559.00
Notes:
Risk Allowance is apportioned between sections based on percentage of Total Works Cost
Project Title: T5070-004 Launceston Link Road Option C
Project Number: 3513000GQ-HLV
Bill of Quantities: Feasability Study Section D
Drawing Reference: 3513000GQ-HLV-SK08
Date: Q3 2015 - 10/09/2015
Cost Summary
Sub Total Works Cost (£)
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years
Series Title Value
200 Site Clearance £3,266.68
300 Fencing £29,771.42
400 Road Restraint Systems (Vehicle and Pedestrian) £0.00
500 Drainage £190,686.38
600 Earthworks £289,698.22
700 Pavements £257,022.70
1100 Kerbs, Footways & Paved Areas £17,075.76
1200 Traffic Signs & Road Markings £3,004.39
1300 Road Lighting £33,676.80
1700 Structural Concrete £0.00
3000 Landscaping and Ecology £3,951.48
Sub Total (£) £828,153.83
-Uplift to Spons rates for 6% contractor's overheads
and 4% contractor's profit 10.24% £84,802.95
£912,956.78
100 Preliminaries 15% £136,943.52
100 Traffic Management 20% £182,591.36
2700 Accomodation Works, Works for Statutory Undertakers 15% £136,943.52
Works Total (£) £1,369,435.17
- Optimism Bias Standard Civil Engineering) 44% £602,551.47
Total Works Costs £1,971,986.64
- Risk Allowance £80,000.00
- Design Fee 10% £197,198.66
- Client costs 5% £98,599.33
- Contract document preparation, procurement, etc. 3% £59,159.60
- Contract administration 5% £98,599.33
- Survey costs £25,000.00
- Supervision fees 10% £197,198.66
- Land cost (assumed value) £0.00
Grand Total (£) £2,727,742.23
Notes:
Risk Allowance is apportioned based on average proportions of Sections A - D
Project Title: T5070-004 Launceston Link Road Option C
Project Number: 3513000GQ-HLV
Bill of Quantities: Feasability Study Section E
Drawing Reference: 3513000GQ-HLV-SK08
Date: Q3 2015 - 19/08/2015
Cost Summary
Sub Total Works Cost (£)
The rates used in costing this series have been taken from Spon's Civil Engineering & Highway Works Price Book 2015 (29th
Edition)
Land cost has not been included as it is currently unknown
Rates are based on construction taking place in the current year so cost shown would be subject to inflation in future years