![Page 1: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/1.jpg)
F08 – 72 – OUTGRESPF08 – 72 – OUTGRESPFirst Contingency Outage First Contingency Outage
Response for SIUCResponse for SIUCClient: SIUC Physical Plant Engineering ServicesTeam Members: Rudy Probst, EE
Kyle Moore, EETerry Campanella, PM,
EE/CpEClint Frederick, EEPhil Craig, EETanner Jones, EE
Faculty Advisor: Dr. Constantine HatziadoniuClient Contact: Steve Lazorchak, PE
![Page 2: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/2.jpg)
Outline of TopicsOutline of TopicsExecutive Summary – RudyDescription, Options, and Justification –
KyleMechanical Considerations Subsystem –
TerrySystem Protection Subsystem – ClintUniversal Transformer Subsystem – PhilSummary – Tanner
![Page 3: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/3.jpg)
Executive SummaryExecutive Summary
Issue: Major transformer failure Summer 2008 causing a major outage
Project: Reduce outage time
Typically SIUC reacts to failure instead of preparation
![Page 4: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/4.jpg)
Executive SummaryExecutive SummaryExpectations
◦Feeder diagram for fault protection◦Emergency transformer◦Mechanical restrictions◦Outage plan
Outcome◦Simulation of feeder diagram◦Transformer recommendation◦Recommendations to reduce outage
time
![Page 5: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/5.jpg)
Executive SummaryExecutive SummaryResults
◦Feeder diagram not as accurate as desired◦On time◦On budget
Estimated cost to implement: ~$92,000
Time to implement: Estimated 8 months
Cost of study: $0
![Page 6: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/6.jpg)
Options InvestigatedOptions InvestigatedDo nothingPurchase 1 transformerPurchase 2 transformersMobile transformer3 banked single-phase
transformersForm consortium to share costs
![Page 7: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/7.jpg)
Option ChosenOption ChosenPurchase two transformers
◦Covers both 480V and 208V transformers◦Covers most indoor transformers on feeder
7
Investigate consortium option◦Many other institutions have similar issues◦Coverage against failure of two
transformers with same secondary voltage
![Page 8: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/8.jpg)
Subsystems FlowchartsSubsystems Flowcharts
First Contingency Outage Response for
SIUC
Mechanical Considerations
System ProtectionUniversal
Transformer Replacement
Implementing recommendations:◦ Will reduce outage time at least eight hours◦Saves money after five uses of each
transformers
![Page 9: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/9.jpg)
Cost and Time to Cost and Time to ImplementImplementCosts
◦Two $46,000 transformers◦Storage facility
Time◦Analyze, confirm, and design
replacement : 20 man-hours◦Finalize contracts to build: eight
man-hours◦Prepare storage area: unknown◦Develop plan to replace transformers:
58 man-hours
![Page 10: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/10.jpg)
Mechanical ConsiderationsMechanical ConsiderationsEngineering C – 2 transformers
◦No clear pathway to the surface◦Tunnels covered with desks, coal
samples, chairs, file cabinets, etc.◦Will have to avoid steam piping and
ledges
![Page 11: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/11.jpg)
Replacement LocationReplacement LocationLimited by breaker handles
◦Block pathway to open area of electrical room
Wide open space at backside of electrical room◦Need cabling to avoid access
locations◦Nails in ceiling limit ability to run
cabling
![Page 12: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/12.jpg)
Limiting FactorsLimiting Factors
![Page 13: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/13.jpg)
Problems at ArenaProblems at Arena
![Page 14: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/14.jpg)
Ideal Tunnel…Ideal Tunnel…
![Page 15: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/15.jpg)
Actual Tunnel…Actual Tunnel…
![Page 16: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/16.jpg)
System ProtectionSystem ProtectionEnsure that replacement
transformers and the electrical system will be properly protected against fault currents
Chose feeder seven to do a protection study
Built a model in EasyPowerSystem data
![Page 17: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/17.jpg)
System ProtectionSystem ProtectionReplaced the present transformers
with our specified replacement transformers◦ 1000 kVA 12,470 V Δ – 4160 V Δ / 480
V Y %Z = 4.5
◦ 1000 kVA 12,470 V Δ – 4160 V Δ / 208 V Y %Z = 4.5
Ran the simulation
![Page 18: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/18.jpg)
Time-Current Characteristic Time-Current Characteristic CurveCurve
![Page 19: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/19.jpg)
Universal TransformerUniversal TransformerMust be electrically and
mechanically compatibleSeveral options consideredFourteen of fifteen transformers
208 V or 480 V secondary voltageThirteen of fifteen transformers
rated 1000 kVA or lessMost outdoor transformers are
non-critical
![Page 20: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/20.jpg)
Mobile TransformerMobile Transformer
Determined to be non-feasibleCable length to transformer
location presents problems◦Voltage drop◦Safety hazards◦Security of power system
![Page 21: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/21.jpg)
SummarySummaryReduce outage periods
Save money for SIUC
Recommend database for all power equipment at SIUC
Estimated cost to implement: ~$92,000
Time to implement: estimated 8 months
![Page 22: F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC Client: SIUC Physical Plant Engineering Services Team Members:Rudy Probst, EE Kyle Moore,](https://reader030.vdocuments.us/reader030/viewer/2022032722/56649ceb5503460f949b700f/html5/thumbnails/22.jpg)
Summary - Summary - AcknowledgementsAcknowledgements
Steve Lazorchak
Damon Adams
Rob EstesJustin HarrellRick Martin
Joe WolfeKeith FieldMrs. PurcellDr. Hatziadoniu